A sponge city road rainwater recycling system and construction method
By using grouting pipes in the reservoir to pour cement grout material and slip parts, the problems of leakage and anti-seepage membrane aging of the reservoir under lateral soil pressure are solved, and the high strength of the reservoir is achieved Long-term stability.
Patent Information
- Application Number
- CN202410030425.0
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2024-01-05
- Publication Date
- 2024-12-03
- Estimated Expiration
- 2044-01-05
AI Technical Summary
Existing reservoirs are prone to leakage and aging, cracking and damage of anti-seepage membranes under lateral active soil pressure.
After the water storage module is assembled to form the main body of the reservoir, a grouting pipe is used to pour cement grout into the grouting chamber to form a high-strength shell, and the grouting pipe slides along the length direction and cooperates with the sliding parts to ensure that the grouting chamber is completed. The uniform filling and compactness of the chamber reduce the risk of leakage under soil pressure.
It effectively improves the sealing and strength of the reservoir under lateral soil pressure, reduces leakage and damage caused by aging of the anti-seepage membrane, and ensures the stability of the reservoir's long-term use.
Smart Images

Figure CN117779929B_ABST
Abstract
Description
Technical Field
[0001] The present application relates to the field of water collection pools, and in particular to a sponge city road rainwater recycling system and a construction method. Background Art
[0002] Sponge city refers to the concept of rainwater management that collects, stores and purifies rainwater when it rains, and releases and utilizes the stored water when water is needed, thereby achieving the free migration of rainwater in the city. For the rainwater reuse system, the reservoir is an important infrastructure for the collection, storage and purification of the entire rainwater reuse system.
[0003] In the existing related technologies, water reservoirs are usually buried underground to reduce the bottom of the urban surface space occupied by the water reservoirs. The input pipes of the water reservoirs are set around the roads to transport the accumulated water on the roads to the water reservoirs in time to reduce the occurrence of excessive accumulation of water on the roads.
[0004] A water reservoir usually includes a water storage module and an impermeable membrane. There are several water storage modules, and the material of the several water storage modules is PP. The main body of the water reservoir is formed by plugging and assembling several water storage modules. Water storage pores are opened inside the water storage module, and the water storage pores of several water storage modules are interconnected to form a water storage chamber. Generally speaking, the volume of the water storage chamber accounts for about 95% of the volume of the water storage module, so that the water storage module has a better unit water storage capacity compared to the traditional reinforced concrete structure. The impermeable membrane is coated on the main body of the water reservoir formed by assembling several water storage modules to prevent the water in the water storage pores from leaking easily and ensure the construction speed of the water reservoir.
[0005] With regard to the above-mentioned related technologies, for a water reservoir installed in an urban building complex, the soil in which the water reservoir is located bears a large vertical load, so the water reservoir is subjected to a large lateral active earth pressure for a long time, and the anti-seepage membrane is prone to aging after long-term use, so that the anti-seepage membrane with greater brittleness after aging is prone to cracking and damage under the long-term action of lateral earth pressure. Summary of the invention
[0006] In order to prevent the water reservoir from leaking under the long-term effect of lateral active earth pressure, the present application provides a sponge city road rainwater recycling system.
[0007] The present application provides a sponge city road rainwater recycling system that adopts the following technical solutions:
[0008] A sponge city road rainwater recycling system comprises a plurality of water storage modules, wherein the plurality of water storage modules are provided with water storage pores, and the plurality of water storage pores are interconnected to form a water storage chamber;
[0009] Several of the water storage modules are provided with grouting pores, and the several grouting pores are interconnected to form a grouting chamber;
[0010] The water storage chamber is located in the area enclosed by the grouting chamber, and the grouting chamber and the water storage chamber are isolated from each other;
[0011] A grouting pipe is arranged in the grouting chamber, and a grouting hole is opened in the grouting pipe, and the grouting hole is connected to the grouting chamber.
[0012] By adopting the above technical scheme, after the water storage modules are assembled to form the water storage tank body, cement grouting material is poured into the grouting chamber through the grouting pipe, so that the cement grouting material forms a high-strength outer shell in the grouting chamber, thereby ensuring the strength of the outer wall of the water storage tank while sealing the water storage chamber, so that the water storage tank is not easy to leak under the long-term action of lateral active earth pressure, and the occurrence of cracking and damage of the anti-seepage membrane due to aging under the action of large earth pressure is reduced.
[0013] Optionally, a plurality of the grouting pipes are provided, and the plurality of the grouting pipes are distributed along the length direction of the water reservoir, and the plurality of the grouting pipes are all slidably fitted in the grouting chamber along the length direction of the water reservoir.
[0014] By adopting the above technical solution, when cement grouting material is poured into the grouting chamber through the grouting pipe, the grouting pipe is made to slide back and forth along the length direction of the water reservoir, so that the cement grouting material is evenly sprayed to various places in the grouting chamber, so that the grouting chamber is evenly and densely filled with cement grouting material.
[0015] Optionally, the plurality of grouting pipes are slidably fitted in the grouting chamber via a sliding member;
[0016] The sliding member comprises a sliding sleeve, a fastening through hole is formed through the sliding sleeve, the grouting pipe is passed through the fastening through hole, and the outer peripheral surface of the grouting pipe is tightly matched with the inner wall of the fastening through hole.
[0017] By adopting the above technical scheme, the grouting pipe is passed through the fastening through hole, that is, the sliding sleeve is sleeved on the grouting pipe, which ensures the bending rigidity of the grouting pipe. When the grouting pipe slides back and forth along the length direction of the water reservoir, the grouting pipe is not prone to having a large curvature bending section due to insufficient bending rigidity, which makes it difficult for the cement grouting material to be evenly sprayed to various places in the grouting chamber, thereby ensuring that the grouting chamber is evenly and densely filled with cement grouting material.
[0018] Optionally, the sliding member further includes roller connectors and sliding rollers. A plurality of the roller connectors are provided, and the plurality of roller connectors are circumferentially distributed around the axis of the sliding sleeve. The plurality of roller connectors are all rotatably fitted to the sliding sleeve. A pressing elastic member is provided between two adjacent roller connectors, and both ends of the pressing elastic member are respectively installed on the two adjacent roller connectors;
[0019] A plurality of the sliding rollers are provided, and the plurality of sliding rollers are respectively rotatably fitted to the respective roller connectors, and the plurality of sliding rollers are all in pressing fit with the inner wall of the grouting chamber.
[0020] By adopting the above technical solution, the sliding rollers are always in pressing fit with the inner wall of the grouting chamber under the action of the pressing elastic member, reducing the friction between the grouting pipe and the inner wall of the grouting chamber, so that the grouting pipe is not easily bent with a large curvature due to excessive friction, and further making it difficult for the cement grouting material to be evenly sprayed to各处 of the grouting chamber, ensuring that the grouting chamber is evenly and densely filled with the cement grouting material.
[0021] Optionally, the cross-section of the grouting chamber is arranged in a "凵" shape, the grouting pipe is arranged in a "凵" shape corresponding to the grouting chamber, and the grouting holes are opened at the bottom of the grouting pipe and are arranged close to the bottom of the grouting chamber.
[0022] By adopting the above technical solution, when the cement grouting material is poured into the grouting chamber through the grouting pipe, the cement grouting material gradually fills the grouting chamber from the bottom up, and then gradually discharges the air in the grouting chamber, reducing the occurrence of the situation that the cement grouting material filled in the grouting chamber contains too many bubbles, ensuring that the grouting chamber is evenly and densely filled with the cement grouting material.
[0023] Optionally, one-way valve members are provided at both ends of the grouting pipe. The one-way valve member includes a valve pipe and an inclined valve plate. The valve pipe is installed on the grouting pipe. The valve pipe is provided with a valve chamber. A plurality of the inclined valve plates are provided, and the plurality of inclined valve plates are all located in the valve chamber and are all rotatably fitted to the valve pipe. The plurality of inclined valve plates are all inclined towards the axis of the grouting pipe along the grouting direction of the grouting pipe.
[0024] By adopting the above technical solution, when the cement grouting material is poured into the grouting chamber through one end of the grouting pipe, the cement grouting material flushes open a plurality of inclined valve plates at one end, and makes a plurality of inclined valve plates at the other end rotate towards each other and press against each other, so that one end of the grouting pipe is opened and the other end is closed, and then the cement grouting material enters the grouting chamber through the grouting holes. The structure is simple and reliable, and is suitable for large-scale construction of reservoirs.
[0025] Optionally, a plurality of grouting pipes are provided, and the plurality of grouting pipes are distributed along the length direction of the reservoir, and the plurality of grouting pipes are all slidably engaged with the grouting chamber along the length direction of the reservoir;
[0026] A plurality of grouting partitions are arranged in the grouting chamber, and the plurality of grouting partitions are all arranged in the vertical direction, and the plurality of grouting partitions all extend along the grouting direction of the grouting holes, and one ends of the plurality of grouting partitions close to the grouting holes are all arc-shaped.
[0027] By adopting the above technical solution, the plurality of grouting partitions divide the grouting chamber into a plurality of regions with smaller volume sizes, reducing the influence of the shrinkage of the cement grouting material during forming, and thus making the cement grouting material not easily crack after forming; the grouting partitions guide the cement grouting material ejected from the grouting holes to both sides, and thus make the cement grouting material more evenly sprayed to各处 of the grouting chamber, so that the grouting chamber is evenly and densely filled with the cement grouting material.
[0028] The present application also provides a construction method for a sponge city road rainwater reuse system, adopting the following technical solution:
[0029] A construction method for a sponge city road rainwater reuse system includes the following steps:
[0030] S1. Pour a concrete cushion layer;
[0031] S2. Assemble a plurality of water storage modules;
[0032] A plurality of the water storage modules are all provided with water storage pores, and the plurality of water storage pores communicate with each other to form a water storage chamber; a plurality of the water storage modules are all provided with grouting pores, and the plurality of grouting pores communicate with each other to form a grouting chamber; the water storage chamber is located in the area surrounded by the grouting chamber, and the grouting chamber is isolated from the water storage chamber;
[0033] S3.灌入 cement grouting material into the grouting chamber through a grouting pipe;
[0034] S4. Cover the tops of the plurality of water storage modules with a waterproof membrane.
[0035] Optionally, in the step S3, the cross-section of the grouting chamber is arranged in a "凵" shape, a plurality of grouting pipes are provided, and the plurality of grouting pipes are all arranged in a "凵" shape corresponding to the grouting chamber, and the plurality of grouting pipes are distributed along the length direction of the reservoir; the bottom of the grouting pipe is provided with grouting holes, and the grouting holes communicate with the grouting chamber and are arranged close to the bottom of the grouting chamber;
[0036] Specifically, cement grouting material is poured into the grouting chamber from the middle of the water reservoir through a plurality of the grouting pipes at intervals in sequence along the length direction of the water reservoir, and after the cement grouting material is poured into the grouting chamber through two grouting pipes respectively, the cement grouting material is first poured into the grouting chamber through the remaining grouting pipes between the two grouting pipes.
[0037] By adopting the above technical scheme, when cement grouting material is poured into the grouting chamber through the grouting pipe, the grouting is divided into several areas for grouting, so that the grouting chamber is not prone to leakage; in addition, when cement grouting material is poured into the grouting chamber through the grouting pipe, the cement grouting material is evenly sprayed into the grouting chamber, and the air in the grouting chamber is gradually discharged from the middle of the water tank to both ends of the water tank along the length direction of the water tank, so that the cement grouting material filled in the grouting chamber is not prone to contain too many bubbles, ensuring that the grouting chamber is evenly and densely filled with cement grouting material.
[0038] Optionally, in step S3, one end of the plurality of grouting pipes is located at the first side, the other ends of the plurality of grouting pipes are located at the second side, and one end of the grouting pipe located at the first side and one end located at the second side are both provided with a one-way valve member;
[0039] When cement grouting material is poured into the grouting chamber through the plurality of grouting pipes, grouting is first performed through one end of the grouting pipe located on the first side, and then grouting is performed through one end of the grouting pipe located on the second side.
[0040] By adopting the above technical solution, the grouting chamber is grouted through both ends of the grouting pipe, so that the air in the grouting pipe is fully discharged, making it difficult for bubbles to appear in the grouting pipe and the grouting chamber, which is beneficial to ensure the strength of the outer wall of the water reservoir.
[0041] In summary, the present application includes at least one of the following beneficial technical effects:
[0042] 1. After the water storage modules are assembled to form the main body of the water storage tank, cement grouting material is poured into the grouting chamber through the grouting pipe, so that the cement grouting material forms a high-strength shell in the grouting chamber, thereby sealing the water storage chamber while ensuring the strength of the outer wall of the water storage tank, so that the water storage tank is not easy to leak under the long-term action of the lateral active earth pressure, and the occurrence of cracking and damage of the anti-seepage membrane due to aging under the action of large earth pressure is reduced.
[0043] 2. When pouring cement grouting material into the grouting chamber through the grouting pipe, the grouting pipe is made to slide back and forth along the length direction of the water reservoir, so that the cement grouting material is evenly sprayed to various places in the grouting chamber, so that the grouting chamber is evenly and densely filled with cement grouting material.
[0044] 3. Grouting is performed on the grouting chamber through both ends of the grouting pipe, so that the air in the grouting pipe is fully discharged, making it difficult for bubbles to appear in the grouting pipe and the grouting chamber, which is beneficial to ensure the strength of the outer wall of the water reservoir. BRIEF DESCRIPTION OF THE DRAWINGS
[0045] Figure 1 It is a flow chart of the overall structure of Example 1 of the present application.
[0046] Figure 2 It is an overall schematic diagram of the overall structure of Example 1 of the present application.
[0047] Figure 3 It is an overall schematic diagram of the water reservoir of Example 1 of the present application.
[0048] Figure 4 It is the first cross-sectional schematic diagram of the water reservoir of Example 1 of the present application.
[0049] Figure 5 It is a second cross-sectional schematic diagram of the water reservoir in Example 1 of the present application.
[0050] Figure 6 It is an overall schematic diagram of the sliding member of Example 1 of the present application.
[0051] Figure 7 It is a cross-sectional schematic diagram of the one-way valve component of Example 1 of the present application.
[0052] Figure 8 It is an overall schematic diagram of the water reservoir of Example 2 of the present application.
[0053] Explanation of the reference numerals: 1. water reservoir; 101. water storage chamber; 102. grouting chamber; 11. water storage module; 111. first water storage module; 112. second water storage module; 113. grouting baffle; 114. sliding limit plate; 2. grouting pipe; 201. grouting hole; 21. assembly pipe body; 3. sliding member; 31. sliding sleeve; 32. roller connector; 321. tightening elastic member; 33. sliding roller; 4. one-way valve member; 41. valve pipe; 411. valve member chamber; 42. inclined raft; 5. first grouting pipe; 6. second grouting pipe; 7. third grouting pipe; 8. fourth grouting pipe; 9. fifth grouting pipe. DETAILED DESCRIPTION
[0054] The following is combined with Figure 1-8 This application is described in further detail.
[0055] Example 1.
[0056] Example 1 of the present application discloses a sponge city road rainwater recycling system. Figure 1The sponge city road rainwater reuse system includes the municipal pipe network, initial abandonment well, water storage tank 1, filtration tank, disinfection tank and water facilities.
[0057] Reference Figure 1 , rainwater is transported to the initial waste well through the municipal pipe network. The rainwater that first enters the initial waste well and contains a large number of large-particle debris is filtered through the sedimentation of the initial waste well and is transported to the reservoir 1, which stores the rainwater. When water is needed, the rainwater is further filtered by the filtering device of the filter tank (not shown in the figure) to remove small-particle debris. After filtering through the filter, the rainwater is disinfected by the ultraviolet disinfection device of the disinfection tank (not shown in the figure). After disinfection, the rainwater is transported to the water use facilities. The flow of rainwater between the reservoir 1, the filter tank, the disinfection tank and the water use facilities is controlled by an electrical control system to reduce labor costs.
[0058] Reference Figure 2 and Figure 3 , the water storage tank 1 includes a plurality of water storage modules 11. In the embodiment 1 of the present application, the plurality of water storage modules 11 are divided into a plurality of first water storage modules 111 and a plurality of second water storage modules 112, and the plurality of first water storage modules 111 are all located in the area enclosed by the second water storage modules 112. The plurality of first water storage modules 111 and the second water storage modules 112 are plugged and assembled with each other to form the main body of the water storage tank 1, and the main body of the water storage tank 1 is arranged in a rectangular parallelepiped shape. A sealing structure (not shown in the figure) can be arranged between two adjacent first water storage modules 111, two adjacent second water storage modules 112, or the first water storage module 111 and the second water storage module 112. The sealing structure can be arranged based on a sealing method known to those skilled in the art, such as a tongue-and-groove snap-on connection, a sealing pad, a sealant, or a water-expandable water stop strip, so as to further ensure the sealing between the two adjacent water storage modules 11, which will not be described in detail here.
[0059] Reference Figure 3 and Figure 4 , a plurality of first water storage modules 111 and each second water storage module 112 are provided with water storage pores, and a plurality of water storage pores are interconnected to form a water storage chamber 101 for storing rainwater;
[0060] A number of first water storage modules 111 are each provided with grouting voids, and a number of the grouting voids communicate with each other to form a grouting chamber 102. The cross-section of the grouting chamber 102 is arranged in a "U" shape. The water storage chamber 101 is located within the area surrounded by the grouting chamber 102, and the grouting chamber 102 is isolated from the water storage chamber 101, so that the cement grouting material in the grouting chamber 102 is not easily infiltrated into the water storage chamber 101 and the water in the water storage chamber 101 is not easily infiltrated into the grouting chamber 102. As a result, the water storage tank 1 is not easily leaked under the long-term action of lateral active earth pressure, reducing the occurrence of cracking and damage of the anti-seepage membrane under the action of a large earth pressure.
[0061] Referring to Figure 3 and Figure 4 , a number of grouting pipes 2 are provided in the grouting chamber 102, and in Embodiment 1 of the present application, the number of the grouting pipes 2 is set to five. The five grouting pipes 2 are each arranged in a "U" shape corresponding to the grouting chamber 102, and the five grouting pipes 2 are all distributed along the length direction of the water storage tank 1. A gap is provided between the outer peripheral surface of the grouting pipe 2 and the inner wall of the grouting chamber 102. A number of grouting holes 201 are provided at the bottom of the grouting pipe 2, and the number of grouting holes 201 is distributed along the extension direction of the grouting pipe 2. The grouting holes 201 communicate with the grouting chamber 102, and the grouting holes 201 are arranged along the length direction of the water storage tank 1, that is, the grouting direction of the grouting holes 201 is arranged along the length direction of the water storage tank 1.
[0062] Referring to Figure 5 , a number of grouting partitions 113 are provided in the grouting chamber 102, and the number of grouting partitions 113 is respectively arranged corresponding to each grouting hole 201. The grouting partitions 113 are arranged in the vertical direction, that is, the height direction of the water storage tank 1, and the grouting partitions 113 extend along the grouting direction of the grouting holes 201, and the top and bottom of the grouting partitions 113 are integrally connected to the inner wall of the grouting chamber 102. One end of the grouting partition 113 close to and facing the grouting hole 201 is arranged in a circular arc shape, so that the cement grouting material ejected from the grouting hole 201 is divided into two tributaries through the grouting partition 113, thereby evenly filling and compacting the grouting chamber 102.
[0063] Referring to Figure 4 , in Embodiment 1 of the present application, the grouting pipe 2 includes a number of assembled pipe bodies 21. The materials of the number of assembled pipe bodies 21 are all selected as bending-resistant materials, such as metal, ceramic or carbon fiber, etc., and in Embodiment 1 of the present application, steel is selected. The heads and tails of two adjacent assembled pipe bodies 21 are threadedly matched with each other, so as to facilitate the assembly of the assembled pipe bodies 21.
[0064] Referring to Figure 5 and Figure 6 , four assembled pipe bodies 21 are provided at the bottom of the grouting pipe 2, and each of the four assembled pipe bodies 21 is provided with a sliding member 3;
[0065] The sliding member 3 includes a sliding sleeve 31, a roller connector 32 and a sliding roller 33. The sliding sleeve 31 is provided with a fastening through hole along its own axial direction. The assembly tube 21 is inserted into the fastening through hole, that is, the sliding sleeve 31 is sleeved on the assembly tube 21, and the outer peripheral surface of the assembly tube 21 is tightly matched with the inner wall of the fastening through hole, so as to ensure the bending rigidity of the assembly tube 21. Four roller connectors 32 are provided, and the four roller connectors 32 are circumferentially distributed around the axis of the assembly tube 21. The roller connector 32 is rotationally matched with the sliding sleeve 31, and the rotation axis between the roller connector 32 and the sliding sleeve 31 is set along the length direction of the sliding sleeve 31.
[0066] A pressing elastic member 321 is provided between two adjacent roller connectors 32, and in the first embodiment of the present application, the number of the pressing elastic members 321 is set to two, and the type of the two pressing elastic members 321 is selected to be a spring. The two pressing elastic members 321 are respectively provided on both sides of the sliding sleeve 31 in the horizontal direction, and the two ends of the pressing elastic member 321 are respectively fixedly installed on the two adjacent roller connectors 32. The pressing elastic member 321 is provided with four sliding rollers 33, and the four sliding rollers 33 are respectively provided in a one-to-one correspondence with each roller connector 32. The sliding roller 33 is rotationally matched with the roller connector 32, and the rotation axis between the sliding roller 33 and the roller connector 32 is also provided along the length direction of the sliding sleeve 31. The sliding roller 33 is tightly fitted against the inner wall of the grouting chamber 102 , and the sliding roller 33 rolls and slides in the grouting chamber 102 , so that the assembled pipe body 21 slides in the grouting chamber 102 along the length direction of the water reservoir 1 with lower friction.
[0067] Reference Figure 5 The grouting chamber 102 is provided with a plurality of sliding limit plates 114, and each of the plurality of sliding limit plates 114 is grouped into two, and each group of sliding limit plates 114 is respectively provided corresponding to each assembly pipe body 21 near the end of the grouting pipe 2. The two sliding limit plates 114 of each group are distributed along the length direction of the water reservoir 1, and the two sliding limit plates 114 of each group are respectively located on both sides of the assembly pipe body 21, and both sides of the sliding limit plates 114 are integrally connected to the inner wall of the grouting chamber 102, so that the assembly pipe body 21 between the two sliding limit plates 114 is not prone to excessive slippage.
[0068] Reference Figure 4 and Figure 7The assembled pipe body 21 near the two ends of the grouting pipe 2 is provided with a one-way valve member 4, and the one-way valve member 4 includes a valve tube 41 and an inclined raft plate 42. The valve tube 41 is provided with a valve member chamber 411, and the top of the assembled pipe body 21 is plugged into the valve member chamber 411, and the top of the assembled pipe body 21 is tightly fitted against the inner wall of the valve member chamber 411, that is, the valve tube 41 is sleeved on the top of the assembled pipe body 21. There are a plurality of inclined raft plates 42, and in Example 1 of the present application, the number of inclined raft plates 42 is set to two. The two inclined raft plates 42 are both located in the valve member chamber 411, and the two inclined raft plates 42 are arranged opposite to each other;
[0069] Both inclined raft plates 42 are rotatably matched with the inner wall of the valve chamber 411, and both inclined raft plates 42 are inclined toward the axis of the assembled pipe body 21 along the axial direction of the assembled pipe body 21, that is, the grouting direction, so that when one end of the assembled pipe body 21 is used as the input end, the inclined raft plates 42 at the input end are flushed open by the cement grouting material to open the input end of the assembled pipe body 21, and the inclined raft plates 42 at the output end of the assembled pipe body 21 are rotated in the direction of approaching each other and finally pressed against each other, thereby closing the output end, so that the cement grouting material enters the grouting chamber 102 through a plurality of grouting holes 201. It has the advantages of simple and reliable structure and is suitable for water storage tanks 1 with larger construction scale.
[0070] The implementation principle of a sponge city road rainwater recycling system in Example 1 of the present application is as follows: after a plurality of first water storage modules 111 and each second water storage module 112 are plugged and assembled to form the main body of the water storage tank 1, cement grouting material is injected into the grouting chamber 102 through the assembly pipe body 21, so that the grouting chamber 102 is filled with cement grouting material to form an outer shell with high strength, thereby ensuring the strength of the outer wall of the water storage tank 1 while sealing the water storage chamber 101, so that the water storage tank 1 is not easy to leak under the long-term action of lateral active earth pressure, and the occurrence of cracking and damage of the anti-seepage membrane due to aging under the action of large earth pressure is reduced.
[0071] Example 2.
[0072] Embodiment 2 of the present application provides a construction method for a sponge city road rainwater recycling system, specifically comprising the following steps:
[0073] S1, pouring concrete cushion;
[0074] S2, assembling several water storage modules 11;
[0075] S3, pouring cement grouting material into the grouting chamber 102 through the grouting pipe 2;
[0076] In Example 2 of the present application, the type of cement grouting material is selected as ultrafine cement, and the particle size of the cement grouting material is less than 20 μm.
[0077] Reference Figure 8 The five grouting pipes 2 are defined as the first grouting pipe 5, the second grouting pipe 6, the third grouting pipe 7, the fourth grouting pipe 8 and the fifth grouting pipe 9 in sequence along the length direction of the water reservoir 1 from one end of the water reservoir 1 to the other end of the water reservoir 1, and one end of the first grouting pipe 5, the second grouting pipe 6, the third grouting pipe 7, the fourth grouting pipe 8 and the fifth grouting pipe 9 are all located on the first side, and the other ends of the first grouting pipe 5, the second grouting pipe 6, the third grouting pipe 7, the fourth grouting pipe 8 and the fifth grouting pipe 9 are all located on the second side.
[0078] S3 includes the following specific steps:
[0079] S31, first pouring cement grouting material into the grouting chamber 102 through one end of the third grouting pipe 7 located on the first side, and then pouring cement grouting material into the grouting chamber 102 through one end of the third grouting pipe 7 located on the second side;
[0080] S32, first pouring cement grouting material into the grouting chamber 102 through one end of the first grouting pipe 5 located on the first side, and then pouring cement grouting material into the grouting chamber 102 through one end of the first grouting pipe 5 located on the second side;
[0081] S33, first pouring cement grouting material into the grouting chamber 102 through one end of the fifth grouting pipe 9 located on the first side, and then pouring cement grouting material into the grouting chamber 102 through one end of the fifth grouting pipe 9 located on the second side;
[0082] S34, first pouring cement grouting material into the grouting chamber 102 through one end of the second grouting pipe 6 located on the first side, and then pouring cement grouting material into the grouting chamber 102 through one end of the second grouting pipe 6 located on the second side;
[0083] S35, first pour cement grouting material into the grouting chamber 102 through the end of the fourth grouting pipe 8 located on the first side, and then pour cement grouting material into the grouting chamber 102 through the end of the fourth grouting pipe 8 located on the second side.
[0084] S4. Cover the tops of the water storage modules 11 with a waterproof membrane.
[0085] The implementation principle of the construction method of a sponge city road rainwater recycling system in Example 2 of the present application is: cement grouting material is grouted into the grouting chamber 102 at intervals in the order of the third grouting pipe 7, the first grouting pipe 5, the fifth grouting pipe 9, the second grouting pipe 6 and the fourth grouting pipe 8, so that the grouting chamber 102 is divided into two areas located on both sides of the third grouting pipe 7, so that the area with a smaller area is grouted during a single grouting, thereby reducing the occurrence of leakage; each time the grouting pipe 2 is replaced, grouting is performed from the first side, which not only effectively discharges the air in the first grouting pipe 5, the second grouting pipe 6, the third grouting pipe 7, the fourth grouting pipe 8 and the fifth grouting pipe 9, but also effectively discharges the air in different areas of the grouting chamber 102, so that the cement grouting material filled in the grouting chamber 102 is not easy to contain too many bubbles, ensuring that the grouting chamber 102 is evenly and densely filled with cement grouting material.
[0086] Example 3.
[0087] The main difference between Example 2 and Example 3 of the present application is that the specific order of S3 is different.
[0088] S3 includes the following specific steps:
[0089] S31, first pouring cement grouting material into the grouting chamber 102 through one end of the third grouting pipe 7 located on the first side, and then pouring cement grouting material into the grouting chamber 102 through one end of the third grouting pipe 7 located on the second side;
[0090] S32, first pouring cement grouting material into the grouting chamber 102 through one end of the fifth grouting pipe 9 located on the first side, and then pouring cement grouting material into the grouting chamber 102 through one end of the fifth grouting pipe 9 located on the second side;
[0091] S33, first pouring cement grouting material into the grouting chamber 102 through one end of the first grouting pipe 5 located on the first side, and then pouring cement grouting material into the grouting chamber 102 through one end of the first grouting pipe 5 located on the second side;
[0092] S34, first pouring cement grouting material into the grouting chamber 102 through one end of the fourth grouting pipe 8 located on the first side, and then pouring cement grouting material into the grouting chamber 102 through one end of the fourth grouting pipe 8 located on the second side;
[0093] S35, first pour cement grouting material into the grouting chamber 102 through the end of the second grouting pipe 6 located on the first side, and then pour cement grouting material into the grouting chamber 102 through the end of the second grouting pipe 6 located on the second side.
[0094] The implementation principle of the construction method of a sponge city road rainwater recycling system in Example 3 of the present application is: cement grouting material is grouted into the grouting chamber 102 at intervals in the order of the third grouting pipe 7, the fifth grouting pipe 9, the first grouting pipe 5, the fourth grouting pipe 8 and the second grouting pipe 6, so that the grouting chamber 102 is divided into two areas located on both sides of the third grouting pipe 7, so that the area with a smaller area is grouted during a single grouting, thereby reducing the occurrence of leakage; each time the grouting pipe 2 is replaced, grouting is performed from the first side, which not only effectively discharges the air in the first grouting pipe 5, the second grouting pipe 6, the third grouting pipe 7, the fourth grouting pipe 8 and the fifth grouting pipe 9, but also effectively discharges the air in different areas of the grouting chamber 102, so that the cement grouting material filled in the grouting chamber 102 is not easy to contain too many bubbles, ensuring that the grouting chamber 102 is evenly and densely filled with cement grouting material.
[0095] The above are all preferred embodiments of the present application, and the protection scope of the present application is not limited thereto. Therefore, any equivalent changes made according to the structure, shape, and principle of the present application should be included in the protection scope of the present application.
Claims
1. A sponge city road rainwater recycling system, characterized by: It includes several water storage modules (11), and each of the several water storage modules (11) is provided with water storage pores, and the several water storage pores communicate with each other to form a water storage chamber (101); Each of the several water storage modules (11) is provided with grouting pores, and the several grouting pores communicate with each other to form a grouting chamber (102); The water storage chamber (101) is located within the area surrounded by the grouting chamber (102), and the grouting chamber (102) is isolated from the water storage chamber (101); A grouting pipe (2) is arranged in the grouting chamber (102), the grouting pipe (2) is provided with grouting holes (201), and the grouting holes (201) communicate with the grouting chamber (102).
2. A sponge city road rainwater recycling system according to claim 1, characterized in that: Several grouting pipes (2) are provided, and the several grouting pipes (2) are distributed along the length direction of the water storage tank (1), and the several grouting pipes (2) are all slidably fitted along the length direction of the water storage tank (1) in the grouting chamber (102).
3. A sponge city road rainwater recycling system according to claim 2, characterized in that: Each of the several grouting pipes (2) is slidably fitted in the grouting chamber (102) through a sliding member (3); The sliding member (3) includes a sliding sleeve (31), the sliding sleeve (31) is provided with a fastening through hole, the grouting pipe (2) is inserted through the fastening through hole, and the outer peripheral surface of the grouting pipe (2) is in tight fit with the inner wall of the fastening through hole.
4. A sponge city road rainwater recycling system according to claim 3, characterized in that: The sliding member (3) further includes a roller connecting member (32) and sliding rollers (33), several roller connecting members (32) are provided, the several roller connecting members (32) are circumferentially distributed around the axis of the sliding sleeve (31), the several roller connecting members (32) are all rotatably fitted on the sliding sleeve (31), a tightening elastic member (321) is arranged between two adjacent roller connecting members (32), and both ends of the tightening elastic member (321) are respectively installed on two adjacent roller connecting members (32); Several sliding rollers (33) are provided, the several sliding rollers (33) are respectively rotatably fitted on each roller connecting member (32), and the several sliding rollers (33) are all in tight fit with the inner wall of the grouting chamber (102).
5. The sponge city road rainwater recycling system according to claim 1 is characterized by: The cross-section of the grouting chamber (102) is arranged in a "U" shape, the grouting pipe (2) is arranged in a "U" shape corresponding to the grouting chamber (102), and the grouting holes (201) are opened at the bottom of the grouting pipe (2) and are arranged close to the bottom of the grouting chamber (102).
6. A sponge city road rainwater recycling system according to claim 5, characterized in that: One-way valve members (4) are arranged at both ends of the grouting pipe (2), the one-way valve members (4) include valve pipes (41) and inclined valve plates (42), the valve pipes (41) are installed on the grouting pipe (2), the valve pipes (41) are provided with valve member chambers (411), several inclined valve plates (42) are provided, the several inclined valve plates (42) are all located in the valve member chambers (411) and are all rotatably fitted on the valve pipes (41), and the several inclined valve plates (42) are all inclined towards the axis of the grouting pipe (2) along the grouting direction of the grouting pipe (2).
7. The sponge city road rainwater recycling system according to claim 5 is characterized by: A plurality of grouting pipes (2) are provided, and the plurality of grouting pipes (2) are distributed along the length direction of the reservoir (1), and the plurality of grouting pipes (2) are all slidably fitted in the grouting chamber (102) along the length direction of the reservoir (1); A plurality of grouting partitions (113) are arranged in the grouting chamber (102), the plurality of grouting partitions (113) are all arranged vertically, and the plurality of grouting partitions (113) all extend along the grouting direction of the grouting holes (201), and one ends of the plurality of grouting partitions (113) close to the grouting holes (201) are all arc-shaped.
8. A construction method for a sponge city road rainwater recycling system, characterized in that: The following steps: S1. Pour a concrete cushion; S2. Assemble a plurality of water storage modules (11); A plurality of the water storage modules (11) are all provided with water storage pores, and the plurality of water storage pores communicate with each other to form a water storage chamber (101); a plurality of the water storage modules (11) are all provided with grouting pores, and the plurality of grouting pores communicate with each other to form a grouting chamber (102); the water storage chamber (101) is located in the area surrounded by the grouting chamber (102), and the grouting chamber (102) is isolated from the water storage chamber (101); S3. Pour cement grouting material into the grouting chamber (102) through the grouting pipes (2); S4. Cover the tops of the plurality of water storage modules (11) with a waterproof membrane.
9. The construction method of a sponge city road rainwater recycling system according to claim 8 is characterized by: In the step S3, the cross section of the grouting chamber (102) is arranged in a "U" shape, a plurality of grouting pipes (2) are provided, and the plurality of grouting pipes (2) are all arranged in a "U" shape corresponding to the grouting chamber (102), and the plurality of grouting pipes (2) are distributed along the length direction of the reservoir (1); the bottom of the grouting pipe (2) is provided with grouting holes (201), and the grouting holes (201) communicate with the grouting chamber (102) and are arranged close to the bottom of the grouting chamber (102); Specifically, starting from the middle of the reservoir (1) and at intervals along the length direction of the reservoir (1), pour cement grouting material into the grouting chamber (102) through a plurality of the grouting pipes (2), and after pouring cement grouting material into the grouting chamber (102) through two grouting pipes (2) respectively, first pour cement grouting material into the grouting chamber (102) through the remaining grouting pipes (2) between the two grouting pipes (2).
10. The construction method of a sponge city road rainwater recycling system according to claim 9 is characterized in that: In the step S3, one ends of the plurality of grouting pipes (2) are all located on the first side, the other ends of the plurality of grouting pipes (2) are all located on the second side, and one-way valve members (4) are arranged at both the ends of the grouting pipes (2) located on the first side and the ends located on the second side; When pouring cement grouting material into the grouting chamber (102) through the plurality of grouting pipes (2), first grout through one end of the grouting pipe (2) located on the first side, and then grout through one end of the grouting pipe (2) located on the second side.
Citation Information
Patent Citations
Quantitative grouting construction process of steel bar sleeve
CN109469263A
Pipe jacking communicating type storage pond applied to narrow space and construction method
CN110700391A
Sponge city drainage module
CN206902904U
Jacking pipe storage pond for narrow working range
CN211006996U
Prefabricated side plate for fabricated concrete pool
CN216713983U