A kind of underground structure outer wall intensive rigid waterproof casing and construction method thereof
By filling the reserved grooves of the dense rigid waterproof casing of the underground structure exterior wall with non-cured rubber asphalt waterproof coating and using a compression mold to tighten the waterproof coil, the problem of high leakage risks in waterproof node construction is solved, and a more efficient waterproof effect is achieved.
Patent Information
- Application Number
- CN202210828804.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2022-07-15
- Publication Date
- 2025-03-11
- Estimated Expiration
- 2042-07-15
AI Technical Summary
The construction of waterproof nodes of dense rigid waterproof casings with existing underground structures has high leakage risks, affecting the use function of the building.
A dense rigid waterproof casing of an underground structure exterior wall including reserved grooves, water-stop steel plates, waterproof coils and compression molds is designed. The waterproof effect is enhanced by filling the reserved grooves with non-cured rubber asphalt waterproof coatings and pressing the waterproof coils with compression molds.
It effectively improves the waterproofing effect, reduces the hidden danger of leakage, and ensures the waterproof performance of the basement exterior wall.
Smart Images

Figure CN115289289B_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of construction engineering, and specifically relates to a dense rigid waterproof sleeve for the external wall of an underground structure and a construction method thereof. Background Technique
[0002] With the continuous development of the construction industry, the application of underground space is becoming more and more extensive. Subsequently, the dense rigid waterproof sleeves for the external walls of basement structures have been increasingly favored by major construction enterprises. The application of dense rigid waterproof sleeves can protect the pipeline from external interference and ensure the smooth installation of the pipeline.
[0003] However, at present, due to the relatively dense rigid waterproof sleeves, the construction of traditional waterproof joint practices is difficult, there are high potential leakage hazards, and it may even affect the service functions of buildings. For this reason, the present invention proposes a dense rigid waterproof sleeve for the external wall of an underground structure and a construction method thereof to solve the above problems. Summary of the Invention
[0004] The purpose of the present invention is to provide a dense rigid waterproof sleeve for the external wall of an underground structure and a construction method thereof to solve the problem of high potential leakage hazards in the waterproof joint construction of dense rigid waterproof sleeves proposed in the above background technique.
[0005] To achieve the above purpose, the present invention provides the following technical solutions: A dense rigid waterproof sleeve for the external wall of an underground structure, including:
[0006] The external wall of the basement, a reserved groove is provided on the surface of the external wall of the basement, a plurality of rigid sleeves arranged in a rectangular array are provided in the middle of the reserved groove, and the rigid sleeves penetrate through the external wall of the basement;
[0007] A waterstop steel plate, the waterstop steel plate is embedded in the bottom of the reserved groove, and a plurality of rigid sleeves are fixedly connected through the waterstop steel plate;
[0008] A waterproof coiled material, the waterproof coiled material is sleeved on the outside of a plurality of rigid sleeves, and the inner side wall of the waterproof coiled material is attached to the surface of the waterstop steel plate; and
[0009] A pressing die, the pressing die is located outside a plurality of rigid sleeves, and the pressing die presses on the edge of the surface of the waterproof coiled material.
[0010] Preferably, the pressing die includes a pressing frame, the pressing frame is set in a "C" shape with an upward opening, and the pressing frame is made by sequentially connecting and welding three angle steels end to end.
[0011] Preferably, two groups of connecting frames are arranged on the front side of the pressing mold, each group of the connecting frames includes two connecting plates parallel to each other, both ends of the connecting plates are fixedly connected to supporting plates perpendicular thereto, and one end of the supporting plate is fixedly connected to the pressing frame.
[0012] Preferably, both ends of the two groups of connecting frames are provided with tension bolts, and one end of the tension bolt movably passes through the rigid sleeve and extends to the back side of the outer wall of the basement.
[0013] Preferably, bolt washers are provided at both ends of the tensioning bolt, and the bolt washers are buckled on the outside of the ends of the connecting frame and the rigid sleeve, and the bolt washers located at both ends of the tensioning bolt are kept tightened by nuts.
[0014] Preferably, a plurality of positioning steel bars are embedded inside the outer wall of the basement, and the plurality of positioning steel bars are respectively located at the two end edges and the lower end edge of the waterstop steel plate, and the plurality of positioning steel bars located at the same edge of the waterstop steel plate are distributed at equal intervals.
[0015] A construction method for the above-mentioned underground structure outer wall intensive rigid waterproof casing comprises the following steps:
[0016] Step 1: Processing of intensive rigid waterproof casing. Select casings of specific sizes according to the drawing requirements, and use plasma tube plate cutting machine and welding robot to centrally process intensive rigid waterproof casing;
[0017] Step 2: Pre-embedded positioning of the intensive rigid waterproof casing. During the reinforcement binding process of the basement structure exterior wall, first weld the positioning steel bars at the bottom of the intensive rigid waterproof casing to temporarily position and support the waterstop steel plate and the rigid casing. After the reinforcement binding is completed, weld vertical positioning steel bars on both sides of the intensive rigid waterproof casing to fix the entire waterstop steel plate and the rigid casing;
[0018] Step 3: Processing and supporting the dense rigid waterproof casing template. When processing and supporting the casing template, fix the rubber strip on the inner side of the casing template to form a reserved groove on the four sides of the entire dense rigid waterproof casing, which is used for overlapping and closing the waterproof membrane;
[0019] Step 4: Construction of the external wall waterproofing nodes of the intensive rigid waterproof casing. The basement outer wall is made of concrete pouring. After the basement outer wall solidifies and the formwork of the basement outer wall is removed, a compacting mold is used with the waterproofing membrane and non-curing rubber asphalt waterproofing coating is poured. After it solidifies, the compacting mold is removed. The waterproofing membrane overlaps mm in the reserved groove, and then a galvanized metal strip is used to close and fix the waterproofing membrane to the reserved groove. Finally, the reserved groove is sealed with waterproof mortar, and the surface of the basement outer wall is ensured to be flush.
[0020] Preferably, in step three, the size of the reserved groove is mm expanded outward along the edge of the waterproof membrane, and the depth of the reserved groove is mm.
[0021] Preferably, in step 4, the specific steps of pressing the mold to match the waterproof coiled material and pouring the non-curing rubber asphalt waterproof coating are:
[0022] S1. First, holes are opened on the waterproof membrane to match the rigid casing and correspond to each other, and the waterproof membrane is cut to a suitable size, and then the waterproof membrane is put on the outside of the dense rigid waterproof casing;
[0023] S2. Pass the tension bolt through the hole of the rigid casing, and position the connecting plate by the tension bolt, so as to tighten and fix the entire pressing mold to ensure that the pressing frame is pressed on the surface of the waterproof membrane;
[0024] S3, lift up the upper part of the waterproof membrane and pour the non-curing rubber asphalt waterproof coating;
[0025] S4. After the non-curing rubber asphalt waterproof coating solidifies, remove the compacting mold, close the upper end of the waterproof membrane into the reserved groove, and fix the upper end with a pressure strip;
[0026] S5. Use waterproof mortar to seal the reserved groove to ensure that the surface of the basement outer wall is flush, leaving only the rigid casing protruding.
[0027] Preferably, in S3, when pouring the non-curing rubber asphalt waterproof coating, the rigid sleeve is gently tapped from the front to ensure that the non-curing rubber asphalt waterproof coating can fill the inner side of the waterproof membrane. In addition, the pouring direction is to slowly advance from one side to the other side.
[0028] Compared with the prior art, the present invention has the following beneficial effects:
[0029] The present invention provides a reserved groove on the front side of the outer wall of the basement, and a waterproof coiled material is sleeved on the outer side of the rigid sleeve. The waterproof coiled material is located in the inner cavity of the reserved groove and fits the bottom of the reserved groove. A non-curing rubber asphalt waterproof coating is poured between the waterproof coiled material and the bottom of the reserved groove. The waterproof coiled material is pressed by a pressing mold, thereby effectively improving the waterproof effect of the device and reducing the risk of leakage. BRIEF DESCRIPTION OF THE DRAWINGS
[0030] Figure 1 It is a three-dimensional schematic diagram of the overall structure of the present invention;
[0031] Figure 2 This is a schematic diagram of the connection between the water-stop steel plate and the rigid casing structure of the present invention;
[0032] Figure 3 It is a three-dimensional schematic diagram of the compacting mold structure of the present invention;
[0033] Figure 4 It is a side view schematic diagram of the overall structure of the present invention;
[0034] Figure 5 It is a schematic top view of the overall structure of the present invention.
[0035] In the figure: 1. Basement exterior wall; 2. Reserved groove; 3. Rigid casing; 4. Waterstop steel plate; 5. Waterproof membrane; 6. Pressing mold; 7. Pressing frame; 8. Connecting plate; 9. Support plate; 10. Tightening bolt; 11. Bolt gasket; 12. Positioning steel bar. DETAILED DESCRIPTION
[0036] In order to make the purpose and technical solution of the present invention clearly and completely described, and the advantages more clearly understood, the embodiments of the present invention are further described in detail with reference to the accompanying drawings. It should be understood that the specific embodiments described herein are part of the embodiments of the present invention, rather than all of the embodiments, and are only used to explain the embodiments of the present invention, and are not used to limit the embodiments of the present invention. All other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0037] In the description of the present invention, it should be noted that the terms "center", "middle", "upper", "lower", "left", "right", "inner", "outer", "top", "bottom", "side", "vertical", "horizontal" and the like indicate positions or positional relationships based on the positions or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific orientation, be constructed and operate in a specific orientation, and therefore cannot be understood as limiting the present invention. In addition, the terms "one", "first", "second", "third", "fourth", "fifth", "sixth" are used for descriptive purposes only, and cannot be understood as indicating or implying relative importance.
[0038] In the description of the present invention, it should be noted that, unless otherwise clearly specified and limited, the terms "installed", "connected", and "connected" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection, or it can be indirectly connected through an intermediate medium, or it can be the internal communication of two components. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.
[0039] For the purposes of simplicity and illustration, the principles of the embodiments are mainly described by reference to examples. In the following description, many specific details are set forth to provide a thorough understanding of the embodiments. However, it is apparent that, for those of ordinary skill in the art, these embodiments may not be limited to these specific details in practice. In some instances, well-known methods and structures are not described in detail to avoid unnecessarily obscuring these embodiments. Additionally, all embodiments may be used in combination with each other.
[0040] Please refer to Figures 1 to 5 , the present invention provides a technical solution:
[0041] Embodiment 1
[0042] A dense rigid waterproof sleeve for the external wall of an underground structure, comprising: an underground exterior wall 1, a waterstop steel plate 4, a waterproof coiled material 5, and a pressing die 6.
[0043] Specifically, a reserved groove 2 is formed on the surface of the underground exterior wall 1, and a plurality of rigid sleeves 3 arranged in a rectangular array are provided in the middle of the reserved groove 2. The rigid sleeves 3 penetrate through the underground exterior wall 1, and the rigid sleeves 3 are cut by a plasma tube sheet integrated machine;
[0044] Secondly, the waterstop steel plate 4 is embedded in the bottom of the reserved groove 2, and a plurality of rigid sleeves 3 are fixedly and penetratingly connected to the waterstop steel plate 4. The plasma tube sheet integrated machine is also used for cutting the waterstop steel plate 4. The welding connection work between the waterstop steel plate 4 and the rigid sleeves 3 is responsible by a welding robot. By using plasma cutting and robot welding, centralized batch processing of the rigid sleeves 3 can be achieved, reducing the working intensity of welding;
[0045] Furthermore, the waterproof coiled material 5 is sleeved outside a plurality of rigid sleeves 3, and the inner side wall of the waterproof coiled material 5 is attached to the surface of the waterstop steel plate 4. The setting of the waterproof coiled material 5 is used to improve the waterproof effect of the device, and a non-curing rubber asphalt waterproof coating is also filled between the waterproof coiled material 5 and the bottom of the reserved groove 2 to further improve the waterproof effect;
[0046] In addition, the pressing die 6 is located outside a plurality of rigid sleeves 3, and the pressing die 6 presses on the edge of the surface of the waterproof coiled material 5. The pressing die 6 is used to press the edge of the waterproof coiled material 5.
[0047] Embodiment 2
[0048] On the basis of Embodiment 1, in order to press the waterproof coiled material 5, the pressing die 6 of the present application includes a pressing frame 7, and the pressing frame 7 is set in a "C" shape with an upward opening. The pressing frame 7 is made by sequentially connecting and welding three angle steels end to end.
[0049] Two groups of connecting frames are arranged on the front of the pressing mold 6, and each group of connecting frames includes two connecting plates 8 parallel to each other. Both ends of the connecting plates 8 are fixedly connected with supporting plates 9 perpendicular thereto. One end of the supporting plate 9 is fixedly connected to the pressing frame 7. The connecting plate 8 can be buckled on the outer side of the end of the rigid sleeve 3 to prevent the pressing mold 6 from moving easily. The pressing frame 7 on the pressing mold 6 is pressed on both sides and the lower part of the waterproof membrane 5.
[0050] Embodiment 3
[0051] On the basis of the second embodiment, in order to position the clamping mold 6, the present application also has tensioning bolts 10 provided at both ends of the two sets of connecting frames, one end of the tensioning bolt 10 movably passes through the rigid sleeve 3 and extends to the back side of the basement outer wall 1.
[0052] Secondly, bolt washers 11 are provided at both ends of the tensioning bolt 10. The bolt washers 11 are buckled on the outer sides of the ends of the connecting frame and the rigid sleeve 3. The bolt washers 11 located at both ends of the tensioning bolt 10 are kept tightened by nuts. Therefore, by tightening the nuts at the ends of the tensioning bolt 10, the clamping mold 6 can be fixed to the front end of the rigid sleeve 3. The bolt washers 11 are provided to position the tensioning bolt 10 to prevent the tensioning bolt 10 from moving.
[0053] Embodiment 4
[0054] On the basis of Example 3, in order to avoid positional displacement of the waterstop steel plate 4 and the rigid sleeve 3 during concrete pouring, the present application also has a plurality of positioning steel bars 12 embedded in the interior of the basement outer wall 1, and the plurality of positioning steel bars 12 are respectively located at the two end edges and the lower end edge of the waterstop steel plate 4, and the plurality of positioning steel bars 12 located at the same edge of the waterstop steel plate 4 are distributed at equal intervals, and the positioning steel bars 12 are welded to the steel bars of the basement outer wall 1 before pouring the basement outer wall 1, and the positioning steel bars 12 are used to support and position the waterstop steel plate 4 to avoid positional displacement of the waterstop steel plate 4 and the rigid sleeve 3 during concrete pouring.
[0055] The present invention also provides a construction method for the underground structure outer wall intensive rigid waterproof casing according to the above, which specifically comprises the following steps:
[0056] Step 1: Processing of intensive rigid waterproof casing. Select casings of specific sizes according to the requirements of the drawings, and use plasma tube plate cutting machine and welding robot to centrally process intensive rigid waterproof casing;
[0057] Step 2: Pre-embedded positioning of the dense rigid waterproof casing. During the reinforcement binding process of the basement structure outer wall, first weld the positioning steel bars 12 at the bottom of the dense rigid waterproof casing to temporarily position and support the water stop steel plate 4 and the rigid casing 3. After the reinforcement binding is completed, weld the vertical positioning steel bars 12 on both sides of the dense rigid waterproof casing to fix the entire water stop steel plate 4 and the rigid casing 3;
[0058] Step 3: Processing and supporting the dense rigid waterproof casing template. When processing and supporting the casing template, fix the rubber strip on the inner side of the casing template to form a reserved groove 2 on the four sides of the entire dense rigid waterproof casing, which is used for overlapping and closing the waterproof membrane 5;
[0059] Step 4: Construction of the external wall waterproofing nodes of the intensive rigid waterproof casing. The basement external wall 1 is made of concrete pouring. After the basement external wall 1 solidifies and the formwork of the basement external wall 1 is removed, the pressing mold 6 is used to cooperate with the waterproof membrane 5 and pour the non-curing rubber asphalt waterproof coating. After it solidifies, the pressing mold 6 is removed, and the waterproof membrane 5 overlaps 100mm in the reserved groove 2. Then, a galvanized metal strip is used to close and fix the waterproof membrane 5 to the reserved groove 2. Finally, the reserved groove 2 is sealed with waterproof mortar, and the surface of the basement external wall 1 is ensured to be flush.
[0060] Embodiment 5
[0061] On the basis of Example 4, in order to determine the size of the reserved groove 2, in step 3 of the present application, the reserved groove 2 is expanded outward by 250 mm along the edge of the waterproof membrane 5, and the depth of the reserved groove 2 is 30 mm.
[0062] Embodiment 6
[0063] On the basis of Example 5, in order to explain in detail the pouring steps of the non-curing rubber asphalt waterproof coating, in step 4 of the present application, the specific steps of pressing the mold 6 to cooperate with the waterproof coiled material 5 and pouring the non-curing rubber asphalt waterproof coating are as follows:
[0064] S1, firstly, holes are opened on the waterproofing membrane 5 which are adapted to and correspond to the rigid casing 3, and the waterproofing membrane 5 is cut to a suitable size, and then the waterproofing membrane 5 is put on the outside of the dense rigid waterproof casing;
[0065] S2, passing the tension bolt 10 through the tube hole of the rigid sleeve 3, and positioning the connecting plate 8 by the tension bolt 10, thereby tightening and fixing the pressing mold 6 as a whole to ensure that the pressing frame 7 is pressed on the surface of the waterproof membrane 5;
[0066] S3, uncovering the upper part of the waterproof membrane 5 and pouring a non-curing rubber asphalt waterproof coating;
[0067] S4, after the non-curing rubber asphalt waterproof coating solidifies, remove the pressing mold 6, close the upper end of the waterproof membrane 5 into the reserved groove 2, and fix the upper end with a pressure strip;
[0068] S5. Use waterproof mortar to seal the reserved groove 2 to ensure that the surface of the basement outer wall 1 is flush, leaving only the rigid casing 3 protruding.
[0069] Embodiment 7
[0070] On the basis of Example 6, in order to ensure that the non-curing rubber asphalt waterproof coating can fill the inner side of the waterproof membrane 5, in S3 of the present application, when pouring the non-curing rubber asphalt waterproof coating, the rigid sleeve 3 is gently tapped from the front to ensure that the non-curing rubber asphalt waterproof coating can fill the inner side of the waterproof membrane 5. In addition, the pouring direction is to slowly advance from one side to the other side.
[0071] Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present invention, and that the scope of the present invention is defined by the appended claims and their equivalents.
Claims
1. A dense rigid waterproof casing for the outer wall of an underground structure, characterized in that: Including: The external basement wall (1), on the surface of which a reserved groove (2) is provided. In the middle of the reserved groove (2), a plurality of rigid sleeves (3) are arranged in a rectangular array, and the rigid sleeves (3) penetrate through the external basement wall (1). A water stop steel plate (4), which is embedded at the bottom of the reserved groove (2), and all the plurality of rigid sleeves (3) are fixedly and penetratingly connected to the water stop steel plate (4). A waterproof coiled material (5), which is sleeved outside the plurality of rigid sleeves (3), and the inner side wall of the waterproof coiled material (5) is attached to the surface of the water stop steel plate (4); and A pressing die (6), which is located outside the plurality of rigid sleeves (3), and the pressing die (6) presses on the edge of the surface of the waterproof coiled material (5). The pressing die (6) includes a pressing frame (7), which is arranged in a "C" shape with an upward opening, and the pressing frame (7) is made by sequentially connecting and welding three angle steels end to end. On the front surface of the pressing die (6), two groups of connecting frames are provided. Each group of connecting frames includes two parallel connecting plates (8). At both ends of the connecting plate (8), perpendicular support plates (9) are fixedly connected, and one end of the support plate (9) is fixedly connected to the pressing frame (7). Tension bolts (10) are arranged at both ends of the two groups of connecting frames. One end of the tension bolt (10) movably penetrates through the rigid sleeve (3) and extends to the back surface of the external basement wall (1). Bolt washers (11) are arranged at both ends of the tension bolt (10). The bolt washers (11) are buckled outside the ends of the connecting frame and the rigid sleeve (3), and the bolt washers (11) at both ends of the tension bolt (10) are kept in tension by nuts. A plurality of positioning steel bars (12) are embedded inside the external basement wall (1). The plurality of positioning steel bars (12) are respectively located at the two end edges and the lower end edge of the water stop steel plate (4). The plurality of positioning steel bars (12) at the same edge of the water stop steel plate (4) are equally spaced.
2. A construction method for an underground structure outer wall intensive rigid waterproof casing according to claim 1, characterized in that: Specifically, it includes the following steps: Step 1: Processing of the dense rigid waterproof sleeve. Select sleeves with specific dimensions according to the drawing requirements, and use a plasma tube-sheet cutting integrated machine and a welding robot to centrally process the dense rigid waterproof sleeve. Step 2: Embedded positioning of the dense rigid waterproof sleeve. During the steel bar binding process of the external wall of the basement structure, first weld positioning steel bars (12) at the bottom of the dense rigid waterproof sleeve for temporary positioning and support of the water stop steel plate (4) and the rigid sleeve (3). After the steel bar binding is completed, weld vertical positioning steel bars (12) on both sides of the dense rigid waterproof sleeve to fix the entire water stop steel plate (4) and the rigid sleeve (3). Step 3: Processing and erection of the template for the dense rigid waterproof sleeve. When processing and erecting the sleeve template, fix the rubber strip inside the sleeve template to form a reserved groove (2) on the four sides of the entire dense rigid waterproof sleeve, and use it for the lapping and closing of the waterproof coiled material (5). Step 4: Construction of the external wall waterproofing node of the intensive rigid waterproof casing. The basement external wall (1) is made of poured concrete. After the basement external wall (1) solidifies and the formwork of the basement external wall (1) is removed, a pressing mold (6) is used in combination with the waterproofing membrane (5) and poured with a non-curing rubber asphalt waterproofing coating. After solidification, the pressing mold (6) is removed. The waterproofing membrane (5) is overlapped by 100 mm in the reserved groove (2). Then, a galvanized metal strip is used to close and fix the waterproofing membrane (5) in the reserved groove (2). Finally, the reserved groove (2) is sealed with waterproof mortar, and the surface of the basement external wall (1) is ensured to be flush.
3. The construction method of the underground structure outer wall intensive rigid waterproof casing according to claim 2 is characterized by: In the step 3, the size of the reserved groove (2) is 250 mm extended outward along the edge of the waterproof coiled material (5), and the depth of the reserved groove (2) is 30 mm.
4. The construction method of the underground structure outer wall intensive rigid waterproof casing according to claim 3 is characterized by: In the step 4, the specific steps of pressing the mold (6) to match the waterproof coiled material (5) and pouring the non-curing rubber asphalt waterproof coating are: S1, firstly, holes are opened on the waterproofing coiled material (5) that are adapted to and correspond to the rigid casing (3), and the waterproofing coiled material (5) is cut to a suitable size, and then the waterproofing coiled material (5) is put on the outside of the dense rigid waterproof casing; S2, passing the tensioning bolt (10) through the tube hole of the rigid sleeve (3), and positioning the connecting plate (8) by means of the tensioning bolt (10), thereby tightening and fixing the entire pressing mold (6) to ensure that the pressing frame (7) is pressed against the surface of the waterproof membrane (5); S3, uncovering the upper part of the waterproofing membrane (5) and pouring a non-curing rubber asphalt waterproof coating; S4, after the non-curing rubber asphalt waterproof coating solidifies, the pressing mold (6) is removed, the upper end of the waterproofing membrane (5) is closed into the reserved groove (2), and the upper end is fixed with a pressure strip; S5. Use waterproof mortar to seal the reserved groove (2) to ensure that the surface of the basement outer wall (1) is flush, leaving only the rigid casing (3) protruding.
5. The construction method of the underground structure outer wall intensive rigid waterproof casing according to claim 4 is characterized by: In S3, when pouring the non-curing rubber asphalt waterproof coating, the rigid sleeve (3) is gently tapped from the front to ensure that the non-curing rubber asphalt waterproof coating can fill the inner side of the waterproof membrane (5). In addition, the pouring direction is to slowly advance from one side to the other side.
Citation Information
Patent Citations
Basement concrete outer wall flexible waterproof wall bushing structure and construction method
CN105909879A
Construction structure and construction method for rigid flange wall bushing
CN113483162A