Intelligent management method and system for steel box girder hoisting construction
By dividing the construction sections and calculating the lifting efficiency evaluation value, the inefficiency problem caused by the difference in progress and quality of the construction section during the steel box girder lifting construction was solved, real-time management and resource optimization were achieved, and construction efficiency and quality were improved.
Patent Information
- Application Number
- CN202410471299.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2024-04-19
- Publication Date
- 2024-11-12
- Estimated Expiration
- 2044-04-19
AI Technical Summary
During the lifting of existing steel box girders, due to the differences in progress and quality of the construction section, the lack of real-time global management, and the inability to detect and solve construction difficulties in a timely manner, resulting in untimely resource allocation.
Divide the construction area into multiple sections, obtain the lifting construction information of each section through preset time nodes, calculate the lifting efficiency evaluation value, filter the sections that do not meet the standards for management, optimize the evaluation of wind speed impact, construction progress and assembly accuracy, and formulate target construction plan.
Real-time monitoring and management of each construction section is realized, problems are discovered in a timely manner, construction efficiency is improved, resource allocation is ensured, and overall construction quality is improved.
Smart Images

Figure CN118261566B_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of intelligent management of steel box girder hoisting construction, and more specifically, to an intelligent management method and system for steel box girder hoisting construction. Background Art
[0002] Steel box girder hoisting construction is usually used in the field of bridge construction. When building a bridge, it is usually constructed in sections, and many factors need to be considered during construction. Generally, the construction period is relatively tight, and a large number of steel box girders need to be hoisted. Therefore, it is necessary to coordinate personnel and equipment to meet the progress of the hoisting construction.
[0003] In the prior art, due to the differences in construction progress and construction quality in different construction sections, various difficulties will be encountered during construction to affect the efficiency of hoisting construction; usually, management personnel regularly check the hoisting construction status and report it, which will undoubtedly waste statistical costs and cannot achieve real-time global management to provide timely support for the deployment of personnel and equipment for construction sections with construction difficulties.
[0004] Therefore, it is necessary to propose an intelligent management method and system for steel box girder hoisting construction to at least partially solve the problems existing in the prior art. Summary of the invention
[0005] A series of simplified concepts are introduced in the Summary of the Invention, which will be further described in detail in the Detailed Description of the Invention. The Summary of the Invention does not mean to attempt to define the key features and essential technical features of the claimed technical solution, nor does it mean to attempt to determine the scope of protection of the claimed technical solution.
[0006] In order to at least partially solve the above problems, the present invention provides an intelligent management method for steel box girder hoisting construction, comprising:
[0007] Divide the steel box girder hoisting construction area into multiple construction sections, and obtain the hoisting construction information corresponding to each construction section at multiple preset time nodes;
[0008] According to the hoisting construction information, obtain the hoisting efficiency evaluation value corresponding to each construction section at each preset time node, and judge whether the hoisting efficiency evaluation value meets the set standard;
[0009] The construction sections corresponding to the hoisting efficiency evaluation values that do not meet the set standards are selected as the construction sections to be managed.
[0010] Preferably, the hoisting construction information includes: a wind speed impact evaluation coefficient of the environment where the construction section is located, a hoisting construction progress evaluation coefficient, and a steel box girder assembly accuracy evaluation coefficient.
[0011] Preferably, obtaining the hoisting construction information corresponding to each construction section at a plurality of preset time nodes includes:
[0012] At each preset time node, obtain the wind speed data of the environment corresponding to each construction section, the proportion of completed construction length corresponding to the current construction time, and the steel box girder hoisting quality coefficient;
[0013] According to the wind speed data of the environment and the critical wind speed of hoisting, the wind speed impact evaluation coefficient of the environment of each construction section is obtained;
[0014] According to the actual completed construction length ratio corresponding to the current construction time and the preset completed construction length ratio, the hoisting construction progress evaluation coefficient of each construction section is obtained;
[0015] According to the steel box girder hoisting quality coefficient and the preset steel box girder hoisting quality coefficient, the steel box girder assembly accuracy evaluation coefficient of each construction section is obtained.
[0016] Preferably, the determination of the critical wind speed of the environment corresponding to each construction section includes:
[0017] Construct a finite element model of the entire process of steel box girder hoisting in each construction section. According to the analysis results of the finite element model, formulate a hoisting construction plan for the steel box girder in each construction section. Each construction section hoists the steel box girder according to the corresponding hoisting construction plan.
[0018] Among them, the lifting construction plan includes: the critical wind speed of the environment where the construction section is located.
[0019] Preferably, the wind speed data of the environment corresponding to each construction section is obtained at each preset time node, and the wind speed impact evaluation coefficient of the environment corresponding to each construction section is obtained according to the wind speed data of the environment and the critical wind speed of the hoisting, including:
[0020] Acquire the wind speed of the environment corresponding to each construction section at multiple collection times between the current preset time node and the previous preset time node to form wind speed data of the environment;
[0021] According to the corresponding wind speed of the environment at multiple collection moments and the critical wind speed of hoisting, the wind speed impact evaluation coefficient of the environment of each construction section at the current preset time node is obtained.
[0022] Preferably, obtaining the actual completed construction length ratio of each construction section corresponding to the current construction duration at each preset time node includes:
[0023] At each preset time node, the actual completed construction length and the total length of the construction section corresponding to each construction section and the current construction time are obtained to obtain the proportion of the actual completed construction length.
[0024] Preferably, obtaining the steel box girder hoisting mass coefficient corresponding to each construction section at each preset time node includes:
[0025] Construct the 3D design model of each construction area in advance according to the design drawings of steel box girder assembly;
[0026] According to the actual size information of the steel box girder that has been hoisted and constructed in each construction section and the design size information of the steel box girder in the design drawings, the size accuracy coefficient of the steel box girder that has been hoisted and constructed is obtained;
[0027] At each preset time node, image data of the steel box girder hoisting of each construction section is obtained, actual assembly position information of the steel box girder that has completed the hoisting construction in the image data is identified, and according to the actual assembly position information and the design assembly position information of the corresponding steel box girder in the design three-dimensional model, the assembly position accuracy coefficient of the steel box girder that has completed the hoisting construction is obtained;
[0028] According to the actual size and actual assembly position information of the steel box girder that has been hoisted, an actual three-dimensional model of each construction section is constructed, and finite element analysis is performed on the actual three-dimensional model to obtain the actual structural strength information of the steel box girder that has been hoisted. According to the actual structural strength information of the steel box girder that has been hoisted and the design structural strength information of the corresponding steel box girder in the design three-dimensional model, the structural strength accuracy coefficient of the steel box girder that has been hoisted is obtained;
[0029] The hoisting quality coefficient of the steel box girder of each construction section is obtained based on the size accuracy coefficient, assembly position accuracy coefficient and structural strength accuracy coefficient of the steel box girder that has completed hoisting construction.
[0030] Preferably, it also includes: analyzing the construction section to be managed, and selecting the one with the greatest impact on the lifting efficiency evaluation value as the priority management target among the wind speed impact evaluation coefficient of the construction section's environment, the lifting construction progress evaluation coefficient, and the steel box girder assembly accuracy evaluation coefficient.
[0031] An intelligent management system for steel box girder hoisting construction, comprising:
[0032] An acquisition module is used to acquire the hoisting construction information corresponding to each construction section at multiple preset time nodes, wherein the steel box girder hoisting construction area is divided into multiple construction sections;
[0033] The evaluation and judgment module obtains the hoisting efficiency evaluation value corresponding to each construction section at each preset time node based on the hoisting construction information, and judges whether the hoisting efficiency evaluation value meets the set standard;
[0034] A screening module is used to screen the construction sections corresponding to the hoisting efficiency evaluation values that do not meet the set standards as the construction sections to be managed;
[0035] The hoisting construction information includes: the wind speed impact evaluation coefficient of the environment where the construction section is located, the hoisting construction progress evaluation coefficient and the steel box girder assembly accuracy evaluation coefficient.
[0036] Preferably, the acquisition module includes:
[0037] An acquisition unit, which acquires wind speed data of the environment corresponding to each construction section, a proportion of the completed construction length corresponding to the current construction time, and a steel box girder hoisting quality coefficient at each preset time node;
[0038] The first calculation unit obtains the wind speed impact evaluation coefficient of the environment where each construction section is located according to the wind speed data of the environment and the critical wind speed of the hoisting;
[0039] The second calculation unit obtains the hoisting construction progress evaluation coefficient of each construction section according to the actual completed construction length ratio corresponding to the current construction time and the preset completed construction length ratio;
[0040] The third calculation unit obtains the steel box girder assembly accuracy evaluation coefficient of each construction section according to the steel box girder hoisting quality coefficient and the preset steel box girder hoisting quality coefficient.
[0041] Compared with the prior art, the present invention has at least the following beneficial effects:
[0042] According to the intelligent management method and system for the hoisting construction of steel box girders described in the present invention, the hoisting construction area of the steel box girder is the total length area of the bridge to be built, which is divided into multiple construction sections for the convenience of segmented construction; a time node for collecting the hoisting construction information corresponding to each construction section can be set, so as to ensure that all construction sections are managed in segments during the entire construction period, and the construction status of each construction section is obtained in time; and after processing the hoisting construction information of each construction section, the corresponding hoisting efficiency judgment value can be obtained, and the construction status of each construction section at a preset time node can be judged by setting standards. If a construction section is screened out, it means that its construction has encountered difficulties, and it is managed according to its actual situation, and problems can be discovered and solved in time to improve the construction efficiency of each construction section.
[0043] The intelligent management method and system for steel box girder hoisting construction described in the present invention, and other advantages, objectives and features of the present invention will be reflected in part through the following description, and in part will also be understood by technical personnel in the field through research and practice of the present invention. BRIEF DESCRIPTION OF THE DRAWINGS
[0044] The accompanying drawings are used to provide a further understanding of the present invention and constitute a part of the specification. Together with the embodiments of the present invention, they are used to explain the present invention and do not constitute a limitation of the present invention. In the accompanying drawings:
[0045] Figure 1 It is a flow chart of the intelligent management method for steel box girder hoisting construction according to the present invention;
[0046] Figure 2 It is a specific flow chart of step S1 in the intelligent management method for steel box girder hoisting construction of the present invention;
[0047] Figure 3 It is a specific flow chart of step S12 in the intelligent management method for steel box girder hoisting construction of the present invention;
[0048] Figure 4 It is a specific flow chart of step S14 in the intelligent management method for steel box girder hoisting construction of the present invention;
[0049] Figure 5 This is a system block diagram of the intelligent management system for steel box girder hoisting construction described in the present invention. DETAILED DESCRIPTION
[0050] The present invention is further described in detail below in conjunction with the accompanying drawings and embodiments so that those skilled in the art can implement the invention with reference to the description.
[0051] It should be understood that the terms such as “having”, “including” and “comprising” used herein do not exclude the existence or addition of one or more other elements or combinations thereof.
[0052] like Figure 1 As shown, the present invention provides an intelligent management method for steel box girder hoisting construction, comprising:
[0053] S1. Divide the steel box girder hoisting construction area into multiple construction sections, and obtain the hoisting construction information corresponding to each construction section at multiple preset time nodes;
[0054] S2. According to the hoisting construction information, obtain the hoisting efficiency evaluation value corresponding to each construction section at each preset time node, and determine whether the hoisting efficiency evaluation value meets the set standard;
[0055] S3. Select the construction sections corresponding to the hoisting efficiency evaluation values that do not meet the set standards as the construction sections to be managed.
[0056] The steel box girder hoisting construction area is the total length area of the bridge to be built, which is divided into multiple construction sections for the convenience of segmented construction. The time node for collecting the hoisting construction information corresponding to each construction section can be set. For example, the bridge construction requires N days, and N days are evenly divided into 50 preset time nodes. The hoisting construction information corresponding to each construction section will be obtained at each preset time node, so as to ensure that all construction sections are managed in sections during the entire construction period, and the construction status of each construction section is obtained in time. Moreover, after processing the hoisting construction information of each construction section, the corresponding hoisting efficiency judgment value can be obtained. A setting standard corresponding to the hoisting efficiency judgment value can be set to judge the construction status of each construction section at the preset time node. If a construction section is screened out, it means that its construction has encountered difficulties. In this way, it is managed according to its actual situation, such as the deployment of personnel and machinery, so that problems can be discovered and solved in time to improve the construction efficiency of each construction section.
[0057] Furthermore, the hoisting construction information includes: a wind speed impact evaluation coefficient of the environment where the construction section is located, a hoisting construction progress evaluation coefficient, and a steel box girder assembly accuracy evaluation coefficient.
[0058] Among them, the lifting efficiency evaluation value corresponding to each construction section at each preset time node is:
[0059] α ij =β Q *Q ij -β F *F ij +β D D ij
[0060] Among them, α ij is the lifting efficiency evaluation value of the i-th construction section at the j-th preset time node, Q ij is the steel box girder assembly accuracy evaluation coefficient of the i-th construction section at the j-th preset time node, F ij is the wind speed impact evaluation coefficient of the environment where the i-th construction section is located at the j-th preset time node, D ij is the evaluation coefficient of the hoisting construction progress of the i-th construction section at the j-th preset time node, β Q , β F and β D For ij 、F ij and D ij The corresponding weight value.
[0061] In this embodiment, the wind speed of the environment where the construction section is located, the progress of the hoisting construction, and the assembly accuracy of the steel box girder are selected as the main factors affecting the hoisting construction efficiency; due to the large volume and weight of the steel box girder, it is affected by the wind speed during hoisting. If the wind speed is too high, the hoisting of the steel box girder will swing and affect the construction progress and assembly accuracy;
[0062] In the above formula, weight values are assigned to the wind speed impact evaluation coefficient of the environment where the construction section is located, the hoisting construction progress evaluation coefficient and the steel box girder assembly accuracy evaluation coefficient, respectively, so that the obtained hoisting efficiency evaluation value is more accurate. Each weight value can be assigned by the degree of influence of each evaluation coefficient on the construction efficiency, which can be obtained from construction experience.
[0063] like Figure 2 As shown, in one embodiment, the hoisting construction information corresponding to each construction section is obtained at multiple preset time nodes, including:
[0064] S11, obtaining the wind speed data of the environment corresponding to each construction section, the proportion of the completed construction length corresponding to the current construction time, and the steel box girder hoisting quality coefficient at each preset time node;
[0065] S12. Obtain the wind speed impact evaluation coefficient of the environment where each construction section is located based on the wind speed data of the environment and the critical wind speed of the hoisting;
[0066] S13, obtaining a hoisting construction progress evaluation coefficient for each construction section according to the actual completed construction length ratio corresponding to the current construction time and the preset completed construction length ratio;
[0067] S14. According to the steel box girder hoisting quality coefficient and the preset steel box girder hoisting quality coefficient, obtain the steel box girder assembly accuracy evaluation coefficient of each construction section.
[0068] The order of steps S12, S13 and S14 is not critical.
[0069] The critical wind speed for hoisting, the preset percentage of completed construction length and the preset steel box girder hoisting quality coefficient are all pre-set. After obtaining the wind speed data of the environment corresponding to each construction section, the percentage of completed construction length corresponding to the current construction time and the steel box girder hoisting quality coefficient at the preset time node, the corresponding hoisting construction information can be obtained by calculation.
[0070] Furthermore, the determination of the critical wind speed of the environment corresponding to each construction section includes:
[0071] Construct a finite element model of the entire process of steel box girder hoisting in each construction section. According to the analysis results of the finite element model, formulate a hoisting construction plan for the steel box girder in each construction section. Each construction section hoists the steel box girder according to the corresponding hoisting construction plan.
[0072] Among them, the lifting construction plan includes: the critical wind speed of the environment where the construction section is located.
[0073] Before starting construction, first investigate the environmental factors of each construction section, then start modeling according to the design drawings, build a finite element model of the entire hoisting process of each construction section, and apply wind loads and hoisting loads to the steel box girder in the finite element model, and analyze and compare the swing amplitude of the steel box girder when hoisting under different load combinations, as well as the stress on the lifting points and slings of the steel box girder, so as to control the safety of the lifting points and slings during hoisting from the strength point of view, and take corresponding measures to simulate the swing amplitude of the steel box girder, and then formulate a hoisting construction plan for each construction section, so as to obtain the critical wind speed that the machinery and control measures used in each construction section can withstand during hoisting, so as to ensure the safety of construction.
[0074] like Figure 3 As shown, further, at each preset time node, the wind speed data of the environment corresponding to each construction section is obtained, and according to the wind speed data of the environment and the critical wind speed of the hoisting, the wind speed impact evaluation coefficient of the environment of each construction section is obtained, including:
[0075] S121, obtaining the wind speed of the environment corresponding to each construction section at multiple collection times between the current preset time node and the previous preset time node to form wind speed data of the environment;
[0076] S122. Obtain a wind speed impact evaluation coefficient of the environment of each construction section at a current preset time node based on the corresponding wind speeds of the environment at multiple collection moments and the critical wind speed of the hoisting.
[0077] Specifically, the wind speed impact evaluation coefficient of each construction section at the current preset time node is:
[0078]
[0079]
[0080] Among them, F ij is the wind speed impact evaluation coefficient of the environment where the i-th construction section is located at the j-th preset time node, f ijk V is the wind speed impact evaluation coefficient of the environment corresponding to the kth collection time of the i-th construction section at the j-th preset time node, imax is the critical wind speed of the environment corresponding to the i-th construction section, Vijk is the wind speed of the environment corresponding to the kth collection time of the i-th construction section at the j-th preset time node. The number of construction sections is n, then i = 1, 2…, n, the number of preset time nodes is m, then j = 1, 2…, m, the number of collection times is R, then k = 1, 2…, R, R0 is V ijk ≤V imax When , the number of corresponding collection moments;
[0081] The time interval between two adjacent preset time nodes is divided into multiple collection moments for collecting the wind speed of the environment where the construction section is located to form the wind speed data of the environment. Then, the wind speed impact evaluation coefficient of the environment where each construction section is located at the current preset time node can be obtained by calculating the critical wind speed of the hoisting through the above formula. In the above formula, the wind speed impact evaluation coefficients of multiple collection moments are summed up to obtain the wind speed impact evaluation coefficients. Among them, the wind speed of the environment corresponding to each collection moment needs to be compared with the critical wind speed. If V ijk ≤V imax , it indicates that the wind speed in the environment has little influence on the steel box girder hoisting construction, then f ijk The value is 0. If V ijk >V imax , it indicates that the wind speed in the environment has a greater impact on the steel box girder hoisting construction, then f ijk Take a non-zero value, that is, calculate using the above formula;
[0082] This is because when the wind speed in the environment is less than or equal to the critical wind speed, the safety of the steel box girder hoisting construction can be met. When the wind speed in the environment is greater than the critical wind speed, the hoisting construction of the steel box girder will encounter difficulties, and the construction may be stopped or the construction progress may be reduced. Therefore, f ijk The larger the value is, the greater the impact of wind speed on hoisting construction. The larger the wind speed impact evaluation coefficient of each construction section at the current preset time node is, the more accurately it can reflect the degree of impact of wind speed changes on hoisting construction.
[0083] In one embodiment, at each preset time node, the actual completed construction length ratio of each construction section corresponding to the current construction duration is obtained, including:
[0084] At each preset time node, the actual completed construction length and the total length of the construction section corresponding to each construction section and the current construction time are obtained to obtain the proportion of the actual completed construction length.
[0085] The current construction duration is: the time taken from the start of construction in this construction section to each preset time node.
[0086] The ratio of the actual completed construction length of each construction section corresponding to the construction time used to the total length of this construction section is the actual completed construction length ratio, and the ratio of the preset completed construction length of each construction section corresponding to the construction time used to the total length of this construction section is the preset completed construction length ratio;
[0087] According to the actual completed construction length ratio corresponding to the current construction time and the preset completed construction length ratio, the hoisting construction progress evaluation coefficient of each construction section is obtained:
[0088]
[0089] Among them, D ij is the evaluation coefficient of the hoisting construction progress of the i-th construction section at the j-th preset time node, d sij and d 0ij are the actual completed construction length and the preset completed construction length of the i-th construction section at the j-th preset time node corresponding to the current construction duration, d i is the total length of the i-th construction section.
[0090] In d sij <d 0ij , it indicates that the actual completed construction length has not reached the preset completed construction length, that is, the hoisting construction progress is slow. In this case, the smaller the actual completed construction length, the smaller the hoisting construction progress evaluation coefficient. sij ≥d 0ij When , it indicates that the actual completed construction length has reached the preset completed construction length, or even exceeded the preset completed construction length, then the hoisting construction progress evaluation coefficient can be taken as 1;
[0091] Through the above calculation method, using the construction time, completed construction length and total length of the construction section, the hoisting construction progress evaluation coefficient of each construction section can be obtained, providing a more accurate data basis for the hoisting efficiency evaluation value.
[0092] like Figure 4 As shown, further, at each preset time node, the steel box girder hoisting mass coefficient corresponding to each construction section is obtained, including:
[0093] S141. Construct a three-dimensional design model of each construction area in advance based on the design drawings of steel box girder assembly;
[0094] S142, obtaining a dimensional accuracy coefficient of the steel box girder that has completed hoisting construction based on the actual dimensional information of the steel box girder that has completed hoisting construction in each construction section and the design dimensional information of the steel box girder in the design drawing;
[0095] The dimensional accuracy coefficient of the steel box girder that has completed the hoisting construction is:
[0096]
[0097] in, is the dimensional accuracy coefficient of the steel box girder that has been hoisted and constructed in the i-th construction section at the j-th preset time node, L ijp , W ijp and H ijp are the actual length, actual width and actual height of the pth completed steel box girder at the jth preset time node of the i-th construction section, respectively. 0ijp , W 0ijp and H 0ijp are the design length, design width and design height of the pth steel box girder that has been completed for the i-th construction section at the j-preset time node, respectively; ΔL, ΔW and ΔH are the allowable design length error, design width error and design height error of the steel box girder, respectively; E is the number of steel box girders that have been completed for the i-th construction section at the j-preset time node, p=1,2…,E;
[0098] The actual size information of the steel box girder can be stored in advance before it leaves the factory. Since it needs to be tested and assembled before leaving the factory to meet the construction requirements, each steel box girder required for each construction section can be numbered, and the actual size information and design size information of the steel box girder with the corresponding number can be stored, so that the size accuracy coefficient of the steel box girder that has completed the hoisting construction can be obtained in advance; since the size of the steel box girder will affect its assembly effect, the size error of the steel box girder is also considered within the hoisting quality range of the steel box girder;
[0099] In the above formula, only the overall length, height and width of the steel box girder are used for calculation. In fact, all the measured dimensions of the steel box girder can be calculated using the above calculation method to obtain a more accurate dimensional accuracy coefficient;
[0100] S143, acquiring image data of the steel box girder hoisting of each construction section at each preset time node, identifying actual assembly position information of the steel box girder that has completed the hoisting construction in the image data, and obtaining the assembly position accuracy coefficient of the steel box girder that has completed the hoisting construction based on the actual assembly position information and the design assembly position information of the corresponding steel box girder in the design three-dimensional model;
[0101] The assembly position accuracy coefficient of the steel box girder that has completed the hoisting construction is:
[0102]
[0103] in, is the assembly position accuracy coefficient of the steel box girder that has been hoisted and constructed in the i-th construction section at the j-th preset time node, ε is the allowable error value of the assembly position of the steel box girder, and x ijp ,y ijp and z ijp are the actual coordinate values of the center of the p-th steel box girder that has been hoisted and constructed in the i-th construction section at the j-th preset time node on the x-axis, y-axis and z-axis of the spatial coordinate system, respectively. 0ijp ,y 0ijp and z 0ijp are the design coordinate values of the center of the p-th steel box girder that has been hoisted and constructed in the i-th construction section at the j-th preset time node on the x-axis, y-axis and z-axis of the space coordinate system, respectively, and e is a natural constant in mathematics;
[0104] During assembly, errors may occur due to the influence of various factors. Surveying and mapping technologies such as 3D laser scanning and digital point cloud can be used to establish a visual 3D vector solid model of the steel box girder. The 3D vector solid model can be compared and analyzed with the design 3D model or pre-established BIM model and other preliminary data to achieve automatic identification of 3D errors in on-site assembly of steel box girders, and to achieve real-time monitoring of on-site assembly accuracy and timely correction of errors.
[0105] The above steps are to obtain the actual assembly position of the steel box girder that has completed the hoisting construction, so as to obtain the error of its assembly position. The allowable error value of the assembly position of the steel box girder can be set, and then the assembly position accuracy coefficient of the steel box girder that has completed the hoisting construction can be obtained by the above calculation method. is the error between the actual space coordinates of the steel box girder and the designed space coordinates;
[0106] Since a large assembly error occurs in a steel box girder, the subsequent hoisted steel box girders will be affected, and the accumulation of errors will cause a large difference between the final bridge line shape and the design drawings. Therefore, the assembly position accuracy coefficient of each steel box girder that has completed the hoisting construction in each construction section is summed up here. The larger the error value between the actual space coordinates of the steel box girder and the design space coordinates, the lower the assembly position accuracy coefficient of the steel box girder that has completed the hoisting construction;
[0107] S144. Based on the actual size and actual assembly position information of the steel box girder that has completed the hoisting construction, construct an actual three-dimensional model of each construction section, and perform finite element analysis on the actual three-dimensional model to obtain actual structural strength information of the steel box girder that has completed the hoisting construction. Based on the actual structural strength information of the steel box girder that has completed the hoisting construction and the design structural strength information of the corresponding steel box girder in the design three-dimensional model, obtain the structural strength accuracy coefficient of the steel box girder that has completed the hoisting construction;
[0108] The structural strength accuracy coefficient of the steel box girder that has completed the hoisting construction is:
[0109]
[0110] in, is the structural strength accuracy coefficient of the steel box girder that has been hoisted and constructed in the i-th construction section at the j-th preset time node, μ is the strength influence coefficient corresponding to the structural strength error of the steel box girder, and its value is 0.2~0.9, σ ij and σ 0ij are the actual structural strength and the designed structural strength of the steel box girder that has been hoisted and constructed in the i-th construction section at the j-th preset time node;
[0111] In this step, the actual structure of the steel box girder that has been hoisted can be subjected to finite element analysis to obtain the actual structural strength of the steel box girder that has been hoisted, and then the structural strength accuracy coefficient of the steel box girder that has been hoisted can be obtained by calculating the above formula, |σ ij -σ 0ij | is the error value between the actual structural strength and the designed structural strength. The larger the error value is, the smaller the structural strength accuracy coefficient of the steel box girder that has completed the hoisting construction is;
[0112] S145, obtaining the steel box girder hoisting quality coefficient of each construction section according to the dimensional accuracy coefficient, assembly position accuracy coefficient and structural strength accuracy coefficient of the steel box girder that has completed hoisting construction;
[0113] The mass coefficient of steel box girder hoisting in each construction section is:
[0114]
[0115] in, is the mass coefficient of steel box girder hoisting at the jth preset time node of the i-th construction section, exp() is an exponential function with e as the base, ω A ,ω B And ω C They are the weight values corresponding to the dimensional accuracy coefficient, assembly position accuracy coefficient and structural strength accuracy coefficient of the steel box girder that has completed the hoisting construction;
[0116] In this step, the weight values of the size accuracy coefficient, assembly position accuracy coefficient and structural strength accuracy coefficient of the steel box girder that has completed the hoisting construction are pre-set, and then the steel box girder hoisting quality coefficient of each construction section can be calculated using the above formula. The higher the value of each accuracy coefficient, the higher the final hoisting quality coefficient of the steel box girder of each construction section, indicating that the hoisting quality is better.
[0117] Through the above method, the influence of the size, assembly position and structural strength of the steel box girder that has completed the hoisting construction on the hoisting quality of the steel box girder is fully considered, thereby obtaining a more accurate steel box girder hoisting quality coefficient for each construction section.
[0118] Furthermore, the steel box girder assembly accuracy evaluation coefficient of each construction section is:
[0119]
[0120] Among them, Q ij is the steel box girder assembly accuracy evaluation coefficient of the i-th construction section at the j-th preset time node, and They are respectively the steel box girder hoisting mass coefficient of the i-th construction section at the j-th preset time node and the preset steel box girder hoisting mass coefficient.
[0121] Quality coefficient of steel box girder hoisting in each construction section The larger the value is, the higher the steel box girder assembly accuracy is, and the larger the relative steel box girder assembly accuracy evaluation coefficient is; When , it indicates that the steel box girder hoisting quality coefficient does not reach the preset steel box girder hoisting quality coefficient, then Q ij The value of is small, When , it indicates that the steel box girder hoisting quality coefficient has reached or exceeded the preset steel box girder hoisting quality coefficient, then Q ij The value of is 1.
[0122] In one embodiment, it also includes: analyzing the construction section to be managed, and selecting the one with the greatest impact on the lifting efficiency evaluation value as the priority management target among the wind speed impact evaluation coefficient of the construction section's environment, the lifting construction progress evaluation coefficient, and the steel box girder assembly accuracy evaluation coefficient.
[0123] Analyze the selected construction sections to be managed, analyze the wind speed impact evaluation coefficient of the environment where the construction section is located, the hoisting construction progress evaluation coefficient and the steel box girder assembly accuracy evaluation coefficient, to determine which one has the greatest impact on the hoisting efficiency judgment value, and then take it as the priority management target. For example, if the wind speed impact evaluation coefficient of the environment has the greatest impact on the hoisting efficiency judgment value, relevant technical personnel can be deployed to analyze the on-site conditions of the construction section to be managed or deploy machinery used to stabilize the swing amplitude of the steel box girder to the construction section to be managed, so as to solve the problems found in time and ensure construction efficiency.
[0124] like Figure 5 As shown, an intelligent management system for steel box girder hoisting construction includes:
[0125] An acquisition module is used to acquire the hoisting construction information corresponding to each construction section at multiple preset time nodes, wherein the steel box girder hoisting construction area is divided into multiple construction sections;
[0126] The evaluation and judgment module obtains the hoisting efficiency evaluation value corresponding to each construction section at each preset time node based on the hoisting construction information, and judges whether the hoisting efficiency evaluation value meets the set standard;
[0127] A screening module is used to screen the construction sections corresponding to the hoisting efficiency evaluation values that do not meet the set standards as the construction sections to be managed;
[0128] The hoisting construction information includes: the wind speed impact evaluation coefficient of the environment where the construction section is located, the hoisting construction progress evaluation coefficient and the steel box girder assembly accuracy evaluation coefficient;
[0129] Among them, the lifting efficiency evaluation value corresponding to each construction section at each preset time node is:
[0130] α ij =β Q *Q ij -β F *F ij +β D D ij
[0131] Among them, α ij is the lifting efficiency evaluation value of the i-th construction section at the j-th preset time node, Q ij is the steel box girder assembly accuracy evaluation coefficient of the i-th construction section at the j-th preset time node, F ij is the wind speed impact evaluation coefficient of the environment where the i-th construction section is located at the j-th preset time node, D ij is the evaluation coefficient of the hoisting construction progress of the i-th construction section at the j-th preset time node, β Q , β F and β D For ij 、F ij and D ij The corresponding weight value.
[0132] Furthermore, the acquisition module includes:
[0133] An acquisition unit, which acquires wind speed data of the environment corresponding to each construction section, a proportion of the completed construction length corresponding to the current construction time, and a steel box girder hoisting quality coefficient at each preset time node;
[0134] The first calculation unit obtains the wind speed impact evaluation coefficient of the environment where each construction section is located according to the wind speed data of the environment and the critical wind speed of the hoisting;
[0135] The second calculation unit obtains the hoisting construction progress evaluation coefficient of each construction section according to the actual completed construction length ratio corresponding to the current construction time and the preset completed construction length ratio;
[0136] The third calculation unit obtains the steel box girder assembly accuracy evaluation coefficient of each construction section according to the steel box girder hoisting quality coefficient and the preset steel box girder hoisting quality coefficient.
[0137] Equipment and image acquisition equipment that can obtain wind speed in the environment can be installed at the construction site of each construction section. Surveying and mapping technologies such as 3D laser scanning and digital point cloud can be used and transmitted to the general management platform in real time to obtain the hoisting construction information of each construction section and realize overall management.
[0138] The acquisition module includes equipment and image acquisition equipment installed at the construction site of each construction section that can obtain the wind speed of the environment, and can realize remote transmission of data; the evaluation and judgment module can transmit data from the sub-management platform to the general management platform at the sub-management platform of each construction section, or the acquisition module directly transmits data to the general management platform, and then screens it through the screening module of the general management platform to determine whether it is a construction section to be managed;
[0139] The steel box girder hoisting construction area is the total length area of the bridge to be built, which is divided into multiple construction sections for the convenience of segmented construction. The time node for collecting the hoisting construction information corresponding to each construction section can be set. For example, the bridge construction requires N days, and N days are evenly divided into 50 preset time nodes. The hoisting construction information corresponding to each construction section will be obtained at each preset time node, so as to ensure that all construction sections are managed in sections during the entire construction period, and the construction status of each construction section is obtained in time. Moreover, after processing the hoisting construction information of each construction section, the corresponding hoisting efficiency judgment value can be obtained. A setting standard corresponding to the hoisting efficiency judgment value can be set to judge the construction status of each construction section at the preset time node. If a construction section is screened out, it means that its construction has encountered difficulties. In this way, it is managed according to its actual situation, such as the deployment of personnel and machinery, so that problems can be discovered and solved in time to improve the construction efficiency of each construction section.
[0140] Although the embodiments of the present invention have been disclosed as above, they are not limited to the applications listed in the specification and the implementation methods. They can be fully applied to various fields suitable for the present invention. For those familiar with the art, additional modifications can be easily implemented. Therefore, without departing from the general concept defined by the claims and the scope of equivalents, the present invention is not limited to the specific details and the illustrations shown and described herein.
Claims
1. An intelligent management method for steel box girder hoisting construction, characterized in that: include: Divide the steel box girder hoisting construction area into multiple construction sections, and obtain the hoisting construction information corresponding to each construction section at multiple preset time nodes; According to the hoisting construction information, obtain the hoisting efficiency evaluation value corresponding to each construction section at each preset time node, and judge whether the hoisting efficiency evaluation value meets the set standard; Select the construction sections corresponding to the hoisting efficiency evaluation values that do not meet the set standards as the construction sections to be managed; The hoisting construction information includes: the wind speed impact evaluation coefficient of the environment where the construction section is located, the hoisting construction progress evaluation coefficient and the steel box girder assembly accuracy evaluation coefficient; Among them, the lifting efficiency evaluation value corresponding to each construction section at each preset time node is: in, For the The construction section is in The lifting efficiency evaluation value of the preset time node, For the The construction section is in The steel box girder assembly accuracy evaluation coefficient at a preset time node, For the The construction section is in The wind speed impact evaluation coefficient of the environment at the preset time node, For the The construction section is in The evaluation coefficient of the hoisting construction progress at the preset time node, , as well as For , as well as The corresponding weight value; Obtain the hoisting construction information corresponding to each construction section at multiple preset time nodes, including: At each preset time node, obtain the wind speed data of the environment corresponding to each construction section, the proportion of completed construction length corresponding to the current construction time, and the steel box girder hoisting quality coefficient; According to the wind speed data of the environment and the critical wind speed of hoisting, the wind speed impact evaluation coefficient of the environment of each construction section is obtained; According to the actual completed construction length ratio corresponding to the current construction time and the preset completed construction length ratio, the hoisting construction progress evaluation coefficient of each construction section is obtained; According to the steel box girder hoisting quality coefficient and the preset steel box girder hoisting quality coefficient, the steel box girder assembly accuracy evaluation coefficient of each construction section is obtained; At each preset time node, the steel box girder hoisting mass coefficient corresponding to each construction section is obtained, including: Construct the 3D design model of each construction area in advance according to the design drawings of steel box girder assembly; According to the actual size information of the steel box girder that has been hoisted and constructed in each construction section and the design size information of the steel box girder in the design drawings, the size accuracy coefficient of the steel box girder that has been hoisted and constructed is obtained; The dimensional accuracy coefficient of the steel box girder that has completed the hoisting construction is: in, For the The construction section is in The dimensional accuracy coefficient of the steel box girder that has been hoisted and constructed at a preset time node, , as well as Respectively The construction section is in The first time node is obtained The actual length, width and height of the steel box girder that has been hoisted. , as well as Respectively The construction section is in The first time node is obtained The design length, width and height of the steel box girder that has been hoisted and installed. , as well as They are the allowable design length error, design width error and design height error of the steel box girder. For the The construction section is in The number of steel box girders that have completed hoisting construction at the preset time node, ; At each preset time node, image data of the steel box girder hoisting of each construction section is obtained, actual assembly position information of the steel box girder that has completed the hoisting construction in the image data is identified, and according to the actual assembly position information and the design assembly position information of the corresponding steel box girder in the design three-dimensional model, the assembly position accuracy coefficient of the steel box girder that has completed the hoisting construction is obtained; The assembly position accuracy coefficient of the steel box girder that has completed the hoisting construction is: in, For the The construction section is in The assembly position accuracy coefficient of the steel box girder that has completed the hoisting construction at a preset time node, is the allowable error value of the assembly position of the steel box girder, , as well as Respectively The construction section is in The first time node is obtained The center of the steel box girder that has been hoisted is in the spatial coordinate system. axis, Axis and The actual coordinate value on the axis, , as well as Respectively The construction section is in The first time node is obtained The center of the steel box girder that has been hoisted is in the spatial coordinate system. axis, Axis and Design coordinate values on the axis, is a natural constant in mathematics; According to the actual size and actual assembly position information of the steel box girder that has been hoisted, an actual three-dimensional model of each construction section is constructed, and finite element analysis is performed on the actual three-dimensional model to obtain the actual structural strength information of the steel box girder that has been hoisted. According to the actual structural strength information of the steel box girder that has been hoisted and the design structural strength information of the corresponding steel box girder in the design three-dimensional model, the structural strength accuracy coefficient of the steel box girder that has been hoisted is obtained; The structural strength accuracy coefficient of the steel box girder that has completed the hoisting construction is: in, For the The construction section is in The structural strength accuracy coefficient of the steel box girder that has been hoisted and constructed at a preset time node, is the strength influence coefficient corresponding to the strength error of the steel box girder structure, and its value is 0.2~0.
9. and Respectively The construction section is in The actual structural strength and designed structural strength of the steel box girder that has been hoisted and constructed at a preset time node; According to the dimensional accuracy coefficient, assembly position accuracy coefficient and structural strength accuracy coefficient of the steel box girder that has been hoisted, the hoisting quality coefficient of the steel box girder in each construction section is obtained; The mass coefficient of steel box girder hoisting in each construction section is: in, For the The construction section is in The mass coefficient of steel box girder hoisting at a preset time node, For The exponential function with base , , as well as They are the weight values corresponding to the dimensional accuracy coefficient, assembly position accuracy coefficient and structural strength accuracy coefficient of the steel box girder that has completed the hoisting construction; The steel box girder assembly accuracy evaluation coefficient for each construction section is: in, For the The construction section is in The steel box girder assembly accuracy evaluation coefficient at a preset time node, and Respectively The construction section is in The steel box girder hoisting mass coefficient at a preset time node and the preset steel box girder hoisting mass coefficient.
2. The intelligent management method for steel box girder hoisting construction according to claim 1 is characterized in that: The determination of the critical wind speed of each construction section in the environment includes: Construct a finite element model of the entire process of steel box girder hoisting in each construction section. According to the analysis results of the finite element model, formulate a hoisting construction plan for the steel box girder in each construction section. Each construction section hoists the steel box girder according to the corresponding hoisting construction plan. Among them, the lifting construction plan includes: the critical wind speed of the environment where the construction section is located.
3. The intelligent management method for steel box girder hoisting construction according to claim 1 is characterized in that: At each preset time node, the wind speed data of the environment corresponding to each construction section is obtained, and based on the wind speed data of the environment and the critical wind speed of the hoisting, the wind speed impact evaluation coefficient of the environment of each construction section is obtained, including: Acquire the wind speed of the environment corresponding to each construction section at multiple collection times between the current preset time node and the previous preset time node to form wind speed data of the environment; According to the corresponding wind speed of the environment at multiple collection moments and the critical wind speed of hoisting, the wind speed impact evaluation coefficient of the environment of each construction section at the current preset time node is obtained.
4. The intelligent management method for steel box girder hoisting construction according to claim 1 is characterized in that: At each preset time node, the actual completed construction length ratio of each construction section corresponding to the current construction time is obtained, including: At each preset time node, the actual completed construction length and the total length of the construction section corresponding to each construction section and the current construction time are obtained to obtain the proportion of the actual completed construction length.
5. The intelligent management method for steel box girder hoisting construction according to claim 1 is characterized in that: Also includes: An analysis is conducted on the construction section to be managed, and among the wind speed impact evaluation coefficient of the construction section's environment, the hoisting construction progress evaluation coefficient, and the steel box girder assembly accuracy evaluation coefficient, the one that has the greatest impact on the hoisting efficiency evaluation value is selected as the priority management target.
6. An intelligent management system for steel box girder hoisting construction, adopting the intelligent management method for steel box girder hoisting construction according to claim 1, characterized in that: include: An acquisition module is used to acquire the hoisting construction information corresponding to each construction section at multiple preset time nodes, wherein the steel box girder hoisting construction area is divided into multiple construction sections; The evaluation and judgment module obtains the hoisting efficiency evaluation value corresponding to each construction section at each preset time node based on the hoisting construction information, and judges whether the hoisting efficiency evaluation value meets the set standard; A screening module is used to screen the construction sections corresponding to the hoisting efficiency evaluation values that do not meet the set standards as the construction sections to be managed; The hoisting construction information includes: the wind speed impact evaluation coefficient of the environment where the construction section is located, the hoisting construction progress evaluation coefficient and the steel box girder assembly accuracy evaluation coefficient; Among them, the lifting efficiency evaluation value corresponding to each construction section at each preset time node is: in, For the The construction section is in The lifting efficiency evaluation value of the preset time node, For the The construction section is in The steel box girder assembly accuracy evaluation coefficient at a preset time node, For the The construction section is in The wind speed impact evaluation coefficient of the environment at the preset time node, For the The construction section is in The evaluation coefficient of the hoisting construction progress at the preset time node, , as well as For , as well as The corresponding weight value.
7. The intelligent management system for steel box girder hoisting construction according to claim 6 is characterized in that: The acquisition module comprises: An acquisition unit, which acquires wind speed data of the environment corresponding to each construction section, a proportion of the completed construction length corresponding to the current construction time, and a steel box girder hoisting quality coefficient at each preset time node; The first calculation unit obtains the wind speed impact evaluation coefficient of the environment where each construction section is located according to the wind speed data of the environment and the critical wind speed of the hoisting; The second calculation unit obtains the hoisting construction progress evaluation coefficient of each construction section according to the actual completed construction length ratio corresponding to the current construction time and the preset completed construction length ratio; The third calculation unit obtains the steel box girder assembly accuracy evaluation coefficient of each construction section according to the steel box girder hoisting quality coefficient and the preset steel box girder hoisting quality coefficient.