Intelligent lifting external protective frame for assembled buildings and construction method
Through the intelligent lifting of the external protective frame system and the automated connection of L-shaped wall fittings and gear rails, the hidden safety hazards and low efficiency problems of high-altitude operations in prefabricated building construction have been solved, and efficient and safe external protective frame lifting has been achieved.
Patent Information
- Application Number
- CN202211578302.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2022-12-09
- Publication Date
- 2024-10-29
- Estimated Expiration
- 2042-12-09
AI Technical Summary
In the construction of prefabricated buildings, there are potential safety hazards and low efficiency problems in high-altitude operations during the lifting of external protective frames, especially because the erecting workers need to repeatedly go to the facade for installation and dismantling operations, and the tower crane lifting time is long.
It adopts an intelligent lifting external protective frame system, including L-shaped wall parts, gear rails and lifting mechanisms. It is connected through the precession motor and gear meshing to realize automatic lifting and alignment fallback. The controller monitors the load and safety to avoid high-altitude operations and accidents. Tower crane occupied.
It improves the lifting efficiency and safety of the external protective frame, avoids the risk of high-altitude operations, reduces the tower crane operation time, and realizes intelligent and automated construction.
Smart Images

Figure CN115807535B_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of building engineering, and in particular to an assembled building intelligent lifting external protective frame and a construction method. Background Art
[0002] The external protective frame is a work platform set up in the construction of prefabricated buildings to ensure safe operations at heights. It is required to have sufficient strength, rigidity and stability, and is mainly composed of a support system, a platform and protection system, a wall attachment system and a hanging point. The external protective frame can provide a 2-3-layer work platform, on which workers can carry out construction processes such as the installation of prefabricated exterior wall components, waterproofing and gluing, and exterior decoration. After the construction of one structural layer is completed, the protective frame needs to be lifted up one structural layer for further construction. The lifting process is mostly for the scaffolding workers to go to the facade to dismantle the support and wall attachment system. After the frame is completely separated from the wall, it is lifted as a whole by the tower crane. After the lifting is in place, the scaffolding workers go to the facade to install the support and wall attachment system of the frame, so as to attach and fix the frame to the wall. The entire lifting process takes 30 to 40 minutes. There are great safety hazards for the scaffolding workers to go to the facade to perform high-altitude operations, and the lifting process takes up a long time of the tower crane operation, resulting in low lifting efficiency. Summary of the invention
[0003] The purpose of the present invention is to provide an intelligent lifting external protective frame for prefabricated buildings and a construction method to solve the problems that during the lifting process, scaffold workers need to go to the facade to repeatedly install and dismantle the frame, resulting in a large safety risk in high-altitude operations, and lifting the external protective frame to the upper structural layer by a tower crane, resulting in low lifting efficiency and a long lifting process.
[0004] In order to solve the above technical problems, the present invention provides a technical solution: an assembled building intelligent lifting external protective frame, comprising:
[0005] The L-shaped wall connecting parts are arranged in multiple rows, and each row of the L-shaped wall connecting parts is threadedly connected to the first embedded bolt hole on the prefabricated wall of the corresponding layer of the prefabricated wall surface of the completed assembled exterior wall; each of the L-shaped wall connecting parts comprises a transversely arranged steel pad beam, a precession motor arranged in the steel pad beam, and a screw connected to the shaft of the precession motor, the screw extending out of the steel pad beam, and a vertically arranged stopper connected to the steel pad beam or the precession motor; the L-shaped wall connecting parts are threadedly connected to the first embedded bolt hole of the corresponding prefabricated wall by driving the screw through the precession motor;
[0006] The rack rails are connected to both sides of each prefabricated wall surface of the completed assembled exterior wall through guide rail wall connecting pieces, and the rack surfaces of the rack rails on both sides are arranged opposite to each other;
[0007] The lifting mechanisms are multiple and match the number of layers of the external protective frames to be installed. Two lifting mechanisms are correspondingly provided for each layer of the external protective frames, and the two lifting mechanisms of each layer are meshed and connected to the racks on both sides; each lifting mechanism includes a fixing plate parallel to the wall, a lifting motor provided on the fixing plate, and a gear connected to the lifting motor; the lifting motor of the lifting mechanism is meshed and connected to the rack through a gear;
[0008] An external protective frame is located on the outside of the wall surface of the completed assembled exterior wall, the longitudinal and transverse bars on both sides of the external protective frame are connected to the fixed plate of the lifting mechanism, and the inner transverse bar of the external protective frame is overlapped on the steel pad beam of the L-shaped wall connecting member through the stopper of the L-shaped wall connecting member, so as to attach the external protective frame to the completed wall surface;
[0009] The controller is connected to the screw-in motor of each of the L-shaped wall connecting members and to the lifting motor of each of the lifting mechanisms.
[0010] Furthermore, in the prefabricated building intelligent lifting external protective frame provided by the present invention, the L-shaped wall connection member also includes a pressure sensor plate arranged on the upper surface of the steel pad beam, the inner cross bar of the external protective frame is overlapped on the pressure sensor plate of the L-shaped wall connection member, and the pressure sensor is arranged on the pressure sensor plate, and each of the pressure sensors is connected to the controller.
[0011] Furthermore, in the assembled building intelligent lifting external protective frame provided by the present invention, the steel pad beam of the L-shaped wall connecting member is the first component, the stopper, the precession motor and the screw of the L-shaped wall connecting member are integrated into a second component, the second component runs through the first component and is distributed at both ends thereof, and a reset spring is arranged between the pressure sensor plate and the precession motor.
[0012] Furthermore, in the assembled building intelligent lifting external protective frame provided by the present invention, the stopper of the L-shaped wall connecting member is integrally connected with the steel pad beam to form a first component, and the precession motor is integrally connected with the screw rod to form a second component.
[0013] Furthermore, in the assembled building intelligent lifting external protective frame provided by the present invention, a through hole penetrating the stopper of the L-shaped wall connecting member is provided on the inner cross bar of the external protective frame.
[0014] Furthermore, in the assembled building intelligent lifting external protective frame provided by the present invention, the lifting mechanism also includes a fastening guide wheel arranged on the fixed plate, and the fastening guide wheel is rollingly arranged on the opposite surface of the rack surface of the rack rail or the fastening guide wheel is rollingly arranged on the side surface of the rack rail close to the wall.
[0015] Furthermore, in the assembled building intelligent lifting external protective frame provided by the present invention, the guide rail wall connecting member is a bolt barrel assembly and a counter screw, the bolt barrel assembly includes a coaxially arranged threaded column and a threaded sleeve, the threaded column is threadedly connected in the second embedded bolt hole of the prefabricated wall, the threaded sleeve is threadedly connected to the counter screw, and the counter screw is fixed on the rack rail.
[0016] In order to solve the above technical problems, the present invention provides a technical solution: a prefabricated building construction method, comprising:
[0017] Step 301, according to the number of layers of the external protective frame of the prefabricated building, the prefabricated wall surface of the corresponding number of layers of the prefabricated exterior wall is constructed through prefabricated walls;
[0018] Step 302, installing the above-mentioned prefabricated building intelligent lifting external protective frame on the wall surface of the completed prefabricated exterior wall;
[0019] Step 303, using the prefabricated building intelligent lifting external protective frame to perform prefabricated exterior wall construction on the wall surface of the completed prefabricated exterior wall through prefabricated wall bodies to form an upper prefabricated wall surface, installing L-shaped wall connecting parts on the upper prefabricated wall surface, and installing the rack rails on the upper prefabricated wall surface on both sides of the upper prefabricated wall surface through guide rail wall connecting parts, and connecting the rack rails on the upper prefabricated wall surface with the rack rails on the lower prefabricated wall surface;
[0020] Step 304, the controller controls the lifting motor of the lifting mechanism to start, and the lifting motor drives the gear to rotate on the rack, so that the external protective frame is separated from the currently connected L-shaped wall connecting member and lifted upward;
[0021] Step 305, the controller controls the screw-in motor of the L-shaped wall connecting member above the bottom layer of the external protective frame to continue to screw into the first embedded bolt hole to control the inward movement of the L-shaped wall connecting member above the bottom layer of the external protective frame;
[0022] Step 306, when the external protective frame is lifted upward and exceeds the uppermost L-shaped wall connecting member, the controller controls the lifting motor to stop lifting; the controller controls the screw-in motor of the L-shaped wall connecting member above the bottom layer of the external protective frame to screw out and remain in the first embedded bolt hole to control the L-shaped wall connecting member above the bottom layer of the external protective frame to move back;
[0023] Step 307, the controller controls the external protective frame to move downward and fall back to the steel pad beam of the L-shaped wall connecting member corresponding to the lifted external protective frame through the lifting electromechanical control;
[0024] Step 308, repeating steps 303 to 307 until the construction of the assembled exterior wall is completed.
[0025] Furthermore, in the prefabricated building construction method provided by the present invention, in step 307, the inner cross bar of the external protective frame is overlapped on the pressure sensor plate on the steel pad beam of the L-shaped wall connecting member, and when the pressure value sensed by the pressure sensor on the pressure sensor plate is equal to the deadweight load of the external protective frame, it is determined that the lifting of the external protective frame is completed.
[0026] Furthermore, in the prefabricated building construction method provided by the present invention, the controller performs safety monitoring of the construction load of the external protective frame through the pressure sensor plate.
[0027] Compared with the prior art, the present invention has the following beneficial effects:
[0028] The present invention provides an assembled building intelligent lifting external protective frame and construction method. Through the automatic rotation in and out of the L-shaped wall connection piece, and the inward movement of the L-shaped wall connection piece in the prefabricated wall, the external protective frame can automatically avoid the position of the L-shaped wall connection piece when it is lifted by the lifting mechanism, so as to prevent the position interference between the external protective frame and the L-shaped wall connection piece during the lifting process, which leads to the failure of automatic lifting; through the return movement of the L-shaped wall connection piece in the prefabricated wall, the external protective frame and the L-shaped wall connection piece are automatically aligned, dropped and overlapped; so far, the controller controls the lifting of the external protective frame relative to the wall surface through the lifting mechanism, and there is no need for the scaffold workers to go to the facade to install and remove the external protective frame, so that the risk of high-altitude operation is avoided during the lifting process, and effective safety protection is provided for the facade workers. During the lifting process, there is no need to occupy the tower crane operation time, which improves the lifting efficiency of the external protective frame.
[0029] The present invention provides an intelligent lifting external protective frame for assembled buildings and a construction method, wherein a lifting mechanism is connected to the external protective frame as an integral whole, and a gear of a lifting motor of the lifting mechanism is meshedly connected with a rack rail, so that the external protective frame can be lifted upward relative to the rack rail through the lifting mechanism, thereby improving the safety and reliability of the external protective frame during the lifting process.
[0030] The intelligent lifting external protective frame and construction method for prefabricated buildings provided by the present invention do not require human intervention in the lifting process, and are completely intelligently adjusted and controlled by a controller, which effectively avoids the risks of high-altitude operations, does not require the working time of the tower crane, improves the lifting efficiency of the frame, and can promote the intelligent and automated construction of prefabricated buildings. BRIEF DESCRIPTION OF THE DRAWINGS
[0031] Figure 1 It is a three-dimensional structural diagram of installing L-shaped wall connecting parts, guide rail wall connecting parts, gear rails and lifting mechanisms on the wall of a completed three-story prefabricated building;
[0032] Figure 2 is Figure 1 A schematic diagram of a three-dimensional structure of an external protective frame without a protective net installed on a lifting mechanism and an L-shaped wall connecting member;
[0033] Figure 3 is Figure 2 A schematic diagram of a three-dimensional structure in which a protective net is installed on an external protective frame;
[0034] Figure 4 is Figure 3 A schematic diagram of the three-dimensional structure of the fourth-layer prefabricated wall formed by installing prefabricated wall panels on the wall of the completed three-layer prefabricated building;
[0035] Figure 5 is Figure 4 A schematic diagram of the three-dimensional structure of the rack rails and L-shaped wall connecting parts installed on the corresponding prefabricated wall panels of the fourth prefabricated wall;
[0036] Figure 6 It is a three-dimensional structural diagram of the prefabricated wall of the fourth floor where the external protective frame of the prefabricated building is lifted intelligently;
[0037] Figure 7 It is a schematic diagram of the structure of the L-shaped wall connecting member moving inward;
[0038] Figure 8 It is a schematic diagram of the structure of the L-shaped wall connection member moving back;
[0039] Fig. 9 It is a structural schematic diagram of the external protective frame falling back onto the L-shaped wall connecting member;
[0040] Fig.10 It is a structural schematic diagram of another connection method between the fastening roller of the lifting mechanism and the rack node;
[0041] Fig.11 It is a structural diagram of the control system of the intelligent lifting external protective frame of the assembled building;
[0042] Fig.12 is a schematic diagram of the three-dimensional structure of the L-shaped wall connecting member of the first embodiment;
[0043] Fig.13 yes Fig.12 A schematic diagram of the three-dimensional structure of the steel cushion beam of the L-shaped wall connecting member and the stopper thereon;
[0044] Fig.14 yes Fig.12 A schematic diagram of the three-dimensional structure of the screw-in motor and the screw rod of the L-shaped wall connecting member;
[0045] Fig.15 is a schematic diagram of the three-dimensional structure of the L-shaped wall connecting member of the second embodiment;
[0046] Fig.16 yes Fig.15 Schematic diagram of the three-dimensional structure of the steel cushion beam;
[0047] Fig.17 yes Fig.15 A schematic diagram of a three-dimensional structure of a precession motor and a stopper and a screw rod connected thereto;
[0048] Fig.18 It is a schematic diagram of a three-dimensional structure in which the rack rail and the prefabricated wall panel nodes are connected through the guide rail wall connection piece;
[0049] Fig.19 It is a three-dimensional structural schematic diagram of the guide rail connecting wall member;
[0050] As shown in the figure:
[0051] 100. Intelligent lifting external protective frame for assembled buildings;
[0052] 110. L-shaped wall connecting member, 111. steel cushion beam, 1111. first through hole, 1112. second through hole, 112. screw-in motor, 113. screw rod, 114. stopper, 115. pressure sensing plate, 116. spring, 117. pressure sensor;
[0053] 120, rack rail, 121, counter screw;
[0054] 130, guide rail wall connection piece, 131, threaded column, 132, threaded sleeve;
[0055] 140. lifting mechanism, 141. fixing plate, 142. lifting motor, 143. gear, 144. fastening guide wheel;
[0056] 150, external protective frame, 151, inner cross bar, 152, longitudinal and transverse bars, 153, protective net;
[0057] 200, wall surface, 201, first-layer prefabricated wall surface, 202, second-layer prefabricated wall surface, 203, third-layer prefabricated wall surface, 204, fourth-layer prefabricated wall surface, 210, prefabricated wall, 211, first pre-buried bolt hole, 212, second pre-buried bolt hole. DETAILED DESCRIPTION
[0058] The present invention is described in detail below in conjunction with the accompanying drawings: The advantages and features of the present invention will become more apparent from the following description. It should be noted that the accompanying drawings are in very simplified form and in non-precise proportions, and are only used to conveniently and clearly assist in explaining the purpose of the embodiments of the present invention.
[0059] Please refer to Figures 1 to 19 The embodiment of the present invention provides an assembled building intelligent lifting external protective frame 100, including an L-shaped wall connecting member 110, a rack rail 120, a guide rail wall connecting member 130, a lifting mechanism 140, an external protective frame 150 and a controller 160, wherein:
[0060] The L-shaped wall connecting parts 110 are arranged in multiple rows, and each row of the L-shaped wall connecting parts 110 is threadedly connected to the first embedded bolt hole 211 on the prefabricated wall 210 of the corresponding layer of the prefabricated wall surface of the wall surface 200 of the completed assembled exterior wall; each of the L-shaped wall connecting parts 110 includes a transversely arranged steel pad beam 111, a screw-in motor 112 arranged in the steel pad beam 111, and a screw 113 connected to the shaft of the screw-in motor 112, the screw 113 extending out of the steel pad beam 111, and a vertically arranged stopper 114 is connected to the steel pad beam 111 or the screw-in motor 112; the L-shaped wall connecting part 110 is threadedly connected to the first embedded bolt hole 211 of the corresponding prefabricated wall 210 by driving the screw 113 through the screw-in motor 112.
[0061] The rack rail 120 is connected to both sides of each prefabricated wall surface of the wall surface 200 of the completed assembled exterior wall through the guide rail wall connecting member 130, and the rack surfaces of the rack rail 120 on both sides are arranged opposite to each other.
[0062] The lifting mechanisms 140 are multiple and match the number of layers of the external protective frames 150 to be installed. Two lifting mechanisms 140 are correspondingly arranged on each layer of the external protective frames 150, and the two lifting mechanisms 140 on each layer are meshed and connected to the racks 120 on both sides; each of the lifting mechanisms 140 includes a fixed plate 141 parallel to the wall 200, a lifting motor 142 arranged on the fixed plate 141, and a gear 143 connected to the lifting motor 142; the lifting motor 142 of the lifting mechanism 140 is meshed and connected to the rack 120 through the gear 143.
[0063] The external protective frame 150 is located outside the wall surface 200 of the completed assembled exterior wall, and the longitudinal and transverse bars 152 on both sides of the external protective frame 150 are connected to the fixing plate 141 of the lifting mechanism 140, and the inner transverse bar 151 of the external protective frame 150 is overlapped on the steel pad beam 111 of the L-shaped wall connecting member 110 through the stopper 114 of the L-shaped wall connecting member 110, so as to attach the external protective frame 150 to the completed wall surface 200. The external protective frame 150 may include a frame body and a protective net 153 composed of an inner transverse bar 151, an outer transverse bar, longitudinal and transverse bars, vertical bars and diagonal bars.
[0064] The controller 160 is connected to the screw-in motor 112 of each of the L-shaped wall connecting members 110 , and is connected to the lifting motor 142 of each of the lifting mechanisms 140 .
[0065] The embodiment of the present invention provides an assembled building intelligent lifting external protective frame 100, in which an L-shaped wall connecting piece is attached to the wall 200, so as to support the construction load of the external protective frame 150; the longitudinal and transverse bars 152 are attached to the rack 120 through the gear 143 connected to the lifting motor 142, so as to support the deadweight load of the external protective frame 150 during the lifting process.
[0066] Please refer to Fig.12 , Fig.15 In order to achieve safe monitoring of the installation and construction load of the external protective frame 150, the embodiment of the present invention provides an assembled building intelligent lifting external protective frame 100, the L-shaped wall connecting member 110 also includes a pressure sensor plate 115 arranged on the upper surface of the steel pad beam 111, and the inner cross bar 151 of the external protective frame 150 is overlapped on the pressure sensor plate 115 of the L-shaped wall connecting member 110, and a pressure sensor 117 is arranged on the pressure sensor plate 115, and each of the pressure sensors 117 is connected to the controller 160.
[0067] The assembled building intelligent lifting external protective frame 100 provided in the embodiment of the present invention, the L-shaped wall connecting member 110 may include the following two schemes.
[0068] Solution 1: Please refer to Figure 12 to Figure 14 The stopper 114 of the L-shaped wall connecting member 110 is integrally connected with the steel cushion beam 111 to form a first component, and the screw motor 112 is integrally connected with the screw rod 113 to form a second component. The steel cushion beam 111 is provided with a first through hole 1111 which is connected with its chamber and is used to extend the screw rod 113.
[0069] Solution 2: Please refer to Figures 15 to 17The steel cushion beam 111 of the L-shaped wall connecting member 110 is the first component, and the stopper 114, the precession motor 112 and the screw 113 of the L-shaped wall connecting member 110 are integrally connected to form the second component. The second component runs through the first component and is distributed at both ends thereof. A spring 116 is connected between the pressure sensor plate 115 and the precession motor 112. At this time, the two ends of the steel cushion beam 111 can be respectively provided with a first through hole 1111 and a second through hole 1112 that are connected to the chamber therein. In the L-shaped wall connecting member 110 of the second scheme, since the second component is integrally connected, the external protective frame 150 overlapped on the steel cushion beam 111 of the L-shaped wall connecting member 110 is relatively uniform in force and has a smaller torque. When there is no inner cross bar 151 overlapping and pressing on the steel cushion beam 111, the pressure sensing plate 115 is bounced up by the action of the spring 116, and the spring 116 is not in contact with the screw-in motor 112 of the second component, so that the second component can be screwed in or out to the first embedded bolt hole 211 and move inward and outward of the wall surface; when there is an inner cross bar 151 overlapping and pressing on the steel cushion beam 111, the pressure sensing plate 115 is in contact with the second component, transferring the construction load to the second component and then to the wall of the assembled exterior wall. Therefore, the load bearing effect of the L-shaped wall connecting member 110 of the second scheme is higher than that of the first scheme.
[0070] Please refer to Fig. 9 In order to achieve reliable connection between the L-shaped wall connection member 110 and the external protective frame 150, the external protective frame 100 for intelligent lifting of prefabricated buildings provided in the embodiment of the present invention is provided with an overlapping hole penetrating the stopper 114 of the L-shaped wall connection member 110 on the inner cross bar 151 of the external protective frame 150. Then the overlapping hole of the inner cross bar 151 passes through the stopper 114 of the L-shaped wall connection member 110 and overlaps the steel cushion beam 111 or the pressure sensor plate 115 thereon. Of course, in order to achieve the purpose of overlapping, the lower surface of the inner cross bar 151 can be overlapped on the steel cushion beam 111 or the pressure sensor plate 115, and the side surface of the inner cross bar 151 can be overlapped on the stopper 114. The stopper 114 can be a cylinder or a square column, etc.
[0071] Please refer to Figures 7 to 9 In order to facilitate the movement of the external protective frame 150 along the rack 120, the embodiment of the present invention provides an assembled building intelligent lifting external protective frame 100, and the lifting mechanism 140 also includes a fastening guide wheel 144 arranged on the fixing plate 141, and the fastening guide wheel 144 is rollingly arranged on the opposite surface of the rack surface of the rack 120. At this time, the fastening guide wheel 144 is arranged opposite to the gear 143, and the fastening guide wheel 144 can balance the meshing force of the gear 143, thereby improving the stability of the lifting of the external protective frame 150. Please refer to Fig.10In order to improve the reliability of the connection between the external protective frame 150 and the rack 120 and prevent the external protective frame 150 from being separated from the rack 120, the fastening guide wheel 144 is rollably set on the side of the rack 120 close to the wall 200. At this time, the fastening guide wheel 144 can make the external protective frame 150 reliably roll on the rack 120. The fastening guide wheel 144 can be set on the guide column, Fig.10 The guide posts in the are right-angled. Figures 7 to 9 The guide posts in the are straight.
[0072] Please refer to Figure 18 to Figure 19 In order to facilitate the adjustment of the spacing between the rack rail 120 and the wall 200, the embodiment of the present invention provides an assembled building intelligent lifting external protective frame 100, wherein the guide rail wall connecting member 130 is a bolt barrel assembly and a counter screw 121, wherein the bolt barrel assembly includes a coaxially arranged threaded column 131 and a threaded sleeve 132, wherein the threaded column 131 is threadedly connected to the second embedded bolt hole 212 of the prefabricated wall 210, and the threaded sleeve 132 is threadedly connected to the counter screw 121, and the counter screw 121 is fixedly arranged on the rack rail 120. At this time, after the threaded column 131 is threadedly connected to the second embedded bolt hole 212, the threaded sleeve 132 is in a reverse threaded connection with the counter screw 121. Of course, in order to achieve the purpose of connecting the rack rail 120 with the wall 200, the guide rail wall connecting member 130 can be a bolt passing through the rack rail 120.
[0073] Please refer to Figures 1 to 19 The embodiment of the present invention further provides a method for constructing an assembled building, which may include:
[0074] Step 301, please refer to Figure 1 , Figures 12 to 17 According to the number of layers of the assembled building intelligent lifting external protective frame 100, the prefabricated wall 210 is used to construct the corresponding number of prefabricated wall surfaces of the assembled exterior wall.
[0075] Step 302, please refer to Figures 2 to 3 , the above-mentioned assembled building intelligent lifting external protective frame 100 is installed on the wall surface 200 of the completed assembled exterior wall. Figures 1 to 3The example shows a three-layer external protective frame 150 and a three-layer prefabricated exterior wall. The three-layer prefabricated exterior wall includes a first layer of prefabricated wall surface 201, a second layer of prefabricated wall surface 202, and a third layer of prefabricated wall surface 203. Each layer of prefabricated wall surface is provided with a row of L-shaped wall connecting parts 110. The L-shaped wall connecting part 110 can be set in the first embedded bolt hole 211 reserved 10 cm away from the top of the center line of each prefabricated wall body 210. It should be noted that not every prefabricated wall body 210 needs to be provided with an L-shaped wall connecting part 110, and it can be provided as needed. The external protective frame 150 can be hoisted to the wall surface for installation by a tower crane after being assembled on the ground. The external protective frame 150 is not limited to three layers.
[0076] Step 303, please refer to Figures 4 to 5 , the prefabricated exterior wall construction is performed on the wall 200 of the prefabricated exterior wall by means of the prefabricated wall 210 to form the upper prefabricated wall, i.e., the fourth prefabricated wall 204, the L-shaped wall connection 110 is installed on the fourth prefabricated wall 204, and the rack rail 120 on the fourth prefabricated wall 204 is installed on both sides of the fourth prefabricated wall 204 by means of the guide rail wall connection 130, and the rack rail 120 on the fourth prefabricated wall 204 is connected with the rack rail 120 on the next prefabricated wall, i.e., the third prefabricated wall 203. After the installation of the external protective frame 150 is completed, the installation of the prefabricated wall 210 and the waterproof gluing, decoration and other construction operations can be carried out.
[0077] Step 304, please refer to Figures 5 and 6 , the controller 160 controls the lifting motor 142 of the lifting mechanism 140 to start, and the lifting motor 142 drives the gear 143 to rotate on the rack 120, so that the external protective frame 150 is separated from the currently connected L-shaped wall connecting member 110 and lifted upward. Before lifting, all construction supplies on the external protective frame 150 are unloaded, and people are prohibited from standing. The lifting is performed only considering the self-weight of the external protective frame 150. When the external protective frame 150 is separated from the L-shaped wall connecting member 110, the external protective frame 150 is connected to the rack 120 through the lifting mechanism 140.
[0078] Step 305, please refer to Figure 7 , the controller 160 controls the screw-in motor 112 of the L-shaped wall connecting member 110 above the bottom layer of the external protective frame 150 to continue to screw into the first pre-buried bolt hole 211 to control the inward movement of the L-shaped wall connecting member 110 above the bottom layer of the external protective frame 150. The L-shaped wall connecting member 110 stops screwing in at a position 2 cm from the inner cross bar 151. The inward movement of the L-shaped wall connecting member 110 is used to avoid the rise of the inner cross bar 151 of the external protective frame 150.
[0079] Step 306, please refer to Figure 8When the external protective frame 150 is lifted upward and exceeds the uppermost L-shaped wall connecting member 110, that is, after exceeding the 2 cm position of the fourth row of L-shaped wall connecting members 110, the controller 160 controls the lifting motor 142 to stop lifting; the controller 160 controls the screw-in motor 112 of the L-shaped wall connecting member 110 above the bottom layer of the external protective frame to screw out and remain in the first embedded bolt hole 211 to control the L-shaped wall connecting member 110 above the bottom layer of the external protective frame 150 to move back. That is, the L-shaped wall connecting member 110 moves back so that it can be aligned with the inner cross bar 151 of the external protective frame 150. That is, when the inner cross bar 151 is provided with a lap hole, the position alignment of the L-shaped wall connecting member 110 and the lap hole of the inner cross bar 151 is achieved. In addition, in order to improve the lifting efficiency, the screwing in and out of the L-shaped wall connecting member 110 and the lifting and falling of the external protective frame 150 can be carried out simultaneously.
[0080] In step 307, the controller 160 controls the external protection frame 150 to move down and fall back to the steel pad beam 111 of the L-shaped wall connecting member 110 corresponding to the lifted external protection frame 150. At this point, the external protection frame 150 is lifted to the fourth prefabricated wall surface 204.
[0081] Step 308 , repeating steps 303 to 307 until all the prefabricated exterior walls are constructed, that is, the prefabricated exterior walls above the fourth prefabricated wall surface 204 are constructed.
[0082] Please refer to Fig.12 and Fig.15 In order to improve the reliability of the external protective frame 150 overlapped on the L-shaped wall connecting member 110, the prefabricated building construction method provided by the embodiment of the present invention, in step 307, the inner cross bar 151 of the external protective frame 150 is overlapped on the pressure sensor plate 115 on the steel pad beam 111 of the L-shaped wall connecting member 110, and when the pressure value sensed by the pressure sensor 117 on the pressure sensor plate 115 is equal to the deadweight load of the external protective frame 150, it is determined that the lifting of the external protective frame 150 is completed. The construction load on the external protective frame 150 can also be monitored in real time through the pressure sensor plate 115, and the load status of the external protective frame 150 can be monitored in real time, and a safety warning can be issued for overload conditions for rectification. A safety warning can be issued when the load value reaches 80% of the limit load.
[0083] Please refer to Fig.11 In the prefabricated building construction method provided by the embodiment of the present invention, the controller 160 performs safety monitoring on the construction load of the external protective frame 150 through the pressure sensor plate 115 .
[0084] The embodiment of the present invention provides an assembled building intelligent lifting external protective frame 100 and a construction method. Through the automatic rotation in and out of the L-shaped wall connecting member 110 and the inward movement of the L-shaped wall connecting member 110 in the prefabricated wall 210, the external protective frame 150 can automatically avoid the position of the L-shaped wall connecting member 110 when it is lifted by the lifting mechanism 140, thereby preventing the external protective frame 150 and the L-shaped wall connecting member 110 from causing position interference during the lifting process, resulting in failure to automatically lift. Through the return movement of the L-shaped wall connecting member 110 in the prefabricated wall 210, the external protective frame 150 and the L-shaped wall connecting member 110 are automatically aligned, dropped and overlapped. At this point, the controller 160 controls the lifting of the external protective frame 150 relative to the wall 200 through the lifting mechanism 140, and there is no need for scaffold workers to go to the facade to install and remove the external protective frame 150, thereby avoiding the risk of high-altitude operations during the lifting process and providing effective safety protection for facade workers. During the lifting process, there is no need to occupy the tower crane operation time, thereby improving the lifting efficiency of the external protective frame 150.
[0085] The embodiment of the present invention provides an assembled building intelligent lifting external protective frame 100 and a construction method, wherein a lifting mechanism 140 is connected as a whole with an external protective frame 150, and a gear 143 of a lifting motor 142 of the lifting mechanism 140 is meshedly connected with a rack rail 120, so that the external protective frame 150 is lifted upward relative to the rack rail 120 through the lifting mechanism 140, thereby improving the safety and reliability of the external protective frame 150 during the lifting process.
[0086] The intelligent lifting external protective frame 100 and construction method for prefabricated buildings provided in the embodiment of the present invention do not require human intervention in the lifting process, and are completely intelligently adjusted and controlled by the controller 160, effectively avoiding the risks of high-altitude operations, eliminating the need to occupy the working time of the tower crane, and improving the lifting efficiency of the frame, which can promote the intelligent and automated construction of prefabricated buildings.
[0087] The assembled building intelligent lifting external protective frame 100 and construction method provided in the embodiment of the present invention realizes the intelligent lifting of the external protective frame 150 through the controller 160, and can control the lifting process within 10 minutes, thereby improving the lifting efficiency of the external protective frame by more than 60%. In order to realize intelligent control, the controller 160 can also be wirelessly connected to a computer, a mobile phone, etc., so as to control the intelligent lifting of the external protective frame 150 through the software of the computer or the mobile phone.
[0088] The assembled building intelligent lifting external protective frame 100 and the construction method provided in the embodiment of the present invention can solve the problems of lightweight autonomous lifting of the frame and effective support of the construction load, and the monitoring of the maximum construction load and safety warning.
[0089] The embodiment of the present invention provides an assembled building intelligent lifting external protective frame 100 and a construction method. The term "setting" in the embodiment of the present invention includes but is not limited to connection relationships such as welding and bolt connection.
[0090] The present invention is not limited to the above-mentioned specific implementation modes. Obviously, the above-mentioned embodiments are only some embodiments of the embodiments of the present invention, but not all embodiments. Based on the described embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field belong to the scope of protection of the present invention. Those skilled in the art can make other levels of modifications and changes to the present invention. In this way, if these modifications and changes of the present invention fall within the scope of the claims of the present invention, the present invention is also intended to include these changes and changes.
Claims
1. An assembled building intelligent lifting external protection frame, characterized in that: include: The L-shaped wall connecting parts are arranged in multiple rows, and each row of the L-shaped wall connecting parts is threadedly connected to the first embedded bolt hole on the prefabricated wall of the corresponding layer of the prefabricated wall surface of the completed assembled exterior wall; each of the L-shaped wall connecting parts comprises a transversely arranged steel pad beam, a precession motor arranged in the steel pad beam, and a screw connected to the shaft of the precession motor, the screw extending out of the steel pad beam, and a vertically arranged stopper connected to the steel pad beam or the precession motor; the L-shaped wall connecting parts are threadedly connected to the first embedded bolt hole of the corresponding prefabricated wall by driving the screw through the precession motor; The rack rails are connected to both sides of each prefabricated wall surface of the completed assembled exterior wall through guide rail wall connecting pieces, and the rack surfaces of the rack rails on both sides are arranged opposite to each other; The lifting mechanisms are multiple and match the number of layers of the external protective frames to be installed. Two lifting mechanisms are correspondingly provided for each layer of the external protective frames, and the two lifting mechanisms of each layer are meshed and connected to the racks on both sides; each lifting mechanism includes a fixing plate parallel to the wall, a lifting motor provided on the fixing plate, and a gear connected to the lifting motor; the lifting motor of the lifting mechanism is meshed and connected to the rack through a gear; An external protective frame is located on the outside of the wall surface of the completed assembled exterior wall, the longitudinal and transverse bars on both sides of the external protective frame are connected to the fixed plate of the lifting mechanism, and the inner transverse bar of the external protective frame is overlapped on the steel pad beam of the L-shaped wall connecting member through the stopper of the L-shaped wall connecting member, so as to attach the external protective frame to the completed wall surface; The controller is connected to the screw-in motor of each of the L-shaped wall connecting members and to the lifting motor of each of the lifting mechanisms.
2. The assembled building intelligent lifting external protection frame according to claim 1 is characterized in that: The L-shaped wall connection member also includes a pressure sensing plate arranged on the upper surface of the steel pad beam, the inner cross bar of the external protective frame is overlapped on the pressure sensing plate of the L-shaped wall connection member, and a pressure sensor is arranged on the pressure sensing plate, and each of the pressure sensors is connected to the controller.
3. The assembled building intelligent lifting external protection frame according to claim 2 is characterized in that: The steel pad beam of the L-shaped wall connection member is the first component, and the stopper, precession motor and screw of the L-shaped wall connection member are integrated to form the second component. The second component runs through the first component and is distributed at both ends thereof. A reset spring is arranged between the pressure sensor plate and the precession motor.
4. The assembled building intelligent lifting external protection frame according to claim 1 is characterized in that: The stopper of the L-shaped wall connecting member is integrally connected with the steel cushion beam to form a first component, and the precession motor is integrally connected with the screw rod to form a second component.
5. The assembled building intelligent lifting external protection frame according to claim 1 is characterized in that: A through hole penetrating the stopper of the L-shaped wall connecting member is arranged on the inner cross bar of the external protective frame.
6. The assembled building intelligent lifting external protection frame according to claim 1 is characterized in that: The lifting mechanism also includes a fastening guide wheel arranged on the fixing plate, and the fastening guide wheel is rollingly arranged on the surface opposite to the rack surface of the rack rail or the fastening guide wheel is rollingly arranged on the side surface of the rack rail close to the wall surface.
7. The assembled building intelligent lifting external protection frame according to claim 1 is characterized in that: The guide rail wall connecting member is a bolt barrel assembly and a counter screw, the bolt barrel assembly includes a coaxially arranged threaded column and a threaded sleeve, the threaded column is threadedly connected in the second embedded bolt hole of the prefabricated wall, the threaded sleeve is threadedly connected to the counter screw, and the counter screw is fixedly arranged on the rack rail.
8. A method for constructing an assembled building, characterized in that: include: Step 301, according to the number of layers of the external protective frame of the prefabricated building, the prefabricated wall surface of the corresponding number of layers of the prefabricated exterior wall is constructed through prefabricated walls; Step 302, installing the assembled building intelligent lifting external protective frame according to claim 2 on the wall surface of the completed assembled exterior wall; Step 303, using the prefabricated building intelligent lifting external protective frame to perform prefabricated exterior wall construction on the wall surface of the completed prefabricated exterior wall through prefabricated wall bodies to form an upper prefabricated wall surface, installing L-shaped wall connecting parts on the upper prefabricated wall surface, and installing the rack rails on the upper prefabricated wall surface on both sides of the upper prefabricated wall surface through guide rail wall connecting parts, and connecting the rack rails on the upper prefabricated wall surface with the rack rails on the lower prefabricated wall surface; Step 304, the controller controls the lifting motor of the lifting mechanism to start, and the lifting motor drives the gear to rotate on the rack, so that the external protective frame is separated from the currently connected L-shaped wall connecting member and lifted upward; Step 305, the controller controls the screw-in motor of the L-shaped wall connecting member above the bottom layer of the external protective frame to continue to screw into the first embedded bolt hole to control the inward movement of the L-shaped wall connecting member above the bottom layer of the external protective frame; Step 306, when the external protective frame is lifted upward and exceeds the uppermost L-shaped wall connecting member, the controller controls the lifting motor to stop lifting; the controller controls the screw-in motor of the L-shaped wall connecting member above the bottom layer of the external protective frame to screw out and remain in the first embedded bolt hole to control the L-shaped wall connecting member above the bottom layer of the external protective frame to move back; Step 307, the controller controls the external protective frame to move downward and fall back to the steel pad beam of the L-shaped wall connecting member corresponding to the lifted external protective frame through the lifting electromechanical control; Step 308, repeating steps 303 to 307 until the construction of the assembled exterior wall is completed.
9. The method for constructing an assembled building according to claim 8, characterized in that: In step 307, the inner cross bar of the external protective frame is overlapped on the pressure sensor plate on the steel pad beam of the L-shaped wall connecting member. When the pressure value sensed by the pressure sensor on the pressure sensor plate is equal to the deadweight load of the external protective frame, it is determined that the lifting of the external protective frame is completed.
10. The method for constructing an assembled building according to claim 8, characterized in that: The controller conducts safety monitoring of the construction load of the external protective frame through the pressure sensor plate.
Citation Information
Patent Citations
Lifting material platform and use method for same
CN102518292A
Protective platform for building construction and application method of protective platform
CN111236613A