Reactor hydraulic simulation test quick connector and pressure pipe pressure device and test method
By designing a pressing device to simulate the underwater environment of the quick joint and the pressure-induced tube, the problem of difficulty in verifying its sealing performance in the prior art is solved, and effective verification of its underwater applicability is achieved.
Patent Information
- Application Number
- CN202211293618.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2022-10-21
- Publication Date
- 2025-03-14
- Estimated Expiration
- 2042-10-21
AI Technical Summary
The prior art is difficult to verify the sealing performance of the quick joint and the pressure lead pipe in underwater pressure environments, and cannot ensure its applicability in the overall hydraulic simulation test of the reactor and other hydraulic characteristic tests.
Design a pressure suppression device, including a pressure-bearing container, a quick joint, a pressure-grabbing pipe, a pressurized pump and a valve. By simulating the internal and external pressure of the pressure-grabbing pipe, the sealing performance of the quick joint and a pressure-grabbing pipe is tested.
The pressure device can truly simulate the underwater use environment of the quick joint and the pressure lead pipe, batch verification of its sealing performance, and ensure its applicability in underwater pressure environment.
Smart Images

Figure CN115560931B_ABST
Abstract
Description
Technical Field
[0001] The patent of this invention relates to the technical field of reactor hydraulic simulation test, and specifically discloses a pressure device and a testing method based on the device to test the applicability of quick connectors and pressure-leading pipes in overall reactor hydraulic simulation tests and other hydraulic characteristic tests. Background Art
[0002] In the reactor overall hydraulic simulation test and other hydraulic characteristics test research, it is often necessary to measure the pressure inside the test model. The test model is filled with water medium and has a certain pressure. The pressure measurement of the underwater pressurized environment adopts the pressure extraction method of (threaded) quick connector plus pressure (soft) pipe (reference Figure 1 ), this pressure-inducing method is relatively simple and easy to disassemble and assemble. The connection method between the pressure-inducing pipe and the quick connector is quick plug-in and pull-out, and the O-ring is sealed. However, since the pressure-inducing method of the quick connector and the pressure-inducing pipe is often used in air environments, a set of pressure-inducing devices needs to be designed to verify the applicability of the quick connector and the pressure-inducing pipe in underwater pressurized environments. Summary of the invention
[0003] Based on this, the patent of this invention intends to design a pressure device, which can simulate the internal and external pressures of the pressure pipe respectively, simulate the actual use environment of the quick connector and the pressure pipe, determine whether there are sealing problems with the quick connector and the pressure pipe, and provide technical support for pressure measurement in underwater pressurized environments.
[0004] To achieve the above object, the present invention is implemented by the following technical solutions:
[0005] On the one hand, a reactor hydraulic simulation test quick connector and a pressure pipe pressurization device are provided, including a pressure vessel R1 / R2, a quick connector JT1 / JT2 / JT3 / JT4 / JT5 / JT6, a pressure pipe TB1 / TB2 / TB3, a pressure pump PP, a valve QV1 / QV2 / QV3 / QV4, and a pressure gauge PG1 / PG2;
[0006] The pressure vessels R1 and R2 have a plurality of quick connector interfaces. The quick connectors JT1 and JT2 are connected to the inside of the pressure vessel R1, and the quick connectors JT1 and JT2 are connected by a pressure pipe TB1; the quick connectors JT3 and JT4 are connected to the outside of the pressure vessel R1, and the quick connectors JT3 and JT1 share a quick connector interface, and the quick connectors JT4 and JT2 share a quick connector interface; the quick connectors JT5 and JT6 are connected to the outside of the pressure vessel R2, and the quick connectors JT4 and JT5 are connected by a pressure pipe TB2, and the quick connectors JT3 and JT6 are connected by a pressure pipe TB3;
[0007] The pressure containers R1 and R2 have a water injection interface, a pressure relief interface and a pressure gauge interface. The pressure pump PP is connected to the water injection interfaces of the pressure containers R1 and R2 respectively. The valve QV2 is arranged at the water injection interface of the pressure container R1, and the valve QV3 is arranged at the water injection interface of the pressure container R2; the valve QV1 is arranged at the pressure relief interface of the pressure container R1, and the valve QV4 is arranged at the pressure relief interface of the pressure container R2; the pressure gauges PG1 and PG2 are connected to the pressure gauge interfaces of the pressure containers R1 and R2 respectively.
[0008] Based on the above scheme, the water pressure P1 in the pressure container R1 is used to simulate the external pressure of the quick connector and the pressure pipe, and the water pressure P2 in the pressure container R2 is used to simulate the internal pressure of the quick connector and the pressure pipe; the pressure-testing device can simulate the installation environment of the quick connector and the pressure pipe, establish the internal and external pressures of the pressure pipe respectively, and test the sealing reliability of the quick connector and the pressure pipe under underwater pressure environment.
[0009] As a preferred solution, a pressure relief interface is provided on the connecting pipeline between the pressure pump PP and the pressure containers R1 and R2, and a valve QV5 is arranged on the pressure relief interface.
[0010] As a preferred solution, a pressure gauge interface is provided on the connecting pipe between the pressure pump PP and the pressure containers R1 and R2, and the pressure gauge PG3 is arranged on the pressure gauge interface.
[0011] As a preferred solution, the pressure container R1 and / or R2 comprises a hollow cylinder and a flange, and the flange closes the upper and lower openings of the hollow cylinder to form a sealing structure.
[0012] As a preferred solution, the quick connector interface, water injection interface, pressure relief interface, and pressure gauge interface are all arranged on the flange.
[0013] As a preferred solution, valves QV1 / QV2 / QV3 / QV4 / QV5 use ball valves.
[0014] On the other hand, a method for testing a reactor hydraulic simulation test quick connector and a pressure pipe is provided, using the reactor hydraulic simulation test quick connector and the pressure pipe pressure test device, and implementing the following steps:
[0015] a. Close valve QV2, open valves QV3 and QV4, and use the pressure pump PP to inject water into the pressure container R2. When water comes out from the rear end of valve QV4, it means that the air in the pressure container R2 has been exhausted. At this time, close valve QV4;
[0016] b. Use the pressure pump PP to gradually increase the pressure in the pressure container R2 until the pressure gauge PG2 reading P2 reaches the predetermined value, and then close the valve QV3;
[0017] c. Open valves QV1 and QV2, and use the pressure pump PP to inject water into the pressure container R1. When water comes out from the rear end of valve QV1, it means that the air in the pressure container R1 has been exhausted. At this time, close valve QV1;
[0018] d. Use the pressure pump PP to gradually increase the pressure in the pressure container R1 until the pressure gauge PG1 reading P1 reaches the predetermined value, and then close the valve QV2;
[0019] e. If the pressure values P1 and P2 remain constant, it means that the quick connectors JT1 and JT2 and the pressure pipe TB1 are sealed reliably; if the pressure values P1 or P2 change, it means that the quick connectors JT1 and JT2 and the pressure pipe TB1 are not sealed well.
[0020] As a preferred solution, in step b, if the pressure value P2 exceeds the predetermined value, the valve QV4 is opened to drain the water and release the pressure to the predetermined value; in step d, if the pressure value P1 exceeds the predetermined value, the valve QV1 is opened to drain the water and release the pressure to the predetermined value.
[0021] As a preferred solution, a pressure relief interface is provided on the connecting pipe between the pressure pump PP and the pressure containers R1 and R2, and a valve QV5 is arranged on the pressure relief interface; when water is injected in step a, the valve QV5 is closed; after the pressure container R2 is injected with water and before the pressure container R1 is injected with water, the valve QV5 is opened to release the pressure at the rear end of the pressure pump PP to atmospheric pressure; when water is injected in step c, the valve QV5 is closed.
[0022] As a preferred solution, after the pressure test is completed, valves QV1 and QV4 are opened in sequence to release pressure.
[0023] In summary, compared with the prior art, the present invention has the following advantages and beneficial effects:
[0024] 1. The pressure device can construct a closed space. The pressure pump PP can increase the internal pressure P2 and external pressure P1 of the quick connector and the pressure pipe, and the ball valves QV1 and QV4 can reduce P1 and P2 respectively;
[0025] 2. After establishing the P1 and P2 pressure conditions, test the sealing performance of the quick connector and the pressure pipe under the condition of differential pressure at both ends. If P1 and P2 can maintain pressure continuously, it proves that the quick connector and the pressure pipe are well sealed and can be used in underwater pressure measurement environment.
[0026] Therefore, the pressure test device can batch verify the applicability of underwater pressure measurement of quick connectors and pressure pipes, truly simulate the pressure inside and outside the pressure pipes, carry out pressure test tests under various working conditions, and detect whether there are leakage problems. It provides technical support for underwater pressure measurement in pressurized environments for related tests. It has certain market prospects. BRIEF DESCRIPTION OF THE DRAWINGS
[0027] The drawings described herein are used to provide a further understanding of the embodiments of the present invention, constitute a part of this application, and do not constitute a limitation of the embodiments of the present invention.
[0028] Figure 1 This is the structural diagram of the quick connector and the pressure pipe.
[0029] Figure 2 This is a diagram of the quick connector and the pressure pipe pressure device.
[0030] Figure 3 It is a structural diagram of a pressure vessel.
[0031] Attached Figure 2 The marks and corresponding parts names are as follows: quick connector--JT1 / JT2 / JT3 / JT4 / JT5 / JT6; pressure pump--PP; pressure vessel--R1 / R2; water pressure--P1 / P2; pressure gauge--PG1 / PG2 / PG3; valve--QV1 / QV2 / QV3 / QV4 / QV5; pressure pipe--TB1 / TB2 / TB3. DETAILED DESCRIPTION
[0032] In order to make the objectives, technical solutions and advantages of the present invention more clearly understood, the principles and features of the present invention are further described in detail below in conjunction with embodiments and drawings. The exemplary implementation modes of the present invention and their description are only used to explain the present invention and are not intended to limit the scope of protection of the present invention.
[0033] In the following description, a large number of specific details are set forth in order to provide a thorough understanding of the present invention. However, it is apparent to one of ordinary skill in the art that these specific details are not necessarily employed to practice the present invention. In other instances, well-known structures, circuits, materials, or methods are not specifically described in order to avoid obscuring the present invention.
[0034] Throughout the description of the specification, references to "one embodiment," "an embodiment," "an example," or "an example" mean that a particular feature, structure, or characteristic described in conjunction with the embodiment or example is included in at least one embodiment of the present invention. Therefore, the phrases "one embodiment," "an embodiment," "an example," or "an example" appearing in various places throughout the specification do not necessarily all refer to the same embodiment or example. In addition, particular features, structures, or characteristics may be combined in one or more embodiments or examples in any suitable combination and / or sub-combination. In addition, it will be appreciated by those of ordinary skill in the art that the figures provided herein are for illustrative purposes and that the figures are not necessarily drawn to scale. The term "and / or" as used herein includes any and all combinations of one or more of the associated listed items.
[0035] The following discloses a variety of different implementation methods or examples of the subject technical solution. To simplify the disclosure, the following describes specific examples of one or more arrangements of each feature, but the examples are not intended to limit this specification. The first feature and the second feature subsequently recorded in the specification are connected, which may include a direct connection implementation, or an implementation that forms additional features. Further, it also includes the use of one or more other intervening features to indirectly connect or combine the first feature and the second feature with each other, so that the first feature and the second feature may not be directly connected. In the description of this specification, the meaning of "multiple" is at least two, such as two, three, etc., unless otherwise clearly and specifically limited.
[0036] The terms used in this specification are those general terms currently widely used in the art in consideration of the functions of the present disclosure, but these terms may vary according to the intention of a person of ordinary skill in the art, precedents, or new technologies in the art. In addition, specific terms may be selected by the applicant, and in this case, their detailed meanings will be described in the detailed description of the present disclosure. Therefore, the terms used in the specification should not be understood as simple names, but rather as an overall description based on the meaning of the terms and the present disclosure.
[0037] Flowcharts or text are used in this specification to illustrate the operation steps performed according to the embodiments of the present application. It should be understood that the operation steps in the embodiments of the present application are not necessarily performed accurately in the order of recording. On the contrary, various steps can be processed in reverse order or simultaneously as needed. At the same time, other operations can also be added to these processes, or one or more operations can be removed from these processes.
[0038] The present invention patent intends to design a pressure device, which can simulate the internal and external pressures of the pressure pipe, simulate the real use environment of the quick connector and the pressure pipe, determine whether there are sealing problems between the quick connector and the pressure pipe, and provide technical support for pressure measurement in underwater pressurized environments. To achieve the above purpose, the present invention is implemented through the following specific embodiments:
[0039] Example
[0040] This embodiment designs a quick connector and a pressure pipe pressure test device. The device has a simple structure, low manufacturing cost, and simple operation. It can test the underwater sealing performance of the quick connector and the pressure pipe. The structure diagram of the quick connector and the pressure pipe is shown in FIG. Figure 1 , see the composition of the pressure device Figure 2 This embodiment provides a reactor hydraulic simulation test quick connector and a pressure pipe pressure device, such as Figure 2As shown, it includes pressure container R1 / R2, quick connector JT1 / JT2 / JT3 / JT4 / JT5 / JT6, pressure pipe TB1 / TB2 / TB3, pressure pump PP, valve QV1 / QV2 / QV3 / QV4, pressure gauge PG1 / PG2;
[0041] The pressure vessels R1 and R2 have a plurality of quick connector interfaces. The quick connectors JT1 and JT2 are connected to the inside of the pressure vessel R1, and the quick connectors JT1 and JT2 are connected by a pressure pipe TB1; the quick connectors JT3 and JT4 are connected to the outside of the pressure vessel R1, and the quick connectors JT3 and JT1 share a quick connector interface, and the quick connectors JT4 and JT2 share a quick connector interface; the quick connectors JT5 and JT6 are connected to the outside of the pressure vessel R2, and the quick connectors JT4 and JT5 are connected by a pressure pipe TB2, and the quick connectors JT3 and JT6 are connected by a pressure pipe TB3;
[0042] The pressure containers R1 and R2 have a water injection interface, a pressure relief interface and a pressure gauge interface. The pressure pump PP is connected to the water injection interfaces of the pressure containers R1 and R2 respectively. The valve QV2 is arranged at the water injection interface of the pressure container R1, and the valve QV3 is arranged at the water injection interface of the pressure container R2; the valve QV1 is arranged at the pressure relief interface of the pressure container R1, and the valve QV4 is arranged at the pressure relief interface of the pressure container R2; the pressure gauges PG1 and PG2 are connected to the pressure gauge interfaces of the pressure containers R1 and R2 respectively.
[0043] The external environment of the quick connectors JT1, JT2 and the pressure pipe 1 in the pressure container R1 is water, and they are the structural parts to be pressure tested. The water pressure P1 in the pressure container R1 is measured by the pressure gauge PG1, and P1 is the external pressure of the quick connectors JT1, JT2 and the pressure pipe 1; the water pressure P2 in the pressure container R2 is measured by the pressure gauge PG2, and the water pressure P2 is transmitted to the quick connectors JT1, JT2 and the pressure pipe 1 through the quick connectors JT3, JT4, JT5, JT6, the pressure pipe 2 and the pressure pipe 3, and P2 is the internal pressure of the quick connectors JT1, JT2 and the pressure pipe 1. The pressure containers R1 and R2 are pressurized by the pressure pump PP, and the pressure containers R1 and R2 are depressurized by the ball valves QV1 and QV4. For convenience, Figure 2 Only the sealing pressure test of JT1, JT2 and the pressure-leading pipe 1 is illustrated. More pressure-leading joints and pressure-leading pipes can be arranged in the pressure vessel R1 as needed to achieve the purpose of batch pressure test.
[0044] First, the pressure vessel R2 is pressurized to P2 by the pressure pump PP, and then the pressure vessel R1 is pressurized to P1. QV1, QV2, QV3, and QV4 are closed to form a closed pressure space. The pressure is maintained for 5 minutes. If P1 and P2 remain constant, it means that the quick connectors JT1, JT2, and the pressure pipe 1 are sealed reliably and can be used for underwater pressure drawing. If P1 and P2 change, it means that the quick connectors JT1, JT2, and the pressure pipe 1 are leaking at the seal and cannot be used for underwater pressure drawing. When the internal pressure P2 of the quick connectors JT1, JT2, and the pressure pipe 1 is greater than the external pressure P1, the seal is generally reliable. When the internal pressure P2 of the quick connectors JT1, JT2, and the pressure pipe 1 is less than the external pressure P1, the seal may leak. The pressure test focuses on the sealing problem in this case.
[0045] Based on the above scheme, the water pressure P1 in the pressure container R1 is used to simulate the external pressure of the quick connector and the pressure pipe, and the water pressure P2 in the pressure container R2 is used to simulate the internal pressure of the quick connector and the pressure pipe; the pressure-testing device can simulate the installation environment of the quick connector and the pressure pipe, establish the internal and external pressures of the pressure pipe respectively, and test the sealing reliability of the quick connector and the pressure pipe under underwater pressure environment.
[0046] In an optional embodiment, if Figure 2 As shown, the connecting pipe between the pressure pump PP and the pressure vessels R1 and R2 has a pressure relief interface, and the valve QV5 is arranged at the pressure relief interface. The connecting pipe between the pressure pump PP and the pressure vessels R1 and R2 has a pressure gauge interface, and the pressure gauge PG3 is arranged at the pressure gauge interface.
[0047] According to the requirements of the quick connector and the pressure pipe pressure test, first design the pressure vessel R1, see Figure 3 , the pressure vessel R2 can be designed with reference to R1. In an optional embodiment, Figure 3 As shown, the pressure container R1 and / or R2 comprises a hollow cylinder and a flange, and the flange closes the upper and lower openings of the hollow cylinder to form a sealing structure. The quick connector interface, water injection interface, pressure relief interface, and pressure gauge interface are all arranged on the flange.
[0048] In an optional embodiment, the valves QV1 / QV2 / QV3 / QV4 / QV5 are ball valves.
[0049] The pressure test conditions to be established are the internal pressure P2 and the external pressure P1 of the quick connector and the pressure pipe. The test device is used to establish the above pressure test conditions. This embodiment provides a reactor hydraulic simulation test quick connector and pressure pipe test method. The reactor hydraulic simulation test quick connector and pressure pipe pressure device are used to implement the following steps:
[0050] First, fill the pressure vessels R1 and R2 with tap water. Figure 2 Install the threaded quick connector and pressure pipe as shown, and then connect all pipes and valves;
[0051] a. Close valves QV1, QV2, and QV5, open valves QV3 and QV4, and use the pressure pump PP to inject water into the pressure container R2 to increase pressure. When water comes out from the rear end of valve QV4, it means that the air in the pressure container R2 has been exhausted. At this time, close valve QV4;
[0052] b. After closing valve QV4, continue to gradually increase the pressure in pressure vessel R2 using pressure pump PP until the pressure gauge PG2 reading P2 reaches the preset value, and then close valve QV3; if the pressure value P2 exceeds the preset value, open valve QV4 to drain and release the pressure to the preset value;
[0053] After the pressure vessel R2 is filled with water and before the pressure vessel R1 is filled with water, the valve QV5 is opened to release the pressure at the rear end of the pressure pump PP to atmospheric pressure, and then the valve QV5 is closed;
[0054] c. Close valves QV3, QV4, and QV5, open valves QV1 and QV2, and use the pressure pump PP to inject water into the pressure container R1 to increase pressure. When water comes out from the rear end of valve QV1, it means that the air in the pressure container R1 has been exhausted. At this time, close valve QV1;
[0055] d. After closing valve QV1, continue to gradually increase the pressure in pressure vessel R1 using pressure pump PP until the pressure gauge PG1 reading P1 reaches the preset value, and then close valve QV2; if the pressure value P1 exceeds the preset value, open valve QV1 to drain and release the pressure to the preset value;
[0056] e. If the pressure values P1 and P2 remain constant and can be maintained for 5 minutes, it means that the quick connectors JT1 and JT2 and the pressure pipe TB1 are sealed reliably and can be used for underwater pressure drawing; if the pressure values P1 or P2 change, it means that the quick connectors JT1 and JT2 and the pressure pipe TB1 are not sealed well. After the pressure test is completed, open valves QV1 and QV4 in turn to release the pressure.
[0057] In summary, compared with the prior art, the present invention has the following advantages and beneficial effects:
[0058] 1. The pressure device can construct a closed space. The pressure pump PP can increase the internal pressure P2 and external pressure P1 of the quick connector and the pressure pipe, and the ball valves QV1 and QV4 can reduce P1 and P2 respectively;
[0059] 2. After establishing the P1 and P2 pressure conditions, test the sealing performance of the quick connector and the pressure pipe under the condition of differential pressure at both ends. If P1 and P2 can maintain pressure continuously, it proves that the quick connector and the pressure pipe are well sealed and can be used in underwater pressure measurement environment.
[0060] Therefore, the pressure test device can batch verify the applicability of underwater pressure measurement of quick connectors and pressure pipes, truly simulate the pressure inside and outside the pressure pipes, carry out pressure test tests under various working conditions, and detect whether there are leakage problems. It provides technical support for underwater pressure measurement in pressurized environments for related tests. It has certain market prospects.
[0061] Those skilled in the art will appreciate that the embodiments of the present application may be provided as methods, systems, or computer program products. Therefore, the present application may adopt the form of a complete hardware embodiment, a complete software embodiment, or an embodiment in combination with software and hardware. Moreover, the present application may adopt the form of a computer program product implemented in one or more computer-usable storage media (including but not limited to disk storage, CD-ROM, optical storage, etc.) that include computer-usable program code.
[0062] The present application is described with reference to the flowcharts and / or block diagrams of the methods, devices (systems), and computer program products according to the embodiments of the present application. It should be understood that each process and / or box in the flowchart and / or block diagram, as well as the combination of the processes and / or boxes in the flowchart and / or block diagram, can be implemented by computer program instructions. These computer program instructions can be provided to a processor of a general-purpose computer, a special-purpose computer, an embedded processor, or other programmable data processing device to generate a machine, so that the instructions executed by the processor of the computer or other programmable data processing device generate instructions for implementing the processes in the flowchart and / or block diagram. Figure 1 A process or multiple processes and / or boxes Figure 1 A device that provides the functions specified in a block or multiple blocks.
[0063] These computer program instructions may also be stored in a computer-readable memory capable of directing a computer or other programmable data processing device to operate in a specific manner, so that the instructions stored in the computer-readable memory produce an article of manufacture comprising an instruction device, which implements the process Figure 1 A process or multiple processes and / or boxes Figure 1 A function specified in one or more boxes.
[0064] These computer program instructions can also be loaded onto a computer or other programmable data processing device so that a series of operating steps are executed on the computer or other programmable device to produce a computer-implemented process, thereby providing instructions for implementing the process. Figure 1 A process or multiple processes and / or boxes Figure 1 The steps for the functions specified in one or more boxes.
[0065] The specific implementation methods described above further illustrate the objectives, technical solutions and beneficial effects of the present invention in detail. It should be understood that the above description is only a preferred implementation method of the present invention and is not intended to limit the scope of protection of the present invention. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principles of the present invention should be included in the scope of protection of the present invention.
Claims
1. A reactor hydraulic simulation test quick connector and a pressure pipe pressure device, characterized in that: Including pressure container R1 / R2, quick connector JT1 / JT2 / JT3 / JT4 / JT5 / JT6, pressure pipe TB1 / TB2 / TB3, pressure pump PP, valve QV1 / QV2 / QV3 / QV4, pressure gauge PG1 / PG2; The pressure vessels R1 and R2 have a plurality of quick connector interfaces. The quick connectors JT1 and JT2 are connected to the inside of the pressure vessel R1, and the quick connectors JT1 and JT2 are connected by a pressure pipe TB1; the quick connectors JT3 and JT4 are connected to the outside of the pressure vessel R1, and the quick connectors JT3 and JT1 share a quick connector interface, and the quick connectors JT4 and JT2 share a quick connector interface; the quick connectors JT5 and JT6 are connected to the outside of the pressure vessel R2, and the quick connectors JT4 and JT5 are connected by a pressure pipe TB2, and the quick connectors JT3 and JT6 are connected by a pressure pipe TB3; The pressure containers R1 and R2 have a water injection interface, a pressure relief interface and a pressure gauge interface. The pressure pump PP is connected to the water injection interfaces of the pressure containers R1 and R2 respectively. The valve QV2 is arranged at the water injection interface of the pressure container R1, and the valve QV3 is arranged at the water injection interface of the pressure container R2; the valve QV1 is arranged at the pressure relief interface of the pressure container R1, and the valve QV4 is arranged at the pressure relief interface of the pressure container R2; the pressure gauges PG1 and PG2 are connected to the pressure gauge interfaces of the pressure containers R1 and R2 respectively.
2. The reactor hydraulic simulation test quick connector and pressure pipe pressure device according to claim 1, characterized in that: A pressure relief interface is provided on the communicating pipeline between the pressure pump PP and the pressure containers R1 and R2, and a valve QV5 is arranged on the pressure relief interface.
3. The reactor hydraulic simulation test quick connector and pressure pipe pressure device according to claim 1, characterized in that: A pressure gauge interface is provided on the communicating pipe between the pressure pump PP and the pressure containers R1 and R2, and the pressure gauge PG3 is arranged on the pressure gauge interface.
4. The reactor hydraulic simulation test quick connector and pressure pipe pressure device according to claim 1, characterized in that: The pressure container R1 and / or R2 comprises a hollow cylinder and a flange, and the flange closes the upper and lower openings of the hollow cylinder to form a sealing structure.
5. The reactor hydraulic simulation test quick connector and pressure pipe pressure device according to claim 4, characterized in that: The quick connector interface, water injection interface, pressure relief interface and pressure gauge interface are all arranged on the flange.
6. The reactor hydraulic simulation test quick connector and pressure pipe pressure device according to claim 2, characterized in that: Valves QV1 / QV2 / QV3 / QV4 / QV5 use ball valves.
7. A reactor hydraulic simulation test quick connector and pressure pipe testing method, characterized in that: Using the reactor hydraulic simulation test quick connector and the pressure pipe pressure device as described in any one of claims 1 to 6, the following steps are implemented: a. Close valve QV2, open valves QV3 and QV4, and use the pressure pump PP to inject water into the pressure container R2. When water comes out from the rear end of valve QV4, it means that the air in the pressure container R2 has been exhausted. At this time, close valve QV4; b. Use the pressure pump PP to gradually increase the pressure in the pressure container R2 until the pressure gauge PG2 reading P2 reaches the predetermined value, and then close the valve QV3; c. Open valves QV1 and QV2, and use the pressure pump PP to inject water into the pressure container R1. When water comes out from the rear end of valve QV1, it means that the air in the pressure container R1 has been exhausted. At this time, close valve QV1; d. Use the pressure pump PP to gradually increase the pressure in the pressure container R1 until the pressure gauge PG1 reading P1 reaches the predetermined value, and then close the valve QV2; e. If the pressure values P1 and P2 remain constant, it means that the quick connectors JT1 and JT2 and the pressure pipe TB1 are sealed reliably; if the pressure values P1 or P2 change, it means that the quick connectors JT1 and JT2 and the pressure pipe TB1 are not sealed well.
8. The reactor hydraulic simulation test quick connector and pressure pipe testing method according to claim 7, characterized in that: In step b, if the pressure value P2 exceeds the preset value, the valve QV4 is opened to drain the water and release the pressure to the preset value; in step d, if the pressure value P1 exceeds the preset value, the valve QV1 is opened to drain the water and release the pressure to the preset value.
9. The reactor hydraulic simulation test quick connector and pressure pipe testing method according to claim 7, characterized in that: A pressure relief interface is provided on the connecting pipeline between the pressure pump PP and the pressure containers R1 and R2, and a valve QV5 is arranged on the pressure relief interface; when water is injected in step a, the valve QV5 is closed; after the pressure container R2 is injected with water and before the pressure container R1 is injected with water, the valve QV5 is opened to release the pressure at the rear end of the pressure pump PP to atmospheric pressure; when water is injected in step c, the valve QV5 is closed.
10. The reactor hydraulic simulation test quick connector and pressure pipe testing method according to claim 7, characterized in that: After the pressure test is completed, open valves QV1 and QV4 in sequence to release pressure.
Citation Information
Patent Citations
Gas tightness detection system suitable for full-size flexible composite pipe and joints thereof
CN113390574A
Hydraulic quick joint integrated test bench
CN204064579U