A construction method for high-position beam drop of a large-span bottom-supported tied-bar steel arch bridge

Through the combination of hydraulic synchronous lifting and lattice gantry, the high-level falling beam construction of large-span lower bearing steel arch bridge is realized, solving the problems of insufficient accuracy, automation and safety in traditional methods, and improving the flexibility of construction Sex and reliability.

CN115418969BActive Publication Date: 2024-12-06MCC (SHANGHAI) STEEL STRUCTURE TECHNOLOGY CORP LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202211230129.2
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2022-09-30
Publication Date
2024-12-06
Estimated Expiration
2042-09-30

AI Technical Summary

Technical Problem

The existing construction methods for falling beams of large-span steel structures have problems such as difficult to control cutting accuracy, low degree of sand box unloading automation, large jack equipment and high cost. Especially when the structural base plate is under a large force and repeated adjustment of the height of the pad beams, there is safety and Inadequate economicality.

Method used

Using hydraulic lifting and integrated beam construction method, the lattice gantry and hydraulic synchronous lifting technology is combined with guide frame and wind rope to achieve three-way adjustment and synchronous beam falling, avoiding multi-stage unloading in traditional methods. and repeated adjustments have improved the level of equipment integration and automation.

Benefits of technology

The beam-falling process is achieved with high accuracy, good synchronization, safe and reliable, avoiding vibration and pendulum and repeated adjustments in traditional methods, simplifying the construction process, improving the operability and safety of construction, and solving the small space and equipment Problem of limitations.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN115418969B_ABST
    Figure CN115418969B_ABST
Patent Text Reader

Abstract

The present invention discloses a construction method for high-position beam drop of a large-span bottom-supported tied-rod steel arch bridge; the method comprises the steps of preparing a gantry: checking the axis, installing a sheet truss; installing diagonal braces and transverse sweeping rods; installing a support beam system, the gantry forms a complete frame system, and removing the wind ropes; installing and lifting the cross beams; preparing lower anchor points; preparing guide frames; hydraulic lifters; wind ropes; temporary piers; beam drop construction: pushing the steel arch bridge to the designed position, installing temporary piers, removing the pushing tire frame and temporary foundation, lifting the lower anchor points, installing the lifting gantry, hydraulic lifting, and dropping the beams as a whole; after the removal is completed, the beams are dropped in place, and the beam drop construction operation of the steel arch bridge is completed; the technology can drop the steel arch ribs to the designed elevation at one time; simplifies the process of repeatedly adjusting the pad beam elevation during beam drop construction; and makes the method more operable and safe.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the field of building construction, in particular to a construction method for high-position beam drop of a large-span bottom-supported tied-rod steel arch bridge. Background Art

[0002] At present, the traditional technologies for beam dropping and unloading of large-span steel structures mainly include direct cutting method, sand box unloading method and hydraulic jack step-by-step unloading method. These traditional technologies have the following obvious shortcomings:

[0003] 1. Direct cutting method: cutting accuracy is difficult to control, and safety and stability are difficult to guarantee;

[0004] 2. Sand box unloading: The traditional construction technology of sand box in my country has low comprehensive cost, mature technology and simple operation; but there must be enough height difference under the structure to place the sand box, the degree of automation is low, the multi-point sand box unloading has poor synchronization and the accuracy is difficult to control;

[0005] 3. The advantage of the step-by-step unloading method with jacks is that the precision is easy to control, but the equipment requirements are high and multiple sets of large-tonnage jacks and pads are needed. The equipment is large in size and there is no space for placement under the structure. During the unloading process, the bottom plate of the structure is locally subjected to large forces, and local repeated forces can easily cause damage to the structure. Multi-stage unloading has the problem of difficult-to-achieve reverse extraction of steel plates and pad beams, with high overall costs, poor comprehensive economic efficiency, and great limitations in use. Summary of the invention

[0006] The purpose of the present invention is to overcome the above-mentioned defects and to provide a hydraulic lifting and integrated beam dropping construction method.

[0007] In order to achieve the above object, the present invention is achieved as follows:

[0008] A construction method for high-position beam drop of a large-span bottom-supported tied-rod steel arch bridge, comprising:

[0009] 1. Preparation process:

[0010] Step 1, prepare the gantry: the gantry is a lattice gantry; including sheet truss members (1-3, 1-4), diagonal braces (1-5), lifting beams (1-1), support beam systems (1-2), and transverse sweeping rods (1-6); the gantry must be able to bear the entire deadweight of the steel arch bridge and balance the lateral force; the gantry is manufactured in blocks according to each component unit, and then sent to the construction site for installation. The root of the gantry is fixed by embedding the embedded parts on the pier, that is, the combination structure of chemical bolts-embedded plates; the structure is installed after the chemical bolts are implanted and tested to be qualified; specifically including

[0011] Step 1.1, axis verification, chemical bolt-embedded plate combination structure installation;

[0012] Step 1.2: Installation of the sheet trusses (1-3, 1-4), connected to the embedded plate by welding;

[0013] Step 1.3, install the diagonal brace (1-5) and the horizontal sweeping rod (1-6);

[0014] Step 1.4: Install the support beam system (1-2), the gantry forms a complete frame system, and remove the guy ropes;

[0015] Step 1.5, installation of the lifting beam (1-1). The lifting beam (1-1) is installed with the center of the lower anchor point of the end beam as the reference datum line to ensure that the reserved hole of the equipment coincides with the projection of the center of the circular hole of the lower anchor point;

[0016] Step 2, prepare the lower anchor point: the lower anchor point includes the lower sling (2-1) and the internal reinforcement combination system (2-2); the selection of the lifting point should fully consider the characteristics of the force system of the lifting structure, and the principle of not changing the structural force system is adopted. During the beam drop construction process, the stress ratio and deformation of the structure are controlled within a reasonable range; the vertical plate of the lower sling (2-1) is inserted into the end cross beam box through a rectangular notch, and the lower sling (2-1) and the internal reinforcement combination system (2-2) are connected to the end cross beam structure by groove penetration welding;

[0017] Step 3, prepare the guide frame: The guide frame includes a "T-shaped" frame assembled and welded by steel pipes. It is used to ensure smooth transmission of the reserved steel strands during the lifting or lowering process of the hydraulic lifter when the height of the beam is high. Each hydraulic lifter must be equipped with a set of guide frames, and the excess steel strands can be freely guided backward and downward along the lifting platform; the guide frame is installed on the side of the hydraulic lifter and is higher than the lifter. The guide frame is guided in the direction of facilitating the installation of oil pipes and sensors and not affecting the free fall of steel strands. The guide frame should be 1.5~2m higher than the sky anchor;

[0018] Step 4, hydraulic lifter: According to the lifting reaction force of each lifting point, determine and select the hydraulic lifter model that meets the requirements, and use high-strength low-relaxation prestressed steel strands to connect the sky anchor and ground anchor of the hydraulic lifter together;

[0019] Step 5, wind rope: Use steel wire rope and winch to connect the steel arch bridge to the solid structure or embedded parts on the ground; the horizontal position of the steel arch bridge can be adjusted by the winch under the condition of beam drop. When the steel arch bridge is in the condition of hovering in the air, tightening the wind rope can offset the wind load and prevent the steel arch bridge from swaying;

[0020] Step 6, temporary conversion pier: used to transfer the deadweight load of the main structure on the upper part of the walking jacking equipment to the top of the temporary conversion pier, and then dismantle the walking jacking equipment and the jacking tire frame; the temporary conversion pier includes the tire frame and the cushion beam, the cushion beam is divided into upper and lower layers, the cushion beam specification is a raft box beam, the lower cushion beam is welded to the tire frame platform, the upper and lower cushion beams are welded and connected, and two groups of "eight-shaped" diagonal braces are welded between the upper cushion beam and the tire frame to ensure the stability of the cushion beam; since the lower part of the temporary conversion pier is heavy, before the steel arch bridge is pushed into place, the tire frame is placed above the pier in advance by using a car crane through the gap between the cross beams in the steel arch bridge. When the steel arch bridge is pushed into place, the cushion beam and diagonal brace of the temporary conversion pier are installed. After the installation is completed, the load of the steel arch bridge is transferred from the jacking equipment to the temporary conversion pier, and the jacking tire frame and the walking jacking equipment are dismantled; the layout principles of the temporary conversion pier are:

[0021] (1) Temporary transfer piers should be arranged symmetrically;

[0022] (2) The centerline of the temporary transfer pier should coincide with the centerline of the end beam, and the support point should be at the location where there is a transverse partition inside the end beam;

[0023] (3) The maximum setting is close to the abutment;

[0024] 2. Beam dropping construction:

[0025] Step 2.1, design idea: push the steel arch bridge to the designed position, install the temporary conversion pier, remove the push frame and temporary foundation, lift the anchor point, install the gantry, hydraulically lift, and drop the beam as a whole; hydraulic lifting and overall beam dropping should be carried out after the gantry and anchor point are installed and in windless weather, and then the steel bridge will be officially dropped; hydraulic lifting and overall beam dropping are divided into the following steps:

[0026] Step 2.2: Use a hydraulic lifter to lift the steel arch bridge to the expected height, separate the steel bridge from the supporting frame below it, stop lifting, and pull the wind rope. The main function of the wind rope is to prevent the steel arch bridge from being displaced by lateral wind load when it is suspended in the air;

[0027] Step 2.3, dismantle the temporary transfer pier under the steel arch bridge;

[0028] Due to the small space for demolition operations, the principle of demolition of temporary transfer piers is to cut and dismantle them in blocks to reduce the weight and cross-sectional size of a single demolished unit, including: first dismantling the diagonal braces, then dismantling the upper and lower cushion beams respectively, and finally dismantling the tire frame; the tire frame is dismantled by cutting and dismantling in blocks again, cutting the legs and the tire frame platform apart, and using a truck crane and a fall chain to collaboratively dismantle them one by one.

[0029] Step 2.4: After the demolition is completed, the beams are dropped into place, completing the beam-dropping construction work of the steel arch bridge.

[0030] This beam dropping method has the following advantages:

[0031] 1. The beam dropping process has the flexibility of three-way adjustment: lifting, dropping and correcting. The lifting equipment is located above the structure and is not restricted by the height difference between the bridge and the pier, thus solving the limitation of the narrow space at the bottom of the bridge. The equipment is integrated, highly automated and has good synchronization.

[0032] 2. The lattice gantry structure has high strength, high stability, safety and reliability;

[0033] 3. The hydraulic synchronous lifting and beam dropping technology has high precision and good synchronization. There will be no vibration during the beam dropping process, and there is no need for a large space between the gantry and the main body. During the lifting and lowering process of the steel arch bridge, the height can be fine-tuned by adjusting the posture in the air and controlling the elevation.

[0034] 4. The technology of hydraulic lifting and overall beam drop is realized, which solves the limitation of the traditional beam drop process that cannot perform three-way deviation correction. The technology of synchronous beam drop, deformation coordination and graded loading is adopted to make the beam drop process safe and reliable. The traditional technology of multi-stage unloading and repeated back-up adjustment of the cushion beam height is avoided. This technology can drop the steel arch rib to the designed elevation at one time, and simplifies the process of repeated adjustment of the cushion beam elevation during beam drop construction. It has more operability and safety. BRIEF DESCRIPTION OF THE DRAWINGS

[0035] Figure 1 This is a schematic diagram of the beam dropping construction.

[0036] Figure 2 Schematic diagram of lifting gantry.

[0037] Figure 3 Schematic diagram of the lifting gantry split unit.

[0038] Figure 4 This is a schematic diagram of the elevation of the beam drop construction.

[0039] Figure 5 This is a schematic diagram of the embedded parts installation.

[0040] Figure 6 Schematic diagram of the combination of the lower hanger and the internal stiffening system.

[0041] Figure 7 Schematic diagram of the guide frame and lifter.

[0042] Figure 8 Schematic diagram of the layout of temporary transfer piers above the bridge piers.

[0043] Fig. 9 This is a schematic diagram of the temporary transfer pier structure layout.

[0044] Fig.10 This is a schematic diagram of the guy rope setting. DETAILED DESCRIPTION

[0045] The present invention is further described below by means of specific examples.

[0046] like Figures 1 to 10 As shown, a construction method for high-position beam drop of a large-span bottom-supported tied-bar steel arch bridge comprises:

[0047] 1. Preparation process:

[0048] Step 1, prepare the gantry 1: the gantry is a lattice gantry; including sheet truss members (1-3, 1-4), diagonal braces (1-5), lifting beams (1-1), support beam systems (1-2), and transverse sweeping rods (1-6); the gantry must be able to bear the entire deadweight of the steel arch bridge and balance the lateral force; the gantry is manufactured in blocks according to each component unit, and then sent to the construction site for installation. The root of the gantry is fixed by using embedded parts implanted on the pier, that is, a combination structure of chemical bolts-embedded plates; the structure is installed after the chemical bolts are implanted and tested to be qualified; specifically including

[0049] Step 1.1, axis verification, chemical bolt-embedded plate combination structure installation;

[0050] Step 1.2: Installation of the sheet trusses (1-3, 1-4), connected to the embedded plate by welding;

[0051] Step 1.3, install the diagonal brace (1-5) and the horizontal sweeping rod (1-6);

[0052] Step 1.4: Install the support beam system (1-2), the gantry forms a complete frame system, and remove the guy ropes;

[0053] Step 1.5, installation of the lifting beam (1-1). The lifting beam (1-1) is installed with the center of the lower anchor point of the end beam as the reference datum line to ensure that the reserved hole of the equipment coincides with the projection of the center of the circular hole of the lower anchor point;

[0054] Step 2, prepare the lower anchor point: the lower anchor point includes the lower sling (2-1) and the internal reinforcement combination system (2-2); the selection of the lifting point should fully consider the characteristics of the force system of the lifting structure, and the principle of not changing the structural force system is adopted. During the beam drop construction process, the stress ratio and deformation of the structure are controlled within a reasonable range; the vertical plate of the lower sling (2-1) is inserted into the end cross beam box through a rectangular notch, and the lower sling (2-1) and the internal reinforcement combination system (2-2) are connected to the end cross beam structure by groove penetration welding;

[0055] Step 3, prepare the guide frame 2: The guide frame includes a "T-shaped" frame assembled and welded by steel pipes 4. It is used to ensure smooth transmission of the reserved steel strands during the lifting or lowering process of the hydraulic lifter when the height of the beam is high. Each hydraulic lifter must be equipped with a set of guide frames, and the excess steel strands can be freely guided backward and downward along the lifting platform; the guide frame is installed on the side of the hydraulic lifter and is higher than the lifter. The guide frame is guided in a direction that is convenient for installing oil pipes and sensors and does not affect the free fall of the steel strands. The guide frame should be 1.5~2m higher than the sky anchor;

[0056] Step 4, hydraulic lifter 3: According to the lifting reaction force of each lifting point, determine and select the hydraulic lifter model that meets the requirements, and use high-strength low-relaxation prestressed steel strands to connect the sky anchor and ground anchor of the hydraulic lifter together;

[0057] Step 5, wind rope 5: Use steel wire rope and winch to connect the steel arch bridge to the solid structure or embedded parts on the ground; the horizontal position of the steel arch bridge can be adjusted by the winch under the beam drop condition. When the steel arch bridge is in the condition of hovering in the air, tightening the wind rope can offset the wind load and prevent the steel arch bridge from swaying;

[0058] Step 6, temporary conversion pier: used to transfer the deadweight load of the main structure on the upper part of the walking jacking equipment to the top of the temporary conversion pier, and then dismantle the walking jacking equipment and the jacking tire frame; the temporary conversion pier includes the tire frame and the cushion beam, the cushion beam is divided into upper and lower layers, the cushion beam specification is a raft box beam, the lower cushion beam is welded to the tire frame platform, the upper and lower cushion beams are welded and connected, and two groups of "eight-shaped" diagonal braces are welded between the upper cushion beam and the tire frame to ensure the stability of the cushion beam; since the lower part of the temporary conversion pier is heavy, before the steel arch bridge is pushed into place, the tire frame is placed above the pier in advance by using a car crane through the gap between the cross beams in the steel arch bridge. When the steel arch bridge is pushed into place, the cushion beam and diagonal brace of the temporary conversion pier are installed. After the installation is completed, the load of the steel arch bridge is transferred from the jacking equipment to the temporary conversion pier, and the jacking tire frame and the walking jacking equipment are dismantled; the layout principles of the temporary conversion pier are:

[0059] (1) Temporary transfer piers should be arranged symmetrically;

[0060] (2) The centerline of the temporary transfer pier should coincide with the centerline of the end beam, and the support point should be at the location where there is a transverse partition inside the end beam;

[0061] (3) The maximum setting is close to the abutment;

[0062] 2. Beam dropping construction:

[0063] Step 2.1, design idea: push the steel arch bridge to the designed position, install the temporary conversion pier, remove the push frame and temporary foundation, lift the anchor point, install the gantry, hydraulically lift, and drop the beam as a whole; hydraulic lifting and overall beam dropping should be carried out after the gantry and anchor point are installed and in windless weather, and then the steel bridge will be officially dropped; hydraulic lifting and overall beam dropping are divided into the following steps:

[0064] Step 2.2: Use a hydraulic lifter to lift the steel arch bridge to the expected height, separate the steel bridge from the supporting frame below it, stop lifting, and pull the wind rope. The main function of the wind rope is to prevent the steel arch bridge from being displaced by lateral wind load when it is suspended in the air;

[0065] Step 2.3, dismantle the temporary transfer pier under the steel arch bridge;

[0066] Due to the small space for demolition operations, the principle of demolition of temporary transfer piers is to cut and dismantle them in blocks to reduce the weight and cross-sectional size of a single demolished unit, including: first dismantling the diagonal braces, then dismantling the upper and lower cushion beams respectively, and finally dismantling the tire frame; the tire frame is dismantled by cutting and dismantling in blocks again, cutting the legs and the tire frame platform apart, and using a truck crane and a fall chain to collaboratively dismantle them one by one.

[0067] Step 2.4: After the demolition is completed, the beams are dropped into place, completing the beam-dropping construction work of the steel arch bridge.

[0068] This beam dropping method has the following advantages:

[0069] 1. The beam dropping process has the flexibility of three-way adjustment: lifting, dropping and correcting. The lifting equipment is located above the structure and is not restricted by the height difference between the bridge and the pier, thus solving the limitation of the narrow space at the bottom of the bridge. The equipment is integrated, highly automated and has good synchronization.

[0070] 2. The lattice gantry structure has high strength, high stability, safety and reliability;

[0071] 3. The hydraulic synchronous lifting and beam dropping technology has high precision and good synchronization. There will be no vibration during the beam dropping process, and there is no need for a large space between the gantry and the main body. During the lifting and lowering process of the steel arch bridge, the height can be fine-tuned by adjusting the posture in the air and controlling the elevation.

[0072] 4. The technology of hydraulic lifting and overall beam drop is realized, which solves the limitation of the traditional beam drop process that cannot perform three-way deviation correction. The technology of synchronous beam drop, deformation coordination and graded loading is adopted to make the beam drop process safe and reliable. The traditional technology of multi-stage unloading and repeated back-up adjustment of the cushion beam height is avoided. This technology can drop the steel arch rib to the designed elevation at one time, and simplifies the process of repeated adjustment of the cushion beam elevation during beam drop construction. It has more operability and safety.

Claims

1. A construction method for high-position beam drop of a large-span bottom-supported tied-bar steel arch bridge, characterized in that: include 1. Preparation process: Step 1, prepare the gantry: the gantry is a lattice gantry; including a first sheet truss member (1-3), a second sheet truss member (1-4), a diagonal brace (1-5), a lifting beam (1-1), a support beam system (1-2), and a transverse sweeping rod (1-6); the gantry must be able to bear the entire deadweight of the steel arch bridge and balance the lateral force; the gantry is manufactured in blocks according to each component unit, and then sent to the construction site for installation, and the root of the gantry is fixed by using embedded parts implanted on the pier, that is, a combination structure of chemical bolts-embedded plates; the structure is installed after the chemical bolts are implanted and tested to be qualified; specifically including Step 1.1, axis verification, chemical bolt-embedded plate combination structure installation; Step 1.2, installing the first sheet truss member (1-3) and the second sheet truss member (1-4), and connecting them with the embedded plate by welding; Step 1.3, install the diagonal brace (1-5) and the horizontal sweeping rod (1-6); Step 1.4: Install the support beam system (1-2), the gantry forms a complete frame system, and remove the first guy rope; Step 1.5, installation of the lifting beam (1-1). The lifting beam (1-1) is installed with the center of the lower anchor point of the end beam as the reference datum line, ensuring that the reserved hole of the hydraulic lifter coincides with the projection of the center of the circular hole of the lower anchor point; Step 2, prepare the lower anchor point: the lower anchor point includes the lower sling (2-1) and the internal reinforcement combination system (2-2); the selection of the lifting point should fully consider the characteristics of the force system of the lifting structure, and the principle of not changing the structural force system is adopted. During the beam drop construction process, the stress ratio and deformation of the structure are controlled within a reasonable range; the vertical plate of the lower sling (2-1) is inserted into the end cross beam box through a rectangular notch, and the lower sling (2-1) and the internal reinforcement combination system (2-2) are connected to the end cross beam structure by groove penetration welding; Step 3, prepare the guide frame: The guide frame includes a "T-shaped" frame assembled and welded by steel pipes. It is used to ensure smooth transmission of the reserved steel strands during the lifting or lowering process of the hydraulic lifter when the height of the beam is high. Each hydraulic lifter must be equipped with a set of guide frames, and the excess steel strands can be freely guided backward and downward along the lifting platform; the guide frame is installed on the side of the hydraulic lifter and is higher than the lifter. The guide frame is guided in the direction of facilitating the installation of oil pipes and sensors and not affecting the free fall of steel strands. The guide frame should be 1.5~2m higher than the sky anchor; Step 4, hydraulic lifter: According to the lifting reaction force of each lifting point, determine and select the hydraulic lifter model that meets the requirements, and use high-strength low-relaxation prestressed steel strands to connect the sky anchor and ground anchor of the hydraulic lifter together; Step 5, second guy rope: Use steel wire rope and winch to connect the steel arch bridge to the solid structure or embedded parts on the ground; the horizontal position of the steel arch bridge can be adjusted by the winch under the beam drop condition. When the steel arch bridge is in the condition of hovering in the air, tightening the second guy rope can offset the wind load and prevent the steel arch bridge from swaying; Step 6, temporary conversion pier: used to transfer the deadweight load of the main structure on the upper part of the walking jacking equipment to the top of the temporary conversion pier, and then dismantle the walking jacking equipment and the jacking tire frame; the temporary conversion pier includes the tire frame and the cushion beam, the cushion beam is divided into upper and lower layers, the cushion beam specification is a raft box beam, the lower cushion beam is welded to the tire frame platform, the upper and lower cushion beams are welded and connected, and two groups of "eight-shaped" diagonal braces are welded between the upper cushion beam and the tire frame to ensure the stability of the cushion beam; since the lower part of the temporary conversion pier is heavy, before the steel arch bridge is pushed into place, the tire frame is placed above the pier in advance by using a car crane through the gap between the cross beams in the steel arch bridge. When the steel arch bridge is pushed into place, the cushion beam and diagonal brace of the temporary conversion pier are installed. After the installation is completed, the load of the steel arch bridge is transferred from the jacking equipment to the temporary conversion pier, and the jacking tire frame and the walking jacking equipment are dismantled; The layout principles of temporary transfer piers are as follows: (1) Temporary transfer piers should be arranged symmetrically; (2) The centerline of the temporary transfer pier should coincide with the centerline of the end beam, and the support point should be at the location where there is a transverse partition inside the end beam; (3) The maximum setting is close to the abutment; 2. Beam drop construction: Step 2.1, design idea: push the steel arch bridge to the designed position, install the temporary conversion pier, remove the push frame and temporary foundation, lift the anchor point, install the gantry, hydraulically lift, and drop the beam as a whole; hydraulic lifting and overall beam dropping should be carried out after the gantry and anchor point are installed and in windless weather, and then the steel bridge will be officially dropped; hydraulic lifting and overall beam dropping are divided into the following steps: Step 2.2: Use a hydraulic lifter to lift the steel arch bridge to the expected height, separate the steel bridge from the cushion beam above the supporting frame below it, stop lifting, and pull the second guy rope. The main function of the second guy rope is to prevent the steel arch bridge from being displaced by lateral wind load when it is suspended in the air; Step 2.3, dismantle the temporary transfer pier under the steel arch bridge; Due to the small demolition space, the principle of demolition of temporary transfer piers is to cut and demolish them in blocks to reduce the weight and cross-sectional size of a single demolition unit, including: first remove the diagonal brace, then remove the upper and lower cushion beams respectively, and finally remove the tire frame; the tire frame is removed by cutting and demolition in blocks again, cutting the legs and the tire frame platform apart, and using the truck crane and the fall chain to cooperate to remove them one by one; Step 2.4: After the demolition is completed, the beams are dropped into place, completing the beam-dropping construction work of the steel arch bridge.