A construction method for foundation pit excavation in a subway section
Through the optimization of the construction sequence through the excavation of warehouses and finite element analysis, combined with the support of drilling piles, the problems of tunnel upwelling and settlement caused by the excavation of foundation pits in the subway section are solved, and the dual goals of meeting the construction period and tunnel safety and stability are achieved.
Patent Information
- Application Number
- CN202410708873.1
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2024-06-03
- Publication Date
- 2024-11-26
- Estimated Expiration
- 2044-06-03
AI Technical Summary
The excavation of foundation pits in the subway section will cause the tunnel to float and settle, causing cracks and leakage of tunnel pipes, and the construction period will be tight, making it difficult to ensure the safety and stability of existing tunnels and the completion of structural construction on schedule.
The excavation construction method of separate warehouses is adopted, and the plot is divided according to the width and construction period requirements of the post-pouring band width and construction period. The excavation sequence is set according to the principle of 2 warehouses and 2 warehouses jumping, and a finite element model is established for analysis, so as to optimize the construction sequence and support measures. , reduce the amount of soil unloading, and use drilled piles and three-axis mixing pile water stop curtains for support.
It effectively reduces the settlement impact of the tunnel, meets the construction period requirements, ensures the safety and stability of the tunnel, and combines finite element analysis and BIM to obtain the optimal warehousing and construction sequence, reducing the impact of soil layer unloading on the deformation of the tunnel.
Smart Images

Figure CN118469766B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of foundation pit construction, and in particular to a foundation pit excavation construction method in a section adjacent to a subway. Background Art
[0002] With the rapid development of the city, the construction projects along and around the subway lines are increasing. In a certain project, there is a subway tunnel section below the proposed structure. The excavation of the foundation pit and the structural construction are the process of unloading and loading, which will cause the tunnel to float and sink. In severe cases, it will cause cracks in the tunnel segments and leakage, which will pose a great safety risk to the existing tunnel. At the same time, the project construction schedule is tight. How to ensure the safety and stability of the existing tunnel while excavating the foundation pit and ensure that the structural construction is completed on schedule is the current problem. Summary of the invention
[0003] The invention provides a foundation pit excavation construction method for a section adjacent to a subway, which can meet the construction period requirement on the one hand, and reduce the influence on the settlement of the subway tunnel on the other hand.
[0004] The technical problem to be solved is: excavation of the foundation pit above the existing subway will cause the tunnel to float, and in severe cases it will cause cracks in the tunnel segments and leakage. At the same time, the project construction schedule is tight. How to ensure the safety and stability of the existing tunnel while excavating the foundation pit, and ensure that the structural construction is completed on schedule.
[0005] In order to solve the above technical problems, the present invention adopts the following technical solutions:
[0006] The present invention provides a construction method for excavating a foundation pit in a subway section, comprising the following steps:
[0007] Step 1: Divide the land into compartments: According to the width of the foundation post-casting belt and the construction period requirements, divide the land into compartments according to the maximum width of the post-casting belt to obtain compartment 1, compartment 2, compartment 3...n compartments. Set the excavation order for each compartment according to the principle of symmetrical construction of 2 compartments and 2 compartments, that is, first construct compartment 1 and 2 at the same time, then construct compartment 3 and 4, and so on. Among them, compartment 1 and 4 are located at the end of the tunnel, and compartment 2 and 3 are located in the middle of the tunnel. Then, the remaining compartments are divided according to the principle of symmetrical construction of skipping compartments;
[0008] Step 2: Determine the construction sequence: excavate the first and second bins simultaneously, and after the bottom slab, top slab and backfilling are completed, excavate the third and fourth bins. After the top slabs of the third and fourth bins are completed, excavate the next bin. Subsequent construction is carried out after the basement bottom slab is completed.
[0009] Step 3: Modeling: Establish a finite element model, solve it according to the following working conditions, and obtain the internal force diagram and displacement diagram; the calculation conditions are: initial ground stress field and displacement are cleared → existing subway structure construction and displacement is cleared → excavation of the first and second warehouses → completion of the construction of the first and second warehouse basement floor and top plates and backfilling, followed by excavation of the third and fourth warehouses → completion of the construction of the third and fourth warehouse floor and top plates, followed by excavation of the fifth and sixth warehouses → completion of the construction of the fifth and sixth warehouse floor plates, followed by excavation of the seventh and eighth warehouses → completion of the construction of the seventh and eighth warehouse floor plates, followed by excavation of the ninth and tenth warehouses → construction of the remaining basements in this block → construction of ground buildings;
[0010] Step 4: Verification: Verify the displacement of the tunnel and track through the displacement cloud map and the existing deformation of the tunnel; select the maximum deformation position of the segment, select the fitting range and function for curve fitting, and obtain the deformation curve equation. Finally, the curve equation is derived to obtain the tunnel deformation curvature radius to verify whether it meets the structural safety control indicators in the specification; select the tunnel maximum deformation condition, perform shield segment joint opening, track lateral height difference, track height difference, and track spacing verification, and determine whether the above verification meets the requirements of the specification. If the above parameters meet the requirements, the compartment division is reasonable, and the construction is carried out strictly in accordance with the compartment division and simulated working conditions. Otherwise, reduce the compartment width, increase the number of compartments, and repeat the above process to verify again;
[0011] Step 5: Foundation pit excavation and construction: Carry out foundation pit excavation and basement structure construction according to the above working conditions.
[0012] The present invention provides a construction method for excavating a foundation pit near a subway section. Further, in step 3, a finite element model is established to perform geometric modeling on the structure to be analyzed;
[0013] Mesh the geometric model, divide the structure into a finite number of small units, and define material properties. During the modeling process, define the material properties of each material, including elastic model, Poisson's ratio, and density;
[0014] Define constraints and external loads in the model;
[0015] After mesh optimization, the finite element model is established and solved according to the set working conditions to obtain the internal force diagram and displacement diagram.
[0016] The present invention discloses a foundation pit excavation construction method for a section adjacent to a subway. Further, parameters are calculated, and Plaxis software is used in combination with construction monitoring data of a constructed plot to invert the stratum stiffness parameters to obtain a maximum horizontal displacement diagram and a maximum vertical displacement diagram. The maximum horizontal displacement of retaining piles and the maximum displacement of surface settlement from the monitoring data of the constructed plot are used, and the maximum horizontal displacement and maximum settlement are calculated with the Plaxis software to determine the stratum stiffness parameters.
[0017] The present invention provides a foundation pit excavation construction method for a subway section. Further, the strata are simplified: similar strata are merged according to the geological profile in the simulation area.
[0018] The present invention provides a foundation pit excavation construction method for a subway section. Further, the construction process is simplified: under the premise of not losing calculation accuracy, the working conditions of important key nodes are considered and minor construction links are omitted, that is, the key node construction is the node that has a greater impact on the load on the upper part of the tunnel, namely earth excavation and loading construction of the upper structure, and the minor nodes are the nodes that have little impact on the cushion layer, waterproofing, and formwork.
[0019] The present invention provides a construction method for foundation pit excavation in a subway section. Further, in step 4, the shield segment joint opening amount is calculated using the following formula: δ≥BD / (ρmin-D / 2)+δ0+δs.
[0020] The present invention provides a construction method for foundation pit excavation in a subway section. Further, in step 5, the foundation pit support adopts the form of bored cast-in-place piles + three-axis mixing piles water-stop curtain.
[0021] The invention discloses a construction method for foundation pit excavation in a section adjacent to a subway station. Further, the earthwork excavation sequence is as follows: the supporting points on the ring beam are determined according to the support construction drawing, the axis of the embedded steel plate is released by a measuring instrument, and then the steel plate is embedded at a corresponding position. After the ring beam concrete is poured and reaches the strength, the earthwork is excavated in layers, and the slope is excavated at a position close to the support structure. After the soil excavation is completed, the cushion layer is poured, and the supporting base supporting points are determined according to the support construction drawing, the axis of the embedded steel plate is released by a measuring instrument, the bottom plate reinforcement is constructed and the steel plate is embedded, the bottom plate concrete is poured, the steel support is welded, the slope is excavated, the remaining cushion layer and the bottom plate are poured, the outer wall and the top plate are cast by formwork, the outer wall is waterproofed and heat-insulated, the fertilizer tank is backfilled to below the steel support outside the wall, the steel support is cut off, waterproofing construction is carried out, and the fertilizer tank is backfilled to the designed elevation.
[0022] Compared with the prior art, the present invention has the following beneficial effects:
[0023] 1. Carrying out excavation in compartments on the land can reduce the impact of excessive one-time soil unloading on the subway, reduce the amount of soil excavation unloading, and reduce the horizontal and vertical deformation of the subway tunnel caused by soil unloading; excavating each compartment according to the principle of symmetrical construction of 2 compartments and 2 compartments, which can meet the construction period requirements on the one hand and reduce the impact on the settlement of the subway tunnel on the other hand;
[0024] 2. Combined with BIM and finite element analysis, the optimal compartment division and construction sequence are obtained to provide guidance for the excavation of existing subway foundation pits;
[0025] 3. The foundation pit is excavated with slope to reduce the amount of soil unloading at one time and reduce the horizontal and vertical deformation of the subway tunnel caused by soil unloading.
[0026] The present invention will be further described below in conjunction with the accompanying drawings. BRIEF DESCRIPTION OF THE DRAWINGS
[0027] Figure 1 It is a schematic diagram of the compartment structure of the present invention. DETAILED DESCRIPTION
[0028] like Figure 1 As shown, the present invention discloses a construction method for excavating a foundation pit in a subway section, comprising the following steps:
[0029] Step 1: Divide the plot into compartments: Divide the plot into compartments according to the width of the foundation post-cast strip and the construction period requirements, and divide the plot into compartments according to the maximum width of the post-cast strip. When dividing the compartments, try to divide them perpendicular to the direction of the subway track to control the number of unloading of a single compartment, and get 1 compartment, 2 compartments, 3 compartments...n compartments. Set the excavation sequence for each compartment according to the principle of symmetrical construction of 2 compartments and 2 compartments, that is, first construct 1 and 2 compartments at the same time, then construct 3 and 4 compartments, and so on. Among them, 1 and 4 compartments are located at the end of the tunnel, 2 and 3 compartments are located in the middle of the tunnel, and then the remaining compartments are divided according to the principle of symmetrical construction of skipping compartments. This application is illustrated by taking 10 compartments of a certain engineering example as an example.
[0030] Step 2: Determine the construction sequence: The first and second chambers are excavated simultaneously. After the construction of the bottom plate, top plate and backfilling of the covering soil is completed, the third and fourth chambers are excavated. After the construction of the top plates of the third and fourth chambers is completed, the next chamber is excavated. The subsequent construction is carried out after the basement bottom plate is completed. The fifth and sixth chambers are constructed in the same way. The second chamber is located in the middle of the tunnel, and the first chamber is located at the end of the tunnel. The simultaneous unloading of these two parts will cause the maximum displacement and floating of the tunnel. Therefore, this part is constructed to the backfilling of the top plate, and the next chamber is constructed after reloading above the tunnel to reduce the differential floating of the tunnel. In addition, this part is constructed first. On the one hand, it reduces the unloading of the soil, avoids the differential floating of the tunnel segments, and ensures that the impact of the unloading of the soil on the subway tunnel is reduced to a minimum, and on the other hand, it meets the construction period requirements.
[0031] Step 3: Modeling and stability verification: The impact of foundation pit excavation on existing stations and sections is indirectly produced through the displacement of soil. Therefore, only by adding soil media to the calculation model can the displacement of the structure be better evaluated. In other words, finite element software with stratum and structural models should be selected to complete the evaluation work.
[0032] The calculation software was selected to use the PLAXIS2D finite element program and the MIDAS GTS large-scale geotechnical and tunnel three-dimensional analysis software to simulate the interaction between the strata and the structure, and to reproduce the stress state of the construction process of the underground project.
[0033] The selection of constitutive model, as a trend prediction, the modified Mohr-Coulomb model can better simulate the different values of elastic modulus under different stress paths when the soil is loaded and unloaded.
[0034] Basic simplifications and assumptions: Due to the complexity of the project, it is impossible to simulate and analyze every construction detail in numerical simulation. At the same time, combined with the actual situation of this project, this numerical simulation made the following simplifications and assumptions:
[0035] 1) Strata simplification: Based on the geological profile in the simulation area, similar strata are merged, that is, the soil layers with smaller content in the soil body are merged into the soil layers with larger content in mechanical parameters such as specific gravity;
[0036] 2) Simplification of construction process: This project design has multiple construction steps. Without losing the calculation accuracy, the important key node conditions are considered and the minor construction links are omitted, that is, the key node construction has a greater impact on the load on the upper part of the tunnel, namely earth excavation, loading construction of the upper structure, such as raft, top plate, backfill, etc. The minor nodes are the nodes with little impact such as cushion layer, waterproofing, formwork, etc.
[0037] 3) Simplified calculation and analysis: The design scheme of the foundation pit of this project is full-section water-stopping. The groundwater in the pit is drained and earth excavation is carried out. This simulation calculation is based on the premise of standardized construction and does not consider the unexpected situation of precipitation outside the pit. The difference between the lateral earth pressure generated by the separate calculation of water and soil and the combined calculation of water and soil is small, so the full stress method of combined water and soil calculation is used for analysis.
[0038] To calculate the parameters, Plaxis software was used in combination with the construction monitoring data of the constructed plots to invert the stratum stiffness parameters and obtain the maximum horizontal displacement diagram and the maximum vertical displacement diagram. The maximum horizontal displacement of the retaining piles and the maximum displacement of the surface settlement from the monitoring data of the constructed plots were used, and the maximum horizontal displacement and maximum settlement were calculated with Plaxis software to determine the stratum stiffness parameters.
[0039] Establish a finite element model and perform geometric modeling of the structure to be analyzed.
[0040] The geometric model is meshed, the structure is divided into a finite number of small units, and the material properties are defined. During the modeling process, the material properties of each material are defined, including the elastic model, Poisson's ratio, density, etc.
[0041] Define constraints and external loads in the model to simulate the stress conditions in actual engineering. Constraints include fixed, hinged, etc., and loads include gravity, overload, etc.
[0042] The meshing module in the Midas software is used to optimize the mesh and complete the establishment of the finite element model. The solution is performed according to the following working conditions to obtain the internal force diagram and displacement diagram.
[0043] The calculation conditions are as follows: initial ground stress field and displacement are cleared → existing subway structure construction and displacement is cleared → excavation of the first and second warehouses → completion of construction of the basement floor and top slabs of the first and second warehouses and backfilling of soil, followed by excavation of the third and fourth warehouses → completion of construction of the floor and top slabs of the third and fourth warehouses, followed by excavation of the fifth and sixth warehouses → completion of construction of the floor slabs of the fifth and sixth warehouses, followed by excavation of the seventh and eighth warehouses → completion of construction of the floor slabs of the seventh and eighth warehouses, followed by excavation of the ninth and tenth warehouses → construction of the remaining basements in this block → construction of ground buildings.
[0044] Select the maximum deformation position of the segment, choose the fitting range and function for curve fitting, get the deformation curve equation, and finally differentiate the curve equation to get the tunnel deformation curvature radius to verify whether it meets the structural safety control indicators in the specification.
[0045] Calculation of shield segment joint opening, δ≥BD / (ρmin-D / 2)+δ0+δs, where δ is the allowable annular joint opening of the sealing gasket in the annular joint under the design water pressure; ρmin is the minimum curve radius of the tunnel longitudinal deformation curve; D is the outer diameter of the lining ring; B is the lining ring width; δ0 is the annular joint gap that may be caused by production and construction errors; δs is the tunnel deflection and joint opening caused by the settlement of adjacent buildings and pile foundations of the tunnel. Under the assumption that the tunnel structure is intact before construction, the minimum curve radius of the tunnel deformation curve, the outer diameter of the tunnel lining, and the ring width are obtained according to numerical simulation, and the annular joint opening δ is calculated to see whether it meets the requirements of the specification.
[0046] Select the working condition where the maximum deformation of the tunnel occurs, and perform verification calculations on the track lateral height difference, track directional height difference, and track spacing. Determine whether the left-line track lateral height difference and the right-line track lateral height difference are less than the control value, whether the maximum left-line track directional height difference and the maximum right-line track directional height difference are less than the control value, and whether the maximum left-line track spacing change and the maximum right-line track directional spacing meet the requirements of the specifications.
[0047] If the above parameters meet the requirements, the compartment division is reasonable and the construction should be carried out strictly in accordance with the compartment division and simulated working conditions. Otherwise, the compartment width should be reduced, the number of compartments should be increased, and the above process should be repeated for verification.
[0048] Step 4: Excavation and construction of foundation pit: According to the above working conditions, the foundation pit excavation and basement structure construction are carried out. The foundation pit support adopts the form of bored cast-in-place piles + three-axis mixing pile water-stop curtain. The excavation order is as follows: the support points on the ring beam are determined according to the support construction drawing, and the axis of the embedded steel plate is released by measuring instruments, and then the steel plate is embedded in the corresponding position. After the ring beam concrete is poured and reaches the strength, the earthwork is excavated in layers, and the slope is excavated near the supporting piles. After the soil excavation is completed, the cushion layer is poured, and the support points of the support base are determined according to the support construction drawings. The axis of the embedded steel plate is released by measuring instruments, the bottom plate reinforcement is constructed and the steel plate is embedded, the bottom plate concrete is poured, and the steel support is welded. A small excavator is used to excavate the slope, pour the remaining cushion layer and bottom plate, support the formwork to cast the exterior wall and top plate, waterproof and heat-insulated the exterior wall, backfill the fertilizer trough to the bottom of the steel outside the wall, cut off the steel support, carry out waterproof construction, and backfill the fertilizer trough to the design elevation.
[0049] During the construction of the corresponding supporting pile ring beam of the bottom plate, steel plates are embedded, and then large slope construction is carried out to reduce the unloading of earth during foundation pit excavation and reduce the impact on the tunnel structure. At the same time, steel plates are embedded on the raft slab, and the deformation of the foundation pit soil and the support structure is coordinated by welding steel diagonal braces on the embedded steel plates.
[0050] Among them, during the excavation of the foundation pit, if there is obvious floating, sand bags will be used as counterweights and evenly distributed loading will be carried out after the bottom plate construction is completed.
[0051] The embodiments described above are merely descriptions of preferred implementation modes of the present invention and are not intended to limit the scope of the present invention. Without departing from the design spirit of the present invention, various modifications and improvements made to the technical solutions of the present invention by ordinary technicians in this field should all fall within the protection scope determined by the claims of the present invention.
Claims
1. A construction method for excavating a foundation pit near a subway section, characterized in that: The following steps are involved: Step 1: Divide the land into compartments: According to the width of the foundation post-casting belt and the construction period requirements, divide the land into compartments according to the maximum width of the post-casting belt, and get compartment 1, compartment 2, compartment 3...n compartments. Set the excavation order for each compartment according to the principle of symmetrical construction of 2 compartments and 2 compartments, first construct compartment 1 and 2 at the same time, then construct compartment 3 and 4, and so on. Among them, compartment 1 and 4 are located at the end of the tunnel, and compartment 2 and 3 are located in the middle of the tunnel. Then, divide the remaining compartments according to the principle of symmetrical construction of skipping compartments; Step 2: Determine the construction sequence: excavate the first and second bins simultaneously, and after the bottom slab, top slab and backfilling are completed, excavate the third and fourth bins. After the top slabs of the third and fourth bins are completed, excavate the next bin. Subsequent construction is carried out after the basement bottom slab is completed. Step 3: Modeling: Establish a finite element model and perform geometric modeling on the structure to be analyzed; Mesh the geometric model, divide the structure into a finite number of small units, and define material properties. During the modeling process, define the material properties of each material, including elastic model, Poisson's ratio, and density; Define constraints and external loads in the model; Optimize the mesh, complete the establishment of the finite element model, solve according to the set working conditions, and obtain the internal force diagram and displacement diagram; the calculation conditions are as follows: initial ground stress field and displacement are cleared → existing subway structure construction and displacement is cleared → excavation of the first and second warehouses → completion of the construction of the first and second warehouse basement floor and top slabs and backfilling, followed by excavation of the third and fourth warehouses → completion of the construction of the third and fourth warehouse floor and top slabs, followed by excavation of the fifth and sixth warehouses → completion of the construction of the fifth and sixth warehouse floor slabs, followed by excavation of the seventh and eighth warehouses → completion of the construction of the seventh and eighth warehouse floor slabs, followed by excavation of the ninth and tenth warehouses → construction of the remaining basements in this block → construction of ground buildings; Step 4: Verification: Verify the displacement of the tunnel and track through the displacement diagram and the existing deformation of the tunnel; select the maximum deformation position of the segment, choose the fitting range and function to perform curve fitting, and obtain the deformation curve equation. Finally, the curve equation is derived to obtain the deformation curvature radius of the tunnel to verify whether it meets the structural safety control indicators in the specification; Select the working condition where the maximum deformation of the tunnel occurs, and calculate the shield segment joint opening, track lateral height difference, track height difference, and track spacing to determine whether the above calculations meet the requirements of the specification. If the above parameters meet the requirements, the compartment division is reasonable, and the construction is carried out strictly in accordance with the compartment division and simulated working conditions. Otherwise, reduce the compartment width, increase the number of compartments, and repeat the above process to calculate again; Step 5: Foundation pit excavation and construction: Carry out foundation pit excavation and basement structure construction according to the above working conditions.
2. The method for excavating a foundation pit near a subway section according to claim 1 is characterized in that: To calculate the parameters, Plaxis software was used in combination with the construction monitoring data of the constructed plots to invert the stratum stiffness parameters and obtain the maximum horizontal displacement diagram and the maximum vertical displacement diagram. The maximum horizontal displacement of the retaining piles and the maximum displacement of the surface settlement from the monitoring data of the constructed plots were used, and the maximum horizontal displacement and maximum settlement were calculated with Plaxis software to determine the stratum stiffness parameters.
3. The method for excavating a foundation pit near a subway section according to claim 1 is characterized in that: Stratigraphic simplification: Similar strata are merged based on the geological profile within the simulation area.
4. The method for excavating a foundation pit near a subway section according to claim 1 is characterized in that: Simplified construction process: Under the premise of not losing calculation accuracy, the working conditions of important key nodes are considered and minor construction links are omitted. The key node construction is the node that has a greater impact on the upper load of the tunnel, namely earth excavation and loading construction of the upper structure. The minor nodes are the nodes that have little impact on the cushion layer, waterproofing, and formwork.
5. The method for excavating a foundation pit near a subway section according to claim 1 is characterized in that: In step 4, the calculation formula for the shield segment joint opening is as follows: δ≥BD / (ρmin-D / 2)+δ0+δs; δ is the allowable annular joint opening of the sealing gasket in the annular joint under the design water pressure; ρmin is the minimum curve radius of the tunnel longitudinal deformation curve; D is the outer diameter of the lining ring; B is the lining ring width; δ0 is the annular joint gap that may be caused by production and construction errors; δs is the tunnel deflection and joint opening caused by the settlement of adjacent buildings and pile foundations.
6. The method for excavating a foundation pit near a subway section according to claim 1, characterized in that: In step 5, the foundation pit support adopts the form of bored cast-in-place piles + three-axis mixing piles water-stop curtain.
7. The method for excavating a foundation pit near a subway section according to claim 6, characterized in that: The order of earth excavation is as follows: determine the support points on the ring beam according to the support construction drawing, use measuring instruments to release the axis of the embedded steel plate, and then embed the steel plate at the corresponding position. After the ring beam concrete is poured and reaches the strength, start the layered excavation of earth, and excavate the slope close to the support structure. After the soil excavation is completed, the cushion layer is poured, and the support points of the support base are determined according to the support construction drawings. Use measuring instruments to release the axis of the embedded steel plate, construct the bottom plate steel bars and embed the steel plate, pour the bottom plate concrete, weld the steel support, excavate the slope, pour the remaining cushion layer and bottom plate, support the formwork to cast the exterior wall and top plate, construct the exterior wall waterproofing and thermal insulation, backfill the fertilizer trough to the bottom of the steel support outside the wall, cut off the steel support, carry out waterproofing construction, and backfill the fertilizer trough to the design elevation.