Construction method of beam erection in small curve of high-speed interchange

Through the single guide beam erecting machine and fine construction step adjustments, the girder erection problem caused by the small curve radius of the ramp in the high-speed interchange project is solved, ensuring the safety and feasibility of the construction, and is suitable for high-speed interchange projects with a small curve radius. .

CN115262426BActive Publication Date: 2024-10-22CHINA RAILWAY 23RD CONSTR BUREAU LTD +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202211152149.2
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2022-09-21
Publication Date
2024-10-22
Estimated Expiration
2042-09-21

AI Technical Summary

Technical Problem

The radius of the ramp curve in the high-speed interchange project is small, making it difficult to construct with the existing bridge construction technology, and the construction safety is difficult to guarantee.

Method used

A single guide beam bridge erecting machine is used. By adjusting the position and construction steps of the bridge erecting machine, and using components such as curved beams, suspension beams, and traversing rails, the prefabricated beams are gradually placed to ensure that the bridge erecting machine can operate with a small curve radius. It can be constructed normally, and the stability and safety of the prefabricated beams can be ensured through the cooperation of jacks and transverse rails.

Benefits of technology

It realizes the feasibility and safety of girder construction when the ramp curve radius is small, avoids the overturning of the bridge erecting machine and the instability of the prefabricated beam, and ensures the normal progress and safety of the construction.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN115262426B_ABST
    Figure CN115262426B_ABST
Patent Text Reader

Abstract

The present invention discloses a method for erecting beams in a high-speed interchange with a small curve, comprising the following steps: bridge erection machine through-hole operation; including the step of supporting the first column to the front pier and supporting the second column on the bridge deck close to the pier; beam feeding operation and beam dropping operation; the front beam crane and the rear beam crane lift the prefabricated beam, and control the entire bridge erection machine to move horizontally to the beam erection position and then drop the beam. The construction method of the present invention solves the problem that the bridge erection machine is difficult to perform beam erection construction due to the small radius of the interchange ramp curve by adjusting the setting position of the bridge erection machine when dropping the beam and the construction steps, so that it can be suitable for normal construction operations with a small curve radius, and can effectively ensure the safety during the construction operation.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention belongs to the technical field of road and bridge construction, and particularly relates to a high-speed interchange small curve beam erection construction method. Background Art

[0002] Interchanges are commonly used for traffic transfers between highways. One highway interchange project was designed as a double-ring, semi-cloverleaf interchange. The main line and ramps of the interchange underpassed existing highway bridges at multiple points. Furthermore, the ramp curve radius was small, only 125 meters, making construction difficult using existing bridge construction techniques and ensuring safety during the construction process. Summary of the Invention

[0003] The purpose of the present invention is to provide a method for constructing a small-curve beam in a high-speed interchange, so as to solve the problem that the construction of a high-speed interchange is difficult due to the small radius of the ramp curve.

[0004] The present invention is achieved through the following technical solutions:

[0005] The construction method for erecting small curved beams at high-speed interchanges uses a single-beam bridge erection machine to erect precast beams. The single-beam bridge erection machine includes a machine arm, a curved beam, column No. 0, column No. 1, column No. 2, column No. 3, a beam crane, and a transverse track for column No. 1 and column No. 2. The curved beam includes a front curved beam and a rear curved beam, and the beam crane includes a front crane and a rear crane.

[0006] The beam erection construction method includes the following steps:

[0007] Bridge erection machine through-hole operation; including the steps of supporting the first column to the front pier and supporting the second column on the bridge deck near the pier;

[0008] Beam feeding and lowering operations: the front and rear beam cranes lift prefabricated beams, and control the entire bridge erection machine to move horizontally to the beam erection position before lowering the beams;

[0009] During the beam lowering operation, when erecting the inner side beam, the center points of the No. 1 and No. 2 columns on the corresponding transverse track should not exceed the corresponding pier cap beam block and the outermost edge of the bridge deck; during the beam lowering process, the No. 1 and No. 2 column transverse tracks are first moved horizontally into place, the transverse track wheels of the No. 1 and No. 2 columns are locked, and then the hoisted precast beam is adjusted to the beam erection position by adjusting the curved beam transverse cylinder;

[0010] When erecting the outer edge beam, move the horizontal track wheel of column No. 1 to the outermost edge of the cap beam, then temporarily drop the precast beam at one end of column No. 1 onto the support pad stone of the corresponding pier, set a horizontal track on the pier close to the bridge deck, drop the precast beam at one end of column No. 2 onto the horizontal track, then push the precast beam horizontally to the beam erection position and drop the beam.

[0011] On the other hand, in the construction method of the present invention, the steps of dropping the outer beam include:

[0012] After the outer beam is pushed horizontally to the beam drop position, the precast beam is lifted by a jack, the jack oil valve is locked, the transverse track is pulled out, the support is installed on the support pad stone, and then the jack is slowly depressurized to drop the precast beam onto the corresponding support.

[0013] On the other hand, in the construction method of the present invention, the transverse track includes a steel rail, a roller set on the steel rail, and a slide plate set on the roller plate, and one end of the outer beam falls on the slide plate of the transverse track;

[0014] Use a jack to push the outer beam laterally. During the pushing process, gradually increase the pushing force according to the required pushing force until the precast beam starts to move, and then reduce the pushing force of the jack after the precast beam starts to move.

[0015] On the other hand, in the construction method of the present invention, the bridge erection machine through-hole operation comprises the following steps:

[0016] a. Connect the front beam carriage to the front curved beam, connect the rear beam carriage to the rear curved beam, flip down the No. 3 column horizontally, and support the No. 1 column on the pier close to the bridge deck;

[0017] b. Retract the No.3 column, drive the arm to move the No.3 column forward to a position close to the No.2 column, and support the No.3 column;

[0018] c. Retract the No.2 column and drive the No.2 column forward a certain distance to support the No.2 column;

[0019] d. Retract the No. 3 column and drive the boom forward to the No. 0 column to reach the front pier. Before supporting the No. 0 column, ensure that the lower crossbeam of the No. 0 column is parallel to the center line of the front pier.

[0020] e. Support the third column, retract the second column, drive the second column forward to the beam erection position, support the second column, and rotate the second column before supporting it so that the second column's transverse track is parallel to the front pier;

[0021] f. Retract column No. 1 and drive it forward to the front pier position, then support column No. 1. Before supporting column No. 1, rotate column No. 1 so that its transverse track is parallel to the center line of the pier;

[0022] g. Retract column No. 3, drive the arm forward, and adjust columns No. 1 and No. 2 to move horizontally along the horizontal track of column No. 1 and column No. 2 respectively. Adjust the arm of the bridge-erecting machine to make it parallel to the prefabricated T-beam at the location to be erected.

[0023] On the other hand, in the construction method of the present invention, during the bridge-building machine's hole-passing operation, the horizontality of the machine arm is adjusted so that the horizontality of the machine arm is always no more than 0.5%; when the No. 0 column and the No. 1 column are supporting, the verticality of the No. 0 column and the No. 1 column is adjusted so that the verticality is always no more than 0.5%.

[0024] On the other hand, in the construction method of the present invention, when setting the No. 1 column and the No. 2 column during the bridge-building machine's through-hole operation, the No. 1 column, the No. 2 column and the center line of the cap beam of the corresponding pier form an angle of 3° to 5°.

[0025] On the other hand, in the construction method of the present invention, the cap beam of each span of the pier is set to a fan-shaped structure, so that the center line of the cap beam and the end face of the precast beam form an angle of 3° to 5°.

[0026] On the other hand, in the construction method of the present invention, the order of erecting beams is inner side beam, secondary inner side beam, outer side beam, secondary outer side beam and middle beam, and the erection operation of a single-span bridge is completed in sequence.

[0027] On the other hand, in the construction method of the present invention, after the inner side beams are erected, the secondary inner side beams are erected, and then the transverse diaphragm steel bars between the two prefabricated beams are welded.

[0028] On the other hand, in the construction method of the present invention, after the outer edge beams are erected, the secondary outer edge beams are erected, and then the transverse diaphragm steel bars between the two prefabricated beams are welded.

[0029] The construction method of the present invention solves the problem that the bridge erection machine has difficulty in performing beam erection construction due to the small curve radius of the interchange ramp by adjusting the setting position of the bridge erection machine when dropping the beam and the construction steps. It makes the bridge erection machine suitable for normal construction operations with a small curve radius and can effectively ensure safety during the construction operation. BRIEF DESCRIPTION OF THE DRAWINGS

[0030] In order to more clearly illustrate the technical solutions of the embodiments of the present invention, the drawings in the embodiments will be briefly introduced below. It should be understood that the following drawings only illustrate certain embodiments of the present invention and therefore should not be regarded as limiting the scope. For ordinary technicians in this field, other relevant drawings can be obtained based on these drawings without paying any creative work.

[0031] Figure 1 It is a schematic diagram of the bridge construction structure of a single guide beam bridge erecting machine according to the construction method of the present invention.

[0032] Figure 2 This is a schematic diagram of step a in the through-hole operation of the bridge-building machine in the construction method of the present invention.

[0033] Figure 3 This is a schematic diagram of step b in the bridge-building machine through-hole operation in the construction method of the present invention.

[0034] Figure 4 This is a schematic diagram of step c in the bridge-building machine through-hole operation in the construction method of the present invention.

[0035] Figure 5 This is a schematic diagram of step d in the through-hole operation of the bridge-building machine in the construction method of the present invention.

[0036] Figure 6 This is a schematic diagram of step e in the through-hole operation of the bridge-building machine in the construction method of the present invention.

[0037] Figure 7 This is a schematic diagram of step f in the bridge-building machine through-hole operation in the construction method of the present invention.

[0038] Figure 8 This is a schematic diagram of the front crane hoisting the beam during the beam feeding operation of the construction method of the present invention.

[0039] Figure 9 This is a schematic diagram of the rear beam crane hoisting during the beam feeding operation of the construction method of the present invention.

[0040] Figure 10 It is a schematic diagram of the inner side beam dropping structure in the beam dropping operation of the construction method of the present invention.

[0041] Figure 11 It is a schematic diagram of the outer beam dropping structure in the beam dropping operation of the construction method of the present invention.

[0042] Figure 12 It is a schematic diagram of the transverse track structure of the construction method of the present invention.

[0043] Figure 13 It is a schematic diagram of the rolling structure in the transverse track of the construction method of the present invention.

[0044] Figure 14 It is a schematic diagram of the structure of prefabricated T-beams erected on piers in the construction method of the present invention.

[0045] in:

[0046] 11. Arm, 12. Column 0, 13. Column 1, 14. Column 2, 15. Column 3, 16. Front curved beam, 17. Rear curved beam;

[0047] 21. Pier, 22. Front pier, 23. Precast T-beam, 231. Inner side beam, 232. Secondary inner side beam, 233. Middle beam, 234. Secondary outer side beam, 235. Outer side beam, 24. Support, 25. Support pad stone, 26. Cap beam;

[0048] 31. Rail, 32. Roller, 33. Slide;

[0049] 41. Front rail beam transport vehicle, 42. Rear rail beam transport vehicle. DETAILED DESCRIPTION

[0050] In order to make the purpose, technical solutions and advantages of the embodiments of the present invention clearer, the technical solutions in the embodiments of the present invention will be clearly and completely described below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments.

[0051] In this embodiment, a DJ180 bridge erection machine is used for construction. This type of bridge erection machine is a single-arm simply supported type that can achieve full-width mechanical transverse movement of beams and drop the beams into place in one go. It has the characteristics of simple structure.

[0052] Reference Figure 1 This type of bridge-building machine includes an arm assembly, a curved beam and a transverse movement mechanism, a No. 0 column 12, a No. 1 column 13, a No. 2 column 14, a No. 3 column 15, a No. 1 column transverse movement track, a No. 2 column transverse movement track, a beam crane and an electric hydraulic control system for controlling the movement of each component.

[0053] Among them, the arm assembly includes the arm 11, which is the main load-bearing structural component of the bridge-building machine; it adopts a box-type section, with upper and lower ear beams on both sides of the section; a rack is provided at the bottom, and the arm is usually made of five-section unit beams assembled and connected by pins.

[0054] The curved beams and their traverse mechanisms are the primary components supporting and driving the boom. They comprise a front curved beam 16 and a rear curved beam 17, mounted on the upper crossbeams of the No. 1 and No. 2 columns, respectively, and connected to the boom via balancing wheels. The traverse mechanism is bolted to the top of the curved beam at one end and bolted to the upper crossbeams of the No. 1 and No. 2 columns, respectively, at the other end. The traverse mechanisms of the front and rear curved beams have identical connection directions and can achieve a traverse range of up to 750mm in both the left and right directions, driving the No. 1 and No. 2 columns laterally on the No. 1 and No. 2 traverse tracks.

[0055] During the curved beam feeding operation, it is necessary to separately adjust the transverse cylinder on the curved beam at column No. 2 to prevent the prefabricated T-beam piece from colliding with the column No. 2; but this will cause column No. 1 to deflect, so it is also necessary to adjust the longitudinal adjustment cylinder at column No. 1 to adjust column No. 1 to a vertical state.

[0056] The zero column is installed at the front end of the machine arm and adopts a two-stage telescopic and narrow door frame structure; it can be flipped in the horizontal direction, and the zero column can be easily flipped to a horizontal position during transportation.

[0057] The No. 1 column is connected to the front curved beam via its upper crossbeam. Its shaft utilizes two telescopic columns, each with a 3000mm adjustment range. Conventional structures typically feature two adjustment sections: a 3400mm adjustment for flat bridges and an 1100mm adjustment for downhill bridges. The No. 1 column is mounted on a lateral track and equipped with a traveling mechanism, enabling it to move horizontally along the track at a speed of 1.6m / min.

[0058] The No. 2 column is connected to the rear curved beam through its upper crossbeam; the column body of the No. 2 column adopts four two-stage retractable columns with an adjustable height of 3000m; the No. 2 column is set on the No. 2 column transverse track, and the No. 2 column is also equipped with a walking mechanism, so that the No. 2 column can move laterally on the No. 2 column transverse track with a transverse speed of 1.6m / min. There are two No. 2 column transverse tracks.

[0059] The third column is mounted at the rear end of the boom and connected to the boom via a frame-shaped connecting bracket. Its body features two telescopic columns, with an adjustable height of 3150m. The conventional structure includes a 400mm adjustment joint, which is useful when erecting uphill bridges. To accommodate beam feeding operations on small curves, the third column is connected to the boom using a flip connection, allowing it to flip backward. A hydraulic cylinder is installed between the boom and the third column to power its rotation.

[0060] The crane is divided into a front crane and a rear crane, depending on its location on the boom. Both cranes are mounted on the lower boom ears via wheels. The crane travels on the boom at a speed of 5 m / min. The crane hoists utilize electric winches at a speed of 0.6 m / min. Each electric winch is equipped with a 7.5 kW brake motor and an electromagnetic brake for bipolar braking.

[0061] The overhead construction method of erecting beams using a single-beam bridge-erecting machine usually includes: loading and transporting beams - feeding beams - dropping beams - and horizontal movement operations.

[0062] In the high-speed hub interchange of this project, the ramp bridge radius is 125m, and the ramp curve radius is relatively small. When erecting the outer beam, the bridge-erecting machine will not be able to move the prefabricated T-beam into place. In this construction plan, a single-beam bridge-erecting machine is used to drop the beam. When erecting the outer beam, in order to ensure the safety of the entire bridge-erecting machine and prevent the bridge-erecting machine from overturning, one end of the outer beam is placed on the pier, and the other end is dropped on the transverse track slide. Then, a jack is used to move the other end of the outer beam into place. The prefabricated T-beams in other locations can be erected using a single-beam bridge-erecting machine according to normal construction operations.

[0063] Specifically, in this embodiment, for the construction condition where the radius of the high-speed interchange ramp is small, the construction scheme adopted is as follows:

[0064] 1) Curved hole-passing and positioning operation of bridge erection machine

[0065] a. When the whole bridge erection machine is ready to pass through the hole, release the connection between the curved beam and the machine arm, pin the front beam erection crane to the curved beam of the No. 1 column, pin the rear beam erection crane to the curved beam of the No. 2 column, flip the No. 3 column horizontally downward, and support the No. 1 column on the pier 21 close to the bridge deck; Figure 2 As shown;

[0066] b. Retract the No.3 column, drive the arm, move the No.3 column forward 9m to the position of the No.2 column, and support the No.3 column. Figure 3 As shown;

[0067] c. Collect the No.2 column and move the No.2 column forward 6.5m, support the No.2 column, such as Figure 4 As shown;

[0068] d. Retract the No.3 column and drive the arm to move the No.3 column forward 2.3m. At this time, the No.0 column reaches the front pier 22. Support the No.0 column. Figure 5 As shown; before supporting the No. 0 column, ensure that the lower crossbeam of the No. 0 column is parallel to the center line of the front pier to reduce the space occupied by the No. 0 column on the pier. According to the actual height of the No. 0 column at the longitudinal slope support, adjust the horizontality of the boom to no more than 0.5%;

[0069] e. Support the third column, retract the second column, drive the second column forward 16.6m to the beam erection position, support the second column, and rotate the second column before supporting it so that the horizontal movement track of the second column is parallel to the front pier. Figure 6 ;

[0070] f. Retract column No.1 and drive it forward 25m to the pier ahead. Support column No.1 and rotate it before supporting it so that its horizontal movement track is parallel to the center line of the pier. Figure 7 ;

[0071] g. Retract column No. 3, drive the arm forward, and adjust column No. 1 and column No. 2 so that they move laterally along the transverse track of column No. 1 and column No. 2 respectively. Adjust the arm of the bridge-erecting machine so that the arm of the bridge-erecting machine is parallel to the prefabricated T-beam at the location to be erected. Ensure the verticality of column No. 1 during the adjustment process. When the verticality of column No. 1 is greater than 0.5%, adjust column No. 1 to a vertical state until the through-hole operation is completed.

[0072] Due to the small radius of the ramp curve, the cap beam 26 of each span of the pier is set to a fan-shaped structure, and the angle between the center line of the cap beam and the end face of the precast beam is 5°; during the beam erection process, the horizontal moving track of the No. 1 column and the horizontal moving track of the No. 2 column of the bridge erection machine should be kept balanced. In order to meet the needs of the horizontal movement of the inner and outer side beams, when setting the No. 1 and No. 2 columns, the horizontal moving track of the No. 1 column, the horizontal moving track of the No. 2 column and the center line of the cap beam are at an angle of 5°.

[0073] 2) Prefabricated T-beam transportation and beam erection operations

[0074] According to the beam erection sequence, the inner side beam 231, the secondary inner side beam 232, the outer side beam 235, the secondary outer side beam 234 are erected in sequence, and finally the middle beam 233 is erected to complete the erection operation of the single-span bridge.

[0075] The precast T-beam 23 is transported using a four-axle rail-mounted beam transporter, including a front rail-mounted beam transporter 41 and a rear rail-mounted beam transporter 42. During beam transport, the two ends of the precast T-beam are placed on the movable pallets of the two rail-mounted beam transporters, respectively, so that the precast T-beam can rotate relative to the rail-mounted beam transporter during transport. The precast T-beam is transported to 100m from the front of the bridge crane, and a double-row beam-lifting gantry is set up 100m in front of the bridge crane. Tracks are laid 50m from the bridge crane, and rail-mounted beam transporters are set up above the tracks. The rail-mounted beam transporters also need to meet the requirement of lowering the height of the bridge crane feeding beams during beam erection construction. Usually, two rail-mounted beam transporters are used, both with a height of 0.65m.

[0076] During the operation of loading and transporting beams, when the prefabricated T-beam is transported to the bottom of the beam-lifting gantry, the beam-lifting gantry will lift the prefabricated T-beam onto the rail beam transport vehicle. The center of gravity of the prefabricated T-beam should fall on the longitudinal center line of the rail beam transport vehicle, with a deviation of no more than 20mm; when the prefabricated T-beam falls on the rail beam transport vehicle, the front end of the prefabricated T-beam shall not exceed 2.5m of the supporting crossbeam of the rail beam transport vehicle, and the upper end of the inclined support of the rail beam transport vehicle shall be padded with hard miscellaneous wood or rubber belts to ensure complete contact with the beam piece, and the diagonal support shall be firmly supported and locked to protect the concrete of the beam piece; before transporting the beam, ensure that the steel wire ropes binding the beam piece are tightened and locked, and the contact points between the steel wire ropes and the beam piece are padded with rubber to protect the concrete of the beam body and the steel wire ropes binding the beam piece, so as to ensure the safe transportation of the prefabricated T-beam.

[0077] Precast T-beams are hoisted using a bottom-of-beam hoisting method with lifting holes installed. Using this hoisting method, wire ropes are passed through the bottom plate of the precast T-beam from the lifting points at both ends of the beam, around the precast T-beam flanges, and then snapped into the clamping ring at the top of the hoist. Due to the small radius of the ramp curve, the dimensional deviations of the flanges on both sides of the precast T-beam are large. To ensure the stability of the side beam hoisting, lifting holes are reserved on both sides of the side beam web during prefabrication to ensure the stability of the side beam hoisting.

[0078] 3) Beam feeding and beam dropping operations

[0079] a. Front crane beam;

[0080] Reference Figure 8 , flip the No.3 column horizontally to the rear, and the rail-mounted beam transporter transports the prefabricated T-beam to the rear of the No.2 column. Adjust the bridge-erecting machine to achieve horizontal movement of the entire machine, so that the front beam crane is directly above one end of the prefabricated T-beam. At this time, the distance between the front beam crane and the No.2 column horizontal movement track is about 3.5m;

[0081] The front crane hoisted the beam, maintaining an inclination angle of no more than 20°. The crane then advanced simultaneously with the rear rail-mounted beam transporter, coordinating the vehicle's speed. During this advancement, the crane's arm tracked the precast T-beam, while the rear rail-mounted beam transporter tracked the precast T-beam. Therefore, the crane's lateral movement was adjusted to adjust the position of the precast T-beam and prevent any scraping between the precast T-beam and the No. 2 column. During this adjustment process, the verticality of the No. 1 column was maintained (no more than 0.5%). If tilting occurred, the longitudinal displacement cylinder above the No. 1 curved beam was promptly adjusted to maintain the column's verticality.

[0082] b. Rear crane beam;

[0083] Reference Figure 9 When the rear rail beam transport vehicle reaches the lifting position of the rear beam crane, the other end of the prefabricated T-beam is lifted by the rear beam crane and raised so that the prefabricated T-beam is in a horizontal state. At this time, the front and rear beam cranes lift the beam forward at the same time, and adjust the position of the No. 2 column laterally during the movement so that the prefabricated T-beam can pass through the No. 2 column smoothly.

[0084] c. Erection of inner side beams and secondary inner side beams;

[0085] Reference Figure 10 When erecting the inner side beam, in order to ensure the stability of the entire bridge erection machine and prevent the bridge erection machine from overturning, the center points of the No. 1 and No. 2 columns of the bridge erection machine on the corresponding transverse track must not exceed the cap beam block and the outermost edge of the bridge deck to avoid the bridge erection machine from tipping over due to the outward extension of the bridge erection machine. Therefore, during the beam lowering process, the No. 1 column transverse track and the No. 2 column transverse track should be moved into place first, and after locking the transverse track wheels of the No. 1 and No. 2 columns, they should be accurately positioned by adjusting the curved beam transverse cylinder to ensure the safety of beam erection.

[0086] When the transverse track wheel of column No. 1 reaches the outermost edge of the cap beam, the transverse track wheel of column No. 2 is 22 cm away from the outermost edge of the bridge deck, and the position of the center line of the curved beam and the center line of the support meet the requirements for beam dropping. At this time, the inner side beam can be directly moved into place by the bridge erection machine.

[0087] After the inner side beam is erected, the secondary inner side beam is erected, and then the cross-partition steel bars between the two prefabricated T-beams are welded to ensure the stability of the beam.

[0088] d. Erection of outer beams and secondary outer beams

[0089] Reference Figure 11 When erecting the outer edge beam, the horizontal track wheel of the bridge erection machine's No. 1 column moves to the outermost edge of the cap beam. At this time, the distance between the centerline of the curved beam at the No. 2 column and the centerline of the cap beam support is 49 cm, making it impossible to drop the prefabricated T-beam piece on the support pad. To ensure the safety of the bridge erection machine, the prefabricated T-beam at the end of the No. 1 column is temporarily dropped on the support pad, and the prefabricated T-beam at the end of the No. 2 column is dropped on the horizontal track and moved into place horizontally using jacks.

[0090] like Figure 12 and 13 The horizontal track here uses No. 43 steel rail 31, and the roller 32 and slide 33 are arranged in sequence on the steel rail 31. The roller is made of 50cm round steel and 2cm steel plate; one end of the prefabricated T-beam to be erected is placed on the slide; the prefabricated T-beam is stably fixed on the slide, and a 15t jack is used to perform the transverse movement of the prefabricated T-beam. After the transverse movement is into place, two QYL32-ton jacks are used to synchronously unload the prefabricated T-beam to the beam erection position.

[0091] The specific steps of the jacking construction operation are as follows: place the prefabricated T-beam on the slide. During the jacking process, the pads need to be followed up in time. The size of the horizontal jacking is estimated based on the support reaction force calculated according to the center beam of the prefabricated T-beam. The jacking force is gradually increased according to the required jacking force until the beam starts to move forward. After the beam starts to move, the jacking force of the jack is appropriately reduced to allow the beam to move forward in a balanced manner.

[0092] During the jacking process of the beam, as the beam advances, the lateral limit controls the deviation of its center line within 10mm. During the jacking process of the T-beam, the deviation of each pier and the center line position of the beam are tracked and measured, and the jacking speed is controlled. A limit device is set between the slide of the transverse track and the pier top to prevent large movement during jacking. Hard wooden blocks are used to fill the space between the limit device and the pier top to prevent the lateral movement distance from exceeding the center line position of the pier support.

[0093] The specific steps of the beam drop construction operation are as follows: After the prefabricated T-beam is pushed into place horizontally, the prefabricated T-beam is lifted with a jack, and the horizontal track is pulled out. After the beam body is lifted into place, the jack oil valve is locked, and the longitudinal and transverse position deviations of the prefabricated T-beam are checked. The support 24 is installed on the support pad 25, and the jack is slowly depressurized to slowly drop the prefabricated T-beam onto the support 24. Figure 14 Schematic diagram of the structure of prefabricated T-beam erected on the pier.

[0094] After the erection of the outer beam is completed, the secondary outer beam is erected and the cross-partition steel bars of the two prefabricated beams are welded to ensure the stability of the beam body.

[0095] e. Middle beam installation

[0096] During the installation of the middle beam, the speed of beam dropping is slowed down to prevent the middle beam from colliding with other beams and causing the beam to overturn.

[0097] After the middle beam is erected, the bridge deck system is installed in time, and then the erection of the next beam is carried out.

[0098] During the beam dropping operation, when the beam is about to be in place, the prefabricated T-beam is aligned with the center line of the support plate led out from the end of the prefabricated T-beam by using a hanging hammer and the cross line of the pad stone. When there is a conflict between the alignment of the longitudinal center line and the end line of the prefabricated T-beam, the center line of the support shall be used as the standard. After the beam is dropped, the rubber bearing shall be in close contact with the steel plate at the bottom of the beam.

[0099] In the description of the present invention, it should be noted that the terms "center", "up", "down", "left", "right", "vertical", "horizontal", "inside", "outside", etc. used to indicate the orientation or position relationship are based on the orientation or position relationship shown in the accompanying drawings, or are the orientation or position relationship in which the product of the invention is usually placed when in use. They are only for the convenience of describing the present invention and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation. Therefore, they should not be understood as limiting the present invention.

[0100] Furthermore, the use of terms such as "horizontal" and "vertical" in the description of the present invention does not necessarily imply that the component must be absolutely horizontal or suspended, but rather that it can be slightly tilted. For example, "horizontal" simply means that its direction is more horizontal than "vertical" and does not mean that the structure must be completely horizontal, but rather that it can be slightly tilted.

[0101] It should also be noted that, in the description of the present invention, unless otherwise expressly specified or limited, the terms "disposed," "installed," "connected," and "connected" should be understood in a broad sense. For example, they may refer to fixed connections, detachable connections, or integral connections; mechanical connections or electrical connections; direct connections or indirect connections through an intermediate medium; and internal connections between two components. Those skilled in the art will understand the specific meanings of the above terms in the present invention in specific contexts.

[0102] The above description is only a preferred embodiment of the present invention and does not limit the present invention in any form. Any simple modification or equivalent change made to the above embodiment based on the technical essence of the present invention shall fall within the scope of protection of the present invention.

Claims

1. Construction method of small curve beam erection for high-speed interchange, It is characterized in that A single-beam bridge erection machine is used to erect prefabricated beams. The single-beam bridge erection machine includes a machine arm, a curved beam, a zero column, a first column, a second column, a third column, a beam crane, and a first column transverse track and a second column transverse track. The curved beam includes a front curved beam and a rear curved beam, and the beam crane includes a front beam crane and a rear beam crane. The beam erection construction method comprises the following steps: Bridge erection machine through-hole operation; including the steps of supporting the first column to the front pier and supporting the second column on the bridge deck near the pier; Beam feeding and beam dropping operations: the front and rear beam cranes lift prefabricated beams, control the entire bridge erecting machine to move horizontally to the beam erecting position, and then drop the beams; During the beam dropping operation, when erecting the inner side beam, the center points of the No. 1 column and the No. 2 column on the corresponding No. 1 column transverse track and the No. 2 column transverse track shall not exceed the corresponding pier cap beam stopper and the outermost edge of the bridge deck; during the beam dropping process, the No. 1 column transverse track and the No. 2 column transverse track shall be first moved to the right position, the transverse track wheels of the No. 1 column and the No. 2 column shall be locked, and then the hoisted prefabricated beam shall be adjusted to the beam erection position by adjusting the curved beam transverse cylinder; When erecting the outer side beam, move the horizontal track wheel of the No. 1 column to the edge of the cap beam, and then temporarily drop the precast beam at one end of the No. 1 column onto the supporting pad stone of the corresponding pier. Set a horizontal track on the pier close to the bridge deck, drop the precast beam at one end of the No. 2 column onto the horizontal track, and then push the precast beam to the beam erection position and drop the beam. During the beam erection process, when setting column No. 1 and column No. 2, the transverse track of column No. 1, the transverse track of column No. 2 and the center line of the cap beam form an angle of 5°.

2. The high-speed interchange small curve beam erection construction method according to claim 1, It is characterized in that The steps for dropping the outer beam include: After the outer beam is pushed horizontally to the beam drop position, the precast beam is lifted by a jack, the jack oil valve is locked, the transverse track is pulled out, the support is installed on the support pad stone, and then the jack is slowly depressurized to drop the precast beam onto the corresponding support.

3. The high-speed interchange small curve beam erection construction method according to claim 1, It is characterized in that The transverse track includes a steel rail, a roller arranged on the steel rail, and a slide plate arranged on the roller plate, and one end of the outer beam falls on the slide plate of the transverse track; A jack is used to push the outer beam laterally. During the pushing process, the pushing force is gradually increased according to the required pushing force until the precast beam starts to move, and the pushing force of the jack is reduced after the precast beam starts to move.

4. The high-speed interchange small curve beam construction method according to claim 1, It is characterized in that The bridge erection machine through-hole operation includes the following steps: a. Connect the front beam crane to the front curved beam, connect the rear beam crane to the rear curved beam, flip down the No. 3 column horizontally, and support the No. 1 column on the pier close to the bridge deck; b. Retract the No.3 column, drive the machine arm to move the No.3 column forward to a position close to the No.2 column, and support the No.3 column; c. Collect the No.2 column and drive the No.2 column forward a certain distance to support the No.2 column; d. Retract the No. 3 column, drive the arm forward to the No. 0 column to reach the front pier position, and then to the No. 0 column. Before supporting the No. 0 column, ensure that the lower crossbeam of the No. 0 column is parallel to the center line of the front pier; e. Support the third column, collect the second column, drive the second column forward to the beam erection position, support the second column, and rotate the second column before supporting it, so that the transverse track of the second column is parallel to the front pier; f. Retract column No.1, drive column No.1 forward to the front pier position, support column No.1, and rotate column No.1 before supporting it, so that the horizontal movement track of column No.1 is parallel to the center line of the pier; g. Retract column No. 3, drive the arm forward, and adjust columns No. 1 and No. 2 to move horizontally along the horizontal track of column No. 1 and column No. 2 respectively, and adjust the arm of the bridge-erecting machine to make it parallel to the prefabricated T-beam at the location to be erected.

5. The high-speed interchange small curve beam erection construction method according to claim 4, It is characterized in that During the hole-passing operation of the bridge-building machine, adjust the horizontality of the machine arm so that the horizontality of the machine arm is always no greater than 0.5%; when supporting the No. 0 column and the No. 1 column, adjust the verticality of the No. 0 column and the No. 1 column so that the verticality is always no greater than 0.5%.

6. The high-speed interchange small curve beam erection construction method according to claim 4, It is characterized in that When setting column No.1 and column No.2 during the through-hole operation of the bridge-building machine, an angle of 3° to 5° is formed between column No.1, column No.2 and the center line of the cap beam of the corresponding pier.

7. The high-speed interchange small curve beam erection construction method according to claim 6, It is characterized in that The cap beam of each span of the pier is set to a fan-shaped structure, so that the center line of the cap beam and the end face of the precast beam form an angle of 3° to 5°.

8. The high-speed interchange small curve beam erection construction method according to claim 1, It is characterized in that The order of beam erection is inner side beam, secondary inner side beam, outer side beam, secondary outer side beam and middle beam, and the erection operation of a single-span bridge is completed in sequence.

9. The high-speed interchange small curve beam erection construction method according to claim 8, It is characterized in that After the inner side beam is erected, the secondary inner side beam is erected, and then the cross diaphragm steel bars between the two prefabricated beams are welded.

10. The high-speed interchange small curve beam erection construction method according to claim 8, It is characterized in that After the outer beam is erected, the secondary outer beam is erected, and then the cross-partition reinforcement between the two prefabricated beams is welded.