Method, device, equipment and readable storage medium for determining temporary plugging agent dosage
By calculating the first and second average sand ratios, combined with the construction displacement and pressure, the dosage of temporary fracturing plugging agent is accurately determined, which solves the problem of inaccurate dosage in the existing technology and improves the oilfield production effect.
Patent Information
- Application Number
- CN202110877248.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2021-07-31
- Publication Date
- 2024-10-29
- Estimated Expiration
- 2041-07-31
AI Technical Summary
In the existing technology, the determination of the dosage of temporary fracturing plugging agent is accidental and specific, which leads to inaccurate dosage during construction and affects the oilfield production effect.
The balance time is determined based on the pressure in the first joint and the first average sand ratio, and the second average sand ratio is determined based on the pressure in the second joint and the balance time. It is calculated based on the construction displacement, balance time, and the first and second average sand ratios. The dosage of temporary blocking agent ensures the accuracy and adaptability of the dosage.
It achieves the authenticity and accuracy of the temporary plugging agent dosage, improves the reservoir transformation effect, and ensures the adaptability and accuracy of oil field exploitation.
Smart Images

Figure CN115680555B_ABST
Abstract
Description
Technical Field
[0001] The present application relates to the technical field of oil reservoir fracturing and production, and in particular to a method, device, equipment and readable storage medium for determining the dosage of a temporary plugging agent. Background Art
[0002] During the oil reservoir exploitation process, fracturing operations can create cracks in the reservoir, improve the connectivity between the reservoir and the oil well, and increase oil production. However, repeated fracturing operations will increase the water content in the cracks, which is not conducive to oil production. The fracturing temporary plugging technology can generate a certain temporary plugging pressure difference at both ends of the temporary plugging agent near the crack mouth of the oil reservoir, thereby temporarily plugging the main crack and opening the lateral cracks, thereby forming a complex crack network, improving the reservoir transformation effect and achieving the purpose of increasing production. The amount of fracturing temporary plugging agent used will affect the transformation effect of the reservoir.
[0003] In the related art, the dosage of temporary plugging agent in pressure temporary plugging construction is generally designed based on construction experience, or the dosage of temporary plugging agent is simply calculated using a formula. However, the results obtained by experience control and simple formula calculation methods have certain randomness and specificity, and the data obtained are single, solidified, and have poor accuracy, and are poorly adapted to the actual mining environment. Summary of the invention
[0004] The present application provides a method, device, equipment and readable storage medium for determining the amount of temporary plugging agent, so as to achieve accurate determination of the amount of temporary plugging agent.
[0005] In one aspect, a method for determining the amount of a temporary plugging agent is provided, the method comprising:
[0006] The equilibrium time is determined according to the first intra-fracture pressure and the first average sand ratio, wherein the first intra-fracture pressure refers to the pressure in the fracture before adding the temporary plugging agent;
[0007] The second average sand ratio is determined according to the second fracture pressure and the equilibrium time. The second fracture pressure refers to the pressure in the fracture after the temporary plugging agent is added.
[0008] The dosage of temporary plugging agent is determined based on the construction displacement, balance time, the first average sand ratio and the second average sand ratio.
[0009] In a possible implementation, determining the equilibrium time according to the first seam pressure and the first average sand ratio includes: determining the first equilibrium height based on the first seam pressure; and determining the equilibrium time based on the first equilibrium height and the first average sand ratio.
[0010] In a possible implementation, determining the first equilibrium height based on the first slit pressure includes: determining the first particle sedimentation equilibrium resistance velocity based on the relationship between the slit pressure and the particle sedimentation equilibrium resistance velocity and the first slit pressure; determining the first equilibrium flow velocity based on the relationship between the particle sedimentation equilibrium resistance velocity and the equilibrium flow velocity and the first particle sedimentation equilibrium resistance velocity; determining the first equilibrium height based on the first equilibrium flow velocity.
[0011] In a possible implementation, a first equilibrium height is determined based on a first equilibrium flow velocity, including: determining a flow section height at a first equilibrium flow velocity based on the first equilibrium flow velocity and the construction displacement; and determining the first equilibrium height based on the flow section height at the first equilibrium and the fracture height of the hydraulic fracture.
[0012] In a possible implementation, before determining the second average sand ratio according to the second fracture pressure and the equilibrium time, the method further includes: determining an expected additional pressure after adding the temporary plugging agent; and taking the sum of the expected additional pressure and the first fracture pressure as the second fracture pressure.
[0013] In a possible implementation, before determining the equilibrium time according to the first seam pressure and the first average sand ratio, the method further includes:
[0014] Based on the single well geological data of the target well and the production dynamic data of the adjacent wells, the fracturing crack morphological parameters and fracturing operation parameters of the target well before adding the temporary plugging agent are obtained. The fracturing crack morphological parameters include the fracture height of the fracturing crack, and the fracturing operation parameters include the first fracture pressure and the first average sand ratio.
[0015] In a possible implementation, the amount of temporary plugging agent is determined based on the construction displacement, the balance time, the first average sand ratio and the second average sand ratio, including:
[0016] The difference between the second average sand ratio and the first average sand ratio is taken as the increment of the average sand ratio; the volume of the temporary plugging agent is determined based on the construction displacement, the balancing time and the increment of the average sand ratio; the dosage of the temporary plugging agent is determined based on the volume of the temporary plugging agent and the density of the temporary plugging agent.
[0017] On the other hand, a device for determining the amount of temporary plugging agent is provided, the device comprising:
[0018] A first determination module is used to determine the equilibrium time according to a first intra-fracture pressure and a first average sand ratio, wherein the first intra-fracture pressure refers to the pressure in the fracturing fracture before adding a temporary plugging agent;
[0019] A second determination module is used to determine a second average sand ratio according to a second fracture pressure and a balance time, wherein the second fracture pressure refers to the pressure in the fracture after adding a temporary plugging agent;
[0020] The third determination module is used to determine the amount of temporary plugging agent based on the construction displacement, the balance time, the first average sand ratio and the second average sand ratio.
[0021] In a possible implementation, the first determination module is used to determine a first equilibrium height based on a first seam pressure; and to determine an equilibrium time based on the first equilibrium height and a first average sand ratio.
[0022] In one possible implementation, the first determination module is used to determine the first particle sedimentation equilibrium resistance velocity based on the relationship between the pressure in the slit and the particle sedimentation equilibrium resistance velocity and the first slit pressure; determine the first equilibrium flow velocity based on the relationship between the particle sedimentation equilibrium resistance velocity and the equilibrium flow velocity and the first particle sedimentation equilibrium resistance velocity; and determine the first equilibrium height based on the first equilibrium flow velocity.
[0023] In a possible implementation, the first determination module is used to determine the first equilibrium flow section height at the first equilibrium flow rate based on the first equilibrium flow rate and the construction displacement; and determine the first equilibrium height based on the first equilibrium flow section height and the fracture height of the fracturing crack.
[0024] In a possible implementation, the device further includes: an additional module, configured to determine an expected additional pressure after adding the temporary plugging agent; and to use the sum of the expected additional pressure and the first slit pressure as the second slit pressure.
[0025] In a possible implementation, the device also includes: an acquisition module, which is used to obtain the fracturing crack morphology parameters and fracturing construction parameters of the target well before adding the temporary plugging agent based on the single well geological data of the target well and the production dynamic data of the adjacent wells, the fracturing crack morphology parameters including the fracture height of the fracturing crack, and the fracturing construction parameters including the first fracture pressure and the first average sand ratio.
[0026] In a possible implementation, the third determination module is used to take the difference between the second average sand ratio and the first average sand ratio as the increment of the average sand ratio; determine the volume of the temporary plugging agent based on the construction displacement, balance time and the increment of the average sand ratio; and determine the amount of the temporary plugging agent based on the volume of the temporary plugging agent and the density of the temporary plugging agent.
[0027] On the other hand, a computer device is provided, which includes a processor and a memory, wherein at least one program code is stored in the memory, and the program code is loaded and executed by the processor to enable the computer device to implement any of the above methods for determining the amount of temporary plugging agent.
[0028] On the other hand, a computer-readable storage medium is provided, in which at least one program code is stored, and the program code is loaded and executed by a processor to enable a computer to implement any of the above-mentioned methods for determining the dosage of a temporary plugging agent.
[0029] On the other hand, a computer program or a computer program product is provided, wherein at least one computer instruction is stored in the computer program or the computer program product, and the at least one computer instruction is loaded and executed by a processor to enable a computer to implement any of the above methods for determining the dosage of a temporary plugging agent.
[0030] The technical solution for determining the amount of temporary plugging agent provided in the embodiment of the present application can ensure the authenticity and accuracy of the amount of temporary plugging agent by accurately calculating the amount of temporary plugging agent based on the acquired data. BRIEF DESCRIPTION OF THE DRAWINGS
[0031] Figure 1 It is a schematic diagram of an implementation environment provided by an embodiment of the present application;
[0032] Figure 2 This is a flow chart of a method for determining the dosage of a temporary plugging agent provided in an embodiment of the present application;
[0033] Figure 3 is a schematic diagram of a device for determining the amount of temporary plugging agent provided in an embodiment of the present application;
[0034] Figure 4 It is a structural diagram of a computer device provided in an embodiment of the present application. DETAILED DESCRIPTION
[0035] Unless otherwise defined, all technical terms used in the embodiments of the present application have the same meanings as those generally understood by those skilled in the art, and are only used to explain the embodiments of the present application and are not intended to limit the present application.
[0036] In the process of oil field development, pressure operation is an important operation to generate fractures in the reservoir and improve the connectivity between the reservoir and the oil well. The related fracturing temporary plugging technology is to inject temporary plugging agents into the reservoir to temporarily plug the main fractures, open the lateral fractures to form a complex fracture network, and improve the reservoir transformation effect. However, the amount of temporary plugging agent used will affect the fracturing effect. The method of determining the amount of temporary plugging agent based on experience in related technologies will lead to inaccurate dosage during construction, which will interfere with oil field production. Therefore, there is an urgent need for a method that can accurately determine the amount of temporary plugging agent before performing temporary plugging operations.
[0037] See also Figure 1 The implementation environment of the embodiment of the present application includes at least one terminal 101 and a server 102, and the method is executed on the terminal 101 or the server 102 respectively. The terminal 101 and the server 102 can be connected in communication to realize the interactive transmission of information. The terminal 101 and the server 102 obtain parameter data for calculation and determine the amount of temporary plugging agent.
[0038] Among them, the terminal 101 can be any electronic product that can interact with the user through one or more methods such as keyboard, touchpad, touch screen, voice interaction, etc., such as PC (Personal Computer), PPC (Pocket Personal Computer), tablet computer, etc.
[0039] Server 102 can be a single server or a server cluster composed of multiple servers. It can also be a cloud server that provides basic cloud computing services such as cloud services, cloud databases, cloud computing, cloud functions, cloud storage, network services, cloud communications, middleware services, domain name services, security services, CDN (Content Delivery Network), as well as big data and artificial intelligence platforms.
[0040] The embodiment of the present application provides a method for determining the amount of temporary plugging agent, based on the actual situation of the oil well at the mining site, obtaining parameter data of the target well for temporary plugging operation, and combining relevant formulas to determine the amount of temporary plugging agent for the target well. To ensure the degree of adaptation and accuracy of the temporary plugging agent dosage to the actual development situation, and to achieve better reservoir development effects. The method provided in the embodiment of the present application includes but is not limited to the following steps 201-203.
[0041] 201. The equilibrium time is determined according to the first intra-fracture pressure and the first average sand ratio. The first intra-fracture pressure refers to the pressure in the fracture before adding the temporary plugging agent.
[0042] The equilibrium time refers to the time required for the sand bank to reach the first equilibrium height under the first intra-fracture pressure and the first average sand ratio. During the development of the target well, when the sand bank reaches the equilibrium height, the hydraulic fracture is in equilibrium under the current pressure. In this step, the first equilibrium height needs to be determined based on the first intra-fracture pressure, and then the equilibrium time is determined based on the first equilibrium height and the first average sand ratio. In a possible implementation, before step 201, the fracture length, fracture height and mixed liquid density of the hydraulic fracture need to be determined.
[0043] The mixed liquid refers to a mixture of fracturing fluid and sand; the average sand ratio indicates the concentration of added sand, which is the ratio of the volume of sand to the volume of fracturing fluid in the sand-liquid mixture (i.e., the mixed liquid). In practical applications, the types of fracturing fluid and sand are determined based on the current implementation environment, and this application does not limit this. For example, the fracturing fluid may be gel fracturing fluid, guar gum, etc., and the type of sand may be quartz sand.
[0044] The process of determining the first equilibrium height includes: determining the first particle settling equilibrium resistance velocity based on the relationship between the pressure in the slit and the particle settling equilibrium resistance velocity and the first slit pressure; determining the first equilibrium flow velocity based on the relationship between the particle settling equilibrium resistance velocity and the equilibrium flow velocity and the first particle settling equilibrium resistance velocity; and determining the first equilibrium height based on the first equilibrium flow velocity. Exemplarily, the process of determining the first equilibrium height includes but is not limited to the following steps 2011-2013.
[0045] Step 2011, obtaining a first fracture pressure in a target well when the hydraulic fracture is in a balanced state, substituting the value of the first fracture pressure into Formula 1 to obtain a first particle settling equilibrium resistance velocity.
[0046]
[0047] Formula 1 represents the relationship between the pressure in the fracture and the equilibrium resistance velocity of particle settling. In the formula, P refers to the pressure in the fracture, unit MPa; U refers to the equilibrium resistance velocity of particle settling, unit m / s; L refers to the length of the fracture, unit m; ρ dc Refers to the density of sand-liquid mixture (mixed liquid density), unit: g / cm 3 , sand-fluid mixture refers to the mixture of sand and fracturing fluid; W refers to the width of the fracturing crack, unit: m.
[0048] Based on Formula 1, after obtaining the first fracture pressure P1, the value of the first fracture pressure P1 and the values of other required parameter data are substituted into Formula 1 to calculate the first particle settling equilibrium resistance velocity U1. Among them, other parameter data, such as the fracture width and fracture length of the fracturing fracture, can be obtained through the fracturing analysis software before step 201, and the density of the mixed liquid can be determined by calculation.
[0049] Step 2012: Substitute the first particle settling equilibrium resistance velocity into Formula 2 to calculate the first equilibrium flow velocity.
[0050]
[0051] Formula 2 represents the relationship between the particle settling equilibrium resistance velocity and the equilibrium flow rate. In the formula, V refers to the equilibrium flow rate, in units of m / s; μ refers to the liquid viscosity, in units of mPa·s, where the liquid viscosity refers to the viscosity of the fracturing fluid; U, W and ρ sc The meaning is the same as in Formula 1, which refers to the particle settling equilibrium resistance velocity, the width of the fracturing crack and the sand-liquid mixing density respectively.
[0052] In this step, U1 calculated in 2011 is substituted into Formula 2, and the first equilibrium flow rate V1 is calculated by combining the values of other corresponding data in the formula. The values of other data are determined before step 201.
[0053] Step 2013: Substitute the first equilibrium flow velocity into Formula 3 to calculate the first equilibrium height.
[0054] In this step, the process of determining the first equilibrium height based on the first equilibrium flow velocity includes: determining the first equilibrium flow section height at the first equilibrium flow velocity based on the first equilibrium flow velocity and the construction displacement; determining the first equilibrium height based on the first equilibrium flow section height and the fracture height of the fracturing crack.
[0055]
[0056] Formula 3 represents the relationship between equilibrium flow velocity and equilibrium height. In the formula, H refers to the equilibrium height of the sand bank under equilibrium state, unit m; H0 refers to the fracture height of the hydraulic fracture, unit m; h refers to the flow section height at equilibrium, unit m; Q refers to the construction displacement, unit m 3 / min, V refers to the equilibrium flow velocity, unit is m / s. Based on the above formula 3, the flow section height h at equilibrium is calculated based on the construction displacement, the fracture height of the hydraulic fracture and the equilibrium flow velocity.
[0057] In an exemplary embodiment, based on the mathematical calculation rules and the form of Formula 3, the first equilibrium flow section height h1 at the first equilibrium flow rate is first calculated according to the construction displacement Q, the seam width W and the first equilibrium flow rate V1 obtained in 2012, and then the difference between H0 and h1 is calculated to obtain the first equilibrium height.
[0058] After determining the first equilibrium height, the process of determining the equilibrium time based on the obtained first equilibrium height and the first average sand ratio includes but is not limited to the following steps 2014 and 2015.
[0059] Step 2014: Based on the relationship between coefficient K, average sand ratio S, and equilibrium height H expressed in formula 4, substitute the values of corresponding parameter data to calculate the value of the first coefficient K1;
[0060]
[0061] In the formula, K is the coefficient, S refers to the average sand ratio, and the decimal form is used in the calculation process; U P It refers to the uniform velocity of particle settling, in m / s; ρ refers to the density of fracturing fluid, in kg / m 3 , V refers to the equilibrium flow velocity, the unit is m / s, H and h have the same meaning as in formula 3.
[0062] In this step, V1, h1, H1 calculated in the above steps 2011-2013 and the first average sand ratio S1 obtained are substituted into Formula 4 to calculate the first coefficient K1.
[0063] Step 2015: Based on the relationship between the time t when the sand bank reaches the equilibrium height, the equilibrium height H, and the coefficient K expressed in Formula 5, substitute the values of the corresponding parameter data to calculate the first equilibrium time.
[0064]
[0065] Formula 5 calculates the time required for the sand bank to reach the equilibrium height by expressing the relationship between time, equilibrium height, construction displacement and coefficient K.
[0066] In this step, the values of K1, H1, h1 and the data of W and Q calculated in the above steps 2011-2014 are substituted into formula 5 to calculate the value of the equilibrium time. In a possible implementation, it is assumed that the equilibrium height has been reached when the sand bank reaches 95% of the equilibrium height. The W and Q point values can be obtained before step 201.
[0067] In the above steps, parameters such as the first intra-fracture pressure and the first average sand ratio are applied. Such parameters are acquired before executing step 201. There are many ways to acquire them, which are not limited in the embodiment of the present application. Based on the contents of formulas 1-5 applied in the above calculation process, it can be seen that in the process of calculating based on the formula, other parameter data such as the fracture height, fracture width, and construction displacement of the hydraulic fracture are also applied. The acquisition method of other parameter data is not limited in the embodiment of the present application.
[0068] 202. The second average sand ratio is determined based on the second fracture pressure and the equilibrium time. The second fracture pressure refers to the pressure in the fracture after the temporary plugging agent is added.
[0069] The method for determining the second intra-fracture pressure includes: determining the expected additional pressure after adding a temporary plugging agent; and taking the sum of the expected additional pressure and the first intra-fracture pressure as the second intra-fracture pressure. The preset additional pressure is the increment of the pressure in the fracturing crack after adding the temporary plugging agent. The preset additional pressure is set according to the actual mining situation. The present application does not limit the size and setting method of the additional pressure. The second average sand ratio refers to the average sand ratio corresponding to the second equilibrium height reached within the equilibrium time under the second intra-fracture pressure. The second equilibrium height is determined based on the second intra-fracture pressure.
[0070] The process of determining the second average sand ratio in this step includes: determining the second equilibrium height based on the second seam pressure; determining the second average sand ratio based on the second equilibrium height and the above equilibrium time. Exemplarily, the method for determining the second equilibrium height is similar to the method for determining the first equilibrium height, and the second equilibrium height is calculated and determined based on the second seam pressure and formula 1-3, which will not be repeated in this application.
[0071] Determining the second average sand ratio based on the second equilibrium height and the equilibrium time includes: based on the time when the sand bank reaches the equilibrium height, and the relationship between the equilibrium height and the coefficient expressed in Formula 5, substituting the values of the above equilibrium time and the second average sand ratio into Formula 5 to obtain the value of the second coefficient at this time; based on the relationship between the coefficient, the average sand ratio, and the equilibrium height expressed in Formula 4, substituting the value of the coefficient at this time and the second equilibrium height to calculate the second equilibrium sand ratio corresponding to the addition of the temporary plugging agent.
[0072] 203. Determine the amount of temporary plugging agent based on the construction displacement, balance time, first average sand ratio and second average sand ratio.
[0073] In this step, determining the amount of temporary plugging agent includes: taking the difference between the second average sand ratio and the first average sand ratio as the increment of the average sand ratio; determining the volume of the temporary plugging agent based on the construction displacement, the balance time and the increment of the average sand ratio; and determining the amount of the temporary plugging agent based on the volume of the temporary plugging agent and the density of the temporary plugging agent. This process can be implemented according to formulas 6 and 7.
[0074] X=Qt(S2-S1) (Formula 6)
[0075] M=ρ Z X (Formula 7)
[0076] Formulas 6 and 7 are respectively the formulas for calculating the volume and dosage of temporary plugging agent, where S1 and S2 refer to the first average sand ratio before adding temporary plugging agent and the second average sand ratio after adding temporary plugging agent, respectively. S1 and S2 are calculated in decimal form in formulas 6 and 7. Q is the aforementioned construction displacement, ρ Z Temporary plugging agent density, unit: kg / m 3 .
[0077] In this step, the parameter data obtained in steps 201 and 202 are substituted into formulas 6 and 7 respectively to calculate the temporary plugging agent dosage, wherein the temporary plugging agent dosage may refer to the mass of the temporary plugging agent to be applied.
[0078] Before executing step 201, it is necessary to obtain the parameter data used in steps 201-203. The method for obtaining the parameter data is: based on the single well geological data of the target well and the production dynamic data of the adjacent wells, the fracturing crack morphology parameters and fracturing construction parameters of the target well before adding the temporary plugging agent are obtained.
[0079] In this step, the production well that needs to be subjected to temporary fracturing plugging operation is determined as the target well, and the single well geological data of the target well and the production dynamic data of the neighboring wells of the target well are obtained; based on the single well geological data of the target well and the production dynamic data of the neighboring wells, the fracturing crack morphological parameters and fracturing construction parameters before adding the temporary plugging agent are determined in combination with the fracturing analysis software. Among them, the fracturing crack morphological parameters before adding the temporary plugging agent include the length, height and width of the fracturing crack before adding the temporary plugging agent; the fracturing construction parameters include the first intra-fracture pressure, the first average sand ratio, the construction displacement, the density of each liquid that needs to be injected into the reservoir during construction, the density of the mixed liquid, the viscosity of the liquid, etc. Exemplarily, the density of the fracturing fluid, the density of the sand, the sand ratio and the porosity of the sand can be obtained respectively, and then the sand-liquid mixed density can be calculated.
[0080] The fracture morphology parameters and fracturing construction parameters before adding the temporary plugging agent are used in the calculation process to determine the amount of temporary plugging agent. The method of obtaining the single well geological logging data of the target well and the production dynamic data of the adjacent wells, as well as the type of fracturing analysis software used, are not limited in this application; for example, geological surveys can be carried out through professional logging equipment, and data monitoring during the mining process can be achieved to obtain real-time feedback data during the mining process.
[0081] In a possible implementation, the length L, height H0, and width W of the fracture are obtained; the first fracture pressure P1 is obtained, that is, the pressure in the fracture before the temporary plugging agent is added. In a possible implementation, the technical solution can be applied to the development site to directly obtain real-time monitoring data in the target well. For example, the net fracture pressure P1 when the fracture reaches a balanced state is used as the first fracture pressure; the sand-liquid mixed density ρ is obtained. sc ; Get the liquid viscosity μ; Get the first average sand ratio S1 before adding the temporary plugging agent. Wherein, the density of the sand-liquid mixture refers to the mixture obtained by mixing sand and fracturing fluid.
[0082] The embodiment of the present application provides a method for determining the amount of a temporary plugging agent, obtaining the fracturing construction parameters and the morphological parameters of the fracturing crack before adding the temporary plugging agent, and calculating the increment of the average sand ratio when the pressure in the fracturing crack reaches the second internal pressure within the equilibrium time, and obtaining the construction displacement, to calculate the amount of the temporary plugging agent. This method can ensure the accuracy of the determined amount of temporary plugging agent through precise calculation; and this method can be applied to a variety of temporary plugging agents and has a wide range of uses; in addition, the parameter data used for calculation is the real data of the mining site, and the amount of fracturing agent used in the construction process can be calculated in real time. The matching degree between the amount of temporary plugging agent and the actual situation is guaranteed, and data can also be obtained in real time to achieve real-time adjustment of the construction plan.
[0083] In order to more clearly introduce the method for determining the amount of temporary plugging agent provided in the embodiment of the present application, the following describes the method for determining the amount of temporary plugging agent provided in the embodiment of the present application in combination with an exemplary embodiment. In this embodiment, a low-permeability tight sandstone reservoir oil well in a certain mining area is used as a target well to determine the amount of temporary plugging agent used in the fracturing process of the target well. In this exemplary embodiment, the fracturing of the well adopts 31 / 2 oil pipe to inject liquid, and the process of determining the amount of temporary plugging agent includes but is not limited to the following steps 1-4.
[0084] Step 1: Based on the single well geological data of the target well and the production dynamic data of the adjacent wells, the fracture morphology parameters and fracturing operation parameters before temporary plugging are obtained.
[0085] During the mining process, if the distance between multiple mining wells in the same mining area is small, the relevant data of the neighboring wells of the production well will have a certain reference value in the process of acquiring the data of the target well. In this step, the geological data of the production well currently undergoing temporary fracturing and the dynamic production data of the neighboring wells of the production well are obtained, and the simulation calculation is performed in combination with the fracturing analysis software to obtain the fracturing crack parameters and fracturing operation parameters before adding the temporary plugging agent.
[0086] In this exemplary embodiment, multiple fracturing cracks are generated during the fracturing process, and the fracturing analysis software is used to determine the simulated equivalent network of the actual fracture network, and then the simulated equivalent parameters are determined. The fracturing crack morphological parameters determined in step 1 before adding the temporary plugging agent include: the simulated equivalent fracture network length L of the fracturing crack is 90m, the simulated equivalent fracture network height H0 is 30m, and the simulated equivalent fracture network width W is 6cm.
[0087] The fracturing operation parameters determined in this step include: total operation displacement Q Z =6m 3 / min, then the single-side seam displacement is Q D =3m 3 / min, the net pressure in the fracture (the first fracture pressure) is 3MPa, the liquid viscosity μ=50mPa·s, and the fracturing fluid density ρ=1g / cm 3 , sand density ρ s =2.65g / cm 3 , temporary plugging agent density ρ z =1.2g / cm 3 , mixed liquid density (sand liquid mixed density) ρ sc =1076g / cm 3 , the first sand ratio S1 before adding temporary plugging agent = 8%.
[0088] In this exemplary embodiment, the process of adding the mixed liquid and the fracturing fluid is performed based on the double-side seams, and therefore the total construction displacement and the construction displacement of the single-side seam are determined. The mixed liquid is a mixture of fracturing fluid and sand. In this exemplary embodiment, the density of the mixed liquid is determined based on the density of the fracturing fluid, the density of the sand, the current sand ratio of the sand, and the porosity of the reservoir.
[0089] Exemplarily, the density of the mixed liquid is calculated as follows: in, Indicates the porosity of the sand. In the embodiment of the present application, the porosity is 40%. 1000 represents the approximate weight of each cubic meter of fracturing fluid (kg), and 2650 is the density of the sand (kg / m3).
[0090] Step 2: Determine the equilibrium time based on the first seam pressure and the first average sand ratio.
[0091] Among the parameter data obtained in step 1, the first seam pressure P1 = 3 MPa required in this step, the simulated equivalent seam network seam length L = 90 m, the simulated equivalent seam network seam height H0 = 30 m, the simulated equivalent seam network seam width W = 6 cm, and the mixed liquid density ρ sc =1076g / cm 3 , liquid viscosity μ = 50mPa·s, single slit displacement Q = 3m 3 / min.
[0092] The equilibrium time is the time required for the sand bank to reach the equilibrium height. In this step, it is the time required for the sand bank to reach the first equilibrium height under the pressure in the first seam. The process of calculating the equilibrium time based on the selected parameter data includes but is not limited to steps 2-1 to 2-4.
[0093] Step 2-1, according to formula 1: Select the first seam pressure P1, simulated equivalent seam network length L, simulated equivalent seam network width W, and mixed liquid density ρ sc Substitute the value of into the corresponding position in formula 1 to obtain the formula: Further calculations revealed that the first particle settling equilibrium resistance velocity U1 = 0.96 m / s.
[0094] Step 2-2: According to Formula 2, the calculated first particle settling equilibrium resistance velocity U1, slit width W, and mixed liquid density ρ sc Substitute the value of the liquid viscosity μ into the corresponding position of Formula 2 to calculate the value of the first equilibrium flow rate V1:
[0095]
[0096] Step 2-3, according to formula 3, select the construction displacement Q, the seam height H0, and the calculated value of the first equilibrium flow velocity V1 to substitute for the corresponding position, and calculate the equilibrium flow section height h1=4.17m under the first equilibrium flow velocity, and the first equilibrium height H1=25.83 reached by the sand bank. The calculation process is as follows:
[0097]
[0098] Step 2-4: According to formula 4, select the first average sand ratio S1, fracturing fluid density ρ, and mixed fluid density ρ sc , particle settling uniform velocity U P And the calculated value of the first equilibrium height H1 is substituted into the corresponding position in Formula 5, where U P The value is 0.17m / s, and K1=0.313 is calculated. According to formula 5, the values of relevant parameter data are substituted to calculate the corresponding equilibrium time t=9.84min.
[0099]
[0100]
[0101] Step 3: Determine a second average sand ratio based on the second seam pressure and the equilibrium time.
[0102] After the temporary plugging agent is added, the pressure in the fracture of the reservoir will change, and a second pressure in the fracture will be obtained. In this exemplary embodiment, an additional pressure ΔP=2MPa is set, and the second pressure in the fracture is P2=P1+ΔP=5MPa.
[0103] In this step, before determining the second average sand ratio, the second equilibrium height is determined based on the second seam pressure, and then the second average sand ratio is determined based on the second equilibrium height and the above-mentioned equilibrium time. The sub-steps for determining the second average sand ratio in this step are step 3-1 and step 3-2.
[0104] Step 3-1: Determine a second equilibrium height based on the second seam internal pressure.
[0105] In the embodiment of the present application, the method for determining the second equilibrium height is the same as the method for determining the first equilibrium height in step 2. According to formula 1, the relevant data is substituted into the corresponding position to calculate the second particle settling equilibrium resistance velocity U2=1.24m / s, and then the second equilibrium flow velocity V2=0.33m / s is obtained based on formula 2; according to formula 3, the second equilibrium flow section height h2=2.49m and the second equilibrium height H2=27.51m are obtained under the second equilibrium flow velocity. The specific calculation process will not be repeated here.
[0106] Step 3-2: According to Formula 5, substitute the values of equilibrium time t, flow section height h2 at the second equilibrium velocity, second equilibrium height H2, fracture width W, and second equilibrium velocity V2 into the corresponding positions to determine the value of K2 under the second fracture pressure. According to the relationship between coefficient K2 and average sand ratio S shown in Formula 4, substitute coefficient K2, fracturing fluid density ρ, and mixed fluid density ρ sc , particle settling uniform velocity U P And the calculated value of the second equilibrium height H2 is used to determine the second equilibrium sand ratio.
[0107] When the equilibrium time is t=9.84 min, according to formulas 4 and 5, the second average sand ratio is S2=9%.
[0108] Step 4: Determine the amount of temporary plugging agent based on the construction displacement, balance time, the first average sand ratio and the second average sand ratio.
[0109] In this step, the values of the first average sand ratio and construction displacement obtained in step 1, as well as the values of the balance time and the second average sand ratio calculated in steps 2 and 3, are substituted into formula 6 to calculate the product of the construction displacement, balance time and increment of the average sand ratio to obtain the volume of the temporary plugging agent. The temporary plugging agent volume and the temporary plugging agent density are multiplied to obtain the temporary plugging agent dosage, also known as the mass of the temporary plugging agent.
[0110] The density of the temporary plugging agent in step 4 is 1200kg / m 3 , the calculation process of step 4 is:
[0111] The volume of temporary plugging agent is calculated based on Formula 6: X = Qt(S2-S1) = 3 × 9.84 × 0.01 = 0.2952 m 3 ; Calculate the temporary plugging agent dosage based on formula 7: M = ρ Z X=0.2852×1200=354.24kg.
[0112] In a possible implementation, formulas 6 and 7 are combined to perform a comprehensive calculation, that is, the temporary plugging agent dosage is M = Qt (S2-S1) ρ Z =3×9.84*0.01*1200=354.24kg.
[0113] In this exemplary embodiment, the M determined at this time indicates the amount of temporary plugging agent used for a single side seam, and the total amount of temporary plugging agent used is M. Z =354×2=708.48kg.
[0114] The method for determining the amount of temporary plugging agent provided by this exemplary embodiment can ensure the accuracy of the determined amount of temporary plugging agent through precise calculation; and the method is applicable to the application of various temporary plugging agents and has a wide range of applications; in addition, the parameter data used for calculation is the real data of the mining site, and the amount of fracturing agent used in the construction process can be calculated in real time. The matching degree between the amount of temporary plugging agent and the actual situation is ensured, and data can be obtained in real time to achieve real-time adjustment of the construction plan.
[0115] The present application also provides a device for determining the amount of temporary plugging agent, see Figure 3 , the device comprises:
[0116] The first determination module 301 is used to determine the equilibrium time according to the first fracture pressure and the first average sand ratio, wherein the first fracture pressure refers to the pressure in the fracture before adding the temporary plugging agent;
[0117] The second determination module 302 is used to determine a second average sand ratio according to a second fracture pressure and a balance time, wherein the second fracture pressure refers to the pressure in the fracture after adding a temporary plugging agent;
[0118] The third determination module 303 is used to determine the amount of temporary plugging agent based on the construction displacement, the balance time, the first average sand ratio and the second average sand ratio.
[0119] In a possible implementation, the first determination module 301 is configured to determine a first equilibrium height based on a first seam pressure; and determine an equilibrium time based on the first equilibrium height and a first average sand ratio.
[0120] In one possible implementation, the first determination module 301 is used to determine the first particle sedimentation equilibrium resistance velocity based on the relationship between the pressure in the slit and the particle sedimentation equilibrium resistance velocity and the first slit pressure; determine the first equilibrium flow velocity based on the relationship between the particle sedimentation equilibrium resistance velocity and the equilibrium flow velocity and the first particle sedimentation equilibrium resistance velocity; and determine the first equilibrium height based on the first equilibrium flow velocity.
[0121] In a possible implementation, the first determination module 301 is used to determine the first equilibrium flow section height at the first equilibrium flow rate based on the first equilibrium flow rate and the construction displacement; and determine the first equilibrium height based on the first equilibrium flow section height and the fracture height of the fracturing crack.
[0122] In a possible implementation, the device further includes: an additional module, configured to determine an expected additional pressure after adding the temporary plugging agent; and to use the sum of the expected additional pressure and the first slit pressure as the second slit pressure.
[0123] In a possible implementation, the device also includes: an acquisition module, which is used to obtain the fracturing crack morphology parameters and fracturing construction parameters of the target well before adding the temporary plugging agent based on the single well geological data of the target well and the production dynamic data of the adjacent wells, the fracturing crack morphology parameters including the fracture height of the fracturing crack, and the fracturing construction parameters including the first fracture pressure and the first average sand ratio.
[0124] In a possible implementation, the third determination module 303 is used to take the difference between the second average sand ratio and the first average sand ratio as the increment of the average sand ratio; determine the volume of the temporary plugging agent based on the construction displacement, the balance time and the increment of the average sand ratio; and determine the amount of the temporary plugging agent based on the volume of the temporary plugging agent and the density of the temporary plugging agent.
[0125] Above Figure 3 When the device provided realizes its functions, only the division of the above-mentioned functional modules is used as an example for illustration. In practical applications, the above-mentioned functions can be assigned to different functional modules as needed, that is, the internal structure of the device is divided into different functional modules to complete all or part of the functions described above. In addition, the device and method embodiments provided in the above embodiments belong to the same concept, and their specific implementation process is detailed in the method embodiment, which will not be repeated here.
[0126] A computer-readable storage medium is provided, in which at least one program code is stored. The program code is loaded and executed by a processor to implement any method for determining the amount of a temporary plugging agent in a method embodiment.
[0127] Optionally, the computer-readable storage medium may be a read-only memory (ROM), a random access memory (RAM), a compact disc (CD-ROM), a magnetic tape, a floppy disk, an optical data storage device, etc.
[0128] In an exemplary embodiment, a computer program or a computer program product is also provided, wherein at least one computer instruction is stored in the computer program or the computer program product, and the at least one computer instruction is loaded and executed by a processor to enable a computer to implement any of the above methods for determining the dosage of a temporary plugging agent.
[0129] See also Figure 4, is a schematic diagram of the structure of a computer device provided in an embodiment of the present application. The computer device may have relatively large differences due to different configurations or performances, and may include one or more processors (Central Processing Units, CPU) 401 and one or more memories 402, wherein the one or more memories 402 store at least one program instruction, and the at least one program instruction is loaded and executed by the one or more processors 401 to implement the method for determining the amount of temporary plugging agent provided in the above-mentioned various method embodiments. Of course, the electronic device may also have components such as a wired or wireless network interface, a keyboard, and an input and output interface for input and output. The electronic device may also include other components for realizing the functions of the device, which will not be described in detail here.
[0130] It should be understood that in the various embodiments of the present application, the size of the serial number of each process does not mean the order of execution. The execution order of each process should be determined by its function and internal logic, and should not constitute any limitation on the implementation process of the embodiments of the present application.
[0131] The term "at least one" in this application means one or more, and the term "plurality" in this application means two or more.
[0132] It should be understood that the terms used in the description of various examples herein are only for describing specific examples and are not intended to be limiting. As used in the description of various examples and the appended claims, the singular forms "a", "an", and "the" are intended to include the plural forms as well, unless the context clearly indicates otherwise.
[0133] It should also be understood that the term “comprise” (also known as “includes,” “including,” “comprises” and / or “comprising”) when used in this specification specifies the presence of stated features, integers, steps, operations, elements, and / or components, but does not preclude the presence or addition of one or more other features, integers, steps, operations, elements, components, and / or groups thereof.
[0134] It should be understood that determining B based on A does not mean determining B only based on A. B can also be determined based on A and / or other information.
[0135] It should also be understood that the terms "if" and "if" may be interpreted to mean "when" or "upon" or "in response to determining" or "in response to detecting." Similarly, the phrases "if it is determined that ..." or "if [a stated condition or event] is detected" may be interpreted to mean "upon determining that ..." or "in response to determining that ..." or "upon detecting [a stated condition or event]" or "in response to detecting [a stated condition or event]," depending on the context.
[0136] It should also be understood that the references to "one embodiment", "an embodiment", or "a possible implementation" throughout the specification mean that specific features, structures, or characteristics related to the embodiment or implementation are included in at least one embodiment of the present application. Therefore, the references to "in one embodiment" or "in an embodiment", or "a possible implementation" throughout the specification do not necessarily refer to the same embodiment. In addition, these specific features, structures, or characteristics may be combined in any suitable manner in one or more embodiments.
[0137] The above are only optional embodiments of the present application, but the protection scope of the present application is not limited thereto. Any changes or substitutions that can be easily conceived by any technician familiar with the technical field within the technical scope disclosed in the present application should be covered by the protection scope of the present application.
Claims
1. A method for determining the dosage of a temporary plugging agent, characterized in that: The method comprises: Determining a first particle settling equilibrium resistance velocity based on a relationship between the intra-fracture pressure and the particle settling equilibrium resistance velocity and a first intra-fracture pressure, wherein the first intra-fracture pressure refers to the pressure in the fracturing fracture before adding a temporary plugging agent; Determining a first equilibrium flow velocity based on a relationship between a particle settling equilibrium resistance velocity and an equilibrium flow velocity and the first particle settling equilibrium resistance velocity; Determine a first equilibrium flow section height at the first equilibrium flow rate based on the first equilibrium flow rate and the construction displacement; determine a first equilibrium height based on the first equilibrium flow section height and the fracture height of the hydraulic fracture; determining an equilibrium time based on the first equilibrium height and the first average sand ratio; Determining a second average sand ratio according to a second intra-fracture pressure and the equilibrium time, wherein the second intra-fracture pressure refers to the pressure in the hydraulic fracture after the temporary plugging agent is added; taking the difference between the second average sand ratio and the first average sand ratio as the increment of the average sand ratio; determining the volume of the temporary plugging agent based on the construction displacement, the balance time and the increment of the average sand ratio; Determining the amount of the temporary plugging agent based on the volume and density of the temporary plugging agent; The relationship between the internal pressure of the slit and the equilibrium resistance velocity of the particle settling is expressed by Formula 1: P refers to the pressure in the crack, in MPa; U refers to the particle settling equilibrium resistance velocity, in m / s; L refers to the length of the fracture, in m; ρ sc Refers to the density of the sand-liquid mixture, in g / cm 3 , the sand-liquid mixture refers to a mixture of sand and fracturing fluid; the W refers to the width of the fracturing crack, in m; The relationship between the particle settling equilibrium resistance velocity and the equilibrium flow velocity is expressed by Formula 2: The V refers to the equilibrium flow velocity, in m / s; the μ refers to the liquid viscosity, in mPa·s, and the liquid viscosity refers to the viscosity of the fracturing fluid; The first equilibrium height is determined based on the relationship between the equilibrium flow rate and the equilibrium height expressed by Formula 3: H refers to the equilibrium height of the sand bank under equilibrium state, in m; H0 refers to the height of the fracturing crack, in m; h refers to the flow section height at equilibrium, in m; Q refers to the construction displacement, in m 3 / min, V refers to the equilibrium flow rate, unit is m / s; The equilibration time is determined based on Formula 5: The t is the time when the sand bank reaches the equilibrium height; the H is the equilibrium height; the h is the flow section height at equilibrium; the Q is the construction displacement; the W is the width of the hydraulic fracture; and the K is a coefficient; The coefficient K is calculated based on Formula 4: The S refers to the average sand ratio; the U P It refers to the uniform velocity of particle settling, in m / s; ρ refers to the density of fracturing fluid, in kg / m 3 ; V refers to the equilibrium flow velocity, in m / s; The volume of the temporary plugging agent is determined based on Formula 6, and the amount of the temporary plugging agent is determined based on Formula 7: X = Qt (S2-S1) Formula 6; M = ρ Z X formula 7; S1 refers to the first average sand ratio before adding the temporary plugging agent, S2 refers to the second average sand ratio corresponding to the temporary plugging agent, and ρ Z Temporary plugging agent density, unit: kg / m 3 .
2. The method according to claim 1, characterized in that Before determining the second average sand ratio according to the second slit pressure and the equilibrium time, the method further includes: Determine the expected additional pressure after adding temporary plugging agent; The sum of the expected additional pressure and the first slit pressure is taken as the second slit pressure.
3. The method according to claim 1, characterized in that Before determining the equilibrium time, the method further includes: Based on the single well geological data of the target well and the production dynamic data of the adjacent wells, the fracturing crack morphological parameters and fracturing construction parameters of the target well before adding the temporary plugging agent are obtained, wherein the fracturing crack morphological parameters include the crack height of the fracturing crack, and the fracturing construction parameters include the first crack pressure and the first average sand ratio.
4. A device for determining the amount of temporary plugging agent, characterized in that: The device is used to implement the method for determining the amount of temporary plugging agent as described in any one of claims 1 to 3, and the device comprises: A first determination module is used to determine the equilibrium time according to a first intra-fracture pressure and a first average sand ratio, wherein the first intra-fracture pressure refers to the pressure in the fracturing fracture before adding a temporary plugging agent; a second determination module, configured to determine a second average sand ratio according to a second intra-fracture pressure and the equilibrium time, wherein the second intra-fracture pressure refers to the pressure in the hydraulic fracture after the temporary plugging agent is added; The third determination module is used to determine the amount of temporary plugging agent based on the construction displacement, the balance time, the first average sand ratio and the second average sand ratio.
5. A computer device, characterized in that: The computer device includes a processor and a memory, wherein at least one computer program is stored in the memory; the at least one computer program is loaded and executed by one or more of the processors, so that the computer implements the method for determining the amount of temporary plugging agent according to any one of claims 1 to 3.
6. A computer-readable storage medium, characterized in that: At least one program code is stored in the computer-readable storage medium, and the program code is loaded and executed by the processor to enable the computer to implement the method for determining the amount of temporary plugging agent according to any one of claims 1 to 3.
Citation Information
Patent Citations
Method for guiding plugging agents into oil well for water plugging by radial well
CN108643856A
Method for controlling use amount of deflection fracturing temporary blocking agent
CN109267985A
Calculation method for dosage of temporary blocking particles for deflection fracturing
CN110685657A
Multi-well-site flow field reconstruction scale fracturing method
CN112523736A
Optimized design method for temporary blocking agent to promote uniform expansion of fractures produced by fracturing in horizontal wells
US20200386081A1