A construction method combining rotary drilling and impact drilling

Through the combination of rotary drilling rigs and impact drilling rigs, mud wall protection and pile jumping methods are used to efficiently drill holes in complex terrain, solving the problems of slow construction speed and high risk of collapse in the existing technology, and achieving stable and fast bridge pier piles. Foundation construction.

CN118346175BActive Publication Date: 2024-10-18贵州交通建设集团有限公司
View PDF 2 Cites 0 Cited by

Patent Information

Application Number
CN202410781820.2
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-06-18
Publication Date
2024-10-18
Estimated Expiration
2044-06-18

AI Technical Summary

Technical Problem

During the construction of bridge pier pile foundations, it is difficult for the existing technology to efficiently destroy soft rock strata and hard rock strata at the same time in complex terrain. Collapse accidents are prone to occur, and the construction speed is low.

Method used

The construction method is a combination of rotary drilling and impact drilling. The rotary drilling rig is used to drill into soft rock formations and mud is used to protect the wall. The impact drilling rig is used to drill into hard rock formations. The pile jumping method and slurry changing method are used to improve efficiency and stability. properties and reduce the risk of hole collapse.

Benefits of technology

It achieves efficient drilling in complex terrain, reduces the risk of hole collapse, increases construction speed, reduces environmental pollution through mud recycling, and ensures pile foundation forming quality.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118346175B_ABST
    Figure CN118346175B_ABST
Patent Text Reader

Abstract

The invention relates to the field of pier pile foundation construction, and discloses a construction method combining a rotary drilling and an impact drilling, comprising the following steps: step 1, preparing a mud pool, a rotary drilling rig and an impact drilling rig, and preparing mud in the mud pool; step 2, using a rotary drilling rig to dig a plurality of shallow holes at a plurality of pile hole positions, and digging a slurry trench to connect all the shallow holes, wherein the depth of the shallow holes is greater than the depth of the slurry trench; step 3, using a rotary drilling rig to vertically drill a pile hole to a first design depth, and at the same time, using a slurry pump to send the slurry into the pile hole, and the rotary drilling rig simultaneously takes out the drill residue in the hole; step 4, using a pile skipping method for construction; step 5, repeating steps 3 and 4, until all pile holes are drilled to a second design depth, and the pile holes constructed later recycle the slurry in the pile holes constructed earlier. It is not easy to collapse the hole, and the construction speed is guaranteed.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the field of pier pile foundation construction, and in particular to a construction method combining a rotary drilling drill and an impact drill. Background Art

[0002] The pile foundation construction of bridge piers is usually carried out in remote areas with complex terrain. The upper part of the pile foundation is a soft rock layer, and the lower part of the pile foundation is a hard rock layer. If a rotary drilling rig is used for drilling, it is only efficient when drilling in a soft rock layer. The drilling progress is slow when drilling in a hard rock layer, and it is impossible to effectively destroy the hard rock layer. It is difficult to form a hole for a long time, and it is easy to cause a collapse and buried drill accident. If an impact drill is used for drilling, its huge impact force can effectively destroy the hard rock layer, but the destructive effect on the soft rock layer is low, so the drilling speed in the soft rock layer is low. If manual digging is used, the cost is lower, the flexibility is high, and it can operate under complex terrain (soft rock layer + hard rock layer) conditions, but the operation efficiency is low and the slag discharge time is long. The slag discharge time increases with the increase of the operation depth.

[0003] Therefore, a drilling method is needed that is suitable for complex terrain, is not prone to hole collapse, and can ensure construction speed. Summary of the invention

[0004] The present invention aims to provide a construction method combining a rotary drill and an impact drill, which is suitable for complex terrains, is not prone to hole collapse, and can ensure construction speed.

[0005] To achieve the above object, the present invention adopts the following technical solution: a construction method combining a rotary drill and an impact drill, comprising the following steps:

[0006] Step 1: Prepare a mud pool, rotary drilling rig and impact drilling rig, and prepare mud in the mud pool;

[0007] Step 2: Use a rotary drilling rig to dig a number of shallow holes at a number of pile hole locations, dig grout trenches to connect all the shallow holes, and the depth of the shallow holes is greater than the depth of the grout trenches;

[0008] The steps for digging slurry trenches to connect all shallow holes are:

[0009] Step 2.1: Prepare the casing, and set the slurry inlet and outlet on the side of the casing;

[0010] Step 2.2: Install the rotary drilling bit on the rotary drilling rig, dig a shallow hole at a pile hole position, replace the rotary drilling bit with a hole expander, expand the shallow hole with the rotary drilling rig, and press the casing into the shallow hole with the rotary drilling rig;

[0011] Step 2.3 Repeat step 2.2 to dig several shallow holes at several pile hole locations;

[0012] Step 2.4: prepare a mud pump and a pump pipe, place the mud pump in the mud pool, and connect the mud pump and the first pile hole with the pump pipe; dig a slurry trench, connect the slurry outlet of the first pile hole casing with the slurry inlet of the nearest casing, and connect the slurry outlet of the nearest casing with the slurry inlets of other casings in sequence;

[0013] Step 3: vertically drill a pile hole to a first designed depth using a rotary drilling rig, and at the same time, send mud into the pile hole through a mud pump, and the rotary drilling rig simultaneously removes the drill cuttings in the hole;

[0014] Step 4: Using the pile skipping method, the rotary drilling rig skips a pile hole and moves to the next pile hole position, and the impact drill is used to vertically drill the pile hole drilled to the first design depth to the second design depth;

[0015] According to the pile skipping method, the pile holes are divided into the first batch of pile holes and the second batch of pile holes for construction;

[0016] When constructing the first batch of pile holes,

[0017] In step 2.4, shallow holes are dug in sequence at the locations of all the first batch of pile holes and the second batch of pile holes, grout trenches are dug to connect all the shallow holes, and casings are installed at the locations of the first batch of pile holes;

[0018] When constructing the second batch of pile holes,

[0019] In step 2.4, casings are installed at the second batch of pile hole locations, the grout trenches during the construction of the first batch of pile holes are blocked, and the grout trenches are re-excavated to sequentially connect the shallow holes at the second batch of pile hole locations;

[0020] Step 5: Repeat steps 3 and 4 until all pile holes are drilled to the second designed depth, and the pile holes constructed later recycle the mud in the pile holes constructed earlier.

[0021] The beneficial effects of this program are:

[0022] This scheme adopts the static mud wall drilling technology, first using a rotary drilling rig to drill in the upper soft rock layer, and then using an impact drill to drill in the lower hard rock layer. The first design depth is the depth of the upper soft geology, and the second design depth is the design depth of the pile foundation on the design drawing; for the design of the pier pile foundation as a group of piles, in order to reduce the mutual disturbance during the construction of adjacent pile foundations, the skipping pile method is usually used for construction. In order to reduce the pollution of mud to the environment, shallow holes are first dug at all pile foundation positions, and slurry trenches are dug to connect all shallow holes, so that the mud in the pile foundation that has been drilled can be introduced into the next pile hole being drilled, thereby recycling the mud and reducing pollution to the environment; due to the use of the skipping pile method, the mud needs to pass through the shallow hole first before entering the next pile hole being drilled. In the present invention, the depth of the shallow hole is greater than the depth of the slurry groove. On the one hand, the shallow hole can buffer the mud and accommodate excessive mud. On the other hand, it can precipitate part of the hole residue in the mud and control the hole residue content in the mud to ensure the fluidity of the mud. At the same time, the precipitated hole residue adheres to the side wall of the shallow hole with the mud, which increases the stability of the side wall of the shallow hole and reduces the possibility of hole collapse when drilling in the shallow hole position in the later stage. In the prior art, a slag inlet is usually provided on the rotary drilling rig, so as to realize the function of collecting the drill residue into the drill bit while drilling, while the impact drill bit needs to rely on its own gravity to generate impact, so it does not have this function and needs to replace the slag removal barrel for slag removal. In the present solution, there is no need to replace the slag removal barrel, and the drill residue is directly discharged into the next pile hole, and the rotary drilling rig can be used for slag removal, which is convenient and quick. When the rotary drilling rig drills into the upper soft rock layer, the surrounding rock is relatively soft and the hole is prone to collapse. In this solution, the mud with the drill cuttings from the lower hard rock layer is introduced into the pile hole for subsequent construction and recycling. The drill cuttings increase the support strength for the soft surrounding rock, thereby reducing the possibility of hole collapse. Further, the method for determining the first design depth is:

[0023] Step 1.1: Use a rotary drilling machine to dig a test pile next to the pile hole, and use dry rotary drilling. The hole diameter of the test pile is smaller than the hole diameter of the pile hole;

[0024] Step 1.2 As the excavation depth increases, the throttle of the rotary drilling rig increases, and the smoke from the chimney of the rotary drilling rig becomes thicker. At this time, a thicker drill rod is replaced until the thickest drill rod is replaced;

[0025] Step 1.3 After replacing the thickest drill rod, when the smoke from the chimney of the rotary drilling rig becomes thick again, drill core samples at the bottom of the test pile at this time and measure the core strength value. If the core strength value is higher than the upper limit of the rock compressive strength specified by the rotary drilling rig, the depth at this time is the first design depth.

[0026] Furthermore, in step 4, when vertical drilling is performed using an impact drill, a static mud wall drilling process is used to suspend the drill cuttings by mud until the first pile hole is drilled to the second design depth and the second pile hole is drilled to the first depth;

[0027] The first pile hole is cleaned by the slurry replacement method, and the replaced slurry is discharged into the second and third pile holes through the slurry groove. At the same time, an impact drill is used to drill the second pile hole, and a rotary drilling rig is used to drill the third pile hole.

[0028] Furthermore, in step 4, the hole cleaning is performed twice. The first hole cleaning is performed after the depth of the first pile hole reaches the second design depth, and the replaced mud with drilling debris is discharged into the second pile hole and the third pile hole through the slurry groove. After the steel cage is installed in the first pile hole, the second hole cleaning is performed;

[0029] Before pouring concrete, the standard for the second hole cleaning is: the mud discharged from the hole has no granular feeling when touched, the mud specific gravity is less than 1.03, the sand content is less than 2%, and the viscosity is 17 to 20s; the thickness of the sediment at the bottom of the hole is not more than 5cm.

[0030] Furthermore, in step 1, a sedimentation tank is also prepared, and a slurry overflow port is provided on the casing, and the slurry overflow port is higher than the first slurry outlet;

[0031] In step 2, the sedimentation tank is connected to all overflow ports through the slurry ditch; the sedimentation tank is connected to the mud pool through the slurry ditch.

[0032] Furthermore, in step one, the number of impact drills prepared is twice the number of rotary drilling rigs.

[0033] This solution also has the following effects:

[0034] 1. According to the drilling sequence, the first few construction pile holes are named as: the first pile hole, the second pile hole and the third pile hole. Since they are piles under the same pier and the pile foundation depths are similar, the slurry replacement method is used to replace the slurry in the first pile hole to complete the hole cleaning. Since the hole cleaning speed is much faster than the rotary drilling rig and the impact drilling rig, in order to fully recycle the replaced slurry, while the first pile hole is being cleaned, the second pile hole is drilled with an impact drilling rig, and the third pile hole is drilled with a rotary drilling rig. Since the pile holes are connected by slurry grooves, the slurry replaced in the first pile hole flows into the first pile hole and the second pile hole in turn, and the side walls of the pile holes are protected by mud. After the first pile hole is cleaned for the first time, the slurry groove connected to the first slurry outlet of the first pile hole is blocked, and the end of the pump pipe is placed at the hole mouth of the second pile hole to replenish the mud in the second pile hole in time;

[0035] Since the first slurry outlet is blocked, the replaced slurry flows out from the overflow outlet into the sedimentation tank during the second hole cleaning. After sedimentation in the sedimentation tank, the slurry enters the mud pool and is re-prepared into slurry. After the second hole cleaning, the slurry specific gravity is guaranteed to be less than 1.03, the sand content is less than 2%, and the viscosity is 17-20s. The thickness of the sediment at the bottom of the hole is not more than 5cm. This ensures that there are fewer impurities after the pile foundation is formed, thereby ensuring the forming quality.

[0036] 2. When the skip pile method is used for construction, after the first batch of pile holes are poured, the original slurry trenches have been blocked by the poured concrete. Therefore, it is necessary to dig the slurry trenches again to connect the second batch of pile holes in order to drill and pour the second batch of pile holes.

[0037] 3. When the hardness of the surrounding rock is relatively high, it is necessary to increase the number of impact drills to ensure that the construction speed of the impact drills can keep up with the construction speed of the rotary drilling rigs. BRIEF DESCRIPTION OF THE DRAWINGS

[0038] Figure 1 This is a schematic diagram of step a in Example 1;

[0039] Figure 2 This is a schematic diagram of step b in Example 1;

[0040] Figure 3 This is a schematic diagram of step c in Example 1;

[0041] Figure 4 This is a schematic diagram of step e in Example 1;

[0042] Figure 5 This is a schematic diagram of slurry trench excavation in step d of Example 1;

[0043] Figure 6 Schematic diagram of slurry trench excavation in step e of Example 1. DETAILED DESCRIPTION

[0044] The following is further described in detail through specific implementation methods:

[0045] The figure marks in the drawings of the specification include: mud pool 1, rotary drilling rig 2, impact drilling rig 3, shallow hole 4, slurry trench 5, casing 6, mud 7, pump pipe 8, first pile hole 9, second pile hole 10, third pile hole 11, first batch of pile holes 12, second batch of pile holes 13.

[0046] Example 1

[0047] A construction method combining a rotary drill and an impact drill comprises the following steps:

[0048] Step 1: prepare a mud pool 1, a sedimentation tank, a rotary drilling rig 2 and an impact drilling rig 3, prepare mud 7 in the mud pool 1, and use a mud mixer to stir the expansive soil to make slurry;

[0049] Step 2: Use a rotary drilling rig 2 to dig a number of shallow holes 4 at a number of pile hole positions, dig slurry trenches 5 to connect all the shallow holes 4, and the depth of the shallow holes 4 is greater than the depth of the slurry trenches 5; the steps of digging slurry trenches 5 to connect all the shallow holes 4 are:

[0050] 2.1 Prepare casing 6, and divide the pile holes into the first batch of pile holes 12 and the second batch of pile holes 13 for construction according to the pile skipping method; Figure 5 As shown, all the pile holes of the slurry trench are connected to form a "2"-shaped line, and the first batch of pile holes 12 and the second batch of piles 13 are arranged at intervals on this line;

[0051] Similarly, the casing 6 is divided into the first batch of casings 6 and the second batch of casings 6. The first batch of casings 6 are provided with a first slurry inlet, a first slurry outlet and an overflow outlet on the side. The first slurry inlet and the first slurry outlet are at the same height, and the overflow outlet is higher than the first slurry outlet. The first batch of casings 6 and the second batch of casings 6 are both formed by rolling 10mm steel plates, and their inner diameters are 15 to 20cm larger than the designed pile diameter. Stiffening rings are welded on the periphery of the upper and lower openings, and the length is 3m. Figure 5 As shown, the positions of the first slurry inlet and the first slurry outlet can be determined by the connection positions of the slurry groove and the first pile holes 12; the difference between the second batch of casings 6 and the first batch of casings 6 is that the second batch of casings 6 have a second slurry inlet, a second slurry outlet and an overflow outlet on the side, the second slurry inlet and the second slurry outlet are at the same height, and the overflow outlet is higher than the second slurry outlet. In this embodiment, Figure 6 As shown, the positions of the second slurry inlet and the second slurry outlet can be determined through the connection position of the slurry groove and the second batch of pile holes 13. Except that the second slurry inlet of the first second batch of casings 6 and the second slurry outlet of the last second batch of casings 6 are blocked, the second slurry inlet and the second slurry outlet are respectively connected to the center of the casing 6, and the angle formed is 90°; the first slurry inlet and the second slurry inlet are collectively referred to as the slurry inlet, and the first slurry outlet and the second slurry outlet are collectively referred to as the slurry outlet;

[0052] 2.2 As Figure 1 As shown, the rotary drilling bit is installed on the rotary drilling rig 2, and the rotary drilling rig 2 digs a shallow hole 4 at a pile hole position. The rotary drilling bit is replaced with a reamer, and the rotary drilling rig 2 expands the shallow hole 4. The rotary drilling rig 2 presses the casing 6 into the shallow hole 4, and presses the casing 6 into a position 2m below the top of the pile. The top of the casing 6 is 0.3m higher than the original ground. Before and after the casing 6 is pressed in, the vertical position of the casing 6 is adjusted by a level meter, and the center position of the casing 6 is found by a crosshair. The casing 6 is moved so that the center of the casing 6 coincides with the center position of the pile hole; clay with an optimal moisture content is backfilled symmetrically and evenly around the casing 6, and compacted in layers to achieve an optimal density.

[0053] 2.3 Repeat step 2.2 to dig a number of shallow holes 4 at a number of pile hole positions; this step can be performed simultaneously with step 2.4;

[0054] 2.4 Prepare a mud pump and a pump pipe 8, place the mud pump in the mud pool 1, and connect the pump pipe 8 to the first pile hole 9; dig a slurry ditch 5, connect the slurry outlet of the casing 6 of the first pile hole 9 with the slurry inlet of the nearest casing 6, connect the slurry outlet of the nearest casing 6 with the slurry inlets of other casings 6 in sequence, connect the sedimentation tank with all overflow ports through the slurry ditch 5, connect the sedimentation tank with the mud pool 1, and the depth of the connection position is lower than the depth of the sedimentation tank to facilitate the sedimentation of the mud 7 in the sedimentation tank. The precipitated mud 7 enters the mud pool 1 and can be reused after treatment.

[0055] According to the pile skipping method, in step 2.4, the pile holes are divided into a first batch of pile holes 12 and a second batch of pile holes 13 for construction;

[0056] Construction of the first batch of pile holes 12: Figure 5 As shown, a rotary drilling rig 2 is used to dig a number of shallow holes 4 at the positions of a number of pile holes, and a slurry groove 5 is excavated to connect all the shallow holes 4. The depth of the shallow hole 4 is greater than the depth of the slurry groove 5. The first batch of casings 6 are installed at the positions of the first batch of pile holes 12, so that the first slurry inlets and the first slurry outlets of all the first batch of casings 6 are aligned with the slurry groove 5, so as to be connected in sequence. At the positions of the second batch of pile holes 13, the slurry groove 5 is used for connection, and there is no need to install the second batch of casings 6 temporarily;

[0057] When constructing the second batch of pile holes 13: Figure 6 As shown, the second batch of casings 6 are installed at the positions of the second batch of pile holes 13, the slurry grooves 5 during the construction of the first batch of pile holes 12 are blocked, and the slurry grooves 5 are re-excavated to sequentially connect the shallow holes 4 at the positions of the second batch of pile holes 13, so that the second slurry inlets and second slurry outlets of all the second batch of casings 6 are aligned with the slurry grooves 5, so as to be sequentially connected;

[0058] Step 3: Use a rotary drilling rig 2 to vertically drill a pile hole to a first designed depth, and at the same time, send mud 7 into the pile hole through a mud pump, and the rotary drilling rig 2 simultaneously takes out the drilling debris in the hole;

[0059] Step 4: using the pile skipping method, the rotary drilling rig 2 is moved to the next pile hole position, the first pile hole 9 is vertically drilled by the impact drill, and the static mud 7 wall protection drilling process is adopted to suspend the drill cuttings by the mud 7 until the first pile hole 9 is drilled to the second design depth, and the second pile hole 10 is drilled to the first depth;

[0060] like Figure 3 As shown, the first pile hole 9 is cleaned by the slurry replacement method, and the hole cleaning is performed twice. The first hole cleaning is performed after the depth of the first pile hole 9 reaches the second design depth, and the replaced mud 7 with drilling debris is discharged into the second pile hole 10 and the third pile hole 11 through the slurry groove 5. After the steel cage is installed in the first pile hole 9, the second hole cleaning is performed;

[0061] Before pouring concrete, the standard for the second hole cleaning is: the mud 7 discharged from the hole has no granular feeling when touched, the mud 7 specific gravity is less than 1.03, the sand content is less than 2%, the viscosity is 17-20s, and the thickness of the sediment at the bottom of the hole is not more than 5cm. The viscosity of the mud is usually characterized by measuring the time (seconds) for unit volume of mud to flow out using a Marsh funnel. The longer this time is, the higher the viscosity of the mud is. "s" in this embodiment represents the time unit "second".

[0062] The displaced mud 7 is discharged into the second pile hole 10 and the third pile hole 11 through the slurry groove 5. At the same time, the second pile hole 10 is drilled by the impact drill 3, and the third pile hole 11 is drilled by the rotary drilling rig 2.

[0063] Step 5: Repeat steps 3 and 4 until all pile holes are drilled to the second designed depth, and the pile holes constructed later recycle the mud in the pile holes constructed earlier.

[0064] In this embodiment, in order to reduce the impact on the environment, the mud 7 between the piles is recycled. In order to further illustrate the recycling method of the mud 7, this embodiment illustrates this method from the perspective of the construction progress relationship of each pile hole. According to the drilling sequence, the first few pile holes constructed in the first batch of pile holes 12 are named as: the first pile hole 9, the second pile hole 10 and the third pile hole 11. This example is suitable for the construction of pile groups under the same pier. Therefore, the distance between the piles is relatively close, the geological conditions and the design bearing capacity are similar, the pile length is also similar, and the first design depth and the second design depth are also similar.

[0065] The pile hole construction method explained from the perspective of the construction progress relationship of each pile hole:

[0066] Step a. Figure 1 As shown, a shallow hole 4 is excavated at the position of the first pile hole 9 and a casing 6 is installed. The first pile hole 9 is drilled to a first design depth h1 by a rotary drilling rig 2. At the same time, a pump pipe 8 is placed at the orifice of the first pile hole 9, and a mud pump is used to pump mud into the first pile hole 9;

[0067] Step b. Figure 2 As shown, the first pile hole 9 is drilled to the second design depth h2 by using an impact drill 3; at the same time, since the present scheme uses the pile skipping method, a rotary drilling rig 2 is required to dig a shallow hole 4 at the position of the second batch of pile holes 13 between the first pile hole 9 and the second pile hole 10, a slurry trench 5 is dug to connect the first pile hole 9 and the second pile hole 10, a shallow hole 4 is dug at the position of the second pile hole 10 and a casing 6 is installed, and a rotary drilling rig is used to drill the second pile hole 10 to the first design depth h1; at the same time, the mud pump is continued to be used to pump mud into the first pile hole 9, and the excess mud 7 flows into the shallow hole 4 and the second pile hole 10 through the slurry trench 5 to meet the construction needs of the second pile hole 10;

[0068] Step c. Figure 3 As shown, the second pile hole 10 is drilled to the second design depth h2 by using an impact drill 3; at the same time, a shallow hole 4 is excavated at the position of the third pile hole 11 and a casing 6 is installed, and the third pile hole 11 is drilled to the first design depth h1 by using a rotary drilling machine; at the same time, a mud pump is placed at the bottom of the first pile pipe, and the mud 7 in the first pile pipe is discharged into the second pile pipe and the third pile pipe. Since the depths of the pile pipes are similar, the mud 7 discharged from the first pile pipe can just meet the construction needs of the second pile hole 10 and the third pile hole 11. If there is excess mud 7, it is discharged from the overflow port. If the mud 7 discharged from the first pile pipe is insufficient, the mud pump is used to directly pump it into the second pile hole 10;

[0069] Step d. Complete the pouring of the first pile hole 9; repeat steps b and c to complete the construction of the remaining first pile holes 12; slurry trench excavation method such as Figure 5 As shown;

[0070] Step e. Install casing 6 at the second batch of pile holes 13, such as Figure 6 As shown, the excavated slurry groove 5 is connected to the second slurry outlet of the second slurry inlet of the second batch of casings 6, and the second slurry outlet of the last casing 6 is connected to the sedimentation tank (not shown in the figure). Figure 4 As shown, the construction of the second batch of pile holes 13 is completed in sequence; the difference between the construction method of the second batch of pile holes 13 and the first batch of pile holes 12 (step b, step c, step d) is that the second batch of pile holes 13 are directly connected through the slurry grooves 5, and the slurry grooves 5 between the second batch of pile holes 13 do not pass through the shallow holes 4 at other pile hole positions.

[0071] Example 2

[0072] The difference between Example 2 and Example 1 is that in step 1, the number of impact drills 3 prepared is twice the number of rotary drilling rigs 2.

[0073] Example 3

[0074] Embodiment 3 is a method for determining the first design depth in Embodiment 1:

[0075] Step 1.1 Use a rotary drilling machine to dig a test pile next to the pile hole, and use dry rotary drilling. The diameter of the test pile is smaller than the diameter of the pile hole to reduce the amount of work;

[0076] Step 1.2: As the excavation depth increases, the throttle of the rotary drilling rig 2 increases, and the smoke from the chimney of the rotary drilling rig 2 becomes thicker. At this time, a thicker drill rod is replaced until the thickest drill rod is replaced;

[0077] Step 1.3 After replacing the thickest drill rod, when the smoke from the chimney of the rotary drilling rig becomes thick again, core samples are taken at the bottom of the test pile at this time, and the core strength value is measured. If the core strength value is higher than the upper limit of the rock compressive strength specified by the rotary drilling rig 2, the depth at this time is the first design depth, otherwise continue drilling and then take core samples until the core strength meets the requirements.

[0078] The above is only an embodiment of the present invention, and the common knowledge such as the known specific technical solutions and / or characteristics in the solution is not described in detail here. It should be pointed out that for those skilled in the art, without departing from the technical solution of the present invention, several modifications and improvements can be made, which should also be regarded as the protection scope of the present invention, and these will not affect the effect of the implementation of the present invention and the practicality of the patent. The scope of protection required by this application shall be based on the content of its claims, and the specific implementation methods and other records in the specification can be used to interpret the content of the claims.

Claims

1. A construction method combining a rotary drill and an impact drill, characterized in that: The following steps are involved: Step 1: Prepare a mud pool, a rotary drilling rig and an impact drilling rig, and prepare mud in the mud pool; Step 2: Use a rotary drilling rig to dig a number of shallow holes at a number of pile hole locations, dig grout trenches to connect all the shallow holes, and the depth of the shallow holes is greater than the depth of the grout trenches; The steps for digging slurry trenches to connect all shallow holes are: Step 2.1: Prepare the casing, and set the slurry inlet and outlet on the side of the casing; Step 2.2: Install the rotary drilling bit on the rotary drilling rig, dig a shallow hole at a pile hole position, replace the rotary drilling bit with a hole expander, expand the shallow hole with the rotary drilling rig, and press the casing into the shallow hole with the rotary drilling rig; Step 2.3 Repeat step 2.2 to dig several shallow holes at several pile hole locations; Step 2.4: prepare a mud pump and a pump pipe, place the mud pump in the mud pool, and connect the mud pump and the first pile hole with the pump pipe; dig a slurry trench, connect the slurry outlet of the first pile hole casing with the slurry inlet of the nearest casing, and connect the slurry outlet of the nearest casing with the slurry inlets of other casings in sequence; Step 3: vertically drill a pile hole to a first designed depth using a rotary drilling rig, and at the same time, send mud into the pile hole through a mud pump, and the rotary drilling rig simultaneously removes the drill cuttings in the hole; Step 4: Using the pile skipping method, the rotary drilling rig skips a pile hole and moves to the next pile hole position, and the impact drill is used to vertically drill the pile hole drilled to the first design depth to the second design depth; According to the skip pile method, the pile holes are divided into the first batch of pile holes and the second batch of pile holes for construction; When constructing the first batch of pile holes, In step 2.4, shallow holes are dug in sequence at the locations of all the first batch of pile holes and the second batch of pile holes, grout trenches are dug to connect all the shallow holes, and casings are installed at the locations of the first batch of pile holes; When constructing the second batch of pile holes, In step 2.4, casings are installed at the second batch of pile hole locations, the grout trenches during the construction of the first batch of pile holes are blocked, and the grout trenches are re-excavated to sequentially connect the shallow holes at the second batch of pile hole locations; Step 5: Repeat steps 3 and 4 until all pile holes are drilled to the second designed depth, and the pile holes constructed later recycle the mud in the pile holes constructed earlier.

2. A construction method combining a rotary drill and an impact drill according to claim 1, characterized in that: The first design depth is determined as follows: Step 1.1: Use a rotary drilling machine to dig a test pile next to the pile hole, and use dry rotary drilling. The hole diameter of the test pile is smaller than the hole diameter of the pile hole; Step 1.2 As the excavation depth increases, the throttle of the rotary drilling rig increases, and the smoke from the chimney of the rotary drilling rig becomes thicker. At this time, a thicker drill rod is replaced until the thickest drill rod is replaced; Step 1.3 After replacing the thickest drill rod, when the smoke from the chimney of the rotary drilling rig becomes thick again, drill core samples at the bottom of the test pile at this time and measure the core strength value. If the core strength value is higher than the upper limit of the rock compressive strength specified by the rotary drilling rig, the depth at this time is the first design depth.

3. The construction method of combining a rotary drill and an impact drill according to claim 2, characterized in that: In step 4, when vertical drilling is performed using an impact drill, a static mud wall drilling process is used to suspend the drill cuttings by mud until the first pile hole is drilled to the second design depth and the second pile hole is drilled to the first depth; The first pile hole is cleaned by the slurry replacement method, and the replaced slurry is discharged into the second and third pile holes through the slurry groove. At the same time, an impact drill is used to drill the second pile hole, and a rotary drilling rig is used to drill the third pile hole.

4. The construction method of combining a rotary drill and an impact drill according to claim 3, characterized in that: In step 4, the hole cleaning is performed twice. The first hole cleaning is performed after the depth of the first pile hole reaches the second design depth, and the replaced mud with drilling debris is discharged into the second pile hole and the third pile hole through the slurry groove. After the steel cage is installed in the first pile hole, the second hole cleaning is performed; Before pouring concrete, the standard for the second hole cleaning is: the mud discharged from the hole has no granular feeling when touched, the mud specific gravity is less than 1.03, the sand content is less than 2%, and the viscosity is 17 to 20s; the thickness of the sediment at the bottom of the hole is not more than 5cm.

5. The construction method of combining a rotary drill and an impact drill according to claim 4, characterized in that: In step 1, a sedimentation tank is also prepared, and overflow ports are provided on the casings. The casings are divided into the first batch of casings and the second batch of casings. The first batch of casings are provided with first slurry outlets on the sides, and the overflow ports are higher than the first slurry outlets. In step 2, the sedimentation tank is connected to all overflow ports through the slurry ditch; the sedimentation tank is connected to the mud pool through the slurry ditch.

6. The construction method of combining a rotary drill and an impact drill according to claim 5, characterized in that: In step 1, the number of impact drills prepared is twice the number of rotary drilling rigs.

Citation Information

Patent Citations

  • Construction method for constructing filling pile with electric drill and rotary digging relay drill

    CN107165160A

  • Construction method of pile foundation for complex rebuilt foundation pit engineering

    CN107938656A