Rail transit vehicle impoundment method, equipment, and storage medium
By obtaining the fault type and location, the vehicle detaining data is generated and sent to the automatic monitoring system, which solves the problems of subjectivity and low degree of automation of the detaining method in the existing technology, realizes timely and accurate detaining of rail transit, and improves fault detection. treatment effect.
Patent Information
- Application Number
- CN202211710845.0
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2022-12-29
- Publication Date
- 2024-10-11
- Estimated Expiration
- 2042-12-29
AI Technical Summary
The existing train detaining methods of rail transit are highly subjective and have a low degree of automation, resulting in low work efficiency. The reliance on manual dispatch results in untimely detaining of trains, which affects wider operations.
By obtaining the fault type, fault impact scope and real-time train location, the train detainment data is generated, including the train detainment time and location, and the data is sent to the automatic train monitoring system to realize automatic train detainment and avoid manual operation delays.
It achieves timely and accurate vehicle detainment under various fault scenarios, improves the fault handling effect, and reduces the wider impact caused by manual operation delays.
Smart Images

Figure CN115805980B_ABST
Abstract
Description
Technical Field
[0001] The present application relates to the field of rail transit technology, and in particular to a method, device, and storage medium for detaining a vehicle in rail transit. Background Art
[0002] In the existing rail transit operation and dispatching, in order to prevent the further spread of the impact of the fault, the first thing the dispatcher has to do is to detain the train, that is, by issuing dispatching instructions, the subsequent trains at the fault point are detained in turn, so that each train is temporarily detained in the section or station. The dispatcher can predict the time caused by the fault by his own operation, determine the scope and location of the detainment.
[0003] The above existing adjustment methods are relatively subjective, and the adjustment effect is closely related to the work experience of the dispatcher. In addition, the existing train adjustment method contacts the driver and the station by phone to manually adjust the train arrival and departure time, which has a low degree of automation. The existing train detention method has the problem of low work efficiency. Summary of the invention
[0004] In order to solve the above-mentioned technical defects, the present application provides a rail transit vehicle detention method, equipment, and storage medium.
[0005] In a first aspect, the present application provides a method for impounding a vehicle in rail transit, the method comprising:
[0006] Obtaining the fault type, fault impact range and real-time train position, wherein the fault type is a train fault or an equipment fault;
[0007] Generate train detention data according to the fault type, fault impact range and real-time train position; the train detention data includes: train detention time and train detention location;
[0008] The vehicle detention data is sent to the train automatic monitoring system, so that the train automatic monitoring system detains the vehicle at the detaining time and the detaining location.
[0009] Optionally, generating train detention data according to the fault type, fault impact range and real-time train position includes:
[0010] Determine an ordered set of affected trains according to the fault type, the fault impact range and the real-time train position; wherein the elements in the ordered set are sorted from early to late according to the departure time of the corresponding trains;
[0011] Taking the first element in the ordered set as the current element;
[0012] Determine the location where the train corresponding to the current element is detained;
[0013] Determine the train detention time corresponding to the current element;
[0014] Determine whether the train corresponding to the next element of the current element in the ordered set is affected;
[0015] If the train corresponding to the next element is affected, the next element is used as the current element, and the step of determining the train detention location corresponding to the current element and subsequent steps are repeated.
[0016] Optionally, determining an ordered set of affected trains according to the fault type, the fault impact range and the real-time train position includes:
[0017] If the fault type is a train fault, the faulty train is taken as the first element of the ordered set; if the fault type is an equipment fault, the first train that passes through the faulty equipment after the fault occurs is taken as the first element of the ordered set;
[0018] A subsequent train is taken as another element of the ordered set, the real-time train position of the subsequent train is within the fault impact range, and the departure time of the subsequent train is later than the departure time of the first element.
[0019] Optionally, determining whether a train corresponding to the next element of the current element in the ordered set is affected includes:
[0020] Obtain the first scheduled arrival and departure time of the train corresponding to the next element of the current element in the ordered set arriving at the nearest platform;
[0021] Get the second scheduled arrival and departure time of the current element at the nearest platform;
[0022] If the second planned arrival and departure time do not satisfy the minimum tracking interval with the first planned arrival and departure time, it is determined that the train corresponding to the next element is affected, and the nearest platform is used as the conflicting platform corresponding to the next element.
[0023] Optionally, the current element is the first element in the ordered set;
[0024] The step of determining the detaining location of the train corresponding to the current element includes:
[0025] If the fault type is a train fault, when the train corresponding to the current element is capable of running to the platform, the train detention location is the next platform; when the train corresponding to the current element is unable to run to the platform, the train detention location is the temporary parking location in the section;
[0026] If the fault type is equipment failure, when there is an idle platform between the train corresponding to the current element and the faulty equipment, the vehicle detention location is the idle platform farthest from the train corresponding to the current element; when there is no idle platform between the train corresponding to the current element and the faulty equipment, the vehicle detention location is the temporary parking location in the section.
[0027] Optionally, the current element is not the first element in the ordered set;
[0028] The step of determining the detaining location of the train corresponding to the current element includes:
[0029] If there is an idle platform between the train corresponding to the current element and the train corresponding to the previous element, the location of the train detention is the platform closest to the train corresponding to the previous element;
[0030] If there is no vacant platform between the train corresponding to the current element and the train corresponding to the previous element, the vehicle detention location is a temporary parking location in the section.
[0031] Optionally, determining the train detention time of the train corresponding to the current element includes:
[0032] Determine the train detention time t = T corresponding to the current element next +t interval -T pre ;
[0033] Among them, T next is the planned time of the train corresponding to the current element at the conflicting platform corresponding to the current element, t interval is the minimum tracking interval, T pre It is the planned time for the train corresponding to the previous element of the current element to arrive at the conflicting platform corresponding to the current element.
[0034] Optionally, the method further comprises:
[0035] Estimated failure end time;
[0036] Continuously monitor the status of the fault;
[0037] If the fault is determined to be restored according to the status within the fault end time, the rail transit vehicle detention method is terminated.
[0038] In a second aspect of the present application, an electronic device is provided, comprising:
[0039] Memory;
[0040] Processor; and
[0041] Computer programs;
[0042] The computer program is stored in the memory and is configured to be executed by the processor to implement the method as described in the first aspect above.
[0043] According to a third aspect of the present application, a computer-readable storage medium is provided, on which a computer program is stored; the computer program is executed by a processor to implement the method described in the first aspect above.
[0044] The present application provides a rail transit vehicle detention method, device, and storage medium, the method comprising: obtaining a fault type, a fault impact range, and a real-time train position, the fault type being a train fault or an equipment fault; generating vehicle detention data according to the fault type, the fault impact range, and the real-time train position; the vehicle detention data comprising: a vehicle detention time and a vehicle detention location; and sending the vehicle detention data to a train automatic monitoring system so that the train automatic monitoring system detains the vehicle at the vehicle detention time and location.
[0045] This application generates vehicle detention data based on the fault type, fault impact range and real-time train position; the vehicle detention data is sent to the train automatic monitoring system, ensuring that the vehicle detention data can be timely and accurately detained in scenarios caused by various fault types, avoiding manual operation that fails to detain the vehicle in time and causing a wider impact, thereby improving the fault handling effect.
[0046] In addition, in one implementation, an ordered set of affected trains is determined based on the fault type, fault impact range and real-time train position, and train detention data is generated based on the ordered set of affected trains, thereby achieving timely and accurate train detention, avoiding wider impact caused by manual operation when not detaining trains in time, and improving the fault handling effect.
[0047] In addition, in one implementation, the ordered set of affected trains includes the faulty train and its subsequent trains, or the first train that passes through the faulty equipment after the fault occurs and its subsequent trains, which ensures the accuracy of the ordered set of detained trains, achieves timely and accurate detention of trains, avoids wider impact caused by manual operation when detaining trains in a timely manner, and improves the fault handling effect.
[0048] In addition, in one implementation, a scheme for determining the affected trains is clarified, ensuring accurate determination of the affected trains, thereby ensuring timely and accurate train detention, avoiding wider impacts caused by manual operation without timely train detention, and improving fault handling effects.
[0049] In addition, in one implementation, the method for determining the location of the vehicle impoundment of the first element in the ordered set is clarified, the accuracy of the vehicle impoundment location is ensured, and timely and accurate vehicle impoundment is achieved, thereby avoiding the impact of a wider range caused by manual operation when the vehicle is not impounded in time, and improving the fault handling effect.
[0050] In addition, in one implementation, the method for determining the location of vehicle impoundment that is not the first element in an ordered set is clarified, thereby ensuring the accuracy of the location of vehicle impoundment, achieving timely and accurate vehicle impoundment, avoiding the impact of a wider range caused by manual operation without timely impounding the vehicle, and improving the effectiveness of fault handling.
[0051] In addition, in one implementation, the method for determining the vehicle seizure time is clarified, the accuracy of the vehicle seizure time is guaranteed, and timely and accurate vehicle seizure is achieved, thereby avoiding the impact of a wider range caused by manual operation without timely seizure of the vehicle and improving the fault handling effect.
[0052] In addition, in one implementation, if the fault is determined to be restored within the fault end time, the rail transit vehicle detention method is terminated, thereby achieving timely and accurate vehicle detention, avoiding a wider range of impacts caused by manual operation without timely vehicle detention, and improving the fault handling effect.
[0053] The electronic device provided by the present application has a computer program on which a processor executes to generate vehicle detention data according to the fault type, the fault impact range and the real-time train position; the vehicle detention data is sent to the train automatic monitoring system, thereby ensuring that the vehicle detention data can be used in the face of vehicle detention scenarios caused by various fault types, and timely and accurate vehicle detention can be carried out, thereby avoiding manual operation that fails to detain the vehicle in a timely manner and causing a wider range of impacts, thereby improving the fault handling effect.
[0054] The computer-readable storage medium provided by the present application has a computer program thereon which is executed by a processor to generate vehicle detention data according to the fault type, fault impact range and real-time train position; the vehicle detention data is sent to the train automatic monitoring system, thereby ensuring that the vehicle detention data can be faced with vehicle detention scenarios caused by various fault types, and timely and accurate vehicle detention is carried out, thereby avoiding manual operation that fails to detain the vehicle in a timely manner and causing a wider range of impact, thereby improving the fault handling effect. BRIEF DESCRIPTION OF THE DRAWINGS
[0055] The drawings described herein are used to provide a further understanding of the present application and constitute a part of the present application. The illustrative embodiments of the present application and their descriptions are used to explain the present application and do not constitute an improper limitation on the present application. In the drawings:
[0056] Figure 1 A schematic diagram of a flow chart of a method for impounding a vehicle in rail transit provided in an embodiment of the present application;
[0057] Figure 2 A schematic diagram of an original operation diagram provided in an embodiment of the present application;
[0058] Figure 3 A schematic diagram of a vehicle seizure in a device failure scenario provided in an embodiment of the present application;
[0059] Figure 4Schematic diagram of the vehicle seizure for temporary parking in a section provided in an embodiment of the present application. DETAILED DESCRIPTION
[0060] In order to make the technical solutions and advantages in the embodiments of the present application more clearly understood, the exemplary embodiments of the present application are further described in detail below in conjunction with the accompanying drawings. Obviously, the described embodiments are only part of the embodiments of the present application, rather than an exhaustive list of all the embodiments. It should be noted that the embodiments in the present application and the features in the embodiments can be combined with each other without conflict.
[0061] In the process of implementing this application, the inventor found that the existing adjustment method is relatively subjective, and the adjustment effect is closely related to the work experience of the dispatcher. In addition, the existing train adjustment method contacts the driver and the station by phone to manually adjust the train arrival and departure time, which has a low degree of automation. The existing train detention method has the problem of low work efficiency.
[0062] In response to the above problems, an embodiment of the present application provides a rail transit vehicle detention method, device, and storage medium, the method comprising: obtaining a fault type, a fault impact range, and a real-time train position, the fault type being a train fault or an equipment fault; generating vehicle detention data according to the fault type, the fault impact range, and the real-time train position; the vehicle detention data comprising: vehicle detention time and vehicle detention location; and sending the vehicle detention data to a train automatic monitoring system so that the train automatic monitoring system detains the vehicle at the vehicle detention time and location.
[0063] See also Figure 1 The implementation process of a rail transit vehicle detention method provided in this embodiment is as follows:
[0064] 101, obtain the fault type, fault impact range and real-time train position.
[0065] Among them, the fault type is train failure or equipment failure.
[0066] In addition, this step can also confirm the location of the fault, the start time of the fault, the estimated end time of the fault, the line station type data, train tracking data, etc.
[0067] 102. Generate train detention data according to the fault type, fault impact range and real-time train position.
[0068] Among them, the vehicle seizure data includes: the time and location of seizure.
[0069] This step can be achieved by following the steps below:
[0070] 1. Determine the ordered set of affected trains based on the fault type, fault impact range, and real-time train location.
[0071] Among them, the elements in the ordered set are sorted from early to late according to the departure time of their corresponding trains.
[0072] In the specific implementation,
[0073] 1) If the fault type is a train fault, the faulty train is taken as the first element of the ordered set. If the fault type is an equipment fault, the first train that passes through the faulty equipment after the fault occurs is taken as the first element of the ordered set.
[0074] 2) Treat the subsequent train as the other element of the ordered set.
[0075] Among them, the real-time train position of the subsequent train is within the fault impact range, and the departure time of the subsequent train is later than the departure time of the first element.
[0076] That is to say, the ordered set of detained trains includes multiple elements, and each element is arranged according to the departure time. The first element is the faulty train or the first train that passes the faulty equipment after the fault occurs. The second element and the following elements are all subsequent trains of the first element, and they are sorted from small to large according to the time difference between the departure time and the departure time of the train corresponding to the first element.
[0077] 2. Set the first element in the ordered set as the current element.
[0078] 3. Determine the location where the train corresponding to the current element is detained.
[0079] Depending on whether the current element is the first element in the ordered set, the scheme for determining the location of the vehicle seizure is different.
[0080] 1) If the current element is the first element in the ordered set, the implementation process of determining the impoundment location of the train corresponding to the current element is:
[0081] If the fault type is a train fault, then
[0082] (1) When the train corresponding to the current element is able to run to the platform, the train is detained at the next station.
[0083] (2) When the train corresponding to the current element is unable to run to the platform, the train detention location is the temporary parking location in the section.
[0084] If the fault type is a device fault, then
[0085] (1) When there is an idle platform between the train corresponding to the current element and the faulty equipment, the location for the train detention is the idle platform farthest from the train corresponding to the current element.
[0086] (2) When there is no vacant platform between the train corresponding to the current element and the faulty equipment, the train detention location is the temporary parking location in the section.
[0087] 2) If the current element is not the first element in the ordered set, the process of determining the impoundment location of the train corresponding to the current element is:
[0088] If there is an idle platform between the train corresponding to the current element and the train corresponding to the previous element, the train detention location is the platform closest to the train corresponding to the previous element.
[0089] If there is no vacant platform between the train corresponding to the current element and the train corresponding to the previous element, the train detention location is the temporary parking location in the section.
[0090] 4. Determine the train detention time corresponding to the current element.
[0091] Determine the train detention time t = T corresponding to the current element next +t interval -T pre .
[0092] Among them, T next is the planned time of the train corresponding to the current element at the conflicting platform corresponding to the current element, t interval is the minimum tracking interval, T pre It is the planned time for the train corresponding to the previous element of the current element to arrive at the conflicting platform corresponding to the current element.
[0093] 5. Determine whether the train corresponding to the next element of the current element in the ordered set is affected.
[0094] For example
[0095] 1) Get the first scheduled arrival and departure time of the train corresponding to the next element of the current element in the ordered set arriving at the nearest platform.
[0096] 2) Get the second planned arrival and departure time of the current element at the nearest platform.
[0097] 3) If the second planned arrival and departure time do not meet the minimum tracking interval with the first planned arrival and departure time, it is determined that the train corresponding to the next element is affected, and the nearest platform is used as the conflicting platform corresponding to the next element.
[0098] 6. If the train corresponding to the next element is affected, take the next element as the current element and repeat step 3 to determine the train detention location corresponding to the current element and subsequent steps.
[0099] 103. Send the vehicle detention data to the train automatic monitoring system.
[0100] The Automatic Train Supervision (ATS) system will detain trains at the time and location based on the detention data.
[0101] During the execution of the above process, the fault end time is also estimated (which can be estimated in step 101), and the fault status is continuously monitored. If the fault is restored according to the status within the fault end time, the rail transit vehicle detention method is terminated.
[0102] The method provided in this embodiment can confirm the location of the fault and the duration of the vehicle detention according to the fault event, obtain the real-time location of the train and the line station type data, generate the vehicle detention data corresponding to the fault time, and send it to ATS for execution. Continue to obtain the fault status, and if the fault is restored within the predicted time, the adjustment is completed. If the fault has not been restored when the time reaches the expected time, update the expected fault recovery time, and continue to call the intelligent vehicle detention algorithm on this basis.
[0103] The method provided in this embodiment can detain a train for various scenarios such as train failure or equipment failure. The implementation process in the scenario of train failure or equipment failure is described again below.
[0104] If no fault occurs, each train follows the following Figure 2 When a train failure occurs,
[0105] 1. Get relevant data.
[0106] The relevant data at least includes the fault type, fault impact range and real-time train position.
[0107] For example: fault type Type, fault start time T start , Estimated fault end time T end , train tracking data TI = {TI1, TI2, ..., TI n}, fault impact scope and real-time train location.
[0108] T start The time when the failure occurs is a certain point in time.
[0109] T end is the time when the fault ends, based on the start time and the estimated duration of the fault t last OK, that is, T end =T start +t last .
[0110] The train tracking data TI is the physical section location of the locomotive of the PN train.
[0111] 2. Determine the ordered set of affected trains based on the fault type, fault impact range and real-time train position.
[0112] According to the fault type, fault impact range and real-time train position, determine the ordered set of affected trains TN = {TN1, TN2, …, TN m}.
[0113] In the train failure scenario, the faulty train is the first element of the ordered set TN1, and the subsequent trains in the direction of the train are the trains that may be affected. The trains have the same running direction as the train corresponding to TN1 and the departure time is T s The train whose departure time is greater than the departure time of the corresponding train of TN1 is the subsequent train.
[0114] TN m Including train number and train departure time.
[0115] 3. Set the first element TN1 in the ordered set as the current element.
[0116] 4. Determine the location where the train corresponding to the current element is detained.
[0117] Determine whether the faulty train TN1 can run to the platform. If it can run to the platform, the train will be detained at the next platform. If it cannot run to the platform, the train will be detained at the temporary parking location in the section, that is, it will be temporarily parked in the section.
[0118] 5. Determine the train detention time corresponding to the current element.
[0119] Check whether the planned arrival and departure time of the train at the subsequent station is consistent with the planned arrival and departure time of the previous train and whether it meets the minimum tracking interval t interval Find the first conflicting station that does not meet the tracking interval, and the planned time of the preceding vehicle is T pre , the planned time of the following vehicle is T next , the vehicle seizure time t = T next +t interval -T pre .
[0120] 6. Determine whether the train corresponding to the next element of the current element in the ordered set is affected.
[0121] For example
[0122] 1) Get the first scheduled arrival and departure time of the train corresponding to the next element of the current element in the ordered set arriving at the nearest platform.
[0123] 2) Get the second planned arrival and departure time of the current element at the nearest platform.
[0124] 3) If the second planned arrival and departure time do not meet the minimum tracking interval with the first planned arrival and departure time, it is determined that the train corresponding to the next element is affected, and the nearest platform is used as the conflicting platform corresponding to the next element.
[0125] 7. If the train corresponding to the next element is affected, take the next element as the current element and repeat step 4 to determine the train detention location corresponding to the current element and subsequent steps.
[0126] For example, if the train corresponding to the second element is affected and the current element becomes the second element, then determine whether there is an idle platform between the train corresponding to the second element and the train corresponding to the first element. If there is an idle platform, the vehicle detention location is the platform closest to the train corresponding to the previous element, that is, the vehicle is detained at the platform closest to the previous vehicle. If there is no idle platform, the vehicle detention location is a temporary parking location in the section, that is, temporary parking in the section.
[0127] Determine the train detention time t=T corresponding to the current element (i.e., the second element) next +t interval -T pre .
[0128] Among them, T next is the planned time for the train corresponding to the current element (i.e., the second element) to arrive at the conflicting platform corresponding to the current element (i.e., the second element), t interval is the minimum tracking interval, T pre It is the planned time of the train corresponding to the previous element (ie, the first element) of the current element (ie, the second element) at the conflicting platform corresponding to the current element (ie, the second element).
[0129] Then, in the ordered set, the train corresponding to the next element of the current element (i.e., the third element) is determined to be affected, and so on, until all elements in the ordered set are confirmed to be affected.
[0130] When a device failure occurs,
[0131] 1. Get relevant data.
[0132] The relevant data at least includes the fault type, fault impact range and real-time train position.
[0133] For example: fault type Type, fault start time T start , Estimated fault end time T end and train tracking data TI = {TI1, TI2, ..., TI n}, fault impact scope and real-time train location.
[0134] T startThe time when the failure occurs is a certain point in time.
[0135] T end is the time when the fault ends, based on the start time and the estimated duration of the fault t last OK, that is, T end =T start +t last .
[0136] The train tracking data TI is the physical section location of the locomotive of the PN train.
[0137] 2. Determine the ordered set of affected trains based on the fault type, fault impact range and real-time train position.
[0138] According to the fault type, fault impact range and real-time train position, determine the ordered set of affected trains TN = {TN1, TN2, …, TN m}.
[0139] In the equipment failure scenario, the first train that passes the faulty equipment after the failure is taken as the first element of the ordered set TN1, and the subsequent trains in the running direction of the train are the trains that may be affected. The running direction is the same as that of TN1, and the departure time is T s The train whose departure time is greater than the departure time of the corresponding train of TN1 is the subsequent train.
[0140] TN m Including train number and train departure time.
[0141] 3. Take the first element TN1 in the ordered set as the current element.
[0142] 4. Determine the location where the train corresponding to the current element is detained.
[0143] Determine whether there is an idle platform between the faulty train TN1 and the faulty equipment. If there is an idle platform, the vehicle will be detained at the idle platform farthest from the train corresponding to TN1, that is, the vehicle will be detained at the farthest platform. If there is no idle platform, the vehicle will be detained at the temporary parking location in the section, that is, it will be temporarily parked in the section.
[0144] 5. Determine the train detention time corresponding to the current element.
[0145] Check whether the planned arrival and departure time of the train at the subsequent station is consistent with the planned arrival and departure time of the previous train and whether it meets the minimum tracking interval t interval Find the first conflicting station that does not meet the tracking interval, and the planned time of the preceding vehicle is T pre , the planned time of the following vehicle is T next , the vehicle seizure time t = T next +t interval-T pre .
[0146] 6. Determine whether the train corresponding to the next element of the current element in the ordered set is affected.
[0147] For example
[0148] 1) Get the first scheduled arrival and departure time of the train corresponding to the next element of the current element in the ordered set arriving at the nearest platform.
[0149] 2) Get the second planned arrival and departure time of the current element at the nearest platform.
[0150] 3) If the second planned arrival and departure time do not meet the minimum tracking interval with the first planned arrival and departure time, it is determined that the train corresponding to the next element is affected, and the nearest platform is used as the conflicting platform corresponding to the next element.
[0151] 7. If the train corresponding to the next element is affected, take the next element as the current element and repeat step 4 to determine the train detention location corresponding to the current element and subsequent steps.
[0152] For example, if the train corresponding to the second element is affected and the current element becomes the second element, then determine whether there is an idle platform between the train corresponding to the second element and the train corresponding to the first element. If there is an idle platform, the vehicle detention location is the platform closest to the train corresponding to the previous element, that is, the vehicle is detained at the platform closest to the previous vehicle. If there is no idle platform, the vehicle detention location is a temporary parking location in the section, that is, temporary parking in the section.
[0153] Determine the train detention time t=T corresponding to the current element (i.e., the second element) next +t interval -T pre .
[0154] Among them, T next is the planned time for the train corresponding to the current element (i.e., the second element) to arrive at the conflicting platform corresponding to the current element (i.e., the second element), t interval is the minimum tracking interval, T pre It is the planned time of the train corresponding to the previous element (ie, the first element) of the current element (ie, the second element) at the conflicting platform corresponding to the current element (ie, the second element).
[0155] Then, in the ordered set, the train corresponding to the next element of the current element (i.e., the third element) is determined to be affected, and so on, until all elements in the ordered set are confirmed to be affected.
[0156] The schematic diagram of vehicle seizure in the event of equipment failure is as follows: Figure 3 The schematic diagram of the train being detained when a train with a faulty switch stops temporarily is as shown in the figure below. Figure 4 shown.
[0157] The rail transit vehicle detention method provided in this embodiment generates vehicle detention data according to the fault type, fault impact range and real-time train position; and sends the vehicle detention data to the train automatic monitoring system, thereby ensuring that the vehicle detention data can be used in the face of vehicle detention scenarios caused by various fault types, and timely and accurate vehicle detention can be carried out, thereby avoiding manual operation that fails to detain the vehicle in time and causing a wider range of impact, thereby improving the fault handling effect.
[0158] Based on the same inventive concept of the rail transit vehicle detention method, this embodiment provides an electronic device, which includes: a memory, a processor, and a computer program.
[0159] The computer program is stored in the memory and is configured to be executed by the processor to implement the above-mentioned rail transit vehicle detention method.
[0160] Specifically,
[0161] Obtain the fault type, fault impact range and real-time train position. The fault type is either a train fault or an equipment fault.
[0162] The train detention data is generated based on the fault type, fault impact range and real-time train location. The train detention data includes: train detention time and train detention location.
[0163] The vehicle detention data is sent to the train automatic monitoring system so that the train automatic monitoring system can detain the vehicle at the detention time and location.
[0164] Optionally, train detention data is generated based on the fault type, fault impact range and real-time train position, including:
[0165] According to the fault type, fault impact range and real-time train position, an ordered set of affected trains is determined, wherein the elements in the ordered set are sorted from early to late according to the departure time of the corresponding trains.
[0166] Sets the first element in the sorted set as the current element.
[0167] Determine the detaining location of the train corresponding to the current element.
[0168] Determine the train detention time corresponding to the current element.
[0169] Determine whether the train corresponding to the next element of the current element in the ordered set is affected.
[0170] If the train corresponding to the next element is affected, the next element is used as the current element, and the step of determining the train detention location corresponding to the current element and subsequent steps are repeated.
[0171] Optionally, determining an ordered set of affected trains according to the fault type, the fault impact range and the real-time train position includes:
[0172] If the fault type is a train fault, the faulty train is taken as the first element of the ordered set. If the fault type is an equipment fault, the first train that passes through the faulty equipment after the fault occurs is taken as the first element of the ordered set.
[0173] The subsequent train is regarded as the other element of the ordered set, the real-time train position of the subsequent train is within the fault impact range, and the departure time of the subsequent train is later than the departure time of the first element.
[0174] Optionally, determining whether a train corresponding to the next element of the current element in the ordered set is affected includes:
[0175] Get the first scheduled arrival and departure time of the train corresponding to the next element of the current element in the ordered set arriving at the nearest platform.
[0176] Get the second scheduled arrival and departure time of the current element at the nearest platform.
[0177] If the second planned arrival and departure time do not meet the minimum tracking interval with the first planned arrival and departure time, it is determined that the train corresponding to the next element is affected, and the nearest platform is used as the conflicting platform corresponding to the next element.
[0178] Optionally, the current element is the first element in the sorted set.
[0179] Determine the location of the train to be detained corresponding to the current element, including:
[0180] If the fault type is a train fault, when the train corresponding to the current element is capable of running to the platform, the train will be detained at the next platform. When the train corresponding to the current element is unable to run to the platform, the train will be detained at the temporary parking location in the section.
[0181] If the fault type is equipment fault, then if there is an idle platform between the train corresponding to the current element and the faulty equipment, the vehicle detention location is the idle platform farthest from the train corresponding to the current element. If there is no idle platform between the train corresponding to the current element and the faulty equipment, the vehicle detention location is the temporary parking location in the section.
[0182] Optionally, the current element is a non-first element in the sorted set.
[0183] Determine the location of the train to be detained corresponding to the current element, including:
[0184] If there is an idle platform between the train corresponding to the current element and the train corresponding to the previous element, the train detention location is the platform closest to the train corresponding to the previous element.
[0185] If there is no vacant platform between the train corresponding to the current element and the train corresponding to the previous element, the train detention location is the temporary parking location in the section.
[0186] Optionally, determining the train detention time corresponding to the current element includes:
[0187] Determine the train detention time t = T corresponding to the current element next +t interval -T pre .
[0188] Among them, T next is the planned time of the train corresponding to the current element at the conflicting platform corresponding to the current element, t interval is the minimum tracking interval, T pre It is the planned time for the train corresponding to the previous element of the current element to arrive at the conflicting platform corresponding to the current element.
[0189] Optionally, the method further comprises:
[0190] Estimated failure end time;
[0191] Continuously monitor the status of the fault;
[0192] If the fault is restored according to the status within the fault end time, the rail transit vehicle detention method is terminated.
[0193] The electronic device provided in this embodiment has a computer program executed by a processor to generate vehicle detention data according to the fault type, fault impact range and real-time train position; the vehicle detention data is sent to the train automatic monitoring system, which ensures that the vehicle detention data can be faced with various fault types. The vehicle detention scenarios can be timely and accurately detained, avoiding manual operation that fails to detain the vehicle in time and causing a wider range of impact, thereby improving the fault handling effect.
[0194] Based on the same inventive concept of the rail transit vehicle impoundment method, this embodiment provides a computer on which a computer program can be stored. The computer program is executed by a processor to implement the rail transit vehicle impoundment method.
[0195] Specifically,
[0196] Obtain the fault type, fault impact range and real-time train position. The fault type is either a train fault or an equipment fault.
[0197] The train detention data is generated based on the fault type, fault impact range and real-time train location. The train detention data includes: train detention time and train detention location.
[0198] The vehicle detention data is sent to the train automatic monitoring system so that the train automatic monitoring system can detain the vehicle at the detention time and location.
[0199] Optionally, train detention data is generated based on the fault type, fault impact range and real-time train position, including:
[0200] According to the fault type, fault impact range and real-time train position, an ordered set of affected trains is determined, wherein the elements in the ordered set are sorted from early to late according to the departure time of the corresponding trains.
[0201] Sets the first element in the sorted set as the current element.
[0202] Determine the detaining location of the train corresponding to the current element.
[0203] Determine the train detention time corresponding to the current element.
[0204] Determine whether the train corresponding to the next element of the current element in the ordered set is affected.
[0205] If the train corresponding to the next element is affected, the next element is used as the current element, and the step of determining the train detention location corresponding to the current element and subsequent steps are repeated.
[0206] Optionally, determining an ordered set of affected trains according to the fault type, the fault impact range and the real-time train position includes:
[0207] If the fault type is a train fault, the faulty train is taken as the first element of the ordered set. If the fault type is an equipment fault, the first train that passes through the faulty equipment after the fault occurs is taken as the first element of the ordered set.
[0208] The subsequent train is regarded as the other element of the ordered set, the real-time train position of the subsequent train is within the fault impact range, and the departure time of the subsequent train is later than the departure time of the first element.
[0209] Optionally, determining whether a train corresponding to the next element of the current element in the ordered set is affected includes:
[0210] Get the first scheduled arrival and departure time of the train corresponding to the next element of the current element in the ordered set arriving at the nearest platform.
[0211] Get the second scheduled arrival and departure time of the current element at the nearest platform.
[0212] If the second planned arrival and departure time do not meet the minimum tracking interval with the first planned arrival and departure time, it is determined that the train corresponding to the next element is affected, and the nearest platform is used as the conflicting platform corresponding to the next element.
[0213] Optionally, the current element is the first element in the sorted set.
[0214] Determine the location of the train to be detained corresponding to the current element, including:
[0215] If the fault type is a train fault, when the train corresponding to the current element is capable of running to the platform, the train will be detained at the next platform. When the train corresponding to the current element is unable to run to the platform, the train will be detained at the temporary parking location in the section.
[0216] If the fault type is equipment fault, then if there is an idle platform between the train corresponding to the current element and the faulty equipment, the vehicle detention location is the idle platform farthest from the train corresponding to the current element. If there is no idle platform between the train corresponding to the current element and the faulty equipment, the vehicle detention location is the temporary parking location in the section.
[0217] Optionally, the current element is a non-first element in the sorted set.
[0218] Determine the location of the train to be detained corresponding to the current element, including:
[0219] If there is an idle platform between the train corresponding to the current element and the train corresponding to the previous element, the train detention location is the platform closest to the train corresponding to the previous element.
[0220] If there is no vacant platform between the train corresponding to the current element and the train corresponding to the previous element, the train detention location is the temporary parking location in the section.
[0221] Optionally, determining the train detention time corresponding to the current element includes:
[0222] Determine the train detention time t = T corresponding to the current element next +t interval -T pre .
[0223] Among them, T next is the planned time of the train corresponding to the current element at the conflicting platform corresponding to the current element, t interval is the minimum tracking interval, T pre It is the planned time for the train corresponding to the previous element of the current element to arrive at the conflicting platform corresponding to the current element.
[0224] Optionally, the method further comprises:
[0225] Estimated failure end time;
[0226] Continuously monitor the status of the fault;
[0227] If the fault is restored according to the status within the fault end time, the rail transit vehicle detention method is terminated.
[0228] The computer-readable storage medium provided in this embodiment has a computer program executed by a processor to generate vehicle detention data according to the fault type, fault impact range and real-time train position; the vehicle detention data is sent to the train automatic monitoring system, thereby ensuring that the vehicle detention data can be faced with vehicle detention scenarios caused by various fault types, and timely and accurate vehicle detention is carried out, thereby avoiding manual operation that fails to detain the vehicle in a timely manner and causing a wider range of impact, thereby improving the fault handling effect.
[0229] Those skilled in the art will appreciate that the embodiments of the present application can be provided as methods, systems, or computer program products. Therefore, the present application can adopt the form of complete hardware embodiments, complete software embodiments, or embodiments in combination with software and hardware. Moreover, the present application can adopt the form of a computer program product implemented on one or more computer-usable storage media (including but not limited to disk storage, CD-ROM, optical storage, etc.) that contain computer-usable program code. The scheme in the embodiments of the present application can be implemented in various computer languages, for example, object-oriented programming language Java and literal scripting language JavaScript, etc.
[0230] The present application is described with reference to the flowcharts and / or block diagrams of the methods, devices (systems), and computer program products according to the embodiments of the present application. It should be understood that each process and / or box in the flowchart and / or block diagram, as well as the combination of the processes and / or boxes in the flowchart and / or block diagram, can be implemented by computer program instructions. These computer program instructions can be provided to a processor of a general-purpose computer, a special-purpose computer, an embedded processor, or other programmable data processing device to generate a machine, so that the instructions executed by the processor of the computer or other programmable data processing device generate instructions for implementing the processes in the flowchart and / or block diagram. Figure 1 A process or multiple processes and / or boxes Figure 1 A device that provides the functions specified in a block or multiple blocks.
[0231] These computer program instructions may also be stored in a computer-readable memory capable of directing a computer or other programmable data processing device to operate in a specific manner, so that the instructions stored in the computer-readable memory produce an article of manufacture comprising an instruction device, which implements the process Figure 1 A process or multiple processes and / or boxes Figure 1 A function specified in one or more boxes.
[0232] These computer program instructions can also be loaded onto a computer or other programmable data processing device so that a series of operating steps are executed on the computer or other programmable device to produce a computer-implemented process, thereby providing instructions for implementing the process. Figure 1 A process or multiple processes and / or boxes Figure 1 The steps for the functions specified in one or more boxes.
[0233] Although the preferred embodiments of the present application have been described, those skilled in the art may make other changes and modifications to these embodiments once they have learned the basic creative concept. Therefore, the appended claims are intended to be interpreted as including the preferred embodiments and all changes and modifications falling within the scope of the present application.
[0234] Obviously, those skilled in the art can make various changes and modifications to the present application without departing from the spirit and scope of the present application. Thus, if these modifications and variations of the present application fall within the scope of the claims of the present application and their equivalents, the present application is also intended to include these modifications and variations.
Claims
1. A method for detaining a vehicle in rail transit, It is characterized in that The method comprises: Obtaining the fault type, fault impact range and real-time train position, wherein the fault type is a train fault or an equipment fault; Generate train detention data according to the fault type, fault impact range and real-time train position; the train detention data includes: train detention time and train detention location; Sending the vehicle detention data to the train automatic monitoring system so that the train automatic monitoring system detains the vehicle at the detaining time and at the detaining location; The generation of train detention data according to the fault type, fault impact range and real-time train position includes: Determine an ordered set of affected trains according to the fault type, the fault impact range and the real-time train position; wherein the elements in the ordered set are sorted from early to late according to the departure time of the corresponding trains; Taking the first element in the ordered set as the current element; Determine the location where the train corresponding to the current element is detained; Determine the train detention time corresponding to the current element; Determine whether the train corresponding to the next element of the current element in the ordered set is affected; include: Obtain the first scheduled arrival and departure time of the train corresponding to the next element of the current element in the ordered set arriving at the nearest platform; Get the second scheduled arrival and departure time of the current element at the nearest platform; If the second planned arrival and departure time do not meet the minimum tracking interval with the first planned arrival and departure time, it is determined that the train corresponding to the next element is affected, and the nearest platform is used as the conflicting platform corresponding to the next element; If the train corresponding to the next element is affected, the next element is used as the current element, and the step of determining the train detention location corresponding to the current element and subsequent steps are repeated.
2. The method according to claim 1, It is characterized in that Determining an ordered set of affected trains according to the fault type, the fault impact range and the real-time train position includes: If the fault type is a train fault, the faulty train is taken as the first element of the ordered set; if the fault type is an equipment fault, the first train that passes through the faulty equipment after the fault occurs is taken as the first element of the ordered set; A subsequent train is taken as another element of the ordered set, the real-time train position of the subsequent train is within the fault impact range, and the departure time of the subsequent train is later than the departure time of the first element.
3. The method according to claim 1, It is characterized in that The current element is the first element in the ordered set; The step of determining the detaining location of the train corresponding to the current element includes: If the fault type is a train fault, when the train corresponding to the current element is capable of running to the platform, the train detention location is the next platform; when the train corresponding to the current element is unable to run to the platform, the train detention location is the temporary parking location in the section; If the fault type is equipment failure, when there is an idle platform between the train corresponding to the current element and the faulty equipment, the vehicle detention location is the idle platform farthest from the train corresponding to the current element; when there is no idle platform between the train corresponding to the current element and the faulty equipment, the vehicle detention location is the temporary parking location in the section.
4. The method according to claim 1, It is characterized in that The current element is not the first element in the ordered set; The step of determining the detaining location of the train corresponding to the current element includes: If there is an idle platform between the train corresponding to the current element and the train corresponding to the previous element, the location of the train detention is the platform closest to the train corresponding to the previous element; If there is no vacant platform between the train corresponding to the current element and the train corresponding to the previous element, the vehicle detention location is a temporary parking location in the section.
5. The method according to claim 3, It is characterized in that Determining the train detention time corresponding to the current element includes: Determine the train detention time t = T corresponding to the current element next +t interval -T pre ; Among them, T next is the planned time of the train corresponding to the current element at the conflicting platform corresponding to the current element, t interval is the minimum tracking interval, T pre It is the planned time for the train corresponding to the previous element of the current element to arrive at the conflicting platform corresponding to the current element.
6. The method according to claim 1, It is characterized in that The method further comprises: Estimated failure end time; Continuously monitor the status of the fault; If the fault is determined to be restored according to the status within the fault end time, the rail transit vehicle detention method is terminated.
7. An electronic device, It is characterized in that include: Memory; processor; as well as Computer programs; The computer program is stored in the memory and is configured to be executed by the processor to implement the method according to any one of claims 1 to 6.
8. A computer-readable storage medium, It is characterized in that A computer program is stored thereon; the computer program is executed by a processor to implement the method according to any one of claims 1 to 6.