Drainage riser installation device and installation method
Through the combination of cable tracks and sliding frames, the problems of low installation efficiency and high safety risks of rainwater riser pipes in narrow working spaces are solved, and mechanized construction is achieved, cost reduction and efficiency and accuracy are improved.
Patent Information
- Application Number
- CN202310255958.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2023-03-16
- Publication Date
- 2024-11-05
- Estimated Expiration
- 2043-03-16
AI Technical Summary
In the rain and sewage diversion renovation project in urban communities, the narrow working space limits the installation efficiency and safety of rainwater risers. The existing mechanical equipment is costly and has high safety risks, and the installation efficiency is low.
Using the combination of cable tracks and sliding frames, drilling devices, locker installation devices, pipeline transportation devices and locking ring installation devices, through wireless positioning and hydraulic support technologies, the mechanized construction of drainage risers is realized, reducing costs, Improve efficiency and reduce safety risks.
Mechanized construction of drainage riser under narrow conditions has been achieved, which reduces construction costs, improves efficiency, and reduces safety risks. The drilling accuracy and locking rings are improved through the cooperation of hydraulic support and sliding frame. Automatic positioning function.
Smart Images

Figure CN116336255B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of drainage pipe installation, and in particular to drainage riser installation equipment and an installation method. Background Art
[0002] When carrying out rainwater and sewage diversion renovation projects in urban areas, the key work in the renovation of combined risers is generally to add new rainwater risers to achieve the purpose of rainwater and sewage diversion. However, due to the narrow working space, mechanical equipment such as ladders cannot be used, and they can only rely on setting up double-row scaffolding or manual seat installation methods. For the former, the construction speed is slow and the cost is high, especially the high measure fee, which is very uneconomical. For the latter, the safety risk is high and the regulations have prohibited its use.
[0003] Meanwhile, in the process of installing pipes, drilling, socket installation, pipe docking and installation and clamping are usually considered as one cycle unit. After one cycle unit is completed, the next cycle unit is started again from drilling, which leads to low installation efficiency.
[0004] Therefore, the project and the site require a drainage riser installation device and installation method for narrow working spaces. Summary of the invention
[0005] The object of the present invention is to provide a drainage riser installation device and an installation method, which realizes the mechanized construction of the drainage riser through a steel cable track and a sliding frame, a drilling device, a clamping seat installation device, a pipeline transportation device, a clamping ring installation device, an operating platform and other devices, thereby reducing the construction cost, improving the construction efficiency, reducing the safety risk, and solving the above-mentioned problems of high safety risk and low installation efficiency.
[0006] In order to overcome the above-mentioned shortcomings, the present invention provides a drainage riser installation device, including a steel cable track and an operating platform, wherein the steel cable track is provided with a plurality of sliding frames that operate independently of each other, and the steel cable track is provided with a drilling device, a clamping seat installation device, a pipeline transportation device and a clamping ring installation device that operate independently of each other in sequence, and the drilling device, the clamping seat installation device, the pipeline transportation device and the clamping ring installation device are all braked and slidably matched with the steel cable track through the sliding frame, the drilling end of the drilling device faces the wall, the clamping seat installation device installs the clamping seat at the drilling position of the drilling device, the pipeline transportation device transports the pipe body to the clamping seat and installs and docks with the upper pipe body, and the clamping ring installation device fixes the pipe body by fixing the clamping ring with the corresponding clamping seat.
[0007] Preferably, the steel cable track and sliding frame, drilling device, socket installation device, pipeline transportation device and clamping ring installation device are all connected to the operating platform by wireless signals, the steel cable track includes a mounting bracket fixed on the top of the wall, a hoisting device and a positioning reference device installed on the mounting bracket, a steel cable connected to the hoisting device and an anchoring end provided at the bottom of the steel cable, the sliding frame and the steel cable are movably fixedly matched by an electric pulley block, the sliding frame is provided with a positioning device, and a plurality of mounting holes are provided in the middle part of the sliding frame, the sliding frame is fixedly matched with the drilling device, the socket installation device, the pipeline transportation device and the clamping ring installation device through the mounting holes and the mounting parts, and the sliding frame corresponds to the drilling device, the socket installation device, the pipeline transportation device and the clamping ring installation device one by one, and the positioning device is connected to the operating platform by wireless signals through the positioning reference device.
[0008] As a more preferred embodiment, the drilling device includes a first fixed bracket, which is fixed to the sliding frame by fasteners on the side away from the wall, and the first fixed bracket is provided with a plurality of hydraulic legs symmetrical about the middle position of the first fixed bracket on the side close to the wall, the hydraulic legs are perpendicular to the wall, and anchor drill bits are provided at the ends of the hydraulic legs, and the output ends of the anchor drill bits point to the wall, and a first sliding bracket is provided in the middle position of the first fixed bracket so as to be laterally movable, and a first hydraulic jacking device is provided on the first sliding bracket, and the first hydraulic jacking device is perpendicular to the wall, and a drilling rig is provided on the output end of the first hydraulic jacking device, and a punching drill bit is provided on the output end of the drilling rig, and the punching drill bit, the drilling rig and the output end of the first hydraulic jacking device are concentric and coaxial, and a camera is provided on the first hydraulic jacking mechanism located on one side of the drilling rig, and the camera end of the camera is aimed at the wall, and the holder mounting device is located below the drilling device.
[0009] Furthermore, the card seat installation device includes a second fixed bracket, which is fixedly cooperated with the sliding frame by fasteners on the side away from the wall, and second sliding brackets are slidably provided on both sides of the second fixed bracket along a direction perpendicular to the wall, a card seat box is provided between the second sliding brackets, and first hydraulic adjustment devices are respectively provided between the two sides of the card seat box and the corresponding second sliding brackets, and the central axis of the first hydraulic adjustment device is located on the same horizontal line, a Y-shaped groove is provided in the card seat box, and a plurality of card seats are stacked in the Y-shaped groove, a card seat installation channel is provided on one side of the card seat box, a first spring device is provided between the bottom of the card seat box on the side away from the card seat installation channel and the card seat, a card seat jacking device and a card seat fixing device are provided on the side of the card seat installation channel away from the wall, a camera is provided on one side of the card seat box, and the pipeline transportation device is located below the card seat installation device.
[0010] Furthermore, the pipeline transportation device includes an upper device, a middle device and a lower device, the upper device is located between the card seat installation device and the clamping ring installation device, the middle device and the lower device are located below the clamping ring installation device, the structures of the upper device, the middle device and the lower device are similar, and all include a third fixed bracket, a third sliding bracket that is laterally slidably matched with the third fixed bracket, a second hydraulic adjustment device that is fixedly matched with the third sliding bracket, and a grasping clamp that is fixedly matched with the output end of the second hydraulic adjustment device, the grasping clamp is controlled to open and close by a grasping clamp power device, and the open end of the grasping clamp faces the wall, a camera is provided on one side of the second hydraulic adjustment device, rubber pads are provided on the grasping clamps located at the upper device and the lower device, and a plurality of rolling pulleys are provided at equal intervals along the clamp wall on the inner side of the grasping clamp located at the middle device, the rolling pulleys are provided with electronic locks for braking, and rubber rings are provided on the surfaces of the rolling pulleys.
[0011] Furthermore, the snap ring installation device includes a fourth fixed bracket, and fourth sliding brackets are slidably provided on both sides of the fourth fixed bracket in a direction perpendicular to the wall, a snap ring box is provided between the fourth sliding brackets, and third hydraulic adjustment devices are respectively provided on both sides of the snap ring box and between the corresponding fourth sliding brackets, and the central axis of the third hydraulic adjustment device is located on the same horizontal line, an inverted U-shaped groove is provided in the snap ring box, and a plurality of snap rings are stacked in the inverted U-shaped groove, a snap ring installation channel is provided on one side of the snap ring box, a second spring device is provided between the bottom of the snap ring box and the snap ring on the side away from the snap ring installation channel, a snap ring jacking device and a snap ring fixing device are provided on the side of the snap ring installation channel away from the wall, and a camera is provided on one side of the snap ring box.
[0012] A method for installing a drainage riser using the drainage riser installation device comprises the following steps:
[0013] The first step is to install the steel cable track and the sliding frame, and respectively install the drilling device, the card seat installation device, the pipeline transportation device and the clamping ring installation device on different sliding frames. The devices are arranged in sequence from top to bottom. The drilling device, the card seat installation device, the pipeline transportation device and the clamping ring installation device are positioned by wireless positioning technology, and the installation position is determined by the operating platform;
[0014] In the second step, the drilling device moves to the first installation position to drill a hole;
[0015] In the third step, the drilling device moves up to the next installation position to drill holes, and the card holder installation device moves up to the drilling position in the previous step to install the card holder;
[0016] In the fourth step, the drilling device moves up to the next installation position to drill holes, the holder installation device moves up to the drilling position in the previous step to install the holder, the pipeline transportation device extracts the pipeline to the holder installation position in the first two steps to butt-jointly install the pipeline, and the clamping ring installation device moves up to the holder installation position in the first two steps to fix the clamping ring to the corresponding holder;
[0017] Step 5, repeat the operation of step 4 until all installation positions are drilled, move the drilling device to a suitable position and close the drilling device, until all the card holders are installed, move the card holder installation device to a suitable position and close the card holder installation device, until all the pipes and clamps are installed, move the pipe transport device and the clamp ring installation device to a suitable position and close them;
[0018] Step 6: Check the pipeline installation status through the camera, reset each device and disassemble it.
[0019] Preferably, the drilling device, socket installation device, pipeline transport device and clamp ring installation device in the fourth step and the fifth step operate independently and synchronously, and the operating platform monitors the operation process of each device in real time through a camera. When problems occur in the operation of each device, the operating platform can switch to manual operation mode for manual installation.
[0020] As a more preferred embodiment, the pipeline transport device in the fourth step clamps the middle and upper parts and the lower parts of the pipeline respectively through the middle device and the lower device. At this time, the rolling pulley of the middle device is in a braking state through the electronic lock, and stops moving when it moves up close to the clamping ring installation device. The rolling pulley of the middle device is unlocked by the electronic lock to release the braking state, and the lower device moves upward to push the pipeline until the upper part of the pipeline is located in the clamp of the upper device and the middle and lower part of the pipeline is located in the clamp of the middle device. The clamp of the upper device clamps the upper part of the pipeline, and the rolling pulley of the middle device is in a braking state through the electronic lock. The middle device and the upper device dock and install the pipeline, and the clamping ring device fixes the installed pipeline by fixing the clamp with the corresponding clamping seat.
[0021] Furthermore, it is characterized in that after the corresponding clamping ring of the pipeline transportation device in the fourth step is installed, the lower device and the middle device move down to re-clamp the pipeline and move up to wait for the fifth step operation.
[0022] Beneficial effects of the present invention:
[0023] 1. This equipment can realize the construction of drainage risers under relatively narrow conditions. It does not require the construction of separate scaffolding or personnel working at heights. It realizes the mechanized construction of drainage risers, and introduces its construction methods and process flow in detail, and explains the work content of each device in each process. This equipment has low construction cost, high construction efficiency and low safety risk;
[0024] 2. The equipment is equipped with an independent frame and is divided into four independent parts, namely, a drilling device, a holder installation device, a pipeline transportation device, and a clamping ring installation device, so as to realize the flow operation of drilling, holder installation, and pipeline installation. Drilling, holder installation, and pipeline installation are carried out synchronously at different positions, which greatly speeds up the construction efficiency.
[0025] 3. The drilling device is equipped with hydraulic supports and anchoring devices to improve the stability of drilling. In addition, the drilling position can be adjusted through the sliding frame and sliding supports to improve the accuracy of the drilling device;
[0026] 4. The base installation device and the snap ring installation device realize the automatic positioning function of the base installation by setting a sliding bracket, a hydraulic adjustment device and a positioning camera, without manual control and adjustment, which improves the practicality of the equipment; in addition, the base box, the snap ring box and the spring device are set to realize continuous operation and improve the equipment efficiency; in addition, the hydraulic jacking device and the fixing device are innovatively installed on the base box and the snap ring box to realize the installation function of the base and the snap ring;
[0027] 5. The pipeline transportation device is equipped with three sections: upper, middle and lower. Rolling pulleys, electronic locks and other devices are installed in the middle device to achieve continuous pipeline installation, greatly improving the efficiency of pipeline installation. In addition, the automatic measurement of data by cameras and multiple positioning devices realize the automatic alignment function of the pipeline installation process, and the manual confirmation after alignment ensures the quality of the operation.
[0028] 6. Set up a standard sliding frame, and connect the fixing brackets of the drilling device, the card seat installation device, the pipeline transportation device, the clamping ring installation device and other devices by screwing, so as to realize the convenience of equipment installation. At the same time, the number of each device can be adjusted as needed to realize more functions;
[0029] 7. The adjustable support equipment is simple and can also be used for the laying of municipal pipelines such as water supply, gas, and cables, and has strong adaptability. BRIEF DESCRIPTION OF THE DRAWINGS
[0030] Figure 1 It is a schematic diagram of installation of the drainage riser installation device of the present invention;
[0031] Figure 2 This is an enlarged schematic diagram of point A of the present invention;
[0032] Figure 3 It is a structural schematic diagram of the drilling device of the present invention;
[0033] Figure 4 It is a structural schematic diagram of the card holder installation device of the present invention;
[0034] Figure 5It is a cross-sectional schematic diagram of the BB section of the present invention;
[0035] Figure 6 It is a schematic diagram of the structure of the upper device of the pipeline transportation device of the present invention;
[0036] Figure 7 It is a schematic diagram of the structure of the middle device of the pipeline transportation device of the present invention;
[0037] Figure 8 It is a cross-sectional schematic diagram of the DD section of the present invention;
[0038] Fig. 9 It is a schematic diagram of the structure of the lower device of the pipeline transportation device of the present invention;
[0039] Fig.10 It is a structural schematic diagram of the clamp ring installation device of the present invention;
[0040] Fig.11 It is a cross-sectional schematic diagram of the CC of the present invention;
[0041] In the figure: 1, cable track; 101, mounting bracket; 102, hoisting equipment; 103, positioning reference device; 104, cable; 105, sliding frame; 106, anchor end; 107, electric pulley block; 108, mounting hole; 109, positioning device;
[0042] 2. Drilling device; 201. First fixed support; 202. Hydraulic support leg; 203. Anchor drill bit; 204. First sliding support; 205. First hydraulic jacking device; 206. Drilling machine; 207. Drill bit; 208. First pulley; 209. First electric gear;
[0043] 3. Camera;
[0044] 4. Card holder installation device; 401. Second fixed bracket; 402. Second sliding bracket; 403. Card holder box; 404. First hydraulic adjustment device; 4031. Y-shaped groove; 405. Card holder; 4032. Card holder installation channel; 4033. First spring device; 406. Card holder jacking device; 407. Card holder fixing device; 408. Second electric gear;
[0045] 5. Pipeline transport device; 501. Upper device; 502. Middle device; 503. Lower device; 504. Third fixed bracket; 505. Third sliding bracket; 506. Second hydraulic adjustment device; 507. Grasping forceps; 508. Grasping forceps power device; 509. Rubber pad; 510. Rolling pulley; 511. Electronic lock; 512. Rubber ring; 513. Second pulley; 514. Third electric gear; 515. Roller shaft;
[0046] 6. Snap ring installation device; 601. Fourth fixed bracket; 602. Fourth sliding bracket; 603. Snap ring box; 604. Third hydraulic adjustment device; 6031. Inverted U-shaped groove; 605. Snap ring; 6032. Snap ring installation channel; 6033. Second spring device; 606. Snap ring jacking device; 607. Snap ring fixing device; 608. Fourth electric gear. DETAILED DESCRIPTION
[0047] The present invention is further described in detail below in conjunction with the accompanying drawings and specific embodiments.
[0048] like Figure 1~2 As shown, as a preferred embodiment 1, a drainage riser installation device comprises a steel cable track 1 and an operating platform, the steel cable track 1 is provided with a plurality of sliding frames 105 which operate independently of each other, the steel cable track 1 is provided with a drilling device 2, a holder installation device 4, a pipe transport device 5 and a clamping ring installation device 6 which operate independently of each other in sequence, the drilling device 2, the holder installation device 4, the pipe transport device 5 and the clamping ring installation device 6 are all brakeably slidably matched with the steel cable track 1 through the sliding frame 105, the drilling end of the drilling device 2 faces the wall, the holder installation device 4 installs the holder 405 at the drilling position of the drilling device 2, the pipe transport device 5 transports the pipe body to the holder 405 and docks it with the upper pipe body, the clamping ring installation device 6 fixes the pipe body by fixing the clamping ring 605 with the corresponding holder 405, the steel cable track 1 and the sliding frame 105, the drilling device 2, the holder installation device 4, the pipe transport device 5 and the clamping ring installation device 6 are all connected with the operating platform by wireless signals;
[0049] A plurality of independently operating sliding frames 105 are arranged on the steel cable track 1, and a drilling device 2, a holder installation device 4, a pipeline transportation device 5 and a clamping ring installation device 6 are respectively arranged on different sliding frames 105. The drilling device 2, the holder installation device 4, the pipeline transportation device 5 and the clamping ring installation device 6 are arranged in order. After the installation position is determined on the operating platform, they can work separately at different positions. The pipeline at each installation position is fixedly installed in turn according to the working sequence of drilling, holder 405 installation, pipeline transportation and docking, and clamping ring 605 installation, so as to facilitate the automatic installation of pipelines in narrow places, and the operating platform is used to assist in the control.
[0050] like Figure 1~2As shown, as a preferred embodiment 2, the steel cable track 1 includes a mounting bracket 101 fixed on the top of the wall, a hoisting device 102 and a positioning reference device 103 installed on the mounting bracket 101, a steel cable 104 connected to the hoisting device 102 and an anchoring end 106 arranged at the bottom of the steel cable 104, a sliding frame 105 and the steel cable 104 are movably fixedly matched through an electric pulley block 107, a positioning device 109 is provided on the sliding frame 105, and a plurality of mounting holes 108 are provided in the middle part of the sliding frame 105. The sliding frame 105 is fixedly matched with the drilling device 2, the card holder mounting device 4, the pipeline transportation device 5 and the clamping ring mounting device 6 through the mounting holes 108 and the mounting parts, and the sliding frame 105 corresponds to the drilling device 2, the card holder mounting device 4, the pipeline transportation device 5 and the clamping ring mounting device 6 one by one, and the positioning device 109 is connected to the operating platform by wireless signals through the positioning reference device 103.
[0051] In Example 2, the hoisting device 102 is generally fixed on the roof through a bracket, and the track length can be adjusted according to the floor height through the hoisting device 102 before construction;
[0052] The positioning reference device 103 can emit wireless signals outward and is installed on the hoisting device 102, generally installed in a relatively stable position, and uses wireless local area network positioning technology to position each device. During the operation process, all positioning devices 109 use this device as a positioning reference point. During the operation process, the operating platform will automatically establish a coordinate system with the positioning reference point, calculate the coordinate position of each installation component, and dynamically update the position of each positioning device 109, and dynamically calculate the required displacement and movement path of each device. The up and down movement is generally completed by the sliding frame 105. The left and right movement and the front and back movement methods of each device are detailed in the detailed structure of each device. In addition, the positioning reference device 103 is also a repeater connecting the operating platform and the sliding frame 105, the drilling device 2, the card seat installation device 4, the pipeline transportation device 5, the clamp ring installation device 6 and other components;
[0053] The steel cables 104 are arranged vertically. To ensure the stability of the track, generally more than two steel cables 104 are provided. The upper ends of the steel cables 104 are connected to the hoisting device 102, and the lower ends are fixed to the ground through the anchoring end 106.
[0054] The main body of the sliding frame 105 is a grid structure. The vertical tube is an electric pulley set 107 to provide power for the frame body. The transverse tube is provided with a mounting hole 108 for installing other devices. In addition, a positioning device 109 is also provided on the electric frame to identify the vertical displacement of the frame.
[0055] like Figure 3As shown in the figure, as a preferred embodiment 3, the drilling device 2 includes a first fixed bracket 201, the first fixed bracket 201 is fixedly matched with the sliding frame 105 by fasteners on the side away from the wall, and the first fixed bracket 201 is provided with a plurality of hydraulic legs 202 symmetrically about the middle position of the first fixed bracket 201 on the side close to the wall, the hydraulic legs 202 are perpendicular to the wall, and the ends of the hydraulic legs 202 are provided with anchor drill bits 203, and the output ends of the anchor drill bits 203 point to the wall, and the middle position of the first fixed bracket 201 can be laterally moved. A sliding bracket 204, wherein the first sliding bracket 204 is provided with a first hydraulic jacking device 205, the first hydraulic jacking device 205 is perpendicular to the wall, a drilling rig 206 is provided on the output end of the first hydraulic jacking device 205, a punching drill 207 is provided on the output end of the drilling rig 206, the punching drill 207 and the drilling rig 206 are concentric and coaxial with the output end of the first hydraulic jacking device 205, a camera 3 is provided on the hydraulic jacking mechanism located on one side of the drilling rig 206, the camera end of the camera 3 is aimed at the wall, and the holder mounting device 4 is located below the drilling device 2.
[0056] In Embodiment 3, the first fixing bracket 201 is a plate-like structure, connected to the vehicle frame body by bolts, and is the main structure of the drilling device 2 that bears force;
[0057] The hydraulic legs 202 are connected to the first fixed bracket 201. There are generally four hydraulic legs 202, which are respectively arranged at the four corner points of the fixed bracket, symmetrically arranged in pairs about the middle position of the first fixed bracket 201, and supported on the wall by hydraulic telescopic means to improve the stability of the drilling construction of the device;
[0058] The anchor drill bit 203 is arranged at the bottom of the hydraulic leg 202. The anchor drill bit 203 is a micro drill bit, which drills into the wall during the erection of the hydraulic leg 202 to improve the force stability of the leg;
[0059] The first sliding bracket 204 is slidably matched with the first fixed bracket 201 through the first electric gear 209 and the first pulley 208. The first electric gear 209 is arranged in the horizontal rack hole in the middle position of the first fixed bracket 201 and meshes with the rack hole. The bottom of the first sliding bracket 204 is rotatably matched with the rotating shaft of the first electric gear 209. The bottom of the first sliding bracket 204 is slidably matched with the surface of the first fixed bracket 201 through the first pulley 208. The rotation of the first electric gear 209 can drive the first sliding bracket 204 to move, thereby driving the first hydraulic jacking device 205, the drilling rig 206, the drilling drill bit 207 and other components to move left and right, which is used for adjusting the drilling position during the construction process;
[0060] The first hydraulic jacking device 205 is installed on the first sliding bracket 204 and is used to provide drilling jacking force for the drilling rig 206;
[0061] The drilling rig 206 is installed on the first hydraulic jacking device 205, and the drilling drill bit 207 is installed on the drilling rig 206; a camera 3 with a positioning function is also arranged on the first hydraulic jacking device 205, and the picture is transmitted to the operating platform in real time to assist drilling positioning.
[0062] like Figures 4 and 5 As shown in the figure, as a preferred embodiment 4, the card seat installation device 4 includes a second fixed bracket 401, the second fixed bracket 401 is fixedly matched with the sliding frame 105 by fasteners on the side away from the wall, and the second sliding brackets 402 are slidably provided on both sides of the second fixed bracket 401 along the direction perpendicular to the wall, and a card seat box 403 is provided between the second sliding brackets 402, and the first hydraulic adjustment device 404 is respectively provided between the two sides of the card seat box 403 and the corresponding second sliding brackets 402, and the central axis of the first hydraulic adjustment device 404 is located at the same water level. On the horizontal line, a Y-shaped groove 4031 is provided in the base box 403, and a plurality of bases 405 are stacked in the Y-shaped groove 4031; a base installation channel 4032 is provided on one side of the base box 403; a first spring device 4033 is provided between the bottom of the base box 403 and the base 405 on the side away from the base installation channel 4032; a base jacking device 406 and a base fixing device 407 are provided on the side of the base installation channel 4032 away from the wall; a camera 3 is provided on one side of the base box 403, and the pipeline transportation device 5 is located below the base installation device 4.
[0063] In Embodiment 4, the second fixing bracket 401 is a plate-like structure, connected to the main body of the sliding frame 105 by bolts, and is the main structure of the card holder installation device 4 that bears force;
[0064] The second sliding bracket 402 is composed of a pair of cross-section rods, which are connected to the second electric gear 408 after passing through the reserved sliding grooves on the fixed bracket to form a rack sliding fit;
[0065] The second electric gear 408 is installed on the second fixed bracket 401. The second electric gear 408 is the power device of the second sliding bracket 402, which can drive the second sliding bracket 402 to move along the vertical direction of the wall to adjust the position of the card seat box 403;
[0066] The first hydraulic adjustment device 404 is respectively installed on the second sliding bracket 402, and the other end is connected to the card base box 403. The first hydraulic adjustment device 404 is respectively provided on both sides of the card base box 403, and the position of the card base box 403 can be adjusted left and right through the first hydraulic device;
[0067] The base box 403 is used to store the drainage pipe base 405. The shape of the groove inside the base box 403 is consistent with the shape of the base 405, which is a Y-shaped groove 4031. A notch is provided at the bottom of one end of the base box 403 as a base installation channel 4032. The other end of the base box 403 is provided with a first spring device 4033 for automatically pushing the base 405.
[0068] A card seat jacking device 406 is provided on the card seat box 403, which is close to the card seat installation channel 4032 and away from the wall. The card seat 405 is pushed out of the card seat box 403 and pushed into the drilled hole pre-drilled by the drilling device 2. The output end of the card seat jacking device 406 is close to the card seat installation channel 4032. The output end is provided with an arc-shaped jacking block matching the card seat 405. The card seat 405 is pushed out by power provided by the telescopic rod. There are two card seat jacking devices 406, which are symmetrical about the card seat 405. A card seat fixing device 407 is provided in the middle. The output end of the card seat fixing device 407 corresponds to the expansion screw in the middle of the card seat 405. After the card seat 405 is pushed into the drilled hole, the position of the card seat fixing device 407 is adjusted by the hydraulic cylinder. The card seat fixing device 407 drills the expansion screw in the card seat 405 to achieve the purpose of fixing the card seat 405.
[0069] A camera 3 with a positioning function is also arranged on the card holder box 403 to assist in positioning the card holder 405 during installation.
[0070] like Figures 6 to 9 As shown, as a preferred embodiment 5, the pipeline transportation device 5 includes an upper device 501, a middle device 502 and a lower device 503, the upper device 501 is located between the card holder installation device 4 and the clamping ring installation device 6, the middle device 502 and the lower device 503 are located below the clamping ring installation device 6, and the upper device 501, the middle device 502 and the lower device 503 have similar structures, and all include a third fixed bracket 504, a third sliding bracket 505 that is laterally slidably matched with the third fixed bracket 504, and a second hydraulic adjustment device that is fixedly matched with the third sliding bracket 505 506 and a gripper 507 fixedly matched with the output end of the second hydraulic adjustment device 506, the gripper 507 is controlled to open and close by a gripper power device 508, and the open end of the gripper 507 faces the wall, a camera 3 is provided on one side of the second hydraulic adjustment device 506, rubber pads 509 are provided on the gripper 507 located at the upper device 501 and the lower device 503, and a plurality of rolling pulleys 510 are provided at equal intervals along the clamp wall on the inner side of the gripper 507 located at the middle device 502, the rolling pulleys 510 are provided with electronic locks 511 for braking, and rubber rings 512 are provided on the surfaces of the rolling pulleys 510.
[0071] In Example 5, the third fixed bracket 504 is a plate-like structure, connected to the main body of the sliding frame 105 by bolts, and is the main structure of the pipeline transportation device 5 that bears force;
[0072] The third sliding bracket 505 is slidably matched with the third fixed bracket 504 through the third electric gear 514 and the second pulley 513. The third electric gear 514 is arranged in the horizontal rack hole in the middle position of the third fixed bracket 504 and meshes with the rack hole. The bottom of the third sliding bracket 505 is rotatably matched with the rotating shaft of the third electric gear 514. The bottom of the third sliding bracket 505 is slidably matched with the surface of the third fixed bracket 504 through the second pulley 513. The third electric gear 514 can drive the third sliding bracket 505 to move along the rack hole, thereby driving the second hydraulic adjustment device 506, the grasping forceps 507 and other components to move left and right to adjust the position of the pipeline;
[0073] The second hydraulic adjustment device 506 is installed on the third sliding bracket 505, and is used to adjust the position of the pipeline in the direction perpendicular to the wall. A gripper 507 is installed at the end of the second hydraulic adjustment device 506, and the gripper 507 is opened and closed by the gripper power device 508 to realize the function of gripping and transporting the pipe;
[0074] The upper device 501 and the lower device 503 of the pipeline transportation are provided with rubber pads 509 on the gripper 507 to increase the friction force of the gripper 507. The gripper 507 of the middle device 502 is provided with a rolling pulley 510 and an electronic lock 511. A rubber ring 512 is provided on the surface of the rolling pulley 510. The electronic lock 511 can be controlled by an electrical signal. When locked, the rolling pulley 510 cannot rotate, and when unlocked, the rolling pulley 510 can roll.
[0075] A camera 3 with a positioning function is also provided on the second hydraulic adjustment device 506 to assist in positioning during the pipe installation process;
[0076] The upper device 501, the middle device 502 and the lower device 503 of the pipeline transportation are all installed on the corresponding sliding brackets, and move up and down through the sliding frame 105. After the pipeline is transported to the right place and fixed, the pipe is released.
[0077] like Figures 10-11As shown, as a preferred embodiment 6, the snap ring installation device 6 includes a fourth fixed bracket 601, and fourth sliding brackets 602 are slidably provided on both sides of the fourth fixed bracket 601 along a direction perpendicular to the wall, a snap ring box 603 is provided between the fourth sliding brackets 602, and third hydraulic adjustment devices 604 are respectively provided on both sides of the snap ring box 603 and between the corresponding fourth sliding brackets 602, and the central axis of the third hydraulic adjustment device 604 is located on the same horizontal line, an inverted U-shaped groove 6031 is provided in the snap ring box 603, and a plurality of snap rings 605 are stacked in the inverted U-shaped groove 6031, a snap ring installation channel 6032 is provided on one side of the snap ring box 603, a second spring device 6033 is provided between the bottom of the snap ring box 603 away from the side of the snap ring installation channel 6032 and the snap ring 605, a snap ring jacking device 606 and a snap ring fixing device 607 are provided on the side of the snap ring installation channel 6032 away from the wall, and a camera 3 is provided on one side of the snap ring box 603.
[0078] In Embodiment 6, the fourth fixing bracket 601 is a plate-like structure, connected to the main body of the sliding frame 105 by bolts, and is the main structure of the clamping ring mounting device 6 that bears force;
[0079] The fourth sliding bracket 602 is composed of a pair of cross-section rods. After the rods pass through the reserved sliding grooves on the fourth fixed bracket 601, they are connected to the fourth electric gear to form a rack sliding fit;
[0080] The fourth electric gear is installed on the fourth fixed bracket 601. The fourth electric gear is the power device of the fourth sliding bracket 602, and can drive the fourth sliding bracket 602 to move along the vertical direction of the wall to adjust the position of the snap ring box 603;
[0081] The third hydraulic adjustment device 604 is respectively installed on the fourth sliding bracket 602, and the other end is connected to the snap ring box 603. The third hydraulic adjustment device 604 is respectively provided on both sides of the snap ring box 603, and the position of the snap ring box 603 can be adjusted left and right through the third hydraulic device;
[0082] The snap ring box 603 is used to store the drainage pipe snap ring 605. The shape of the inner groove of the snap ring box 603 is consistent with the shape of the snap ring 605, which is an inverted U-shaped groove 6031. A notch is provided at one end of the snap ring box 603 as a snap ring installation channel 6032. The other end of the snap ring box 603 is provided with a second spring device 6033 for automatically pushing the snap ring 605.
[0083] A snap ring jacking device 606 is provided on the snap ring box 603, close to the snap ring installation channel 6032, and away from the wall. The snap ring 605 is pushed out of the snap ring box 603 and aligned with the pre-installed holder 405. The output end of the snap ring jacking device 606 is close to the snap ring installation channel 6032. The output end is provided with an arc-shaped jacking block matching the snap ring 405. The snap ring 605 is pushed out by the thrust of the telescopic rod. The snap ring fixing devices 607 are provided on both sides of the snap ring jacking device 606. The snap ring fixing devices 607 are symmetrical about the snap ring 605, and the output ends of the snap ring fixing devices 607 correspond to the tension screws on both sides of the snap ring 605. After the snap ring 605 is in place, the tension screws in the snap ring 605 are drilled and tightened by the snap ring fixing device 607 to make it fixedly matched with the corresponding holder 405, so as to achieve the purpose of fixing the drain pipe;
[0084] A camera 3 with a positioning function is also arranged at the bottom of the snap ring box 603 to assist in positioning the snap ring 605 during installation.
[0085] As a preferred embodiment 7, a drainage riser installation method using the drainage riser installation device described in embodiments 1 to 6 comprises the following steps:
[0086] The first step is to install the steel cable track 1 and the sliding frame 105, and respectively install the drilling device 2, the card holder installation device 4, the pipeline transportation device 5 and the clamping ring installation device 6 on different sliding frames 105, and arrange the devices in sequence from top to bottom. The drilling device 2, the card holder installation device 4, the pipeline transportation device 5 and the clamping ring installation device 6 are positioned by wireless positioning technology, and the installation position is determined by the operating platform;
[0087] In the second step, the drilling device 2 moves to the first installation position to drill a hole;
[0088] In the third step, the drilling device 2 moves up to the next installation position to drill holes, and the card holder installation device 4 moves up to the drilling position in the previous step to install the card holder 405;
[0089] In the fourth step, the drilling device 2 moves up to the next installation position to drill holes, the holder installation device 4 moves up to the drilling position in the previous step to install the holder 405, the pipeline transportation device 5 extracts the pipeline to the holder 405 installation position in the previous two steps to perform pipeline docking installation, and the clamping ring installation device 6 moves up to the holder 405 installation position in the previous two steps to fix the clamping ring 605 to the corresponding holder 405;
[0090] Step 5, repeat the operation of step 4 until all installation positions are drilled, move the drilling device 2 to a suitable position and close the drilling device 2, until all the holders 405 are installed, move the holder installation device 4 to a suitable position and close the holder installation device 4, until all the pipes and clamps 605 are installed, move the pipe transport device 5 and the clamp installation device 6 to a suitable position and close them;
[0091] Step 6: Check the pipeline installation status through camera 3, reset each device and disassemble it.
[0092] In Example 7, the construction principle and operation steps of the drainage riser installation equipment are as follows:
[0093] First, install the cable track 1 and fix it according to the installation position of the drainage riser, then install the sliding frame 105, drilling device 2, clamping seat installation device 4, pipe transportation device 5, and clamp ring installation device 6 in place. Then, after inputting the relevant parameters of the drainage riser through the operation platform, the operation platform automatically calculates the drilling position, quantity, pipe quantity, installation position and other related information;
[0094] By automatically calculating the drilling coordinate information, the operating platform automatically calculates the movement route of the drilling device 2 and issues instructions. After the drilling device 2 is transported to the specified position by the sliding frame 105, the drilling device 2 automatically adjusts the position of the hydraulic support leg 202 and fixes the hydraulic support leg 202 by the anchoring device, and then adjusts the position of the drilling rig 206 by the hydraulic jacking device to drill. After the drilling is completed, the drilling rig 206 is retracted by the hydraulic jacking device, and the anchoring device is loosened by reversing, and the hydraulic support leg 202 is retracted, and then the next drilling is carried out. When a problem occurs during the drilling process, the operating platform will automatically prompt, turn on the camera 3, and switch to the manual operation mode. The drilling operation sequence is from bottom to top, and the operation process is independent and not affected by other operation steps until the drilling operation is completed.
[0095] When the number of holes drilled meets the continuous operation requirements, the operating platform automatically issues a command to start the card holder installation device 4, and automatically calculates the installation coordinate information of the card holder 405 through the drilling information, controls the card holder installation device 4 to reach the specified position, first transports the card holder installation device 4 to the specified position through the sliding frame 105, and then automatically adjusts the position of the card holder box 403 through the second sliding bracket 402 and the first hydraulic adjustment device 404. After the position is aligned, the card holder 405 is pushed into the drilled hole through the card holder jacking device 406, and the card holder 405 is fixed through the card holder fixing device 407. Similarly, when there is a problem with the installation of the card holder 405, the operating platform will automatically prompt, turn on the camera 3, and switch to the manual operation mode. After the fixing is completed, the next card holder 405 is installed; the installation sequence of the card holder 405 is also from bottom to top, and the operation process is independent and not affected by the subsequent operation steps until the installation of the card holder 405 is completed.
[0096] When the number of installed holders 405 meets the requirements of subsequent operations, the operating platform automatically issues instructions to start the pipeline transport device 5 and the clamp installation device 6, first transport the pipeline transport upper device 501 and the clamp installation device 6 to the predetermined position, and then prompt to place the pipeline, and install the drainage riser on the gripper 507 of the pipeline transport lower device 503 and the pipeline transport middle device 502 through manual cooperation, and then send the pipeline to the installation position through the sliding frame 105, and then according to the continuous transportation working principle of the above-mentioned pipeline transport device 5, transfer the pipeline to the pipeline transport upper device 501 and the pipeline transport middle device 502, and the transfer is completed. After that, the lower device 503 of pipeline transportation is released and moves downward to prepare for the next cycle of operation; during the transfer process, the distance from the end of the pipeline to the middle device 502 of pipeline transportation is measured by camera 3, and the installation coordinates are calculated by the operating platform and then the command is issued, and then the position of the pipeline is adjusted by the sliding frame 105, the third sliding bracket 505, and the second hydraulic adjustment device 506. After it is aligned with the installed pipeline, the operating platform prompts and after manual confirmation, the next step is carried out; if it is manually confirmed that the pipeline is not aligned, it is converted into manual operation mode, and the displacement is fine-tuned by controlling the sliding frame 105, the sliding bracket, the hydraulic adjustment device, etc.
[0097] After the pipeline is aligned, the operating platform calculates the installation coordinates of the clamping ring 605 through the installation coordinate information of the holder 405, and issues instructions to control the clamping ring installation device 6 to move into position. It is first transported to the position of the installed holder 405 through the sliding frame 105, and then the position of the clamping ring box 603 is automatically adjusted through the fourth sliding bracket 602 and the third hydraulic adjustment device 604. After the position is aligned, the clamping ring 605 is moved to the installation position through the clamping ring jacking device 606, and the clamping ring 605 is fixed by the clamping ring fixing device 607. The clamping ring 605 is fixed in a bottom-up order. After the first clamping ring 605 is fixed, the pipeline transportation middle device 502 is released and moves downward, and performs the next cycle transportation operation together with the pipeline transportation lower device 503. The synchronized clamping ring installation device 6 performs the next clamping ring 605 installation operation until all the clamping rings 605 of the installed pipe section are installed. The pipeline transportation upper device 501 is released and performs the next cycle operation until all pipelines are installed. The pipeline transportation and the installation of the clamp ring 605 are carried out simultaneously, which greatly improves the installation efficiency.
[0098] As a preferred embodiment 8, the drilling device 2, the holder installation device 4, the pipeline transportation device 5 and the clamping ring installation device 6 in the fourth step and the fifth step operate independently and synchronously, and the operating platform monitors the operation process of each device in real time through the camera 3. When problems occur in the operation of each device, the operating platform can switch to the manual operation mode for manual installation.
[0099] In Example 8, each device operates independently and can perform different operations at the same time. The operating platform is a tablet computer with a device operating system installed. After inputting relevant parameters, it can automatically calculate the number and position of drilling holes, the number of pipes, the installation position and other information. During the process, the device position can be automatically adjusted through relevant positioning information. The operating platform transmits information with the sliding frame 105, the drilling device 2, the card holder installation device 4, the pipeline transportation device 5, and the clamp ring installation device 6 through the local wireless network covered by the positioning reference device 103. The operating platform command signal is first transmitted wirelessly to the positioning reference device 103, and then wirelessly transmitted to each device. The information signal of each device is first transmitted wirelessly to the positioning reference device 103, and then wirelessly transmitted to the operating platform.
[0100] As a preferred embodiment 9, the pipeline transportation device 5 in the fourth step clamps the middle and upper parts and the lower parts of the pipeline respectively through the middle device 502 and the lower device 503. At this time, the rolling pulley 510 of the middle device 502 is in a braking state through the electronic lock 511, and stops moving when it moves up close to the clamping ring installation device 6. The rolling pulley 510 of the middle device 502 is unlocked by the electronic lock 511 to release the braking state, and the lower device 503 moves upward to push the pipeline until the upper part of the pipeline is located in the clamp of the upper device 501 and the middle and lower parts of the pipeline are located in the clamp of the middle device 502. The clamp of the upper device 501 clamps the upper part of the pipeline, and the rolling pulley 510 of the middle device 502 is in a braking state through the electronic lock 511. The middle device 502 and the upper device 501 dock and install the pipeline, and the clamping ring 605 device fixes the installed pipeline by fixing the clamping ring 605 with the corresponding clamping seat 405.
[0101] As a preferred embodiment 10, after the corresponding clamping ring 605 of the pipeline transport device 5 in the fourth step is installed, the lower device 503 and the middle device 502 move down to re-clamp the pipeline and move up to wait for the fifth step operation.
[0102] In Examples 9 to 10, when the pipeline transportation operation is performed, the pipeline transportation middle device 502 and the pipeline transportation lower device 503 are a working unit, the pipeline transportation middle device 502 rolling pulley 510 is in a locked state, clamping the middle and upper part of the pipeline, the pipeline transportation lower device 503 clamps the lower part of the pipeline, and the pipeline is transported upward by the sliding frame 105; when the pipeline installation operation is performed, the pipeline transportation middle device 502 and the pipeline transportation upper device 501 are a working unit, the pipeline transportation upper device 501 clamps the upper part of the pipeline by adjusting the position, the pipeline transportation middle device 502 rolling pulley 510 is opened, the pipeline transportation upper device 501 pulls the pipeline upward, the pipeline transportation middle device 502 is fixed, and the pipeline transportation lower device 503 moves upward. Push the pipeline upward. When the lower part of the pipeline moves into place, all pipeline transport devices 5 stop moving, the rolling pulley 510 of the middle pipeline transport device 502 is locked, and the lower pipeline transport device 503 is released and moves downward to prepare for the next working cycle. After the middle pipeline transport device 502 and the lower pipeline transport device 503 are fine-tuned to align the pipeline, the clamping ring installation device 6 installs the lower clamping ring 605 in place. After the lower clamping ring 605 is installed, the middle pipeline transport device 502 is released and moves downward to perform the next cycle. The synchronous clamping ring installation device 6 installs the subsequent clamping ring 605 from bottom to top. After the upper clamping ring 605 is installed, the upper pipeline transport device 501 is released to prepare for the next working cycle. This cycle is repeated to achieve continuous pipeline installation operations.
Claims
1. A drainage riser installation device, comprising a cable track (1) and an operating platform, characterized in that: The steel cable track (1) is provided with a plurality of sliding frames (105) that operate independently of each other. The steel cable track (1) is provided with a drilling device (2), a clamping seat installation device (4), a pipeline transportation device (5) and a clamping ring installation device (6) that operate independently of each other in sequence. The drilling device (2), the clamping seat installation device (4), the pipeline transportation device (5) and the clamping ring installation device (6) are all brakeably slidably matched with the steel cable track (1) through the sliding frame (105). The drilling end of the drilling device (2) faces the wall. The holder installation device (4) installs the holder (405) at the drilling position of the drilling device (2); the pipeline transportation device (5) transports the pipe body to the holder (405) and installs and docks it with the upper pipe body; the clamping ring installation device (6) fixes the pipe body by fixing the clamping ring (605) with the corresponding holder (405); the steel cable track (1) and the sliding frame (105), the drilling device (2), the holder installation device (4), the pipeline transportation device (5) and the clamping ring installation device (6) are all connected to the operating platform by wireless signals.
2. A drainage riser installation device according to claim 1, characterized in that: The steel cable track (1) comprises a mounting bracket (101) fixed to the top of a wall, a hoisting device (102) and a positioning reference device (103) mounted on the mounting bracket (101), a steel cable (104) connected to the hoisting device (102), and an anchoring end (106) disposed at the bottom of the steel cable (104); a sliding frame (105) and the steel cable (104) are movably fixedly matched via an electric pulley block (107); a positioning device (109) is disposed on the sliding frame (105); and the sliding frame (105) is provided with a positioning device (109). ) is provided with a plurality of mounting holes (108) in the middle portion, and the sliding frame (105) is fixedly matched with the drilling device (2), the clamping seat mounting device (4), the pipeline transportation device (5) and the clamping ring mounting device (6) through the mounting holes (108) and the mounting parts, and the sliding frame (105) corresponds to the drilling device (2), the clamping seat mounting device (4), the pipeline transportation device (5) and the clamping ring mounting device (6) one by one, and the positioning device (109) is connected to the operating platform by wireless signals through the positioning reference device (103).
3. A drainage riser installation device according to claim 2, characterized in that: The drilling device (2) comprises a first fixed support (201), the first fixed support (201) being fixedly matched with the sliding frame (105) via fasteners on a side away from the wall, the first fixed support (201) being provided with a plurality of hydraulic legs (202) symmetrically arranged about the middle position of the first fixed support (201) on a side close to the wall, the hydraulic legs (202) being perpendicular to the wall, the ends of the hydraulic legs (202) being provided with anchor drill bits (203), the output ends of the anchor drill bits (203) being directed toward the wall, and a first sliding support (204) being provided in a transversely movable manner in the middle position of the first fixed support (201). The first sliding bracket (204) is provided with a first hydraulic jacking device (205), the first hydraulic jacking device (205) is perpendicular to the wall, a drilling machine (206) is provided on the output end of the first hydraulic jacking device (205), a drilling bit (207) is provided on the output end of the drilling machine (206), the drilling bit (207), and the output end of the first hydraulic jacking device (205) are coaxial and concentric, a camera (3) is provided on the hydraulic jacking mechanism located on one side of the drilling machine (206), and the camera end of the camera (3) is aimed at the wall, and the holder mounting device (4) is located below the drilling device (2).
4. A drainage riser installation device according to claim 3, characterized in that: The card holder installation device (4) comprises a second fixed bracket (401), the second fixed bracket (401) being fixedly matched with the sliding frame (105) via a fastener on a side away from the wall, second sliding brackets (402) being slidably provided on both sides of the second fixed bracket (401) in a direction perpendicular to the wall, a card holder box (403) being provided between the second sliding brackets (402), first hydraulic adjustment devices (404) being provided between the two sides of the card holder box (403) and the corresponding second sliding brackets (402), the central axis of the first hydraulic adjustment device (404) being located on the same horizontal line, and the card holder box (403) being provided between the two sides of the card holder box (403) and the corresponding second sliding brackets (402). 3) is provided with a Y-shaped groove (4031), a plurality of card seats (405) are stacked in the Y-shaped groove (4031), a card seat installation channel (4032) is provided on one side of the card seat box (403), a first spring device (4033) is provided between the bottom of the card seat box (403) on the side away from the card seat installation channel (4032) and the card seat (405), a card seat jacking device (406) and a card seat fixing device (407) are provided on the side of the card seat installation channel (4032) away from the wall, a camera (3) is provided on one side of the card seat box (403), and a pipeline transportation device (5) is located below the card seat installation device (4).
5. A drainage riser installation device according to claim 4, characterized in that: The pipeline transportation device (5) comprises an upper device (501), a middle device (502) and a lower device (503); the upper device (501) is located between the clamping seat mounting device (4) and the clamping ring mounting device (6); the middle device (502) and the lower device (503) are located below the clamping ring mounting device (6); the upper device (501), the middle device (502) and the lower device (503) have similar structures and all comprise a third fixed bracket (504), a third sliding bracket (505) laterally slidingly matched with the third fixed bracket (504), a second hydraulic adjustment device (506) fixedly matched with the third sliding bracket (505) and a second hydraulic adjustment device (507) fixedly matched with the second sliding bracket (507). A gripper (507) is fixedly matched at the output end of the hydraulic adjustment device (506), and the gripper (507) is controlled to open and close by a gripper power device (508), and the open end of the gripper (507) faces the wall. A camera (3) is provided on one side of the second hydraulic adjustment device (506), and rubber pads (509) are provided on the grippers (507) located at the upper device (501) and the lower device (503). A plurality of rolling pulleys (510) are provided at equal intervals along the gripper wall on the inner side of the gripper (507) located at the middle device (502), and the rolling pulleys (510) are provided with electronic locks (511) for braking, and rubber rings (512) are provided on the surfaces of the rolling pulleys (510).
6. A drainage riser installation device according to claim 5, characterized in that: The snap ring installation device (6) comprises a fourth fixed bracket (601), fourth sliding brackets (602) are slidably provided on both sides of the fourth fixed bracket (601) in a direction perpendicular to the wall, a snap ring box (603) is provided between the fourth sliding brackets (602), third hydraulic adjustment devices (604) are respectively provided between the two sides of the snap ring box (603) and the corresponding fourth sliding brackets (602), the central axes of the third hydraulic adjustment devices (604) are located on the same horizontal line, and an inverted U-shaped groove is provided inside the snap ring box (603). A plurality of snap rings (605) are stacked in the inverted U-shaped groove (6031); a snap ring installation channel (6032) is provided on one side of the snap ring box (603); a second spring device (6033) is provided between the bottom of the snap ring box (603) and the snap ring (605) on a side away from the snap ring installation channel (6032); a snap ring (605) jacking device and a snap ring (605) fixing device are provided on a side of the snap ring box (603) away from the wall; and a camera (3) is provided on one side of the snap ring box (603).
7. A method for installing a drainage riser using the drainage riser installation device according to any one of claims 1 to 6, characterized in that: The following steps are involved: The first step is to install the steel cable track (1) and the sliding frame (105), and respectively install the drilling device (2), the card holder installation device (4), the pipeline transportation device (5) and the clamping ring installation device (6) on different sliding frames (105), and arrange the devices in order from top to bottom. The drilling device (2), the card holder installation device (4), the pipeline transportation device (5) and the clamping ring installation device (6) are positioned by wireless positioning technology, and the installation position is determined by the operating platform; In the second step, the drilling device (2) moves to the first installation position to perform drilling; In the third step, the drilling device (2) moves up to the next installation position to drill holes, and the holder installation device (4) moves up to the drilling position in the previous step to install the holder (405); In the fourth step, the drilling device (2) moves up to the next installation position to drill a hole, the holder installation device (4) moves up to the drilling position in the previous step to install the holder (405), the pipeline transportation device (5) extracts the pipeline to the holder (405) installation position in the previous two steps to perform pipeline docking installation, and the clamping ring installation device (6) moves up to the holder (405) installation position in the previous two steps to fix the clamping ring (605) to the corresponding holder (405); Step 5, repeat the operation of step 4 until all the installation positions are drilled, move the drilling device (2) to a suitable position and close the drilling device (2), until all the holders (405) are installed, move the holder installation device (4) to a suitable position and close the holder installation device (4), until all the pipes and clamping rings (605) are installed, move the pipe transport device (5) and the clamping ring installation device (6) to a suitable position and close them; Step 6: Check the installation of the pipeline through the camera (3), reset each device and disassemble it.
8. A drainage riser installation method according to claim 7, characterized in that: The drilling device (2), the holder installation device (4), the pipeline transportation device (5) and the clamping ring installation device (6) in the fourth step and the fifth step operate independently and synchronously, and the operating platform monitors the operation process of each device in real time through the camera (3). When a problem occurs in the operation of each device, the operating platform can switch to the manual operation mode for manual installation.
9. A drainage riser installation method according to claim 8, characterized in that: In the fourth step, the pipeline transport device (5) clamps the middle upper part and the lower part of the pipeline respectively through the middle device (502) and the lower device (503). At this time, the rolling pulley (510) of the middle device (502) is in a braking state through the electronic lock (511), and stops moving when it moves up to the clamp ring installation device (6). The rolling pulley (510) of the middle device (502) is unlocked through the electronic lock (511) to release the braking state, and the lower device (503) moves upward to push the pipeline until the upper part of the pipeline. The middle and lower part of the pipeline is located in the clamp of the upper device (501), and the middle and lower part of the pipeline is located in the clamp of the middle device (502). The clamp of the upper device (501) clamps the upper part of the pipeline. The rolling pulley (510) of the middle device (502) is in a braking state through an electronic lock (511). The middle device (502) and the upper device (501) are docked and installed on the pipeline. The clamping ring (605) device fixes the installed pipeline by fixing the clamping ring (605) with the corresponding clamping seat (405).
10. A drainage riser installation method according to claim 9, characterized in that: After the corresponding clamping ring (605) of the pipeline transport device (5) in the fourth step is installed, the lower device (503) and the middle device (502) move downward to re-clamp the pipeline and move upward to wait for the fifth step operation.
Citation Information
Patent Citations
Hoisting equipment and hoisting method for hoisting inner courtyard pipeline
CN104627849A
Combined type stand pipe and modularized installation method thereof
CN104806822A
Drainage tunnel stand pipe planting construction device and method
CN107190776A
Vertical integral prefabricated pipe set assembly type construction method based on forklift
CN108910786A
Construction method for installing multi-split device and pipelines in steel structure building
CN110848467A