A fire prevention and control early warning system and method based on multi-source data analysis

By zoning and multi-source data analysis of crop warehouses, and establishing evaluation and benefit models, the problems of fire warning delays and false alarms in the existing technology are solved, the warning accuracy and management efficiency are improved, and the safe storage and system stability of crops are ensured. sex.

CN116343423BActive Publication Date: 2024-12-03SHENZHEN POLYTECHNIC
View PDF 2 Cites 0 Cited by

Patent Information

Application Number
CN202310332266.5
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2023-03-31
Publication Date
2024-12-03
Estimated Expiration
2043-03-31

AI Technical Summary

Technical Problem

The existing crop storage warehouse fire warning system has delayed alarm processing when an open fire is monitored, resulting in the spread of the fire. The monitoring methods for different crops are different, resulting in the system false alarm or untimely alarms.

Method used

By partitioning the storage factory according to crop types and establishing evaluation models and benefit models based on multi-source data analysis, reordering the supervision order of partitions, generating early warning signals and management, and improving early warning accuracy and management efficiency.

Benefits of technology

It improves the accuracy and efficiency of fire warning, ensures safe storage of crops, avoids economic losses, and maintains the stability and early warning accuracy of the system when sensor performance declines.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN116343423B_ABST
    Figure CN116343423B_ABST
Patent Text Reader

Abstract

The present invention discloses a fire prevention and control early warning system and method based on multi-source data analysis, the early warning method comprises the following steps: by collecting a number of data of each partition, establishing an evaluation model after analyzing and processing the data, re-ranking the importance of the partitions based on the evaluation model and the partition benefit model, the system selects the supervision order of the partitions through the importance ranking, and in the fire early warning process, generates corresponding early warning signals and management through the comparison results of the evaluation model and the early warning gradient value, performs partition management on different crops, improves the early warning accuracy of the system, and re-ranks the importance of the partitions based on the evaluation model and the partition benefit model, which is conducive to improving the management efficiency of the system. The present invention uses the comparison results of the evaluation model and the early warning gradient value obtained through comprehensive data analysis to warn the partitions, improves the system data processing efficiency, and improves the storage fire prevention and control effect.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of crop fire early warning, and in particular to a fire prevention and control early warning system and method based on multi-source data analysis. Background Art

[0002] Crops refer to agricultural plants used for human food, feed, industrial raw materials, medicinal materials and other purposes, including cereals, vegetables, fruits, cotton, oilseeds, tea, sugar, grassland, trees, flowers, etc. Crops occupy an important position in human survival and social and economic development. Crop production is an important part of agricultural production and one of the main sources of income for farmers.

[0003] The crop fire prevention and control early warning system is an information system designed to improve the ability to prevent and control crop fires. Its main purpose is to improve the early warning capability of crop storage warehouse fires and avoid excessive crop losses when storage warehouses catch fire.

[0004] The prior art has the following deficiencies:

[0005] 1. Existing crop storage warehouse fire warnings usually use fire detectors, smoke detectors, thermal imaging cameras and other equipment to monitor and control the storage warehouses online, that is, the system alarms when an open fire is detected. However, when an open fire occurs, there is an intermediate process from the system alarm to the processing. For some flammable crops (such as cotton), the appearance of open fire will cause the fire to spread rapidly, resulting in the inability to remedy it in time, causing great economic losses;

[0006] 2. For large storage factories, different crops need to be stored in different areas. However, the existing system adopts a unified fire prevention and control method for all storage areas. Since different crops require different monitoring methods, unified prevention and control is prone to false alarms or untimely alarms, which has great limitations. Summary of the invention

[0007] The purpose of the present invention is to provide a fire prevention and control early warning system and method based on multi-source data analysis to solve the shortcomings of the background technology.

[0008] In order to achieve the above object, the present invention provides the following technical solution: a fire prevention and control early warning method based on multi-source data analysis, the early warning method comprising the following steps:

[0009] S1: Divide the storage plant into zones according to the types of crops and initialize and sort each zone according to the flammability of the crops, marking them as {i1, i2, ..., i n}, n is a positive integer greater than 0;

[0010] S2: Collect some data from each partition, and establish an evaluation model after analyzing and processing the data;

[0011] S3: Re-rank the importance of the partitions based on the evaluation model and the partition benefit model, and the system selects the supervision order of the partitions according to the importance ranking;

[0012] S4: In the process of fire warning, the corresponding warning signal and management are generated by comparing the evaluation model with the warning gradient value.

[0013] In a preferred embodiment, in step S2, establishing the evaluation model includes the following steps:

[0014] The environmental data and storage equipment data of each partition are obtained through sensor equipment, and the evaluation model is established after the environmental data and storage equipment data are normalized. , the expression is:

[0015]

[0016] In the formula, are the proportional coefficients of environmental data and storage equipment data, respectively, and , is the flammability coefficient of crops, is the number of the crop warehouse in the storage area, , is a positive integer, For environmental data, For storage equipment data.

[0017] In a preferred embodiment, the environmental data Including ambient temperature , Ambient humidity , ambient air enthalpy ;

[0018] The storage equipment data includes the electrical equipment stability coefficient And the stability factor of fire fighting equipment , is the equipment load, is the device voltage, is the aging rate of fire equipment, It is the maintenance rate of fire fighting equipment.

[0019] In a preferred embodiment, the crop flammability coefficient The calculation expression is:

[0020] , where They are moisture content, carbon content, oxygen content, nitrogen content and ash content, expressed in weight percentage.

[0021] In a preferred embodiment, in step S4, generating a corresponding warning signal and managing the comparison result between the evaluation model and the warning gradient value includes the following steps:

[0022] S4.1: Setting the warning gradient value , warning gradient value ,and , the evaluation model Compare with the warning gradient value;

[0023] S4.2: If the evaluation model Warning gradient value , no warning signal is generated;

[0024] S4.3: If the warning gradient value Evaluation Model Warning gradient value , generate a first-level warning signal and make corresponding adjustments;

[0025] S4.4: If the evaluation model Warning gradient value , generate a secondary warning signal and make corresponding adjustments.

[0026] In a preferred embodiment, in step S3, establishing the benefit model includes the following steps:

[0027] S3.1: Based on the big database, obtain the historical economic benefits of crops, the market demand-supply ratio, and the theoretical total value of crops, and calculate the benefit model through the formula , the expression is:

[0028]

[0029] In the formula, They are historical economic benefits, market demand-supply ratio, and theoretical total value of crops. are the ratio coefficients of historical economic benefits, market demand-supply ratio, and theoretical total value of crops, respectively. , market demand-supply ratio middle, is the market demand for crops, The market supply of crops.

[0030] In a preferred embodiment, it also includes

[0031] S5: Obtain the response speed, sampling frequency and transmission medium interference rate of the early warning system sensor to establish a correction coefficient, the expression is:

[0032]

[0033] In the formula, is the correction factor, are the proportional coefficients of transmission medium interference rate, response speed, and sampling frequency, respectively, and 0 , They are transmission medium interference rate, response speed, and sampling frequency;

[0034] The correction factor With operating threshold For comparison, if the correction factor , the system itself sends out a warning signal.

[0035] In a preferred embodiment, it also includes

[0036] S6: Get the correction factor After that, recalculate the warning gradient value , warning gradient value , then the correction gradient value = , corrected gradient value = , compare the evaluation model with the corrected gradient value.

[0037] In a preferred embodiment, in step S3, re-ranking the partitions by importance includes the following steps:

[0038] S3.1: Calibrate the evaluation model , the benefit model is calibrated as , evaluation model and benefit model The importance value is obtained by weighted calculation, and the expression is:

[0039]

[0040] In the formula, is the importance value, , The evaluation models are and benefit model The weight of

[0041] S3.2: Obtaining importance values Then, according to the importance value Re-sort the partitions in order of importance from large to small and generate a sorting table. The system selects the supervision order of the partitions based on the sorting table.

[0042] The present invention also provides a fire prevention and control early warning system based on multi-source data analysis, including a partitioning module, a collection module, a model building module, a sorting module, and an early warning module;

[0043] The partitioning module divides the storage factory into zones according to the types of crops and initializes and sorts each zone according to the flammability of the crops, marking them as {i1, i2, ..., i n}, n is a positive integer greater than 0, the acquisition module collects a number of data from each partition, obtains crop benefit data through the big database, the model building module establishes an evaluation model through a number of data from each partition, and establishes a benefit model through the crop benefit data, the sorting module re-sorts the importance of the partitions based on the evaluation model and the partition benefit model, the system selects the supervision order of the partitions by importance sorting, and the early warning module generates corresponding early warning signals and management through the comparison results of the evaluation model and the early warning gradient value.

[0044] In the above technical solution, the technical effects and advantages provided by the present invention are:

[0045] 1. The present invention collects a number of data from each partition, establishes an evaluation model after analyzing and processing the data, re-ranks the importance of the partitions based on the evaluation model and the partition benefit model, and the system selects the supervision order of the partitions by importance ranking. In the process of fire warning, the corresponding warning signal and management are generated by comparing the evaluation model with the warning gradient value, and different crops are managed by partitions to improve the warning accuracy of the system. The importance of the partitions is re-ranked based on the evaluation model and the partition benefit model, which is conducive to improving the management efficiency of the system. Finally, the comparison result of the evaluation model and the warning gradient value obtained by comprehensive data analysis is used to warn the partitions, thereby improving the data processing efficiency of the system and improving the storage fire prevention and control effect;

[0046] 2. The present invention obtains the environmental data and storage equipment data of the partition, normalizes the environmental data and storage equipment data, and then establishes an evaluation model , comprehensive data processing is conducive to improving the system's data processing efficiency, and through the crop flammability coefficient Evaluation Model Make corrections to improve the evaluation model The accuracy when used for different crops, and judging whether to issue a warning signal by comparing the evaluation model with the warning gradient value, is conducive to improving the warning effect of the system's storage and ensuring the safe storage of crops;

[0047] 3. The present invention obtains the benefit model of crops Then, the benefit model and evaluation model Weighted calculation enables each partition to obtain an importance value, so that when the system performs early warning management on multiple partitions, it can effectively prioritize the partitions ranked higher in the sorting table, thereby improving the management efficiency of the system;

[0048] 4. The present invention obtains the correction coefficient After that, recalculate the warning gradient value , warning gradient value , then the correction gradient value = , corrected gradient value = When the sensor acquisition performance decreases, the sensor acquisition accuracy decreases (for example, the actual temperature is 20°C, and the temperature collected by the sensor after the performance decreases is 18°C). At this time, the correction coefficient Reduce the warning gradient value , warning gradient value The initial value of can effectively improve the speed of system response, thereby ensuring that the system's warning accuracy remains unchanged when the sensor performance decreases, and improving the stability of the warning system. BRIEF DESCRIPTION OF THE DRAWINGS

[0049] In order to more clearly illustrate the embodiments of the present application or the technical solutions in the prior art, the drawings required for use in the embodiments will be briefly introduced below. Obviously, the drawings described below are only some embodiments recorded in the present invention. For ordinary technicians in this field, other drawings can also be obtained based on these drawings.

[0050] Figure 1 The present invention is a flow chart of the method. DETAILED DESCRIPTION

[0051] In order to make the purpose, technical solution and advantages of the embodiments of the present invention clearer, the technical solution in the embodiments of the present invention will be clearly and completely described below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0052] Example 1

[0053] See also Figure 1 As shown, the fire prevention and control early warning method based on multi-source data analysis described in this embodiment includes the following steps:

[0054] The storage factory is divided into zones according to the types of crops, and each zone is initialized and sorted according to the flammability of the crops, marked as {i1, i2, ..., in}, n is a positive integer greater than 0, collects a number of data from each partition, establishes an evaluation model after analyzing and processing a number of data, re-ranks the importance of the partitions based on the evaluation model and the partition benefit model, and the system selects the supervision order of the partitions by ranking the importance. In the process of fire warning, the corresponding warning signal and management are generated by comparing the evaluation model with the warning gradient value;

[0055] This application collects a number of data from each partition, establishes an evaluation model after analyzing and processing the data, re-ranks the importance of the partitions based on the evaluation model and the partition benefit model, and the system selects the supervision order of the partitions by importance ranking. In the fire warning process, the corresponding warning signal and management are generated by comparing the evaluation model with the warning gradient value, and different crops are managed in different zones to improve the warning accuracy of the system. The importance of the partitions is re-ranked based on the evaluation model and the partition benefit model, which is beneficial to improving the management efficiency of the system. Finally, the comparison results of the evaluation model and the warning gradient value obtained through comprehensive data analysis are used to warn the partitions, thereby improving the system data processing efficiency and improving the storage fire prevention and control effect.

[0056] In this embodiment, the importance of the partitions is re-ranked based on the evaluation model and the partition benefit model. The system selects the supervision order of the partitions by importance ranking, including the following steps:

[0057] The evaluation model is calibrated as , the benefit model is calibrated as , evaluation model and benefit model The importance value is obtained by weighted calculation, and the expression is:

[0058]

[0059] In the formula, is the importance value, , The evaluation models are and benefit model The weight of the evaluation model is that the fire prevention and control level is greater than the economic benefits of crops during the storage management of crops. The weight is greater than the benefit model The weight of

[0060] Get importance value Then, according to the importance value Re-sort the partitions in order of importance from large to small and generate a sorting table. The system selects the supervision order of the partitions based on the sorting table.

[0061] Specifically, the supervision order of selecting partitions in this embodiment is exemplified as follows:

[0062] Set up the storage factory to be partitioned according to the type of crops, and initialize and sort each partition according to the flammability of the crops, marked as {i1, i2, i3};

[0063] Evaluation model for {i1, i2, i3} partition The values ​​are 5.627, 3.589, and 6.756 respectively, and the benefit model of the {i1, i2, i3} partition The values ​​are 4.872, 4.443, and 3.526 respectively, so the evaluation model and benefit model After weighted calculation, the importance value of the {i1, i2, i3} partition They are 5.325, 3.931, and 5.464 respectively. Based on the importance value The partitions are reordered in order of importance from large to small, and a sorting table {i3, i1, i2} is generated. The system selects the supervision order of the partitions through the sorting table {i3, i1, i2}.

[0064] In order to better illustrate this embodiment, the storage factory is divided into zones according to the types of crops, and each zone is initialized and sorted according to the flammability of the crops. In this embodiment, zones i1, i2, and i3 are used to store rice, cotton, and apples respectively. Flammability of rice Apple is flammable, then the initialization order of the partitions is {i2, i1, i3}.

[0065] Example 2

[0066] In the above embodiment 1, collecting a number of data from each partition, and establishing an evaluation model after analyzing and processing the data includes the following steps:

[0067] The environmental data and storage equipment data of each partition are obtained through sensor equipment, and the evaluation model is established after the environmental data and storage equipment data are normalized. , the expression is:

[0068]

[0069] In the formula, are the proportional coefficients of environmental data and storage equipment data, respectively, and , is the flammability coefficient of crops, is the number of the crop warehouse in the storage area, , is a positive integer, For environmental data, For storage equipment data, The specific value of is set by technicians in this field according to the environment of the storage factory and is not limited here.

[0070] In this embodiment, the environmental data Including ambient temperature , Ambient humidity , ambient air enthalpy , storage equipment data including electrical equipment stability coefficient And the stability factor of fire fighting equipment , is the equipment load, is the device voltage, is the aging rate of fire equipment, It is the maintenance rate of fire fighting equipment.

[0071] The flammability coefficient of crops , used to measure the burning properties of crops, the calculation expression is:

[0072] The flammability coefficient of crops The calculation expression is:

[0073] , where They are moisture, carbon content, oxygen content, nitrogen content and ash content, in weight percentage

[0074] In the formula They are moisture content, carbon content, oxygen content, nitrogen content and ash content, expressed in weight percentage. The larger the flammability coefficient, the more flammable the crop is.

[0075] By crop flammability coefficient To modify the evaluation model , so that the evaluation model When used in different crop partitions, the evaluation accuracy of the crop partitions can be improved.

[0076] In the fire warning process, the generation of corresponding warning signals and management through the comparison results of the evaluation model and the warning gradient value include the following steps:

[0077] Set the warning gradient value , warning gradient value ,and , the evaluation model Compare with the warning gradient value;

[0078] If the evaluation model Warning gradient value ,The system analyzes that the crop storage partition has good storage stability for crops and does not generate an early warning signal;

[0079] If the warning gradient value Evaluation Model Warning gradient value , the system analyzes that there is a possibility of fire in the crop storage area, and the fire prevention and control performance of the storage area is poor when a fire occurs, generates a first-level warning signal and makes corresponding adjustments;

[0080] If the evaluation model Warning gradient value , the system analyzes that the possibility of fire in the crop storage area is high, and the fire prevention and control performance of the storage area is poor when a fire occurs, so it generates a secondary warning signal and makes corresponding adjustments;

[0081] Among them, the importance of the second-level warning signal is greater than that of the first-level warning signal;

[0082] Generate a first-level warning signal and make corresponding adjustments, including: when a first-level warning signal is issued, patrol personnel are required to regularly patrol the crop area, and the warning system will The main influencing coefficients in the data are regulated. If the main influencing coefficients are environmental data, the regulation methods include: warehouse emissions, humidification and cooling. If the main influencing coefficients are storage equipment data, it is necessary to stop the power supply to the electrical equipment or remind to replace and maintain the fire-fighting equipment.

[0083] Generate a secondary warning signal and make corresponding adjustments, including: when a secondary warning signal is issued, inspection personnel are required to inspect the crop area in time, and the early warning system will The main influencing coefficients are regulated. If the main influencing coefficient is environmental data, the regulation methods include: warehouse emissions, humidification and cooling. If the main influencing coefficient is storage equipment data, it is necessary to stop the power supply to the electrical equipment or remind to replace and maintain the fire-fighting equipment. When the second-level warning signal is issued, there is a high possibility of fire in the warehouse, and the warehouse has poor fire prevention and control performance when a fire occurs, so patrol personnel are required to check in time.

[0084] The present invention obtains the environmental data and storage equipment data of the partition, normalizes the environmental data and storage equipment data, and establishes an evaluation model , comprehensive data processing is conducive to improving the system's data processing efficiency, and through the crop flammability coefficient Evaluation Model Make corrections to improve the evaluation model The accuracy when used for different crops, and the comparison results between the evaluation model and the warning gradient value to determine whether to issue a warning signal, is conducive to improving the warning effect of the system's storage and ensuring the safe storage of crops.

[0085] Example 3

[0086] The storage factory is divided into zones according to the types of crops, and each zone is initialized and sorted according to the flammability of the crops, marked as {i1, i2, ..., i n}, n is a positive integer greater than 0, collects a number of data from each partition, establishes an evaluation model after analyzing and processing a number of data, re-ranks the importance of the partitions based on the evaluation model and the partition benefit model, and the system selects the supervision order of the partitions by ranking the importance. In the process of fire warning, the corresponding warning signal and management are generated by comparing the evaluation model with the warning gradient value;

[0087] In the above-mentioned embodiment 1, the importance of the partitions is re-ranked based on the evaluation model and the partition benefit model. When carrying out prevention and control management of crops in different partitions, it is necessary not only to consider the fire prevention level of the crops, but also the economic benefits brought by the crops. The higher the economic benefits of the crops, the higher the attention. Specifically:

[0088] The system obtains the historical economic benefits of crops, the market demand-supply ratio, and the theoretical total value of crops based on a large database, and calculates the benefit model through a formula , the expression is:

[0089]

[0090] In the formula, They are historical economic benefits, market demand-supply ratio, and theoretical total value of crops. are the ratio coefficients of historical economic benefits, market demand-supply ratio, and theoretical total value of crops, respectively. , proportionality coefficient The specific setting is made by those skilled in the art according to the types of crops and is not limited here.

[0091] Market demand-supply ratio middle, is the market demand for crops, The market supply of crops.

[0092] Obtain the benefit model of crops Then, the benefit model and evaluation model Weighted calculation enables each partition to obtain an importance value, so that when the system performs early warning management on multiple partitions, it can effectively give priority to the partitions ranked higher in the sorting table, thereby improving the management efficiency of the system.

[0093] Example 4

[0094] In this application, when the early warning system is used, it mainly collects multi-source data through multiple sensors and then conducts comprehensive analysis. However, during the use of sensors, as the sensors continue to age or are affected by external factors, the collection accuracy of the sensors will be affected. In order to further improve the early warning accuracy of the early warning system, we design the following solutions:

[0095] The response speed, sampling frequency and transmission medium interference rate of the early warning system sensor are obtained to establish the correction coefficient. The expression is:

[0096]

[0097] In the formula, is the correction factor, are the proportional coefficients of transmission medium interference rate, response speed, and sampling frequency, respectively, and 0 , They are respectively the transmission medium interference rate, the response speed, and the sampling frequency. The specific value of the proportional coefficient is set by those skilled in the art according to the specific model of the sensor and is not limited here.

[0098] Get the correction factor After that, recalculate the warning gradient value , warning gradient value , then the correction gradient value = , corrected gradient value = When the sensor acquisition performance decreases, the sensor acquisition accuracy decreases (for example, the actual temperature is 20°C, and the temperature collected by the sensor after the performance decreases is 18°C). At this time, the correction coefficient Reduce the warning gradient value , warning gradient value The initial value of can effectively improve the speed of system response, thereby ensuring that the system's early warning accuracy remains unchanged when the sensor performance decreases, and improving the stability of the early warning system;

[0099] And, the correction factor With operating threshold For comparison, if the correction factor , the system itself sends out a warning signal to remind the system maintenance personnel that the sensor equipment needs to be maintained.

[0100] The generation of corresponding warning signals and management through the comparison results of the evaluation model and the correction gradient value includes the following steps:

[0101] If the evaluation model Correction gradient value ,The system analyzes that the crop storage partition has good storage stability for crops and does not generate an early warning signal;

[0102] If the correction gradient value Evaluation Model Correction gradient value , the system analyzes that there is a possibility of fire in the crop storage area, and the fire prevention and control performance of the storage area is poor when a fire occurs, generates a first-level warning signal and makes corresponding adjustments;

[0103] If the evaluation model Correction gradient value The system analyzes that there is a high possibility of fire in the crop storage area, and the fire prevention and control performance of the storage area is poor when a fire occurs. It generates a secondary warning signal and makes corresponding adjustments, thereby improving the stability of the early warning system during operation.

[0104] Example 5

[0105] The fire prevention and control early warning system based on multi-source data analysis described in this embodiment includes a partitioning module, a collection module, a model building module, a sorting module, and an early warning module;

[0106] in,

[0107] Partitioning module: used to partition the storage factory according to the type of crops, and initialize and sort each partition according to the flammability of the crops, marked as {i1, i2, ..., i n}, n is a positive integer greater than 0.

[0108] Collection module: used to collect certain data of each partition and obtain crop benefit data through a large database;

[0109] Model building module: build an evaluation model through a number of data from each partition, and build a benefit model through crop benefit data;

[0110] Sorting module: re-rank the importance of the partitions based on the evaluation model and the partition benefit model. The system selects the supervision order of the partitions based on the importance ranking;

[0111] Early warning module: Generate corresponding early warning signals and management by comparing the evaluation model with the early warning gradient value.

[0112] The above formulas are all dimensionless and numerical calculations. The formula is a formula for the most recent real situation obtained by collecting a large amount of data and performing software simulation. The preset data in the formula is set by technicians in this field according to actual conditions.

[0113] The above embodiments can be implemented in whole or in part by software, hardware, firmware or any other combination. When implemented by software, the above embodiments can be implemented in whole or in part in the form of a computer program product. The computer program product includes one or more computer instructions or computer programs. When the computer instructions or computer programs are loaded or executed on a computer, the process or function described in the embodiment of the present application is generated in whole or in part. The computer can be a general-purpose computer, a special-purpose computer, a computer network, or other programmable device. The computer instructions can be stored in a computer-readable storage medium, or transmitted from one computer-readable storage medium to another computer-readable storage medium. For example, the computer instructions can be transmitted from one website site, computer, server or data center to another website site, computer, server or data center by wired (e.g., infrared, wireless, microwave, etc.). The computer-readable storage medium can be any available medium that a computer can access or a data storage device such as a server or data center that contains one or more available media sets. The available medium can be a magnetic medium (e.g., a floppy disk, a hard disk, a tape), an optical medium (e.g., a DVD), or a semiconductor medium. The semiconductor medium can be a solid-state hard disk.

[0114] It should be understood that the term "and / or" in this article is only a description of the association relationship of associated objects, indicating that there can be three relationships. For example, A and / or B can represent: A exists alone, A and B exist at the same time, and B exists alone. A and B can be singular or plural. In addition, the character " / " in this article generally indicates that the associated objects before and after are in an "or" relationship, but it may also indicate an "and / or" relationship. Please refer to the context for specific understanding.

[0115] In this application, "at least one" means one or more, and "more than one" means two or more. "At least one of the following" or similar expressions refers to any combination of these items, including any combination of single or plural items. For example, at least one of a, b, or c can be represented by: a, b, c, ab, ac, bc, or abc, where a, b, c can be single or multiple.

[0116] It should be understood that in the various embodiments of the present application, the size of the serial numbers of the above-mentioned processes does not mean the order of execution. The execution order of each process should be determined by its function and internal logic, and should not constitute any limitation on the implementation process of the embodiments of the present application.

[0117] Those of ordinary skill in the art will appreciate that the units and algorithm steps of each example described in conjunction with the embodiments disclosed herein can be implemented in electronic hardware, or a combination of computer software and electronic hardware. Whether these functions are performed in hardware or software depends on the specific application and design constraints of the technical solution. Professional and technical personnel can use different methods to implement the described functions for each specific application, but such implementation should not be considered to be beyond the scope of this application.

[0118] Those skilled in the art can clearly understand that, for the convenience and brevity of description, the specific working processes of the systems, devices and units described above can refer to the corresponding processes in the aforementioned method embodiments and will not be repeated here.

[0119] In the several embodiments provided in the present application, it should be understood that the disclosed systems, devices and methods can be implemented in other ways. For example, the device embodiments described above are only schematic. For example, the division of the units is only a logical function division. There may be other division methods in actual implementation, such as multiple units or components can be combined or integrated into another system, or some features can be ignored or not executed. Another point is that the mutual coupling or direct coupling or communication connection shown or discussed can be through some interfaces, indirect coupling or communication connection of devices or units, which can be electrical, mechanical or other forms.

[0120] The units described as separate components may or may not be physically separated, and the components shown as units may or may not be physical units, that is, they may be located in one place or distributed on multiple network units. Some or all of the units may be selected according to actual needs to achieve the purpose of the solution of this embodiment.

[0121] In addition, each functional unit in each embodiment of the present application may be integrated into one processing unit, or each unit may exist physically separately, or two or more units may be integrated into one unit.

[0122] If the functions are implemented in the form of software functional units and sold or used as independent products, they can be stored in a computer-readable storage medium. Based on this understanding, the technical solution of the present application can be essentially or partly embodied in the form of a software product that contributes to the prior art. The computer software product is stored in a storage medium and includes several instructions for a computer device (which can be a personal computer, a server, or a network device, etc.) to perform all or part of the steps of the methods described in the various embodiments of the present application. The aforementioned storage media include: various media that can store program codes, such as USB flash drives, mobile hard disks, read-only memories (ROM), random access memories (RAM), magnetic disks or optical disks.

[0123] The above is only a specific implementation of the present application, but the protection scope of the present application is not limited thereto. Any person skilled in the art who is familiar with the present technical field can easily think of changes or substitutions within the technical scope disclosed in the present application, which should be included in the protection scope of the present application. Therefore, the protection scope of the present application should be based on the protection scope of the claims.

Claims

1. A fire prevention and control early warning method based on multi-source data analysis, characterized in that: The early warning method comprises the following steps: S1: Divide the storage plant into zones according to the types of crops and initialize and sort each zone according to the flammability of the crops, marking them as {i1, i2, ..., i n }, n is a positive integer greater than 0; S2: Collect some data from each partition, and establish an evaluation model after analyzing and processing the data; S3: Re-rank the importance of the partitions based on the evaluation model and the partition benefit model, and the system selects the supervision order of the partitions according to the importance ranking; S4: In the process of fire warning, the corresponding warning signal and management are generated by comparing the evaluation model with the warning gradient value; In step S2, establishing the evaluation model includes the following steps: The environmental data and storage equipment data of the partitions are obtained through sensor equipment respectively, and the evaluation model is established after the environmental data and storage equipment data are normalized. , the expression is: In the formula, are the proportional coefficients of environmental data and storage equipment data, respectively, and , is the flammability coefficient of crops, is the number of the crop warehouse in the storage area, , is a positive integer, For environmental data, For storage equipment data; The environmental data Including ambient temperature , Ambient humidity , ambient air enthalpy ; The storage equipment data includes the electrical equipment stability coefficient And the stability factor of fire fighting equipment , is the equipment load, is the device voltage, is the aging rate of fire equipment, The maintenance rate of fire fighting equipment; The flammability coefficient of crops The calculation expression is: , where They are moisture content, carbon content, oxygen content, nitrogen content and ash content, expressed in weight percentage.

2. A fire prevention and control early warning method based on multi-source data analysis according to claim 1, characterized in that: In step S4, generating a corresponding warning signal by comparing the evaluation model with the warning gradient value and the management includes the following steps: S4.1: Setting the warning gradient value , warning gradient value ,and , the evaluation model Compare with the warning gradient value; S4.2: If the evaluation model Warning gradient value , no warning signal is generated; S4.3: If the warning gradient value Evaluation Model Warning gradient value , generate a first-level warning signal and make corresponding adjustments; S4.4: If the evaluation model Warning gradient value , generate a secondary warning signal and make corresponding adjustments.

3. A fire prevention and control early warning method based on multi-source data analysis according to claim 2, characterized in that: In step S3, the establishment of the benefit model includes the following steps: S3.1: Based on the big database, obtain the historical economic benefits of crops, the market demand-supply ratio, and the theoretical total value of crops, and calculate the benefit model through the formula , the expression is: In the formula, They are historical economic benefits, market demand-supply ratio, and theoretical total value of crops. are the ratio coefficients of historical economic benefits, market demand-supply ratio, and theoretical total value of crops, respectively. , market demand-supply ratio middle, is the market demand for crops, The market supply of crops.

4. A fire prevention and control early warning method based on multi-source data analysis according to claim 3, characterized in that: Also includes S5: Obtain the response speed, sampling frequency and transmission medium interference rate of the early warning system sensor to establish a correction coefficient, the expression is: In the formula, is the correction factor, are the proportional coefficients of transmission medium interference rate, response speed, and sampling frequency, respectively, and 0 , They are transmission medium interference rate, response speed, and sampling frequency; The correction factor With operating threshold For comparison, if the correction factor , the system itself sends out a warning signal.

5. A fire prevention and control early warning method based on multi-source data analysis according to claim 4, characterized in that: Also includes S6: Get the correction factor After that, recalculate the warning gradient value , warning gradient value , then the correction gradient value = , corrected gradient value = , compare the evaluation model with the corrected gradient value.

6. A fire prevention and control early warning method based on multi-source data analysis according to claim 1, characterized in that: In step S3, re-ranking the partitions in terms of importance includes the following steps: S3.1: Calibrate the evaluation model , the benefit model is calibrated as , evaluation model and benefit model The importance value is obtained by weighted calculation, and the expression is: In the formula, is the importance value, , The evaluation models are and benefit model The weight of S3.2: Obtaining importance values Then, according to the importance value Re-sort the partitions in order of importance from large to small and generate a sorting table. The system selects the supervision order of the partitions based on the sorting table.

7. A fire prevention and control early warning system based on multi-source data analysis, used to implement the early warning method according to any one of claims 1 to 6, characterized in that: It includes partition module, collection module, model building module, sorting module and early warning module; The partitioning module divides the storage factory into zones according to the types of crops and initializes and sorts each zone according to the flammability of the crops, marking them as {i1, i2, ..., i n }, n is a positive integer greater than 0, the acquisition module collects a number of data from each partition, obtains crop benefit data through the big database, the model building module establishes an evaluation model through a number of data from each partition, and establishes a benefit model through the crop benefit data, the sorting module re-sorts the importance of the partitions based on the evaluation model and the partition benefit model, the system selects the supervision order of the partitions by importance sorting, and the early warning module generates corresponding early warning signals and management through the comparison results of the evaluation model and the early warning gradient value.

Citation Information

Patent Citations

  • Warehouse intelligent management and fireproof early warning system and device thereof

    CN115630897A

  • KR20230037211A