A construction method for changing the layout of building tower cranes without stopping work

By laying multiple tower cranes in the basement and above-ground structural stages during tower construction and converting the tower crane when the core cylinder reaches three floors, the problems of extended construction period and vacuum period of lifting capacity during the tower crane conversion process are solved, and construction is realized Continuity and security of progress.

CN116220367BActive Publication Date: 2024-12-03CHINA CONSTR SECOND ENG BUREAU LTD
View PDF 2 Cites 0 Cited by

Patent Information

Application Number
CN202310244060.7
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2023-03-09
Publication Date
2024-12-03
Estimated Expiration
2043-03-09

AI Technical Summary

Technical Problem

During tower construction, the conversion process of tower cranes leads to an extension of construction period, a vacuum period for lifting capacity and a shutdown. Especially when constructing in a high-rise building with dual core cylinders, the construction progress is affected, and there is a risk of collision between the tower crane and the core cylinder exterior wall. .

Method used

The second and third tower cranes are arranged in the basement stage. The outer climbing mold is installed simultaneously during the construction of the above-ground structure, and the foundation beam is installed when the core cylinder reaches the third floor. Then the tower crane is installed and dismantled at the same time, and the continuous construction is carried out through the outer climbing mold. Ensure that the tower crane layout does not stop to change and avoid the vacuum period of lifting capacity.

Benefits of technology

Through reasonable construction deployment and optimization of installation and disassembly plans, the tower crane conversion is achieved without affecting the construction progress, reducing the construction period and economic losses, avoiding the collision risk between the tower crane and the core cylinder exterior wall, and ensuring construction efficiency and safety.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN116220367B_ABST
    Figure CN116220367B_ABST
Patent Text Reader

Abstract

The invention discloses a construction method for non-stop conversion of tower crane arrangement of a building, comprising the following steps: arranging a second tower crane and a third tower crane near both sides of a double-core tube building, the double-core tube comprising a first core tube and a second core tube, carrying out construction of the first core tube, synchronously installing an outer climbing formwork on the first core tube layer by layer, carrying out construction of the second core tube, synchronously installing an outer climbing formwork on the second core tube layer by layer, installing a fourth tower crane and disassembling the second tower crane, installing a fifth tower crane and disassembling the third tower crane, and respectively carrying out continuous construction of both the first core tube and the second core tube through the outer climbing formwork, implementing the inner climbing formwork and outer frame structure construction of the first core tube through the fourth tower crane after installation, implementing the inner climbing formwork and outer frame structure construction of the second core tube through the fifth tower crane after installation, and completing non-stop conversion of tower crane arrangement. This construction method realizes tower crane conversion under non-stop conditions, and minimizes the impact of tower crane installation and disassembly on on-site operations.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of building construction, and in particular to a method for converting the arrangement of a building tower crane without stopping work. Background Art

[0002] At present, the basement structures of tower buildings are mostly made of reinforced concrete materials. In the construction of basement structures and replacement of supports, the use of flat-arm tower cranes can fully meet the material lifting tasks. In the ground structure construction stage, since the tower structure contains a large number of steel components, in order to ensure the construction period and improve construction efficiency, it is necessary to use a boom tower crane with stronger lifting capacity to be responsible for the lifting operation of the tower's ground structure. Therefore, when the construction shifts from the basement to the ground tower construction stage, the original flat-arm tower crane needs to be dismantled and a new boom tower crane needs to be installed. The installation and disassembly of such large-scale lifting equipment is time-consuming and has a wide impact range. After installation, a vacuum period of construction lifting capacity is prone to occur, resulting in delays in the construction period and even partial shutdowns, causing economic losses.

[0003] This problem is even more serious in the construction of high-rise buildings with double core tubes. For example, during the ground structure construction stage, the flat-arm tower crane of the South Tower needs to be converted into a self-climbing boom tower crane installed in the core tube. According to the installation requirements of the boom tower crane, two inner climbing support frames need to be installed in the core tube before the tower body is installed. The inner climbing support frames are fixed to the structural beams in the core tube. Therefore, the construction progress of the core tube will directly affect the installation progress of the boom tower crane. The core tube of the tower is constructed using climbing formwork. The initial installation of the climbing formwork frame requires the use of flat-arm tower crane lifting equipment. Therefore, the installation progress of the climbing formwork frame will also affect the construction of the core tube structure. During the tower crane conversion process, there is still a risk of collision between the boom tower crane and the outer wall of the core tube, and between the boom tower crane and the flat-arm tower crane. Summary of the invention

[0004] The purpose of the present invention is to provide a construction method for changing the layout of a building crane without stopping work, which can effectively save working hours and improve efficiency.

[0005] A construction method for non-stop construction tower crane layout conversion, comprising the following steps:

[0006] Step 1: During the basement construction phase, a second tower crane and a third tower crane are respectively arranged near both sides of the double core tube building, wherein the double core tube includes a first core tube and a second core tube, the second tower crane is located near a side of the first core tube facing away from the second core tube, and the third tower crane is located near a side of the second core tube facing away from the first core tube;

[0007] Step 2: During the ground structure construction phase, the first core tube is constructed, and the outer climbing formwork is installed layer by layer on the first core tube simultaneously; the second core tube is constructed, and the outer climbing formwork is installed layer by layer on the second core tube simultaneously;

[0008] Step 3: When the first core tube and the second core tube are constructed to the third floor and the external climbing formwork is installed, foundation beams are installed on both the first core tube and the second core tube, the tower body of the fourth tower crane is installed on the foundation beam of the first core tube, and the tower body of the fifth tower crane is installed on the foundation beam of the second core tube;

[0009] Step 4: simultaneously installing the fourth tower crane and dismantling the second tower crane, simultaneously installing the fifth tower crane and dismantling the third tower crane, and performing continuous construction of both the first core tube and the second core tube by external climbing formwork respectively;

[0010] Step 5: Use the installed fourth tower crane to construct the inner climbing formwork and outer frame structure of the first core tube, and use the installed fifth tower crane to construct the inner climbing formwork and outer frame structure of the second core tube, so as to complete the tower crane arrangement without stopping work.

[0011] As a preferred embodiment of the present invention, in the step two, when constructing the first core tube and the second core tube, the outer walls of the first to third floors are constructed by setting up external scaffolding, and when installing the outer climbing formwork of the first core tube and the second core tube, the outer climbing formwork frame body and its lower hanging frame body of the first core tube and the outer climbing formwork frame body and its lower hanging frame body of the second core tube are hoisted respectively by the second tower crane and the third tower crane; in the step three, the steel structure is hoisted into the core tube by the lower hanging frame body of the external climbing formwork to carry out foundation beam construction.

[0012] As a preferred embodiment of the present invention, in step four, the third tower crane is cut off by the second tower crane, the second tower crane is first dismantled and the fourth tower crane is installed by the truck crane, and then the third tower crane is dismantled and the fifth tower crane is installed by the truck crane.

[0013] As a preferred embodiment of the present invention, in step 4, after the fourth tower crane is installed and put into use, the fourth tower crane is used to replace the truck crane to dismantle the third tower crane and install the fifth tower crane.

[0014] As a preferred solution of the present invention, in the step one, the connecting line of the tower bodies of the second tower crane and the third tower crane is perpendicular to the first core tube and the second core tube.

[0015] As a preferred solution of the present invention, in step one, the foundations of the second tower crane and the third tower crane are positioned away from the support beam.

[0016] As a preferred solution of the present invention, the second tower crane and the third tower crane are flat-arm tower cranes, and the third tower crane and the fourth tower crane are movable-arm tower cranes.

[0017] As a preferred embodiment of the present invention, in step one, a horizontal safety distance and a vertical safety distance are set between the second tower crane and the third tower crane.

[0018] As a preferred embodiment of the present invention, in step 4, the lifting and lowering of the tower crane is controlled to maintain a safe height difference in the vertical direction between adjacent tower cranes after each tower lifting.

[0019] Compared with the prior art, the beneficial effect of the construction method for non-stop construction crane layout conversion of the embodiment of the present invention is that this construction method realizes the tower crane conversion without stopping work through reasonable construction deployment and optimized installation and disassembly plan, and minimizes the impact of tower crane installation and disassembly on on-site operations. BRIEF DESCRIPTION OF THE DRAWINGS

[0020] Figure 1 is a schematic diagram of arranging a second tower crane and a third tower crane according to an embodiment of the present invention;

[0021] Figure 2 is a schematic diagram of a tower crane conversion process according to an embodiment of the present invention;

[0022] Figure 3 It is a schematic diagram of completing the arrangement of the fourth tower crane and the fifth tower crane according to an embodiment of the present invention. DETAILED DESCRIPTION

[0023] The specific implementation of the present invention is further described in detail below in conjunction with the accompanying drawings and examples. The following examples are used to illustrate the present invention, but are not intended to limit the scope of the present invention.

[0024] In the description of the present invention, it should be understood that, unless otherwise clearly specified and limited, the terms "installation", "connection" and "connection" used in the present invention should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection, or it can be indirectly connected through an intermediate medium, or it can be the internal communication of two components. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.

[0025] In the description of the present invention, it is also necessary to understand that the orientation or positional relationship indicated by the terms "upper", "lower", "left", "right", "front", "back", "top", "bottom", etc. is based on the orientation or positional relationship shown in the accompanying drawings, and is only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the machine or component referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as a limitation on the present invention. It should be understood that the terms "first", "second", etc. are used in the present invention to describe various information, but such information should not be limited to these terms, which are only used to distinguish the same type of information from each other. For example, without departing from the scope of the present invention, the "first" information may also be referred to as the "second" information, and similarly, the "second" information may also be referred to as the "first" information.

[0026] refer to Figure 1 -3. A method for non-stop construction conversion of building crane arrangement according to an embodiment of the present invention comprises the following steps:

[0027] Step 1: During the basement construction phase, a second tower crane 2 and a third tower crane 3 are respectively arranged near both sides of the double-core tube building, wherein the double-core tube includes a first core tube 6 and a second core tube 7, and the second tower crane 2 is located near the side of the first core tube 6 facing away from the second core tube 7, and the third tower crane 3 is located near the side of the second core tube 7 facing away from the first core tube 6; the working radius of the second tower crane 2 at least covers the first core tube 6, and the working radius of the third tower crane 3 at least covers the second core tube 7, and the working radius of the second tower crane 2 and the third tower crane 3 intersect with each other, so that the second tower crane 2 and the third tower crane 3 have sufficient site coverage;

[0028] Step 2: During the ground structure construction phase, the first core tube 6 is constructed, and the outer climbing formwork is installed layer by layer on the first core tube 6 simultaneously, and the second core tube 7 is constructed, and the outer climbing formwork is installed layer by layer on the second core tube 7 simultaneously;

[0029] Step 3: When the first core tube 6 and the second core tube 7 are constructed to the third floor and the external climbing formwork is installed, foundation beams are installed on both the first core tube 6 and the second core tube 7, the tower body of the fourth tower crane 4 is installed on the foundation beam of the first core tube 6, and the tower body of the fifth tower crane 5 is installed on the foundation beam of the second core tube 7;

[0030] Step 4: simultaneously install the fourth tower crane 4 and dismantle the second tower crane 2, simultaneously install the fifth tower crane 5 and dismantle the third tower crane 3, and respectively perform continuous construction of the first core tube 6 and the second core tube 7 through external climbing formwork, so that the debugging, registration and other processes after the installation of the fourth tower crane 4 and the fifth tower crane 5 do not affect the construction of the core tube;

[0031] Step five, implement the inner climbing formwork and outer frame structure construction of the first core tube 6 through the fourth tower crane 4 after installation, and implement the inner climbing formwork and outer frame structure construction of the second core tube 7 through the fifth tower crane 5 after installation, and complete the tower crane arrangement without stopping the conversion, which ensures that the core tube can continue to be constructed upward without obstruction when it reaches the third floor. After the fourth tower crane 4 and the fifth tower crane 5 are installed, they will immediately take over the dismantling of the second tower crane 2 and the third tower crane 3, and undertake the installation of the inner climbing formwork and the construction of the outer frame structure of the core tube. The transition is smooth, avoiding the vacuum period of lifting capacity, and effectively reducing economic losses.

[0032] Exemplarily, in the step two, when the construction of the first core tube 6 and the second core tube 7 is carried out, the outer walls of the first to third floors are constructed by setting up external scaffolding, and when the outer climbing formwork of the first core tube 6 and the second core tube 7 is installed, the outer climbing formwork frame and its lower hanging frame of the first core tube 6 and the outer climbing formwork frame and its lower hanging frame of the second core tube 7 are hoisted by the second tower crane 2 and the third tower crane 3 respectively; in the step three, the steel components are hoisted into the core tube by the lower hanging frame of the external climbing formwork to carry out the construction of the foundation beams of the first to third floors; this construction process is efficient and low-cost.

[0033] Exemplarily, in step four, the third tower crane 3 is cut off by the second tower crane 2 to avoid the third tower crane 3 and the fourth tower crane 4 being too close and possibly colliding. The second tower crane 2 is first dismantled and the fourth tower crane 4 is installed by the automobile crane, and then the third tower crane 3 is dismantled and the fifth tower crane 5 is installed by the automobile crane. The automobile crane is flexibly used to carry out construction without occupying the construction site and causing any impact.

[0034] Exemplarily, in step four, after the fourth tower crane 4 is installed and put into use, the fourth tower crane 4 is used to replace the automobile crane to dismantle the third tower crane 3 and install the fifth tower crane 5, thereby further reducing the investment in automobile cranes and effectively utilizing the fourth tower crane 4 without waste.

[0035] refer to Figure 1 Exemplarily, in the step one, the tower body connection line of the second tower crane 2 and the third tower crane 3 is perpendicular to the first core tube 6 and the second core tube 7, which effectively improves the coverage rate of the material yard at the edge of the site, and effectively ensures the width required for the installation of the external climbing formwork of the core tube, avoids the conflict between the climbing formwork installation and the position of the tower crane tower body, and evenly distributes the lifting capacity of the fourth tower crane 4 and the fifth tower crane 5 in the middle of the two core tubes.

[0036] Exemplarily, in step one, the foundation positioning of the second tower crane 2 and the third tower crane 3 avoids the support beam, reduces the construction of dismantling and replacing supports in the foundation pit, and avoids the professional machine room as much as possible, minimizing the impact on the subsequent installation and commissioning of electromechanical equipment.

[0037] refer to Figure 1 -3. Exemplarily, the second tower crane 2 and the third tower crane 3 are flat-arm tower cranes, and the third tower crane 3 and the fourth tower crane 4 are movable-arm tower cranes. The tower cranes are rationally allocated and selected to ensure construction efficiency.

[0038] refer to Figure 1 For example, in step one, a horizontal safety distance and a vertical safety distance are set between the second tower crane 2 and the third tower crane 3 to ensure that anti-collision requirements are met.

[0039] Exemplarily, in step 4, the lifting and lowering of the tower crane is controlled to maintain a safe height difference in the vertical direction between adjacent tower cranes after each tower lifting to avoid collision accidents.

[0040] The above is only a preferred embodiment of the present invention. It should be pointed out that for ordinary technicians in this technical field, several improvements and substitutions can be made without departing from the technical principles of the present invention. These improvements and substitutions should also be regarded as the scope of protection of the present invention.

Claims

1. A construction method for changing the layout of a building crane without stopping work, characterized in that The following steps are involved: Step 1: During the basement construction phase, a second tower crane and a third tower crane are respectively arranged near both sides of the double core tube building, wherein the double core tube includes a first core tube and a second core tube, the second tower crane is located near a side of the first core tube facing away from the second core tube, and the third tower crane is located near a side of the second core tube facing away from the first core tube; Step 2: During the ground structure construction phase, the first core tube is constructed, and the outer climbing formwork is installed layer by layer on the first core tube simultaneously; the second core tube is constructed, and the outer climbing formwork is installed layer by layer on the second core tube simultaneously; Step 3: When the first core tube and the second core tube are constructed to the third floor and the external climbing formwork is installed, foundation beams are installed on both the first core tube and the second core tube, the tower body of the fourth tower crane is installed on the foundation beam of the first core tube, and the tower body of the fifth tower crane is installed on the foundation beam of the second core tube; Step 4: simultaneously installing the fourth tower crane and dismantling the second tower crane, simultaneously installing the fifth tower crane and dismantling the third tower crane, and performing continuous construction of both the first core tube and the second core tube by external climbing formwork respectively; Step 5: Use the installed fourth tower crane to implement the inner climbing formwork and outer frame structure construction of the first core tube, and use the installed fifth tower crane to implement the inner climbing formwork and outer frame structure construction of the second core tube, so as to complete the tower crane layout and non-stop conversion; In the step 2, when the first core tube and the second core tube are constructed, the outer walls of the first to third floors are constructed by setting up external scaffolding, and when the outer climbing formwork of the first core tube and the second core tube are installed, the outer climbing formwork frame and its lower hanging frame of the first core tube and the outer climbing formwork frame and its lower hanging frame of the second core tube are hoisted by the second tower crane and the third tower crane respectively; in the step 3, the steel structure is hoisted into the core tube by the lower hanging frame of the outer climbing formwork for foundation beam construction; in the step 4, the third tower crane is cut off by the second tower crane, the second tower crane is first dismantled and the fourth tower crane is installed by the automobile crane, and then the third tower crane is dismantled and the fifth tower crane is installed by the automobile crane. After the fourth tower crane is installed and put into use, the fourth tower crane is used to replace the automobile crane to dismantle the third tower crane and install the fifth tower crane.

2. A method for non-stop construction of tower crane layout conversion according to claim 1, characterized in that: In the step 1, the tower body connection line of the second tower crane and the third tower crane is perpendicular to the first core tube and the second core tube.

3. A method for non-stop construction of tower crane layout according to claim 1, characterized in that: In the step 1, the foundations of the second tower crane and the third tower crane are positioned away from the support beam.

4. The method for non-stop construction of tower crane arrangement according to claim 1 is characterized in that: The second tower crane and the third tower crane are flat-arm tower cranes, and the third tower crane and the fourth tower crane are movable-arm tower cranes.

5. The method for non-stop construction of tower crane arrangement according to claim 1, characterized in that: In the step 1, a horizontal safety distance and a vertical safety distance are set between the second tower crane and the third tower crane.

6. The method for non-stop construction of tower crane arrangement according to claim 1, characterized in that: In the step 4, the lifting and lowering of the tower crane is controlled to maintain a safe height difference in the vertical direction between adjacent tower cranes after each tower lifting.

Citation Information

Patent Citations

  • Method for disassembling large tower crane by utilizing small tower crane

    CN104876131A

  • Large-differential double-tower crane hoisting construction method

    CN107140534A