A safety evaluation method for pipeline corridor construction based on multi-source information fusion

The pipeline construction safety evaluation method through multi-source information fusion, combined with entropy value and analytic hierarchy process, solves the problem of the inability to accurately judge the safety status of the pipeline corridor in real time in the existing technology, and achieves more efficient safety status assessment and monitoring.

CN118378902BActive Publication Date: 2024-10-01HEFEI UNIV OF TECH
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202410823087.6
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-06-25
Publication Date
2024-10-01
Estimated Expiration
2044-06-25

AI Technical Summary

Technical Problem

The existing technology cannot realize real-time monitoring and accurate judgment of the safety status of the pipe gallery during the construction process, and the judgment of a single monitoring item is not enough to reflect the overall safety status during the construction process.

Method used

A pipeline construction safety evaluation method based on multi-source information fusion is adopted to divide risk levels, calculate expected value, entropy value and super-entropy value, obtain real-time monitoring data, calculate basic probability function value, perform conflict detection and weighted correction, and use entropy value Method and analytic hierarchy process are used to calculate objective and subjective weights, and comprehensive weights are integrated with evidence to determine the risk level of the pipeline corridor.

Benefits of technology

It improves the accuracy of pipe gallery safety status assessment and real-time monitoring capabilities, reduces reliance on manual inspections, and enhances the safety and efficiency of the construction site.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118378902B_ABST
    Figure CN118378902B_ABST
Patent Text Reader

Abstract

The present invention relates to the technical field of pipeline corridor safety status assessment, and specifically to a pipeline corridor construction safety assessment method based on multi-source information fusion. The present invention selects real-time monitoring data during the pipeline corridor construction process, adopts a cloud model algorithm to pre-process the data to obtain corresponding basic probability function values, and handles the conflict problem of basic probability function values ​​based on Mahalanobis distance. Then, combined with the risk level, the comprehensive weights of various indicators in the pipeline corridor system are determined based on subjective weights and objective weights, and then the comprehensive weight calculation is used to obtain the safety status of the pipeline corridor during the construction process. The above operation can effectively improve the judgment of the safety status of the pipeline corridor.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of pipeline corridor safety status assessment, and in particular to a pipeline corridor construction safety assessment method based on multi-source information fusion. Background Art

[0002] As a municipal pipeline that can better solve problems such as "air spider web" and "road zipper" caused by the installation of traditional pipelines, the pipeline corridor is an important municipal infrastructure project to ensure the sustainable development of the city.

[0003] The safety status of the tunnel during construction mainly depends on the on-site inspection and judgment of experienced experts or safety inspectors. This process requires a lot of manpower and material resources, and it is impossible to achieve real-time monitoring of the construction process. Therefore, a large number of sensors are equipped in the current tunnel construction process, and the sensors are used to record the deformation, stress and other key data of the soil around the tunnel and the existing structures in real time. These measured data can directly or indirectly reflect the safety status of the tunnel. Through data recording, and drawing a time curve based on the measured data, the maximum safety measured value of each project is checked to judge the safety status of the tunnel. However, in the actual use of this method, only a single monitoring project is used to judge the safety status of the tunnel at the same time. In the process of tunnel construction, each detection project is interdependent and affects each other. Therefore, when only a single project is used to judge the safety status of the tunnel, due to the overly single consideration, it is impossible to accurately judge the overall safety status of the tunnel construction. Therefore, the current method of using a single monitoring project to judge the safety status of the tunnel needs to be improved. Summary of the invention

[0004] In order to avoid and overcome the technical problems existing in the prior art, the present invention provides a pipeline corridor construction safety evaluation method based on multi-source information fusion. The present invention can effectively improve the accuracy of pipeline corridor safety status evaluation.

[0005] To achieve the above object, the present invention provides the following technical solutions:

[0006] A pipeline corridor construction safety evaluation method based on multi-source information fusion includes the following steps:

[0007] S1. Divide the risk level of pipeline corridor construction, determine the value range of various indicators in each risk level, and calculate the expected value, entropy value and super entropy value of the value range of various indicators in each risk level;

[0008] S2. Real-time monitoring data detected at each detection point of the tunnel during the tunnel construction process are obtained, and one detection point only detects real-time monitoring data of one risk level in one indicator; the basic probability function value of the current detection point at each risk level is calculated according to the real-time monitoring data, and the basic probability function value combination of the same detection point at each risk level constitutes a piece of evidence for the detection point;

[0009] S3, perform conflict checks on various evidences belonging to the same indicator, and store the non-conflicting evidences in the evidence set; perform weighted correction on the conflicting evidences to update the basic probability function value of the corresponding evidences, and store the updated evidences in the evidence set;

[0010] S4. Based on the acquired real-time monitoring data, the objective weights of various indicators are calculated using the entropy method; at the same time, the subjective weights of various indicators are calculated using the analytic hierarchy process, and the subjective weights and objective weights are combined to form the comprehensive weights of various indicators;

[0011] S5. Use the obtained comprehensive weight to fuse the various pieces of evidence in the evidence set to obtain the risk probability that characterizes the pipeline corridor at each risk level, and determine the risk level of the pipeline corridor based on the risk probability.

[0012] As a further solution of the present invention: the expected value, entropy value and super entropy value calculation formulas of various indicators in each risk level are as follows:

[0013] The expected value is calculated as follows:

[0014] ;

[0015] In the formula, represents the expected value of the jth indicator in the ith risk level, The superscript Q in denotes the expected label. The subscript V in represents the risk level. The subscript X in represents an indicator; It represents the maximum value of the value range of the j-th indicator in the i-th risk level; It represents the minimum value of the range of values ​​of the j-th indicator in the i-th risk level;

[0016] The calculation formula of entropy value is as follows:

[0017] ;

[0018] In the formula, It represents the entropy value of the value range of the jth indicator in the i-th risk level, and L is the entropy value label; The denominator of cloud entropy representing the value range of the jth indicator in the i-th risk level;

[0019] The value of super entropy is the set value, that is, the super entropy value of the value range of the jth indicator in the i-th risk level is .

[0020] As a further solution of the present invention: the basic probability function value calculation process is as follows:

[0021] S21. According to the expected value, entropy value and super entropy value of each risk level of various indicators, the random cloud entropy is calculated by a random generation formula; and by changing the value of the random number in the random generation formula, a set number of random cloud entropies are randomly generated in each risk level of various indicators; the random generation formula is specifically as follows:

[0022] ;

[0023] In the formula, represents the random cloud entropy within the value range of the ith risk level at the gth detection point belonging to the jth indicator; , G represents the total number of detection points in the tunnel; , J represents the total number of indicator types; , I represents the total number of risk levels; represents the random cloud entropy within the range of the i-th risk level at the g-th detection point belonging to the j-th indicator The number of the nth value of ; , It represents the total number of random cloud entropies within the value range of the i-th risk level at the g-th detection point belonging to the j-th indicator; represents the random cloud entropy within the range of the i-th risk level at the g-th detection point belonging to the j-th indicator No. A value; Represents a random number from 0 to 1; exp represents the natural exponential function;

[0024] S22. During the construction of the pipe gallery, only one type of detection sensor is set at each detection point of the pipe gallery to detect the real-time monitoring data of the corresponding indicator type, and only one real-time monitoring data is generated at one detection point; based on the obtained real-time monitoring data, random cloud entropy, expected value, entropy value and super entropy value, the sub-probability function value of each random cloud entropy of the current detection point within each risk level is calculated; the calculation formula of the sub-probability function value is as follows:

[0025] ;

[0026] represents the random cloud entropy within the range of the i-th risk level at the g-th detection point belonging to the j-th indicator No. The value of the sub-probability function; It represents the real-time monitoring data detected at the g-th detection point belonging to the j-th indicator, and the superscript s is the sign of the real-time monitoring data;

[0027] S23, averaging all sub-probability function values ​​of the current detection point in the current risk level to obtain the mean value of the sub-probability function value of the indicator type corresponding to the current detection point in the current risk level, and the mean value of the sub-probability function value is the basic probability function value of the current detection point in the current risk level; the basic probability function value calculation formula is as follows:

[0028] ;

[0029] In the formula, represents the random cloud entropy within the range of the i-th risk level at the g-th detection point belonging to the j-th indicator The basic probability function value of .

[0030] As a further solution of the present invention: the calculation process of the cloud entropy denominator value is as follows:

[0031] S1A1. Obtain all random cloud entropies in the current risk level of the current indicator, and all random cloud entropies obtained at this time conform to Gaussian distribution;

[0032] S1A2, drawing a Gaussian distribution bell curve using the random cloud entropy obtained in step S1A1;

[0033] S1A3. Obtain the expected value of the Gaussian distribution bell curve in step S1A2 , and count the number of values ​​that fall into the range of the Gaussian distribution bell curve , and calculate the ratio of this number to the total number of random cloud entropies in the bell curve of the Gaussian distribution;

[0034] S1A4, due to expected value It is a fixed value, so by changing the value of the cloud entropy denominator d, different value ranges and corresponding ratios can be obtained;

[0035] S1A5, taking the ratio as the dependent variable and the cloud entropy denominator value d as the independent variable, a cloud entropy fitting curve is constructed; then the ratio is selected according to the set requirements, and the cloud entropy denominator value corresponding to the ratio can be obtained through the cloud entropy fitting curve;

[0036] S1A6. According to the contents of steps S1A1 to S1A5, the random cloud entropies in each risk level of various indicators are traversed to obtain the cloud entropy fitting curves corresponding to each risk level of various indicators; then the ratio is selected according to the set requirements to obtain the corresponding cloud entropy denominator value.

[0037] As a further solution of the present invention: after calculating the basic probability function values ​​of the current detection point at each risk level, these basic probability function values ​​are arranged in sequence according to the risk level and constitute a piece of evidence for the current detection point, and the evidence is recorded as original evidence.

[0038] As a further solution of the present invention, the conflict detection process is as follows:

[0039] S31. Selecting original evidences of the same indicator type from the original evidences obtained by calculation, and sorting the selected original evidences according to the arrangement order of the detection points; and storing the sorted original evidences in the original data set in sequence;

[0040] S32. Based on the original data set obtained in step S31, two original evidences are randomly selected from the original data set, and the conflict values ​​of the two original evidences are calculated. The calculation formula of the conflict value is as follows:

[0041] ;

[0042] In the formula, K represents the conflict value; represents the random cloud entropy within the r-th risk level value range at the b-th detection point belonging to the j-th indicator The value of the basic probability function of ; represents the random cloud entropy within the value range of the rth risk level at the bth detection point belonging to the jth indicator; ;

[0043] S33, calculating the conflict values ​​between all the arbitrary two original evidences in the original data set obtained in step S31 according to the content of step S32; after the calculation is completed, if all the conflict values ​​obtained are less than 1, there is no conflict between the original evidences in the original data set, no modification is made to the original evidences in the original data set, and the original evidences corresponding to the original data set are stored in the evidence set; otherwise, there is a conflict between the original evidences in the original data set, and weighted corrections from step S34 to step S38 need to be performed on each piece of evidence;

[0044] S34. Calculate the Mahalanobis distance between any two pieces of original evidence in the original data set with conflicts. The Mahalanobis distance calculation formula is as follows:

[0045] ;

[0046] In the formula, represents the Mahalanobis distance between the original evidence of the g-th detection point belonging to the j-th indicator and the original evidence of the b-th detection point belonging to the j-th indicator; represents the original evidence of the g-th detection point belonging to the j-th indicator; represents the original evidence of the b-th detection point belonging to the j-th indicator; T represents the matrix transpose; Represents original evidence and original evidence The covariance matrix between ; Represents the covariance matrix The inverse matrix of

[0047] S35. Calculate the Mahalanobis distance between any original evidence in the original data set and other original evidence according to the content of step S34, and sum and average all the calculated Mahalanobis distances to obtain the average distance corresponding to the any original evidence; the average distance calculation formula is as follows:

[0048] ;

[0049] In the formula, It represents the average distance between the original evidence of the g-th detection point belonging to the j-th indicator and all other original evidences belonging to the j-th indicator;

[0050] S36. After obtaining the average distances of all the original evidence in the original data set in step S35, first calculate the reciprocals of the average distances, then sum and average the reciprocals of the average distances, and record the average value obtained after the sum and average operation as the original weight of each original evidence in the original data set in step S34; the original weight calculation formula is as follows:

[0051] ;

[0052] In the formula, represents the original weight assigned to the original evidence of the g-th detection point belonging to the j-th indicator;

[0053] S37, calculating the original weight of each original evidence in the original data set in step S34 according to step S36, and then multiplying the original weight of the current original evidence by each basic probability function value in the original evidence respectively, so as to achieve weighting of each basic probability function value in the original evidence;

[0054] Traversing all basic probability function values ​​in the original data set to complete weighting of all basic probability function values ​​in the original data set;

[0055] Then, the weighted basic probability function values ​​of the same risk level in the original data set are summed, and the summation result is recorded as a new basic probability function value; and the new basic probability function value is used to replace the original basic probability function values ​​of all original evidence in the original data set at the current risk level; the calculation formula of the new basic probability function value is as follows:

[0056] ;

[0057] In the formula, The new basic probability function value representing the i-th risk level of the j-th indicator;

[0058] S38, replacing the original basic probability function value at each risk level in each original evidence in the original data set according to the content of step S37, thereby completing the update of the original evidence, and storing the updated original evidence in the evidence set;

[0059] S39. According to the contents of step S31 to step S33, conflict detection is performed on the original evidence of different indicator types; and the original evidence with conflicts is subjected to weighted correction from step S34 to step S38, and the original evidence after weighted correction is recorded as weighted evidence and stored in the evidence set, and the evidence set at this time is defined as a weighted set.

[0060] As a further solution of the present invention: Based on the real-time monitoring data, the steps of calculating the objective weights of various indicators using the entropy method are as follows:

[0061] S4A1. The real-time monitoring data of each monitoring point detected is recorded as a sample value, and each sample value is stored in a sample set of the corresponding indicator; the sample set is represented as: ; ,in, represents the sample set of the first indicator, represents the sample set of the jth indicator; represents the sample set of the Jth indicator; Represents the sample value of the first detection point belonging to the jth indicator; represents the sample value of the g-th detection point belonging to the j-th indicator; represents the sample value of the Gth detection point belonging to the jth indicator;

[0062] S4A2. Standardize the calculated sample values ​​of each detection point to obtain the corresponding standard value, and store the obtained standard value in the standard set of the corresponding indicator; the calculation formula of the standard value is as follows:

[0063] ;

[0064] In the formula, Represents a sample set The smallest sample value in ; Represents a sample set The largest sample value in ; Represents a sample set In The standard value obtained after standardization;

[0065] S4A3, performing standardization processing on each sample value in each sample set according to the content of step S4A2 to obtain a corresponding standard value;

[0066] S4A4. Based on the standard values ​​calculated in step S4A3, the information entropy values ​​of various indicators are calculated using the information entropy value calculation formula; the information entropy value calculation formula is as follows:

[0067] ;

[0068] In the formula, represents the information entropy value of the jth indicator, The superscript P in represents the label of the information entropy value; represents the exponential function; express The reciprocal of represents the exponential function of G;

[0069] S4A5. Based on the information entropy values ​​of various indicators calculated in step S4A4, the information utility values ​​of various indicators are calculated using the information utility value calculation formula; the information utility value calculation formula is as follows:

[0070] ;

[0071] In the formula, represents the information utility value of the j-th indicator;

[0072] S4A6. Based on the information utility values ​​of various indicators calculated in step S4A5, the objective weights of various indicators are calculated using an objective weight calculation formula; the objective weight calculation formula is specifically as follows:

[0073] ;

[0074] In the formula, represents the objective weight of the jth indicator, The superscript 1 in represents the label of the objective weight.

[0075] As a further solution of the present invention: the process of calculating the subjective weights of various indicators using the hierarchical analysis method is as follows:

[0076] S4B1. Construct a hierarchical model: take the safety status of the pipeline corridor construction as the target layer, various indicators as the criterion layer, and the specific values ​​of various indicators as the solution layer;

[0077] S4B2. Evaluate the importance of the two indicators according to the set evaluation criteria, and construct a judgment matrix based on the importance. The judgment matrix is ​​specifically expressed as follows;

[0078] ;

[0079] Where C represents the judgment matrix; represents the element in the jth row and fth column of the judgment matrix C, that is, Indicates the importance between the j-th indicator and the f-th indicator;

[0080] S4B3. Calculate the result of multiplying each row in the judgment matrix C and raising it to the Jth power, and record the result as the multiplication weight. Store the multiplication weight calculated for each row in the judgment matrix C in the feature vector. The calculation formula of the multiplication weight is as follows:

[0081] ;

[0082] In the formula, Represents the weight of the j-th row in the judgment matrix C; the eigenvector formed It is expressed as: ,in, Represents the multiplication weight of the first row in the judgment matrix C; Represents the multiplication weight of the Jth row in the judgment matrix C;

[0083] S4B4, based on the feature vector obtained in step S4B3 , for the feature vector The combined weights in are normalized, and the result of the normalization is the subjective weight of the corresponding indicator, and the subjective weights are stored in the weight matrix in turn; the calculation formula of the subjective weight is as follows:

[0084] ;

[0085] In the formula, represents the subjective weight of the jth indicator, The superscript 2 in represents the label of the subjective weight;

[0086] Weight Matrix It is expressed as: ,in, Indicates the subjective weight of the first indicator; represents the subjective weight of the Jth indicator;

[0087] S4B5, based on the weight matrix obtained in step S4B4 , calculate the row elements and weight matrix in the judgment matrix C The product of the transposed matrix of and sum the products; then the summation result and the weight matrix Compare with the sum Z of each element in, and average the comparison results. The average value obtained is the maximum characteristic root of the judgment matrix C. The calculation formula of the maximum characteristic root is as follows:

[0088] ;

[0089] In the formula, represents the maximum eigenvalue of the judgment matrix C; represents the vector composed of the j-th row elements of the judgment matrix C;

[0090] S4B6. After obtaining the maximum characteristic root of the judgment matrix C, calculate the consistency ratio of the judgment matrix C; the consistency ratio calculation formula is as follows:

[0091] ;

[0092] In the formula, Represents the consistency ratio of the judgment matrix C; It represents the consistency index;

[0093] S4B7. When the consistency ratio is less than 0.1, it indicates that the assessment of the importance between the two indicators in the judgment matrix C is correct; otherwise, it indicates that there is a logical error in the assessment of the importance between any two indicators in the judgment matrix C, and it is necessary to reassess the importance between any two indicators according to the set assessment criteria, and recalculate the corresponding consistency ratio according to the contents of steps S4B3 to S4B6 until the consistency ratio is less than 0.1.

[0094] As a further solution of the present invention: the comprehensive weight is specifically expressed as follows:

[0095] ;

[0096] In the formula, Represents the comprehensive weight of the j-th indicator.

[0097] As a further solution of the present invention: the specific steps of step S5 are as follows:

[0098] S51, calculating the sum of the basic probability function values ​​in the weighted evidence, and finding the difference between the sum and 1, recording the difference as uncertainty and storing it in the weighted evidence, and then defining the weighted evidence after adding the uncertainty as measurement evidence;

[0099] S52, converting all weighted evidences in the weighted set into measurement evidences according to the content of step S51; selecting measurement evidences belonging to the same indicator type from the various measurement evidences obtained by calculation, and sorting the selected measurement evidences according to the arrangement order of the detection points; and storing the sorted measurement evidences in the measurement data set in sequence;

[0100] S53, construct an empty measurement evidence as the preset evidence, and select two measurement evidences from the measurement data set to form an evidence pair; first calculate the product of two basic probability function values ​​belonging to the same risk level in the evidence pair, and record the product as the first product; then calculate the product of the basic function probability value of each risk level of any measurement evidence in the evidence pair and the uncertainty of the other measurement evidence, and record the product as the second product; then calculate the conflict value of the evidence pair according to the content of step S32;

[0101] Select any risk level of the evidence pair, obtain all first products and second products of the evidence pair at the risk level, sum the obtained first products and second products, compare the summed result with the conflict value of the evidence pair, and store the comparison result under the risk level of the preset evidence;

[0102] Traverse all risk levels of the evidence pair, and store the obtained comparison results under the risk level corresponding to the preset evidence; at the same time, calculate the uncertainty of the preset evidence, store the uncertainty in the preset evidence, and make the preset evidence a measurement evidence; then store the preset evidence with the uncertainty in the measurement data set, and delete the measurement evidence pair that has been used from the measurement data set;

[0103] S54, traversing all the measurement evidences in the measurement data set according to the content of step S53, so as to finally obtain a preset evidence storing uncertainty, and the preset evidence is the preliminary fusion evidence of the indicator type corresponding to the measurement data set;

[0104] S55, generating measurement data sets of different indicator types according to the contents of step S53 to step S54, and then calculating preliminary fusion evidence of various indicators;

[0105] S56, multiplying the comprehensive weights of various indicators by the respective values ​​in the preliminary fusion evidence of the corresponding indicators, and replacing the values ​​with the products, and then recording the preliminary fusion evidence after all the values ​​have been replaced as preliminary weighted evidence;

[0106] S57, traversing the preliminary fusion evidence of various indicators according to the content of step S56, and obtaining corresponding preliminary weighted evidence;

[0107] S58, adding the values ​​belonging to the same risk level in each preliminary weighted evidence, and replacing the values ​​of the risk level in each preliminary weighted evidence with the result of the addition;

[0108] Traverse all risk levels to complete the replacement of the values ​​in each preliminary weighted evidence, and record the preliminary weighted evidence after the replacement as the final weighted evidence;

[0109] S59. Traverse all the final weighted evidences according to the contents of step S53 to generate preliminary fusion evidence representing all indicator types. The preliminary fusion evidence is the final evidence after all indicators are fused, and the numerical values ​​at each risk level in the final evidence are the risk probabilities that characterize the risk level of the pipeline corridor, where the risk level corresponding to the maximum risk probability is the risk level of the pipeline corridor.

[0110] Compared with the prior art, the present invention has the following beneficial effects:

[0111] The present invention selects real-time monitoring data during the construction of the pipe gallery, uses a cloud model algorithm to pre-process the data to obtain the corresponding basic probability function value, and handles the conflict problem of the basic probability function value based on the Mahalanobis distance. Then, combined with the risk level, the comprehensive weights of various indicators in the pipe gallery system are determined based on the subjective weight and the objective weight, and then the comprehensive weight calculation is used to obtain the safety status of the pipe gallery during the construction process. The above operation can effectively improve the judgment of the safety status of the pipe gallery. BRIEF DESCRIPTION OF THE DRAWINGS

[0112] Figure 1 This is the main flow chart of the present invention.

[0113] Figure 2 It is a schematic diagram of the structure of the pipe gallery system of the present invention.

[0114] Figure 3 This is the fuzzy acceptance curve diagram in the present invention. DETAILED DESCRIPTION

[0115] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0116] See also Figures 1 to 3 In an embodiment of the present invention, a pipeline corridor construction safety evaluation method based on multi-source information fusion includes the following contents.

[0117] 1. Divide the risk levels and calculate the corresponding expected value, entropy value and super entropy value.

[0118] like Figure 1 As shown in the figure, the risk level of pipeline corridor construction is divided, and the value range of various indicators in each risk level is determined. A comprehensive pipeline corridor construction risk assessment system is established, and the risk level and corresponding risk interval of different monitoring project indicators are divided, and the safety threshold range of each risk level is clarified. , vertical displacement of pile top , deep horizontal displacement , concrete support axial force As a project indicator, five risk levels are divided, namely V = {low risk V1, relatively low risk V2, medium risk V3, relatively high risk V4, high risk V5}. The specific data are shown in Table 1.

[0119] ;

[0120] Use the corresponding calculation formula to calculate the expected value, entropy value and super entropy value of the value range of various indicators in each risk level. In the process of calculating the entropy value, the cloud entropy denominator value is calculated according to the corresponding steps. According to the safety requirements of different pipeline construction projects, the ratio at this time is recorded as the fuzzy acceptance D, and the value of the fuzzy acceptance is adaptively adjusted to obtain the corresponding cloud entropy denominator value. The fuzzy acceptance curve calculated in this embodiment is as follows Figure 3 As shown, the fuzzy acceptance degree D in the specific embodiment is 10%, and the value of the cloud entropy denominator value d is calculated to be 3.34. The specific values ​​of the expected value, entropy value and super entropy value are shown in Table 2.

[0121] ;

[0122] 2. Generate original evidence.

[0123] During the construction of the tunnel, the real-time monitoring data detected at each detection point of the tunnel is obtained, and one detection point only detects the real-time monitoring data of one indicator and one risk level; the basic probability function value of the current detection point at each risk level is calculated according to the real-time monitoring data, and the basic probability function value of the same detection point at each risk level together constitutes an evidence of the detection point, and the evidence is recorded as the original evidence.

[0124] Import the acquired real-time monitoring data into the cloud model and calculate the basic probability function value (BPA) according to the corresponding steps. The calculation process of BPA is as follows:

[0125] S21. According to the expected value, entropy value and super entropy value of each risk level of various indicators, the random cloud entropy is calculated through a random generation formula; and by changing the value of the random number in the random generation formula, a set number of random cloud entropies are randomly generated in each risk level of various indicators.

[0126] S22. During the construction of the tunnel, only one type of detection sensor is set at each detection point of the tunnel to detect the real-time monitoring data of the corresponding indicator type, and one detection point only generates one piece of real-time monitoring data; based on the obtained real-time monitoring data, random cloud entropy, expected value, entropy value and super entropy value, the sub-probability function value of each random cloud entropy of the current detection point in each risk level is calculated.

[0127] S23. Take the average of all sub-probability function values ​​of the current detection point in the current risk level to obtain the mean of the sub-probability function values ​​of the indicator type corresponding to the current detection point in the current risk level. The mean of the sub-probability function values ​​is the basic probability function value of the current detection point in the current risk level.

[0128] 3. Conflict detection.

[0129] Conduct conflict checks on various evidences belonging to the same indicator, and store non-conflicting evidences in an evidence set; perform weighted corrections on conflicting evidences to update the basic probability function values ​​of the corresponding evidences, and store the updated evidences in an evidence set.

[0130] The conflict detection process is as follows:

[0131] S31. Selecting original evidences of the same indicator type from the original evidences obtained by calculation, and sorting the selected original evidences according to the arrangement order of the detection points; and storing the sorted original evidences in the original data set in sequence;

[0132] S32. Based on the original data set obtained in step S31, select any two original evidences from the original data set; calculate the product of any two basic probability function values ​​of the two original evidences belonging to different risk levels, and sum all the calculated products, and the sum result is the conflict value.

[0133] S33. Calculate the conflict value between any two original evidences in the original data set obtained in step S31 according to the content of step S32. After the calculation is completed, if all the conflict values ​​obtained are less than 1, there is no conflict between the original evidences in the original data set, and no modification is made to the original evidences in the original data set, and the original evidences corresponding to the original data set are stored in the evidence set. Otherwise, there is a conflict between the original evidences in the original data set, and each piece of evidence needs to be weightedly corrected from step S34 to step S38.

[0134] S34. Calculate the Mahalanobis distance between any two pieces of original evidence in the original data set with conflicts.

[0135] S35. Calculate the Mahalanobis distance between any original evidence in the original data set and other original evidence according to the content of step S34, and sum and average all the calculated Mahalanobis distances to obtain the average distance corresponding to the any original evidence.

[0136] S36. After obtaining the average distance of all original evidence in the original data set through step S5, first calculate the reciprocals of each average distance, then sum and average the reciprocals of the average distances, and record the average value obtained after the sum and averaging operation as the original weight of each original evidence in the original data set in step S34.

[0137] S37. Calculate the original weight of each original evidence in the original data set in step S34 according to step S36, and then multiply the original weight of the current original evidence by each basic probability function value in the original evidence to achieve the weighting of each basic probability function value in the original evidence. Traverse all basic probability function values ​​in the original data set to complete the weighting of all basic probability function values ​​in the original data set. Then sum up the weighted basic probability function values ​​of the same risk level in the original data set, and record the summation result as the new basic probability function value; and replace the original basic probability function values ​​of all original evidence in the original data set at the current risk level with the new basic probability function value.

[0138] S38. Replace the original basic probability function value at each risk level in each original evidence in the original data set according to the content of step S37, so as to complete the update of the original evidence, and store the updated original evidence in the evidence set.

[0139] S39. According to the contents of step S31 to step S33, conflict detection is performed on the original evidence of different indicator types; and the original evidence with conflicts is subjected to weighted correction from step S34 to step S38, and the original evidence after weighted correction is recorded as weighted evidence and stored in the evidence set, and the evidence set at this time is defined as a weighted set.

[0140] The original data sets corresponding to each detection point of soil settlement are shown in Table 3. The preliminary fusion evidence formed after conflict detection of the original data sets corresponding to soil settlement is shown in Table 4.

[0141] ;

[0142] ;

[0143] The original data sets corresponding to each detection point of the vertical displacement of the pile top are shown in Table 5. The initial fusion evidence formed by the original data sets corresponding to the vertical displacement of the pile top after conflict detection is shown in Table 6.

[0144] ;

[0145] ;

[0146] The original data sets corresponding to each detection point of deep horizontal displacement are shown in Table 7. The initial fusion evidence formed after conflict detection of the original data sets corresponding to deep horizontal displacement is shown in Table 8.

[0147] ;

[0148] ;

[0149] The original data sets corresponding to each detection point of the concrete support axial force are shown in Table 9. The initial fusion evidence formed after the conflict detection of the original data sets corresponding to the concrete support axial force is shown in Table 10.

[0150] ;

[0151] ;

[0152] 4. Calculate the comprehensive weight.

[0153] Based on the real-time monitoring data obtained, the objective weights of various indicators are calculated using the entropy method. The objective weight calculation results are shown in Table 11.

[0154] ;

[0155] The results of subjective weight calculation are shown in Table 12.

[0156] ;

[0157] When using the formula to calculate the consistency ratio, according to the judgment matrix The order of the corresponding consistency index is Value. Consistency index The values ​​are shown in Table 13. Judgment Matrix in the Embodiment of the Present Invention It is a 4-order matrix. As shown in Table 13, the consistency index The calculated consistency ratio is shown in Table 14.

[0158] ;

[0159] ;

[0160] The subjective weights and objective weights are combined to form the comprehensive weights of various indicators. The comprehensive weights are shown in Table 15.

[0161] ;

[0162] S5. Risk level assessment.

[0163] The obtained comprehensive weights are used to fuse each piece of evidence in the evidence set to obtain the risk probability that characterizes the corridor at each risk level, and the risk level of the corridor is determined based on the specific risk probability value. The fusion results are shown in Table 16.

[0164] ;

[0165] The fusion results of the present invention are more accurate than those of traditional evidence theory (Dempster and Euclidean distance), and the uncertainty of the comprehensive evidence is lower. Compared with traditional manual on-site inspections, the multi-source information fusion intelligent evaluation system for pipeline corridor construction safety of the present invention can achieve real-time monitoring based on on-site measured data, ensure the safety of the construction site, improve construction efficiency, and improve the accuracy of pipeline corridor construction safety status prediction.

[0166] The above description is only a preferred specific implementation manner of the present invention, but the protection scope of the present invention is not limited thereto. Any technician familiar with the technical field can make equivalent replacements or changes according to the technical scheme and inventive concept of the present invention within the technical scope disclosed by the present invention, which should be covered by the protection scope of the present invention.

Claims

1. A pipeline corridor construction safety evaluation method based on multi-source information fusion, characterized in that: The following steps are involved: S1. Divide the risk level of pipeline corridor construction, determine the value range of various indicators in each risk level, and calculate the expected value, entropy value and super entropy value of the value range of various indicators in each risk level; S2. Real-time monitoring data detected at each detection point of the tunnel during the tunnel construction process are obtained, and one detection point only detects real-time monitoring data of one risk level in one indicator; the basic probability function value of the current detection point at each risk level is calculated according to the real-time monitoring data, and the basic probability function value combination of the same detection point at each risk level constitutes a piece of evidence for the detection point; S3, perform conflict checks on various evidences belonging to the same indicator, and store the non-conflicting evidences in the evidence set; perform weighted correction on the conflicting evidences to update the basic probability function value of the corresponding evidences, and store the updated evidences in the evidence set; S4. Based on the acquired real-time monitoring data, the objective weights of various indicators are calculated using the entropy method; at the same time, the subjective weights of various indicators are calculated using the analytic hierarchy process, and the subjective weights and objective weights are combined to form the comprehensive weights of various indicators; S5. Use the obtained comprehensive weight to fuse the pieces of evidence in the evidence set to obtain the risk probability that characterizes the corridor at each risk level, and determine the risk level of the corridor based on the risk probability; The calculation process of the basic probability function value is as follows: S21. According to the expected value, entropy value and super entropy value of each risk level of various indicators, the random cloud entropy is calculated by a random generation formula; and by changing the value of the random number in the random generation formula, a set number of random cloud entropies are randomly generated in each risk level of various indicators; the random generation formula is specifically as follows: ; In the formula, x j,g,i represents the random cloud entropy within the range of the i-th risk level at the g-th detection point belonging to the j-th indicator; g∈[1,G], G represents the total number of detection points in the corridor; j∈[1,J], J represents the total number of indicator types; i∈[1,I], I represents the total number of risk levels; n j,g,i represents the random cloud entropy x within the range of the i-th risk level at the g-th detection point belonging to the j-th indicator j,g,i The number of the nth value of j,g,i ∈[1,N j,g,i ],N j,g,i It represents the total number of random cloud entropies within the value range of the i-th risk level at the g-th detection point belonging to the j-th indicator; represents the random cloud entropy x within the range of the i-th risk level at the g-th detection point belonging to the j-th indicator j,g,i The nth j,g,i value; rand(0,1) represents a random number between 0 and 1; exp represents the natural exponential function; It represents the entropy value of the value range of the jth indicator in the i-th risk level, and L is the entropy value label; the value of super entropy is the set value, that is, the super entropy value of the value range of the jth indicator in the i-th risk level is ; S22. During the construction of the pipe gallery, only one type of detection sensor is set at each detection point of the pipe gallery to detect the real-time monitoring data of the corresponding indicator type, and only one real-time monitoring data is generated at one detection point; based on the obtained real-time monitoring data, random cloud entropy, expected value, entropy value and super entropy value, the sub-probability function value of each random cloud entropy of the current detection point within each risk level is calculated; the calculation formula of the sub-probability function value is as follows: ; represents the random cloud entropy x within the range of the i-th risk level at the g-th detection point belonging to the j-th indicator j,g,i The nth j,g,i The value of the sub-probability function; It represents the real-time monitoring data detected at the g-th detection point belonging to the j-th indicator, and the superscript s is the sign of the real-time monitoring data; represents the expected value of the jth indicator in the ith risk level, The superscript Q in denotes the expected label. The subscript V in represents the risk level. The subscript X in represents an indicator; S23, averaging all sub-probability function values ​​of the current detection point in the current risk level to obtain the mean value of the sub-probability function value of the indicator type corresponding to the current detection point in the current risk level, and the mean value of the sub-probability function value is the basic probability function value of the current detection point in the current risk level; the basic probability function value calculation formula is as follows: ; In the formula, represents the random cloud entropy x within the range of the i-th risk level at the g-th detection point belonging to the j-th indicator j,g,i The basic probability function value of .

2. According to a method for evaluating the safety of pipe gallery construction based on multi-source information fusion according to claim 1, it is characterized in that: The calculation formulas for the expected value, entropy value and super entropy value of various indicators at each risk level are as follows: The expected value is calculated as follows: ; In the formula, It represents the maximum value of the value range of the j-th indicator in the i-th risk level; It represents the minimum value of the range of values ​​of the j-th indicator in the i-th risk level; The calculation formula of entropy value is as follows: ; In the formula, The cloud entropy denominator value representing the value range of the j-th indicator in the i-th risk level.

3. According to claim 2, a pipeline corridor construction safety evaluation method based on multi-source information fusion is characterized in that: The calculation process of the cloud entropy denominator value is as follows: S1A1. Obtain all random cloud entropies in the current risk level of the current indicator, and all random cloud entropies obtained at this time conform to Gaussian distribution; S1A2, drawing a Gaussian distribution bell curve using the random cloud entropy obtained in step S1A1; S1A3. Obtain the expected value of the Gaussian distribution bell curve in step S1A2 , and count the number of random cloud entropies that fall outside the value interval [μ-d,μ+d] in the Gaussian distribution bell curve, and calculate the ratio of this number to the total number of random cloud entropies in the Gaussian distribution bell curve; S1A4. Since the expected value μ is a fixed value, the value of the denominator d of the cloud entropy is changed to obtain different value intervals and corresponding ratios; S1A5, taking the ratio as the dependent variable and the cloud entropy denominator value d as the independent variable, a cloud entropy fitting curve is constructed; then the ratio is selected according to the set requirements, and the cloud entropy denominator value corresponding to the ratio can be obtained through the cloud entropy fitting curve; S1A6. According to the contents of steps S1A1 to S1A5, the random cloud entropies in each risk level of various indicators are traversed to obtain the cloud entropy fitting curves corresponding to each risk level of various indicators; then the ratio is selected according to the set requirements to obtain the corresponding cloud entropy denominator value.

4. A pipeline corridor construction safety evaluation method based on multi-source information fusion according to claim 3, characterized in that: After the basic probability function values ​​of the current detection point at each risk level are calculated, these basic probability function values ​​are arranged in sequence according to the risk level and constitute a piece of evidence for the current detection point, and the evidence is recorded as the original evidence.

5. A pipeline corridor construction safety evaluation method based on multi-source information fusion according to claim 4, characterized in that: The conflict detection process is as follows: S31. Selecting original evidences of the same indicator type from the original evidences obtained by calculation, and sorting the selected original evidences according to the arrangement order of the detection points; and storing the sorted original evidences in the original data set in sequence; S32. Based on the original data set obtained in step S31, two original evidences are randomly selected from the original data set, and the conflict values ​​of the two original evidences are calculated. The calculation formula of the conflict value is as follows: ; In the formula, K represents the conflict value; represents the random cloud entropy x within the r-th risk level range at the b-th detection point belonging to the j-th indicator j,b,r The basic probability function value of x j,b,r represents the random cloud entropy within the value range of the rth risk level at the bth detection point belonging to the jth indicator; b∈[1,G], r∈[1,I]; S33, calculating the conflict values ​​between all the arbitrary two original evidences in the original data set obtained in step S31 according to the content of step S32; after the calculation is completed, if all the conflict values ​​obtained are less than 1, there is no conflict between the original evidences in the original data set, no modification is made to the original evidences in the original data set, and the original evidences corresponding to the original data set are stored in the evidence set; Otherwise, there are conflicts among the original evidences in the original data set, and each piece of evidence needs to be weightedly corrected from step S34 to step S38; S34. Calculate the Mahalanobis distance between any two pieces of original evidence in the original data set with conflicts. The Mahalanobis distance calculation formula is as follows: ; Where, d j,g,b H represents the Mahalanobis distance between the original evidence of the g-th detection point belonging to the j-th indicator and the original evidence of the b-th detection point belonging to the j-th indicator; j,g H represents the original evidence of the g-th detection point belonging to the j-th indicator; j,b represents the original evidence of the bth detection point belonging to the jth indicator; T represents the matrix transpose; Σ j,g,b Represents the original evidence H j,g and the original evidence H j,b The covariance matrix between ; Denotes the covariance matrix Σ j,g,b The inverse matrix of S35. Calculate the Mahalanobis distance between any original evidence in the original data set and other original evidence according to the content of step S34, and sum and average all the calculated Mahalanobis distances to obtain the average distance corresponding to the any original evidence; the average distance calculation formula is as follows: ; In the formula, It represents the average distance between the original evidence of the g-th detection point belonging to the j-th indicator and all other original evidences belonging to the j-th indicator; S36. After obtaining the average distances of all the original evidence in the original data set in step S35, first calculate the reciprocals of the average distances, then sum and average the reciprocals of the average distances, and record the average value obtained after the sum and average operation as the original weight of each original evidence in the original data set in step S34; the original weight calculation formula is as follows: ; In the formula, ω j,g represents the original weight assigned to the original evidence of the g-th detection point belonging to the j-th indicator; S37, calculating the original weight of each original evidence in the original data set in step S34 according to step S36, and then multiplying the original weight of the current original evidence by each basic probability function value in the original evidence respectively, so as to achieve weighting of each basic probability function value in the original evidence; Traversing all basic probability function values ​​in the original data set to complete weighting of all basic probability function values ​​in the original data set; In the formula, ω j,g represents the original weight assigned to the original evidence of the g-th detection point belonging to the j-th indicator; S37, calculating the original weight of each original evidence in the original data set in step S34 according to step S36, and then multiplying the original weight of the current original evidence by each basic probability function value in the original evidence respectively, so as to achieve weighting of each basic probability function value in the original evidence; Traversing all basic probability function values ​​in the original data set to complete weighting of all basic probability function values ​​in the original data set; ; In the formula, The new basic probability function value representing the i-th risk level of the j-th indicator; S38, replacing the original basic probability function value at each risk level in each original evidence in the original data set according to the content of step S37, thereby completing the update of the original evidence, and storing the updated original evidence in the evidence set; S39. According to the contents of step S31 to step S33, conflict detection is performed on the original evidence of different indicator types; and the original evidence with conflicts is subjected to weighted correction from step S34 to step S38, and the original evidence after weighted correction is recorded as weighted evidence and stored in the evidence set, and the evidence set at this time is defined as a weighted set.

6. A pipeline corridor construction safety evaluation method based on multi-source information fusion according to claim 5, characterized in that: Based on real-time monitoring data, the steps for calculating the objective weights of various indicators using the entropy method are as follows: S4A1. Record the real-time monitoring data of each monitoring point detected as a sample value, and store each sample value in a sample set of the corresponding indicator; the sample set is represented by: Y1, ..., Y j , …, Y J ; Y j ={y j,1 , …, y j,g , …, y j,G }, where Y1 represents the sample set of the first indicator, Y j represents the sample set of the jth indicator; Y J represents the sample set of the Jth indicator; y j,1 represents the sample value of the first detection point belonging to the jth indicator; y j,g represents the sample value of the g-th detection point belonging to the j-th indicator; y j,G represents the sample value of the Gth detection point belonging to the jth indicator; S4A2. Standardize the calculated sample values ​​of each detection point to obtain the corresponding standard value, and store the obtained standard value in the standard set of the corresponding indicator; the calculation formula of the standard value is as follows: ; Where, min(Y j ) represents the sample set Y j The smallest sample value in j ) represents the sample set Y j The largest sample value in ; Represents the sample set Y j The y in j,g The standard value obtained after standardization; S4A3, performing standardization processing on each sample value in each sample set according to the content of step S4A2 to obtain a corresponding standard value; S4A4. Based on the standard values ​​calculated in step S4A3, the information entropy values ​​of various indicators are calculated using the information entropy value calculation formula; the information entropy value calculation formula is as follows: ; In the formula, represents the information entropy value of the jth indicator, Superscript in A label representing the information entropy value; represents the exponential function; (lnG) -1 represents the reciprocal of lnG, lnG represents the exponential function of G; S4A5. Based on the information entropy values ​​of various indicators calculated in step S4A4, the information utility values ​​of various indicators are calculated using the information utility value calculation formula; the information utility value calculation formula is as follows: ; Where D j represents the information utility value of the j-th indicator; S4A6. Based on the information utility values ​​of various indicators calculated in step S4A5, the objective weights of various indicators are calculated using an objective weight calculation formula; the objective weight calculation formula is specifically as follows: ; In the formula, represents the objective weight of the jth indicator, The superscript 1 in represents the label of the objective weight.

7. A pipeline corridor construction safety evaluation method based on multi-source information fusion according to claim 6, characterized in that: The process of calculating the subjective weights of various indicators using the hierarchical analysis method is as follows: S4B1. Construct a hierarchical model: take the safety status of the pipeline corridor construction as the target layer, various indicators as the criterion layer, and the specific values ​​of various indicators as the solution layer; S4B2. Evaluate the importance of the two indicators according to the set evaluation criteria, and construct a judgment matrix based on the importance. The judgment matrix is ​​specifically expressed as follows: ; Where C represents the judgment matrix; c jf Represents the element in the jth row and fth column of the judgment matrix C, that is, c jf Indicates the importance between the j-th indicator and the f-th indicator; S4B3. Calculate the result of multiplying each row in the judgment matrix C and raising it to the Jth power, and record the result as the multiplication weight. Store the multiplication weight calculated for each row in the judgment matrix C in the feature vector. The calculation formula of the multiplication weight is as follows: ; In the formula, Represents the weight of the j-th row in the judgment matrix C; the eigenvector formed It is expressed as: ,in, Represents the multiplication weight of the first row in the judgment matrix C; Represents the multiplication weight of the Jth row in the judgment matrix C; S4B4, based on the feature vector obtained in step S4B3 , for the feature vector The combined weights in are normalized, and the result of the normalization is the subjective weight of the corresponding indicator, and the subjective weights are stored in the weight matrix in sequence; the calculation formula of the subjective weight is as follows: ; In the formula, represents the subjective weight of the jth indicator, The superscript 2 in represents the label of the subjective weight; Weight matrix W 2 It is expressed as: ,in, Indicates the subjective weight of the first indicator; represents the subjective weight of the Jth indicator; S4B5, based on the weight matrix W obtained in step S4B4 2 , calculate the row elements in the judgment matrix C and the weight matrix W 2 The product of the transposed matrix of and sum the products; then the summation result is added to the weight matrix W 2 Compare with the sum Z of each element in, and average the comparison results. The average value obtained is the maximum characteristic root of the judgment matrix C. The calculation formula of the maximum characteristic root is as follows: ; In the formula, λ max represents the maximum eigenvalue of the judgment matrix C; C j Represents the vector composed of the j-th row elements of the judgment matrix C; S4B6. After obtaining the maximum characteristic root of the judgment matrix C, calculate the consistency ratio of the judgment matrix C; the consistency ratio calculation formula is as follows: ; In the formula, CR represents the consistency ratio of the judgment matrix C; RI represents the consistency index; S4B7. When the consistency ratio is less than 0.1, it indicates that the assessment of the importance between the two indicators in the judgment matrix C is correct; otherwise, it indicates that there is a logical error in the assessment of the importance between any two indicators in the judgment matrix C, and it is necessary to reassess the importance between any two indicators according to the set assessment criteria, and recalculate the corresponding consistency ratio according to the contents of steps S4B3 to S4B6 until the consistency ratio is less than 0.

1.

8. A pipeline corridor construction safety evaluation method based on multi-source information fusion according to claim 7, characterized in that: The comprehensive weight is specifically expressed as follows: ; In the formula, Represents the comprehensive weight of the j-th indicator.

9. A pipeline corridor construction safety evaluation method based on multi-source information fusion according to claim 8, characterized in that: The specific steps of step S5 are as follows: S51, calculating the sum of the basic probability function values ​​in the weighted evidence, and finding the difference between the sum and 1, recording the difference as uncertainty and storing it in the weighted evidence, and then defining the weighted evidence after adding the uncertainty as measurement evidence; S52, converting all weighted evidences in the weighted set into measurement evidences according to the content of step S51; From the various metric evidences obtained by calculation, metric evidences belonging to the same indicator type are selected, and the selected metric evidences are sorted according to the arrangement order of the detection points; And the sorted measurement evidence is stored in the measurement data set in sequence; S53, construct an empty measurement evidence as the preset evidence, and select two measurement evidences from the measurement data set to form an evidence pair; first calculate the product of two basic probability function values ​​belonging to the same risk level in the evidence pair, and record the product as the first product; then calculate the product of the basic function probability value of each risk level of any measurement evidence in the evidence pair and the uncertainty of the other measurement evidence, and record the product as the second product; then calculate the conflict value of the evidence pair according to the content of step S32; Select any risk level of the evidence pair, obtain all first products and second products of the evidence pair at the risk level, sum the obtained first products and second products, compare the summed result with the conflict value of the evidence pair, and store the comparison result under the risk level of the preset evidence; Traverse all risk levels of the evidence pair, and store the obtained comparison results under the risk level corresponding to the preset evidence; at the same time, calculate the uncertainty of the preset evidence, store the uncertainty in the preset evidence, and make the preset evidence a measurement evidence; then store the preset evidence with the uncertainty in the measurement data set, and delete the measurement evidence pair that has been used from the measurement data set; S54, traversing all the measurement evidences in the measurement data set according to the content of step S53, so as to finally obtain a preset evidence storing uncertainty, and the preset evidence is the preliminary fusion evidence of the indicator type corresponding to the measurement data set; S55, generating measurement data sets of different indicator types according to the contents of step S53 to step S54, and then calculating preliminary fusion evidence of various indicators; S56, multiplying the comprehensive weights of various indicators by the respective values ​​in the preliminary fusion evidence of the corresponding indicators, and replacing the values ​​with the products, and then recording the preliminary fusion evidence after all the values ​​have been replaced as preliminary weighted evidence; S57, traversing the preliminary fusion evidence of various indicators according to the content of step S56, and obtaining corresponding preliminary weighted evidence; S58, adding the values ​​belonging to the same risk level in each preliminary weighted evidence, and replacing the values ​​of the risk level in each preliminary weighted evidence with the result of the addition; Traverse all risk levels to complete the replacement of the values ​​in each preliminary weighted evidence, and record the preliminary weighted evidence after the replacement as the final weighted evidence; S59. Traverse all the final weighted evidences according to the contents of step S53 to generate preliminary fusion evidence representing all indicator types. The preliminary fusion evidence is the final evidence after all indicators are fused, and the numerical values ​​at each risk level in the final evidence are the risk probabilities that characterize the risk level of the pipeline corridor, where the risk level corresponding to the maximum risk probability is the risk level of the pipeline corridor.