A construction method for marking the intersection line of beams and slabs inside a house to the roof surface
Through the combination of laser projection and calibration method, the problem of calibration of the position of the roof beam and slab intersecting line is solved, and the accurate calibration of the beam and slab intersecting line in the house is achieved, and the impact of obstacles in the house is overcome, with high accuracy and low error .
Patent Information
- Application Number
- CN202311397139.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2023-10-26
- Publication Date
- 2024-11-08
- Estimated Expiration
- 2043-10-26
AI Technical Summary
In architectural structures, it is difficult to accurately calibrate the position of beam and slab intersecting lines on the roof ceiling, especially in the lack of detailed drawings and space limitations inside the building, conventional measurement methods cannot effectively calibrate the position of beam and slab intersecting lines.
At least two laser projectors are used to set longitudinal rectangular lines directly below the intersecting line of the beam and plate. Parallel lines outside the house are determined by projecting and parallel extraction methods. The calibrator and laser projector project on the roof to form calibration lines, and accurately locate the beam The position of the board intersecting line.
The precise calibration of the beam and slab intersecting line in the house is achieved on the roof ceiling. The method is simple and practical, with a small number of instruments and a light weight. It overcomes the influence of obstacles in the house and has high accuracy and low error.
Smart Images

Figure CN117489135B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the field of building civil engineering, and in particular to a construction method for marking the intersection line of beams and slabs in a house to the roof surface. Background Art
[0002] In conventional building structures, the column structure inside the building generally does not extend upward to the roof surface, and there are construction errors in the construction of the beam-slab intersection line. Some buildings have been built for a long time and have no relevant drawings. When the roof needs to be loaded, the lower beam-slab intersection line needs to be projected specifically on the roof surface. However, due to the space limitations of the building and the scope of application of conventional instruments and equipment, conventional measurement and layout methods cannot calibrate the position of the beam-slab intersection line inside the building on the roof surface. Summary of the invention
[0003] In order to solve the above technical problems, the present invention provides a construction method for marking the intersection line of beams and slabs inside a house to the roof surface. This method can mark the position of the intersection line of beams and slabs inside a building on the roof surface.
[0004] In order to achieve the above-mentioned purpose, the technical solution adopted by the present invention is: to provide a construction method for marking the intersection line of beams and slabs in a house to the roof surface, which is characterized by comprising the following steps:
[0005] 1) Projection of beam-slab intersection line: at least two first laser line projectors are arranged directly below the beam-slab intersection line, so that the longitudinal rectangular lines emitted by at least two first laser line projectors overlap with each other, and the longitudinal rectangular lines overlap with the beam-slab intersection line above the house, at which time the longitudinal rectangular lines form a beam-slab intersection projection line on the ground;
[0006] 2) Parallel derivation of the beam-slab intersection line: At least two first laser line projectors are used as vertical feet to draw a vertical line in the direction perpendicular to the beam-slab intersection projection line to obtain at least two first calibration points. The distance between each first calibration point and its corresponding first laser line projector is L1. The outdoor parallel line parallel to the beam-slab intersection projection line is obtained by connecting at least two first calibration points;
[0007] 3) Setting up the outdoor laser projector: Set the second laser projector on the parallel lines outside the house so that the longitudinal rectangular lines it emits coincide with the parallel lines outside the house;
[0008] 4) Determine the roof calibration line: set at least two calibration objects on the same horizontal plane on the outermost wall of the roof, and project the longitudinal rectangular lines onto the at least two calibration objects with a second laser line projector outside the house to form at least two second calibration points. The at least two second calibration points are connected by a line to obtain a roof calibration line parallel to the parallel line outside the house;
[0009] 5) Calibrate the roof projection line of the intersection of beam and slab: With at least two second calibration points as the foot of perpendicular, draw a perpendicular line in the direction perpendicular to the roof calibration line to obtain at least two third calibration points. The distance between each third calibration point and its corresponding second calibration point is L2, and L2=L1. The roof projection line of the intersection of beam and slab is obtained by connecting at least two third calibration points.
[0010] As a further improvement of the present invention, in step 2), the first calibration point is formed by the first laser line projector emitting a horizontal rectangular line to the ground outside the house, and the distance between the first calibration point and the first laser line projector is measured along the horizontal rectangular line.
[0011] As a further improvement of the present invention, the horizontal rectangular lines of the first laser line projector are emitted from inside the house to the outside through windows, holes or doorways.
[0012] As a further improvement of the present invention, in step 4), the calibration object is a horizontal directional alignment ruler, which can be adjusted vertically 360 degrees by hinges, and the water bubble is used to determine whether it is horizontal during adjustment. At the same time, it has a vertical telescopic structure for fine-tuning the height.
[0013] As a further improvement of the present invention, in step 5), at least two third laser line projectors are arranged on the roof, and the height of the third laser line projectors is at the same horizontal plane as the calibration object. The height is adjusted based on the overlap of the horizontal rectangular lines emitted by the third laser line projector with the calibration object. At the same time, the position of the third laser line projector is adjusted so that the horizontal rectangular lines emitted by the third laser line projector overlap with the calibration object and are perpendicular to the ceiling calibration line. The distance between the second calibration point and the third calibration point is measured along the horizontal rectangular lines of the third laser line projector.
[0014] As a further improvement of the present invention, in step 5), when the third calibration point is located above the roof plane, the third calibration point is transferred to the roof plane by the pendulum ball method.
[0015] As a further improvement of the present invention, all laser line projectors adopt 12-line laser line projectors, but when using them, it is necessary to adjust the bubble on the instrument to the center position.
[0016] The beneficial effects of the present invention are as follows: the present invention uses a simple measuring instrument and the projection and displacement of the beam-slab intersection line to realize the calibration of the position of the beam-slab intersection line inside the building on the roof surface. This method is simple and practical, uses a small number of instruments, is light in weight, is compact and portable, is easy to set up, and is easy to implement. The present invention can overcome the difficulty of measuring due to many obstacles in the house, and has the characteristics of high accuracy and small error. BRIEF DESCRIPTION OF THE DRAWINGS
[0017] Figure 1 This is a schematic diagram of the interior and exterior construction;
[0018] Figure 2 This is a schematic diagram of the rooftop construction;
[0019] Marking description: First laser line projector 1, beam-slab intersection line 2, beam-slab intersection projection line 3, first calibration point 4, outdoor parallel line 5, second laser line projector 6, calibration object 7, second calibration point 8, ceiling calibration line 9, third calibration point 10, beam-slab intersection ceiling projection line 11, third laser line projector 12 DETAILED DESCRIPTION
[0020] The present invention will be further described below in conjunction with specific embodiments and accompanying drawings.
[0021] A construction method for calibrating the intersection line of beams and slabs inside a house to the roof surface has been successfully used in the Liyutan photovoltaic project in Xuwen County, Guangdong. The method is implemented in the following steps:
[0022] 1) Projection of beam-slab intersection line: two first laser line projectors 1 are set just below the beam-slab intersection line 2, so that the longitudinal rectangular lines emitted by the two first laser line projectors 1 overlap with each other, and the longitudinal rectangular lines overlap with the beam-slab intersection line 2 above the house. At this time, the longitudinal rectangular lines form a beam-slab intersection projection line 3 on the ground;
[0023] 2) Parallel lead-out of the intersection line of beam and slab: With the two first laser line projectors 1 as the foot of the perpendicular, draw a perpendicular line in the direction perpendicular to the intersection projection line 3 of the beam and slab to obtain two first calibration points 4. The distance between each first calibration point 4 and its corresponding first laser line projector 1 is L1. The two first calibration points 4 are connected by a line to obtain an outdoor parallel line 5 parallel to the intersection projection line 3 of the beam and slab. It should be noted that the first laser line projector 1 can emit horizontal rectangular lines, which are emitted to the outdoor ground through visible light-transmitting structures such as windows, openings or doorways, and the first calibration points 4 are located on the horizontal rectangular lines on the outdoor ground.
[0024] 3) Setting up the outdoor laser projection device: Set the second laser projection device 6 on the outdoor parallel line 5 so that the longitudinal rectangular line it emits coincides with the outdoor parallel line 5;
[0025] 4) Determine the ceiling calibration line: Two calibration objects 7 are set on the outermost wall of the roof on the same horizontal plane. The calibration object 7 uses a horizontal directional alignment ruler. The horizontal directional alignment ruler can be adjusted vertically 360 degrees through a hinge, and the water bubble is used to determine whether it is horizontal during adjustment. At the same time, it has a vertical telescopic structure for fine-tuning the height. The second laser projection 6 outside the house emits longitudinal rectangular lines and projects them onto the two calibration objects 7 to form two second calibration points 8. The two second calibration points 8 are connected by a line to obtain a ceiling calibration line 9 parallel to the outdoor parallel line 5;
[0026] 5) Calibrate the roof projection line of the intersection of beam and slab: Take the two second calibration points 8 as the foot of the vertical line and draw a vertical line in the direction perpendicular to the roof calibration line 9 to obtain two third calibration points 10. By measuring, the distance between each third calibration point 10 and its corresponding second calibration point 8 is L2, and L2 = L1. The two third calibration points 10 are connected to obtain the roof projection line 11 of the intersection of beam and slab. It should be noted that in this embodiment, since the calibration point is located above the roof plane, the pendulum ball method is required to transfer the third calibration point 10 to the roof plane, so that the roof projection line 11 of the intersection of beam and slab can be formed on the roof plane.
[0027] The beams and columns on the same line can be synchronously calibrated on the roof surface through the actual measured quantity data between the indoor and outdoor ground projection lines to achieve other detailed projections.
[0028] Similarly, by looping steps 1) to 5), the intersection line 2 of the beams and slabs inside the house can be projected onto the roof surface, and the roof surface is not affected by the horizontal tilt.
[0029] In addition, in order to accurately measure the value of L2 and reduce errors, in step 5), two third laser line projectors 12 are also arranged on the roof. The third laser line projectors 12 are placed behind the visual projection line 11 of the intersection of the beam and the slab. The height of the third laser line projector 12 is on the same horizontal plane as the calibration object 7. The height is adjusted based on the overlap of the horizontal rectangular lines emitted by the third laser line projector 12 with the calibration object 7. At the same time, the position of the third laser line projector 12 is adjusted so that the horizontal rectangular lines it emits overlap with the calibration object 7 and are perpendicular to the ceiling calibration line 9. The distance between the second calibration point 8 and the third calibration point 10 is measured along the horizontal rectangular lines of the third laser line projector 12.
[0030] The first, second and third laser line projectors mentioned above all use 12-line laser line projectors with a tripod bracket, which can generate a horizontal plane and two orthogonal vertical planes. Each laser plane can generate a circle line projected within 360° with the laser light point as the center. The laser line projector host is equipped with a bubble and a buzzer for continuous alarm to help with quick leveling. The horizontal and vertical laser accuracy of the laser line projector is ≤±1mm / 10m. When using the laser line projector, it is necessary to adjust the bubble on the instrument to the center position. In order to reduce measurement errors, in other embodiments, the number of the first, second and third laser line projectors can be more than two.
[0031] Taking into account the visibility of lasers, the above method needs to be implemented under weak or dim light conditions, and three sets of laser projectors indoors, outdoors and on the roof can operate simultaneously.
[0032] This method has the following advantages:
[0033] 1. Only one measuring instrument is needed, which can meet the measurement requirements both indoors and outdoors. The method of overlapping and intersecting lines can overcome the difficulty of measuring due to many obstacles in the house. The measuring instrument is light in weight, compact and portable, and easy to set up.
[0034] 2. The calibration object 7 can be used as an aerial laser receiving station to realize functions such as reception and horizontal control, and play the role of a comprehensive aerial vertical and horizontal conversion.
[0035] 3. Realize the integration of modern laser measurement technology and traditional ruler measurement and hammer ball point projection technology.
[0036] 4. Strong versatility. It can meet the complex structure of the roof and the house, and only needs a small number of windows to be the same as the outside world. It can realize the reverse projection of the beam and column structure inside the house to the roof, and meet the construction requirements of special and general sites.
[0037] 5. Low error, the error can be controlled within ±1mm within a height of 10m. The multi-machine synchronous measurement technology is adopted to reduce the cumulative error of laser conduction.
[0038] 6. The method is simple and the measurement is reliable. The horizontal adjustment of the laser line projector can be adjusted through the ordinary theodolite and the tripod of the total station to achieve automatic leveling and manual leveling. Ordinary surveyors can meet its operating requirements.
[0039] 7. The measurement sequence is clear. The present invention clarifies the conduction mode of first measuring inside the house and then measuring outside the house; first measuring low and then measuring high, and assists with the ruler measurement and hammer ball positioning method, which makes it easy for construction personnel to understand and implement.
[0040] 8. Strong promotional potential. The concept of the present invention can not only be applied to high-precision projection of indoor and outdoor roof structures, but also can be used to achieve precise measurement of indoor structures by using a relative coordinate system.
[0041] The above embodiments are only used to illustrate the present invention and are not intended to limit the present invention in any form. Any person with ordinary knowledge in the technical field may make partial changes or modifications to the technical contents disclosed in the present invention without departing from the scope of the technical features of the present invention, and the equivalent embodiments without departing from the technical features of the present invention are still within the scope of the technical features of the present invention.
Claims
1. A construction method for marking the intersection line of beams and slabs in a house to the roof surface, characterized in that The following steps are involved: 1) Projection of beam-slab intersection line: at least two first laser line projectors are arranged directly below the beam-slab intersection line, so that the longitudinal rectangular lines emitted by at least two first laser line projectors overlap with each other, and the longitudinal rectangular lines overlap with the beam-slab intersection line above the house, at which time the longitudinal rectangular lines form a beam-slab intersection projection line on the ground; 2) Parallel derivation of the beam-slab intersection line: At least two first laser line projectors are used as vertical feet to draw a vertical line in the direction perpendicular to the beam-slab intersection projection line to obtain at least two first calibration points. The distance between each first calibration point and its corresponding first laser line projector is L1. The outdoor parallel line parallel to the beam-slab intersection projection line is obtained by connecting at least two first calibration points; 3) Setting up the outdoor laser projector: Set the second laser projector on the parallel lines outside the house so that the longitudinal rectangular lines it emits coincide with the parallel lines outside the house; 4) Determine the roof calibration line: set at least two calibration objects on the same horizontal plane on the outermost wall of the roof, and project the longitudinal rectangular lines onto the at least two calibration objects with a second laser line projector outside the house to form at least two second calibration points. The at least two second calibration points are connected by a line to obtain a roof calibration line parallel to the parallel line outside the house; 5) Calibrate the roof projection line of the intersection of beam and slab: With at least two second calibration points as the foot of perpendicular, draw a perpendicular line in the direction perpendicular to the roof calibration line to obtain at least two third calibration points. The distance between each third calibration point and its corresponding second calibration point is L2, and L2=L1. The roof projection line of the intersection of beam and slab is obtained by connecting at least two third calibration points.
2. A construction method for marking the intersection line of beams and slabs in a house to the roof surface according to claim 1, characterized in that: In step 2), the first calibration point is formed by the first laser line projector emitting a transverse rectangular line to the ground outside the house, and the distance between the first calibration point and the first laser line projector is measured along the transverse rectangular line.
3. A construction method for marking the intersection line of beams and slabs in a house to the roof surface according to claim 2, characterized in that: The horizontal rectangular lines of the first laser projector are emitted from inside the house to the outside through windows, holes or doorways.
4. The construction method for marking the intersection line of beams and slabs in a house to the roof surface according to claim 1, characterized in that: In step 4), the calibration object is a horizontal directional alignment ruler, which can be adjusted vertically 360 degrees through hinges, and the water bubble is used to determine whether it is horizontal during adjustment. At the same time, it has a vertical telescopic structure for fine-tuning the height.
5. The construction method for marking the intersection line of beams and slabs in a house to the roof surface according to claim 1, characterized in that: In step 5), at least two third laser line projectors are arranged on the roof. The height of the third laser line projector is at the same horizontal plane as the calibration object. The height is adjusted based on the standard that the horizontal rectangular lines emitted by the third laser line projector overlap with the calibration object. At the same time, the position of the third laser line projector is adjusted so that the horizontal rectangular lines emitted by it overlap with the calibration object and are perpendicular to the ceiling calibration line. The distance between the second calibration point and the third calibration point is measured along the horizontal rectangular lines of the third laser line projector.
6. The construction method for marking the intersection line of beams and slabs in a house to the roof surface according to claim 1, characterized in that: In step 5), when the third calibration point is located above the roof plane, the third calibration point is transferred to the roof plane by the pendulum ball method.
7. The construction method for marking the intersection line of beams and slabs in a house to the roof surface according to claim 1, characterized in that: All laser line projectors use 12-line laser line projectors. When using them, you need to adjust the bubble on the instrument to the center position.