A BIM-based information engineering intelligent management method and system
Through BIM technology and neural network models, construction site image recognition and material estimation are realized, which solves the problem of insufficient materials during construction and improves construction efficiency and management quality.
Patent Information
- Application Number
- CN202410343014.7
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2024-03-25
- Publication Date
- 2024-10-29
- Estimated Expiration
- 2044-03-25
AI Technical Summary
In construction projects, existing technology is difficult to estimate the quantity of remaining building materials efficiently and accurately, leading to delays in construction progress and insufficient materials.
Adopt BIM-based information engineering intelligent management method, obtain construction site images through image collection terminals, use neural network models to identify construction areas, match grid processing rules, automatically calculate required material estimates, and compare with inventory materials to generate Reports enable automated material estimating and management.
It improves construction efficiency and the accuracy of material estimation, reduces manual management burden, ensures construction is completed on time, and reduces the risk of material shortages and inventory backlogs.
Smart Images

Figure CN118134190B_ABST
Abstract
Description
Technical Field
[0001] The present application relates to the field of digital engineering technology, and in particular to an intelligent management method and system for information engineering based on BIM. Background Art
[0002] At present, in order to complete the construction project smoothly, BIM technology is applied in the construction field. Through the pre-designed building model, the construction progress and the number of building materials at the construction site are monitored in real time. In order to proceed as planned, the user will calculate whether the remaining number of building materials is sufficient to avoid delays in the completion date due to temporary lack of building materials. However, as the construction progresses, users need to frequently make estimates based on the current project progress and remaining building materials. The work is cumbersome and prone to errors and omissions, which affect the completion of the construction project on time. Therefore, it needs to be improved. Summary of the invention
[0003] In order to facilitate the estimation of remaining building materials in combination with the current construction progress, improve construction efficiency, and ensure that the project is completed on time, this application provides an intelligent management method and system for information engineering based on BIM.
[0004] The above-mentioned invention objective of the present application is achieved through the following technical solutions:
[0005] An intelligent management method for information engineering based on BIM, comprising the steps of:
[0006] When receiving an image acquisition instruction from a user terminal, a start instruction is sent to an image acquisition terminal located in the construction site, and the image acquisition terminal acquires an image of the construction site when receiving the start instruction;
[0007] Sending the acquired construction site images to the neural network model;
[0008] Based on the pre-divided construction area image in the neural network model, the construction area in the construction site image is identified and extracted;
[0009] Filter out the grid processing rules corresponding to the construction area, perform image decomposition processing on the construction site image, and output the unconstructed area;
[0010] Based on the matching of the required material estimates corresponding to the unconstructed areas, the required material estimates are compared with the current inventory materials to generate a report, and the report is sent to the user terminal.
[0011] By adopting the above technical solution, when the construction project starts, the user sends an image acquisition instruction through the user terminal. At this time, the image acquisition terminal located in the construction site regularly obtains the construction site image of the construction site. The pre-divided construction area image is a construction site image with clear boundaries set according to the construction plan before construction. Since the location of the construction area is different at different construction progresses, the construction area in the construction site image is identified and extracted, and then the grid processing rules corresponding to the construction area are screened out to output the unconstructed area. For example, the constructed area is paved with tiles, and the area is displayed with color. The obtained construction site image is different in color from the colorless picture of the unconstructed area, so it can be judged whether the construction of the area has been completed.
[0012] When the area is an unconstructed area, the estimated value of materials required for the area is matched, and the estimated value of materials required is compared with the current inventory materials to generate a report and send it to the user terminal. Then, each unconstructed area corresponds to the estimated value of materials required. Therefore, the user terminal can obtain the estimated value of materials required for the unconstructed area and the materials that need to be replenished. The user does not need to frequently settle the remaining building materials to obtain the data of the required materials, and the estimated value of materials required can be automatically obtained, which saves the user the cumbersome operation process and improves the convenience of estimating the remaining building materials. The image acquisition terminal obtains the picture of the construction site for recognition and the neural network model performs image recognition and analysis, and automatic calculation to improve the accuracy of the estimation of the remaining building materials.
[0013] In a preferred example of the present application: after the step of identifying and extracting the construction area in the construction site image based on the pre-divided construction area image in the neural network model, the following steps are performed:
[0014] When the angle of the image acquisition terminal is different, the acquired construction site images are different;
[0015] Based on the different construction site images obtained, the shapes of the construction areas extracted are different;
[0016] The grid division methods are different according to the construction areas with different shapes.
[0017] By adopting the above technical solution, when the image acquisition terminal is at different angles, the acquired construction site images are different. Due to the different construction site images, the construction area also changes accordingly. For example, the construction area will appear in different shapes such as rectangles, diamonds or triangles. By matching different construction areas with different corresponding grid division methods, automatic construction area recognition and grid division are realized, which reduces the burden of manual management and improves management efficiency.
[0018] In a preferred example of the present application, the step of screening out the grid processing rules corresponding to the construction area, performing image decomposition processing on the construction site image, and outputting the unconstructed area includes the following steps:
[0019] Filter out the grid processing rules corresponding to the construction area;
[0020] Based on the selected grid processing rules, the construction site image is decomposed into several grid areas;
[0021] Perform regional feature recognition on a number of grid areas to obtain recognition results for each grid area;
[0022] Match the recognition result of each grid area with the standard feature image;
[0023] If the recognition result matches the standard feature image, the recognition result is a completed area;
[0024] If the recognition result does not match the standard feature image, the recognition result is an unfinished area;
[0025] According to the collection instruction, the recognition results are collected and counted as unfinished areas, and the unconstructed areas are output.
[0026] By adopting the above technical solution, the standard feature image refers to the area where the construction area has been completed; the construction site image is decomposed into several grid areas corresponding to a specific structure. For example, when the construction has been completed, the recognition result is displayed in color, and when the construction is not completed, the recognition result is displayed without color. By matching the recognition result with the standard feature image, the completed area and the unfinished area can be obtained, and the real-time monitoring and status evaluation of the construction site can be carried out. At the same time, the collection statistics of the unfinished areas can obtain the unconstructed areas in the entire construction site, providing intuitive data support, thereby improving the efficiency and quality of the entire construction management.
[0027] In a preferred example of the present application, the step of screening out the grid processing rules corresponding to the construction area comprises the steps of:
[0028] Perform image contour recognition on the construction area to obtain the image contour of the construction area;
[0029] Comparing the image contour with a plurality of pre-stored reference contours representing the construction site contour, and marking the position where the image contour matches the reference contour features as the construction site division area;
[0030] Based on the pre-stored grid division method of the reference contour, the grid processing rules corresponding to the construction site division area are screened out.
[0031] By adopting the above technical scheme, since the shapes of the construction areas obtained at different angles are different, the image contour of the construction area is recognized and the image contour of the construction area is obtained. By comparing the image contour with a plurality of pre-stored reference contours representing the construction site contour, different image contours of the construction area can be obtained, and then the corresponding grid processing rules of each image contour of the construction area can be obtained, so as to ensure the effective coverage and management of the construction area, realize the automation and intelligence of the construction site management, prevent the construction progress from being affected by the changes in the image contour, reduce manual intervention and improve work efficiency.
[0032] In a preferred example of the present application: after the step of sending the acquired construction site image to the neural network model, the following steps are performed:
[0033] Based on the neural network model and the construction site images, the construction period is planned and a construction schedule is generated;
[0034] Based on the unconstructed area, obtain the current construction progress in real time;
[0035] Compare the current construction progress with the construction schedule;
[0036] The construction progress chart is updated in real time according to the current construction progress and sent to the user terminal.
[0037] By adopting the above technical solution, according to the analysis results of the neural network model and combined with the project construction plan, a reasonable construction period plan is formulated and a construction period schedule is generated, so that users can understand the construction progress in real time. By real-time identification of unconstructed areas and constructed areas, the current construction period schedule can be calculated, and the current construction period schedule obtained in real time can be compared with the construction period schedule. The construction period schedule is updated in real time according to actual conditions, so that users can grasp the construction period progress at any time, reasonably allocate human and material resources, and reduce construction costs.
[0038] In a preferred example of the present application, before the step of matching the estimated values of required materials corresponding to the unconstructed areas, comparing the estimated values of required materials with the current inventory materials to generate a report, and sending the report to the user terminal, the following steps are performed:
[0039] Based on the current inventory materials, obtain the used consumables value;
[0040] Compare the used consumables value with the preset consumables value of the current construction progress;
[0041] If the used consumables value is equal to or less than the preset consumables value, the estimated value of required materials is directly obtained;
[0042] If the used consumables value exceeds the preset consumables value, the required material estimate and consumables warning information will be sent to the user terminal.
[0043] By adopting the above technical solution, the used consumables value is obtained through the current inventory materials, and the used consumables value is compared with the preset consumables value of the current construction progress, so as to determine whether the current remaining materials meet the construction requirements and whether further adjustments and supplements are needed. The materials can be accurately controlled, and the used consumables value and remaining materials in the construction process as well as the estimated value of required materials can be monitored in real time, ensuring that the construction project remains efficient and transparent in material management, reducing the risk of inventory backlogs and material shortages, and improving cost control and project management capabilities.
[0044] In a preferred example of the present application, the step of generating a report by matching the estimated values of required materials corresponding to the unconstructed areas and comparing the estimated values of required materials with the current inventory materials includes the following steps:
[0045] Based on the unconstructed area and the preset consumables value, the neural network model automatically calculates the estimated value of materials required for the current construction period;
[0046] Compare the estimated material requirements with the current inventory to generate reports including material shortages and material sufficiencies;
[0047] When the report is insufficient, further obtain the value of materials that need to be replenished;
[0048] The report is sent to the user terminal and displays the value of materials that need to be replenished.
[0049] By adopting the above technical solution and using a neural network model, it is possible to automatically obtain the estimated value of materials required for the current construction period, and generate a report by comparing the estimated value of required materials with the current inventory materials. It is possible to obtain whether the current remaining materials meet the construction requirements. If not, the amount of materials that need to be replenished is further obtained, which facilitates users to estimate the remaining building materials, ensures that the materials can meet construction needs, avoids the situation where insufficient materials affect construction, and ensures the normal progress of the project.
[0050] The second object of the invention is achieved by the following technical solutions:
[0051] An intelligent management system for information engineering based on BIM, comprising:
[0052] An image acquisition module is used to send a start instruction to an image acquisition terminal located in the construction site at intervals when receiving an image acquisition instruction from a user terminal, so that the image acquisition terminal acquires an image of the construction site when receiving the start instruction;
[0053] A neural network model module, used for sending the acquired construction site image to the neural network model;
[0054] An image recognition module is used to identify and extract the construction area in the construction site image based on the construction area image pre-divided in the neural network model;
[0055] The image processing module is used to filter out the grid processing rules corresponding to the construction area, perform image decomposition processing on the construction site image, and output the unconstructed area;
[0056] The report sending module is used to match the estimated values of required materials corresponding to the unconstructed areas, compare the estimated values of required materials with the current inventory materials to generate a report, and send the report to the user terminal.
[0057] By adopting the above technical solution, when the construction project starts, the user sends an image acquisition instruction through the user terminal. At this time, the image acquisition terminal located in the construction site regularly obtains the construction site image of the construction site. The pre-divided construction area image is a construction site image with clear boundaries set according to the construction plan before construction. Since the location of the construction area is different at different construction progresses, the construction area in the construction site image is identified and extracted, and then the grid processing rules corresponding to the construction area are screened out to output the unconstructed area. For example, the constructed area is paved with tiles, and the area is displayed with color. The obtained construction site image is different in color from the colorless picture of the unconstructed area, so it can be judged whether the construction of the area has been completed.
[0058] When the area is an unconstructed area, the estimated value of materials required for the area is matched, and the estimated value of materials required is compared with the current inventory materials to generate a report and send it to the user terminal. Then, each unconstructed area corresponds to the estimated value of materials required. Therefore, the user terminal can obtain the estimated value of materials required for the unconstructed area and the materials that need to be replenished. The user does not need to frequently settle the remaining building materials to obtain the data of the required materials, and the estimated value of materials required can be automatically obtained, which saves the user the cumbersome operation process and improves the convenience of estimating the remaining building materials. The image acquisition terminal obtains the picture of the construction site for recognition and the neural network model performs image recognition and analysis, and automatic calculation to improve the accuracy of the estimation of the remaining building materials.
[0059] The third objective of the present application is achieved through the following technical solutions:
[0060] A computer device comprises a memory, a processor and a computer program stored in the memory and executable on the processor, wherein the processor implements the steps of the above-mentioned BIM-based information engineering intelligent management method when executing the computer program.
[0061] The fourth objective of the present application is achieved through the following technical solutions:
[0062] A computer-readable storage medium stores a computer program, and when the computer program is executed by a processor, the steps of the above-mentioned BIM-based information engineering intelligent management method are implemented.
[0063] In summary, the present application includes at least one of the following beneficial technical effects:
[0064] 1. When the area is an unconstructed area, the estimated value of materials required for the area is matched, and the estimated value of materials required is compared with the current inventory materials to generate a report and send it to the user terminal. Then, each unconstructed area corresponds to the estimated value of materials required, so the user terminal can obtain the estimated value of materials required for the unconstructed area and the materials that need to be replenished. The user does not need to frequently settle the remaining building materials to obtain the data of the required materials, and the estimated value of the required materials is automatically obtained, which saves the user cumbersome operation process and improves the convenience of estimating the remaining building materials. The image acquisition terminal obtains the picture of the construction site for recognition and the neural network model performs image recognition and analysis, and automatic calculation to improve the accuracy of the estimation of the remaining building materials;
[0065] 2. When the image acquisition terminal is at different angles, the obtained construction site images are different. Due to the different construction site images, the construction area also changes accordingly. For example, the construction area will appear in different shapes such as rectangles, diamonds or triangles. By matching different construction areas with different corresponding grid division methods, automatic construction area identification and grid division are realized, which reduces the burden of manual management and improves management efficiency;
[0066] 3. The standard feature image refers to the completed area of the construction area; the construction site image is decomposed into several grid areas corresponding to a specific structure. For example, when the construction is completed, the recognition result is displayed in color, and when the construction is not completed, the recognition result is displayed without color. By matching the recognition result with the standard feature image, the completed area and the unfinished area can be obtained, and the real-time monitoring and status evaluation of the construction site can be carried out. At the same time, the unfinished area is collected and counted, and the unconstructed area in the entire construction site can be obtained, providing intuitive data support, thereby improving the efficiency and quality of the entire construction management;
[0067] 4. Since the shapes of the construction areas obtained at different angles are different, the image contour of the construction area is recognized to obtain the image contour of the construction area. By comparing the image contour with multiple pre-stored reference contours representing the construction site contour, different image contours of the construction area can be obtained, and then the corresponding grid processing rules of each image contour of the construction area can be obtained to ensure effective coverage and management of the construction area, realize automation and intelligent management of the construction site, prevent the construction progress from being affected by changes in the image contour, reduce manual intervention, and improve work efficiency. BRIEF DESCRIPTION OF THE DRAWINGS
[0068] Figure 1 This is a flowchart of an implementation example of an information engineering intelligent management method based on BIM in the present application;
[0069] Figure 2 This is an implementation flow chart after step S30 in an embodiment of an information engineering intelligent management method based on BIM of the present application;
[0070] Figure 3 This is a flowchart for implementing step S40 in an embodiment of a method for intelligent management of information engineering based on BIM in the present application;
[0071] Figure 4 This is a flowchart for implementing step S410 in an embodiment of an information engineering intelligent management method based on BIM of the present application;
[0072] Figure 5 This is an implementation flow chart after step S20 in an embodiment of an information engineering intelligent management method based on BIM of the present application;
[0073] Figure 6 This is an implementation flow chart before step S50 in an embodiment of an information engineering intelligent management method based on BIM of the present application;
[0074] Figure 7 This is a flowchart for implementing step S50 in an embodiment of a method for intelligent management of information engineering based on BIM in the present application;
[0075] Figure 8 This is a principle block diagram of a computer device of the present application. DETAILED DESCRIPTION
[0076] The following is combined with Figure 1-8 This application is described in further detail.
[0077] In one embodiment, if Figure 1 As shown, the present application discloses an intelligent management method for information engineering based on BIM, which specifically includes the following steps:
[0078] S10: When receiving an image acquisition instruction from a user terminal, sending a start instruction to an image acquisition terminal located in the construction site, and the image acquisition terminal acquires an image of the construction site when receiving the start instruction;
[0079] In this embodiment, the user terminal refers to a PC for user operation or a mobile terminal carried by the user, interval sending refers to sending a start instruction at a certain interval; the image acquisition instruction refers to an instruction triggered by the user through the user terminal to start the image acquisition terminal.
[0080] The image acquisition terminal refers to a sensor fixed at the construction site. The sensor includes an omnidirectional camera to obtain real-time construction site images of the entire construction site, and has the function of rotating the picture angle 360 degrees; the construction site image refers to the image of the construction site taken by the omnidirectional camera.
[0081] Specifically, at the beginning of a construction project, the user starts to log in through a PC or a mobile terminal APP to issue an image capture command to send a start command to an image capture terminal located at the construction site at intervals. When the image capture terminal receives the start command, it acquires images of the construction site at intervals.
[0082] S20: sending the acquired construction site image to the neural network model;
[0083] In this embodiment, the neural network model refers to a model that processes and analyzes images of the construction site through CNN (convolutional neural network), and uses an image processing library such as OpenCV to implement the image recognition algorithm. For edge detection, line detection and contour detection, corresponding functions and methods can be used for processing. Optionally, the Canny operator is used for edge detection, the Hough transform is used for line detection, and the contour detection function in OpenCV is used. At the same time, the BIM model of the construction site is generated in combination with the device terminal.
[0084] Specifically, the acquired construction site images are sent to the neural network model, which extracts and analyzes the features of the construction site images, identifies the various areas and data in the image, and generates a BIM model of the construction site in combination with the equipment terminal. The data obtained by the neural network model analysis is associated with the information of each area, thereby achieving more comprehensive monitoring and management of the construction site and improving construction efficiency.
[0085] S30: Based on the construction area image pre-divided in the neural network model, identifying and extracting the construction area in the construction site image;
[0086] In this embodiment, the pre-divided construction area image refers to a construction area image in which the entire construction site is pre-divided into different areas in the neural network model; the construction area refers to the construction area in the construction site image captured by the image acquisition terminal.
[0087] Specifically, the neural network model obtains the construction site image and compares it with the pre-divided construction area image, identifies and extracts the construction area part in the construction site image, and removes the part that is not in the construction area.
[0088] S40: Filter out the grid processing rules corresponding to the construction area, perform image decomposition processing on the construction site image, and output the unconstructed area;
[0089] In this embodiment, the grid processing rule refers to dividing the construction area into a number of grids and setting corresponding management rules and standards for construction areas of different shapes to facilitate better monitoring and management.
[0090] Specifically, by screening out the grid processing rules corresponding to the construction area, for example, when the construction area is a triangle, there is a triangle gridding method, and rectangles and other images have their corresponding grid division processing methods. After the corresponding rules are selected, the construction site image is decomposed into several grids, and by comparing the decomposed grids, the unconstructed area is output. However, the constructed area and the unconstructed area, that is, the "completed area" and the "unfinished area" are text messages in this embodiment and are attached with different color attributes, so as to achieve fast and accurate judgment on the completion status of the construction area, thereby better monitoring the progress and quality of the work.
[0091] S50: Based on the matching of the estimated values of required materials corresponding to the unconstructed areas, the estimated values of required materials are compared with the current inventory materials to generate a report, and the report is sent to the user terminal.
[0092] In this embodiment, the estimated value of required materials refers to the amount of materials actually required for the unfinished area, and the current inventory materials refer to the amount of materials remaining in the inventory management. The report in this embodiment is a text message, namely "insufficient material quantity" and "sufficient material quantity", and is accompanied by the amount of materials remaining in the material library and the amount of materials required, and different color attributes. Optionally, the insufficient material quantity and the sufficient material quantity can also be displayed using different color attributes;
[0093] Specifically, since inventory management is associated with the BIM model, a material quantity report can be generated based on the required material quantity and the current inventory material. The report is sent to the user terminal and displayed in the form of a chart with the materials that need to be replenished attached. Optionally, the report is sent to the user terminal with different color attributes, so that the quantity of remaining building materials can be understood through different color attributes.
[0094] In one embodiment, referring to Figure 2 After step S30, perform the following steps:
[0095] S31: When the angle of the image acquisition terminal is different, the acquired construction site image is different;
[0096] S32: Based on the different acquired construction site images, different shapes of the construction areas are identified and extracted;
[0097] S33: The grid division methods are different according to the construction areas with different shapes.
[0098] In this embodiment, the images of the construction site captured by the image acquisition terminal (omnidirectional camera) are different due to changes in the angle. Therefore, it is necessary to identify and extract the different shapes of the construction area in the construction site image, and match different grid division methods according to the construction areas of different shapes. For example, if the shape of the construction area is a rectangle, the rectangular grid division method is matched. The corresponding matches are performed in sequence to subdivide the construction area into smaller units for more accurate monitoring and management.
[0099] In one embodiment, referring to Figure 3 Step S40 comprises the steps of:
[0100] S410: Filter out the grid processing rules corresponding to the construction area;
[0101] S420: Based on the selected grid processing rules, the construction site image is decomposed into a plurality of grid areas;
[0102] S430: performing regional feature recognition on a plurality of grid regions to obtain a recognition result of each grid region;
[0103] S440: Matching the recognition result of each grid area with the standard feature image;
[0104] S450: If the recognition result matches the standard feature image, the recognition result is a completed area;
[0105] S460: If the recognition result does not match the standard feature image, the recognition result is an unfinished area;
[0106] S470: According to the collection instruction, the recognition results are collected and counted as unfinished areas, and the unconstructed areas are output.
[0107] In this embodiment, according to the shape of the construction area, matching rules are screened out from the preset grid processing rules, and then the construction site image is divided into several grid areas for block processing. For example, regional image recognition is performed on the areas in each grid area whether bricks are laid, and the recognition results are obtained. The recognition results of each grid area are matched with the standard feature image to determine whether they meet the standard feature image. If the grid area has completed brick paving, it meets the standard feature image, and the area where bricks have not been laid does not meet the standard feature image. For the brick-paved areas that have successfully matched, they are marked as completed areas; for the areas that have failed to match and have not yet completed brick paving, they are marked as unfinished areas; through the collection instruction, the unfinished areas are collected and counted to obtain the location information and quantity of all unconstructed areas, and the statistical results of the unconstructed areas are output for real-time monitoring and status evaluation of the construction site. At the same time, intuitive data support is provided, thereby improving the efficiency and quality of the entire construction management.
[0108] In one embodiment, referring to Figure 4 Step S410 comprises the following steps:
[0109] S411: Perform image contour recognition on the construction area to obtain the image contour of the construction area;
[0110] S422: Compare the picture outline with a plurality of pre-stored reference outlines representing the construction site outline, and mark the position where the picture outline matches the reference outline features as the construction site division area;
[0111] S433: Based on the pre-stored grid division method of the reference contour, the grid processing rules corresponding to the construction site division area are screened out.
[0112] In this embodiment, the image of the construction area is processed by enabling image screen contour recognition to extract the contour lines of the construction area. A set of reference contours are pre-stored in the neural network model. These contours represent possible contours of different construction site images. The extracted construction area contours are compared with the reference contours. The positions marked on the construction site image that match the characteristics of the reference contours are the divided areas of the construction site. The grid processing rules suitable for the construction area are screened out according to the pre-stored grid division method.
[0113] In one embodiment, referring to Figure 5 , after step S20, perform the following steps:
[0114] S21: Perform construction period planning based on the neural network model and the construction site image, and generate a construction period schedule;
[0115] S22: Based on the unconstructed area, obtain the current construction progress in real time;
[0116] S23: Compare the current construction progress with the construction progress table;
[0117] S24: Update the construction progress schedule in real time according to the current construction progress and send it to the user terminal.
[0118] In this embodiment, a construction schedule can be obtained by combining a neural network model with the construction site image and a construction schedule. Since the neural network model analyzes the image data and identifies the unconstructed areas, the current construction schedule is calculated based on the area and location of the unconstructed areas. The current construction schedule acquired in real time is compared with the generated construction schedule, and the amount of building materials used in the current construction schedule can be calculated, thereby realizing real-time monitoring and planning of the construction schedule, which helps to improve construction efficiency and complete the project on time.
[0119] In one embodiment, referring to Figure 6 , before step S50, perform the following steps:
[0120] S510: Based on the current inventory materials, obtain the used consumables value;
[0121] S520: Compare the used consumables value with the preset consumables value of the current construction progress;
[0122] S530: If the used consumables value is equal to or less than the preset consumables value, directly obtain the required material estimation value;
[0123] S540: If the used consumables value exceeds the preset consumables value, the required material estimation value and consumables warning information are sent to the user terminal.
[0124] In this embodiment, specifically, the total material quantity and the remaining material of the current inventory material are compared through the current inventory material to obtain the used consumable value; the used consumable value is compared with the preset consumable value of the current construction schedule to determine whether it meets the preset consumable quantity of the current construction schedule; if the used consumable value does not exceed the preset consumable value, the estimated value of the required materials is directly obtained, otherwise the estimated value of the required materials and the consumable warning information are sent to the user terminal so that the user can replenish the materials in time to ensure the normal progress of subsequent work.
[0125] In one embodiment, referring to Figure 7 , step S50, comprising the steps of:
[0126] S501: Based on the unconstructed area and the preset consumables value, the neural network model automatically calculates the estimated value of materials required for the current construction period;
[0127] S502: Compare the estimated value of required materials with the current inventory materials to generate a report, which includes insufficient materials and sufficient materials;
[0128] S503: When the report is that the material is insufficient, further obtain the value of the material that needs to be replenished;
[0129] S504: Send the report to the user terminal and display the value of materials that need to be replenished.
[0130] In this embodiment, the equipment terminal analyzes the data of unconstructed areas and preset consumable values through a neural network model, and automatically calculates an estimated value of the quantity of materials required for the current construction period, ensuring sufficient material supply at each stage, avoiding project delays due to material shortages, and improving construction efficiency.
[0131] Specifically, the equipment terminal analyzes the data of unconstructed areas and preset consumable values through a neural network model, automatically calculates the estimated value of the number of materials required for the current construction period, and compares the calculated estimated value of the required materials with the materials currently in stock to generate a report, which includes which materials are insufficient to support the current project and which materials are sufficient, helping managers to quickly understand the material supply situation; if the report shows that there is a shortage of materials, the equipment terminal will further obtain a specific list of materials that need to be replenished, and send the generated report to the user terminal. The report clearly shows the list of materials that still need to be replenished, allowing managers to take immediate action to ensure the timely replenishment of required materials, thereby ensuring the smooth progress of the project.
[0132] It should be understood that the size of the serial numbers of the steps in the above embodiments does not mean the order of execution. The execution order of each process should be determined by its function and internal logic, and should not constitute any limitation on the implementation process of the embodiments of the present application.
[0133] In one embodiment, a BIM-based information engineering intelligent management system is provided, and the BIM-based information engineering intelligent management system corresponds to the BIM-based information engineering intelligent management method in the above embodiment. The BIM-based information engineering intelligent management system includes:
[0134] An image acquisition module is used to send a start instruction to an image acquisition terminal located in the construction site at intervals when receiving an image acquisition instruction from a user terminal, so that the image acquisition terminal acquires an image of the construction site when receiving the start instruction;
[0135] A neural network model module, used for sending the acquired construction site image to the neural network model;
[0136] An image recognition module is used to identify and extract the construction area in the construction site image based on the construction area image pre-divided in the neural network model;
[0137] The image processing module is used to filter out the grid processing rules corresponding to the construction area, perform image decomposition processing on the construction site image, and output the unconstructed area;
[0138] The report sending module is used to match the estimated values of required materials corresponding to the unconstructed areas, compare the estimated values of required materials with the current inventory materials to generate a report, and send the report to the user terminal.
[0139] Optionally, also include:
[0140] The multi-angle acquisition module is used to obtain different construction site images when the angle of the image acquisition terminal is different;
[0141] An image detection module, used to identify and extract different shapes of the construction area based on different images of the construction site acquired;
[0142] The grid matching module is used to match the corresponding grid division methods based on the construction areas of different shapes.
[0143] Optionally, the image processing module includes:
[0144] A rule screening submodule is used to screen out the grid processing rules corresponding to the construction area;
[0145] The image decomposition submodule decomposes the construction site image into several grid areas based on the selected grid processing rules;
[0146] The regional feature recognition submodule performs regional feature recognition on a number of grid regions and obtains the recognition result of each grid region;
[0147] The region matching submodule is used to match the recognition result of each grid region with the standard feature image;
[0148] A marking submodule, for if the recognition result matches the standard feature image, the recognition result is a completed area; if the recognition result does not match the standard feature image, the recognition result is an unfinished area;
[0149] The statistical submodule is used to collect statistics of the unfinished areas according to the collection instructions and output the unconstructed areas.
[0150] Optionally, the rule screening submodule includes:
[0151] The image contour recognition submodule is used to perform image contour recognition on the construction area to obtain the image contour of the construction area;
[0152] The picture contour comparison submodule compares the picture contour with a plurality of pre-stored reference contours representing the construction site contour, and marks the position where the picture contour matches the reference contour features as the construction site division area;
[0153] The gridding screening submodule screens out the gridding processing rules corresponding to the construction site division area based on the grid division method pre-stored in the reference contour.
[0154] Optionally, also include:
[0155] A construction schedule generation module is used to plan the construction period based on the neural network model and the construction site image, and generate a construction schedule;
[0156] The module for obtaining construction progress is used to obtain the current construction progress in real time based on the unconstructed area;
[0157] Compare construction progress module, used to compare the current construction progress with the construction progress table;
[0158] The construction schedule update module is used to update the construction schedule in real time according to the current construction progress and send it to the user terminal.
[0159] Optionally, also include:
[0160] The inventory management module is used to obtain the used consumables value based on the current inventory materials;
[0161] The consumables quantity comparison module is used to compare the used consumables value with the preset consumables value of the current construction progress;
[0162] A material acquisition module, used to directly acquire an estimated value of required materials if the used consumables value is equal to or less than a preset consumables value;
[0163] The material warning module is used to send the required material estimation value and consumable warning information to the user terminal if the used consumable value exceeds the preset consumable value.
[0164] Optionally, also include:
[0165] Automatic calculation module, which is used to automatically calculate the estimated value of materials required for the current construction period based on the unconstructed area and the preset consumables value through the neural network model;
[0166] Inventory material comparison module, used to compare the required material estimates with the current inventory materials to generate reports, including insufficient and sufficient materials;
[0167] The replenishment material calculation module is used to further obtain the value of the materials that need to be replenished when the report shows that the materials are insufficient;
[0168] The report sending module is used to send the report to the user terminal and display the value of materials that need to be replenished.
[0169] For the specific definition of a BIM-based information engineering intelligent management system, please refer to the definition of a BIM-based information engineering intelligent management method above, which will not be repeated here. Each module in the above-mentioned BIM-based information engineering intelligent management system can be implemented in whole or in part through software, hardware and their combination. The above-mentioned modules can be embedded in or independent of the processor in the computer device in the form of hardware, or can be stored in the memory of the computer device in the form of software, so that the processor can call and execute the operations corresponding to the above modules.
[0170] In one embodiment, a computer device is provided. The computer device may be a server, and its internal structure diagram may be as follows: Figure 8 As shown. The computer device includes a processor, a memory, a network interface and a database connected through a system bus. Among them, the processor of the computer device is used to provide computing and control capabilities. The memory of the computer device includes a non-volatile storage medium and an internal memory. The non-volatile storage medium stores an operating system, a computer program and a database. The internal memory provides an environment for the operation of the operating system and the computer program in the non-volatile storage medium. The database of the computer device is used to store construction areas, preset construction site construction areas, project progress information, the number of required materials and the number of materials in the material library. The network interface of the computer device is used to communicate with an external terminal through a network connection. When the computer program is executed by the processor, a method for intelligent management of information engineering based on BIM is implemented.
[0171] In one embodiment, a computer device is provided, including a memory, a processor, and a computer program stored in the memory and executable on the processor, wherein when the processor executes the computer program, a BIM-based information engineering intelligent management method is implemented;
[0172] In one embodiment, a computer-readable storage medium is provided, on which a computer program is stored. When the computer program is executed by a processor, a BIM-based information engineering intelligent management method is implemented.
[0173] Those skilled in the art can understand that all or part of the processes in the above-mentioned embodiment methods can be completed by instructing the relevant hardware through a computer program, and the computer program can be stored in a non-volatile computer-readable storage medium. When the computer program is executed, it can include the processes of the embodiments of the above-mentioned methods. Among them, any reference to memory, storage, database or other media used in the embodiments provided in this application can include non-volatile and / or volatile memory. Non-volatile memory can include read-only memory (ROM), programmable ROM (PROM), electrically programmable ROM (EPROM), electrically erasable programmable ROM (EEPROM) or flash memory. Volatile memory can include random access memory (RAM) or external cache memory. As an illustration and not limitation, RAM is available in many forms, such as static RAM (SRAM), dynamic RAM (DRAM), synchronous DRAM (SDRAM), double data rate SDRAM (DDRSDRAM), enhanced SDRAM (ESDRAM), synchronous link (Synchlink) DRAM (SLDRAM), memory bus (Rambus) direct RAM (RDRAM), direct memory bus dynamic RAM (DRDRAM), and memory bus dynamic RAM (RDRAM).
[0174] Those skilled in the art can clearly understand that for the convenience and simplicity of description, only the division of the above-mentioned functional units and modules is used as an example. In actual applications, the above-mentioned functions can be distributed and completed by different functional units and modules as needed, that is, the internal structure of the device can be divided into different functional units or modules to complete all or part of the functions described above.
[0175] The embodiments described above are only used to illustrate the technical solutions of the present application, rather than to limit them. Although the present application has been described in detail with reference to the aforementioned embodiments, a person skilled in the art should understand that the technical solutions described in the aforementioned embodiments may still be modified, or some of the technical features may be replaced by equivalents. Such modifications or replacements do not deviate the essence of the corresponding technical solutions from the spirit and scope of the technical solutions of the embodiments of the present application, and should all be included in the protection scope of the present application.
Claims
1. A BIM-based information engineering intelligent management method, characterized by: Includes steps: When receiving an image acquisition instruction from a user terminal, a start instruction is sent to an image acquisition terminal located in the construction site at intervals, and the image acquisition terminal acquires an image of the construction site when receiving the start instruction; the acquired image of the construction site is sent to a neural network model; based on the construction area image pre-divided in the neural network model, the construction area in the construction site image is identified and extracted; a grid processing rule corresponding to the construction area is screened out, the image of the construction site is decomposed, and an unconstructed area is output; based on the matching of the estimated value of the required materials corresponding to the unconstructed area, the estimated value of the required materials is compared with the current inventory materials to generate a report, and the report is sent to the user terminal; Among them, the step of screening out the grid processing rules corresponding to the construction area, performing image decomposition processing on the construction site image, and outputting the unconstructed area includes the steps of: screening out the grid processing rules corresponding to the construction area; based on the screened grid processing rules, performing image decomposition processing on the construction site image into a plurality of grid areas; performing regional feature recognition on the plurality of grid areas to obtain the recognition result of each grid area; matching the recognition result of each grid area with the standard feature image; if the recognition result matches the standard feature image, the recognition result is a completed area; if the recognition result does not match the standard feature image, the recognition result is an unfinished area; according to the collection instruction, the recognition results are collected as unfinished areas for statistics, and the unconstructed area is output; Among them, the step of screening out the grid processing rules corresponding to the construction area includes the steps of: performing image picture contour recognition on the construction area to obtain the picture contour of the construction area; comparing the picture contour with a plurality of pre-stored reference contours representing the construction site contour, and marking the position where the picture contour matches the reference contour features as the construction site division area; based on the pre-stored grid division method of the reference contour, screening out the grid processing rules corresponding to the construction site division area.
2. The BIM-based information engineering intelligent management method according to claim 1, characterized in that: After the step of sending the acquired construction site image to the neural network model, the following steps are performed: Based on the neural network model and the construction site image, the construction period is planned and a construction schedule is generated; based on the unconstructed area, the current construction period progress is obtained in real time; the current construction period progress is compared with the construction schedule; the construction period progress schedule is updated in real time according to the current construction period progress and sent to the user terminal.
3. The BIM-based information engineering intelligent management method according to claim 1, characterized in that: Before the step of matching the estimated values of required materials corresponding to the unconstructed areas, comparing the estimated values of required materials with the current inventory materials to generate a report, and sending the report to the user terminal, the following steps are performed: Based on the current inventory materials, obtain the used consumables value; compare the used consumables value with the preset consumables value of the current construction progress; if the used consumables value is equal to or less than the preset consumables value, directly obtain the estimated value of required materials; if the used consumables value exceeds the preset consumables value, send the estimated value of required materials and consumables warning information to the user terminal.
4. The BIM-based information engineering intelligent management method according to claim 1, characterized in that: The step of matching the estimated values of required materials corresponding to the unconstructed areas, comparing the estimated values of required materials with the current inventory materials to generate a report, and sending the report to the user terminal comprises the following steps: Based on the unconstructed areas and the preset consumables values, the neural network model automatically calculates the estimated value of materials required for the current construction period; compares the estimated value of required materials with the current inventory materials to generate a report, which includes insufficient materials and sufficient materials; when the report shows insufficient materials, further obtains the value of materials that need to be replenished; sends the report to the user terminal and displays the value of materials that need to be replenished.
5. An intelligent management system for information engineering based on BIM, characterized in that: include: An image acquisition module is used to send a start instruction to an image acquisition terminal located in the construction site at intervals when receiving an image acquisition instruction from a user terminal, so that the image acquisition terminal acquires an image of the construction site when receiving the start instruction; A neural network model module, used for sending the acquired construction site image to the neural network model; An image recognition module is used to identify and extract the construction area in the construction site image based on the construction area image pre-divided in the neural network model; The image processing module is used to filter out the grid processing rules corresponding to the construction area, perform image decomposition processing on the construction site image, and output the unconstructed area; A report sending module, used for matching the estimated values of required materials corresponding to the unconstructed areas, comparing the estimated values of required materials with the current inventory materials to generate a report, and sending the report to the user terminal; Wherein, the image processing module includes: A rule screening submodule is used to screen out the grid processing rules corresponding to the construction area; The image decomposition submodule decomposes the construction site image into several grid areas based on the selected grid processing rules; The regional feature recognition submodule performs regional feature recognition on a number of grid regions and obtains the recognition result of each grid region; The region matching submodule is used to match the recognition result of each grid region with the standard feature image; A marking submodule, for if the recognition result matches the standard feature image, the recognition result is a completed area; if the recognition result does not match the standard feature image, the recognition result is an unfinished area; A statistical submodule is used to collect statistics of unfinished areas according to the collection instruction and output the unconstructed areas; Wherein, the rule screening submodule includes: The image contour recognition submodule is used to perform image contour recognition on the construction area to obtain the image contour of the construction area; The picture contour comparison submodule compares the picture contour with a plurality of pre-stored reference contours representing the construction site contour, and marks the position where the picture contour matches the reference contour features as the construction site division area; The gridding screening submodule screens out the gridding processing rules corresponding to the construction site division area based on the grid division method pre-stored in the reference contour.
6. A computer device comprising a memory, a processor, and a computer program stored in the memory and executable on the processor, characterized in that: When the processor executes the computer program, the steps of the BIM-based information engineering intelligent management method as described in any one of claims 1 to 4 are implemented.
7. A computer-readable storage medium storing a computer program, characterized in that: When the computer program is executed by a processor, the steps of an intelligent management method for information engineering based on BIM are implemented as described in any one of claims 1 to 4.
Citation Information
Patent Citations
Construction monitoring method and device, electronic equipment and storage medium
CN113111827A
BIM-based transportation airport construction management method, system and device and storage medium
CN114626700A
Water conservancy project information management system and device based on big data, and computing equipment
CN117474489A