A method for constructing an offshore wind power single pile foundation and a special vessel

By using the precise positioning and high-precision measurement technology equipped with special ships in offshore wind power construction and combining professional software for pile sliding control, the construction complexity and accuracy problems in the existing technology are solved, and the rapidity of offshore wind power single pile foundation is achieved. , economical and efficient construction.

CN114319356BActive Publication Date: 2024-11-15GUANGDONG HUAERCHEN OFFSHORE WIND POWER ENG
View PDF 0 Cites 5 Cited by

Patent Information

Application Number
CN202111516393.8
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2021-12-09
Publication Date
2024-11-15
Estimated Expiration
2041-12-09

AI Technical Summary

Technical Problem

The existing offshore wind power single pile foundation construction technology is difficult to ensure the rapid construction, good economicality, and the accuracy of steel pile position, verticality, elevation and height difference, and the construction process is complex, affecting efficiency and safety.

Method used

A method of construction of offshore wind power single pile foundation, including the use of a special ship equipped with a pile positioning system, anchor chain group, guide platform, crane frame, pile hammer system and hydraulic system, through precise positioning, suspension structure, hydraulic top and high precision Measurement technology ensures the accuracy of vertical mud and position of steel piles, and combines professional pile driving analysis software to control piles.

Benefits of technology

The construction speed and economy are achieved, the accuracy of the absolute position, elevation and pile axis inclination of the steel piles are ensured, construction efficiency and safety are improved, and production costs are reduced.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN114319356B_ABST
    Figure CN114319356B_ABST
Patent Text Reader

Abstract

The present invention relates to the field of offshore wind power construction, and in particular to a method for constructing a single-pile foundation for offshore wind power and a special ship. After the method is accurately positioned according to the pile driving positioning system, the construction of a fixed guide platform is first carried out; after the platform construction is completed, the special ship crane completes the lifting and flipping of the steel pile, and feeds the steel pile into the guide platform clamp. After adjusting the verticality, the steel pile begins to sink into the mud by its own weight, and the self-weight entry into the mud is completed. The special ship crane lifts the hydraulic hammer to the top of the pile and starts hammering the pile. During the process, the verticality is measured to ensure that the pile is sunk until the pile is sunk; after the pile is sunk in place, the special ship dismantles the guide platform, hoists the auxiliary structure, and the construction is completed and the ship is moved to the next position.
Need to check novelty before this filing date? Find Prior Art

Description

[Technical field]

[0001] The present invention relates to the field of offshore wind power construction, and in particular to an offshore wind power single pile foundation construction method and a special vessel. [Background technology]

[0002] Offshore wind power generation is one of the most promising low-carbon new energy sources with the largest scale of development and commercial development prospects. It has become an important part of my country's energy system and has been vigorously promoted in countries around the world. Wind turbines are constantly developing towards large-scale, wind farms are getting farther and farther away from the shore, and the construction sea area is getting deeper and deeper, which continuously promotes the optimization and improvement of offshore wind power construction technology and the functions of special construction ships.

[0003] As the most commonly used offshore wind power foundation type in China, the single pile foundation has the characteristics of high applicability and fast construction. It is widely used in major offshore wind power bases. Improving the construction efficiency and quality of the single pile foundation is of great significance to promoting the development of domestic offshore wind power. Therefore, in response to the above requirements, we need to design a construction method that is fast and convenient, economical, and can ensure the accuracy and scientificity of the steel pile position, verticality, elevation and elevation difference, as well as a special ship used in this method. [Summary of the invention]

[0004] The purpose of the present invention is to provide an offshore wind power single pile foundation construction method and a special vessel in view of the defects and shortcomings of the prior art.

[0005] In view of the above problems, the present invention adopts the following technical solutions:

[0006] A method for constructing an offshore wind power monopile foundation comprises the following steps:

[0007] 1. Construction preparation: The prepared guide frame is placed at the opening leg of the special ship, and the positioning pile is hung on the guide frame through the supporting structure;

[0008] 2. Positioning of special vessel: The special vessel is accurately positioned to the piling position through GPS and anchor shifting;

[0009] 3. Positioning pile sinking: The positioning pile is hammered into the seabed by a vibrating hammer, and then the guide frame is lifted by a special ship crane and hung on the positioning pile through a hanging mechanism. The guide frame is separated from the hull of the special ship and fixed above the sea surface;

[0010] 4. Adjust the guide frame: Ensure that the guide frame is basically level by adjusting the suspension mechanism;

[0011] 5. Move the structural steel piles in: Use a special ship crane to lift the hook, stand up the structural steel piles, and move the structural steel piles into the upper and lower clamps of the guide frame;

[0012] 6. Centering of structural steel piles: The upper and lower clamps are closed, and the hydraulic jacks on the upper and lower clamps are pushed out to make the structural steel piles located at the center of the upper and lower clamps;

[0013] 7. Self-sinking of structural steel piles: The special ship crane slowly drops the hook, and at the same time, the verticality of the structural steel pile is measured in real time and adjusted through the clamp cylinder, so that the structural steel pile sinks into the mud in a vertical state;

[0014] 8. Pile sinking preparation: Use special software to conduct geological analysis, find out the strata prone to pile slippage and design a pile slippage control plan;

[0015] 9. Structural steel pile sinking: Use a hydraulic hammer to drive the structural steel pile to the designed elevation;

[0016] 10. Pile driving measurement control: ensure that the structural steel piles meet the process requirements;

[0017] 11. Dismantling of the guide platform: The special ship crane hangs the guide frame and releases the suspension device, and places the guide frame along the positioning piles at the opening legs of the special ship. The vibrating hammer pulls out the positioning piles from the seabed and hangs the positioning piles on the guide frame through the supporting structure;

[0018] 12. Lifting of accessory structures: A special ship crane is used to lift the cage and other accessory structures. After the lifting is completed, the ship is moved to the next position for pile sinking construction.

[0019] The specific process of step three is:

[0020] 1) The special ship is accurately positioned, and four positioning piles are sunk in sequence using a vibrating hammer. At this time, the guide frame still falls on the special ship;

[0021] 2) After the four positioning piles are sunk into place, the crane on the special ship lifts the guide frame and raises it to a certain height;

[0022] 3) Use the suspension structure to hang the guide frame on the positioning pile;

[0023] 4) The positioning pile and the guide frame are locked by steel wedges.

[0024] The specific process of step eight is:

[0025] 1) Combine the previous survey and design data with the professional piling analysis software GRLWEAP to analyze the pile driving situation. According to the pile driving energy and penetration, find out the strata where pile slippage may occur and take precautions in advance.

[0026] The specific process of step five is:

[0027] 1) The pile transport barge berths to one side of the special ship, and the special ship crane lifts the upper and lower lifting points of the structural steel piles;

[0028] 2) After the structural steel pile is hoisted horizontally to a certain height, the pile transport barge leaves the special ship, and the special ship crane continues to lift the hook. The special ship crane loosens the lifting point while swinging the boom to the left. After the structural steel pile is transferred to the bow of the ship, the structural steel pile becomes vertical. After the structural steel pile is erected, the lifting point is removed;

[0029] 3) After the special ship crane vertically lifts the structural steel pile, the structural steel pile is fed into the upper and lower clamps of the guide frame by swinging and changing the amplitude of the crane arm. The upper and lower clamps are closed and hydraulically pushed out to fix the structural steel pile at the center position of the upper and lower clamps;

[0030] 4) Use theodolite to measure the verticality of the structural steel piles, adjust the hydraulic jacking stroke according to the measurement results, and adjust the structural steel piles to a vertical state;

[0031] 5) After the structural steel pile is straightened, the special ship crane slowly releases the hook, and the structural steel pile begins to sink into the mud by its own weight. During the process of sinking into the mud by its own weight, the hook is stopped and the verticality of the structural steel pile is measured and verified every time it sinks a certain distance. If the structural steel pile is tilted, the verticality of the structural steel pile is adjusted to a vertical state through the clamp cylinder. The structural steel pile can continue to sink only after it is vertical;

[0032] 6) After the structural steel piles are driven into the mud by their own weight, the special ship crane is unhooked.

[0033] Specifically, the pile driving deviation in step 10 includes absolute position deviation, elevation deviation and pile axis inclination deviation.

[0034] Specifically, the absolute position deviation is 500 mm, the elevation deviation is 50 mm, and the pile axis inclination deviation is ≤3‰.

[0035] Specifically, the specific measurement process of the absolute position deviation is:

[0036] 1) Use the GPS pile positioning system for precise positioning to ensure that the deviation between the center coordinates of the upper and lower clamps and the center coordinates of the structural steel piles is within the error range;

[0037] 2) After the guide frame is constructed, use GPS to measure the deviation between the center of the upper and lower clamps and the center of the structural steel pile. When the structural steel pile is aligned and sunk, use a jack to further adjust the plane position of the structural steel pile to ensure that the plane position deviation of the steel pile is less than 50cm.

[0038] Specifically, the specific measurement process of the elevation deviation is:

[0039] 1) After the guide frame is constructed, the surveyor measures the elevation of the lower hoop through GPS and keeps a record;

[0040] 2) During the pile sinking process, when the pile top elevation is close to the design elevation through the guide frame elevation, stop the hammer and measure the pile top elevation at this time. According to the measurement results and the penetration of the hammer, predict the number of hammer blows required;

[0041] 3) Continue hammering the pile. After a certain number of hammering, stop hammering and measure the pile top elevation. Based on the measurement results and the penetration of the hammer, predict the number of hammering required.

[0042] 4) Repeat the above 3 steps until the design elevation is reached.

[0043] Specifically, the specific measurement process of the pile axis inclination deviation is:

[0044] 1) Before the structural steel piles are driven into the mud, the verticality of the structural steel piles is measured with a theodolite, and the vertical state of the structural steel piles is adjusted by the hydraulic jack of the guide frame. The theodolite is arranged on the guide frame, and the two are arranged at 90°. During the process of the structural steel piles being driven into the mud by their own weight, the sinking is stopped every 50 to 100 cm to measure and adjust the verticality of the steel piles;

[0045] 2) Before pile sinking, lift the measuring guide frame to the top of the pile, accurately measure the horizontality of the flange on the top of the pile before sinking the pile, and accurately adjust the horizontality of the flange on the top of the pile based on the measurement results to ensure that the height difference of the flange on the top of the pile is within 3mm;

[0046] 3) During the pile sinking process, the high-precision dual-axis inclinometer on the hydraulic hammer can monitor the horizontality of the flange on the top of the steel pile in real time. During the pile sinking process, the sinking is paused every 50 to 200 cm, and the verticality of the structural steel pile is adjusted according to the measurement results to ensure that the verticality of the structural steel pile is within the design requirements. At the same time, a theodolite is set up on the guide frame to measure the verticality. The results of the two measurement methods are checked and compared with each other to ensure that the measurement results are correct and that the horizontality deviation of the flange on the top of the pile is within the allowable range.

[0047] A special ship for offshore wind power single pile foundation construction, including a hull body, on which a pile positioning system, an anchor chain group, a guide platform, a crane, a pile hammer system, a crane, a hydraulic system and an electrical system are arranged, the main structure of the crane is a box beam truss structure, the lower part of the crane is connected to the hull body through a bottom column, a diagonal brace and a lower pull rod, the crane is arranged on the top of the crane, the guide platform is erected on the hull body, the pile hammer system is placed on the deck surface of the hull body, the anchor chain group is arranged at both ends of the hull body, the pile positioning system and the anchor chain group are both electrically connected to the control system on the hull body, and the rotation radius of the crane is greater than the distance between the guide platform and the crane.

[0048] The beneficial effects of the offshore wind power monopile foundation construction method and the special ship of the present invention are as follows:

[0049] The structural steel piles driven by this construction method are quick and convenient to construct, have good economy, and the absolute position, elevation and pile axis inclination deviation of the structural steel piles are accurate, and can ensure the uniformity and scientificity of the stress of the structural steel pile structure.

[0050] The special ship of the present invention is provided with a pile positioning system, an anchor chain group and a guide platform, and the pile positioning system and the anchor chain group cooperate with each other, and the ship is accurately positioned at the pile driving position by twisting the anchor and moving the ship. The guide platform adopts an upper and lower clamp structure and is hung on the special ship. The positioning pile is suspended on the guide frame through a supporting structure and moves with the special ship, so that a single ship can complete the operation process of establishing the guide platform and lifting and turning the structural steel piles, which is convenient and fast in construction, ensures the safety of offshore operations, and reduces production costs.

[0051] The concept, specific structure and effects of the present invention will be further described below in conjunction with the accompanying drawings to fully understand the purpose, characteristics and effects of the present invention.

Brief Description of the Drawings

[0052] Figure 1 It is a schematic diagram of the present invention;

[0053] Figure 2 A schematic diagram of the guiding platform;

[0054] Figure 3 for Figure 2 -A enlarged view;

[0055] Figure 4 This is the main view of the column;

[0056] Figure 5 This is the main view of the crane;

[0057] Figure 6-8 This is a schematic diagram of the crane;

[0058] Fig. 9 for Figure 6 -A partial enlarged view;

[0059] Fig.10 is a flow chart of the present invention;

[0060] The hull body 100; the crane 110; the first auxiliary ship 210; the second auxiliary ship 220; the working anchor 310; the guide frame 410; the positioning pile 420; the outrigger 430; the upper clamp 411; the lower clamp 412; the hydraulic jack 510; the roller 520; the roller 530; the column 610; the crane frame 600; the boom 111; the turntable 112; the column 113; the diagonal brace 114; the luffing pulley block 115; the slewing bearing 116; the shelf 117. [Specific implementation method]

[0061] In the description of the present invention, it should be understood that the orientations or positional relationships indicated by the terms "center", "upper", "lower", "front", "back", "left", "right", etc. are based on the orientations or positional relationships shown in the drawings, and are only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as limiting the present invention. In addition, the terms "first" and "second" are used for descriptive purposes only and cannot be understood as indicating or implying relative importance.

[0062] In the description of the present invention, it should be noted that, unless otherwise clearly specified and limited, the terms "installation", "connection" and "connected" should be understood in a broad sense. For example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection, or it can be an indirect connection through an intermediate medium, or it can be the internal connection of two components. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances. In addition, in the description of the present invention, unless otherwise specified, "multiple" and "several" mean two or more.

[0063] See also Figure 1-10 , Figure 1-10 The invention discloses an offshore wind power monopile foundation construction method and an optimal implementation method of a special vessel:

[0064] A method for constructing an offshore wind power monopile foundation comprises the following steps:

[0065] Construction preparation: various materials and equipment are ready, the prepared guide frame 410 is placed at the opening leg of the special ship, and the positioning pile 420 is suspended on the guide frame 410 through the supporting structure.

[0066] The specific process is:

[0067] (1) Collection and investigation of equipment, personnel entering the construction site and construction sea area conditions;

[0068] (2) Prepare implementation construction organization design and special construction technology and safety plans;

[0069] (3) Establish measurement control points and measurement signal propagation base stations;

[0070] (4) Pre-job training and technical briefing for construction personnel;

[0071] (5) Maintenance and trial operation of mechanical equipment;

[0072] (6) Lifting equipment, tools and safety protection equipment are in place.

[0073] 1. Special vessel positioning: The special vessel is accurately positioned to the piling position through GPS and anchor shifting.

[0074] The specific process is:

[0075] (1) The special vessel is equipped with a GPS pile driving positioning system, which consists of three parts: a computer terminal and a video display screen in the control room (which can display positioning data in real time), an optoelectronic rangefinder and a DV probe in the second-floor cabin, and three GPS stations on the front and rear decks (with one GPS standby).

[0076] (2) Based on the hydrological and meteorological data of the windy sea area, the direction of the ocean current and the ebb tide are known, and the bow direction of the ship is determined by combining the influence of tide and waves.

[0077] (3) Input the coordinates of the position to be constructed and the position angle into the GPS piling positioning system, and the pile position deviation and torsion angle deviation will be displayed in real time on the positioning system display interface. According to the deviation, the special vessel sails to the position and drops 8 working anchors 310. The special vessel adopts self-propelled mode when moving within the wind farm area. The special vessel is equipped with 8 anchors (four anchors at the front and four at the rear), and the anchor rope length of each anchor is 700m. According to the situation of this project, the anchoring distance of the special vessel (from the ship's side) is 500m.

[0078] (4) The anchor chain group consisting of 8 working anchors 310 of the special ship can be monitored by computer and operated centrally on the bridge. After the 8 working anchors 310 of the special ship are in place, the deviation is displayed through the positioning system, and the conditions of each anchor are adjusted on the bridge, and the ship is accurately positioned to the piling position by twisting the anchors and moving the ship.

[0079] 2. Sinking of the positioning pile: Sinking the positioning pile 420 by a vibrating hammer, and then hanging the guide frame 410 on the positioning pile 420 by a hanging mechanism.

[0080] The specific process of step three is:

[0081] (1) After the special vessel has been precisely positioned, four positioning piles 420 are sequentially sunk using a vibrating hammer; at this time, the guide frame 410 is still on the special vessel.

[0082] (2) After the four positioning piles 420 are sunk into place, the special ship crane 110 lifts the guide frame 410.

[0083] (3) After the guide frame 410 is lifted to a certain height, the guide frame 410 is hung on the top of the positioning pile 420 using a suspension structure. The suspension structure is composed of a steel structure hook, fine-rolled threaded steel bars, and nuts. Three hooks are arranged on the top of each positioning pile 420 to support the weight of the guide frame 410 through the fine-rolled threaded steel bars, ensuring that each fine-rolled threaded steel bar is evenly stressed.

[0084] (4) After the guide frame 410 platform is leveled, the positioning piles 420 and the guide frame 410 are locked with steel wedges to form a stable and reliable offshore positioning and guiding platform.

[0085] (5) The height of the guide platform should take into account the influence of rising and falling tides to ensure that the deck of the special vessel does not touch the guide frame 410 at high tide.

[0086] 3. Adjusting the guide frame: ensuring that the guide frame 410 is basically level by adjusting the suspension mechanism;

[0087] The specific process is:

[0088] Measure the horizontality of the guide frame 410 platform, and ensure that the guide frame 410 platform is basically level by adjusting the hanging length of the fine-rolled thread.

[0089] 4. Moving in the structural steel piles: The special ship crane 110 is used to hook and erect the structural steel piles, and the structural steel piles are moved into the upper hoop 411 and the lower hoop 412 of the guide frame 410 .

[0090] The specific process is:

[0091] (1) The construction of the guide platform 410 is completed, the pile transport barge is moored to the side of the special ship, and the special ship crane 110 lifts the upper and lower lifting points of the structural steel piles.

[0092] (2) After the structural steel pile is hoisted horizontally to a certain height, the pile transport barge leaves the special ship, and the special ship crane 110 continues to lift the hook. The special ship crane 110 loosens the lifting point while swinging the boom to the left. After the structural steel pile is transferred to the bow of the ship, the structural steel pile is turned into a vertical state. After the structural steel pile is erected, the lifting point is removed.

[0093] 5. Centering of structural steel piles: After the special ship crane vertically lifts the structural steel piles, the structural steel piles are fed into the upper and lower clamps of the guide frame by swinging and changing the amplitude of the crane boom. The upper clamp 411 and the lower clamp 412 are closed, and the hydraulic jack 510 located on the upper clamp 411 and the lower clamp 412 is pushed out, so that the structural steel pile is located at the center of the upper clamp 411 and the lower clamp 412.

[0094] 6. Sinking of structural steel piles: The floating crane drops the hook and measures the verticality at regular intervals, so that the structural steel piles can sink into the mud in a vertical state.

[0095] The specific process is:

[0096] (1) The surveyors used theodolite to measure the verticality of the steel piles. The on-site technicians adjusted the stroke of the hydraulic jack 510 according to the measurement results to adjust the steel piles to a vertical state.

[0097] (2) After the structural steel pile is straightened, the special ship crane 110 slowly releases the hook, and the structural steel pile begins to sink into the mud by its own weight. During the process of sinking into the mud by its own weight, the hook is stopped and the verticality of the structural steel pile is measured and verified every time it sinks a certain distance. If the structural steel pile is tilted, the verticality of the structural steel pile is adjusted to a vertical state through the clamp cylinder 510. The structural steel pile can continue to sink only after it is vertical.

[0098] (3) After the steel pile is driven into the mud by its own weight, the special ship crane 110 is unhooked.

[0099] 7. Preparation for pile driving: Measure the verticality of structural steel piles and conduct geological analysis to find out the strata prone to pile sliding and design a pile sliding plan.

[0100] The specific process is:

[0101] (1) Before pile driving construction, the pile driving situation is analyzed by combining the preliminary survey and design data with the professional pile driving analysis software GRLWEAP. Based on the pile driving energy and penetration data, the strata where pile slippage may occur are identified and preventive measures are taken in advance.

[0102] (2) After the crane 110 has lifted the hydraulic hammer to the top of the pile, the hoisting wire rope is lowered until the top of the hydraulic hammer is flat, and then it is lowered about 10 cm before stopping to loosen the hook to prevent the impact of the sudden pile slipping on the crane 110. In the subsequent pile sinking process, the same amount of rope loosening is ensured for the crane 110. Try to loosen the rope less and more frequently. In the event of pile slipping, the crane 110 can lift the weight and lift the hydraulic hammer as soon as possible to reduce the impact on the crane 110 in the event of pile slipping.

[0103] (3) The hydraulic hammer itself has two brake sensors to prevent empty hammers. One is located on the top of the hydraulic hammer. When the hammer top shackle is between vertical and 45 degrees, the sensor will sense and send a brake signal to automatically stop hammering; that is, when the pile slips, the hydraulic hammer will automatically stop hammering before being lifted. The other is located above the hydraulic hammer roller. When the entire weight of the hydraulic hammer falls on the top of the pile, the hydraulic hammer roller will be lifted up, and the sensor senses the signal to allow hammering. When the pile slips, the wire rope of the hanging hammer is strong, and the weight of the hydraulic hammer does not fall completely on the top of the pile, the sensor will send a signal to automatically stop hammering.

[0104] (4) When the pile is first hammered, it is most likely to slip, so the initial impact energy of the pile is set to the minimum energy of the hydraulic hammer. The pile is started with a single hammer, that is, the hammer is stopped after each hammer blow to observe the penetration of the steel pile. Single hammers are continuously struck 3 to 5 times to observe the penetration of the steel pile. If the penetration is less than 5 cm / single hammer, continuous pile driving can be started. Otherwise, single hammers are continued.

[0105] (5) During the pile driving process, when the pile is approaching a stratum where it may slip, the impact energy and hammering rate should be reduced in advance to prevent possible pile slippage.

[0106] (6) During the pile sinking process, the hammering rate and energy should be adjusted in real time according to the penetration depth. The pile penetration depth should be controlled between 1 cm and 2 cm. In many cases, excessive penetration is a precursor to pile slippage. When the penetration depth is large, the hammering energy and hammering rate should be reduced, and even a single hammering with the minimum energy can be used to prevent pile slippage.

[0107] 8. Structural steel pile driving: Use a hydraulic hammer to drive the structural steel piles to the designed elevation.

[0108] Step 9 The specific process is:

[0109] The steel pipe pile sinking is based on the elevation control and the penetration is used as a check. All piles should be sunk to the design elevation, but when one of the following situations occurs, the pile sinking can be stopped and the pile sinking record should be made and notified to the on-site supervisor:

[0110] (1) The pile top reaches the design elevation and the average penetration of the last six consecutive 25 cm sections does not exceed 20 mm.

[0111] (2) The pile top does not reach the design elevation, and the pile top superelevation is less than 1.5 m. The average penetration of the last 50 cm with the maximum hammer energy is still less than 3 mm.

[0112] (3) The pile top does not reach the design elevation and the pile top superelevation is less than 1.5 m, but the total number of hammer blows exceeds 7,000, or the number of hammer blows for the last 1 m of pile driving at the maximum hammer force exceeds 1,000.

[0113] When encountering one of the following situations, pile sinking should be stopped immediately, and the pile sinking records should be promptly notified to the site supervisor and the owner, and the designer should be contacted to discuss and take corresponding measures:

[0114] (1) The pile top reaches the designed elevation and the average penetration of the last 25 cm exceeds 20 mm.

[0115] (2) The pile top does not reach the design elevation, and the pile top height is greater than 1.5 m. The average penetration of the last 50 cm with the maximum hammer energy is still less than 3 mm.

[0116] (3) The pile body is seriously offset and tilted.

[0117] 9. Pile driving measurement control: Ensure that the allowable deviation of the structural steel piles meets the process requirements.

[0118] In this embodiment, the absolute position deviation is 500 mm, the elevation deviation is 50 mm, and the pile axis inclination deviation is ≤ 3‰.

[0119] Step 10 The specific process is:

[0120] 1. Absolute position measurement and control of steel piles:

[0121] (1) Use the GPS pile positioning system for precise positioning to ensure that the deviation between the center coordinates of the guide platform clamp and the center coordinates of the construction steel pile is within the error range.

[0122] (2) After the construction of the guide frame 410 platform is completed, the deviation between the center of the guide platform clamp and the center of the pile position is measured by GPS. When the steel pile is aligned and sunk, the plane position of the steel pile is further adjusted by a jack to ensure that the deviation of the plane position of the steel pile is less than 50 cm.

[0123] 2. Pile top elevation measurement control:

[0124] (1) After the guide platform is constructed, the surveyor will use GPS to measure the elevation of the lower guide platform and keep records.

[0125] (2) During the pile sinking process, when the top elevation of the pile is close to the design elevation, the hammer is stopped and the top elevation of the pile is measured. The number of hammer blows required is estimated based on the measurement results and the penetration of the hammer.

[0126] (3) Continue hammering the pile. After a certain number of hammer strikes, stop hammering and measure the pile top elevation. Based on the measurement results and the penetration rate, predict the number of hammer strikes required.

[0127] (4) Repeat the above process (3) until the design elevation is reached.

[0128] When conducting elevation measurement control, the elevation control benchmark given in the design drawings should be clearly defined to ensure the unity of the elevation system.

[0129] 3. Steel pile verticality measurement and control:

[0130] (1) Before the steel pile is driven into the mud, the verticality of the steel pile is measured with a theodolite, and the vertical state of the steel pile is adjusted by the hydraulic jack 510 on the guide platform. The theodolite is arranged on the positioning guide platform, and the two are arranged at 90°. When the steel pile is driven into the mud by its own weight, it stops sinking every 50 to 100 cm to measure and adjust the verticality of the steel pile.

[0131] (2) Before pile sinking, lift the measuring platform to the top of the pile and accurately measure the horizontality of the flange on the top of the pile before sinking the pile. And accurately adjust the horizontality of the flange on the top of the pile based on the measurement results to ensure that the height difference of the flange on the top of the pile is within 3 mm.

[0132] (3) During the pile sinking process, the high-precision dual-axis inclinometer on the hydraulic hammer can monitor the horizontality of the flange on the top of the steel pile in real time. During the pile sinking process, the sinking is paused every 50 to 200 cm, and the verticality of the steel pile is adjusted according to the measurement results to ensure that the verticality of the steel pile is within the design requirements. At the same time, a theodolite is set up on the guide platform to measure the verticality. The results of the two measurement methods are checked and compared with each other to ensure that the measurement results are correct and that the horizontality deviation of the flange on the top of the pile is within the allowable range.

[0133] More specifically, the high-precision dual-axis inclinometer is installed on the hydraulic hammer, which measures the horizontality of the pile top through its own high-sensitivity sensor and related chips. When the hammer is stopped for measurement, its built-in radio station sends the sensor data to the remote computer. The computer analyzes the received radio station signal through its professional measurement software, and can calculate the pile inclination, pile top slope ratio and pile top offset in real time. The inclination measurement error of the high-precision dual-axis inclinometer can reach 0.1‰. Before the first measurement, the dual-axis inclinometer must be calibrated.

[0134] Dismantling of the guide platform: The special ship crane 110 lifts the guide frame 410 and places it on the special ship deck, vibrates the hammer to the top of the positioning pile 420, pulls the positioning pile 420 out of the seabed and hangs it on the guide frame 410 through the supporting structure.

[0135] Step 11 The specific process is:

[0136] After the piles are sunk to the designed elevation, the hydraulic hammer and pile driver are hoisted back to their original positions. The special ship crane 110 begins to dismantle the guide platform.

[0137] (1) Remove the locking wedge between the guide frame 410 and the positioning pile 420;

[0138] (2) lifting the guide frame 410 to a certain height so that the suspension structure is not stressed, and removing the suspension structure at the top of the positioning pile 420;

[0139] (3) After the dismantling of the suspension structure is completed, the special ship crane 110 lifts the guide frame 410 and places it on a fixed position on the special ship deck.

[0140] (4) The dedicated ship crane 110 lifts the vibrating hammer to the top of the positioning pile 420 , pulls out four positioning piles 420 from the seabed in turn, and hangs the positioning piles 420 on the guide frame 410 .

[0141] In this embodiment, it is also necessary to hoist the auxiliary structure on the structural steel piles.

[0142] The specific process is:

[0143] (1) After the cage has been hoisted to a certain tonnage by the special ship crane 110, the cage locking device on the barge is released. After the locking device is released, the cage is hoisted from the barge to a certain height and placed above the top of the pile where the pile has been sunk.

[0144] (2) The special ship crane 110 is aligned and slowly lowered to put the cage structure on the outside of the steel pile. According to the marks on the steel pile and cage before leaving the factory, the cage angle is slowly rotated by mooring the wind so that the marks coincide and the cage is installed in position.

[0145] (3) After the cage structure is aligned, the special ship crane 110 releases the hook to install it in place.

[0146] (4) The special ship crane 110 lifts the inner platform from the barge for installation. Similarly, it is installed according to the marking lines made before leaving the factory. After the inner platform ring plate is lowered to the pile, the special ship crane 110 is unhooked, the screws are tightened on the inner platform, and the ground wire is connected.

[0147] A special ship for offshore wind power monopile foundation construction includes a hull body 100. In this embodiment, the hull body 100 is an open ship, and the open ship is provided with a first auxiliary ship 210 and a second auxiliary ship 220, and a passage is formed between the first auxiliary ship 210 and the second auxiliary ship 220.

[0148] In this embodiment, the crane 100 includes a boom 111, a turntable 112, a column 113, a diagonal brace 114, a luffing pulley block 115 and a slewing bearing 116. The column 113 is fixedly arranged on the crane frame 600 and is vertically arranged. One end of the diagonal brace 114 is fixedly connected to the top of the column 113, and the other end of the diagonal brace 114 is fixed to the two rear corners of the top of the crane frame. The turntable 112 is sleeved on the column 113 by bolt connection with the slewing bearing 116. The slewing bearing 116 is bolted to the flange welded to the lower part of the column 113. One end of the boom 111 is pivotally connected to the turntable 112 through a pin shaft. A luffing pulley block 115 is arranged between the other end of the boom 111 and the top of the column 113. The boom 111 is rotated up and down around the rotation through the luffing pulley block 115. In this embodiment, a shelf 117 is also provided on the deck. When not in use, the boom 111 is stored by placing the boom 111 on the shelf 117 on the deck surface through the luffing pulley set 115. The slewing support 116 is composed of a motor, a brake, a planetary gear reducer, and large and small gears. The small gear and the large gear are positioned by a partial flange. The slewing support is a three-row roller type with an external gear and is waterproof. The reducer is installed on the column and arranged in four corners.

[0149] Specifically, the hull body 100 is provided with a piling positioning system, an anchor chain group, a guide platform and a crane 110; in this embodiment, for better construction, the guide platform and the crane 110 are installed on the first auxiliary ship 210 and the second auxiliary ship 220, and the guide platform is partially immersed in the river water to achieve towing.

[0150] More specifically, the guide platform includes a guide frame 410 and four positioning piles 420, the positioning piles 420 are evenly arranged in the circumferential direction of the guide frame 410, and the guide frame 410 located at the relative position of the positioning piles 420 is provided with a support leg 430 for erecting the first auxiliary ship 210 and the second auxiliary ship 220. In this embodiment, the length of the positioning pile is 50 meters, the diameter is 2.42m, and the plate thickness is 25mm; four positioning piles are arranged at the four corners of the guide frame. The support leg 430 is used to be fixedly connected with the first auxiliary ship 210 and the second auxiliary ship 220, so that the guide frame 410 is erected on the special ship and moves with the movement of the special ship; in this embodiment, the positioning pile 420 is suspended on the guide frame 410 through a supporting mechanism. When working, the crane 110 lifts the positioning column, then disassembles the corresponding supporting mechanism, and then sinks the positioning column through a vibrating hammer. After the piling is completed, the crane 110 lifts the positioning column, and at the same time, the positioning column is pulled up by a vibrating hammer, and then the positioning column is hung on the guide frame 410 by a supporting mechanism. The problem of multiple insertion and extraction of the guide frame 410 is solved, and the enterprise productivity is improved.

[0151] More specifically, the guide frame 410 includes an upper hoop 411 and a lower hoop 412. In this embodiment, the height distance between the upper hoop 411 and the lower hoop 412 is 10.5 meters. The effective working diameter of the upper and lower hoops is 5.5m to 7.2m. Four hydraulic jacks 510 are provided on the upper hoop 411 and the lower hoop 412. Rollers 520 are provided at the ends of the hydraulic jacks 510. The rollers 520 are rollingly connected to the ends of the hydraulic jacks 510 through rollers 530. During operation, the verticality of the steel pile is always maintained by the hydraulic jacks 510 of the upper hoop 411 and the lower hoop 412; in this embodiment, the thrust of a single hydraulic jack 510 is 150t, and the rollers 520 are rubber wheels, which can effectively protect the paint on the surface of the steel pile from being damaged during the construction process.

[0152] More specifically, the anchor chain group is arranged at both ends of the hull 100; in this embodiment, the anchor chain group includes 8 working anchors 310, the first auxiliary ship 210 and the second auxiliary ship 220 are both provided with a bow and a stern, the bows of the first auxiliary ship 210 and the second auxiliary ship 220 are both provided with 2 working anchors 310, and the sterns of the first auxiliary ship 210 and the second auxiliary ship 220 are both provided with 2 working anchors 310. In this embodiment, the anchor rope length of each working anchor is 700m, and according to the conditions of this project, the anchoring distance of this special ship is 500m.

[0153] More specifically, the pile positioning system includes a computer terminal located in the control room, an optoelectronic rangefinder located in the second-floor cabin, a DV probe, and three GPS stations set on the front and rear decks, and the GPS stations, optoelectronic rangefinders, and DV probes are all electrically connected to the computer terminal. By inputting the marking and position angle of the machine position to be constructed in the computer terminal, the computer terminal can display the pile position deviation and torsion angle deviation in real time. According to the deviation, the special ship sails to the machine position and throws 8 working anchors 310. The anchor chain group composed of 8 working anchors 310 of the special ship can be centrally operated through the computer terminal. After the 8 working anchors 310 of the special ship are thrown in place, the deviation is displayed through the GPS station, and the conditions of each anchor are adjusted on the computer terminal, and the ship is accurately positioned to the piling position by twisting the anchors and moving the ship.

[0154] The pile positioning system and the anchor chain group are electrically connected to the control system on the hull 100, and the rotation radius of the crane 110 is greater than the distance between the guide platform and the crane 110. In this embodiment, the maximum lifting capacity of the crane 110 is 1,800 tons, which meets the needs of daily work. In this embodiment, based on the horizontal plane, the vertical rotation angle of the crane is 80° upward and 41° downward. Based on 45° to the right of the center line of the hull 100, the maximum left and right rotation is 105°.

[0155] Finally, it should be noted that the above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. Although the present invention has been described in detail with reference to the aforementioned embodiments, those skilled in the art can still modify the technical solutions described in the aforementioned embodiments or replace some of the technical features therein by equivalents. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present invention shall be included in the protection scope of the present invention.

Claims

1. A method for constructing an offshore wind power monopile foundation, characterized in that: The following steps are involved:

1. Construction preparation: The prepared guide frame is placed at the opening leg of the special ship, and the positioning pile is hung on the guide frame through the supporting structure; 2. Positioning of a special vessel: The special vessel is accurately positioned at the piling position by GPS and anchor shifting. The special vessel comprises a hull (100). The hull (100) is provided with a piling positioning system, an anchor chain group, a guide platform, a crane (600), a pile hammer system, a crane (110), a hydraulic system and an electrical system. The main structure of the crane (600) is a box beam truss structure. The lower part of the crane (600) is connected to the hull through a bottom column, a diagonal brace and a lower pull rod. The crane is arranged on the top of the crane. The guide platform is erected on the hull (100). The pile hammer system is placed on the deck of the hull. The anchor chain group is arranged at both ends of the hull (100). The piling positioning system and the anchor chain group are both electrically connected to the control system on the hull (100). The rotation radius of the crane (110) is greater than the distance between the guide platform and the crane (110).

3. Positioning pile sinking: The positioning pile is hammered into the seabed by a vibrating hammer, and then the guide frame is lifted by a special ship crane and hung on the positioning pile through a hanging mechanism. The guide frame is separated from the hull of the special ship and fixed above the sea surface; 4. Adjust the guide frame: Ensure that the guide frame is basically level by adjusting the suspension mechanism; 5. Move the structural steel piles in: Use a special ship crane to lift the hook, stand up the structural steel piles, and move the structural steel piles into the upper and lower clamps of the guide frame; 6. Centering of structural steel piles: The upper and lower clamps are closed, and the hydraulic jacks on the upper and lower clamps are pushed out to make the structural steel piles located at the center of the upper and lower clamps; 7. Self-sinking of structural steel piles: The special ship crane slowly drops the hook, and at the same time, the verticality of the structural steel pile is measured in real time and adjusted through the clamp cylinder, so that the structural steel pile sinks into the mud in a vertical state; 8. Pile sinking preparation: Use special software to conduct geological analysis, find out the strata prone to pile slippage and design a pile slippage control plan; 9. Structural steel pile sinking: Use a hydraulic hammer to drive the structural steel pile to the designed elevation; 10. Pile driving measurement control: To ensure that the structural steel piles meet the process requirements, the pile driving deviation includes the absolute position deviation, elevation deviation and pile axis inclination deviation. The specific measurement process of the pile axis inclination deviation is as follows: 1) Before the structural steel piles are put into the mud, the verticality of the structural steel piles is measured by the theodolite, and the vertical state of the structural steel piles is adjusted by the hydraulic jack of the guide frame. The theodolite is arranged on the guide frame, and the two are arranged at 90°. During the process of the structural steel piles entering the mud by their own weight, they stop sinking every 50 to 100 cm to measure and adjust the verticality of the steel piles; 2) Before pile sinking, lift the measuring guide frame to the top of the pile, accurately measure the horizontality of the flange on the top of the pile before sinking the pile, and accurately adjust the horizontality of the flange on the top of the pile based on the measurement results to ensure that the height difference of the flange on the top of the pile is within 3mm; 3) During the pile sinking process, the high-precision dual-axis inclinometer on the hydraulic hammer can monitor the horizontality of the flange on the top of the steel pile in real time. During the pile sinking process, the sinking is paused every 50 to 200 cm, and the verticality of the structural steel pile is adjusted according to the measurement results to ensure that the verticality of the structural steel pile is within the design requirements. At the same time, a theodolite is set up on the guide frame to measure the verticality. The results of the two measurement methods are checked and compared with each other to ensure that the measurement results are correct and that the horizontality deviation of the flange on the top of the pile is within the allowable range; 11. Dismantling of the guide platform: The special ship crane hangs the guide frame and releases the suspension device, and places the guide frame along the positioning piles at the opening legs of the special ship. The vibrating hammer pulls out the positioning piles from the seabed and hangs the positioning piles on the guide frame through the supporting structure; 12. Lifting of accessory structures: A special ship crane lifts the accessory structure. After the lifting is completed, the ship is moved to the next position for pile sinking construction.

2. The offshore wind power monopile foundation construction method according to claim 1, characterized in that: The specific process of step three is: 1) The special ship is accurately positioned, and four positioning piles are sunk in sequence using a vibrating hammer. At this time, the guide frame still falls on the special ship; 2) After the four positioning piles are sunk into place, the crane on the special ship lifts the guide frame and raises it to a certain height; 3) Use the suspension structure to hang the guide frame on the positioning pile; 4) The positioning pile and the guide frame are locked by steel wedges.

3. The offshore wind power monopile foundation construction method according to claim 1, characterized in that: The specific process of step eight is: 1) Combine the preliminary survey and design data with the professional piling analysis software GRLWEAP to analyze the pile driving situation. According to the pile driving energy and penetration, find out the strata where pile slip may occur and take precautions in advance.

4. The offshore wind power monopile foundation construction method according to claim 1, characterized in that: The specific process of step five is: 1) The pile transport barge berths to one side of the special ship, and the special ship crane lifts the upper and lower lifting points of the structural steel piles; 2) After the structural steel pile is hoisted horizontally to a certain height, the pile transport barge leaves the special ship, and the special ship crane continues to lift the hook. The special ship crane loosens the lifting point while swinging the boom to the left. After the structural steel pile is transferred to the bow of the ship, the structural steel pile becomes vertical. After the structural steel pile is erected, the lifting point is removed; 3) After the special ship crane vertically lifts the structural steel pile, the structural steel pile is fed into the upper and lower clamps of the guide frame by swinging and changing the amplitude of the crane arm. The upper and lower clamps are closed and hydraulically pushed out to fix the structural steel pile at the center position of the upper and lower clamps; 4) Use theodolite to measure the verticality of the structural steel piles, adjust the hydraulic jacking stroke according to the measurement results, and adjust the structural steel piles to a vertical state; 5) After the structural steel pile is straightened, the special ship crane slowly releases the hook, and the structural steel pile begins to sink into the mud by its own weight. During the process of sinking into the mud by its own weight, the hook is stopped and the verticality of the structural steel pile is measured and verified every time it sinks a certain distance. If the structural steel pile is tilted, the verticality of the structural steel pile is adjusted to a vertical state through the clamp cylinder. The structural steel pile can continue to sink only after it is vertical; 6) After the structural steel piles are driven into the mud by their own weight, the special ship crane is unhooked.

5. The offshore wind power monopile foundation construction method according to claim 1, characterized in that: The absolute position deviation is 500 mm, the elevation deviation is 50 mm, and the pile axis inclination deviation is ≤3‰.

6. The offshore wind power monopile foundation construction method according to claim 1, characterized in that: The specific measurement process of the absolute position deviation is as follows: 1) Use the GPS pile positioning system for precise positioning to ensure that the deviation between the center coordinates of the upper and lower clamps and the center coordinates of the structural steel piles is within the error range; 2) After the guide frame is constructed, use GPS to measure the deviation between the center of the upper and lower clamps and the center of the structural steel pile. When the structural steel pile is aligned and sunk, use a jack to further adjust the plane position of the structural steel pile to ensure that the plane position deviation of the steel pile is less than 50cm.

7. The offshore wind power monopile foundation construction method according to claim 1, characterized in that: The specific measurement process of the elevation deviation is as follows: 1) After the guide frame is constructed, the surveyor measures the elevation of the lower hoop through GPS and keeps a record; 2) During the pile sinking process, when the pile top elevation is close to the design elevation through the guide frame elevation, stop the hammer and measure the pile top elevation at this time. According to the measurement results and the penetration of the hammer, predict the number of hammer blows required; 3) Continue hammering the pile. After a certain number of hammering, stop hammering and measure the pile top elevation. Based on the measurement results and the penetration of the hammer, predict the number of hammering required. 4) Repeat the above 3 steps until the design elevation is reached.

Citation Information

Cited By

  • Shallow pile pitching floating state operation method for self-elevating wind power installation vessel

    CN120556475A

  • Underwater pile stabilizing frame for pile sinking of pile foundation

    CN121138372A

  • Offshore piling system

    CN224578725U

  • A platform base of a pile foundation pile sinking underwater pile stabilizing frame

    CN224833836U

  • An underwater pile stabilizing frame with angle-shifting guide tube for pile driving.

    CN224955161U