Neutral or phase loss detection

By regularly collecting voltage measurement and exploratory algorithms, using the characteristics of line-neutral lines and line-line voltages, the losses of neutral lines and phases in the power network are accurately detected, and the problems of distinction in the existing technology are solved and multiphase is realized Accurate loss detection in the network.

CN117310358BActive Publication Date: 2024-11-08SAGEMCOM ENERGY & TELECOM SAS
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202310780473.7
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Priority Date
2022-06-28
Filing Date
2023-06-28
Publication Date
2024-11-08
Estimated Expiration
2043-06-28

AI Technical Summary

Technical Problem

The prior art is difficult to accurately detect the loss of neutral lines and phases in power networks, especially in multiphase power networks, especially when neutral lines are cut into multiple instruments, it is impossible to distinguish between neutral lines and phase losses, and traditionally The method relies on current measurement or abnormal imbalance based on line-neutral voltages and cannot be effectively detected under changes in floating phase and neutral voltages.

Method used

Regular voltage acquisition measurement is used to identify the current value of electrical parameters through exploratory algorithms and reference tables, distinguish neutral line loss from phase loss, and use the amplitude and angle differences between line-neutral line voltage and line-line voltage to establish predetermined criteria. To infer connection configuration, loss detection of neutral lines and phases is achieved without current measurement or estimation of impedance.

Benefits of technology

It realizes accurate and reliable detection of neutral line and phase losses in a multi-phase power network, and can distinguish neutral line losses from phase losses. It is suitable for multi-meter configurations, improves detection accuracy and responsiveness, and avoids traditional Method limitations.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN117310358B_ABST
    Figure CN117310358B_ABST
Patent Text Reader

Abstract

A method for monitoring a multiphase network (6) comprises the following steps which are repeated periodically: - collecting voltage measurements made by a voltage sensor of an item of electrical equipment and generating a current value of an electrical parameter; - accessing a reference table (20) comprising a list of connection configurations, each connection configuration being associated with a different combination of reference values ​​of said electrical parameter, the list of connection configurations comprising configurations corresponding to a combination of connection states of each phase (P1, P2, P3) and a neutral conductor (N); - implementing an exploratory algorithm which aims at exploring the reference table (20) to identify the current connection configuration.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the field of electricity distribution networks and equipment connected to such networks. Background Art

[0002] Interruptions in the neutral conductor upstream of the electricity meter are the responsibility of the energy supplier and may cause major problems in the electrical installations in the end customer's facility located downstream of the electricity meter.

[0003] Depending on the impedance on each phase conductor downstream of the interruption in the neutral conductor, the voltage imbalance may be significant. Dangerous voltages may result and may damage equipment connected in the customer's property. It is therefore important to be able to detect the occurrence of a neutral loss event in a reliable and responsive manner so that appropriate preventive and / or protective measures can be taken. In addition to detecting the loss of the neutral, it is also important to detect the loss of at least one phase, particularly in the context of active and passive maintenance of the power network in order to maximize its quality. Traditionally, detecting the loss of the neutral is based on detecting an abnormal imbalance between the line-neutral voltages and / or the absence of current on the neutral. Therefore, a known prior art method involves detecting the loss of the neutral by using a detection criterion that is purely based on finding an abnormal imbalance between the line-neutral voltages. This criterion is not fully reliable, particularly because it makes it impossible to distinguish between a neutral loss and a phase loss.

[0004] Another known prior art method uses a detection criterion based on the current in the neutral conductor. This method therefore requires the presence of current measurement components on the neutral conductor, which represents an additional cost and implies major physical and electrical implementation constraints.

[0005] In another known prior art approach, implementation specifically involves measuring the downstream load in order to be able to predict an expected voltage imbalance and detect this imbalance when it actually occurs.

[0006] However, the effectiveness of this solution is directly related to the relevance of the measured downstream impedance, which is a limiting factor, since the theoretical analysis proposed considers a linear load that is constant over time, which is not necessarily the case in practical reality in the field.

[0007] Furthermore, the method is based on theoretical studies for a single meter. However, if the neutral cut involves several meters, each with different (unrelated) and unbalanced downstream loads, these meters share the same floating neutral, the potential of which is set by the combination of the different downstream loads behind all these meters.

[0008] exist Figure 1This situation is shown in . It can be seen that two meters 1a and 1b connected to the same electricity network 2 comprising three phases P1 , P2 , P3 and a neutral line N are affected by the interruption of the neutral line at a breakpoint 4 .

[0009] The approach discussed does not allow the detection of a loss of neutral in such a configuration. Indeed, in the case of a neutral cut involving a cluster of meters, the estimation of the downstream impedance of a given meter only takes into account the load downstream of said meter. However, the actual load that causes the actual imbalance is the result of the combination of all the downstream loads of all the meters in the cluster. This approach therefore makes it impossible to detect the loss of neutral in this case, since the combination of all the downstream loads cannot be approached and therefore it is impossible to make an estimation for a given meter.

[0010] Loss of phase detection is typically reported when the line-to-neutral voltage measured for the phase in question (between phase and neutral) falls below some predetermined threshold. It is generally accepted that in the event of a phase loss, the load downstream of the breakpoint "brings" the phase voltage back to neutral, resulting in a line-to-neutral voltage measurement that is in principle close to 0V.

[0011] However, this simplified approach does not cover the upstream realities that may be encountered in the field.

[0012] In practice, there may also be loads between the phases downstream of the break point, to the extent that the phase that becomes the floating phase is naturally established according to the balance of the downstream loads (relative to the neutral, but also with respect to the phases that are still present), this may result in it having potentially high line-neutral voltage values ​​(in absolute terms, it can vary between 0 V and Vn, which is the nominal line-to-neutral voltage of the network), and the detectability of the phase loss cannot therefore be definitively established based solely on the measurement of its line-neutral voltage.

[0013] Furthermore, neutral loss and phase loss may occur simultaneously and detection of the latter becomes more problematic in such cases if the detection is established solely on the basis of measurements of their line-neutral voltages.

[0014] Finally, it should be added that some prior art methods for detecting loss of a neutral conductor and / or one or more phases use as criterion a comparison with one (or several) reference values ​​established based on measurements made before a physical interruption in the conductor occurs.

[0015] This presents several potential problems. First, once the interruption of the neutral and / or one or more phases has occurred, the actual condition (voltage) of the power network becomes unmeasurable, and therefore the criterion for comparison is stuck with the value obtained at the last moment before the one or more interruptions occurred. If the voltage of the power network is considered to be relatively stable over time, the interruption may last long enough to make the actual voltage of the power network eventually significantly different from the last known measurement, thereby making the comparison criterion outdated and thus potentially making the detection less reliable over time. In addition, the loss of a conductor (neutral or phase) can occur suddenly, but can also develop slowly, with the line impedance drifting until it is so high that it resembles the loss of a conductor. In this case, the gradual increase in line impedance can occur over a considerable period of time (several seconds, minutes, etc.). This means that since the interruption is not sudden, the comparison criterion (which is usually based on the conditions (network voltage) measured on the network before the (all) conductor interruptions) can no longer be clearly established, making the implementation less reliable and more problematic. Summary of the invention

[0016] The object of the present invention is a method for detecting the loss of a neutral conductor and / or of at least one phase of an electric power network which method does not have the disadvantages of the prior art methods described above.

[0017] - To achieve this object, a method for monitoring a multiphase power network is proposed, the method being at least partially implemented in a processing unit of an item of electrical equipment connected to the multiphase power network and comprising the following steps, which are repeated periodically: acquiring voltage measurements made by voltage sensors of the item of electrical equipment connected to the multiphase power network;

[0018] - Produce current values ​​of electrical parameters from voltage measurements;

[0019] - accessing a reference table comprising a list of connection configurations, each connection configuration being associated with a different combination of reference values ​​of said electrical parameter, the list of connection configurations comprising first connection configurations, each first connection configuration corresponding to a different combination of a connected state or a disconnected state of each phase and the neutral line; implementing an exploratory algorithm, which is intended to explore the reference table to identify the connection configuration associated with the current value of the electrical parameter.

[0020] The monitoring method according to the invention therefore consists in generating current values ​​of electrical parameters, obtained purely from voltage measurements, then exploring a reference table and identifying the connection configuration corresponding to these current values ​​of electrical parameters. The reference table may contain reference values ​​of electrical parameters associated with all possible situations: normal connected or disconnected state of the line, different impedance values ​​downstream of disconnection, reversal of phases and neutral, different combinations of phases disconnected but brought to the potential of another phase, etc.

[0021] Systematic and exhaustive exploration of the table allows inferring the connectivity configuration in a very accurate and very reliable way.

[0022] This monitoring method does not require current measurements and does not require estimation of impedance downstream of the loss of neutral or phase. This monitoring method makes it possible in particular to distinguish between a loss of neutral and a loss of phase. It is functional regardless of the number of meters connected to the severed line. It does not require the use of reference values ​​established on the basis of measurements made before a physical interruption in the conductor occurs.

[0023] A monitoring method as previously described is also proposed, wherein the list of connection configurations comprises second connection configurations which correspond, for one of the phases respectively, to a neutral line and a reversal of said phase.

[0024] There is also proposed a monitoring method as described above, wherein the connection configuration list comprises third connection configurations, each third connection configuration corresponding to one of the phases that is disconnected and at the potential of another phase.

[0025] A monitoring method as described above is also proposed, wherein the implementation of the exploratory algorithm comprises the following steps:

[0026] - testing the connection configuration by checking whether a predetermined criterion associated with the connection configuration is met, the predetermined criterion being defined based on the electrical parameter; if the predetermined criterion is met, it is inferred therefrom that the connection configuration is the configuration corresponding to the current value of the electrical parameter,

[0027] - If no, repeat the test steps with another connection configuration.

[0028] A monitoring method as described above is also proposed, wherein the electrical parameters include:

[0029] - measured line-neutral voltages, each measured line-neutral voltage representing the amplitude of the line-neutral voltage between one of the phases and the neutral line; and / or

[0030] - measured line-to-line voltages, each measured line-to-line voltage representing an amplitude of a line-to-line voltage between two different phases; and / or

[0031] - measured angles, each measured angle being equal to the angle between a vector representation of the line-neutral voltage between one phase and the neutral and a vector representation of the line-neutral voltage between another phase and the neutral.

[0032] A monitoring method as previously described is also proposed, wherein the measured angles are obtained by implementing a zero-crossing detection method on the voltages measured between the phases and the neutral line.

[0033] A monitoring method as previously described is also proposed, wherein the implemented heuristic algorithm is a first heuristic algorithm using only measured line-neutral voltage and measured line-line voltage as electrical parameters.

[0034] A monitoring method as described above is also proposed, wherein a first heuristic algorithm comprises a step of attempting to detect one or more abnormal measured line-line voltages, the first heuristic algorithm then consisting in testing a set of connection configurations, these sets being defined as a function of the number of abnormal measured line-line voltages.

[0035] A monitoring method as described above is also proposed, wherein the measured line-to-line voltage U' is converted into i Considered abnormal:

[0036] U' i <Uprev i –αor if U' i >Uprev i +α,

[0037] in:

[0038] α is the uncertainty margin,

[0039] And among them:

[0040] Uprev i =V n .SQRT(ai 2 +aj 2 +ai.aj),

[0041] Where ai=V i / V n ,aj=V j / V n , V i is the measured line-to-neutral voltage for phase Pi, V j is the measured phase-to-neutral voltage for Pj, and V n is the nominal line-neutral voltage.

[0042] A monitoring method as described above is also proposed, wherein the predetermined criteria comprise respective comparisons made between:

[0043] -The resulting voltage is obtained by adding:

[0044] oTwo different measured line-neutral voltages; or

[0045] oMeasured line-neutral voltage and measured line-line voltage;

[0046] - and the measured line-to-neutral voltage or the measured line-to-line voltage.

[0047] A monitoring method as previously described is also proposed, wherein the implemented heuristic algorithm is a second heuristic algorithm using only the measured line-neutral voltage and the measured angle as electrical parameters.

[0048] It is also proposed a monitoring method as previously described, wherein the predetermined criterion associated with the following connection configurations comprises only a comparison between the measured angle and an angle threshold:

[0049] -The neutral line and all phases are connected normally;

[0050] - Neutral line is reversed with one of the phases;

[0051] -The neutral is disconnected and all phases are connected.

[0052] A monitoring method as previously described is also proposed, wherein a second heuristic algorithm tests whether the phases are wired to the meter in a direct or indirect order.

[0053] An item of electrical equipment comprising a voltage sensor and a processing unit is also proposed, in which the monitoring method as described above is implemented.

[0054] An electrical equipment item as described above is also proposed, which is a meter.

[0055] A computer program is also provided, comprising instructions for causing a processor unit of an electric meter as described above to execute the steps of the monitoring method as described above.

[0056] A computer-readable storage medium is also proposed, on which the computer program as described above is stored.

[0057] The invention will be better understood from the following description of specific non-limiting examples of its implementation. BRIEF DESCRIPTION OF THE DRAWINGS

[0058] With reference to the accompanying drawings, in which:

[0059] [ Figure 1 ] Figure 1 Two electricity meters connected to a network in which the neutral wire has been cut are shown;

[0060] [ Figure 2 ] Figure 2 An electric meter is shown in which the present invention is implemented;

[0061] [ Figure 3 ] Figure 3 The Fresnel diagram for the nominal case, with no neutral line loss, is shown;

[0062] [ Figure 4 ] Figure 4 comprising a first diagram showing a cut of a neutral conductor on a network, and a second diagram showing a cut of phase P1;

[0063] [ Figure 5 ] Figure 5 The effect of a breakpoint downstream of neutral loss on the Fresnel diagram is shown;

[0064] [ Figure 6 ] Figure 6 The results of different connection configurations for the voltages shown in the Fresnel diagram are shown;

[0065] [ Figure 7 ] Figure 7 The various steps of the monitoring method according to the present invention are shown. DETAILED DESCRIPTION

[0066] refer to Figure 2 A polyphase (in this case three-phase) electricity meter 5 is connected to a polyphase (in this case three-phase) electricity network 6 comprising three phases P1, P2, P3 and a neutral line N. The meter 5 is intended to measure the electricity distributed by the electricity network 6 to a consumer installation 7.

[0067] The meter 5 comprises, for each phase Pi (i ranging from 1 to 3), a terminal 8 connected to said phase Pi and a phase conductor 9 connected to said terminal 8. The meter 5 also comprises a terminal 10 connected to a neutral line N and a neutral conductor 11 connected to said terminal 10.

[0068] The meter 5 further comprises a voltage sensor connected to the electricity network 6 via the phase conductors 9 and the neutral 11 conductors and via the terminals 8 and 10. The voltage sensor can be used to measure:

[0069] - a line-to-neutral voltage V′1 between phase P3 and neutral conductor N, which is (usually) the image of the line-to-neutral voltage V1 of network 6 at meter 5 ;

[0070] - a line-to-neutral voltage V′2 between phase P2 and neutral conductor N, which is (usually) the image of the line-to-neutral voltage V2 of network 6 at meter 5 ;

[0071] - the line-to-neutral voltage V′ 3 between the phase P3 and the neutral conductor N, which is (usually) the image of the line-to-neutral voltage V3 of the network 6 at the meter 5 .

[0072] The voltage sensor includes a first resistance bridge, a second resistance bridge, a third resistance bridge and an analog-to-digital converter 14 (ADC).

[0073] The first resistance bridge comprises two resistance bridges R installed between the phase conductor 9 and the neutral conductor 11 1A and R1B , the phase conductor 9 is connected to the phase P1. The second resistance bridge comprises two resistance bridges R installed between the phase conductor 9 and the neutral conductor 11. 2A and R 2B , the phase conductor 9 is connected to the phase P2. The third resistance bridge comprises two resistance bridges R installed between the phase conductor 9 and the neutral conductor 11. 3A and R 3B , phase conductor 9 is connected to phase P3.

[0074] ADC 14 includes a resistor connected to two resistors R 1A and R 1B The first input terminal is connected to the point between the two resistors R 2A and R 2B The second input terminal is connected to the point between the two resistors R 3A and R 3B The third input terminal of the point between.

[0075] The resistive bridge allows the amplitudes of the measured voltages to be reduced so that they are compatible with the measurement range of the ADC 14. The ADC 14 digitizes the measured voltages.

[0076] The characteristics of the ADC 14 (number of bits, sampling frequency) are compatible with the need to produce a usable voltage measurement. Typically, the ADC 14 used is an ADC with 12 or more bits and a sampling frequency of 1 ksps (kilosamples per second).

[0077] The electricity meter 5 further comprises a processing unit 15 .

[0078] The processing unit 15 includes one or more processing components 16, and for example any general or special purpose processor or microprocessor (e.g., a DSP (digital signal processor), a microcontroller, or indeed a programmable logic circuit such as an FPGA (field programmable gate array) or an ASIC (application-specific integrated circuit).

[0079] The processing circuit 15 also comprises one or more memories 17. At least one of these memories 17 forms a computer-readable storage medium on which is stored at least one computer program, the at least one computer program comprising instructions for causing the processing unit 15 to perform at least some of the steps of the monitoring method according to the invention. One of these memories 17 may be integrated into one of the processing components 16.

[0080] In this case, the ADC 14 is integrated into the processing unit 15 and optionally into one of the processing components 16 .

[0081] The processing unit 15 therefore acquires measurements V′1 , V′2 , V′3 of the line-neutral voltage and generates the following measurements from these measurements: the line-to-line voltage U′1 between phase P1 and phase P2 , which is (usually) the image of the voltage U1 of the network 6 at the meter 5 ;

[0082] - The line-to-line voltage U′2 between phase P2 and phase P3, which is (usually) the image of the voltage U2 of the network 6 at the meter 5; the line-to-line voltage U′3 between phase P3 and phase P1, which is (usually) the image of the voltage U3 of the network 6 at the meter 5.

[0083] At each sampling time, each of these line-to-line voltages is obtained by subtracting the two line-to-neutral voltages of the phase in question. The voltage considered is then:

[0084] - measured line-neutral voltages, each measured line-neutral voltage representing an amplitude of a line-neutral voltage between one of the phases and the neutral line;

[0085] - measured line-to-line voltages, each measured line-to-line voltage representing an amplitude of a line-to-line voltage between two different phases.

[0086] In this case, the measured line-neutral voltage and the measured line-to-line voltage are rms voltages - but the voltages representing the amplitudes may be different, such as the maximum amplitude values.

[0087] Therefore, the voltage considered thereafter is the RMS voltage calculated (and possibly corrected by calibration parameters) based on a sample of these line-neutral voltage measurements (e.g., each second based on a sample from the previous second, or over a sliding window of seconds, or over another time depth deemed appropriate).

[0088] The processing unit 15 therefore estimates the measured line-neutral voltage V'1 (which is the voltage RMS voltage), V'2 and V'3, and the measured line-to-line voltage U'1 (which is the voltage RMS voltage), U'2 and U'3.

[0089] The processing unit also estimates the measured angles Phi1, Phi2 and Phi3. Each measured angle is equal to the angle between the vector representation of the line-neutral voltage between one phase and neutral and the vector representation of the line-neutral voltage between the other phase and neutral.

[0090] Therefore, Phi1 is and The angle between Phi2 and and The angle between Phi3 and and The angle between.

[0091] The measured angle is estimated by implementing a zero-crossing detection method and performing appropriate filtering on the voltage measurements, and in particular on the measured line-neutral voltage.

[0092] The invention aims to detect the loss of the neutral conductor and / or one or more phases purely based on the analysis of the voltage measurements made by the electricity meter 5 and without using reference measurements before the time of the break in one or more conductors from the network.

[0093] Figure 3 shows the Fresnel diagram for the nominal case when a neutral conductor is present and has balanced line-neutral voltages. It can also be seen that the vector and angles Phi1, Phi2, and Phi3.

[0094] Figure 4 The top diagram in FIG. 1 shows and models what happens after a loss of a neutral conductor (cutting of the neutral conductor). It is assumed that the breakpoint 18 of the neutral conductor N is located upstream of the meter 5. The neutral conductor located downstream of the breakpoint 18 becomes a floating conductor and is connected to the neutral conductor according to the breakpoints (Z1, Z2, Z3, Z 12 , Z 12 , Z 23 ) is established by the load downstream. In this example, the term "upstream" means on the network 6 side, and the term "downstream" means on the facility 7 side. Figure 4 The bottom diagram in shows and models what happens after the loss of phase P1 (cut-off phase). It is assumed that the breakpoint 19 of phase P1 is located upstream of the meter 5. The phase located downstream of the breakpoint 19 becomes a floating line and is established according to the load located downstream of the breakpoint connected to it. In this specific case, it can be seen that the measured voltages V'2, V'3 and U'2 correspond to the actual voltages of the network (V2, V3 and U2). However, the measured voltages V'1, U'1 and U'3 are no longer the voltages of the network (V1, U1 and U3), except in the specific case of a perfectly balanced downstream load.

[0095] Although Figure 4 This is not shown in , but two breakpoints (on one phase and neutral, or indeed on two phases) may also be considered. Similarly, the voltage on each of the two lines that have become floating lines is established according to the loads located downstream of the breakpoints respectively connected to them.

[0096] See also Figure 5 , after the loss of the neutral conductor N, for example, the voltages according to the downstream loads are naturally balanced: in the Fresnel diagram, the position of the neutral conductor that has become a floating neutral conductor downstream of the break point is located "somewhere" within the triangle formed by the three phases, depending on the value of the downstream loads.

[0097] Therefore, in Figure 5 It can be seen that in the case of neutral loss, the measured line-to-line voltage corresponds to the actual line-to-line voltage of the network (U' x =U x ). However, the measured line-neutral voltages are no longer those of the network (V' x ≠V x ), except in the special case of a perfectly balanced downstream load. It should be noted that Figure 5 This scenario is depicted, where the downstream load is assumed to be unbalanced.

[0098] The monitoring method according to the invention consists in detecting the disconnection of the neutral conductor and / or of one or more phases solely on the basis of voltage measurements.

[0099] The invention firstly comprises a preliminary step consisting in systematically and exhaustively listing and studying the different possible situations and defining, for each of the considered connection configurations, the expected values ​​of the electrical parameters obtained from the voltage measurements.

[0100] Therefore, reference table 20 is created (see Figure 2 ), the reference table comprising a list of connection configurations, each connection configuration being associated with a different combination of reference values ​​of said electrical parameters.

[0101] The list of connection configurations includes first connection configurations, each of which corresponds to a different combination of a connected (normal) or disconnected (cut) state of each phase Pi and the neutral line N.

[0102] For example, the first connection configuration corresponds to the following combination:

[0103] N: Close - P1: Open - P2: Open - P3: Open,

[0104] Therein "off" means that the line in question (phase or neutral) is disconnected and thus has a cut-off, and therein conversely "on" means that the connection is normal.

[0105] Other first connection configurations are, for example:

[0106] N: On - P1: Off - P2: On - P3: On,

[0107] N: On - P1: Off - P2: Off - P3: On,

[0108] etc.

[0109] The list of connection configurations also includes a second connection configuration corresponding to a reversal of the neutral and of one of the phases, respectively at terminals 8 and 10 of the meter 5 . The reversal results, for example, from incorrect workmanship when installing the meter 5 .

[0110] For example, the second connection configuration corresponds to the following combination:

[0111] N: Open (reverse) - P1: Open (reverse) - P2: Open - P3: Open.

[0112] In the second connection configuration, the neutral line and the phase P1 are not cut off but inverted.

[0113] The list of connection configurations also includes third connection configurations each corresponding to one of the phases, which phases are disconnected and brought to the potential of another phase due to the condition of the downstream load.

[0114] For example, the third connection configuration corresponds to the following combination:

[0115] N: On - P1: Off (On) - P2: On - P3: On.

[0116] In a third connection configuration, phase P1 is switched off but brought to the potential of one of phases P2 or P3.

[0117] Figure 6 A specific number of connection configurations are shown:

[0118] - In diagram D1 , all lines N, P1 , P2 , P3 are connected (nominal situation), or in practice the neutral line N is disconnected but the loads are balanced;

[0119] - In Figure D2, the neutral line N is disconnected and the load is unbalanced; in Figure D3, phase P1 is disconnected;

[0120] - In diagram D4, phases P1 and P2 are disconnected;

[0121] - In Figure D5, the neutral line N and phase P1 are disconnected;

[0122] - In Figure D6, the neutral line N and the phase P1 are reversed.

[0123] In the reference table 20 mentioned above, the electrical parameters used include:

[0124] - measured line-neutral voltages, each measured line-neutral voltage representing (as already seen) the amplitude of the line-neutral voltage between one of the phases and the neutral; and / or

[0125] - measured line-to-line voltages, each measured line-to-line voltage representing (as already seen) the amplitude of the line-to-line voltage between two different phases; and / or

[0126] - measured angles, each equal (as already seen) to the angle between the vector representation of the line-neutral voltage between one phase and the neutral and the vector representation of the line-neutral voltage between the other phase and the neutral.

[0127] The reference table 20 has thus been created in a design department, a laboratory or a factory and has been downloaded to one of the memories 17 of the processing unit 15. Alternatively, the reference table 20 may be stored remotely (in a data concentrator, a server of a computer system, in the cloud, etc.) and the processing unit 15 of the meter 5 may access it via suitable communication means. The reference table 20 may be updated while the meter 5 is operating.

[0128] Thus, the inventors have analysed the reference table 20 and have deduced therefrom heuristic paths and discriminating criteria for reliably determining the current connection configuration - and in particular the presence or absence of the neutral conductor N and the phases Pi - during operation.

[0129] An example of a reference table is provided in Appendix 1 of this specification.

[0130] Reference Table 20 lists in an almost exhaustive manner the different practical situations and represents the characteristics of each of these situations (position of each line in the Fresnel reference diagram, values ​​of line-neutral voltage and line-to-line voltage, angles between phases). However, for simplicity and readability, the table in the Appendix is ​​limited to equal and nominal line-to-neutral voltages (V1 = V2 = V3 = V n ), and are limited to phases wired in direct sequence.

[0131] The tables in the appendix show the general case for a given connection situation in bold print, and the specific case (usually when the conditions of the downstream load are such that the disconnected line becomes the same potential as the other line) in guideline print.

[0132] Careful analysis and systematic investigations have shown that, based purely on measured line-to-neutral voltages, and / or differences in measured line-to-line voltages and / or phase angles, it is possible to distinguish between each of these situations and thus deterministically infer which situation is present and ultimately which lines (neutral and / or phase(s)) are present or missing.

[0133] A suitable algorithm is then used which iteratively explores the different possible configurations and checks at each step whether the criteria corresponding to the particular configuration of interest (line-neutral voltage and line-line voltage and / or line-neutral voltage and angle) are met.

[0134] See also Figure 7, for the processing unit 15 , the monitoring method according to the invention therefore consists in acquiring voltage measurements made by the voltage sensor of the meter 5 : step E1 .

[0135] The voltage measurements are then processed to produce the current values ​​of these electrical parameters: calculation of measured line-neutral voltage, measured line-line voltage, phase angle difference, etc.: step E2.

[0136] The processing unit 15 then accesses the reference table 20 and implements a heuristic algorithm aimed at searching the reference table to identify the connection configuration associated with the current value of the electrical parameter: step E3 .

[0137] The exploratory algorithm allows to classify the current state from multiple and exhaustive study cases based on the current values ​​of the electrical parameters.The exploratory algorithm allows to systematically and exhaustively explore the reference table and thus explore all expected study cases according to different possible connection configuration cases.

[0138] Therefore, the input information of the heuristic algorithm comprises the current value of the electrical parameter. At the output of the heuristic algorithm, it is reported which line(s) (neutral and / or phase) is connected or disconnected.

[0139] This mechanism for detecting loss of neutral and / or one or more phases is implemented continuously (eg, every second in the loop as new voltage measurements are available).

[0140] The exploratory algorithm consists of the following steps:

[0141] - testing the connection configuration by checking whether predetermined criteria associated with said connection configuration are met, the predetermined criteria being defined based on electrical parameters;

[0142] - if a predetermined criterion is met, it is inferred therefrom that the connection configuration is the configuration corresponding to the current value of the electrical parameter,

[0143] - If no, repeat the test steps with another connection configuration.

[0144] The heuristic algorithm acquires a first predetermined criterion associated with connection configuration number 1 , corresponding to a first hypothesis of the state of the lines (phases and neutral): step E4 .

[0145] The heuristic algorithm tests whether these first predetermined criteria are met: step E5. If this is the case, the heuristic algorithm deduces from this that the current connection configuration corresponds to connection configuration number 1.

[0146] If not, the heuristic algorithm acquires a second predetermined criterion associated with connection configuration number 2, corresponding to a second hypothesis of the state of the lines (phases and neutral): step E6.

[0147] The heuristic algorithm tests whether these second predetermined criteria are met: step E7. If this is the case, the heuristic algorithm deduces from this that the current connection configuration corresponds to connection configuration number 2.

[0148] These steps are repeated a certain number of times. In the Nth iteration, the heuristic algorithm obtains the Nth predetermined criterion (step EN) and tests the connection configuration number N, which corresponds to the Nth hypothesis of the line state: step EN+1.

[0149] If the Nth predetermined criterion is met, the heuristic algorithm infers therefrom that the current connection configuration corresponds to connection configuration number N. If not, the heuristic algorithm infers therefrom that the connection configuration corresponds to an unknown connection situation.

[0150] The number N is the number of different connection configurations listed in reference table 20.

[0151] The heuristic algorithm will now be described in more detail.

[0152] First, a first heuristic algorithm will be described.The first heuristic algorithm uses only the measured line-neutral voltage and the measured line-line voltage as electrical parameters.

[0153] A first heuristic algorithm written in a pseudo-language and thus easily transcribed into all major computer languages ​​is provided in Annex 2.

[0154] The first heuristic algorithm first comprises a preliminary part defining a number of parameters and in particular a very low voltage threshold Voff. This threshold, compared with the measured line-neutral voltage, corresponds to a voltage so low that it can be considered as a phase not present.

[0155] The first heuristic algorithm then comprises a loop instruction every second. In fact, as has been seen, the steps of the monitoring method are repeated regularly: at regular intervals (in this case 1 second), the processing unit 15 acquires new voltage measurements and generates new current values ​​of the electrical parameters. Thus, the first heuristic algorithm is repeated every second in order to identify new connection configurations associated with new current values ​​of the electrical parameters.

[0156] The first heuristic algorithm then calculates the expected line-to-line voltages from the measured line-to-neutral voltages when no line is cut.

[0157] The first heuristic algorithm then attempts to detect one or more measured line-to-line voltages that are abnormal.

[0158] For phases Pi and Pj, if the following is true, then the measured line-to-line voltage U' i Considered abnormal:

[0159] U'i <Uprev i –α or U' i >Uprev i +α,

[0160] in:

[0161] α is the uncertainty margin,

[0162] And among them:

[0163] Uprev i =V n .SQRT(ai 2 +aj 2 +ai.aj),

[0164] Where ai=V i / V n ,aj=V j / V n , V i is the measured line-to-neutral voltage for phase Pi, V j is the measured phase-to-neutral voltage for Pj, and V n is the nominal line-neutral voltage.

[0165] The above formula corresponds to:

[0166] U n =SQRT(3).V n

[0167] It is obtained under nominal conditions with the voltage balanced and at nominal value. It should be noted that this relationship is accurate if and only if the angular relationship between phases Pi and Pj is 120°. Therefore, U' i The measurements are given above and V' is measured with i and V' j The non-compliance of the calculations obtained is sufficient to prove that the angular relationship between phases i and j is not 120°.

[0168] A first heuristic algorithm then consists in testing the set of connection configurations by checking whether predetermined criteria associated with the connection configurations are satisfied.

[0169] In this case, the predetermined criteria include respective comparisons between:

[0170] -The resulting voltage is obtained by adding:

[0171] o two different measured line-neutral voltages; or

[0172] o measured line-to-neutral voltage and measured line-to-line voltage;

[0173] - and the measured line-to-neutral voltage or the measured line-to-line voltage.

[0174] A configuration set is defined as a function of the number of abnormal measured line-to-line voltages.

[0175] Therefore, if the number of abnormal measured line-to-line voltages is equal to zero, the first heuristic algorithm defaults to considering the current connection configuration to be the nominal connection configuration for time T, where the neutral and phases are normally connected, and then tests a connection configuration where at least one phase is disconnected.

[0176] The first heuristic algorithm therefore first assumes that the neutral and three phases are connected normally.

[0177] The first heuristic algorithm then attempts to calculate the measured line-to-neutral voltage V' by, for each phase Pi, i The line-to-neutral voltage is strictly less than V o ff, it is considered that the phase Pi is disconnected.

[0178] If the number of abnormal measured line-to-line voltages is equal to 1, the first heuristic algorithm defaults the current connection configuration to be the nominal connection configuration and then tests connection configurations in which a single phase is disconnected and connection configurations in which a phase is disconnected and brought to the potential of another phase.

[0179] The first heuristic algorithm therefore first assumes that the neutral and three phases are connected normally.

[0180] Then, for each phase Pi, the algorithm checks whether:

[0181] V'i+U'i=V'j, or whether V'i+U'k=V'k (where j=i+1 and k=i+2).

[0182] If this is the case, the algorithm infers from this that phase Pi is disconnected.

[0183] If the algorithm has detected that Pi is disconnected, the algorithm checks whether:

[0184] V'i=V'j or whether V'i=V'k.

[0185] If this is the case, it can be inferred from this that phase Pi is connected to another phase.

[0186] If the number of abnormal measured line-to-line voltages is equal to 2, the first heuristic algorithm defaults the current connection configuration to be the nominal connection configuration and then tests a connection configuration in which a single phase is disconnected (and brought back between the two other phases and the neutral).

[0187] The first heuristic algorithm therefore first assumes that the neutral and three phases are connected normally.

[0188] Then, for each phase Pi, the algorithm checks whether:

[0189] V'i<V'j and U'i<V'j, or whether

[0190] V'i<V'k and U'k<V'k.

[0191] If this is the case, the algorithm infers from this that phase Pi is disconnected.

[0192] If the number of abnormal measured line-to-line voltages is equal to 3, the first exploratory algorithm defaults to assuming that the current connection configuration is a connection configuration in which only the neutral line is cut (and in which a significant imbalance is clearly present in the downstream load), then tests a connection configuration in which one of the phases and the neutral line are cut (and brought back between the two other phases), then tests a connection configuration in which one of the phases is connected to another phase, then a connection configuration in which two phases are cut (brought back between the neutral line and the remaining phases), then a connection configuration in which three phases are connected to each other, and then a connection configuration in which one of the phases is reversed with respect to the neutral line.

[0193] The first heuristic algorithm begins by assuming that the neutral is disconnected and the three phases are correctly connected.

[0194] Next, for each phase Pi, the algorithm checks whether:

[0195] V'j+V'k=U'j and U'i+U'k=U'j

[0196] If this is the case, the algorithm infers from this that phase Pi is disconnected.

[0197] If the algorithm has detected that Pi is disconnected, it checks whether:

[0198] U'i=U'j or whether U'k=U'j.

[0199] If this is the case, it can be inferred from this that phase Pi is connected to another phase.

[0200] Next, the algorithm attempts to detect the loss of only two phases (bringing back between neutral and the remaining phases).

[0201] At each phase Pi, the algorithm checks whether:

[0202] V'i+U'k=V'k and V'j+U'j=V'k

[0203] If this is the case, the algorithm infers from this that phase Pi and phase Pj are disconnected.

[0204] If the algorithm has detected that Pi and phase Pj are disconnected, the algorithm checks whether:

[0205] V'i=V'j and whether V'i=V'k.

[0206] If this is the case, it can be inferred from this that the three phases are connected together.

[0207] Next, the algorithm attempts to detect a neutral and a phase reversal in the meter's wiring.

[0208] For each phase, knowing the measured line-to-neutral voltage and assuming reversal of neutral and phase Pi, the algorithm calculates the expected line-to-line voltages Uprev_inv[i], Uprev_inv[j], Uprev_inv[k].

[0209] If the following apply:

[0210] Uprev_inv[i]=V'j and Uprev_inv[j]=U'j and Uprev_inv[k]=V'k, the algorithm infers from this that the neutral and phase Pi are inverted.

[0211] Next, for each phase Pi, the algorithm compares the line-neutral voltage V′i with a predetermined threshold in order to assign a state regarding the voltage level from the network: voltage, undervoltage, significant undervoltage, dangerous overvoltage, etc.

[0212] The algorithm also assigns a state to the criticality of the voltage level on the downstream side and makes it possible to control the opening of a circuit breaker in order to protect the equipment connected downstream of the meter 5 (equipment of the installation 7 ).

[0213] It should be noted that all of these comparisons can be made by adding margins that allow for uncertainty to be taken into account; for example, as shown in the first heuristic algorithm provided in Appendix 2, instead of checking whether:

[0214] V'i+U'i=V'j or V'i+U'k=V'k,

[0215] Check the following:

[0216] V'i+U'i=V'j+ / -(2.Y) or V'i+U'k=V'k+ / -(2.Y),

[0217] Y is the margin that allows to take into account the uncertainty in the voltage measurement.

[0218] Therefore, the first heuristic algorithm (similar to the second algorithm described below) provides the required margin to account for measurement uncertainties and initial tolerances of the power network.

[0219] A second heuristic algorithm will now be described.

[0220] The second heuristic algorithm uses only the measured line-neutral voltage and the measured angle as electrical parameters.

[0221] A second heuristic algorithm written in pseudo language is provided in Appendix 3.

[0222] The second heuristic algorithm first comprises a preliminary part which defines a number of parameters and in particular a high angle threshold and a low angle threshold.

[0223] The second heuristic algorithm then includes loop instructions per second.

[0224] The second heuristic algorithm then compares each measured line-neutral voltage to a threshold value Voff, and if all measured line-neutral voltages are strictly smaller than said threshold value Voff, the algorithm is disabled.

[0225] For each phase Pi, if the line-neutral voltage measured on the phase Pi is strictly smaller than a predetermined threshold Voff, the measured angle relating to said phase is not considered reliable and is set to zero.

[0226] The algorithm first tests the nominal connection configuration, where the neutral and phases are connected normally.

[0227] The algorithm compares each measured angle with a reference value Aref and if the measured angles are equal to Aref (possibly taking into account an uncertainty margin), the algorithm deduces from this that the neutral and the three phases are connected normally and that the phases are wired to the meter 5 in direct sequence.

[0228] If this condition is not met, the algorithm compares each measured angle with a reference value -Aref and if the measured angles are all equal to -Aref, the algorithm deduces from this that the neutral and the phases are normally connected and that the phases are wired to the meter in direct order.

[0229] The algorithm then tests connection configurations in which one phase is reversed with respect to the neutral line in each configuration.

[0230] For this purpose, the algorithm compares each measured angle with a high angle threshold and a low angle threshold. Thus, the predetermined criterion comprises only a comparison between the measured angle and the angle thresholds.

[0231] Next, the algorithm tests a connection configuration in which a single phase is disconnected and the other two phases and neutral are normally connected. The predetermined criteria include a comparison between the measured angle and an angle threshold, and a comparison between the measured line-neutral voltage and a voltage threshold.

[0232] If the algorithm has detected a disconnected phase, it attempts to detect whether said phase has been brought to the potential of one of the other phases.

[0233] Next, the algorithm attempts to detect a connection configuration where the neutral is disconnected and the other three phases are still connected.

[0234] Again, the predetermined criterion merely comprises a comparison between the measured angle and an angle threshold.

[0235] The algorithm then tests a connection configuration where two lines are disconnected and the other lines remain connected.

[0236] The predetermined criteria include a comparison between a measured angle and an angle threshold, and a comparison between a measured line-neutral voltage and a voltage threshold.

[0237] The algorithm then attempts to detect a connection configuration where two phases are disconnected and the neutral and another phase remain connected (a specific case of the above configuration).

[0238] If the algorithm has detected a disconnected phase, it attempts to detect whether said phase has been brought to the potential of one of the other phases.

[0239] The algorithm then attempts to detect a disconnect configuration (a special case of the above configuration) where the neutral and one phase are disconnected and the other two phases are normally connected.

[0240] If the algorithm has detected a disconnected phase, it attempts to detect whether said phase has been brought to the potential of one of the other phases.

[0241] Next, the algorithm again tests the connection configuration where the neutral and one phase are disconnected and the other two phases are normally connected.

[0242] Finally, similar to the first heuristic algorithm, for each phase Pi, the second heuristic algorithm compares the line-neutral voltage V'i with a predetermined threshold in order to assign a state regarding the voltage level from the network: voltage, undervoltage, significant undervoltage, dangerous overvoltage, etc.

[0243] The algorithm also assigns a state to the criticality of the voltage level on the downstream side and makes it possible to control the opening of a circuit breaker in order to protect the equipment connected downstream of the meter 5 (equipment of the installation 7 ).

[0244] The invention is therefore based on criteria that are easily measured in the industry (voltage measurements and their processing) and of high certainty, and it does not require any reference measurements from before the suspected loss of neutral. The voltage measurements made at time T are sufficient in themselves to be able to determine whether a loss of neutral and / or one or more phases has occurred, as they are sufficient to determine the current connection configuration by analyzing the corresponding characteristic conditions in the Fresnel diagram. In the final realization of the proposed solution, regardless of the specific implementation of the method, suitable uncertainty margins are advantageously allowed, in particular concerning the accuracy of the voltage measurements and possible angles (typically + / -1V or + / -1% and + / -2° respectively, depending on the method and acquisition means), as proposed in the specific implementation of the provided heuristic algorithm.

[0245] Optionally, in order to minimize the risk of false positives, regardless of the specific embodiment of the method, it may be ascertained that predetermined detection criteria are met over several successive iterations before reporting a loss of neutral and / or one or more phases.

[0246] Optionally, the detection of the loss of the neutral conductor and / or of one or more phases generates an alarm which is time-stamped in one of the memories 17 of the processing unit 15 of the meter 5 and / or in the case of a communicating meter (e.g. communicating via a transmission channel based on PLC technology or cellular radio technology), an alarm signal can be sent to equipment external to the meter and, for example, to a telematics system (possibly autonomously, depending on the advanced protocol used).

[0247] Optionally, the detection of the loss of the neutral conductor and / or one or more phases generates a specific and dedicated display on a local display of the meter or by means of indicator lights.

[0248] Optionally, detection of loss of neutral and / or one or more phases generates emission of an acoustic signal.

[0249] Optionally, when loss of neutral is detected and when the imbalance of the line-neutral voltage is deemed to be abnormally significant, an alarm signal is generated and time-stamped in a memory of the meter's processing unit and / or, in the case of a communicating meter, sent to equipment external to the meter and, for example, to a telematics system.

[0250] Optionally, when a loss of neutral is detected and when the imbalance of the line-neutral voltage is deemed too high and dangerous for downstream equipment, in the case of meters provided with circuit breakers, these are activated to switch to the open state and thus protect the downstream equipment.

[0251] Finally, it is also possible to use the invention proposed here in a different way, so as not to detect the loss of a conductor (phase(s) and / or neutral), but to automatically detect the wiring for connection to the network (2 conductors, 3 conductors, 4 conductors, etc.).

[0252] Naturally, the invention is not limited to the described implementation examples but covers any variant coming within the ambit of the invention as defined by the claims.

[0253] The item of electrical equipment in which the invention is (at least partially) implemented is not necessarily a meter but can be any type of equipment (eg a circuit breaker) which is connected to a network and can be provided with a voltage sensor.

[0254] appendix

[0255] Appendix 1

[0256] An example of a reference table is provided here.

[0257] The reference table consisting of 32 rows and 20 columns has been split into 4 tables to improve the readability of the table.

[0258] Table 1 includes 32 rows and 6 columns on the left hand side of the reference table; Table 2 includes 32 rows and 5 columns located to the right of the columns of Table 1; Table 3 includes 32 rows and 6 columns located to the right of the columns of Table 2; Table 4 includes 32 rows and 3 columns located to the right of the columns of Table 3.

[0259] Table 1:

[0260]

[0261]

[0262]

[0263] Table 2:

[0264]

[0265]

[0266]

[0267] Table 3:

[0268]

[0269]

[0270] Table 4:

[0271]

[0272]

[0273] Appendix 2

[0274] The first heuristic algorithm is as follows:

[0275]

[0276]

[0277]

[0278]

[0279]

[0280]

[0281] Appendix 3

[0282] The second heuristic algorithm is as follows:

[0283]

[0284]

[0285]

[0286]

[0287]

[0288]

[0289]

[0290]

[0291]

[0292]

[0293]

[0294]

Claims

1. A method for monitoring a multiphase power network, the method being at least partly implemented in a processing unit of an item of electrical equipment connected to the multiphase power network and comprising the following steps which are periodically repeated: The voltage sensor (R 1A ,R 1B ,R 2A ,R 2B ,R 3A ,R 3B ) voltage measurements made; generating a present value of an electrical parameter from said voltage measurement; accessing a reference table (20), the reference table comprising a list of connection configurations, each connection configuration being associated with a different combination of reference values ​​of the electrical parameter, the list of connection configurations comprising first connection configurations each corresponding to a different combination of connected or disconnected states of each phase (P1, P2, P3) and a neutral conductor (N); An exploratory algorithm is implemented that is directed to exploring the reference table to identify a connection configuration associated with a current value of the electrical parameter.

2. The method for monitoring a multiphase power network according to claim 1, characterized in that The connection configuration list includes second connection configurations corresponding to the neutral line (N) and the reversal of the phase (P1, P2, P3) for each of the phases (P1, P2, P3).

3. The method for monitoring a multiphase power network according to claim 2, characterized in that: The implementation of the heuristic algorithm includes the following steps: testing a connection configuration by checking whether a predetermined criterion associated with the connection configuration is satisfied, the predetermined criterion being defined based on the electrical parameter; If the predetermined criterion is met, it is inferred therefrom that the connection configuration is the configuration corresponding to the current value of the electrical parameter, If no, repeat the test steps with another connection configuration, The electrical parameters include: measured line-to-neutral voltages, each measured line-to-neutral voltage representing a line-to-neutral voltage between one of the phases and the neutral line Amplitude; and / or Measured line-to-line voltages, each of which represents the line-to-line voltage between two different phases )’s amplitude; and / or measured angles (Phi1, Phi2, Phi3), each measured angle being equal to the angle between a vector representation of the line-to-neutral voltage between one phase and the neutral and a vector representation of the line-to-neutral voltage between another phase and the neutral, wherein the heuristic algorithm implemented is a second heuristic algorithm using only the measured line-neutral voltage and the measured angle as electrical parameters, wherein the predetermined criterion associated with the following connection configurations comprises only a comparison between the measured angle and an angle threshold: The neutral line and all phases are normally connected; said neutral line is inverted with respect to one of said phases; The neutral line is disconnected and all phases are connected.

4. The method for monitoring a multiphase power network according to claim 1, characterized in that: The connection configuration list includes third connection configurations each corresponding to one of the phases that is disconnected and at a potential of another phase.

5. The method for monitoring a multiphase power network according to claim 1, characterized in that: The implementation of the heuristic algorithm includes the following steps: testing a connection configuration by checking whether a predetermined criterion associated with the connection configuration is satisfied, the predetermined criterion being defined based on the electrical parameter; If the predetermined criterion is met, it is inferred therefrom that the connection configuration is the configuration corresponding to the current value of the electrical parameter, If no, repeat the test steps with another connection configuration.

6. The method for monitoring a multiphase power network according to claim 5, characterized in that: The electrical parameters include: measured line-to-neutral voltages, each measured line-to-neutral voltage representing a line-to-neutral voltage between one of the phases and the neutral line Amplitude; and / or Measured line-to-line voltages, each of which represents the line-to-line voltage between two different phases )’s amplitude; and / or measured angles (Phi1, Phi2, Phi3), each measured angle being equal to the angle between a vector representation of the line-to-neutral voltage between one phase and the neutral and a vector representation of the line-to-neutral voltage between another phase and the neutral, wherein the heuristic algorithm implemented is a first heuristic algorithm using only measured line-neutral voltage and measured line-line voltage as electrical parameters, Wherein said first heuristic algorithm comprises a step of attempting to detect abnormal one or more measured line-line voltages, said first heuristic algorithm then consists in testing a set of connection configurations, said set being defined as a function of the number of abnormal measured line-line voltages.

7. The method for monitoring a multiphase power network according to claim 6, characterized in that: In the following cases, the measured line-to-line voltage U' i Considered abnormal: IN' i <Uprev i –α or U' i >Edit i +α, in: α is the uncertainty margin, And among them: Uprev i =V n .SQRT(ai 2 +aj2+ai.aj), Where ai=V i / V n , aj = V j / V n , V i is the measured line-to-neutral voltage for phase Pi, V j is the measured phase-to-neutral voltage for Pj, and V n is the nominal line-neutral voltage.

8. The method for monitoring a multiphase power network according to claim 5, characterized in that: The electrical parameters include: measured line-to-neutral voltages, each measured line-to-neutral voltage representing a line-to-neutral voltage between one of the phases and the neutral line Amplitude; and / or Measured line-to-line voltages, each of which represents the line-to-line voltage between two different phases Amplitude; and / or measured angles (Phi1, Phi2, Phi3), each measured angle being equal to the angle between a vector representation of the line-to-neutral voltage between one phase and the neutral and a vector representation of the line-to-neutral voltage between another phase and the neutral, wherein the heuristic algorithm implemented is a first heuristic algorithm using only measured line-neutral voltage and measured line-line voltage as electrical parameters, wherein the predetermined criteria include a comparison made between: The resulting voltage is obtained by adding: Two different measured line-neutral voltages; or measured line-to-neutral voltage and measured line-to-line voltage; and the measured line-to-neutral voltage or the measured line-to-line voltage.

9. The method for monitoring a multiphase power network according to claim 1, characterized in that: The electrical parameters include: measured line-to-neutral voltages, each measured line-to-neutral voltage representing a line-to-neutral voltage between one of the phases and the neutral line Amplitude; and / or Measured line-to-line voltages, each of which represents the line-to-line voltage between two different phases Amplitude; and / or Angles (Phi1, Phi2, Phi3) are measured, each equal to the angle between a vector representation of the line-to-neutral voltage between one phase and the neutral and a vector representation of the line-to-neutral voltage between another phase and the neutral.

10. The method for monitoring a multiphase power network according to claim 9, characterized in that: The measured angle is obtained by implementing a zero-crossing detection method on the voltage measured between the phase and the neutral line.

11. The method for monitoring a multiphase power network according to claim 9, characterized in that: The heuristic algorithm implemented is a first heuristic algorithm using only measured line-neutral voltage and measured line-line voltage as electrical parameters.

12. The method for monitoring a multiphase power network according to claim 9, characterized in that: The heuristic algorithm implemented is a second heuristic algorithm using only the measured line-neutral voltage and the measured angle as electrical parameters.

13. The method for monitoring a multiphase power network according to claim 12, characterized in that: The second heuristic algorithm tests whether the phases are connected to the item of electrical equipment in a direct or indirect order.

14. An item of electrical equipment comprising a voltage sensor and a processing unit, in which the method for monitoring a multiphase power network according to claim 1 is implemented.

15. An item of electrical equipment as claimed in claim 14, the item of electrical equipment being a meter.

16. A non-volatile computer-readable storage medium having stored thereon a computer program comprising instructions, the instructions causing a processing unit of an electrical equipment item to execute the steps of the method for monitoring a multiphase power network according to claim 1, wherein the electrical equipment item comprises the voltage sensor and a processing unit in which the method for monitoring a multiphase power network is implemented.

17. A computer program product having stored thereon a computer program comprising instructions, the instructions being executed by a processor to implement the steps of the method for monitoring a multiphase power network as claimed in claim 1.