An integrated energy storage high-voltage box

By designing an integrated energy storage high-voltage box, including multi-cluster lithium battery packs and independent condensation unit lines, the charging difficulties in mobile energy storage applications are solved, convenient and economical charging methods are achieved, and the service life of the battery cell is extended .

CN118117709BActive Publication Date: 2024-11-19CHINA CONSTR FOURTH ENG DIV CORP LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202410267671.8
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-03-08
Publication Date
2024-11-19
Estimated Expiration
2044-03-08

AI Technical Summary

Technical Problem

In mobile application scenarios, especially when there is no city power supply on the construction site in the early stage of the construction project, charging is difficult and inconvenient. The fixed energy storage working mode limits the charging efficiency and convenience of the battery pack.

Method used

An integrated energy storage high voltage box is designed, including multi-cluster large-capacity lithium battery packs and independent condensing unit circuits, which supports charging guns to be individually charged and discharged in parallel, compatible with charging piles on the market, independently manage thermal systems, and ensure battery cell environment and life.

Benefits of technology

It realizes the convenience and economy of charging in mobile energy storage applications, avoids the problem of power supply disconnection of other systems when the main charging and discharge is turned off, and extends the service life of the battery cell.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118117709B_ABST
    Figure CN118117709B_ABST
Patent Text Reader

Abstract

The present invention provides an integrated energy storage high-voltage box, including a box body, wherein a charging and discharging mechanism and a cooling device are arranged in the box body, wherein the charging and discharging mechanism specifically includes at least 16 battery groups each consisting of 160 to 210 large-capacity lithium batteries connected in series, wherein each battery group is named in sequence as a battery group A, a battery group B, a battery group C, etc. During charging, each battery group is charged individually by a charging gun, and during discharging, at least two battery groups are discharged in parallel, and the condensing unit circuit is a separate branch; each battery group includes a pre-charging circuit, a main discharging circuit, a main charging circuit, and a standby condensing unit circuit arranged in parallel.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of power distribution devices for construction sites, and in particular to an integrated energy storage high-voltage box. Background Art

[0002] As energy storage technology continues to mature, energy storage products are increasingly being used in various scenarios in life and production. The design of the high-voltage box is an important and indispensable part of the energy storage control system, which determines the various important technical indicators and application scope of energy storage products.

[0003] At present, most of the energy storage on the market are fixed, and the working principle is to use the battery to convert the mains power to the load through the PCS inverter, and at the same time, the mains power is converted into DC to charge the battery through the PCS. Charging and discharging are all completed through the PCS. For fixed energy storage products, this is indeed a good solution from the cost point of view, but for some application scenarios, especially mobile ones, there are no available charging sources around, this charging mode that can only be achieved through the PCS is greatly limited. For example, in the early stage of the construction project, there is no mains power supply at the construction site. According to the fixed energy storage working mode, the energy storage battery placed on the construction site with the PCS can realize the conversion of battery power into mains power for construction site equipment and daily electricity. However, since there is no mains power at the construction site, or it is far away from the mains power area, charging the battery pack after it runs out of power is a more troublesome problem. The battery pack and PCS need to be transported together to find a charging source. Due to the high charging power, there are also requirements for the charging line, which makes charging very limited.

[0004] To this end, a function is needed to charge the battery pack through a charging pile, so that the energy storage battery pack can be charged through PCS and can also be charged using charging piles on the market, making charging more convenient. Summary of the invention

[0005] In order to solve the above problems, the present invention provides an integrated energy storage high-voltage box, which is implemented as follows:

[0006] An integrated energy storage high-voltage box, comprising a box body, wherein a charging and discharging mechanism and a cooling device are arranged in the box body, wherein the charging and discharging mechanism specifically comprises at least 16 battery packs composed of 160 to 210 large-capacity lithium batteries connected in series, wherein each battery pack is named in sequence as a battery pack A, a battery pack B, a battery pack C, etc. During charging, each battery pack is charged individually by a charging gun, and during discharging, at least two battery packs are discharged in parallel, and the condensing unit line is a separate branch;

[0007] Each battery group includes a pre-charging circuit, a main discharging circuit, a main charging circuit and a standby condensing unit circuit which are arranged in parallel.

[0008] As a further improvement, taking the A cluster battery pack as an example,

[0009] The A cluster battery pack includes an A cluster master control, a positive terminal, a negative terminal, an A cluster fuse, and a first temperature sensor for detecting the temperature of the A cluster fuse. The A cluster battery pack is also provided with two voltage collection points BAT+ / A and FUSE+ / A for collecting the real-time bus voltage of the A cluster battery pack.

[0010] The pre-charging circuit of the A cluster battery pack includes an A cluster pre-charging DC contactor, the positive terminal of the A cluster pre-charging DC contactor is connected to K1+ / A of the A cluster master control, the negative terminal of the A cluster pre-charging DC contactor is connected to the POWER- terminal of the A cluster master control, and a power resistor R1 is provided in series on the pre-charging circuit of the A cluster battery pack in the direction of the output terminal of the A cluster pre-charging DC contactor;

[0011] The main discharge circuit of the A-cluster battery pack includes an A-cluster main discharge DC contactor, the positive terminal of the A-cluster main discharge DC contactor is connected to K2+ / A of the A-cluster master control, the negative terminal of the A-cluster main discharge DC contactor is connected to the POWER- terminal of the A-cluster master control, and two clusters of voltage collection points PER+ / A and PER+ / B are respectively arranged on the main discharge circuit of the A-cluster battery pack in the direction of the output end of the A-cluster main discharge DC contactor. The main discharge circuit of the A-cluster battery pack is also provided with a second temperature sensor for monitoring the temperature of the positive terminal of the main discharge DC contactor, and the second temperature sensor is connected to the RT4 interface of the A-cluster master control;

[0012] The main charging circuit of the A cluster battery pack includes an A cluster charging positive pole control contactor and an A cluster charging negative pole control contactor, the positive terminal of the A cluster charging positive pole control contactor is connected to the K3+ / A interface of the A cluster master controller, the negative terminal of the A cluster charging positive pole control contactor is connected to the POWER- terminal of the A cluster master controller, the positive terminal of the A cluster charging negative pole control contactor is connected to the POWER+ terminal of the A cluster master controller, and the negative terminal of the A cluster charging negative pole control contactor is connected to the K10- / A of the A cluster master controller;

[0013] The condensing unit circuit of the A cluster battery pack includes a backup condensing unit control contactor, the positive terminal of the condensing unit control contactor is connected to the K5+ / A interface of the A cluster main controller, the negative terminal of the condensing unit control contactor is connected to the POWER- terminal of the A cluster main controller, and the condensing unit circuit is also provided with a first diode D1 for limiting reverse current in the output direction of the condensing unit control contactor.

[0014] As a further improvement, the cluster A battery pack also includes a cluster A discharge negative pole main control contactor, the positive terminal of the cluster A discharge negative pole main control contactor is connected to the K6+ / A interface of the cluster A main controller, the negative terminal of the cluster A discharge negative pole main control contactor is connected to the POWER- terminal of the cluster A main controller, and a third temperature sensor for detecting the temperature of the cluster A discharge negative pole main control contactor is also provided on the line where the cluster A discharge negative pole main control contactor is located, and the third temperature sensor is connected to the RT5+ / A interface of the cluster A main controller.

[0015] As a further improvement, the A cluster battery pack is further provided with an A cluster current detection sensor for detecting the size of the charging / discharging current, and the detected current data is transmitted to the IBAT2 / A interface of the A cluster master controller.

[0016] As a further improvement, the circuit structure of the other battery groups is the same as the circuit structure of the battery group A.

[0017] As a further improvement, taking the two battery groups of the A cluster battery group and the B cluster battery group as an example, a first circuit breaker is provided between the A cluster charging positive pole control contactor of the A cluster battery group and the A cluster charging base, the power line interface DC+ of the A cluster charging base is connected to the A cluster battery group through the wiring terminal P5, the power line interface DC- of the A cluster charging base is connected to the A cluster battery group through the wiring terminal P6, and the corresponding pin of the communication interface of the A cluster charging base is connected to the corresponding pin of the charging gun through the wiring terminal P3;

[0018] A second circuit breaker is arranged between the B cluster charging positive pole control contactor of the B cluster battery pack and the B cluster charging base, the power line interface DC+ of the B cluster charging base is connected to the B cluster battery pack through the wiring terminal P30, the power line interface DC- of the B cluster charging base is connected to the B cluster battery pack through the wiring terminal P31, and the corresponding pin of the communication interface of the B cluster charging base is communication-connected to the corresponding pin of the charging gun through the wiring terminal P35.

[0019] As a further improvement, the battery packs in cluster A and the battery packs in cluster B respectively include a charging base PE connection terminal of cluster A and a charging base PE connection terminal of cluster B, and the battery packs in other clusters are the same as the battery packs in cluster A and the battery packs in cluster B.

[0020] As a further improvement, the control coils of the main discharge positive and negative on-off controllers of the circuit are controlled by OUT0_J and OUT1_J of the master control respectively.

[0021] The beneficial effects of the present invention are:

[0022] Most high-voltage boxes on the market mainly use a 1-way main charge / discharge circuit control mode. The other power consumption of the system (including the power consumption of the liquid cooling / air cooling system) is obtained from the main charge and discharge circuit. The disadvantage is that when the main charge and discharge is turned off, the power supply of other systems will also be disconnected. It may be acceptable for fixed energy storage systems, but it is obviously inappropriate for mobile ones, especially for systems where charging and discharging are in different locations. The control circuit of the high-voltage box liquid cooling unit adopts a separate branch method, which is not restricted by whether to charge or discharge, and independently manages the thermal system, which is conducive to ensuring a good working environment for the battery cell and extending the cycle life of the battery cell. The charging part is compatible with the charging mode of charging piles in the market, making mobile energy storage charging more economical and convenient. BRIEF DESCRIPTION OF THE DRAWINGS

[0023] Figure 1 An internal circuit assembly diagram of a high-voltage energy storage box provided by the present invention;

[0024] Figure 2 for Figure 1 The schematic diagram of the circuit structure on the left side of the A cluster battery pack in the upper left part of the middle;

[0025] Figure 3 for Figure 1 The schematic diagram of the circuit structure on the left side of the B cluster battery pack in the upper left part of the middle;

[0026] Figure 4 for Figure 1 The schematic diagram of the circuit structure on the left side of the N-cluster battery pack in the lower left part of the middle;

[0027] Figure 5 for Figure 2 The schematic diagram of the circuit structure of the right side of the A cluster battery pack on the right side;

[0028] Figure 6 for Figure 3 The schematic diagram of the circuit structure of the right side of the B cluster battery pack on the right side;

[0029] Figure 7 for Figure 4 The schematic diagram of the circuit structure of the N-cluster battery pack on the right;

[0030] Figure 8 The datasheet pin definition diagram of the A cluster main control circuit of the model M79C2-I-12 / 24V-900V of the present invention;

[0031] Fig. 9 The datasheet pin definition diagram of the B cluster main control circuit of the model M79C2-I-12 / 24V-900V of the present invention;

[0032] Fig.10 The datasheet pin definition diagram of the B cluster main control circuit of the model M79C2-I-12 / 24V-900V of the present invention;

[0033] Fig.11 The datasheet pin definition diagram of two 24V buses of the present invention;

[0034] Fig.12 This is a schematic diagram of the pin definition of the master control datasheet of the model ESMU-U1A-V1.0 of the present invention;

[0035] Fig.13 for Figure 1 The schematic diagram of the circuit structure on the right side of the lower middle part;

[0036] Fig.14 The datasheet pin definition diagram of the 24V power input / 45A, standby condensing circuit LED, and pack slave control communication interface of the present invention;

[0037] Fig.15 This is a schematic diagram of the pin definition of the cooling fan datasheet of the present invention;

[0038] Fig.16 for Figure 2 The schematic diagram of the circuit structure on the lower side;

[0039] Fig.17 for Figure 3 Schematic diagram of the circuit structure on the lower side.

[0040] Fig.18 for Figure 1 Schematic diagram of the circuit structure on the upper right side. DETAILED DESCRIPTION

[0041] In order to make the purpose, technical solutions and advantages of the embodiments of the present invention clearer, the technical solutions in the embodiments of the present invention will be clearly and completely described below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention. Therefore, the following detailed description of the embodiments of the present invention provided in the drawings is not intended to limit the scope of the invention claimed for protection, but merely represents selected embodiments of the present invention.

[0042] In the description of the present invention, the terms "first" and "second" are used for descriptive purposes only and should not be understood as indicating or implying relative importance or implicitly indicating the number of the indicated technical features. Therefore, the features defined as "first" and "second" may explicitly or implicitly include one or more of the features.

[0043] An integrated energy storage high-voltage box, comprising a box body, wherein a charging and discharging mechanism and a cooling device are arranged in the box body, wherein the charging and discharging mechanism specifically comprises at least 16 battery packs composed of 160 to 210 large-capacity lithium batteries connected in series, wherein each battery pack is named in sequence as a battery pack A, a battery pack B, a battery pack C, etc. During charging, each battery pack is charged individually by a charging gun, and during discharging, at least two battery packs are discharged in parallel, and the condensing unit line is a separate branch;

[0044] Each battery group includes a pre-charging circuit, a main discharging circuit, a main charging circuit and a standby condensing unit circuit which are arranged in parallel.

[0045] As a further improvement, taking the A cluster battery pack as an example,

[0046] The A cluster battery pack includes an A cluster master control, a positive terminal, a negative terminal, an A cluster fuse, and a first temperature sensor for detecting the temperature of the A cluster fuse. The A cluster battery pack is also provided with two voltage collection points BAT+ / A and FUSE+ / A for collecting the real-time bus voltage of the A cluster battery pack.

[0047] The pre-charging circuit of the A cluster battery pack includes an A cluster pre-charging DC contactor, the positive terminal of the A cluster pre-charging DC contactor is connected to K1+ / A of the A cluster master control, the negative terminal of the A cluster pre-charging DC contactor is connected to the POWER- terminal of the A cluster master control, and a power resistor R1 is provided in series on the pre-charging circuit of the A cluster battery pack in the direction of the output terminal of the A cluster pre-charging DC contactor;

[0048] The main discharge circuit of the A-cluster battery pack includes an A-cluster main discharge DC contactor, the positive terminal of the A-cluster main discharge DC contactor is connected to K2+ / A of the A-cluster master control, the negative terminal of the A-cluster main discharge DC contactor is connected to the POWER- terminal of the A-cluster master control, and two clusters of voltage collection points PER+ / A and PER+ / B are respectively arranged on the main discharge circuit of the A-cluster battery pack in the direction of the output end of the A-cluster main discharge DC contactor. The main discharge circuit of the A-cluster battery pack is also provided with a second temperature sensor for monitoring the temperature of the positive terminal of the main discharge DC contactor, and the second temperature sensor is connected to the RT4 interface of the A-cluster master control;

[0049] The main charging circuit of the A cluster battery pack includes an A cluster charging positive pole control contactor and an A cluster charging negative pole control contactor, the positive terminal of the A cluster charging positive pole control contactor is connected to the K3+ / A interface of the A cluster master controller, the negative terminal of the A cluster charging positive pole control contactor is connected to the POWER- terminal of the A cluster master controller, the positive terminal of the A cluster charging negative pole control contactor is connected to the POWER+ terminal of the A cluster master controller, and the negative terminal of the A cluster charging negative pole control contactor is connected to the K10- / A of the A cluster master controller;

[0050] The condensing unit circuit of the A cluster battery pack includes a backup condensing unit control contactor, the positive terminal of the condensing unit control contactor is connected to the K5+ / A interface of the A cluster main controller, the negative terminal of the condensing unit control contactor is connected to the POWER- terminal of the A cluster main controller, and the condensing unit circuit is also provided with a first diode D1 for limiting reverse current in the output direction of the condensing unit control contactor.

[0051] As a further improvement, the cluster A battery pack also includes a cluster A discharge negative pole main control contactor, the positive terminal of the cluster A discharge negative pole main control contactor is connected to the K6+ / A interface of the cluster A main controller, the negative terminal of the cluster A discharge negative pole main control contactor is connected to the POWER- terminal of the cluster A main controller, and a third temperature sensor for detecting the temperature of the cluster A discharge negative pole main control contactor is also provided on the line where the cluster A discharge negative pole main control contactor is located, and the third temperature sensor is connected to the RT5+ / A interface of the cluster A main controller.

[0052] As a further improvement, the A cluster battery pack is further provided with an A cluster current detection sensor for detecting the size of the charging / discharging current, and the detected current data is transmitted to the IBAT2 / A interface of the A cluster master controller.

[0053] As a further improvement, the circuit structure of the other battery groups is the same as the circuit structure of the battery group A.

[0054] As a further improvement, taking the two battery groups of the A cluster battery group and the B cluster battery group as an example, a first circuit breaker is provided between the A cluster charging positive pole control contactor of the A cluster battery group and the A cluster charging base, the power line interface DC+ of the A cluster charging base is connected to the A cluster battery group through the wiring terminal P5, the power line interface DC- of the A cluster charging base is connected to the A cluster battery group through the wiring terminal P6, and the corresponding pin of the communication interface of the A cluster charging base is connected to the corresponding pin of the charging gun through the wiring terminal P3;

[0055] A second circuit breaker is arranged between the B cluster charging positive pole control contactor of the B cluster battery pack and the B cluster charging base, the power line interface DC+ of the B cluster charging base is connected to the B cluster battery pack through the wiring terminal P30, the power line interface DC- of the B cluster charging base is connected to the B cluster battery pack through the wiring terminal P31, and the corresponding pin of the communication interface of the B cluster charging base is communication-connected to the corresponding pin of the charging gun through the wiring terminal P35.

[0056] As a further improvement, the A cluster battery pack and the B cluster battery pack respectively include the A cluster charging seat PE connection terminals and the B cluster charging seat PE connection terminals, and the other cluster battery packs are the same as the A cluster battery pack and the B cluster battery pack.

[0057] As a further improvement, the control coils of the main discharge positive and negative on-off controllers of the circuit are controlled by OUT0_J and OUT1_J of the master control respectively.

[0058] Specifically, referring to the diagram, an example is given with a battery pack group A and a battery pack group B.

[0059] In the figure, P4 is the positive terminal of cluster A battery group, F1 is cluster A fuse, NTC3 / A is the first temperature sensor used to detect the fuse, BAT+ / A and FUSE+ / A are two voltage collection point locations, which are used to collect the real-time bus voltage of cluster A battery group. Each cluster battery group line is divided into pre-charge, main discharge, main charge, and standby condensing unit lines.

[0060] K1+ / A is the pre-charging DC contactor of cluster A. The positive terminal of the coil of the pre-charging DC contactor of cluster A is connected to K1+ / A of the main control of cluster A, and the negative terminal is connected to POWER-. The R1 power resistor is connected in series behind the K1+ / A contactor. When starting the load, the pre-charging circuit is started first. The pre-charging circuit is connected in series with a power current limiting resistor, which is mainly used to charge the input capacitor of the load at the moment of starting to prevent instantaneous large current shock. K2+ / A is the main discharge DC contactor. The positive terminal of the contactor coil is connected to the K2+ / A interface of the main control of cluster A, and the negative terminal is connected to POWER-. PER+ / A and PER+ / B are the voltage collection points of the two clusters after the contactor respectively. NTC4 / A is the temperature sensor of K2+ / A, which is connected to the RT4 interface of the main control of cluster A. K3+ / A is the positive control contactor of the charging gun of cluster A. The positive terminal of the contactor coil is connected to the K3+ / A interface of the main control of cluster A, and the negative terminal is connected to POWER-. K10- / A is the negative pole control contactor of cluster A charging. The positive pole of the contactor coil is connected to POWER+, and the negative pole is connected to K10- / A of cluster A master control. K4+ / A is the positive pole control contactor of the standby condensing unit. The positive pole of the contactor coil is connected to K5+ / A of cluster A master control, and the negative pole is connected to POWER-. The positive pole of the condensing unit is connected in series with the D1 anti-reverse diode, i.e., the first diode, to prevent reverse flow when both battery clusters are turned on. K6+ / A- is the total contactor of the negative pole of cluster A discharge. The positive pole of the coil is connected to K6+ / A of cluster A master control, and the negative pole is connected to POWER-. NTC5 / A is the NTC for detecting K6+ / A, which is connected to the RT5+ / A interface of cluster A master control. HALL2 / A is the current detection sensor of cluster A battery group, which is used to measure the size of the charging / discharging current of cluster A battery group, and the measurement data is transmitted back to the corresponding interface of cluster A master control IBAT2 / A.

[0061] P8 is the negative terminal of cluster A battery pack.

[0062] P13 is the positive terminal of the battery pack of cluster B. F3 is the positive fuse of cluster B, and NTC3 / B is the temperature sensor (NTC) of fuse F3, which is connected to the RT3+ / B interface of cluster B master control. K4+ / B is the positive control contactor of cluster B condensing unit, which is connected in series with D28 anti-reverse current diode, and HEAT+ / A and HEAT+ / B are the voltage sampling terminals of the positive pole of the condensing unit after the contactor. K1+ / B is the positive control relay of cluster B pre-charging circuit, the positive pole of the coil is connected to K1+ / B of cluster B master control, the negative pole is connected to POWER-, and the R96 power resistor is connected in series to form the pre-charging circuit of cluster B. K2+ / B is the positive contactor of cluster B main discharge circuit, the positive pole of the contactor coil is connected to K2+ / B of cluster B master control, and the negative pole is connected to POWER-. NTC4 is the temperature sensor of K2+ / B, which is connected to the RT4 interface of cluster B master control. K3+ / B is the positive pole control contactor for charging cluster B. The positive pole of the contactor coil is connected to K3+ / B of the main control of cluster B, and the negative pole is connected to POWER-. K10- / B contactor is the negative pole control contactor for charging cluster B. The positive pole of its coil is connected to POWER+, and the negative pole is connected to K10- / B of the main control of cluster B. K6+ / B- is the negative pole control contactor for discharging cluster B. The positive pole of the contactor is connected to K6+ / B of the main control of cluster B, and the negative pole is connected to POWER-. NTC5 / B is the temperature sensor of the negative pole contactor of cluster B, connected to RT5+ / B of the main control of cluster B.

[0063] HALL1 / B is the B cluster charge and discharge current sensor, which detects the B cluster charge and discharge current and transmits the detection value back to the B cluster master.

[0064] QF4 is the circuit breaker between the charging seat and the positive charging control contactor of cluster A, P5 is connected to the power line interface DC+ of the charging seat, P6 is connected to the power line interface DC- of the charging seat, and P3 is connected to the corresponding pin of the communication interface of the charging seat of cluster A. QF5 is the circuit breaker between the charging seat and the positive charging control contactor of cluster B, P30 is the terminal connecting the power line interface DC+ of the charging seat, and P31 is the terminal connecting the negative pole DC- of the charging seat of cluster B. P35 is the wiring terminal for communicating with the charging seat of cluster B, connected to the corresponding pin of the charging gun, and P1 and P32 are the PE wiring terminals of the charging seat of cluster A and cluster B respectively.

[0065] K6 and K8 are the main discharge positive and negative on-off control contactors, respectively. The control coils are controlled by the main control OUT0_J and OUT1_J. QF1 is the discharge total output control circuit breaker with auxiliary contact IN0 and shunt trip. The auxiliary contact signal is fed back to the main control IN0, allowing the main control to monitor the switch status of the circuit breaker in real time. The circuit breaker is equipped with an electric opening / closing mechanism, P16 is the opening and closing mechanism wiring terminal, S_ON is the closing control line, S_OFF is the opening control signal, the wiring terminal S1 and S_OFF are connected for opening, S1 and S_ON are connected for closing, the panel touch switch S2 controls the closing, and the emergency brake S3 and S3 self-locking multi-position switch are linked to open. P7 and P9 are the main discharge positive and negative connector terminal blocks, respectively. The connector terminal blocks have high-voltage interlock signal wiring, which are connected to the main control IN3 and IN2 detection terminals, respectively, to detect whether the terminal connector is in place when connected, and transmit the signal back to the main control. The YT1 connector is mainly used as the communication interface between the master control and the external EMS. F2 is the positive fuse of the condensing unit circuit, and the K9 contactor controls the positive output of the condensing unit. The K9 contactor coil is controlled by the master control OUT2_J.

[0066] QF2 is the output control circuit breaker of the condensing unit, P12 and P10 are the positive and negative connectors of the DC condensing unit power supply, and P11 is the communication interface of the condensing unit. The system backup power DC-DC circuit is connected in front of the K9 contactor to convert the high voltage of the battery pack into 24V for powering the control circuit and charging the backup power supply. It consists of fuse F4, circuit breaker QF3, DCDC module, diode DF, power resistor RC, circuit breaker QF6, and lead-acid battery BATTERY.

[0067] P17, P2, YT3, P14, P21 are the corresponding connectors.

[0068] The part marked with a dotted line in the middle of the schematic diagram is the connection terminal pin & definition of the master control. The left side is the connection terminal & pin definition of the A cluster master control, and the right side is the connection terminal & pin definition of the B cluster master control. P28 and P26 are the front-end acquisition communication & power supply connectors of cluster B and cluster A respectively. P23 ​​is the external backup battery input interface, which is connected to the internal power supply POWER through the circuit breaker QF6. P33 and P15 are the two fan interfaces of the high-voltage box, corresponding to the K7+ interface of the A cluster and B cluster master control, which is the control of the high-voltage box cooling fan.

[0069] Each branch circuit breaker in the circuit can be manually operated for easy maintenance, and it also has multiple protection functions such as overload and short circuit. After the main discharge output circuit breaker QF1 is closed, its auxiliary contact IN0 notifies the master control to close the circuit. The master control determines whether to discharge by coordinating and detecting the high-voltage interlocking signal of the P7 and P9 connectors.

[0070] The discharge process is: let the A and B cluster master control open K1+ / A, K1+ / B first, and the K6+ / A, K6+ / B master control opens K6, K8 to pre-charge and discharge through QF1. After the pre-charge and discharge are completed, open the A and B cluster main discharge contactors K2+ / A, K2+ / B, and then turn off the pre-charge circuit contactors K1+ / A, K1+ / B. When the discharge is turned off, the master control receives the shutdown signal and notifies the external PCS to turn off the load first, and then disconnects K6, K8, and K2+ / A, K2+ / B in sequence. The working logic of the main charging branch is: after the charging seat connector is connected to the charging gun of the charging pile (A cluster connector P5, P6, P3, P1, B cluster connector P30, P31, P35, P32), the A and B cluster master detects the charging gun insertion signal and makes corresponding evaluations. When it is considered that the charging conditions are met, the A cluster master opens the K3+ / A, K10- / A contactors in sequence, and the B cluster master opens the K3+ / B, K10- / B contactors in sequence. The A and B cluster master independently control the charging of their respective cluster battery packs. When charging is completed or charging is turned off, the A and B cluster master closes its charging branch control contactor. When there is an imbalance in the A and B clusters, the master control will coordinate and alarm. The A cluster of the condensing unit branch is turned on and off through K4+ / A, and the B cluster is turned on and off through K4+ / B. If you only want to disconnect the liquid cooling unit, you can control it through the master control K9 contactor. Under normal circumstances, the condensing unit is always on and waiting for an opportunity, unless there is an over-discharge or other situation that requires thorough protection of the battery pack, then K4+ / A and K4+ / B must be turned off.

[0071] The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. For those skilled in the art, the present invention may have various modifications and variations. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present invention shall be included in the protection scope of the present invention.

Claims

1. An integrated energy storage high-voltage box, comprising a box body, wherein a charging and discharging mechanism and a cooling device are arranged in the box body, characterized in that: The charging and discharging mechanism specifically includes at least 16 battery packs each consisting of 160 to 210 large-capacity lithium batteries connected in series, each battery pack being named in sequence as battery pack A, battery pack B, battery pack C, ... battery pack N. During charging, each battery pack is charged individually by a charging gun, and during discharging, at least two battery packs are connected in parallel for discharge; Each battery cluster includes a pre-charging circuit, a main discharging circuit, a main charging circuit and a standby condensing unit circuit arranged in parallel, and the condensing unit circuit is a separate branch; Taking the A cluster battery pack as an example, the A cluster battery pack includes an A cluster master control, a positive terminal, a negative terminal, an A cluster fuse, and a first temperature sensor for detecting the temperature of the A cluster fuse. The A cluster battery pack is also provided with two voltage collection point positions BAT+ / A and FUSE+ / A for collecting the real-time bus voltage of the A cluster battery pack; The pre-charging circuit of the A cluster battery pack includes an A cluster pre-charging DC contactor, the positive terminal of the A cluster pre-charging DC contactor is connected to the K1+ / A interface of the A cluster master control, the negative terminal of the A cluster pre-charging DC contactor is connected to the POWER- terminal of the A cluster master control, and a power resistor R1 is provided in series on the pre-charging circuit of the A cluster battery pack in the direction of the output terminal of the A cluster pre-charging DC contactor; The main discharge circuit of the A-cluster battery pack includes an A-cluster main discharge DC contactor, the positive terminal of the A-cluster main discharge DC contactor is connected to the K2+ / A interface of the A-cluster master control, the negative terminal of the A-cluster main discharge DC contactor is connected to the POWER- terminal of the A-cluster master control, and two clusters of voltage collection points PER+ / A and PER+ / B are respectively arranged on the main discharge circuit of the A-cluster battery pack in the direction of the output end of the A-cluster main discharge DC contactor. The main discharge circuit of the A-cluster battery pack is also provided with a second temperature sensor for monitoring the temperature of the positive terminal of the main discharge DC contactor, and the second temperature sensor is connected to the RT4+ / A interface of the A-cluster master control; The main charging circuit of the A cluster battery pack includes an A cluster charging positive pole control contactor and an A cluster charging negative pole control contactor, the positive terminal of the A cluster charging positive pole control contactor is connected to the K3+ / A interface of the A cluster master control, the negative terminal of the A cluster charging positive pole control contactor is connected to the POWER- terminal of the A cluster master control, the positive terminal of the A cluster charging negative pole control contactor is connected to the POWER+ terminal of the A cluster master control, and the negative terminal of the A cluster charging negative pole control contactor is connected to the K10- / A interface of the A cluster master control; The condensing unit circuit of the A cluster battery pack includes a backup condensing unit control contactor, the positive terminal of the condensing unit control contactor is connected to the K5+ / A interface of the A cluster main control, the negative terminal of the condensing unit control contactor is connected to the POWER- terminal of the A cluster main control, and the condensing unit circuit is also provided with a first diode D1 for limiting reverse current in the output direction of the condensing unit control contactor.

2. An integrated energy storage high-voltage box as claimed in claim 1, characterized in that: The cluster A battery pack also includes a cluster A discharge negative pole main control contactor, the positive terminal of the cluster A discharge negative pole main control contactor is connected to the K6+ / A interface of the cluster A master control, and the negative terminal of the cluster A discharge negative pole main control contactor is connected to the POWER- terminal of the cluster A master control. A third temperature sensor for detecting the temperature of the cluster A discharge negative pole main control contactor is also provided on the line where the cluster A discharge negative pole main control contactor is located, and the third temperature sensor is connected to the RT5+ / A interface of the cluster A master control.

3. An integrated energy storage high-voltage box as claimed in claim 2, characterized in that: The A cluster battery pack is also provided with an A cluster current detection sensor for detecting the size of the charging / discharging current, and the detected current data is transmitted to the IBAT2 / A interface of the A cluster master control.

4. An integrated energy storage high-voltage box as claimed in claim 3, characterized in that: The circuit structures of the other battery groups are the same as the circuit structure of the battery group A.