Measurement and positioning method for offshore precast pile construction

Through the total station line of sight edge measurement and positioning method, the accuracy problem of piling ships caused by the complex offshore construction environment has been solved, the efficient and precise construction of offshore prefabricated piles has been achieved, and the construction quality has been ensured.

CN118441693BActive Publication Date: 2024-10-18SINOHYDRO FOUND ENG +1
View PDF 1 Cites 0 Cited by

Patent Information

Application Number
CN202410904237.6
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-07-08
Publication Date
2024-10-18
Estimated Expiration
2044-07-08

AI Technical Summary

Technical Problem

The complex offshore construction environment makes it difficult for piling ships to meet construction requirements in deep water and high wave conditions, affecting the quality of offshore projects.

Method used

Using the total station line of sight edge measurement and positioning method, through the steps of setting control points, calculating azimuth angles, setting up stations, piling ships in place, piling control and pile foundation re-measurement, the total station and RTK base station are used to accurately position and adjust piling. ship, ensuring the verticality and positional accuracy of the prefabricated piles.

Benefits of technology

It improves the positioning accuracy and construction efficiency of offshore prefabricated pile construction, controls the pile position deviation within 75mm, and meets the quality requirements of offshore projects.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118441693B_ABST
    Figure CN118441693B_ABST
Patent Text Reader

Abstract

The present invention discloses a method for measuring and positioning offshore precast pile construction, including the steps of setting control points, calculating azimuths, setting instrument stations, positioning pile-driving ships, controlling pile driving, and re-surveying pile foundations. In the process of measuring and positioning, this method adds at least two control points for setting up total stations, so that the angle formed by the observation sight lines of two total stations when observing the same precast pile is 90 degrees, which is more convenient for ship movement and makes positioning more accurate; at the same time, this method also proposes a pile foundation re-surveying method, which uses measuring instruments and drawing tools to obtain the specific coordinates of the precast pile positions remotely, so as to meet the requirements of design and construction specifications and ensure the construction quality of precast piles. Based on this method, the construction deviation of offshore precast piles is controlled, and good results have been achieved in construction.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the field of offshore pile foundation construction, and in particular to a method for measuring and positioning offshore prefabricated pile construction. Background Art

[0002] In recent years, with the continuous increase of offshore construction projects, the requirements for offshore construction quality have also been continuously improved, and offshore construction measurement and positioning have become particularly important. However, due to the particularity of the construction environment, the difficulty of offshore construction measurement and positioning has been greatly increased.

[0003] A pile-driving ship is a type of offshore piling equipment. The piles are installed in the soil layer under the sea through the pile-driving ship. After the piles are installed, wind power generation and other operating platforms can be installed on the piles. During the piling process, the pile-driving ship needs to move back and forth between the operating area and the pile transport ship to perform piling and pile lifting operations. After the positioning system determines the position of the hull, the anchor cable is manually controlled to control the movement of the hull. Due to the ups and downs of the sea, especially when the water is deep and the waves are large, the construction accuracy of the pile-driving ship is difficult to meet the construction requirements. Summary of the invention

[0004] In order to overcome the above shortcomings, the present invention provides a method for measuring and positioning offshore precast pile construction. The present invention uses a total station line of sight trimming measurement and positioning method to control the construction deviation of offshore precast piles, and achieves good results in construction.

[0005] The technical solution adopted by the present invention to solve the technical problem is:

[0006] The measurement and positioning method for offshore precast pile construction includes:

[0007] S1 set control point

[0008] There are at least two control points;

[0009] Based on the precast pile construction axis, a pile row tangent parallel to the axis is obtained, at least one point is selected on one side and the extension line of the pile row tangent, and its coordinates are obtained. The obtained coordinates are staked out to the land of the construction area by the surveying and staking method, and are marked and used as control points;

[0010] S2 calculates the azimuth

[0011] The clockwise angle between the tangent line connecting each control point to the precast pile foundation and the vertical coordinate axis is the azimuth of the control point;

[0012] S3 Instrument Station

[0013] The total station is set up at at least two control points and the sighting orientation is completed. The sighting part of the total station is adjusted and locked according to the azimuth of the control point, so that when the total station observes the same precast pile, the angle formed by the sight line is 90±20°;

[0014] Set up the RTK base station to collect coordinates of the points in use in the construction area;

[0015] S4 piling vessel in place

[0016] After the pile-driving ship has installed the prefabricated piles, the center coordinates of the prefabricated pile position are input into the RTK base station. Through the surveying and setting out method, the pile-driving ship is guided to move slowly to the vicinity of the prefabricated pile position and anchor the ship.

[0017] The observer guides the ship to move slowly by collecting and stirring the anchor rope through the aiming star above the total station telescope until the observer sees the precast pile in the observation field of the total station, and when the vertical wire of the total station is tangent to the edge of the precast pile, it means that the precast pile has been aligned with the correct pile position;

[0018] Fix the anchor rope and use the prefabricated pile's own weight to slowly lower it until it reaches the seabed;

[0019] S5 Pile Driving Control

[0020] When the precast piles cannot sink naturally, the piling ship starts piling the precast piles;

[0021] If the pile position is offset during the hammering process, the observer needs to stop the ship in time and direct the ship to adjust the pile position repeatedly until the prefabricated pile returns to its original position;

[0022] The observer needs to observe the deviation between the prefabricated pile foundation and the vertical wire of the total station at all times. When the observed value (the physical phase estimate in the instrument telescope) is greater than 30 mm, the ship needs to be adjusted;

[0023] The observer needs to adjust the vertical fine-tuning nut of the total station telescope at the same time to observe the verticality of the precast pile. The verticality of the precast pile should be ≤3%. When the precast pile is not parallel to the vertical wire of the instrument, the operation needs to be stopped to adjust the verticality of the precast pile until the precast pile is parallel to the vertical wire of the total station within the field of view of the instrument.

[0024] S6 Pile Foundation Retest

[0025] The observer re-measures the completed prefabricated pile foundation to determine the specific location coordinates of the pile;

[0026] The specific retest method is:

[0027] The S61 observer uses the total station to locate the prefabricated pile foundation that has been completed, and the aiming position is at the height of the pile cut;

[0028] S62 adjusts the horizontal micro-motion nut of the instrument telescope to make the center of the telescope aim at the center of the prefabricated pile. To make the instrument aim more accurately, the auxiliary vertical wire in the instrument telescope can be used for reference;

[0029] S63 After the center of the precast pile is determined and sighted, the coordinates of the center point of the precast pile are measured using the prism-free measurement function of the instrument, and the average value is taken after three measurements;

[0030] S64 uses drawing software to first input the coordinates of a certain control point, then input the coordinates of the center point of the precast pile measured by S63, connect the two coordinate points with a straight line, and draw a circle with the same diameter as the precast pile with the second coordinate point as the center (the diameter of the precast pile is 900mm). At this time, the straight line is extended to connect with the other side of the circle to form an intersection point, which is the actual center of the precast pile.

[0031] The coordinates of the center of the precast pile are obtained through the query command, and compared with the designed pile position coordinates to calculate the pile position deviation value, which should be ≤75mm.

[0032] As an improvement of the above technical solution, the tangent line of the pile row parallel to the axis obtained based on the precast pile construction axis is the tangent line of the pile row located outside the construction axis.

[0033] As an improvement of the above technical solution, the vertical coordinate axis refers to the north direction of the geodetic coordinate system, that is, the starting direction of the azimuth is due north.

[0034] As an improvement of the above technical solution, when performing backsight orientation with a total station, the distance between the selected backsight point and the instrument should not be less than the distance between the instrument and the prefabricated pile position.

[0035] As an improvement to the above technical solution, after the pile foundation has been hammered into the seabed, the adjustment of the ship movement should be ≤30mm / time.

[0036] The beneficial effects brought by the present invention are:

[0037] This positioning method is the total station line of sight cutting edge measurement positioning method. In order to facilitate construction measurement and layout, control points are added by measuring turning points during the measurement and positioning process for setting up the total station. When two total stations observe the same precast pile, the angle formed by their observation lines of sight is about 90 degrees. This layout structure makes it easier to move and more efficient to adjust the position of the pile-driving ship, and the positioning is more accurate.

[0038] When adjusting a moving ship, the measuring instrument is always in a locked state, and the horizontal angle displayed by the instrument is consistent with the azimuth calculated by this method, which is convenient for the observer to contact the ship liaison in real time through a walkie-talkie to guide him to make ship adjustments and control the subsequent piling process.

[0039] At the same time, this method also proposes a pile foundation re-measurement method. Using measuring instruments and drawing tools, the specific coordinates of the precast pile position can be obtained remotely to meet the requirements of design and construction specifications and ensure the construction quality of the precast pile.

[0040] This method is used to control the construction deviation of offshore precast piles, and good results have been achieved in construction. BRIEF DESCRIPTION OF THE DRAWINGS

[0041] The present invention will be further described below in conjunction with the accompanying drawings and specific embodiments.

[0042] Figure 1 This is a schematic diagram of a method for setting control points in S1 of Example 1;

[0043] Figure 2 This is a schematic diagram of the method for calculating the azimuth angle of S2 in Example 1;

[0044] Figure 3 This is a schematic diagram of the station setting method of the S3 instrument in Example 1;

[0045] Figure 4 Schematic diagram of the observer observation method of Example 1 Figure 1 ;

[0046] Figure 5 Schematic diagram of the observer observation method of Example 1 Figure 2 ;

[0047] Figure 6 Schematic diagram of the aiming method for re-surveying the S6 pile foundation in Example 1. DETAILED DESCRIPTION

[0048] The following will be combined with the embodiments of the present invention and the accompanying drawings to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention. Example 1

[0049] This embodiment describes in detail a method for measuring and positioning offshore precast pile construction, comprising the following steps:

[0050] S1 set control point

[0051] There are two control points;

[0052] Based on the precast pile construction axis, a tangent line of the pile row parallel to the axis and located outside the axis is obtained, and a point is selected on one side and the extension line of the tangent line of the pile row, and its coordinates are obtained. The obtained coordinates are staked out to the land of the construction area by the surveying and staking method, and are marked and used as control points;

[0053] According to the accuracy requirements of construction measurement, the control points in this step can be selected by direct measurement point transfer. The transfer point requires that the coordinate error of X (with the north direction N of the geodetic coordinate system as the X axis) and Y (with the east direction E of the geodetic coordinate system as the Y axis) cannot be greater than 2mm;

[0054] Figure 1 to Figure 2 The control point positions set in this embodiment are shown. Figure 1 The method of selecting a suitable point on the extension line of the pile row tangent as the control point is shown; Figure 2 It shows a method of selecting a point on the outside of the pile row tangent (to the side of the ship) and on the extension line (opposite to the ship), and finally obtaining the control point through measurement and layout.

[0055] The control point is set up for setting up two total stations, and according to the control point setting method of this embodiment, when the two total stations observe the same precast pile, the angle formed by their observation sight lines is about 90 degrees. In this way, when commanding the pile-driving ship to adjust its position, it will be more convenient to move (the pile-driving ship is generally parallel to the construction axis, and when adjusting the position of the precast pile, it can only climb the mast forward or backward or lift the mast backward, and move the ship left and right by retracting and releasing the anchor rope), and the observation and positioning will be more accurate.

[0056] S2 calculates the azimuth

[0057] The clockwise angle between the tangent line connecting each control point to the precast pile foundation and the vertical coordinate axis is the azimuth of the control point;

[0058] Reference Figure 2 This step can be performed in CAD software. For example, on the drawing, connect the control point CP4 and the control points JE and JF to the outer circle tangent of the construction pile position. The clockwise angle between the tangent and the vertical coordinate axis in the CAD drawing (the north direction of the geodetic coordinate system) is the azimuth of the control point where the tangent is located, that is, the starting direction of the azimuth is due north.

[0059] S3 Instrument Station

[0060] Reference Figure 3 , set up the total station at the control point CP4 and the control point JF, aim at the backsight point after centering and leveling, and complete the backsight orientation. In the positioning process of this embodiment, the measuring instrument must be backsight oriented (that is, the degree plate is zeroed). Only after the backsight orientation is completed, the horizontal angle displayed on the instrument is the azimuth;

[0061] Adjust the collimator of the total station and lock it according to the azimuth of the control point. Figure 4 , Figure 5 , when the total station observes the same precast pile, the angle formed by its observation sight line should be greater than 70° and less than 110°, preferably 90°;

[0062] At this step, it should be noted that the centering error when setting up the instrument and the prism of the backsight point cannot be greater than the specification requirements, that is, ≤1mm. The backsight collimation error cannot be greater than the specification requirements, that is, ≤1mm; at the same time, the distance between the backsight point and the instrument should not be less than the distance between the instrument and the prefabricated pile position.

[0063] Afterwards, the RTK base station was set up and the mobile station was used to collect coordinates of the points in use in the construction area;

[0064] After the coordinates are collected, point correction is first performed. After the correction is completed, the control points are measured and collected for the second time and compared with the original coordinates of the control points to check that the coordinate error is ≤3mm.

[0065] S4 piling vessel in place

[0066] After the pile-driving ship has installed the prefabricated piles, the center coordinates of the prefabricated pile position are input into the RTK base station. Through the surveying and setting out method, the pile-driving ship is guided to move slowly to the vicinity of the prefabricated pile position and anchor the ship. At this time, the two total stations have been adjusted and locked according to the calculated pile position azimuths.

[0067] The observer guides the ship to move slowly by collecting and stirring the anchor rope through the aiming star above the total station telescope until the observer sees the precast pile in the observation field of the total station, and the vertical wires of the total station are tangent to the edge of the precast pile, indicating that the precast pile has been aligned with the correct pile position;

[0068] Fix the anchor rope and use the prefabricated pile's own weight to slowly lower it until it reaches the seabed;

[0069] S5 Pile Driving Control

[0070] When the precast piles cannot sink naturally, the piling ship starts piling the precast piles;

[0071] If the pile position is offset during the hammering process, the observer needs to stop the ship in time and direct the ship to adjust the pile position repeatedly until the prefabricated pile returns to its original position;

[0072] The observer needs to observe the deviation between the prefabricated pile foundation and the vertical wire of the total station at all times. When the observed value (the physical phase estimate in the instrument telescope) is greater than 30mm, the ship needs to be adjusted; if the observed value is ≤30mm, no adjustment is required and the piling operation can continue;

[0073] The observer needs to adjust the vertical fine-tuning nut of the total station telescope at the same time to observe the verticality of the precast pile. The verticality of the precast pile should be ≤3%. When the precast pile is not parallel to the vertical wire of the instrument, the operation needs to be stopped and the driver of the pile-driving ship needs to be instructed to adjust the verticality of the precast pile until the precast pile is parallel to the vertical wire of the total station within the field of view of the instrument.

[0074] At this time, due to the waves, the ship will be offset, and the observer needs to re-instruct the ship driver to align the pile position until the prefabricated piles are in the correct position before construction can continue.

[0075] When the pile foundation has been hammered into the seabed, if it encounters soft silt or hard reefs, the precast pile will tilt and move. At this time, the observer should stop the operation in time, direct the ship to move, and adjust the precast pile. However, since the precast pile has entered the seabed, if the adjustment of the pile-driving ship is too large, it will cause damage to the precast pile. Therefore, the movement of the ship should be adjusted ≤30mm / time. After one adjustment, the operation should continue. After hammering 1-3 times, if there is still a deviation, stop and continue to adjust, and then continue construction. Repeat several times until the precast pile returns to its original position.

[0076] S6 Pile Foundation Retest

[0077] The observer re-measures the completed precast pile foundation to determine the specific location coordinates of the pile. After the precast pile construction is completed and the construction ship moves away, the observer needs to conduct actual measurement of the precast pile to determine the final pile position coordinates.

[0078] The specific retest method is:

[0079] The S61 observer uses the total station to locate the prefabricated pile foundation that has been completed, and the aiming position is at the height of the pile cut;

[0080] S62 adjusts the horizontal micro-motion nut of the instrument telescope to make the center of the telescope aim at the center of the prefabricated pile. In order to make the instrument aim more accurately, refer to Figure 6 , you can use the auxiliary vertical wire in the instrument telescope for reference;

[0081] S63 After the center of the precast pile is determined and sighted, the coordinates of the center point of the precast pile are measured using the prism-free measurement function of the instrument, and the average value is taken after three measurements;

[0082] S64 uses CAD drawing software to first input the coordinates of a certain control point, then input the coordinates of the center point of the precast pile measured by S63, connect the two coordinate points with a straight line, and draw a circle with the same diameter as the precast pile (the diameter of the precast pile is 900mm) with the second coordinate point as the center. At this time, extend the straight line to connect with the other side of the circle, and the intersection point is the actual center of the precast pile;

[0083] The coordinates of the center of the precast pile are obtained through the query command, and compared with the designed pile position coordinates to calculate the pile position deviation value, which should be ≤75mm.

[0084] It should be noted that the above is only a preferred embodiment of the present invention and is not intended to limit the present invention. Although the present invention has been described in detail with reference to the aforementioned embodiments, it is still possible for those skilled in the art to modify the technical solutions described in the aforementioned embodiments or to make equivalent substitutions for some of the technical features therein. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principles of the present invention should be included in the protection scope of the present invention.

Claims

1. A method for measuring and positioning offshore precast pile construction, characterized in that: include S1 set control point At least two control points are provided; based on the precast pile construction axis, a tangent line of the pile row parallel to the axis is obtained, at least one point is selected on one side and the extension line of the tangent line of the pile row, and its coordinates are obtained, and the obtained coordinates are laid out to the land of the construction area by the surveying and laying out method, and are marked and used as control points; The tangent line of the pile row parallel to the axis obtained based on the construction axis of the precast pile is the tangent line of the pile row located outside the construction axis; S2 calculates the azimuth The clockwise angle between the tangent line connecting each control point to the precast pile foundation and the vertical coordinate axis is the azimuth of the control point; S3 Instrument Station The total station is set up at at least two control points and the sighting orientation is completed. The sighting part of the total station is adjusted and locked according to the azimuth of the control point, so that when the total station observes the same precast pile, the angle of its observation sight line is 90±20°; the RTK base station is set to collect the coordinates of the points in use in the construction area; S4 piling vessel in place After the pile-driving ship has installed the prefabricated pile, the center coordinates of the prefabricated pile position are input into the RTK base station. Through the surveying and setting out method, the pile-driving ship is guided to move slowly to the vicinity of the prefabricated pile position, and the ship is anchored and fixed; the observer guides the ship to move slowly by retracting and stirring the anchor rope through the total station telescope until the observer sees the prefabricated pile in the observation field of the total station, and when the vertical wire of the total station is tangent to the edge of the prefabricated pile, it means that the prefabricated pile has been aligned with the correct pile position; the anchor rope is fixed, and the prefabricated pile is slowly lowered by its own gravity until it enters the seabed; S5 Pile Driving Control When the precast piles cannot sink naturally, the piling ship starts piling the precast piles; During the pounding process of the pile-driving ship, if the pile position is offset, the observer needs to stop in time and direct the ship to adjust the pile position repeatedly until the precast pile returns to its original position; the observer needs to observe the deviation between the precast pile foundation and the vertical wire of the total station at all times, and the ship needs to be adjusted when the observed value is greater than 30mm; the observer needs to adjust the vertical fine-tuning nut of the total station telescope at the same time to observe the verticality of the precast pile. When the precast pile is not parallel to the vertical wire of the instrument, the operation needs to be stopped to adjust the verticality of the precast pile until the precast pile is parallel to the vertical wire of the total station within the field of view of the instrument; S6 Pile Foundation Retest The observer re-measures the completed prefabricated pile foundation to determine the specific location coordinates of the pile; the specific re-measurement method is: The S61 observer uses the total station to locate the prefabricated pile foundation that has been completed, and the aiming position is at the height of the pile cut; S62 Adjust the instrument telescope so that the center of the telescope is aligned with the center of the prefabricated pile, and use the auxiliary vertical wire in the instrument telescope for reference; S63 After the center of the precast pile is determined, the coordinates of the center point of the precast pile are measured by an instrument, and the average value is obtained by measuring three times; S64 uses drawing software to first input the coordinates of a control point, then input the coordinates of the center point of the precast pile measured by S63, connect the two coordinate points with a straight line, and draw a circle with the same diameter as the precast pile with the second coordinate point as the center. At this time, extend the straight line to connect with the other side of the circle to form an intersection point, which is the actual center of the precast pile; obtain the coordinates of the center of the precast pile by query, and compare them with the designed pile position coordinates to calculate the pile position deviation value, which should be ≤75mm.

2. The offshore precast pile construction measurement and positioning method according to claim 1 is characterized by: The vertical coordinate axis refers to the north direction of the geodetic coordinate system, that is, the starting direction of the azimuth is due north.

3. The offshore precast pile construction measurement and positioning method according to claim 1 is characterized by: When performing backsight orientation of the total station, the distance between the selected backsight point and the instrument should not be less than the distance between the instrument and the prefabricated pile position.

4. The offshore precast pile construction measurement and positioning method according to claim 1 is characterized by: When the pile foundation has been hammered into the seabed, the adjustment of ship movement should be ≤30mm / time.

5. The offshore precast pile construction measurement and positioning method according to claim 1 is characterized by: When observing the verticality of precast piles, the verticality at the bottom of the precast piles should be ≤3%.