A floating offshore wind turbine embedded anchoring device and its installation method
By combining steel pipe piles and anchor plates, and utilizing the combination of limiting devices and anchor chain assemblies, the high cost and low efficiency of floating offshore wind power anchoring devices have been solved, achieving efficient and low-cost anchoring construction.
Patent Information
- Application Number
- CN202311826866.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2023-12-27
- Publication Date
- 2026-11-17
- Estimated Expiration
- 2043-12-27
AI Technical Summary
Existing floating offshore wind turbine anchoring devices suffer from high costs, long construction times, and low construction efficiency.
The system employs a combination structure of steel pipe piles and anchor plates. A limiting device connects the steel pipe piles and anchor plates when they sink to the seabed. During pile driving, the force of the steel pipe piles is used to sink the anchor plates together. After pile driving is completed, they can be easily separated. The anchor plates are driven into the seabed using existing pile driving technology, and the state of the anchor plates is adjusted in conjunction with the anchor chain assembly.
It achieves precise positioning, deep penetration, structural stability, convenient construction, and low cost, thereby improving construction efficiency and reducing overall cost.
Smart Images

Figure CN117944815B_ABST
Abstract
Description
Technical Field
[0001] This invention relates to the field of offshore wind power technology, and more specifically, to a floating offshore wind turbine embedded anchoring device and its installation method. Background Technology
[0002] As offshore wind power gradually expands from shallow to deep waters, the application of floating wind power systems has become an inevitable trend. Floating wind turbines are connected to anchoring devices via anchor chains. To ensure the stability of the turbine, the anchoring device is crucial. Currently, commonly used anchoring devices include high-holding-force anchors, suction anchors, suction-penetrating plate anchors, pile anchors, and gravity anchors. High-holding-power anchors require tugboats to tow them a considerable distance to the predetermined depth during installation. This towing can easily break the submarine cable, and the installation method itself makes precise positioning difficult. Suction anchors can pinpoint the anchor's location, but this anchoring method results in shallower embedment depths and higher costs. Suction-driven plate anchors are a newer type, using a suction barrel to penetrate the anchor into the soil. This method allows for precise positioning, and the suction barrel can be retrieved, resulting in lower overall costs. However, the penetration depth is limited by the height of the suction barrel, which is suitable for shallow soils and is typically not very high. When the anchoring depth is insufficient, more anchoring devices are needed to achieve the required anchoring capacity, increasing costs. Pile anchors are suitable for seabeds requiring rock embedment. Gravity anchors rely on weight for stability but are quite expensive.
[0003] Chinese Patent Publication No. 202211330028.2, published on January 13, 2023, is entitled "Suction-type Caisson Foundation". This application discloses a suction-type caisson foundation. The patent document draws on the technology of extrusion-expanded cast-in-place piles and adds a drilling and expansion device to the suction anchor. This device increases the bearing capacity of the suction anchor, but it is more complex and requires a large amount of concrete to be inserted, resulting in higher overall cost and longer construction time.
[0004] Chinese Patent Publication No. 202310237522.2, published on May 30, 2023, is entitled "Floating Wind Turbine Anchoring Foundation Device and Method for Mooring Wind Turbines". The above method mainly achieves stability by anchoring the body and the seawater inside. It is essentially a gravity foundation. The seawater in the sea cannot provide additional downward force. To achieve the anchoring requirements, the anchoring device mainly relies on the weight of the anchoring body. This method is a costly one. Summary of the Invention
[0005] This invention overcomes the shortcomings of existing anchoring devices, such as high cost, long construction time, and low construction efficiency, and provides a floating offshore wind power embedded anchoring device, which features precise positioning, deep penetration, stable structure, low cost, convenient construction, and high efficiency.
[0006] To solve the above-mentioned technical problems, the present invention adopts the following technical solution: a floating offshore wind power embedded anchoring device, comprising: a steel pipe pile and an anchoring plate, a limiting device is provided between the steel pipe pile and the anchoring plate, the anchoring plate includes an arc-shaped anchoring plate that is in contact with the surface of the steel pipe pile, and straight anchoring plates are provided on both sides of the arc-shaped anchoring plate. The limiting device includes a first limiting device and a second limiting device; the first limiting device includes a first latch provided on the outer wall of the steel pipe pile, the opening direction of the first latch is downward; the second limiting device includes a second latch provided at the bottom of the anchor plate, the opening direction of the second latch is upward; the bottom edge of the steel pipe pile is locked in the second latch, and the upper edge of the anchor plate is locked in the first latch. The limiting device ensures that the steel pipe pile can only be separated from the anchor plate when the steel pipe column is pulled upwards; An anchor chain assembly is connected to the anchor plate, and a chain is connected to the anchor chain assembly.
[0007] In this invention, the cooperation of the first and second locking mechanisms allows the steel pipe pile and anchor plate to be connected together when sunk into the seabed. During pile driving, the steel pipe pile can be driven downwards along with the anchor plate, and when it needs to be pulled out, the steel pipe pile can be easily separated from the anchor plate. This allows the anchor plate to be driven into the seabed using existing pile driving techniques. Therefore, by setting a limiting device, this invention facilitates the separation of the steel pipe pile from the anchor plate when it is pulled out, greatly improving construction efficiency. Furthermore, the structure of the steel pipe pile and anchor plate in this invention is simple, with low support costs, thus reducing the overall cost. It features precise positioning, deep penetration, structural stability, low cost, convenient construction, and high efficiency.
[0008] Preferably, a transition anchor plate is provided between the straight anchor plate and the curved anchor plate.
[0009] The above setup allows for the convenient installation of two anchor plates simultaneously.
[0010] As a preferred embodiment, the steel pipe column has several L-shaped plates evenly distributed around its circumference, and the L-shaped plates cooperate with the steel pipe column to form the first bayonet.
[0011] The first bayonet is formed by an L-shaped plate, which has the characteristics of simple structure and reduces the overall cost.
[0012] Preferably, the second bayonet is an arc-shaped groove located at the bottom of the anchor plate.
[0013] In this embodiment, the second bayonet can also be configured as several L-shaped plates with upward openings. However, the second bayonet adopts an arc-shaped groove, which increases the contact area between the steel pipe column and the arc-shaped groove during piling, effectively reducing the pressure on the arc-shaped groove and reducing the possibility of deformation of the arc-shaped groove.
[0014] Preferably, the anchor plate is provided with a reinforcing strip along the vertical direction, and the reinforcing strip is provided with a number of connecting rings along its length direction, and the anchor chain assembly is connected to the connecting rings.
[0015] Reinforcing ribs can increase the strength of anchor plates.
[0016] Preferably, the anchor chain assembly includes several short chains connected to a connecting ring, with the ends of the short chains furthest from the connecting ring connected to a long chain.
[0017] By combining short and long chains, the force on the anchor plate is more even and stable when the long chain pulls the short chain.
[0018] Preferably, two anchor plates are provided, with the arc-shaped anchor plates of the two anchor plates respectively located on both sides of the steel pipe column; the straight anchor plates of the two anchor plates are attached to each other.
[0019] Setting up two anchor plates allows for the simultaneous installation of two anchor plates, improving the efficiency of anchor plate installation.
[0020] An installation method for a floating offshore wind turbine embedded anchoring device includes the following steps: S01: Assemble the steel pipe pile and anchor plate, insert the steel pipe pile into the second bayonet, insert the anchor plate into the first bayonet, and straighten the anchor chain assembly vertically; S02: Drive the steel pipe piles into the seabed; S03: Drive the steel pipe piles and anchor plates into the seabed; S04: Pull out the steel pipe pile; S05: A device for pulling the anchor chain assembly and adjusting the anchor plate.
[0021] By following the above steps, the installation efficiency of the anchoring device can be effectively improved. It features precise positioning, deep penetration, stable structure, low cost, convenient construction, and high efficiency.
[0022] Preferably, S05 includes the following steps: S051: Drag the long chain from a vertical position for a distance until the angle between the long chain and the anchor plate reaches 30°~60°. At this time, the bottom short chain is taut and the top short chain is slack. S052: Pull the long chain. At this time, only the bottom short chain is under tension. The anchor plate is unbalanced and deflects. Stop pulling when it rotates 30°~45°. S053: Pull back the long chain until the angle between the long chain and the anchor plate reaches 30°~60°; S054: Pull the long chain again, and the anchor plate will deflect. Stop pulling when the anchor plate rotates to the predetermined state or rotates 30°~45° again. S055: Repeat steps S052 to S054 until the anchor plate is adjusted to the appropriate state.
[0023] The above steps make it easy to adjust the anchor plate to the appropriate angle and position.
[0024] Compared with the prior art, the beneficial effects of the present invention are: (1) In this invention, the steel pipe pile can be erected on the second slot of the anchor plate and sunk into the seabed together with the anchor plate through the cooperation of the first slot and the second slot. During the sinking process, the steel pipe pile and the anchor plate can be connected together. When driving the pile, the anchor plate uses the force of the steel pipe pile to drive the pile downward together. After the pile driving is completed, when the steel pipe pile needs to be pulled out, the steel pipe pile can be smoothly separated from the anchor plate. The anchor plate remains on the seabed, while the steel pipe pile is pulled out, so that the steel pipe pile can be reused. Therefore, the installation of the anchor plate is achieved by the cooperation of the steel pipe pile and the anchor plate. The anchor plate can be driven into the seabed by the existing pile driving technology, which can greatly improve the construction efficiency and reduce the construction cost. (2) The steel pipe piles and anchor plates in this invention have simple structures and low support costs, thereby reducing the overall cost; (3) The anchor plate of the present invention uses the force of the steel pipe pile, so the anchor plate is deeply anchored into the soil, thus having the characteristic of high bearing capacity; (4) The implementation of this invention enables the use of tension leg floating wind turbines with high anchoring bearing capacity, which indirectly greatly reduces the cost of the entire floating wind turbine. In summary, this invention features precise positioning, deep penetration, stable structure, low cost, convenient construction, and high efficiency. Attached Figure Description
[0025] Figure 1 This is the front view of the present invention; Figure 2 This is a side view of the present invention; Figure 3 This is a top view of the present invention; Figure 4 This is a cross-sectional view of the present invention; Figure 5 This is a first schematic diagram of the anchor plate adjustment process of the present invention; Figure 6 This is a second schematic diagram of the anchor plate adjustment process of the present invention; Figure 7 This is a third schematic diagram of the anchor plate adjustment process of the present invention; Figure 8 This is the fourth schematic diagram of the anchor plate adjustment process of the present invention; Figure 9 This is the fifth schematic diagram of the anchor plate adjustment process of the present invention; In the diagram: 1. Steel pipe pile, 11. L-shaped plate, 2. Anchor plate, 21. Arc-shaped anchor plate, 22. Transition anchor plate, 23. Straight anchor plate, 24. Arc-shaped groove, 3. First bayonet, 4. Second bayonet, 5. Reinforcing strip, 51. Connecting ring, 6. Anchor chain assembly, 61. Short chain, 62. Long chain. Detailed Implementation
[0026] The technical solution of the present invention will be further described in detail below through specific embodiments and with reference to the accompanying drawings: Example 1: Refer to Figures 1 to 4 As shown, a floating offshore wind turbine embedded anchoring device includes: a steel pipe pile 1 and an anchoring plate 2. A limiting device is provided between the steel pipe pile 1 and the anchoring plate 2. The limiting device allows the steel pipe pile 1 to separate from the anchoring plate 2 only when the steel pipe pile is pulled upward. An anchor chain assembly 6 is connected to the anchoring plate 2.
[0027] Anchor plate 2 includes an arc-shaped anchor plate 21 that fits against the surface of the steel pipe pile 1. Straight anchor plates 23 are provided on both sides of the arc-shaped anchor plate 21, and the straight anchor plates 23 and the arc-shaped anchor plate 21 are connected by a transition anchor plate 22. When anchor plate 2 and steel pipe pile 1 are installed together, the arc-shaped anchor plate 21 fits against the surface of the steel pipe pile 1, and the straight anchor plates 23 on both sides of the arc-shaped anchor plate 21 are on the same plane and pass through the axis of the steel pipe pile 1. In this invention, anchor plates 2 can be provided in two pieces to cooperate with the steel pipe pile 1, or only one piece can be provided. Providing two anchor plates 2 allows for simultaneous installation of both anchor plates 2, improving the efficiency of installation. When two anchor plates 2 are provided, the arc-shaped anchor plates 21 of the two anchor plates 2 are respectively located on both sides of the steel pipe pile, and the straight anchor plates 23 of the two anchor plates 2 are fitted together (e.g., ...). Figure 3 (As shown).
[0028] The limiting device in this invention includes a first limiting device and a second limiting device; the first limiting device includes a first latch 3 disposed in the circumferential direction of the outer wall of the steel pipe pile 1, and the opening direction of the first latch 3 is downward; the second limiting device includes a second latch 4 disposed at the bottom of the anchor plate 2, and the opening direction of the second latch 4 is upward; in use, the bottom edge of the steel pipe pile 1 is locked in the second latch 4, and the upper edge of the anchor plate 2 is locked in the first latch 3.
[0029] Several L-shaped plates 11 are evenly distributed around the circumference of the steel pipe column. The L-shaped plates 11 have an L-shaped cross-section and cooperate with the steel pipe column to form a first locking slot 3. The edges of the L-shaped plates 11 at the first locking slot 3 are chamfered to facilitate the insertion of the anchor plate 2 into the first locking slot 3. In this embodiment, the first locking slot 3 can also be set as an arc groove in the circumferential direction of the steel pipe column.
[0030] The second notch 4 is an arc-shaped groove 24 located at the bottom of the arc-shaped anchor plate 21, with the arc-shaped groove 24 positioned on the inner side of the arc-shaped anchor plate 21. The arc-shaped groove 24 cooperates with the steel pipe pile 1, allowing the bottom end of the steel pipe pile 1 to be inserted into the arc-shaped groove 24.
[0031] In addition, a reinforcing strip 5 is provided vertically on the anchor plate 2, and several connecting rings 51 are provided along the length of the reinforcing strip 5. The anchor chain assembly 6 is connected to the connecting rings 51. The reinforcing strip can improve the strength of the anchor plate 2. The anchor chain assembly 6 includes several short chains 61 connected to the connecting rings 51, and the ends of the short chains 61 away from the connecting rings 51 are all connected to the long chain 62. In this embodiment, there are three connecting rings 51 and three short chains 61. The three short chains 61 are connected to the connecting rings 51 respectively, and the ends of the three short chains 61 away from the connecting rings 51 converge together and connect to the long chain 62.
[0032] The working principle of this invention is as follows: 1. Insert the bottom of the steel pipe pile 1 into the second slot 4, insert the upper edge of the anchor plate 2 into the first slot 3, and pull the anchor chain vertically straight. The first slot 3 and the second slot 4 serve as limiting points, and the anchor chain provides the force to pull the anchor plate 2 upwards. 2. According to the existing offshore wind power pile foundation construction technology, steel pipe pile 1 is sunk to the seabed. Due to the connection limitations between steel pipe pile 1 and anchor plate 2, the two are lowered to the seabed as a single connecting body. The seabed is 30 meters away from the water surface. 3. Drive the connection between the steel pipe pile 1 and the anchor plate 2 to a depth of 40 meters according to the existing vibratory hammer piling method for offshore wind power monopile foundations; 4. Pull out steel pipe pile 1; 5. Pull the anchor chain assembly 6 and adjust the state of the anchor plate 2 to a suitable state.
[0033] The process of pulling the anchor chain to adjust the state of anchor plate 2 is as follows: Figures 5 to 9 As shown: 5.1 Drag the long chain 62 from a vertical position for a certain distance until the angle between the long chain 62 and the anchor plate 2 reaches 30°~60°. At this time, the bottom short chain 61 is taut, and the top two are slack. The state of the anchor chain changes as follows: Figure 5 and Figure 6 As shown; 5.2 Pulling the anchor chain, only the lowest short chain 61 is under tension, causing the anchor plate 2 to deflect due to unbalanced forces. Figure 7 As shown, stop pulling when rotating 30°~45°; 5.3 Pull back the long chain 62, causing the angle between the long chain 62 and the anchor plate 2 to decrease, such as... Figure 8 As shown, until the angle between the long chain 62 and the anchor plate 2 reaches 30°~60°; 5.4 Pulling the long chain 62 again causes the anchor plate 2 to deflect, as... Figure 9 As shown, stop pulling when the rotation reaches the predetermined state or 30°~45°; 5.5 Repeat steps 5.2 to 5.4 until the anchor plate 2 is adjusted to the appropriate state.
[0034] In this invention, the installation of the anchor plate 2 is achieved through the cooperation of the steel pipe pile 1 and the anchor plate 2, which allows the anchor plate 2 to be driven into the seabed using existing piling technology, thereby greatly improving construction efficiency. Furthermore, the steel pipe pile 1 and the anchor plate 2 in this invention have simple structures and low manufacturing costs, thus reducing the overall cost. It features precise positioning, deep penetration, stable structure, low cost, convenient construction, and high efficiency.
[0035] Example 2: An installation method for a floating offshore wind turbine embedded anchoring device, which uses the floating offshore wind turbine embedded anchoring device described in Example 1.
[0036] An installation method for a floating offshore wind turbine embedded anchoring device includes the following steps: S01: Assemble the steel pipe pile 1 and the anchor plate 2. Insert the steel pipe pile 1 into the second bayonet 4 and the anchor plate 2 into the first bayonet 3. Straighten the anchor chain assembly 6 vertically. Specifically: Insert the bottom of the steel pipe pile 1 into the second bayonet 4 and insert the upper edge of the anchor plate 2 into the first bayonet 3. S02: Sink steel pipe pile 1 into the seabed; Specifically: Sink steel pipe pile 1 to the seabed according to the existing offshore wind power pile foundation construction technology. Due to the connection limitation between steel pipe pile 1 and anchor plate 2, the two are lowered to the seabed together as a connecting body. The seabed is 30 meters away from the water surface. S03: Drive the steel pipe pile 1 and anchor plate 2 into the seabed; specifically: drive the connection between the steel pipe pile 1 and anchor plate 2 into the seabed to a depth of 40 meters according to the existing vibratory hammer piling method for offshore wind power monopile foundations. S04: Pull out steel pipe pile 1; S05: A device for pulling the anchor chain assembly 6 and adjusting the anchor plate 2.
[0037] S05 specifically includes the following steps: S051: Drag the long chain 62 from a vertical position for a certain distance until the angle between the long chain 62 and the anchor plate 2 reaches 30°~60°. At this time, the bottom short chain 61 is taut, and the top short chains 61 are slack. Figure 5 and Figure 6 As shown; S052: Pulling the long chain 62, only the bottom short chain 61 is under tension. The anchor plate 2 is unbalanced and deflects. Stop pulling when it rotates 30°~45°. Figure 7 ; S053: Pull back the long chain 62 to reduce the angle between the long chain 62 and the anchor plate 2 until the angle between the long chain 62 and the anchor plate 2 reaches 30°~60°. Figure 8 As shown; S054: Pull the long chain 62 again, and the anchor plate 2 will deflect. Stop pulling when the anchor plate 2 rotates to the predetermined state or rotates another 30°~45°. Figure 9 As shown; S055: Repeat steps S052 to S054 until the anchor plate 2 is adjusted to the appropriate state.
[0038] By following the above steps, the installation efficiency of the anchoring device can be effectively improved. It features precise positioning, deep penetration, stable structure, low cost, convenient construction, and high efficiency.
[0039] The embodiments described above are merely preferred embodiments of the present invention and are not intended to limit the present invention in any way. Other variations and modifications may be made without departing from the technical solutions described in the claims.
Claims
1. A floating offshore wind turbine embedded anchoring device, characterized in that, include: The steel pipe pile and the anchor plate are provided with a limiting device between the steel pipe pile and the anchor plate. The anchor plate includes an arc-shaped anchor plate that fits against the surface of the steel pipe pile, and straight anchor plates are provided on both sides of the arc-shaped anchor plate. The limiting device includes a first limiting device and a second limiting device; the first limiting device includes a first latch provided on the outer wall of the steel pipe pile, the opening direction of the first latch is downward; the second limiting device includes a second latch provided at the bottom of the anchor plate, the opening direction of the second latch is upward; the bottom edge of the steel pipe pile is locked in the second latch, and the upper edge of the anchor plate is locked in the first latch. The limiting device ensures that the steel pipe pile can only be separated from the anchor plate when the steel pipe column is pulled upwards; An anchor chain assembly is connected to the anchor plate, and a chain is connected to the anchor chain assembly.
2. The floating offshore wind turbine embedded anchoring device according to claim 1, characterized in that, A transition anchor plate is used to connect the straight anchor plate and the curved anchor plate.
3. The floating offshore wind turbine embedded anchoring device according to claim 1 or 2, characterized in that, The steel pipe column has several L-shaped plates evenly distributed around its circumference, and the L-shaped plates cooperate with the steel pipe column to form the first bayonet.
4. The floating offshore wind turbine embedded anchoring device according to claim 1 or 2, characterized in that, The second bayonet is an arc-shaped groove located at the bottom of the anchor plate.
5. The floating offshore wind turbine embedded anchoring device according to claim 1 or 2, characterized in that, The anchor plate is provided with a reinforcing strip along the vertical direction, and the reinforcing strip is provided with several connecting rings along its length. The anchor chain assembly is connected to the connecting rings.
6. The floating offshore wind turbine embedded anchoring device according to claim 5, characterized in that, The anchor chain assembly includes several short chains connected to connecting rings, with the ends of the short chains furthest from the connecting rings connected to long chains.
7. The floating offshore wind turbine embedded anchoring device according to claim 1 or 2, characterized in that, There are two anchor plates. The arc-shaped anchor plates of the two anchor plates are respectively set on both sides of the steel pipe column; the straight anchor plates of the two anchor plates are attached to each other.
8. A method for installing a floating offshore wind turbine embedded anchoring device, which uses the floating offshore wind turbine embedded anchoring device according to any one of claims 1 to 7, characterized in that, Includes the following steps: S01: Assemble the steel pipe pile and anchor plate, insert the steel pipe pile into the second bayonet, insert the anchor plate into the first bayonet, and straighten the anchor chain assembly vertically; S02: Drive the steel pipe piles into the seabed; S03: Drive the steel pipe piles and anchor plates into the seabed; S04: Pull out the steel pipe pile; S05: A device for pulling the anchor chain assembly and adjusting the anchor plate.
9. The installation method of the floating offshore wind turbine embedded anchoring device according to claim 8, characterized in that, S05 specifically includes the following steps: S051: Drag the long chain from a vertical position for a distance until the angle between the long chain and the anchor plate reaches 30°~60°. At this time, the bottom short chain is taut and the top short chain is slack. S052: Pull the long chain. At this time, only the bottom short chain is under tension. The anchor plate is unbalanced and deflects. Stop pulling when it rotates 30°~45°. S053: Pull back the long chain until the angle between the long chain and the anchor plate reaches 30°~60°; S054: Pull the long chain again, and the anchor plate will deflect. Stop pulling when the anchor plate rotates to the predetermined state or rotates 30°~45° again. S055: Repeat steps S052 to S054 until the anchor plate is adjusted to the appropriate state.
Citation Information
Patent Citations
Suction type caisson foundation
CN115596002A
Floating wind turbine anchoring foundation device and method for mooring wind turbine using same
CN116176768B
Suction type anchor pile combined structure and installation and construction method thereof
CN113338329A
Construction method of offshore composite foundation
CN115404897A