A hydropower data analysis, evaluation and early warning system and method based on digital twins
By constructing functional relationships and thresholds between power production, water level and water quality in hydropower stations, combined with digital twin models and machine learning, real-time monitoring and optimization of multi-faceted anomalies in hydropower stations are achieved, solving the problems of various early warning processing in hydropower stations, and improving improve operational efficiency and safety.
Patent Information
- Application Number
- CN202410757359.7
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2024-06-13
- Publication Date
- 2024-10-15
- Estimated Expiration
- 2044-06-13
AI Technical Summary
In hydropower stations, due to the impact of various data on normal work, there may be multiple early warnings and decisions in intelligent early warnings and decisions. The impact of different early warnings cannot be reasonably processed, resulting in the inability to effectively monitor and optimize the operation of the hydropower station.
By collecting electricity production, water level and water quality data of hydropower stations, we construct the electricity production-flow rate function, water level-flow rate function and water quality-flow rate function, calculate the corresponding thresholds, and use the digital twin model for real-time monitoring and early warning, combined with machine learning algorithms Build a judgment and early warning model to adjust the water flow rate in real time to solve abnormal problems.
It realizes real-time early warning and optimization of various abnormalities in hydropower stations to ensure the normal operation of hydropower stations. It solves various abnormal problems by adjusting water flow velocity parameters and improves the operating efficiency and safety of hydropower stations.
Smart Images

Figure CN118333791B_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of digital twins, and in particular to a hydropower data analysis, evaluation and early warning system and method based on digital twins. Background Art
[0002] With the advent of computers, computer languages have played a vital role in the development of science and technology. Computer languages are present in many aspects of life. Among them, digital twin models play a vital role in many fields. Digital twin models can simulate and predict the behavior of physical systems in real time. This allows dynamic monitoring of the operation of the actual system, timely detection of potential problems and prediction, which helps to improve the efficiency and safety of the system. It can be used to optimize system performance, improve efficiency and reduce energy consumption by adjusting parameters. In addition, digital twin technology provides model-based decision support to help make more informed decisions and operation strategies. The use of digital twin technology in hydropower stations can monitor and optimize the operating status of hydropower stations in real time. Through digital twin models, the performance of hydropower stations under different operating conditions can be simulated, the response of the system can be predicted, and real-time optimization suggestions can be provided to maximize the efficiency and economy of power generation. Digital twin models can be used for fault diagnosis and predicting maintenance needs. By simulating the working status of hydropower station equipment, potential signs of failure can be detected in time, and maintenance suggestions can be provided to reduce downtime and repair costs. When using digital twin technology to conduct real-time data monitoring of hydropower stations, since there are various data in the hydropower station that affect the normal operation of the hydropower station, there may be multiple warnings and decisions each time in the intelligent early warning and decision-making, but different warnings have different impacts on the hydropower station, so it is impossible to reasonably handle multiple abnormal warnings of the hydropower station; therefore, the present invention proposes a hydropower data analysis, evaluation and early warning system and method based on digital twins. Summary of the invention
[0003] The purpose of the present invention is to provide a hydropower data analysis, evaluation and early warning system and method based on digital twins to solve the problems raised in the above background technology.
[0004] In order to solve the above technical problems, the present invention provides the following technical solutions:
[0005] A hydropower data analysis, evaluation and early warning method based on digital twins, the method comprising the following steps:
[0006] S100, collecting various data in the hydropower station, respectively constructing a power output-flow velocity function, a water level-flow velocity function and a water quality-flow velocity function, and calculating a power output threshold, a water level threshold and a water quality threshold of the hydropower station;
[0007] Furthermore, the specific steps for calculating the power output threshold of the hydropower station and constructing the power output-flow rate function are as follows:
[0008] S101. Collect the historical electricity production data of the hydropower station: , is the 1st, 2nd, 3rd, ...sth electricity production data collected in history, s is a positive integer; the water flow velocity data corresponding to each electricity production data collected is , is the 1st, 2nd, 3rd, ...sth water flow velocity data corresponding to each collected electricity production data, s is a positive integer;
[0009] S102, using the collected electricity production data and the corresponding water flow velocity data to draw an electricity production-flow velocity curve, and using the segmentation method to calculate the functional relationship in the curve: , where Q is the electricity production data, is the corresponding relationship between electricity production and water flow rate;
[0010] S103, performing a derivative operation on the calculated function, and obtaining the function derivative relationship in the curve graph as follows: , is the relationship function between the rate of change of electricity production and the flow velocity, is the rate of change of electricity production;
[0011] S104, analyzing the calculated function derivative relationship, determining when When , it is proved that the electricity output of the hydropower station decreases. The derivative values of the function are judged and the derivative values of all the electricity output decreases are collected and obtained as follows: , To determine the derivative value of the 1st, 2nd, 3rd...nth electricity production reduction, n is a positive integer, and n <s;
[0012] S105, averaging the calculated n derivative values, the formula is:
[0013]
[0014] In the formula, is the average value of the derivative value when the electricity production is reduced. is the derivative value when the electricity production decreases, ; The average value of the derivative value of the calculated electricity production minus the hour The threshold value of electricity production of hydropower station is set.
[0015] According to the above method, the power output threshold of the hydropower station is calculated, and the power output of the hydropower station can be judged according to the power output threshold. When the power output of the hydropower station is low, an early warning is issued to allow the operation and maintenance personnel to adjust the equipment parameters to increase the power output;
[0016] Furthermore, the specific steps for calculating the water level threshold of the hydropower station and constructing the water level-flow rate function are as follows:
[0017] S121. Collect water level data at each equipment failure in the history of the hydropower station, specifically: , The water level data collected at the 1st, 2nd, 3rd...mth equipment failures, m is a positive integer; and the water flow velocity data at different water levels in the hydropower station are collected, specifically , is the water flow data collected at the 1st, 2nd, 3rd...bth water levels, where b is a positive integer;
[0018] S122, using the collected water level data and the water flow velocity data at different water levels to draw a water level-flow velocity curve, and using the segmentation method to calculate the functional relationship in the curve: , where W is the different water level data in the history of the hydropower station, is the correspondence between water level data and water flow velocity;
[0019] S123. Calculate the average water level data of the hydropower station equipment failure in history. The formula is:
[0020]
[0021] In the formula, To calculate the average water level data of hydropower station equipment failure in history, is the water level data of each equipment failure in the history of the hydropower station, ; The average water level data of the hydropower station equipment failure in history will be calculated Set as the water level threshold of the hydropower station.
[0022] The water level in a hydropower station is an important factor affecting the operation of the hydropower station. When the water level of the hydropower station is too high, it may cause abnormalities in the power generation equipment of the hydropower station, resulting in failure to work normally; and when the water level is too high, it may also cause floods and waterlogging disasters. Therefore, real-time monitoring of the water level of the hydropower station can effectively protect the normal operation and safety of the hydropower station;
[0023] Furthermore, the specific steps for calculating the water quality threshold of the hydropower station and constructing the water quality-flow rate function are as follows:
[0024] S131. Collect water quality data for each equipment failure in the history of the hydropower station, specifically: , is the water quality data of the 1st, 2nd, 3rd...mth equipment failure in the history of the hydropower station, where m is a positive integer; and the water flow velocity data of the hydropower station with different water quality data is collected, specifically: , is the water flow velocity data collected for the 1st, 2nd, 3rd...ath water quality data of the hydropower station, where a is a positive integer;
[0025] S132, using the collected water quality data of the hydropower station and the water flow velocity data at different water qualities to draw a water quality-flow velocity curve, and using the segmentation method to calculate the functional relationship in the curve: , where Z is the different water quality data in the history of the hydropower station, is the correspondence between water quality data and water flow velocity;
[0026] S133. Calculate the average water quality data of hydropower station equipment failures in history using the formula:
[0027]
[0028] In the formula, To calculate the average water quality data of hydropower station equipment failures in history, is the water quality data of each equipment failure in the history of the hydropower station, ; The average water quality data of the hydropower station equipment failure in history will be calculated Set as the water quality threshold for hydropower stations.
[0029] The water quality data in the hydropower station includes the silt, impurities, mixtures and stones in the water. When there is too much water quality and silt in the hydropower station, it may damage the power generation equipment of the hydropower station and make the hydropower station unable to work normally. Therefore, calculating the water quality data in the hydropower station and judging the real-time water quality data can effectively reduce the probability of damage to the power generation equipment and ensure the normal operation of the hydropower station;
[0030] S200, collect physical data of the hydropower station, build a digital twin model, and use the digital twin model to monitor the hydropower station in real time;
[0031] Furthermore, the specific steps to build a digital twin model are:
[0032] S201, collect all physical data of the hydropower station, including hydropower station size, water pressure, water flow velocity, meteorological data, terrain data and equipment data;
[0033] S202, using the collected data to perform 3D modeling of the hydropower station, and constructing a digital twin hydropower station based on the physical hydropower station;
[0034] S203. After constructing the digital twin hydropower station of the hydropower station, the three functional relationships of the calculated power output-flow velocity function, the water level-flow velocity function, and the water quality-flow velocity function and the three thresholds of the power output threshold, the water level threshold, and the water quality threshold are input into the digital twin hydropower station, and a judgment and early warning model of the digital twin hydropower station is constructed using a machine learning algorithm;
[0035] S204. After constructing the judgment and early warning model of the digital twin hydropower station, the power output, water quality and water level data in the hydropower station are monitored in real time, and abnormal conditions of the hydropower station are warned based on the constructed judgment and early warning model.
[0036] In the power generation work of hydropower stations, because the hydropower station is large in scale and there are many factors affecting the normal operation of the hydropower station, it is inconvenient to monitor the hydropower station in real time. Therefore, digital twin technology is used to establish a 3D digital twin hydropower station model. The model can be used to realize real-time monitoring of the hydropower station and ensure the normal operation of the hydropower station;
[0037] S300, using the digital twin model to collect flow velocity data of the hydropower station in real time, and judging and warning the real-time data of the hydropower station according to the three threshold data calculated in S100;
[0038] Furthermore, the specific steps for judging and warning the real-time data of the hydropower station are as follows:
[0039] S301. Real-time monitoring and collection of water flow velocity in hydropower stations According to the calculated electricity production-flow rate function, water level-flow rate function and water quality-flow rate function, the corresponding real-time electricity production, water level and water quality data are calculated respectively. The formula is:
[0040]
[0041]
[0042]
[0043] in the formula To calculate the real-time electricity production data, The real-time water level data is calculated. Real-time water quality data calculated;
[0044] S302, when When the power output of the hydropower station changes abnormally, it is judged that the power output change speed is abnormal and an abnormal power output warning is issued; on the contrary, when The hydropower station operates normally.
[0045] S303, when When the risk of equipment failure in the hydropower station is determined, an equipment failure warning is issued; on the contrary, when The hydropower station operates normally.
[0046] S304, when When the risk of equipment failure in the hydropower station is determined, an equipment failure warning is issued; on the contrary, when The hydropower station operates normally.
[0047] S400, after monitoring and warning the real-time data, assess the risk of each warning respectively, and classify the warning according to the assessment results;
[0048] Furthermore, the specific steps for evaluating the risk of each warning are as follows:
[0049] S401, collect the total number of equipment failures in the history of the hydropower station as H, extract the number of failures caused by the water level exceeding the water level threshold from the H equipment failures as J, extract the number of failures caused by the water quality exceeding the water quality threshold from the H equipment failures as K, collect the number of power supply anomalies of the hydropower station due to the change rate of electricity output being less than the electricity output threshold in the history of the hydropower station as Y, and collect the number of all power supply anomalies in the history as D;
[0050] S402. Conduct risk assessment on the three types of warnings respectively, the formula is:
[0051]
[0052]
[0053]
[0054] In the formula, To calculate the probability of abnormality after water level warning, To calculate the probability of abnormality after water quality warning, To calculate the probability of abnormality after the power production warning;
[0055] S403. The calculated probabilities of abnormalities occurring after the three warnings are used as the risk assessment values of the corresponding warnings. The three calculated probabilities are sorted, and the three warnings are graded according to the order from large to small. The one with the highest calculated probability of abnormality occurring is the highest level, and then it is downgraded in sequence according to the probability order.
[0056] S500, analyzing adjustment parameters of water flow velocity according to the early warning result of the hydropower station and the three functions obtained by calculation;
[0057] Furthermore, the specific steps of calculating the adjustment parameters of the water flow velocity according to the early warning results of the hydropower station and the three calculated functions are as follows:
[0058] S501. When the digital twin hydropower station issues three warnings, the three threshold data of the hydropower station are respectively input into the three functions obtained by calculation to form three equations, specifically:
[0059]
[0060]
[0061]
[0062] According to the above three equations, we can calculate the solution set A1 of three functions: 、A2: and A3: , there is at least one solution in each set;
[0063] S502, subtract the calculated solutions in the three sets from the real-time collected water flow velocity of the hydropower station, and the formula is:
[0064]
[0065] In the formula, To calculate the water flow rate adjustment parameters that need to be changed after the power production warning is issued, i takes a value from 1 to u; finally, u water flow rate adjustment parameters that need to be changed after the power production warning is issued are calculated, and the difference with the smallest value is selected. As a water flow rate adjustment parameter that needs to be changed after the power production warning is issued;
[0066] S503. According to the same method as above, two water flow rate adjustment parameters that need to be changed after the water level and water quality warnings in the equipment failure reminder are issued are calculated. The formula is:
[0067]
[0068]
[0069] In the formula, In order to calculate the water flow rate adjustment parameters that need to be changed after the equipment failure warning is issued due to abnormal water level, In order to calculate the water flow rate adjustment parameters that need to be changed after the equipment failure warning is issued due to abnormal water quality, is the water flow velocity corresponding to the water level threshold; are the water flow velocities corresponding to the water quality thresholds;
[0070] S504. When three different warnings are finally calculated according to the above steps, the theoretical water flow velocity adjustment parameters calculated to eliminate the warnings are as follows: , , .
[0071] S600, comprehensively analyzing each issued warning and water flow velocity adjustment parameter, obtaining final water flow velocity adjustment data and verifying it, and then outputting the final water flow velocity adjustment parameter that is greater than the threshold after adjustment as a reference value.
[0072] Furthermore, the specific steps for conducting a comprehensive analysis of each warning and water flow rate adjustment parameter are as follows:
[0073] When only one of the three types of warnings is issued in the hydropower station, the final water flow velocity adjustment parameter of the hydropower station is the water flow velocity adjustment parameter corresponding to the type of warning issued, specifically: or or ;
[0074] When any two of the three warnings are issued in the hydropower station, a situation analysis is conducted:
[0075] When the water flow velocity adjustment parameters calculated for the two warnings issued have the same sign, compare the water flow velocity adjustment parameters calculated for the two warnings, and select the larger water flow velocity adjustment parameter as the final water flow velocity adjustment parameter. ;
[0076] When the water flow velocity adjustment parameters calculated for the two warnings issued have different signs, the water flow velocity adjustment parameters corresponding to the warning type with the higher level are selected as the final water flow velocity adjustment parameters of the hydropower station according to the levels of the two warnings calculated in S400. ;
[0077] When a hydropower station issues three types of warnings, analysis is conducted based on the situation:
[0078] When the water flow velocity adjustment parameters corresponding to the three warnings are of the same sign, the water flow velocity adjustment parameters calculated corresponding to the three warnings are compared, and the largest water flow velocity adjustment parameter is selected as the final water flow velocity adjustment parameter. ;
[0079] When any two of the water flow velocity adjustment parameters corresponding to the three warnings have different signs, the abnormal occurrence probability of the warnings corresponding to the two water flow velocity adjustment parameters with the same sign is added together to obtain 1, add the value obtained 1 The probability of abnormal occurrence of the warning corresponding to the water flow velocity adjustment parameter with the last different sign 2 for comparison, when 1> 2, the final flow velocity adjustment parameter of the hydropower station is the larger value of the two adjustment parameters with the same sign. 1< 2, the final water flow velocity adjustment parameter of the hydropower station is the only water flow velocity adjustment parameter with a different sign;
[0080] After calculating the final water flow velocity adjustment parameters according to different situations, the adjustment parameters are input into the digital twin model, and the adjusted water flow velocity is calculated using the formula:
[0081]
[0082] In the formula, Using the water flow velocity adjusted by the digital twin model, the adjusted water flow velocity is brought into the three functional relationships in the digital twin model to calculate the corresponding power generation, water level and water quality data. The three data calculated after adjusting the water flow velocity are compared with the corresponding power generation threshold, water level threshold and water quality threshold. When the warning data corresponding to the selected water flow velocity adjustment parameter is greater than its threshold in different warning situations, it is proved that the selected final adjustment parameter can optimize the early warning problem. The final water flow velocity adjustment parameter that has passed the verification is set to 1. The final water flow rate adjustment parameter that does not pass is ;
[0083] After verification, the water flow rate adjustment parameters 1 output, adjust the water flow rate parameter 1 As a reference value for operation and maintenance personnel to maintain the hydropower station, verify the flow rate adjustment parameters that do not pass To discard.
[0084] A hydropower data analysis, evaluation and early warning system based on digital twins, the hydropower data analysis, evaluation and early warning system comprising a threshold calculation module, a function calculation module, a digital twin model construction module, an early warning module, a comprehensive analysis module and a parameter output module;
[0085] The threshold calculation module is used to analyze the electricity production, equipment failure, water level and water quality data collected in the history of the hydropower station to calculate the electricity production threshold, water level threshold and water quality threshold;
[0086] The function calculation module is used to collect the electricity output, flow rate, water level and water quality data in the history of the hydropower station to calculate and draw curves, and obtain three functional relationships: electricity output-flow rate function, water level-flow rate function, and water quality-flow rate function;
[0087] The digital twin model building module is used to collect physical data of the hydropower station and build a digital twin model of the hydropower station through 3D modeling and machine learning technology;
[0088] The early warning module is used to collect the power output, water level and water quality data of the hydropower station in real time using the digital twin model, and to judge the real-time data and issue corresponding early warnings;
[0089] The comprehensive analysis module is used to perform proportional calculation on the three water flow velocity adjustment parameters calculated after the early warning, and calculate the final water flow velocity adjustment parameters;
[0090] The parameter output module is used to calculate the final adjustment parameters of the water flow rate, and then transmit the adjustment parameters of the water flow rate to the operation and maintenance personnel to adjust the real-time water flow rate.
[0091] The early warning module is used to determine whether the three real-time data of electricity production, water level and water quality are abnormal, and then calculate the difference between the real-time water flow velocity and the threshold water flow velocity corresponding to each early warning according to the three functional relationships of electricity production-flow velocity function, water level-flow velocity function and water quality-flow velocity function, and obtain the adjustment parameters for the real-time water flow velocity after issuing each different early warning.
[0092] Compared with the prior art, the beneficial effects achieved by the present invention are:
[0093] 1. The present invention collects and analyzes the data of electricity output, water level and water quality in the hydropower station, and obtains the threshold values of the three data for the normal operation of the hydropower station, so that in the real-time monitoring of the hydropower station, early warning of abnormalities of the hydropower station can be given in many aspects to ensure the normal operation of the hydropower station.
[0094] 2. The present invention calculates three functional relationships, namely, power generation-flow velocity function, water level-flow velocity function, and water quality-flow velocity function, based on historical hydropower station data. When the hydropower station issues multiple warnings, the adjustment parameters of the same data, namely, water flow velocity, can be calculated according to different functional relationships, thereby achieving the solution to various abnormal problems of the hydropower station by adjusting one data.
[0095] 3. After issuing multiple warnings, the present invention calculates multiple adjustment parameters of water flow velocities based on the multiple warnings. However, since the water flow velocity has different effects on each data, they cannot all be adjusted. The present invention implements a comprehensive analysis of the multiple adjustment parameters to obtain the final adjustment parameters of the water flow velocity. BRIEF DESCRIPTION OF THE DRAWINGS
[0096] The accompanying drawings are used to provide a further understanding of the present invention and constitute a part of the specification. Together with the embodiments of the present invention, they are used to explain the present invention and do not constitute a limitation of the present invention. In the accompanying drawings:
[0097] Figure 1 It is a module distribution diagram of a hydropower data analysis, evaluation and early warning system based on digital twins of the present invention;
[0098] Figure 2 It is a schematic diagram of the steps of a hydropower data analysis, evaluation and early warning method based on digital twins of the present invention. DETAILED DESCRIPTION
[0099] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0100] See also Figure 1-Figure 2 , the present invention provides a technical solution:
[0101] A hydropower data analysis, evaluation and early warning method based on digital twins, the method comprising the following steps:
[0102] S100, collecting various data in the hydropower station, respectively constructing a power output-flow velocity function, a water level-flow velocity function and a water quality-flow velocity function, and calculating a power output threshold, a water level threshold and a water quality threshold of the hydropower station;
[0103] The specific steps to calculate the power generation threshold of the hydropower station and construct the power generation-flow rate function are as follows:
[0104] S101. Collect the historical electricity production data of the hydropower station: , is the 1st, 2nd, 3rd, ...sth electricity production data collected in history, s is a positive integer; the water flow velocity data corresponding to each electricity production data collected is , is the 1st, 2nd, 3rd, ...sth water flow velocity data corresponding to each collected electricity production data, s is a positive integer;
[0105] S102, using the collected electricity production data and the corresponding water flow velocity data to draw an electricity production-flow velocity curve, and using the segmentation method to calculate the functional relationship in the curve: , where Q is the electricity production data, is the corresponding relationship between electricity production and water flow rate;
[0106] S103, performing a derivative operation on the calculated function, and obtaining the function derivative relationship in the curve graph as follows: , is the relationship function between the rate of change of electricity production and the flow velocity, is the rate of change of electricity production;
[0107] S104, analyzing the calculated function derivative relationship, determining when When , it is proved that the electricity output of the hydropower station decreases. The derivative values of the function are judged and the derivative values of all the electricity output decreases are collected and obtained as follows: , To determine the derivative value of the 1st, 2nd, 3rd...nth electricity production reduction, n is a positive integer, and n <s;
[0108] S105, averaging the calculated n derivative values, the formula is:
[0109]
[0110] In the formula, is the average value of the derivative value when the electricity production is reduced. is the derivative value when the electricity production decreases, ; The average value of the derivative value of the calculated electricity production minus the hour The threshold value of electricity production of hydropower station is set.
[0111] According to the above method, the power output threshold of the hydropower station is calculated, and the power output of the hydropower station can be judged according to the power output threshold. When the power output of the hydropower station is low, an early warning is issued to allow the operation and maintenance personnel to adjust the equipment parameters to increase the power output;
[0112] The specific steps to calculate the water level threshold of the hydropower station and construct the water level-flow rate function are as follows:
[0113] S121. Collect water level data at each equipment failure in the history of the hydropower station, specifically: , The water level data collected at the 1st, 2nd, 3rd...mth equipment failures, m is a positive integer; and the water flow velocity data at different water levels in the hydropower station are collected, specifically , is the water flow data collected at the 1st, 2nd, 3rd...bth water levels, where b is a positive integer;
[0114] S122, using the collected water level data and the water flow velocity data at different water levels to draw a water level-flow velocity curve, and using the segmentation method to calculate the functional relationship in the curve: , where W is the different water level data in the history of the hydropower station, is the correspondence between water level data and water flow velocity;
[0115] S123. Calculate the average water level data of the hydropower station equipment failure in history. The formula is:
[0116]
[0117] In the formula, To calculate the average water level data of hydropower station equipment failure in history, is the water level data of each equipment failure in the history of the hydropower station, ; The average water level data of the hydropower station equipment failure in history will be calculated Set as the water level threshold of the hydropower station.
[0118] The water level in a hydropower station is an important factor affecting the operation of the hydropower station. When the water level of the hydropower station is too high, it may cause abnormalities in the power generation equipment of the hydropower station, resulting in failure to work normally; and when the water level is too high, it may also cause floods and waterlogging disasters. Therefore, real-time monitoring of the water level of the hydropower station can effectively protect the normal operation and safety of the hydropower station;
[0119] The specific steps to calculate the water quality threshold of the hydropower station and construct the water quality-flow rate function are:
[0120] S131. Collect water quality data for each equipment failure in the history of the hydropower station, specifically: , is the water quality data of the 1st, 2nd, 3rd...mth equipment failure in the history of the hydropower station, where m is a positive integer; and the water flow velocity data of the hydropower station with different water quality data is collected, specifically: , is the water flow velocity data collected for the 1st, 2nd, 3rd...ath water quality data of the hydropower station, where a is a positive integer;
[0121] S132, using the collected water quality data of the hydropower station and the water flow velocity data at different water qualities to draw a water quality-flow velocity curve, and using the segmentation method to calculate the functional relationship in the curve: , where Z is the different water quality data in the history of the hydropower station, is the correspondence between water quality data and water flow velocity;
[0122] S133. Calculate the average water quality data of hydropower station equipment failures in history using the formula:
[0123]
[0124] In the formula, To calculate the average water quality data of hydropower station equipment failures in history, is the water quality data of each equipment failure in the history of the hydropower station, ; The average water quality data of the hydropower station equipment failure in history will be calculated Set as the water quality threshold for hydropower stations.
[0125] The water quality data in the hydropower station includes the silt, impurities, mixtures and stones in the water. When there is too much water quality and silt in the hydropower station, it may damage the power generation equipment of the hydropower station and make the hydropower station unable to work normally. Therefore, calculating the water quality data in the hydropower station and judging the real-time water quality data can effectively reduce the probability of damage to the power generation equipment and ensure the normal operation of the hydropower station;
[0126] S200, collect physical data of the hydropower station, build a digital twin model, and use the digital twin model to monitor the hydropower station in real time;
[0127] The specific steps to build a digital twin model are:
[0128] S201, collect all physical data of the hydropower station, including hydropower station size, water pressure, water flow velocity, meteorological data, terrain data and equipment data;
[0129] S202, using the collected data to perform 3D modeling of the hydropower station, and constructing a digital twin hydropower station based on the physical hydropower station;
[0130] S203. After constructing the digital twin hydropower station of the hydropower station, the three functional relationships of the calculated power output-flow velocity function, the water level-flow velocity function, and the water quality-flow velocity function and the three thresholds of the power output threshold, the water level threshold, and the water quality threshold are input into the digital twin hydropower station, and a judgment and early warning model of the digital twin hydropower station is constructed using a machine learning algorithm;
[0131] S204. After constructing the judgment and early warning model of the digital twin hydropower station, the power output, water quality and water level data in the hydropower station are monitored in real time, and abnormal conditions of the hydropower station are warned based on the constructed judgment and early warning model.
[0132] In the power generation work of hydropower stations, because the hydropower station is large in scale and there are many factors affecting the normal operation of the hydropower station, it is inconvenient to monitor the hydropower station in real time. Therefore, digital twin technology is used to establish a 3D digital twin hydropower station model. The model can be used to realize real-time monitoring of the hydropower station and ensure the normal operation of the hydropower station;
[0133] S300, using the digital twin model to collect flow velocity data of the hydropower station in real time, and judging and warning the real-time data of the hydropower station according to the three threshold data calculated in S100;
[0134] The specific steps for judging and warning the real-time data of the hydropower station are as follows:
[0135] S301. Real-time monitoring and collection of water flow velocity in hydropower stations According to the calculated electricity production-flow rate function, water level-flow rate function and water quality-flow rate function, the corresponding real-time electricity production, water level and water quality data are calculated respectively. The formula is:
[0136]
[0137]
[0138]
[0139] in the formula To calculate the real-time electricity production data, The real-time water level data is calculated. Real-time water quality data calculated;
[0140] S302, when When the power output of the hydropower station changes abnormally, it is judged that the power output change speed is abnormal and an abnormal power output warning is issued; on the contrary, when The hydropower station operates normally.
[0141] S303, when When the risk of equipment failure in the hydropower station is determined, an equipment failure warning is issued; on the contrary, when The hydropower station operates normally.
[0142] S304, when When the risk of equipment failure in the hydropower station is determined, an equipment failure warning is issued; on the contrary, when The hydropower station operates normally.
[0143] S400, after monitoring and warning the real-time data, assess the risk of each warning respectively, and classify the warning according to the assessment results;
[0144] The specific steps for assessing the risk of each warning are as follows:
[0145] S401, collect the total number of equipment failures in the history of the hydropower station as H, extract the number of failures caused by the water level exceeding the water level threshold from the H equipment failures as J, extract the number of failures caused by the water quality exceeding the water quality threshold from the H equipment failures as K, collect the number of power supply anomalies of the hydropower station due to the change rate of electricity output being less than the electricity output threshold in the history of the hydropower station as Y, and collect the number of all power supply anomalies in the history as D;
[0146] S402. Conduct risk assessment on the three types of warnings respectively, the formula is:
[0147]
[0148]
[0149]
[0150] In the formula, To calculate the probability of abnormality after water level warning, To calculate the probability of abnormality after water quality warning, To calculate the probability of abnormality after the power production warning;
[0151] S403. The calculated probabilities of abnormalities occurring after the three warnings are used as the risk assessment values of the corresponding warnings. The three calculated probabilities are sorted, and the three warnings are graded according to the order from large to small. The one with the highest calculated probability of abnormality occurring is the highest level, and then it is downgraded in sequence according to the probability order.
[0152] S500, analyzing adjustment parameters of water flow velocity according to the early warning result of the hydropower station and the three functions obtained by calculation;
[0153] The specific steps of calculating the adjustment parameters of the water flow velocity based on the early warning results of the hydropower station and the three functions calculated are:
[0154] S501. When the digital twin hydropower station issues three warnings, the three threshold data of the hydropower station are respectively input into the three functions obtained by calculation to form three equations, specifically:
[0155]
[0156]
[0157]
[0158] According to the above three equations, we can calculate the solution set A1 of three functions: 、A2: and A3: , there is at least one solution in each set;
[0159] S502, subtract the calculated solutions in the three sets from the real-time collected water flow velocity of the hydropower station, and the formula is:
[0160]
[0161] In the formula, To calculate the water flow rate adjustment parameters that need to be changed after the power production warning is issued, i takes a value from 1 to u; finally, u water flow rate adjustment parameters that need to be changed after the power production warning is issued are calculated, and the difference with the smallest value is selected. As a water flow rate adjustment parameter that needs to be changed after the power production warning is issued;
[0162] S503. According to the same method as above, two water flow rate adjustment parameters that need to be changed after the water level and water quality warnings in the equipment failure reminder are issued are calculated. The formula is:
[0163]
[0164]
[0165] In the formula, In order to calculate the water flow rate adjustment parameters that need to be changed after the equipment failure warning is issued due to abnormal water level, In order to calculate the water flow rate adjustment parameters that need to be changed after the equipment failure warning is issued due to abnormal water quality, is the water flow velocity corresponding to the water level threshold; are the water flow velocities corresponding to the water quality thresholds;
[0166] S504. When three different warnings are finally calculated according to the above steps, the theoretical water flow velocity adjustment parameters calculated to eliminate the warnings are as follows: , , .
[0167] S600, comprehensively analyzing each issued warning and water flow velocity adjustment parameter, obtaining final water flow velocity adjustment data and verifying it, and then outputting the final water flow velocity adjustment parameter that is greater than the threshold after adjustment as a reference value.
[0168] The specific steps for comprehensive analysis of each warning and water flow rate adjustment parameter are as follows:
[0169] When only one of the three types of warnings is issued in the hydropower station, the final water flow velocity adjustment parameter of the hydropower station is the water flow velocity adjustment parameter corresponding to the type of warning issued, specifically: or or ;
[0170] When any two of the three warnings are issued in the hydropower station, a situation analysis is conducted:
[0171] When the water flow velocity adjustment parameters calculated for the two warnings issued have the same sign, compare the water flow velocity adjustment parameters calculated for the two warnings, and select the larger water flow velocity adjustment parameter as the final water flow velocity adjustment parameter. ;
[0172] When the water flow velocity adjustment parameters calculated for the two warnings issued have different signs, the water flow velocity adjustment parameters corresponding to the warning type with the higher level are selected as the final water flow velocity adjustment parameters of the hydropower station according to the levels of the two warnings calculated in S400. ;
[0173] When a hydropower station issues three types of warnings, analysis is conducted based on the situation:
[0174] When the water flow velocity adjustment parameters corresponding to the three warnings are of the same sign, the water flow velocity adjustment parameters calculated corresponding to the three warnings are compared, and the largest water flow velocity adjustment parameter is selected as the final water flow velocity adjustment parameter. ;
[0175] When any two of the water flow velocity adjustment parameters corresponding to the three warnings have different signs, the abnormal occurrence probability of the warnings corresponding to the two water flow velocity adjustment parameters with the same sign is added together to obtain 1, add the value obtained 1 The probability of abnormal occurrence of the warning corresponding to the water flow velocity adjustment parameter with the last different sign 2 for comparison, when 1> 2, the final flow velocity adjustment parameter of the hydropower station is the larger value of the two adjustment parameters with the same sign. 1< 2, the final water flow velocity adjustment parameter of the hydropower station is the only water flow velocity adjustment parameter with a different sign;
[0176] After calculating the final water flow velocity adjustment parameters according to different situations, the adjustment parameters are input into the digital twin model, and the adjusted water flow velocity is calculated using the formula:
[0177]
[0178] In the formula, Using the water flow velocity adjusted by the digital twin model, the adjusted water flow velocity is brought into the three functional relationships in the digital twin model to calculate the corresponding power generation, water level and water quality data. The three data calculated after adjusting the water flow velocity are compared with the corresponding power generation threshold, water level threshold and water quality threshold. When the warning data corresponding to the selected water flow velocity adjustment parameter is greater than its threshold in different warning situations, it is proved that the selected final adjustment parameter can optimize the early warning problem. The final water flow velocity adjustment parameter that has passed the verification is set to 1. The final water flow rate adjustment parameter that does not pass is ;
[0179] After verification, the water flow rate adjustment parameters 1 output, adjust the water flow rate parameter 1 As a reference value for operation and maintenance personnel to maintain the hydropower station, verify the flow rate adjustment parameters that do not pass To discard.
[0180] A hydropower data analysis, evaluation and early warning system based on digital twins, the hydropower data analysis, evaluation and early warning system comprising a threshold calculation module, a function calculation module, a digital twin model construction module, an early warning module, a comprehensive analysis module and a parameter output module;
[0181] The threshold calculation module is used to analyze the electricity production, equipment failure, water level and water quality data collected in the history of the hydropower station to calculate the electricity production threshold, water level threshold and water quality threshold;
[0182] The function calculation module is used to collect the electricity output, flow rate, water level and water quality data in the history of the hydropower station to calculate and draw curves, and obtain three functional relationships: electricity output-flow rate function, water level-flow rate function, and water quality-flow rate function;
[0183] The digital twin model building module is used to collect physical data of the hydropower station and build a digital twin model of the hydropower station through 3D modeling and machine learning technology;
[0184] The early warning module is used to collect the power output, water level and water quality data of the hydropower station in real time using the digital twin model, and to judge the real-time data and issue corresponding early warnings;
[0185] The comprehensive analysis module is used to perform proportional calculation on the three water flow velocity adjustment parameters calculated after the early warning, and calculate the final water flow velocity adjustment parameters;
[0186] The parameter output module is used to calculate the final adjustment parameters of the water flow rate, and then transmit the adjustment parameters of the water flow rate to the operation and maintenance personnel to adjust the real-time water flow rate.
[0187] The early warning module is used to determine whether the three real-time data of electricity production, water level and water quality are abnormal, and then calculate the difference between the real-time water flow velocity and the threshold water flow velocity corresponding to each early warning according to the three functional relationships of electricity production-flow velocity function, water level-flow velocity function and water quality-flow velocity function, and obtain the adjustment parameters for the real-time water flow velocity after issuing each different early warning.
[0188] Example 1
[0189] A digital twin model of a hydropower station is now established. After the model is established, the historical data of the transmission station are collected. The power output, water level and water quality threshold data of the hydropower station are calculated to be 8KW·h, 1840m, and 5.0%, respectively. The three functional relationships of the power output-flow rate function, water level-flow rate function, and water quality-flow rate function obtained by calculation are , =0.05L+1.4, Z=2L+1.2;
[0190] The hydropower station is monitored in real time according to the digital twin model. The real-time water flow velocity collected is 1.8m / s. The real-time power output, water level and water quality data calculated by substituting this data into the function are 5.4KW·h, 1.49km and 4.8% respectively. According to the corresponding thresholds, it is judged that one of the power output data does not meet the conditions, so the hydropower station issues a power output warning.
[0191] After the early warning, the adjustment parameters of the three water flow rates were calculated to be 0.87 based on the three functional relationships; the total number of equipment failures in the history of the hydropower station was collected as 57, and the number of failures caused by abnormal water level among H equipment failures was 46, and the number of failures caused by abnormal water quality among 57 equipment failures was 11; after calculation, it was found that the influence of water level and water quality on hydropower station equipment was 80% and 19% respectively, the number of power supply abnormalities in the hydropower station in the history was 8, and the number of power supply abnormalities caused by power production early warning was 3. The probability of power supply abnormality after power production early warning was calculated to be 37.5%.
[0192] A comprehensive analysis of the adjustment parameters for each flow velocity was conducted. It was found that the hydropower station only issued one warning, so the final flow velocity adjustment parameter was 0.87. The adjusted flow velocity was calculated to be 2.67. This parameter was verified and substituted into the function In the calculation, we get =8.01, the calculated result is greater than the threshold of electricity production, so it is verified that the final adjustment parameter selected by 0.87 data can optimally solve the early warning problem;
[0193] Finally, 0.87 is output as the reference value of the water flow velocity adjustment parameter for operation and maintenance personnel during maintenance after this warning.
[0194] It should be noted that, in this article, relational terms such as first and second, etc. are only used to distinguish one entity or operation from another entity or operation, and do not necessarily require or imply any such actual relationship or order between these entities or operations. Moreover, the terms "include", "comprise" or any other variants thereof are intended to cover non-exclusive inclusion, so that a process, method, article or device including a series of elements includes not only those elements, but also other elements not explicitly listed, or also includes elements inherent to such process, method, article or device.
[0195] Finally, it should be noted that the above is only a preferred embodiment of the present invention and is not intended to limit the present invention. Although the present invention has been described in detail with reference to the aforementioned embodiments, those skilled in the art can still modify the technical solutions described in the aforementioned embodiments or replace some of the technical features therein by equivalents. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present invention shall be included in the protection scope of the present invention.
Claims
1. A hydropower data analysis, evaluation and early warning method based on digital twins, characterized by: The method comprises the following steps: S100, collecting various data in the hydropower station, respectively constructing a power output-flow velocity function, a water level-flow velocity function and a water quality-flow velocity function, and calculating a power output threshold, a water level threshold and a water quality threshold of the hydropower station; The specific steps to calculate the power generation threshold of the hydropower station and construct the power generation-flow rate function are as follows: S111. Collect the historical electricity production data of the hydropower station: , is the 1st, 2nd, 3rd, ...sth electricity production data collected in history, s is a positive integer; the water flow velocity data corresponding to each electricity production data collected is , is the 1st, 2nd, 3rd, ...sth water flow velocity data corresponding to each collected electricity production data, s is a positive integer; S112, using the collected electricity production data and the corresponding water flow velocity data to draw an electricity production-flow velocity curve, and using the segmentation method to calculate the functional relationship in the curve: , where Q is the electricity production data, is the corresponding relationship between electricity production and water flow rate; S113, performing a derivative operation on the calculated function, and obtaining the function derivative relationship in the curve graph is: , is the relationship function between the rate of change of electricity production and the flow velocity, is the rate of change of electricity production; S114. Analyze the calculated function derivative relationship and determine when When , it is proved that the electricity output of the hydropower station decreases. The derivative values of the function are judged and the derivative values of all the electricity output decreases are collected and obtained as follows: , To determine the derivative value of the 1st, 2nd, 3rd...nth electricity production reduction, n is a positive integer, and n <s; S115, averaging the calculated n derivative values, the formula is: ; In the formula, is the average value of the derivative value when the electricity production is reduced. is the derivative value when the electricity production decreases, ; The average value of the derivative value of the calculated electricity production minus the hour Set as the threshold for electricity production of hydropower stations; The specific steps for calculating the water level threshold and water level-flow rate function of the hydropower station are as follows: S121. Collect water level data at each equipment failure in the history of the hydropower station, specifically: , The water level data collected at the 1st, 2nd, 3rd...mth equipment failures, m is a positive integer; and the water flow velocity data at different water levels in the hydropower station are collected, specifically , is the water flow data collected at the 1st, 2nd, 3rd...bth water levels, where b is a positive integer; S122, using the collected water level data and the water flow velocity data at different water levels to draw a water level-flow velocity curve, and using the segmentation method to calculate the functional relationship in the curve: , where W is the different water level data in the history of the hydropower station, is the correspondence between water level data and water flow velocity; S123. Calculate the average water level data of the hydropower station equipment failure in history. The formula is: ; In the formula, To calculate the average water level data of hydropower station equipment failure in history, is the water level data of each equipment failure in the history of the hydropower station, ; The average water level data of the hydropower station equipment failure in history will be calculated Defined as the water level threshold of the hydropower station; The specific steps to calculate the water quality threshold and water quality-flow rate function of the hydropower station are: S131. Collect water quality data for each equipment failure in the history of the hydropower station, specifically: , is the water quality data of the 1st, 2nd, 3rd...mth equipment failure in the history of the hydropower station, where m is a positive integer; and the water flow velocity data of the hydropower station with different water quality data is collected, specifically: , is the water flow velocity data collected for the 1st, 2nd, 3rd...ath water quality data of the hydropower station, where a is a positive integer; S132, using the collected water quality data of the hydropower station and the water flow velocity data at different water qualities to draw a water quality-flow velocity curve, and using the segmentation method to calculate the functional relationship in the curve: , where Z is the different water quality data in the history of the hydropower station, is the correspondence between water quality data and water flow velocity; S133. Calculate the average water quality data of hydropower station equipment failures in history using the formula: ; In the formula, To calculate the average water quality data of hydropower station equipment failures in history, is the water quality data of each equipment failure in the history of the hydropower station, ; The average water quality data of the hydropower station equipment failure in history will be calculated Set as the water quality threshold for hydropower stations; S200, collect physical data of the hydropower station, build a digital twin model, and use the digital twin model to monitor the hydropower station in real time; S300, using the digital twin model to collect flow velocity data of the hydropower station in real time, and judging and warning the real-time data of the hydropower station according to the three threshold data calculated in S100; S400, after monitoring and warning the real-time data, assess the risk of each warning respectively, and classify the warning according to the assessment results; S500, analyzing adjustment parameters of water flow velocity according to the early warning result of the hydropower station and the three functions obtained by calculation; S600, comprehensively analyzing each issued warning and water flow velocity adjustment parameter, obtaining final water flow velocity adjustment data and verifying it, and then outputting the final water flow velocity adjustment parameter that is greater than the threshold after adjustment as a reference value.
2. The hydropower data analysis, evaluation and early warning method based on digital twin according to claim 1 is characterized by: The specific steps of constructing the digital twin model in S200 are: S201, collect all physical data of the hydropower station, including hydropower station size, water pressure, water flow velocity, meteorological data, terrain data and equipment data; S202, using the collected data to perform 3D modeling of the hydropower station, and constructing a digital twin hydropower station based on the physical hydropower station; S203. After constructing the digital twin hydropower station of the hydropower station, the three functional relationships of the calculated power output-flow velocity function, the water level-flow velocity function, and the water quality-flow velocity function and the three thresholds of the power output threshold, the water level threshold, and the water quality threshold are input into the digital twin hydropower station, and a judgment and early warning model of the digital twin hydropower station is constructed using a machine learning algorithm; S204. After constructing the judgment and early warning model of the digital twin hydropower station, the power output, water quality and water level data in the hydropower station are monitored in real time, and abnormal conditions of the hydropower station are warned based on the constructed judgment and early warning model.
3. The hydropower data analysis, evaluation and early warning method based on digital twin according to claim 1 is characterized by: The specific steps of judging and warning the real-time data of the hydropower station in S300 are: S301. Real-time monitoring and collection of water flow velocity in hydropower stations According to the calculated electricity production-flow rate function, water level-flow rate function and water quality-flow rate function, the corresponding real-time electricity production, water level and water quality data are calculated respectively. The formula is: ; ; ; in the formula To calculate the real-time electricity production data, The real-time water level data is calculated. Real-time water quality data calculated; S302, when When the power output of the hydropower station changes abnormally, it is judged that the power output change speed is abnormal and an abnormal power output warning is issued; on the contrary, when The hydropower station operates normally. S303, when When the equipment in the hydropower station is at risk of failure, it is judged that the equipment failure warning is issued; On the contrary, when The hydropower station operates normally. S304, when When the equipment in the hydropower station is at risk of failure, it is judged that the equipment failure warning is issued; On the contrary, when The hydropower station operates normally.
4. The hydropower data analysis, evaluation and early warning method based on digital twin according to claim 1 is characterized by: The specific steps of evaluating the risk of each warning in S400 are: S401, collect the total number of equipment failures in the history of the hydropower station as H, extract the number of failures caused by the water level exceeding the water level threshold from the H equipment failures as J, extract the number of failures caused by the water quality exceeding the water quality threshold from the H equipment failures as K, collect the number of power supply anomalies of the hydropower station due to the change rate of electricity output being less than the electricity output threshold in the history of the hydropower station as Y, and collect the number of all power supply anomalies in the history as D; S402. Conduct risk assessment on the three types of warnings respectively, the formula is: ; ; ; In the formula, To calculate the probability of abnormality after water level warning, To calculate the probability of abnormality after water quality warning, To calculate the probability of abnormality after the power production warning; S403. The calculated probabilities of abnormalities occurring after the three warnings are used as the risk assessment values of the corresponding warnings. The three calculated probabilities are sorted, and the three warnings are graded according to the order from large to small. The one with the highest calculated probability of abnormality occurring is the highest level, and then it is downgraded in sequence according to the probability order.
5. The hydropower data analysis, evaluation and early warning method based on digital twin according to claim 1 is characterized by: The specific steps of calculating the adjustment parameters of the water flow velocity according to the early warning results of the hydropower station and the three calculated functions in S500 are: S501. When the digital twin hydropower station issues three warnings, the three threshold data of the hydropower station are respectively input into the three functions obtained by calculation to form three equations, specifically: ; ; ; According to the above three equations, we can calculate the solution set A1 of three functions: 、A2: and A3: , there is at least one solution in each set; S502, subtract the calculated solutions in the three sets from the real-time collected water flow velocity of the hydropower station, and the formula is: ; In the formula, To calculate the water flow rate adjustment parameters that need to be changed after the power production warning is issued, i takes a value from 1 to u; finally, u water flow rate adjustment parameters that need to be changed after the power production warning is issued are calculated, and the difference with the smallest value is selected. As a water flow rate adjustment parameter that needs to be changed after the power production warning is issued; S503. According to the same method as above, two water flow rate adjustment parameters that need to be changed after the water level and water quality warnings in the equipment failure reminder are issued are calculated. The formula is: ; ; In the formula, In order to calculate the water flow rate adjustment parameters that need to be changed after the equipment failure warning is issued due to abnormal water level, In order to calculate the water flow rate adjustment parameters that need to be changed after the equipment failure warning is issued due to abnormal water quality, is the water flow velocity corresponding to the water level threshold; are the water flow velocities corresponding to the water quality thresholds; S504. When three different warnings are finally calculated according to the above steps, the theoretical water flow velocity adjustment parameters calculated to eliminate the warnings are as follows: , , .
6. The hydropower data analysis, evaluation and early warning method based on digital twin according to claim 1 is characterized by: The specific steps of comprehensively analyzing each warning issued and water flow rate adjustment parameter in S600 are: When only one of the three types of warnings is issued in the hydropower station, the final water flow velocity adjustment parameter of the hydropower station is the water flow velocity adjustment parameter corresponding to the type of warning issued, specifically: or or ; When any two of the three warnings are issued in a hydropower station, analysis is performed according to the situation: When the water flow velocity adjustment parameters calculated for the two warnings issued have the same sign, compare the water flow velocity adjustment parameters calculated for the two warnings, and select the larger water flow velocity adjustment parameter as the final water flow velocity adjustment parameter. ; When the water flow velocity adjustment parameters calculated for the two warnings issued have different signs, the water flow velocity adjustment parameters corresponding to the warning type with the higher level are selected as the final water flow velocity adjustment parameters of the hydropower station according to the levels of the two warnings calculated in S400. ; When a hydropower station issues three types of warnings, analysis is conducted based on the situation: When the water flow velocity adjustment parameters corresponding to the three warnings are of the same sign, the water flow velocity adjustment parameters calculated corresponding to the three warnings are compared, and the largest water flow velocity adjustment parameter is selected as the final water flow velocity adjustment parameter. ; When any two of the water flow velocity adjustment parameters corresponding to the three warnings have different signs, the abnormal occurrence probability of the warnings corresponding to the two water flow velocity adjustment parameters with the same sign is added together to obtain 1, add the value obtained 1 The probability of abnormal occurrence of the warning corresponding to the water flow velocity adjustment parameter with the last different sign 2 for comparison, when 1> 2, the final flow velocity adjustment parameter of the hydropower station is the larger value of the two adjustment parameters with the same sign. 1< 2, the final water flow velocity adjustment parameter of the hydropower station is the only water flow velocity adjustment parameter with a different sign; After calculating the final water flow velocity adjustment parameters according to different situations, the adjustment parameters are input into the digital twin model, and the adjusted water flow velocity is calculated using the formula: ; In the formula, Using the water flow velocity adjusted by the digital twin model, the adjusted water flow velocity is brought into the three functional relationships in the digital twin model to calculate the corresponding power generation, water level and water quality data. The three data calculated after adjusting the water flow velocity are compared with the corresponding power generation threshold, water level threshold and water quality threshold. When the warning data corresponding to the selected water flow velocity adjustment parameter is greater than its threshold in different warning situations, it is proved that the selected final adjustment parameter can optimize the early warning problem. The final water flow velocity adjustment parameter that has passed the verification is set to 1. The final water flow rate adjustment parameter that does not pass is ; After verification, the water flow rate adjustment parameters 1 output, adjust the water flow rate parameter 1 As a reference value for operation and maintenance personnel to maintain the hydropower station, verify the flow rate adjustment parameters that do not pass To discard.
7. A hydropower data analysis, evaluation and early warning system based on digital twins using a hydropower data analysis, evaluation and early warning method based on digital twins as described in any one of claims 1 to 6, characterized in that: The hydropower data analysis, evaluation and early warning system includes a threshold calculation module, a function calculation module, a digital twin model construction module, an early warning module, a comprehensive analysis module and a parameter output module; The threshold calculation module is used to analyze the electricity production, equipment failure, water level and water quality data collected in the history of the hydropower station to calculate the electricity production threshold, water level threshold and water quality threshold; The function calculation module is used to collect the electricity output, flow rate, water level and water quality data in the history of the hydropower station to calculate and draw curves, and obtain three functional relationships: electricity output-flow rate function, water level-flow rate function, and water quality-flow rate function; The digital twin model building module is used to collect physical data of the hydropower station and build a digital twin model of the hydropower station through 3D modeling and machine learning technology; The early warning module is used to collect the power output, water level and water quality data of the hydropower station in real time using the digital twin model, and to judge the real-time data and issue corresponding early warnings; The comprehensive analysis module is used to perform proportional calculation on the three water flow velocity adjustment parameters calculated after the early warning, and calculate the final water flow velocity adjustment parameters; The parameter output module is used to calculate the final adjustment parameters of the water flow rate, and then transmit the adjustment parameters of the water flow rate to the operation and maintenance personnel to adjust the real-time water flow rate.