Pipeline cross operation protection device and construction method
By using pipeline crossing protection devices and construction methods, including pipe clamps, support frames, rubber pads and fireproof layers, as well as high-pressure jet grouting piles and grouting reinforcement, the protection problem in the construction of new pipelines crossing existing pipelines has been solved, and the foundation pit support capacity and construction safety have been improved.
Patent Information
- Application Number
- CN202210848414.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2022-07-19
- Publication Date
- 2024-11-12
- Estimated Expiration
- 2042-07-19
AI Technical Summary
During the process of adding or renovating pipelines, when new pipelines intersect with existing pipelines, the lack of effective protection measures can easily lead to pipeline damage or breakage, especially when the pipelines are laid deep, making protection more difficult.
A pipeline cross-operation protection device is provided, including a pipe clamp that can be fitted onto the pipeline and a movable support frame. The support frame can be moved to adapt to the pipeline axis direction, and a rubber pad layer and a fireproof layer are set on the outer surface of the pipeline. Combined with retaining steel plates and foundation pit support structures, the device is supported by high-pressure jet grouting piles and grouting reinforcement methods.
It improved the foundation pit support capacity at pipeline intersections, ensured the safety and stability of pipeline intersection construction, avoided pipeline damage and breakage, and ensured the normal progress of construction.
Smart Images

Figure CN115234710B_ABST
Abstract
Description
Technical Field
[0001] The present application relates to the field of pipeline construction, and in particular to a pipeline cross-operation protection device and a construction method. Background Art
[0002] Municipal engineering refers to the construction of various public transportation facilities, water supply, drainage, gas, urban flood control, environmental sanitation, lighting and other infrastructure in urban construction. It is the indispensable material basis for the survival and development of cities, and the basic condition for improving people's living standards and opening up to the outside world.
[0003] Pipeline engineering is an inseparable part of municipal engineering. It is generally designed and constructed as an ancillary project together with road engineering. However, due to the influence of long-term planning, the addition and reconstruction of pipelines are inevitable. New pipelines often cross the construction of existing pipelines. If effective protection measures are not taken for the existing pipelines during construction or detailed pipeline surveys and briefings are not carried out, pipeline damage and breakage are likely to occur, especially when the pipelines are laid deeper, it is more difficult to protect the existing pipelines. Summary of the invention
[0004] The purpose of the present application is to provide a pipeline crossing operation protection device and a construction method, which can improve the pipeline support capacity and ensure the safety of foundation pit support at the intersection of pipelines.
[0005] The embodiment of the present application is implemented as follows:
[0006] The present application provides a pipeline cross-operation protection device, which includes a pipe clamp that can be sleeved on the pipeline and a support frame movably connected to the bottom of the pipe clamp, and the support frame is configured to be movable toward or away from the pipe clamp and to be movable in a direction perpendicular to the pipeline axis.
[0007] In some optional embodiments, the inner wall of the pipe clamp is provided with a rubber cushion layer sleeved on the outer wall of the pipe, and a fireproof layer is provided between the inner wall of the pipe clamp and the rubber cushion layer.
[0008] In some optional embodiments, the bottom of the pipe clamp is connected to the pipe clamp base thread, the support frame includes at least two supporting longitudinal rods with external threads in the middle and at least four supporting cross rods, the two ends of the supporting cross rods are respectively connected to the two supporting longitudinal rods, and the middle part of each supporting longitudinal rod is provided with at least two limiting sleeves through a threaded sleeve, and the limiting sleeve and the pipe clamp base thread are connected by a lifting screw with adjustable length.
[0009] In some optional implementation schemes, two retaining steel plates are further included. The retaining steel plates are provided with slots for the pipes to pass through. The slots are also provided with double-layer rubber pads that are sleeved on the pipes.
[0010] The present application also provides a pipeline cross operation construction method, which comprises the following steps:
[0011] Level the site and lay out the construction trench for the pipeline to be built, and slope the sides of the construction trench for the pipeline to be built;
[0012] Carry out the construction of the standard section enclosure structure of the pipeline to be built, the enclosure structure at the intersection of the pipeline to be built and the existing pipeline, and the enclosure reinforcement structure at the intersection of the pipeline to be built and the existing pipeline respectively;
[0013] Carry out high-pressure jet grouting pile construction at the inner corner of the retaining structure of the standard section of the pipeline to be built and the retaining reinforcement structure at the intersection of the pipeline to be built and the existing pipeline;
[0014] Grouting reinforcement is performed on both sides of the existing pipeline between the retaining structure at the intersection of the pipeline to be built and the existing pipeline and the retaining reinforcement structure at the intersection of the pipeline to be built and the existing pipeline;
[0015] Carry out layered excavation to the bottom of the support piles to obtain the pipeline construction pit, and fully expose the existing pipeline. Construct the transverse support structure of the foundation pit support on both sides of the pipeline construction pit, respectively. Weld the retaining steel plates sleeved on the existing pipeline on both sides of the pipeline construction pit, and connect and fix the retaining steel plates to the support piles;
[0016] A double-layer rubber pad is installed between the existing pipeline and the retaining steel plate, and a fireproof layer is wrapped around the outer surface of the existing pipeline;
[0017] A pipe clamp is installed on the existing pipeline for support, and a support frame that can move toward or away from the pipe clamp and can move in a direction perpendicular to the axis of the existing pipeline is connected to the bottom of the pipe clamp. Two foundation pit support bracket support structures connected at both ends to the two sides of the pipeline construction foundation pit are constructed to support the two ends of the support frame;
[0018] Excavate the pipeline construction pit to the base and install the pipeline to be built;
[0019] Remove the pipe clamps and support frames, and remove the supporting piles, retaining steel plates and lateral supporting structures of the foundation pit, and backfill the earth in layers.
[0020] In some optional embodiments, the distance between the top of the foundation pit support support structure and the existing pipeline is 0.5m.
[0021] In some optional implementation schemes, the retaining structure of the standard section of the pipeline to be built is respectively arranged on both sides above the pipeline to be built and staggered with the existing pipeline; the retaining structure at the intersection of the pipeline to be built and the existing pipeline is arranged above the existing pipeline and respectively located on both sides of the inner walls of the construction base trench of the pipeline to be built; the retaining reinforcement structure at the intersection of the pipeline to be built and the existing pipeline is respectively arranged on both sides of the construction base trench of the pipeline to be built and located on both sides above the existing pipeline; and the two ends of the retaining reinforcement structure at the intersection of the pipeline to be built and the existing pipeline are respectively connected to the retaining structure of the standard section of the pipeline to be built and the retaining structure at the intersection of the pipeline to be built and the existing pipeline on the corresponding sides.
[0022] In some optional embodiments, when grouting reinforcement is performed on both sides of the existing pipeline between the retaining structure at the intersection of the pipeline to be built and the existing pipeline and the retaining reinforcement structure at the intersection of the pipeline to be built and the existing pipeline, the grouting depth is more than 5m below the existing pipeline.
[0023] The beneficial effects of the present application are as follows: the pipeline crossing operation construction method provided by the present application comprises the following steps: leveling the site earthwork and laying out the construction foundation trench of the pipeline to be built, and laying out the slopes on both sides of the construction foundation trench of the pipeline to be built; constructing the retaining structure of the standard section of the pipeline to be built, the retaining structure at the intersection of the pipeline to be built and the existing pipeline, and the retaining reinforcement structure at the intersection of the pipeline to be built and the existing pipeline respectively; constructing high-pressure rotary jet piles at the inner corners of the retaining structure of the standard section of the pipeline to be built and the retaining reinforcement structure at the intersection of the pipeline to be built and the existing pipeline; grouting reinforcement is performed on both sides of the existing pipeline between the retaining structure at the intersection of the pipeline to be built and the existing pipeline and the retaining reinforcement structure at the intersection of the pipeline to be built and the existing pipeline; excavating the earthwork in layers to the bottom of the support piles to obtain the pipeline construction pit, and fully exposing the existing pipeline, The transverse support structure of the foundation pit is constructed on both sides of the construction pit, and the retaining steel plates installed on the existing pipelines are welded on both sides of the pipeline construction pit, and the retaining steel plates are connected and fixed to the supporting piles; a double-layer rubber pad is set between the existing pipeline and the retaining steel plate, and a fireproof layer is wrapped on the outer surface of the existing pipeline; a pipe clamp is installed on the existing pipeline for support, and a support frame that can move toward or away from the pipe clamp and can move in a direction perpendicular to the axis of the existing pipeline is connected to the bottom of the pipe clamp, and two foundation pit support bracket support structures are constructed with two ends connected to both sides of the pipeline construction pit to support the two ends of the support frame; the pipeline construction pit is excavated to the base, and the installation construction of the pipeline to be built is carried out; the pipe clamp and the support frame are removed, and the supporting piles, retaining steel plates and the transverse support structure of the foundation pit support are removed, and the earthwork is backfilled in layers. The pipeline crossing operation protection device and construction method provided in this application can improve the support capacity of the pipeline enclosure and ensure the safety of the foundation pit support at the intersection of the pipelines. BRIEF DESCRIPTION OF THE DRAWINGS
[0024] In order to more clearly illustrate the technical solutions of the embodiments of the present application, the drawings required for use in the embodiments will be briefly introduced below. It should be understood that the following drawings only show certain embodiments of the present application and therefore should not be regarded as limiting the scope. For ordinary technicians in this field, other related drawings can be obtained based on these drawings without paying creative work.
[0025] Figure 1 A schematic diagram of the planar structure of the construction of the retaining structure, high-pressure jet grouting piles and grouting reinforcement in the construction base trench in the pipeline cross operation construction method provided in the embodiment of the present application;
[0026] Figure 2A schematic diagram of the cross-sectional structure of the pipeline cross-operation construction method provided in the embodiment of the present application when constructing a foundation trench to construct a foundation pit support transverse support structure, a foundation pit support bracket support structure, and installing a retaining steel plate and a pipeline cross-operation protection device;
[0027] Figure 3 A schematic diagram of the cross-sectional structure of a retaining steel plate sleeved on an existing pipeline obtained by construction in the pipeline cross-operation construction method provided in an embodiment of the present application;
[0028] Figure 4 For along Figure 3 Section view of the AA section line;
[0029] Figure 5 A schematic structural diagram of a first-view of a pipeline cross-operation protection device in a pipeline cross-operation construction method provided in an embodiment of the present application;
[0030] Figure 6 A schematic structural diagram of a second perspective of a pipeline cross-operation protection device in a pipeline cross-operation construction method provided in an embodiment of the present application being sleeved on an existing pipeline;
[0031] Figure 7 A schematic cross-sectional structural diagram from a third perspective of a pipeline cross-operation protection device in a pipeline cross-operation construction method provided in an embodiment of the present application, which is sleeved on an existing pipeline.
[0032] In the figure: 100, pipe clamp; 101, clamp body; 102, connecting bolt; 110, rubber cushion layer; 120, fireproof layer; 130, pipe clamp base thread; 200, support frame; 210, supporting longitudinal rod; 220, supporting cross rod; 230, limiting sleeve; 240, lifting screw; 241, adjustable screw; 250, retaining steel plate; 260, notch; 270, double-layer rubber pad; 300, existing pipeline; 310, retaining structure of standard section of pipeline to be built; 320, retaining structure at the intersection of pipeline to be built and existing pipeline; 330, retaining reinforcement structure at the intersection of pipeline to be built and existing pipeline; 340, lateral support structure of foundation pit support; 350, support structure of foundation pit support bracket; 360, high-pressure jet jet pile; 370, grouting hole; 400, pipeline to be built. DETAILED DESCRIPTION
[0033] In order to make the purpose, technical solution and advantages of the embodiments of the present application clearer, the technical solution in the embodiments of the present application will be clearly and completely described below in conjunction with the drawings in the embodiments of the present application. Obviously, the described embodiments are part of the embodiments of the present application, rather than all the embodiments. The components of the embodiments of the present application described and shown in the drawings here can be arranged and designed in various different configurations.
[0034] Therefore, the following detailed description of the embodiments of the present application provided in the accompanying drawings is not intended to limit the scope of the present application for which protection is sought, but merely represents selected embodiments of the present application. Based on the embodiments in the present application, all other embodiments obtained by ordinary technicians in the field without creative work are within the scope of protection of the present application.
[0035] It should be noted that similar reference numerals and letters denote similar items in the following drawings, and therefore, once an item is defined in one drawing, further definition and explanation thereof is not required in subsequent drawings.
[0036] In the description of the present application, it should be noted that the terms "center", "upper", "lower", "left", "right", "vertical", "horizontal", "inner", "outer", etc. indicate positions or positional relationships based on the positions or positional relationships shown in the accompanying drawings, or the positions or positional relationships in which the product of the application is usually placed when in use. They are only for the convenience of describing the present application and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific position, be constructed and operated in a specific position, and therefore cannot be understood as a limitation on the present application. In addition, the terms "first", "second", "third", etc. are only used to distinguish the description, and cannot be understood as indicating or implying relative importance.
[0037] In addition, the terms "horizontal", "vertical", "overhanging" and the like do not mean that the components are required to be absolutely horizontal or overhanging, but can be slightly tilted. For example, "horizontal" only means that its direction is more horizontal than "vertical", and does not mean that the structure must be completely horizontal, but can be slightly tilted.
[0038] In the description of this application, it should also be noted that, unless otherwise clearly specified and limited, the terms "set", "install", "connect", and "connect" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection, or it can be indirectly connected through an intermediate medium, or it can be the internal communication of two elements. For ordinary technicians in this field, the specific meanings of the above terms in this application can be understood according to specific circumstances.
[0039] In the present application, unless otherwise clearly specified and limited, a first feature being "above" or "below" a second feature may include that the first and second features are in direct contact, or may include that the first and second features are not in direct contact but are in contact through another feature between them. Moreover, a first feature being "above", "above" and "above" a second feature includes that the first feature is directly above and obliquely above the second feature, or simply indicates that the first feature is higher in level than the second feature. A first feature being "below", "below" and "below" a second feature includes that the first feature is directly below and obliquely below the second feature, or simply indicates that the first feature is lower in level than the second feature.
[0040] The features and performance of the pipeline cross-operation protection device and pipeline cross-operation construction method of the present application are further described in detail below in conjunction with the embodiments.
[0041] like Figure 1 , Figure 2 , Figure 3 , Figure 4 , Figure 5 , Figure 6 and Figure 7 As shown, the embodiment of the present application provides a pipeline cross operation construction method, which includes the following steps:
[0042] Level the earthwork at the construction site and lay out the foundation trench for the pipeline 400 to be built, conduct pipeline detection at the intersection of the existing pipeline 300 and the pipeline 400 to be built, and issue a detection report;
[0043] Excavate 0.5m deep soil outside the construction trench of the pipeline 400 to be built and slope it at a ratio of 1:2, leveling the land at the bottom of the slope to meet the construction conditions of the retaining pile driver;
[0044] The construction of the standard section enclosure structure 310 of the pipeline to be built, the enclosure structure 320 at the intersection of the pipeline to be built and the existing pipeline, and the enclosure reinforcement structure 330 at the intersection of the pipeline to be built and the existing pipeline are carried out respectively, wherein: the standard section enclosure structure 310 of the pipeline to be built is respectively arranged on both sides above the pipeline to be built 400 and is disconnected in the middle to stagger the existing pipeline 300, the enclosure structure 320 at the intersection of the pipeline to be built and the existing pipeline is arranged above the existing pipeline 300 and is respectively located on both sides of the inner walls of the construction base trench of the pipeline to be built 400, the enclosure reinforcement structure 330 at the intersection of the pipeline to be built and the existing pipeline is respectively arranged on both sides of the construction base trench of the pipeline to be built 400 and is located on both sides above the existing pipeline 300, and the two ends of the enclosure reinforcement structure 330 at the intersection of the pipeline to be built and the existing pipeline are respectively connected to the standard section enclosure structure 310 of the pipeline to be built and the enclosure structure 320 at the intersection of the pipeline to be built and the existing pipeline located on both sides of the existing pipeline 300.
[0045] The support depth of the retaining structure 310 of the standard section of the pipeline to be built is calculated according to the foundation pit support design. The support depth of the retaining structure 320 at the intersection of the pipeline to be built and the existing pipeline is designed according to the elevation depth of the existing pipeline 300. The retaining structure 310 of the standard section of the pipeline to be built, the retaining structure 320 at the intersection of the pipeline to be built and the existing pipeline, and the retaining reinforcement structure 330 at the intersection of the pipeline to be built and the existing pipeline have a certain safety distance from the existing pipeline 300 and the pipeline to be built 400 in accordance with the requirements of the corresponding pipeline specifications;
[0046] High-pressure jet grouting piles 360 are constructed at the inner corners of the standard section retaining structure 310 of the pipeline to be built and the retaining reinforcement structure 330 at the intersection of the pipeline to be built and the existing pipeline;
[0047] Grouting reinforcement is performed on both sides of the existing pipeline 300 between the enclosure structure 320 at the intersection of the pipeline to be built and the existing pipeline and the enclosure reinforcement structure 330 at the intersection of the pipeline to be built and the existing pipeline. The depth of the grouting reinforcement is 5m below the existing pipeline 300. The spacing of the grouting holes 370 of the grouting reinforcement is determined according to the geological conditions of the construction area.
[0048] Carry out foundation pit drainage construction to 1.0m below the foundation pit excavation surface;
[0049] Support piles are set up and earthwork is excavated in layers. The excavation depth is more than 2m to the bottom of the support piles to obtain a pipeline construction pit, and the existing pipeline 300 in the pipeline construction pit is completely exposed. The foundation pit support transverse support structure 340 is constructed on both sides of the pipeline construction pit. The retaining steel plates 250 sleeved on both ends of the existing pipeline 300 are welded on both sides of the pipeline construction pit. The two sides and the top of the retaining steel plate 250 are welded and fixed to the support piles respectively. The retaining steel plate 250 is composed of three steel plates with a height of 2m connected in sequence from top to bottom. During the excavation process, three steel plates are constructed in sequence to obtain the retaining steel plate 250. A notch 260 for the existing pipeline 300 to pass through is opened in the middle of the retaining steel plate 250;
[0050] A double-layer rubber pad 270 with a thickness of 3 mm is arranged between the existing pipeline 300 and the notch 260 in the middle of the retaining steel plate 250, and a fire blanket or soaked cotton felt is wrapped on the outer surface of the existing pipeline 300 as a fireproof layer 120, and the fireproof layer 120 is fixed by steel wire tying. The double-layer rubber pad 270 is used to improve the shock absorption effect during the welding of the retaining steel plate 250, and the fire blanket or soaked cotton felt as the fireproof layer 120 can avoid the influence of the welding of the retaining steel plate 250 on the existing pipeline 300, and prevent the galvanized layer of the existing pipeline 300 from being damaged by corrosion.
[0051] The existing pipeline 300 is supported and protected by a pipeline cross-operation protection device, which includes a pipe clamp 100 that can be sleeved on the existing pipeline 300, and the pipe clamp 100 includes two semicircular ring-shaped clamp bodies 101 and a connecting bolt 102 for detachably connecting the two clamp bodies 101. The inner wall of the pipe clamp 100 is provided with a rubber cushion layer 110 sleeved on the fireproof layer 120 of the outer wall of the existing pipeline 300. A support frame 200 that can move toward or away from the pipe clamp 100 and can move in a direction perpendicular to the axis of the existing pipeline 300 is connected to the bottom of the pipe clamp 100; the bottom of the pipe clamp 100 is connected with a pipe clamp base thread 130, which supports The frame 200 includes two parallel supporting longitudinal rods 210 with external threads in the middle and four supporting cross rods 220. The two ends of each supporting cross rod 220 are respectively connected to the two supporting longitudinal rods 210. The middle part of each supporting longitudinal rod 210 is provided with two limiting sleeves 230 through threaded sleeves. The limiting sleeves 230 and the pipe clamp base thread 130 are connected through an adjustable length lifting screw 240. The lifting screw 240 includes two adjustable screws 241 coaxially connected by threads. The top of the lifting screw 240 is threadedly connected to the threaded hole at the bottom of the pipe clamp base thread 130, and the bottom of the lifting screw 240 is fixedly connected to the limiting sleeve 230.
[0052] A foundation pit support bracket support structure 350 located on both sides of the lower part of the existing pipeline 300 is constructed in the pipeline construction pit. The two ends of the foundation pit support bracket support structure 350 are respectively connected to the two sides of the pipeline construction pit and the top is 0.5m away from the existing pipeline 300. The two ends of the two supporting longitudinal rods 210 are respectively welded and fixed to the two foundation pit support bracket support structures 350.
[0053] Excavate the pipeline construction pit to the base and install the pipeline 400 to be built;
[0054] The pipe clamp 100, the support frame 200, the foundation pit support lateral support structure 340, the foundation pit support bracket support structure 350, and the retaining steel plate 250 are removed, the earth is backfilled in layers and compacted to the designed ground, the support piles are pulled out, and the support pile holes are filled.
[0055] The construction method provided in the embodiment of the present application is to respectively construct the standard section enclosure structure 310 of the pipeline to be built, the enclosure structure 320 at the intersection of the pipeline to be built and the existing pipeline, and the enclosure reinforcement structure 330 at the intersection of the pipeline to be built and the existing pipeline during the construction at the intersection of the existing pipeline 300 and the pipeline to be built 400, so as to ensure the safety of the foundation pit support at the intersection of the existing pipeline 300 and the pipeline to be built 400, and at the same time, grouting reinforcement is performed on both sides of the existing pipeline 300 between the enclosure structure 320 at the intersection of the pipeline to be built and the existing pipeline and the enclosure reinforcement structure 330 at the intersection of the pipeline to be built and the existing pipeline, and high-pressure rotary jet piles 360 are respectively constructed at the inner corners of the enclosure structure 310 of the pipeline to be built and the enclosure reinforcement structure 330 at the intersection of the pipeline to be built and the existing pipeline. , which can effectively improve the structural strength of the foundation pit at the intersection of the pipelines and the water-stopping effect of the foundation pit, and ensure the normal progress of the pipeline construction work. Subsequently, when the excavation is performed to expose the existing pipeline 300, a retaining steel plate 250 with a notch 260 is used to support both ends of the existing pipeline 300, and a double-layer rubber pad 270 and a fireproof layer 120 are used to protect the existing pipeline 300, and then a pipeline cross-operation protection device is used to support and protect the existing pipeline 300. After the construction of the pipeline 400 to be built is completed, the pipeline cross-operation protection device, the foundation pit support lateral support structure 340, the foundation pit support bracket support structure 350, and the retaining steel plate 250 are removed, and then the earth is backfilled in layers and compacted to the designed ground, the support piles are pulled out, and the support pile holes are filled to complete the construction work.
[0056] Among them, the pipeline cross operation protection device includes a pipe clamp 100 that can be tightened and loosened to be separated from the existing pipeline 300 and a support frame 200 that can move toward or away from the pipe clamp 100 and can move in a direction perpendicular to the axis of the existing pipeline 300. The construction workers can rotate the two limiting sleeves 230 to make them move along the corresponding supporting longitudinal rods 210, thereby adjusting the two supporting longitudinal rods 210 to move in a direction perpendicular to the axis of the existing pipeline 300 to connect and support the foundation pit support support structure 350 on both sides of the lower part of the existing pipeline 300. The length of the lifting screw 240 is adjusted by rotating the two adjustable screws 241 to adjust the height distance between the two supporting longitudinal rods 210 and the pipe clamp 100, so as to ensure that the supporting longitudinal rod 210 is connected and supported on the two foundation pit support bracket support structures 350, thereby utilizing the two foundation pit support bracket support structures 350 to support the support frame 200, the pipe clamp 100 and the existing pipeline 300 mounted with the pipe clamp 100, thereby ensuring the stability of the existing pipeline 300 during the construction process and avoiding damage to the existing pipeline 300 during the construction process of the pipeline 400 to be built.
[0057] The embodiments described above are part of the embodiments of the present application, rather than all of the embodiments. The detailed description of the embodiments of the present application is not intended to limit the scope of the present application for protection, but merely represents the selected embodiments of the present application. Based on the embodiments in the present application, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present application.
Claims
1. A pipeline cross operation construction method, characterized in that: It includes the following steps: Level the site and lay out the construction trench for the pipeline to be built, and slope the sides of the construction trench for the pipeline to be built; The construction of the standard section enclosure structure of the pipeline to be built, the enclosure structure at the intersection of the pipeline to be built and the existing pipeline, and the enclosure reinforcement structure at the intersection of the pipeline to be built and the existing pipeline are respectively carried out; the standard section enclosure structure of the pipeline to be built is respectively arranged on both sides above the pipeline to be built and staggered with the existing pipeline, the enclosure structure at the intersection of the pipeline to be built and the existing pipeline is arranged above the existing pipeline and respectively located on both sides of the inner wall of the construction base trench of the pipeline to be built, the enclosure reinforcement structure at the intersection of the pipeline to be built and the existing pipeline is respectively arranged on both sides of the construction base trench of the pipeline to be built and located on both sides above the existing pipeline, and the two ends of the enclosure reinforcement structure at the intersection of the pipeline to be built and the existing pipeline are respectively connected to the standard section enclosure structure of the pipeline to be built and the enclosure structure at the intersection of the pipeline to be built and the existing pipeline on the corresponding sides; Carry out high-pressure jet grouting pile construction at the inner corner of the retaining structure of the standard section of the pipeline to be built and the retaining reinforcement structure at the intersection of the pipeline to be built and the existing pipeline; Grouting reinforcement is performed on both sides of the existing pipeline between the retaining structure at the intersection of the pipeline to be built and the existing pipeline and the retaining reinforcement structure at the intersection of the pipeline to be built and the existing pipeline; Excavate the earthwork in layers to the bottom of the support piles to obtain a pipeline construction pit, and fully expose the existing pipeline. Construct a transverse support structure for the foundation pit support on both sides of the pipeline construction pit. Weld retaining steel plates sleeved on the existing pipeline on both sides of the pipeline construction pit. The retaining steel plates are connected and fixed to the support piles. A double-layer rubber pad is arranged between the existing pipeline and the retaining steel plate, and a fireproof layer is wrapped on the outer surface of the existing pipeline; A pipe clamp is sleeved on the existing pipeline for support, a support frame that can move toward or away from the pipe clamp and can move in a direction perpendicular to the axis of the existing pipeline is connected to the bottom of the pipe clamp, and two foundation pit support bracket support structures are constructed with two ends respectively connected to two sides of the pipeline construction foundation pit to support the two ends of the support frame; Excavating the pipeline construction pit to the base, and carrying out installation construction of the pipeline to be built; The pipe clamp and the support frame are removed, and the support piles, the retaining steel plate and the transverse support structure of the foundation pit support are removed, and the earth is backfilled in layers.
2. The pipeline cross operation construction method according to claim 1, characterized in that: The inner wall of the pipe clamp is provided with a rubber cushion layer which is sleeved on the outer wall of the pipeline, and a fireproof layer is provided between the inner wall of the pipe clamp and the rubber cushion layer.
3. The pipeline cross operation construction method according to claim 1, characterized in that: The bottom of the pipe clamp is connected to a pipe clamp base thread, and the support frame includes at least two supporting longitudinal rods with external threads in the middle and at least four supporting cross rods, the two ends of the supporting cross rods are respectively connected to the two supporting longitudinal rods, and the middle part of each of the supporting longitudinal rods is provided with at least two limiting sleeves through a threaded sleeve, and the limiting sleeve and the pipe clamp base thread are connected by a lifting screw with an adjustable length.
4. The pipeline cross operation construction method according to claim 1, characterized in that: The invention also comprises two retaining steel plates, wherein the retaining steel plates are provided with slots through which the pipes pass, and the slots are provided with double-layer rubber pads which are sleeved on the pipes.
5. The pipeline cross operation construction method according to claim 1, characterized in that: The distance between the top of the foundation pit support support structure and the existing pipeline is 0.5m.
6. The pipeline cross operation construction method according to claim 1, characterized in that: When grouting reinforcement is carried out on both sides of the existing pipeline between the retaining structure at the intersection of the pipeline to be built and the existing pipeline and the retaining reinforcement structure at the intersection of the pipeline to be built and the existing pipeline, the grouting depth is more than 5m below the existing pipeline.