A slope anchor with high anchoring force
By using glass wire cloth and temperature adjustment devices in slope anchors, fiberglass material is formed, and combined with segmented grouting technology, the problems of poor anchoring effect and long curing time of traditional anchors are solved, and the anchoring force and construction efficiency are improved , ensuring curing quality and compactness.
Patent Information
- Application Number
- CN202410935886.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-12
- Publication Date
- 2024-11-08
- Estimated Expiration
- 2044-07-12
AI Technical Summary
The anchoring effect of traditional slope anchors is affected by the nature of the soil layer and the construction process. The grouting and curing time is long, and the curing time is longer in low-temperature environments. It is easily affected by soil layer disturbances, affecting the anchoring force.
A high-anchoring force slope anchor rod is designed, adopting the hollow structure of the anchor rod main body, the conical body is connected to the molded tube, and a glass wire cloth and a temperature adjustment device are installed in the molded tube. The glass wire cloth is expanded to form a fiberglass material by injecting epoxy resin, combined with The temperature adjustment device of the sliding plate and partition plate improves the curing speed and quality, and realizes segmented perfusion through multiple sets of grouting holes and pressure-sensitive diaphragms to reduce bubble risk.
The anchoring force between the anchor rod and the slope is improved, the curing quality and construction efficiency are ensured, the curing defects caused by excessive temperature are avoided, the bubble risk during the infusion process is reduced, and the anchoring quality is ensured.
Smart Images

Figure CN118461595B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of municipal slope anchor rods, and in particular to a slope anchor rod with high anchoring force. Background Art
[0002] Slope anchor is a common engineering equipment, mainly used to reinforce slopes and prevent disasters such as landslides. Traditional slope anchors are mainly fixed in the soil layer by mechanical means, and then the anchor is tightly combined with the soil layer by grouting and other methods, thereby improving the anchoring force of the anchor. However, the anchoring effect of this method is often affected by factors such as soil properties and construction technology, and it is difficult to achieve the ideal effect.
[0003] In addition, after the anchor construction, it is necessary to wait for the grouting to solidify. Generally, the anchor grouting solidification time is relatively long, and the lower the construction environment temperature, the longer the solidification time required. If the solidification time is long, the disturbance of the soil layer inside the slope due to other factors may further affect the grouting solidification effect and quality, thereby affecting the anchoring force between the anchor and the soil layer. Summary of the invention
[0004] In order to solve the above technical problems, the present invention provides a high anchoring force slope anchor, and the technical solution adopted is as follows:
[0005] A high anchoring force slope anchor, comprising an anchor body, the interior of the anchor body is hollow, the anchor body is provided with a plurality of grouting holes along the length direction, a cone is provided at the front end of the anchor, a forming tube is connected between the cone and the anchor, the forming tube is provided with a plurality of injection holes along the circumferential direction, glass cloth is provided outside the injection holes, the glass cloth is in the shape of long strips and distributed along the length direction of the anchor body, one end close to the cone is fixedly connected to the forming tube, and the other end is a free end; and a temperature regulating device is also fixedly connected to one end of the forming tube close to the cone.
[0006] Furthermore, the temperature regulating device includes a sliding plate and a partition plate, the sliding plate and the inner wall of the forming tube form a closed heating chamber, and the sliding plate is slidably connected along the axial direction of the forming tube, the partition plate divides the heating chamber into a calcium hydroxide chamber and a water chamber, and the partition plate is composed of a first split plate and a second split plate, one end of the first split plate is fixedly connected to the sliding plate, and the other end is fixedly connected to a connecting rod and slidably connected to the inside of the second split plate, one end of the second split plate away from the first split plate is fixedly connected to the forming tube, a connecting hole for connecting the calcium hydroxide chamber and the water chamber is provided on the second split plate, and a baffle is also slidably connected to the inside of the second split plate, one end of the baffle is fixedly connected to the connecting rod, and in the initial state when the sliding plate is not subject to external pressure, the baffle blocks the connecting hole, and the calcium hydroxide chamber and the water chamber are not connected.
[0007] Furthermore, a spring is connected between one end of the baffle away from the connecting rod and the inner wall of the second split plate.
[0008] Furthermore, the forming tube is made of any one of copper, aluminum and titanium alloy.
[0009] Furthermore, a fixing groove is provided on the outer wall of the forming tube, and the pouring hole and the glass cloth are both located in the fixing groove.
[0010] Furthermore, a pressure-sensitive membrane is provided on the grouting hole, and the rupture pressure of the multiple groups of the pressure-sensitive membranes gradually increases from the conical body to the outer end of the anchor rod.
[0011] The beneficial effects of the present invention are:
[0012] 1. Glass cloth is set on the forming tube at the end of the anchor rod. By pouring epoxy resin into the anchor rod, the glass cloth can be expanded outward, so that the glass cloth and epoxy resin are mixed and cured to form an expansion part of glass fiber reinforced plastic material, thereby enhancing the anchoring force between the end of the anchor rod and the slope. In addition, when the anchor rod is inserted into the drill hole, the glass cloth is tightly attached to the surface of the end of the anchor rod, which can reduce the soil layer from entering the anchor rod to a certain extent, ensuring the later curing effect and curing quality;
[0013] 2. A temperature regulating device is set inside the forming tube to regulate the temperature during the curing process of epoxy resin and glass cloth, thereby effectively improving the curing speed and quality, and further effectively improving the construction efficiency;
[0014] 3. The temperature regulating device is composed of a sliding plate and a partition plate. When epoxy resin is poured into the anchor rod, the sliding plate slides along the inner wall of the forming tube under pressure, thereby driving the first split plate to slide along the second split plate. The first split plate drives the connecting rod to push the baffle plate inward, so that the connecting hole is opened, and calcium hydroxide enters the water cavity and releases heat after mixing with water, thereby heating the forming tube and improving the curing efficiency of the epoxy resin and glass cloth near the forming tube. Moreover, when the temperature reaches a certain level, the internal pressure increases due to the temperature increase, and the pressure on the sliding plate is equal to or less than the internal air pressure of the calcium hydroxide cavity and the water cavity. At this time, the sliding plate slides outward to drive the first split plate and the connecting rod to move outward. The baffle plate is reset to the outside under the action of the spring and blocks the connecting hole. Calcium hydroxide and water stop mixing, thereby adjusting the internal temperature of the forming tube to avoid defects such as bubbles in the curing process of epoxy resin and glass cloth caused by excessive temperature.
[0015] 4. There are multiple groups of grouting holes arranged along the axial direction on the anchor body. Pressure-sensitive diaphragms with different bursting pressures are arranged in the grouting holes, and the bursting pressure gradually increases from the inside to the outside. The anchor is poured in sections from the inside to the outside, which can reduce the risk of bubbles or cavities during the pouring process, effectively improve the density of the grouting, and ensure the quality of anchoring. BRIEF DESCRIPTION OF THE DRAWINGS
[0016] Figure 1 Schematic diagram of the structure of the present invention
[0017] Figure 2 for Figure 1 Enlarged diagram of the middle A part
[0018] Figure 3 Schematic diagram of the temperature control device during grouting into the anchor rod
[0019] Figure 4 Schematic diagram of the anchor structure after pouring
[0020] Among them: 1-anchor body, 2-forming tube, 3-conical body, 4-grouting hole, 5-pressure sensitive diaphragm, 6-fixing groove, 7-glass cloth, 8-pouring hole, 9-sliding plate, 10-first split plate, 11-second split plate, 12-connecting rod, 13-baffle, 14-connecting hole, 15-first slide groove, 16-second slide groove, 17-spring, 18-expansion part. DETAILED DESCRIPTION
[0021] The exemplary embodiments of the present disclosure will be described in more detail below with reference to the accompanying drawings. Although the exemplary embodiments of the present disclosure are shown in the accompanying drawings, it should be understood that the present disclosure can be implemented in various forms and should not be limited by the embodiments set forth herein. On the contrary, these embodiments are provided to enable a more thorough understanding of the present disclosure and to fully convey the scope of the present disclosure to those skilled in the art.
[0022] In the description of the invention, it is necessary to understand that the terms "longitudinal", "lateral", "up", "down", "front", "back", "left", "right", "vertical", "horizontal", "top", "bottom", "inside" and "outside" etc. indicating orientations or positional relationships are based on the orientations or positional relationships shown in the accompanying drawings and are only for the convenience of describing the invention, rather than indicating or implying that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as a limitation on the invention.
[0023] In this embodiment, the end of the anchor body 1 close to the cone 3 is defined as the inner end, and the end away from the cone 3, that is, the end located on the slope surface, is defined as the outer end.
[0024] like Figure 1-Figure 4A high anchoring force slope anchor shown in the figure includes an anchor body 1, a forming tube 2 and a cone 3. The anchor body 1 is provided with a perfusion channel distributed along its own axial direction. The forming tube 2 is coaxially fixedly connected to one end of the inner side of the anchor body 1. A plurality of groups of perfusion holes 8 are provided on the outer surface of the forming tube 2 along the circumferential direction. Glass fiber cloth 7 is provided on the outer side of the perfusion holes 8. The forming tube 2 is made of aluminum alloy material with good thermal conductivity and is also provided with a temperature regulating device. The cone 3 is fixedly connected to one end of the inner side of the forming tube 2.
[0025] Specifically, three groups of grouting holes 4 are axially arranged on the outer wall of the anchor body 1, and pressure-sensitive diaphragms 5 are arranged inside the grouting holes 4. The rupture pressure of the pressure-sensitive diaphragms 5 in the three groups of grouting holes 4 gradually increases from the inside to the outside.
[0026] Through the above structure, grouting can be started from the depth of the anchoring section, which can ensure that the farthest gap is filled with slurry first. As the grouting goes deeper, the gradually increasing pressure can push the slurry into smaller cracks and denser soil layers, thereby improving the permeability and anchoring effect of the slurry. During the grouting process, the gradually increasing pressure helps to squeeze out the air and groundwater in the hole, reduce the formation of bubbles and cavities, and thus improve the grouting density and the bearing capacity of the anchor rod.
[0027] Forming tube 2 Figure 2 and Figure 3 As shown, the whole is a cylindrical shell structure with an open left end and a cover on the right end. A plurality of groups of fixed grooves 6 are arranged along the circumferential direction on the outer surface of the forming tube 2. Glass cloth 7 is arranged in the fixed groove 6. The inner end of the glass cloth 7 is fixedly connected to the forming tube 2, and the outer end is a free end. The length of the glass cloth 7 is not greater than the length of the fixed groove 6, and the thickness is less than the depth of the fixed groove 6. A plurality of groups of injection holes 8 are also arranged on the forming tube 2. The injection holes 8 are distributed through the wall thickness of the forming tube 2 and the fixed groove 6. In the initial state, that is, the state without grouting, the glass cloth 7 fits the inside of the fixed groove 6 as a whole and blocks the injection holes 8.
[0028] When epoxy resin is poured into the anchor body 1, the epoxy resin first pushes the glass cloth 7 outward through the pouring hole 8, and the epoxy resin and the glass cloth 7 are mixed and solidified to form a Figure 4 The expansion part 18 made of fiberglass as shown can effectively improve the strength of the expansion part 18 through this structure, thereby improving the anchoring force between the anchor rod and the slope soil layer; and during the grouting process, after the expansion part 18 is formed, the pressure-sensitive diaphragms 5 in the three groups of grouting holes 4 are ruptured in turn and form a solidified part on the outside. The use of segmented grouting from the inside to the outside combined with a gradually pressurized grouting method can reduce the risk of generating bubbles or cavities during the grouting process, effectively improve the density of the grouting, and ensure the anchoring quality.
[0029] The temperature regulating device comprises a sliding plate 9, a first split plate 10, a second split plate 11, a connecting rod 12 and a baffle 13. The sliding plate 9 is connected to the inside of the forming tube 2 along the axial direction of the forming tube 2, and a closed heating chamber is formed between the sliding plate 9 and the forming tube 2. The outer end of the first split plate 10 is fixedly connected to the sliding plate 9, and the inner end is fixedly connected to the connecting rod 12 and is slidably connected to the inside of the second split plate 11. The first split plate 10 and the second split plate 11 divide the heating chamber into a calcium hydroxide chamber and a water chamber. The second split plate 11 is provided with a There are connecting holes 14 extending vertically through the thickness direction of the plate, and a first slide groove 15 and a second slide groove 16 are arranged inside. The first slide groove 15 extends outward from an inner end of the second split plate 11 to the connecting hole 14. The second slide groove 16 is located in the right inner part of the second split plate 11 and the outer end is connected to the connecting hole 14. The baffle 13 is slidably connected to the second slide groove 16 and the inside of the connecting hole 14. The inner end of the baffle 13 is fixedly connected to the connecting rod 12, and a spring 17 is connected between the outer end and the second slide groove 16. The length of the spring 17 is distributed along the axial direction of the forming tube 2.
[0030] In such Figure 2 In the initial state shown, the spring 17 is in a naturally extended state, at which time the sliding plate 9 is not subjected to external pressure, and the baffle 13 completely blocks the connecting hole 14. When epoxy resin is poured into the anchor body 1, the sliding plate 9 is subjected to pressure to move inward, and the sliding plate 9 drives the first split plate 10, the connecting rod 12 and the baffle 13 to move inward. As the pouring pressure gradually increases, the baffle 13 continues to move inward until it reaches the position shown in FIG. Figure 3 In the state shown, the baffle 13 opens the connecting hole 14, and the connecting rod 12 is located inside the connecting hole 14 and does not block or significantly obstruct the connecting hole 14. At this time, calcium hydroxide falls into the water cavity through the connecting hole 14, reacts with water and releases heat, and transfers heat to the expansion part 18 formed by the mixture of glass cloth 7 and epoxy resin through the forming tube 2. By heating the glass cloth 7 and the epoxy resin, the temperature conditions for the mixed curing of the two can be ensured under the low-temperature construction environment, which effectively improves the curing speed and curing quality of the expansion part 18; moreover, when the temperature inside the heating chamber is too high, the air pressure inside the heating chamber increases. When the force of the air pressure on the sliding plate 9 is greater than the grouting pressure, the sliding plate 9 will move to the outer end, that is, Figure 2 As shown, the connecting rod 12 and the baffle 13 move to the left, thereby driving the connecting rod 12 and the baffle 13 to move to the left, and then the connecting hole 14 is blocked by the baffle 13, so as to prevent the calcium hydroxide from continuing to mix with the water, thereby avoiding overheating, and further avoiding defects such as bubbles in the expansion portion 18 caused by excessive temperature; of course, in order to prevent the baffle 13 from continuing to slide to the left and causing the connecting hole 14 to leak, a limiting protrusion (not shown in the figure) can be provided on the inner wall of the forming tube 2 on the left side of the sliding plate 9.
[0031] The device forms an expansion portion 18 made of glass fiber reinforced plastics by injecting epoxy resin and mixing it with the glass fiber cloth 7 at the end of the anchor body 1. The strength of the expansion portion 18 is improved while effectively improving the anchoring force between the anchor and the slope soil layer. A temperature regulating device is provided in the forming tube 2 to improve the curing efficiency and curing quality between the epoxy resin and the glass fiber cloth 7, thereby further improving the anchoring quality of the expansion portion 18. The temperature regulating device can prevent the expansion portion 18 from being overheated during the curing process, thereby affecting the curing effect. The use of segmented grouting from the inside to the outside combined with a gradually pressurized grouting method can reduce the risk of bubbles or cavities generated during the grouting process, effectively improve the density of the grouting, and ensure the anchoring quality.
[0032] The above description is only a preferred embodiment of the present invention. It should be pointed out that for ordinary technicians in this technical field, several improvements can be made without departing from the principle of the present invention. These improvements should also be regarded as the protection scope of the present invention.
Claims
1. A high anchoring force slope anchor, comprising an anchor body, wherein the anchor body is hollow inside, characterized in that: The anchor rod body is provided with a plurality of groups of grouting holes along the length direction, a cone is provided at the front end of the anchor rod, a forming tube is connected between the cone and the anchor rod, the forming tube is provided with a plurality of groups of injection holes along the circumferential direction, glass cloth is provided outside the injection holes, the glass cloth is in the shape of long strips and distributed along the length direction of the anchor rod body, one end close to the cone is fixedly connected to the forming tube, and the other end is a free end, a fixing groove is provided on the outer wall of the forming tube, the injection holes and the glass cloth are both located in the fixing groove, the length of the glass cloth is not greater than the length of the fixing groove, and the thickness is less than the fixing groove. The depth of the groove is such that in the initial state, i.e., without grouting, the glass cloth is integrally attached to the inside of the fixed groove and blocks the injection hole; a pressure-sensitive diaphragm is provided on the grouting hole, and the rupture pressure of multiple groups of the pressure-sensitive diaphragms gradually increases from the cone to the outer end of the anchor rod. When epoxy resin is injected into the inside of the anchor rod body, the epoxy resin first pushes the glass cloth outward through the injection hole, and the epoxy resin and the glass cloth are mixed and solidified to form an expansion part of the glass fiber reinforced plastic material; and a temperature regulating device is fixedly connected to the inside of the forming tube near one end of the cone.
2. The high anchoring force slope anchor according to claim 1, characterized in that: The forming tube is made of any one of copper, aluminum and titanium alloy.
Citation Information
Patent Citations
Elastic seepage-proofing plate of barrage and construction method thereof
CN102776867A
Seismic resistant modular anchoring device
CN110424388A
Unmanned aerial vehicle loading device and method in intelligent science and technology environment
CN113581450A
Self-expanding early warning anchor rod and construction method and early warning method thereof
CN117569345A
Anchoring force enhanced full-bonding steel pipe anchor rod with pneumatic nailing function and mounting method thereof
CN117845912A
Cited By
Slotting type high-anchoring-force anchor rod with front end capable of rebounding and expanding and using method
CN121382271A