A construction process for outer frame protection screen

By using a mobile hydraulic lifting system and anchoring device in super high-rise buildings, the problems of resource waste and low construction efficiency in existing outer frame protection structures have been solved, enabling flexible construction applications and resource conservation, and improving construction efficiency.

CN116220405BActive Publication Date: 2024-12-03CHINA CONSTR SECOND ENG BUREAU LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202310118566.3
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2023-02-13
Publication Date
2024-12-03
Estimated Expiration
2043-02-13

AI Technical Summary

Technical Problem

Existing external frame protective structures suffer from problems such as resource waste, low construction efficiency, poor operability, and inflexible resource allocation in the construction of super high-rise buildings, and cannot meet the needs of different construction progress.

Method used

By employing a mobile hydraulic lifting system and anchoring devices, and setting anchoring points in both non-clamping and clamping sections, combined with anti-tilting devices and tie rods, the protective platform can be flexibly raised and stably connected, reducing resource consumption and adapting to different construction schedules.

Benefits of technology

It improves the flexibility and efficiency of the construction process, reduces resource consumption, adapts to the needs of multi-level and non-multi-level construction, and shortens the construction period.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN116220405B_ABST
    Figure CN116220405B_ABST
Patent Text Reader

Abstract

The invention discloses a construction process of an external frame protection screen, comprising the following steps: anchoring a protection platform, wherein in a non-jump-layer construction section, the anchoring point of the protection platform is set at the bottom of a layer plate below the top layer of the protection platform, and when the curing of the lowest layer of concrete is completed, the protection platform is lifted by a mobile hydraulic lifting system; in a jump-layer construction section, the anchoring point of the protection platform is set at the bottom of a plate at a jump-layer start layer and an end layer, and after the jump-layer column is completely constructed, the protection platform is lifted by a tower crane; at the position of the adjacent working surface of the side column, the protection platform is anchored and connected by at least one anchoring device respectively located on both sides of the side column, and an independent protection platform is set up on both sides of the adjacent working surface of the corner column, one protection platform is anchored and connected by at least one anchoring device respectively located on both sides of the corner column, and the other protection platform is anchored and connected by at least one anchoring device, and the two protection platforms are overlapped and connected at corresponding close positions.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of building construction, and in particular to a construction process for an outer frame protection screen. Background Art

[0002] At present, steel-concrete columns combined with truss floor decks are a frequently used structural type for super high-rise buildings. The reinforcement binding and concrete pouring of the truss floor decks can be completed on the floor. The safety protection around the working floor slabs generally uses guardrails to meet the construction requirements. The edge lines of the outer frame columns are flush with the edge lines of the structural floor slabs, resulting in the outer edge of the outer frame columns being exposed to the air. When the side columns are steel-framed and reinforced concrete composite columns, the reinforcement binding, formwork installation and concrete pouring processes of the columns require personnel to stand on the outside of the columns to complete the construction work. Therefore, it is necessary to apply protection and construction platform structures to the edges of the side columns.

[0003] At present, there are many forms of external protection commonly used in construction, such as guardrails, scaffolding, climbing frames and side column protection platforms, while the climbing frame of the integral structure has the functions of both an operating platform and protection, and has good functionality and safety. However, since an operating platform is only required during the construction of the outer frame columns, and no operating platform is required during the construction of the outer frame structure floor, the use of the integral climbing frame will not only cause waste, but also hinder the installation of the construction elevator, resulting in the number of covered floors of the construction elevator being lower than the height of the climbing frame, which is not conducive to improving construction efficiency and has poor economy. On the other hand, the climbing of the integral climbing frame is not flexible enough. The construction area of ​​each layer of the outer frame structure is divided into three parts based on the position of the core tube. When the construction progress of different areas is inconsistent, the integral climbing frame cannot be climbed separately according to the construction progress of different areas, and the operability is limited. In addition, when the leap section and the non-leap section appear alternately, the climbing attachment device of the climbing frame is difficult to arrange and the operability is poor.

[0004] The side column protection platform is a "concave-shaped" side column protection platform, which has the dual functions of providing a construction platform and safety protection. Its functionality meets the requirements, but it cannot climb autonomously and needs to be lifted by a tower crane. The side column protection platform will occupy part of the tower crane resources, hindering the construction of the outer frame structure. Secondly, the side column protection platform can only cover one floor, which can neither meet the requirements of steel bar binding cycle construction nor adapt to the situation where the construction height of the split-level column is too large.

[0005] These old construction techniques of external protective structures cannot meet the construction needs well, nor can they better address the current requirements for improving construction efficiency and reducing resource utilization. Summary of the invention

[0006] The purpose of the present invention is to provide a construction process for an outer frame protection screen that meets construction requirements, improves construction efficiency and reduces resource occupation.

[0007] A construction process for an external frame protective screen comprises the following steps: anchoring a protective platform, wherein in a non-jump-level construction section, the anchor point of the protective platform is set at the bottom of a layer plate below the top layer of the protective platform, and when the curing of the lowest concrete layer is completed, the protective platform is lifted by a mobile hydraulic lifting system; in a jump-level construction section, the anchor point of the protective platform is set at the bottom of the plate at the start and end layers of the jump-level, and after the jump-level column is completely constructed, the protective platform is lifted by a tower crane; at the adjacent working surface of the side column, the protective platform is anchored and connected by at least one anchor device located on both sides of the side column, and an independent protective platform is set up on both sides of the adjacent working surface of the corner column, one protective platform is anchored and connected by at least one anchor device located on both sides of the corner column, and the other protective platform is anchored and connected by at least one anchor device, and the two protective platforms are overlapped and connected at corresponding close locations.

[0008] As a preferred embodiment of the present invention, when anchoring on a concrete floor, the middle of the anchoring device is aligned with the reserved hole of the concrete floor, steel components are arranged on the anchoring device and on the lower side of the concrete floor, and a pair of drawing rods are passed through the reserved holes of the steel components, the anchoring device and the concrete floor and locked with nuts.

[0009] As a preferred embodiment of the present invention, when anchoring on the structural steel beam, the anchoring installation begins after the steel truss floor deck is laid. The anchoring device is horizontally perpendicular to the structural steel beam, and two steel structure pads distributed one after the other along the axial direction of the anchoring device are arranged on the steel truss floor deck between the anchoring device and the structural steel beam. A steel member is placed vertically on the anchoring device, a hoop is vertically arranged on the bottom side of the structural steel beam, and at least two tension rods distributed front and back are passed through the steel member, the anchoring device, the steel structure pad, the steel truss floor deck and the hoop and locked with nuts.

[0010] As a preferred embodiment of the present invention, when anchoring the floor near the inner side of the structural steel beam, two steel structure pads distributed one in front and one in back along the axial direction of the anchoring device are arranged on the steel truss floor deck at the structural steel beam, and a cantilever beam is arranged on the steel structure pad, a steel member is arranged on the cantilever beam, a hoop is vertically arranged on the bottom side of the structural steel beam, and at least two tension rods distributed front and back are passed through the steel member, cantilever beam, steel structure pad, steel truss floor deck and hoop and locked with nuts, the anchoring device is arranged on the cantilever beam, the steel member is arranged on the anchoring device, and the tension rods are passed through the steel member, the anchoring device and the cantilever beam and locked with nuts.

[0011] As a preferred embodiment of the present invention, the steel structure pad is a box-shaped body formed by welding rectangular steel blocks at both ends, and the thickness of the steel structure pad is the thickness of the concrete slab to be cast, and the steel structure pad is wrapped with extruded board on all sides.

[0012] As a preferred solution of the present invention, a steel gasket abutting against the nut is installed on the drawing rod, and a waist-shaped hole extending in the axial direction is provided in the middle of the anchoring device.

[0013] As a preferred embodiment of the present invention, the mobile hydraulic lifting system includes a hydraulic jack, a climbing boot, a guide rail and a guide boot. When the protective platform climbs on a non-step layer, the climbing boot fixed to the hook on the guide rail is pushed by the hydraulic jack, so that the guide rail drives the protective platform to rise. When the hydraulic jack contracts, the guide boot abuts against the hook of the guide rail.

[0014] As a preferred solution of the present invention, in the non-step section, the upper part of the protection platform is connected to the main structure through an anti-tilt device, the anti-tilt device includes a beam holding device, a connecting beam and a U-shaped steel, the lower end of the beam holding device is connected to the connecting beam so as to be horizontally adjustable, the connecting beam is connected to the protection platform, the upper side of the beam holding device is clamped with the lower end of the structural steel beam and can be adjusted and installed through bolts to fit the connecting hole for fastening.

[0015] Compared with the prior art, the construction process of an outer frame protection screen in an embodiment of the present invention has the beneficial effects of being able to flexibly carry out construction applications as needed, being well adapted to leap floors and non-leap floors, being able to well save resource occupation, and being able to effectively help reduce construction period and improve construction efficiency. BRIEF DESCRIPTION OF THE DRAWINGS

[0016] Figure 1 This is an installation elevation diagram of an embodiment of the present invention on a non-metamorphosis floor;

[0017] Figure 2 This is an installation elevation diagram of an embodiment of the present invention on a mezzanine floor;

[0018] Figure 3 is a plan view of the installation of an embodiment of the present invention at a side column position;

[0019] Figure 4 is a plan view of the installation of an embodiment of the present invention at a corner column position;

[0020] Figure 5 is a side view of an installation structure for anchoring on a concrete floor slab according to an embodiment of the present invention;

[0021] Figure 6 yes Figure 5 A top view of the installation structure of the embodiment;

[0022] Figure 7 is a side view of an installation structure of an embodiment of the present invention anchored on a structural steel beam;

[0023] Figure 8 is a side view of the installation structure of an embodiment of the present invention anchored on an inner structural steel beam;

[0024] Fig. 9 This is an installation and application elevation view of a mobile hydraulic lifting system according to an embodiment of the present invention;

[0025] Fig.10 It is an installation and application elevation view of the anti-tilt device according to an embodiment of the present invention. DETAILED DESCRIPTION

[0026] The specific implementation of the present invention is further described in detail below in conjunction with the accompanying drawings and examples. The following examples are used to illustrate the present invention, but are not intended to limit the scope of the present invention.

[0027] In the description of the present invention, it should be understood that, unless otherwise clearly specified and limited, the terms "installation", "connection" and "connection" used in the present invention should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection, or it can be indirectly connected through an intermediate medium, or it can be the internal communication of two components. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.

[0028] In the description of the present invention, it is also necessary to understand that the orientation or positional relationship indicated by the terms "upper", "lower", "left", "right", "front", "back", "top", "bottom", etc. is based on the orientation or positional relationship shown in the accompanying drawings, and is only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the machine or component referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as a limitation on the present invention. It should be understood that the terms "first", "second", etc. are used in the present invention to describe various information, but such information should not be limited to these terms, which are only used to distinguish the same type of information from each other. For example, without departing from the scope of the present invention, the "first" information may also be referred to as the "second" information, and similarly, the "second" information may also be referred to as the "first" information.

[0029] refer to Figure 1-4. A construction process for an outer frame protection screen according to an embodiment of the present invention comprises the following steps: anchoring a protection platform 1 whose width is not affected by changes in the size of the side columns and the height of the floor, whose length is equal to the size of the adjacent side columns + the width of the working surface of the scaffolding on both sides + the distance between the scaffolding and the side columns, and whose height is greater than the sum of the heights of three non-leaf floors; in the non-leaf construction section, the anchor point of the protection platform 1 is set at the bottom of the slab three or more layers below the top layer of the protection platform 1; combined with the steel bar super-layer circulation construction technology, the lower layer concrete demolding and curing, the middle layer concrete pouring and the upper layer steel bar binding construction can be carried out simultaneously, which greatly improves the construction speed; and when the curing of the lowest layer concrete is completed, it can be climbed immediately, using a mobile hydraulic lifting system for climbing; in the leap construction section, the anchor point of the protection platform 1 is set at the bottom of the slab of the starting layer and the ending layer of the leap, and a steel pipe rack and a diagonal tie rod are set up at the floor of the starting layer of the leap to improve the stability of the protection platform, waiting for the construction to be completed. After the construction of the leap column is completed, it can be lifted by a tower crane; at the adjacent working surface of the side column 5, the protection platform 1 is anchored and connected by at least one anchoring device 2 located on both sides of the side column 5, and an independent protection platform 1 is set up on both sides of the adjacent working surface of the corner column 6, one protection platform 1 is anchored and connected by at least one anchoring device 2 located on both sides of the corner column 6, and the other protection platform 1 is anchored and connected by at least one anchoring device 2, and the two protection platforms 1 are overlapped and connected between the corresponding gaps in the vicinity, that is, the anchoring devices 2 of the two protection platforms 1 at the corner column 6 are vertically distributed and do not interfere with each other, and the two protection platforms 1 support each other; therefore, the construction process of the outer frame protection screen can be flexibly applied as needed, can adapt to leap layers and non-leap layers, can save resources well, and can effectively help reduce construction period and improve construction efficiency.

[0030] refer to Figure 5 and 6 For example, when anchoring on a concrete floor, anchoring installation begins after the strength of the concrete structural slab reaches 20 MPa. The middle of the anchor device 2 is aligned with the reserved hole of the concrete floor. A steel member 21 is arranged on the anchor device 2 and on the lower side of the concrete floor. A pair of tension rods 22 are passed through the steel member 21, the anchor device 2 and the reserved hole of the concrete floor and are locked with nuts. Preferably, each anchor device 2 is installed on the concrete floor in an axially distributed manner through at least two groups of steel members 21 and tension rods 22.

[0031] refer to Figure 7For example, when anchoring on the structural steel beam, the anchoring installation begins after the steel truss floor deck is laid. The anchoring device 2 is horizontally perpendicular to the structural steel beam, and two steel structure pads 23 distributed one after the other along the axial direction of the anchoring device 2 are arranged on the steel truss floor deck 7 between the anchoring device 2 and the structural steel beam, and a steel member 21 is placed vertically on the anchoring device 2. A hoop 24 is vertically arranged on the bottom side of the structural steel beam, and at least two tension rods 22 distributed front and back are passed through the steel member 21, the anchoring device 2, the steel structure pad 23, the steel truss floor deck 7 and the hoop 24 and are locked with nuts, so that the structural steel beam is avoided from both sides by the tension rods 22 and the anchoring installation is realized.

[0032] refer to Figure 8 For example, when anchoring the floor near the inner side of the structural steel beam, two steel structure pads 23 distributed one in front of the other along the axial direction of the anchoring device 2 are arranged on the steel truss floor deck 7 at the structural steel beam, and a cantilever beam 25 is arranged on the steel structure pad 23, and a steel member 21 is arranged on the cantilever beam 25, and a hoop 24 is vertically arranged on the bottom side of the structural steel beam, and at least two tension rods 22 distributed front and back are passed through the steel member 21, the cantilever beam 25, the steel structure pad 23, the steel truss floor deck 7 and the hoop 24 and locked with nuts, the anchoring device 2 is arranged on the outward extending part of the cantilever beam 25, the steel member 21 is arranged on the anchoring device 2, and the tension rod 22 is passed through the steel member 21, the anchoring device 2 and the cantilever beam 25 and locked with nuts, so as to realize the extension connection between the anchoring device 2 and the structural steel beam on the cantilever beam 25.

[0033] refer to Figure 7 Or 8, illustratively, the steel structure pad 23 is a box-shaped body formed by welding the ends of rectangular steel blocks, and the thickness of the steel structure pad 23 is the thickness of the concrete slab to be cast, so as to avoid covering the anchor device 2 when the concrete floor is cast, and the steel structure pad 23 is wrapped with extruded board on all sides to facilitate the removal of the steel structure pad 23 during dismantling.

[0034] refer to Figure 5 -8. Exemplarily, a steel gasket 26 abutting against the nut is installed on the drawing rod 22, so that the steel gasket 26 abuts between the nut and the steel member 21, the clamp 24 or the cantilever beam 25, thereby improving the firmness of the locking connection. A waist-shaped hole extending in the axial direction is provided in the middle of the anchor device 2, so as to facilitate the adjustment of the installation position of the anchor device 2.

[0035] refer to Fig. 9The lifting mechanism 32 is actuated by the hydraulic jack 31 and the lifting shoe 32 is actuated by the guide shoe 34. The lifting mechanism 32 is actuated by the hydraulic jack 31 and the lifting shoe 32 is actuated by the guide shoe 34. The lifting mechanism 32 is actuated by the hydraulic jack 31 and the lifting shoe 32 is actuated by the guide shoe 34.

[0036] refer to Fig.10 For example, in the non-step section, the upper part of the protection platform 1 is connected to the main structure through an anti-tilt device, the anti-tilt device includes a beam holding device 41, a connecting beam 42 and a U-shaped steel 43, the lower end of the beam holding device 41 is connected to the connecting beam 42 in a horizontally adjustable manner, the connecting beam 42 is connected to the protection platform 1, the upper side of the beam holding device 41 is clamped with the lower end of the structural steel beam and the U-shaped steel 43 can be adjusted and installed through the bolt-matching connecting hole for fastening, so that the horizontal force of the wind load acting on the upper part of the protection platform 1 can be transmitted to the main structure, ensuring the safety and stability of the protection platform 1.

[0037] The above is only a preferred embodiment of the present invention. It should be pointed out that for ordinary technicians in this technical field, several improvements and substitutions can be made without departing from the technical principles of the present invention. These improvements and substitutions should also be regarded as the scope of protection of the present invention.

Claims

1. A construction process for an outer frame protective screen, characterized in that The steps include: anchoring the protection platform, in the non-jump-layer construction section, the anchor point of the protection platform is set at the bottom of the layer plate below the top layer of the protection platform, and when the bottom layer concrete curing is completed, it is climbed by a mobile hydraulic lifting system; in the jump-layer construction section, the anchor point of the protection platform is set at the bottom of the plate of the jump-layer starting layer and the ending layer, and the tower crane is used to lift it after the jump-layer column is completely constructed; at the position of the adjacent working surface of the side column, the protection platform is anchored and connected by at least one anchor device on both sides of the side column, and an independent protection platform is set up on both sides of the adjacent working surface of the corner column, one protection platform is anchored and connected by at least one anchor device on both sides of the corner column, and the other protection platform is anchored and connected by at least one anchor device, and the two protection platforms are overlapped and connected at corresponding close locations; When anchoring on the structural steel beam, the anchoring installation begins after the steel truss floor deck is laid. The anchoring device is horizontally perpendicular to the structural steel beam. Two steel structure pads are arranged on the steel truss floor deck between the anchoring device and the structural steel beam, one in front of the other along the axial direction of the anchoring device. A steel member is placed vertically on the anchoring device, and a hoop is vertically arranged on the bottom side of the structural steel beam. At least two tension rods distributed front and back are passed through the steel member, the anchoring device, the steel structure pad, the steel truss floor deck and the hoop and locked with nuts. When anchoring the floor near the inner side of the structural steel beam, two steel structure pads are arranged on the steel truss floor deck at the structural steel beam, one in front of the other in the axial direction of the anchor device, and a cantilever beam is arranged on the steel structure pad, a steel member is arranged on the cantilever beam, and a hoop is vertically arranged on the bottom side of the structural steel beam, and at least two tension rods distributed front and back are passed through the steel member, the cantilever beam, the steel structure pad, the steel truss floor deck and the hoop and locked with nuts, the anchor device is arranged on the cantilever beam, the steel member is arranged on the anchor device, and the tension rod is passed through the steel member, the anchor device and the cantilever beam and locked with nuts; The steel structure pad is a box-shaped body formed by welding the ends of rectangular steel blocks, and the thickness of the steel structure pad is the thickness of the concrete slab to be poured, and the steel structure pad is wrapped with extruded panels on all sides.

2. The outer frame protection screen construction process according to claim 1 is characterized in that: A steel gasket abutting against a nut is installed on the drawing rod, and a waist-shaped hole extending in the axial direction is arranged in the middle of the anchoring device.

3. The outer frame protection screen construction process according to claim 1 is characterized in that: The mobile hydraulic lifting system includes a hydraulic jack, a climbing shoe, a guide rail and a guide shoe. When the protective platform climbs on a non-step layer, the hydraulic jack pushes the climbing shoe fixed to the hook on the guide rail, so that the guide rail drives the protective platform to rise. When the hydraulic jack contracts, the guide shoe abuts against the hook of the guide rail.

4. The outer frame protection screen construction process according to claim 1 is characterized in that: In the non-step section, the upper part of the protection platform is connected to the main structure through an anti-tilt device. The anti-tilt device includes a beam holding device, a connecting beam and a U-shaped steel. The lower end of the beam holding device can be connected to the connecting beam in a horizontally adjustable manner. The connecting beam is connected to the protection platform. The upper side of the beam holding device is clamped with the lower end of the structural steel beam and can be adjusted and installed through bolts and connecting holes to fasten the U-shaped steel.