A green construction dust suppression device
The green construction dust suppression device addresses non-uniform spraying and high costs by using multiple arc-shaped nozzles with a winch mechanism and air supply, achieving efficient dust suppression and temperature control.
Patent Information
- Application Number
- CN202410669443.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2024-05-28
- Publication Date
- 2024-12-13
- Estimated Expiration
- 2044-05-28
AI Technical Summary
Existing dust suppression devices lack efficient and uniform coverage, particularly in areas where construction dust is generated, leading to non-uniform spraying, high manufacturing and maintenance costs, and inadequate temperature control.
A green construction dust suppression device with multiple arc-shaped nozzles and a winch mechanism for angle adjustment, combined with a blower for air supply and a water curtain mechanism for temperature control, ensuring uniform spraying and reduced costs.
The device achieves uniform dust suppression with reduced manufacturing and maintenance costs, enhanced spraying performance, and improved comfort through air-assisted misting and temperature regulation.
Smart Images

Figure CN118477423B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the field of dust reduction equipment, and more specifically to a green construction dust reduction device. Background Art
[0002] Green environmental protection is the theme of the development of the world today, and it has attracted great attention in various fields and industries around the world, and green construction is no exception. A large amount of dust is usually generated during the operation of port coal transportation, urban road construction, raw material yards, power plant coal yards, and construction sites. Therefore, in order to respond to the call for green construction, dust suppression devices are usually installed on the working surface to suppress dust.
[0003] Existing dust suppression devices are generally divided into two categories, namely, vehicle-mounted movable dust suppression devices and column-fixed dust suppression devices. Although column-fixed dust suppression devices have some advantages in actual use, they still have the following shortcomings:
[0004] 1. The existing dust suppression device with fixed column installation usually has one nozzle on the top, which is driven by the corresponding motor to rotate circumferentially or pitch up and down. Such a structure not only has a small number of nozzles, which is not conducive to the simultaneous circumferential coverage of the area around the column, but also drives the movement of the nozzle by the motor, which increases the manufacturing cost and is not conducive to the control of production costs;
[0005] 2. The existing column-fixed dust suppression device lacks a corresponding air supply structure at the nozzle, so that the range of spraying water mist can only be adjusted by the spraying force of the nozzle, which affects the uniformity and spraying range of the spraying water mist;
[0006] Therefore, we proposed a green construction dust reduction device to solve the above problems. Summary of the invention
[0007] In view of the problems existing in the prior art, the purpose of the present invention is to provide a green construction dust suppression device, which opens no less than 4 air outlets on the outer wall of the top of the hollow column, and no less than 4 arc-shaped nozzles are arranged inside the air outlet, so that the top of the hollow column can spray water mist in a circular area at the same time, and the number of arc-shaped nozzles is large, so that the spraying surface is more uniform and the water mist spraying performance is stronger; at the same time, the pitch angle of the arc-shaped nozzle is adjusted by a winch mechanism in conjunction with a steel cable and a pulling member, which has a simple structure, low manufacturing cost, low maintenance rate, and greatly reduces the installation cost. The overall manufacturing cost and the probability of later maintenance are reduced; and a blower for air supply is installed inside the equipment cabinet, and is connected to the inside of the hollow column through a blower pipe, so that air can be blown at the air outlet, and the uniformity and spraying range of the water mist sprayed by the arc-shaped nozzle are assisted, which is convenient for use on the construction site; and when the wind passes through the inside of the hollow column and is blown out from the air outlet, a water curtain mechanism is also provided inside the hollow column, so that water can pass through the moist cylindrical water curtain paper, thereby reducing the temperature of the wind discharged from the air outlet, which is beneficial to reducing the temperature of the surrounding area of the hollow column and improving the comfort during use.
[0008] To solve the above problems, the present invention adopts the following technical solutions.
[0009] A green construction dust suppression device comprises a hollow column and an equipment cabinet, wherein both ends of the hollow column are sealed structures, a nozzle mechanism, a water curtain mechanism, a winch mechanism and a drainage mechanism are sequentially arranged inside the hollow column from top to bottom, a partition is fixedly installed inside the equipment cabinet, a blower is fixedly installed on the top of the partition, a water supply pump is fixedly installed at the bottom of the inner wall of the equipment cabinet located at the bottom of the partition, and a water pipe manifold is fixedly installed on one side of the inner wall of the equipment cabinet located on one side of the water supply pump;
[0010] The spray head mechanism comprises an upper mounting plate and a lower mounting plate fixedly mounted on the inner wall of the hollow column, the upper mounting plate and the lower mounting plate are both symmetrically and equidistantly provided with not less than 4 sliding holes, and a pulling piece is slidably connected between two corresponding sliding holes in the longitudinal direction, a supporting spring is sleeved on the top of the pulling piece, and the top and bottom of the supporting spring are respectively in contact with the top of the pulling piece and the top of the upper mounting plate, a metal ring strip is fixedly welded between the upper mounting plate and the lower mounting plate at the position corresponding to the pulling piece, and not less than 4 arc-shaped spray heads are rotatably connected inside the metal ring strip, an ear piece is fixedly welded on one side of the arc-shaped spray head, and the ear piece is rotatably connected inside the pulling piece through a pin shaft, and a water supply hose is fixedly connected to the water inlet end of the bottom of the arc-shaped spray head, and a group of arc-shaped avoidance holes are also provided on the lower mounting plate, and the bottom of the water supply hose extends to the bottom of the hollow column through the corresponding arc-shaped avoidance holes;
[0011] An inspection opening is provided on one side of the outer wall of the hollow column, and a sealing plate is fixedly installed on the outside of the inspection opening. The water curtain mechanism includes an upper limit mesh plate and a lower limit mesh plate fixedly installed on the inner wall of the hollow column, and the positions of the upper limit mesh plate and the lower limit mesh plate correspond to the top and bottom positions of the inspection opening. A cylindrical water curtain paper is clamped between the upper limit mesh plate and the lower limit mesh plate, and pipeline avoidance holes are provided on the upper limit mesh plate and the lower limit mesh plate.
[0012] Furthermore, an air outlet is provided on the outer wall of the hollow column corresponding to the position of the metal ring strip, and the arc-shaped nozzle extends to the outside of the hollow column through the air outlet.
[0013] Furthermore, a bearing hole is provided on the outer wall of the hollow column corresponding to the air outlet position, and the winch mechanism includes a winch shaft rotatably connected to the inside of the bearing hole through a bearing, a hand wheel is fixedly welded to the outer end of the winch shaft, a gear is fixedly welded to the outer side of the winch shaft between the hand wheel and the outer wall of the hollow column, a clamp is meshed with the top of the gear, one side of the clamp is rotatably connected to the outer wall of the hollow column through a pin, a steel cable is fixedly connected to the bottom of the pulling member, and the bottom of the steel cable is wrapped around the inner end of the winch shaft.
[0014] Furthermore, the drainage mechanism includes an L-shaped drain pipe fixedly welded to the bottom of the hollow column, the bottom of the L-shaped drain pipe extends to the outside of the hollow column, a water leakage mesh plate is fixedly installed on the inner wall of the hollow column at the top of the L-shaped drain pipe, a float rod is slidably connected to the center of the water leakage mesh plate, a stainless steel float ball is fixedly welded to the top of the float rod, a sealing plug is fixedly installed at the bottom of the float rod, and the bottom of the sealing plug is in contact with the top of the L-shaped drain pipe.
[0015] Furthermore, the water outlet end at the top of the water supply pump is connected to one side of the water pipe manifold through an inlet pipe 1, and a valve 1 is provided on the inlet pipe 1. A water inlet pipe 2 is fixedly connected to the water inlet end on one side of the water supply pump, and one end of the inlet pipe 2 passes through the outside of the equipment cabinet. A tap water pipe valve is also fixedly installed on the top of the water pipe manifold.
[0016] Furthermore, a number of fine-tuning valves one equal to the number of the water supply hoses is fixedly installed on the other side of the water pipe manifold, and the bottom of the water supply hose passes through the hollow column and the bottom of the equipment cabinet in sequence and is connected to the water outlet end of the fine-tuning valve one. The outer sides of several water supply hoses located between the hollow column and the equipment cabinet are socketed through protective tubes, and the two ends of the protective tubes are respectively fixedly welded to the hollow column and the side wall of the equipment cabinet, and the inside of the hole of the hollow column at the connection between the protective tube and the hollow column is filled with sealing mud.
[0017] Furthermore, a fine-tuning valve 2 is fixedly installed on the other side of the water pipe manifold, and a spray pipe is fixedly connected to the water outlet end of the fine-tuning valve 2. The other end of the spray pipe passes through the outside of the equipment cabinet and the top of the hollow column in sequence, and the other end of the spray pipe extends to the top of the upper limit mesh plate. A number of spray heads are fixedly installed at the bottom of the spray pipe located on the top of the upper limit mesh plate.
[0018] Furthermore, a blast pipe is fixedly connected to the air outlet end of one side of the blower, one end of the blast pipe passes through the outside of the equipment cabinet and the bottom of the hollow column in sequence, and the interior of the blast pipe is connected to the interior of the hollow column.
[0019] Compared with the prior art, the advantages of the present invention are:
[0020] (1) This scheme, by opening no less than 4 air outlets on the outer wall of the top of the hollow column, and setting no less than 4 arc-shaped nozzles inside the air outlets, enables the top of the hollow column to spray water mist in a circular area at the same time, and the number of arc-shaped nozzles is large, so that the spraying surface is more uniform and the water mist spraying performance is stronger. At the same time, by setting the fine-tuning valve 1, the water spraying amount and water spraying intensity of the corresponding connected arc-shaped nozzle can be adjusted, thereby achieving the effect of zone adjustment control, which is convenient for use;
[0021] (2) In this solution, the pitch angle of the arc-shaped sprinkler is adjusted by a winch mechanism in conjunction with a steel cable and a pulling member. This has a simple structure, low manufacturing cost, and low maintenance rate, which greatly reduces the overall manufacturing cost of the device and the probability of subsequent maintenance.
[0022] (3) In this solution, a blower for supplying air is installed inside the equipment cabinet and connected to the inside of the hollow column through a blower pipe, so that air can be blown at the air outlet to assist the arc-shaped sprinkler head in spraying water mist evenly and in spraying range, making it convenient for use on the construction site;
[0023] (4) In this solution, when the wind passes through the inside of the hollow column and is blown out from the air outlet, a water curtain mechanism is also provided inside the hollow column, so that water can pass through the moist cylindrical water curtain paper, thereby reducing the temperature of the wind discharged from the air outlet, which is beneficial to reducing the temperature of the surrounding area of the hollow column and improving the comfort during use. BRIEF DESCRIPTION OF THE DRAWINGS
[0024] Figure 1 It is a schematic diagram of the overall structure of the present invention;
[0025] Figure 2 It is a schematic diagram of the top structure of the hollow column of the present invention;
[0026] Figure 3 It is a schematic diagram of the internal structure of the equipment cabinet of the present invention;
[0027] Figure 4 It is a schematic diagram of the structure of the water pipe manifold of the present invention;
[0028] Figure 5 It is a schematic diagram of the structure of the nozzle mechanism of the present invention;
[0029] Figure 6 It is a schematic diagram of the partial structure of the nozzle mechanism of the present invention;
[0030] Figure 7 It is a schematic cross-sectional structure diagram of the water curtain mechanism of the present invention;
[0031] Figure 8 It is a schematic diagram of the cross-sectional structure of the drainage mechanism of the present invention.
[0032] Description of the numbers in the figure:
[0033] 1. Hollow column; 101. Inspection port; 102. Closing plate; 103. Air outlet; 104. Bearing hole;
[0034] 2. Equipment cabinet; 201. Partition;
[0035] 3. Nozzle mechanism; 301. Upper mounting plate; 302. Lower mounting plate; 303. Sliding hole; 304. Pulling piece; 305. Support spring; 306. Metal ring strip; 307. Arc-shaped nozzle; 308. Water supply hose; 309. Arc-shaped avoidance hole;
[0036] 4. Water curtain mechanism; 401. Upper limit mesh plate; 402. Lower limit mesh plate; 403. Cylindrical water curtain paper; 404. Pipeline avoidance hole;
[0037] 5. Winch mechanism; 501. Winch shaft; 502. Gear; 503. Clamp; 504. Steel cable;
[0038] 6. Drainage mechanism; 601. L-shaped drain pipe; 602. Leakage mesh plate; 603. Float rod; 604. Stainless steel float ball; 605. Sealing plug;
[0039] 7. Blower; 8. Water supply pump; 9. Water pipe manifold; 901. Fine-tuning valve one; 902. Fine-tuning valve two; 10. Water inlet pipe one; 1001. Valve one; 11. Water inlet pipe two; 12. Tap water pipe valve; 13. Protective pipe; 14. Sprinkler pipe; 1401. Sprinkler head; 15. Blower pipe. DETAILED DESCRIPTION
[0040] The technical solutions in the embodiments of the present invention will be clearly and completely described below in conjunction with the drawings in the specification of the present invention; it is obvious that the described embodiments are only part of the embodiments of the present invention, rather than all the embodiments, and all other embodiments obtained by ordinary technicians in this field based on the embodiments of the present invention without making creative work are within the scope of protection of the present invention. Embodiment 1
[0041] See also Figure 1-Figure 8 A green construction dust suppression device comprises a hollow column 1 and an equipment cabinet 2. Both ends of the hollow column 1 are sealed structures. A nozzle mechanism 3, a water curtain mechanism 4, a winch mechanism 5 and a drainage mechanism 6 are arranged in sequence from top to bottom inside the hollow column 1. A partition 201 is fixedly installed inside the equipment cabinet 2. A blower 7 is fixedly installed on the top of the partition 201. A water supply pump 8 is fixedly installed at the bottom of the inner wall of the equipment cabinet 2 located at the bottom of the partition 201, and a water pipe manifold 9 is fixedly installed on one side of the inner wall of the equipment cabinet 2 located on one side of the water supply pump 8;
[0042] The water outlet end of the top of the water supply pump 8 is connected to one side of the water pipe manifold 9 through an inlet pipe 10, and a valve 1001 is provided on the inlet pipe 10. A water inlet pipe 11 is fixedly connected to the water inlet end of one side of the water supply pump 8. One end of the inlet pipe 11 passes through the outside of the equipment cabinet 2. A tap water pipe valve 12 is also fixedly installed on the top of the water pipe manifold 9. The number of fine-adjustment valves 1901 equal to the number of water supply hoses 308 is fixedly installed on the other side of the water pipe manifold 9. The bottom of the water supply hose 308 passes through the hollow column 1 and the bottom of the equipment cabinet 2 in turn and is connected to the water outlet end of the fine-adjustment valve 901. Several valves located between the hollow column 1 and the equipment cabinet 2 The outer side of each water supply hose 308 is sleeved by a protective tube 13, and the two ends of the protective tube 13 are respectively fixedly welded to the hollow column 1 and the side wall of the equipment cabinet 2, and the hole of the hollow column 1 at the connection between the protective tube 13 and the hollow column 1 is filled with sealing mud. A fine-tuning valve 902 is also fixedly installed on the other side of the water pipe manifold 9, and a spray pipe 14 is fixedly connected to the water outlet end of the fine-tuning valve 902. The other end of the spray pipe 14 passes through the outer side of the equipment cabinet 2 and the top of the hollow column 1 in sequence, and the other end of the spray pipe 14 extends to the top of the upper limit mesh plate 401, and a plurality of spray heads 1401 are fixedly installed at the bottom of the spray pipe 14 located at the top of the upper limit mesh plate 401;
[0043] A blast pipe 15 is fixedly connected to the air outlet end of one side of the blower 7 , one end of the blast pipe 15 passes through the outside of the equipment cabinet 2 and the bottom of the hollow column 1 in sequence, and the inside of the blast pipe 15 is connected to the inside of the hollow column 1 .
[0044] (1) The spraying and blowing principles of this green construction dust suppression device are:
[0045] First, connect the water inlet pipe 11 to the water source and start the water supply pump 8, supply water to the water pipe manifold 9 through the connection of the water inlet pipe 10, or close the valve 1001, directly connect the tap water pipe to the water pipe valve 12 to supply water to the water pipe manifold 9, and then the water enters the corresponding water supply hose 308 through several fine-tuning valves 901, and finally sprays out from the arc-shaped nozzle 307 at the air outlet 103 inside the hollow column 1 as the water supply hose 308 rises, so as to achieve the effect of spraying water mist in the annular area on the top of the hollow column 1;
[0046] By setting the fine-tuning valve 901, the water spraying amount and water spraying intensity of the corresponding arc-shaped sprinkler head 307 can be adjusted, thereby achieving the effect of zone adjustment control, which is convenient for use;
[0047] At the same time, the blower 7 is started, and the air on the outside of the equipment cabinet 2 is sucked into the blower 7 through the ventilation holes on the equipment cabinet 2, and blown into the hollow column 1 through the connection of the blower pipe 15, and continuously climbs upward inside the hollow column 1 and passes through the water curtain mechanism 4, and finally blows out at each air outlet 103, assisting the arc-shaped nozzle 307 to spray water mist in an area and a range. The hole of the hollow column 1 at the connection between the protective tube 13 and the hollow column 1 is filled with sealing mud, so that the connection between the hole of the protective tube 13 and the hollow column 1 and the connection when the water supply hose 308 passes through can be sealed, thereby improving the airtightness and reducing the probability of air leakage and water leakage. Embodiment 2
[0048] In view of the above embodiment 1, for further description, refer to Figure 3 , Figure 5 as well as Figure 6 The nozzle mechanism 3 includes an upper mounting plate 301 and a lower mounting plate 302 fixedly mounted on the inner wall of the hollow column 1. The upper mounting plate 301 and the lower mounting plate 302 are both symmetrically and equidistantly provided with not less than four sliding holes 303, and a pulling member 304 is slidably connected between two corresponding sliding holes 303 in the longitudinal direction, and a supporting spring 305 is sleeved on the top of the pulling member 304. The top and bottom of the supporting spring 305 are in contact with the top of the pulling member 304 and the top of the upper mounting plate 301 respectively, and the upper mounting plate at the position of the corresponding pulling member 304 A metal ring strip 306 is fixedly welded between 301 and the lower mounting plate 302, and no less than 4 arc-shaped nozzles 307 are rotatably connected inside the metal ring strip 306. An ear piece is fixedly welded on one side of the arc-shaped nozzle 307, and the ear piece is rotatably connected inside the pulling member 304 through a pin, and a water supply hose 308 is fixedly connected to the water inlet end at the bottom of the arc-shaped nozzle 307. A group of arc-shaped avoidance holes 309 are also opened on the lower mounting plate 302, and the bottom of the water supply hose 308 extends to the bottom of the hollow column 1 through the corresponding arc-shaped avoidance holes 309;
[0049] An air outlet 103 is provided on the outer wall of the hollow column 1 at the position of the corresponding metal ring strip 306, and the arc-shaped nozzle 307 extends to the outside of the hollow column 1 through the air outlet 103. A bearing hole 104 is also provided on the outer wall of the hollow column 1 at the position of the corresponding air outlet 103. The winch mechanism 5 includes a winding shaft 501 rotatably connected to the inside of the bearing hole 104 through a bearing, and a hand wheel is fixedly welded to the outer end of the winding shaft 501. A gear 502 is fixedly welded to the outer side of the winding shaft 501 between the hand wheel and the outer wall of the hollow column 1, and a clamp 503 is meshed with the top of the gear 502. One side of the clamp 503 is rotatably connected to the outer wall of the hollow column 1 through a pin shaft. A steel cable 504 is fixedly connected to the bottom of the pulling member 304, and the bottom of the steel cable 504 is wound around the inner end of the winding shaft 501.
[0050] (2) The nozzle mechanism adjustment principle of this green construction dust suppression device is:
[0051] When it is necessary to adjust the pitch angle of the arc-shaped nozzle 307 inside the same metal ring strip 306, first push open the clamp 503 on the winch mechanism 5 at the bottom of the corresponding metal ring strip 306 to disengage the limit of the gear 502, and then turn the winch shaft 501 by the hand wheel to tighten or loosen the steel cable 504 from the bottom. At this time, the pulling member 304 of the nozzle mechanism 3 can be pulled down or lifted up by the connection of the steel cable 504, and then the arc-shaped nozzle 307 can be rotated up and down in the metal ring strip 306 by the rotation connection of the ear piece. After the adjustment is completed, the clamp 503 is released to clamp the gear 502, and the arc-shaped nozzle 307 can be positioned.
[0052] During this process, the support spring 305 has the effect of pulling the top of the pulling member 304 in the opposite direction, which facilitates the upward reset or adjustment of the pulling member 304. The arc-shaped avoidance hole 309 not only facilitates the insertion of the water supply hose 308, but also provides a channel for the flow of wind inside the hollow column 1. Embodiment 3
[0053] In view of the above-mentioned embodiment 1 and embodiment 2, for further description, refer to Figure 1 , Figure 7 as well as Figure 8 An inspection port 101 is provided on one side of the outer wall of the hollow column 1, and a sealing plate 102 is fixedly installed on the outer side of the inspection port 101. The water curtain mechanism 4 includes an upper limit mesh plate 401 and a lower limit mesh plate 402 fixedly installed on the inner wall of the hollow column 1, and the positions of the upper limit mesh plate 401 and the lower limit mesh plate 402 correspond to the top and bottom positions of the inspection port 101. A cylindrical water curtain paper 403 is clamped between the upper limit mesh plate 401 and the lower limit mesh plate 402, and pipeline avoidance holes 404 are provided on the upper limit mesh plate 401 and the lower limit mesh plate 402;
[0054] The drainage mechanism 6 includes an L-shaped drainage pipe 601 fixedly welded to the bottom of the hollow column 1, the bottom of the L-shaped drainage pipe 601 passes through the outside of the hollow column 1, a water leakage mesh plate 602 is fixedly installed on the inner wall of the hollow column 1 at the top of the L-shaped drainage pipe 601, a floating rod 603 is slidably connected at the center position of the water leakage mesh plate 602, a stainless steel float 604 is fixedly welded to the top of the floating rod 603, a sealing plug 605 is fixedly installed at the bottom of the floating rod 603, and the bottom of the sealing plug 605 is in contact with the top of the L-shaped drainage pipe 601.
[0055] (3) The cooling principle of the water curtain mechanism of this green construction dust suppression device is:
[0056] First, open the fine-adjusting valve 2 902 at the water pipe manifold 9, so that the water inside the water pipe manifold 9 can enter the inside of the spray pipe 14 through the fine-adjusting valve 2 902, and then rise and spray on the top of the water curtain mechanism 4, so as to continuously moisten the cylindrical water curtain paper 403 inside the water curtain mechanism 4. At this time, the wind inside the hollow column 1 passes upward from the bottom of the cylindrical water curtain paper 403 to achieve the effect of cooling, and then is discharged from the air outlet 103, and the water sprayed on the cylindrical water curtain paper 403 continuously falls to The drainage mechanism 6 is gathered together. When the water level is higher than the stainless steel float 604, the stainless steel float 604 floats up and drives the sealing plug 605 to move up and out of contact with the top of the L-shaped drainage pipe 601. At this time, the water can be discharged through the L-shaped drainage pipe 601. When the water level drops, the stainless steel float 604 and the sealing plug 605 continue to drop until the top of the L-shaped drainage pipe 601 is sealed. This structural form can achieve intermittent drainage and prevent air leakage during drainage.
[0057] The pipeline avoidance holes 404 provided on both the upper limit mesh plate 401 and the lower limit mesh plate 402 facilitate the insertion of the steel cable 504 and the water supply hose 308 and provide a channel for the flow of wind.
[0058] The above is only a preferred specific implementation of the present invention; however, the protection scope of the present invention is not limited thereto. Any technician familiar with the technical field can make equivalent replacements or changes according to the technical solution and its improved conception within the technical scope disclosed by the present invention, which should be covered by the protection scope of the present invention.
Claims
1. A green construction dust reduction device, comprising a hollow column (1) and an equipment cabinet (2), Features: The two ends of the hollow column (1) are sealed structures. A nozzle mechanism (3), a water curtain mechanism (4), a winch mechanism (5) and a drainage mechanism (6) are arranged in sequence from top to bottom inside the hollow column (1). A partition (201) is fixedly installed inside the equipment cabinet (2). A blower (7) is fixedly installed on the top of the partition (201). A water supply pump (8) is fixedly installed on the bottom of the inner wall of the equipment cabinet (2) at the bottom of the partition (201), and a water pipe manifold (9) is fixedly installed on one side of the inner wall of the equipment cabinet (2) at one side of the water supply pump (8); The nozzle mechanism (3) comprises an upper mounting plate (301) and a lower mounting plate (302) fixedly mounted on the inner wall of the hollow column (1); the upper mounting plate (301) and the lower mounting plate (302) are both symmetrically provided with not less than four sliding holes (303) at equal distances, and a pulling member (304) is slidably connected between two corresponding sliding holes (303) in the longitudinal direction; a supporting spring (305) is sleeved on the top of the pulling member (304); the top and bottom of the supporting spring (305) are in contact with the top of the pulling member (304) and the top of the upper mounting plate (301) respectively, and the upper mounting plate (301) at the position corresponding to the pulling member (304) is in contact with the upper mounting plate (301) at the position corresponding to the pulling member (304). A metal ring strip (306) is fixedly welded between the plate (301) and the lower mounting plate (302), and no less than four arc-shaped nozzles (307) are rotatably connected inside the metal ring strip (306). An ear piece is fixedly welded on one side of the arc-shaped nozzle (307), and the ear piece is rotatably connected inside the pulling member (304) through a pin shaft, and a water supply hose (308) is fixedly connected to the water inlet end at the bottom of the arc-shaped nozzle (307). A group of arc-shaped avoidance holes (309) are also opened on the lower mounting plate (302), and the bottom of the water supply hose (308) extends to the bottom of the hollow column (1) through the corresponding arc-shaped avoidance holes (309); An inspection opening (101) is provided on one side of the outer wall of the hollow column (1), and a sealing plate (102) is fixedly installed on the outer side of the inspection opening (101); the water curtain mechanism (4) comprises an upper limit mesh plate (401) and a lower limit mesh plate (402) fixedly installed on the inner wall of the hollow column (1), and the positions of the upper limit mesh plate (401) and the lower limit mesh plate (402) correspond to the top and bottom positions of the inspection opening (101); a cylindrical water curtain paper (403) is clamped between the upper limit mesh plate (401) and the lower limit mesh plate (402), and pipeline avoidance holes (404) are provided on both the upper limit mesh plate (401) and the lower limit mesh plate (402); An air outlet (103) is provided on the outer wall of the hollow column (1) at a position corresponding to the metal ring strip (306), and the arc-shaped nozzle (307) extends through the air outlet (103) to the outside of the hollow column (1); A bearing hole (104) is also provided on the outer wall of the hollow column (1) at a position corresponding to the air outlet (103); the winch mechanism (5) comprises a winch shaft (501) rotatably connected to the inside of the bearing hole (104) via a bearing; a hand wheel is fixedly welded to the outer end of the winch shaft (501); a gear (502) is fixedly welded to the outer side of the winch shaft (501) between the hand wheel and the outer wall of the hollow column (1); a clamp (503) is meshed at the top of the gear (502); one side of the clamp (503) is rotatably connected to the outer wall of the hollow column (1) via a pin; a steel cable (504) is fixedly connected to the bottom of the pulling member (304); the bottom of the steel cable (504) is wound around the inner end of the winch shaft (501).
2. A green construction dust suppression device according to claim 1, Features: The drainage mechanism (6) comprises an L-shaped drainage pipe (601) fixedly welded to the bottom of the hollow column (1), the bottom of the L-shaped drainage pipe (601) passes through the outside of the hollow column (1), a water leakage mesh plate (602) is fixedly installed on the inner wall of the hollow column (1) at the top of the L-shaped drainage pipe (601), a floating rod (603) is slidably connected at the center of the water leakage mesh plate (602), a stainless steel floating ball (604) is fixedly welded to the top of the floating rod (603), and a sealing plug (605) is fixedly installed at the bottom of the floating rod (603), and the bottom of the sealing plug (605) is in contact with the top of the L-shaped drainage pipe (601).
3. A green construction dust suppression device according to claim 1, Features: The water outlet end at the top of the water supply pump (8) is connected to one side of the water pipe manifold (9) via a water inlet pipe 1 (10), and a valve 1 (1001) is provided on the water inlet pipe 1 (10). A water inlet pipe 2 (11) is fixedly connected to the water inlet end on one side of the water supply pump (8), and one end of the water inlet pipe 2 (11) passes through the outside of the equipment cabinet (2). A tap water pipe valve (12) is also fixedly installed on the top of the water pipe manifold (9).
4. A green construction dust suppression device according to claim 1, Features: The other side of the water pipe manifold (9) is fixedly installed with a number of fine-tuning valves (901) equal to the number of the water supply hoses (308). The bottom of the water supply hose (308) passes through the bottom of the hollow column (1) and the equipment cabinet (2) in sequence and is connected to the water outlet end of the fine-tuning valve (901). The outer sides of a plurality of the water supply hoses (308) located between the hollow column (1) and the equipment cabinet (2) are sleeved by a protective tube (13), and the two ends of the protective tube (13) are respectively fixedly welded to the side walls of the hollow column (1) and the equipment cabinet (2). The inside of the hole of the hollow column (1) located at the connection between the protective tube (13) and the hollow column (1) is filled with sealing mud.
5. A green construction dust suppression device according to claim 1, Features: A second fine-tuning valve (902) is also fixedly installed on the other side of the water pipe manifold (9); a spray pipe (14) is fixedly connected to the water outlet end of the second fine-tuning valve (902); the other end of the spray pipe (14) passes through the outside of the equipment cabinet (2) and the top of the hollow column (1) in sequence, and the other end of the spray pipe (14) extends to the top of the upper limit mesh plate (401); and a plurality of spray heads (1401) are fixedly installed at the bottom of the spray pipe (14) located at the top of the upper limit mesh plate (401).
6. A green construction dust suppression device according to claim 1, Features: A blast pipe (15) is fixedly connected to the air outlet end on one side of the blower (7), one end of the blast pipe (15) passes through the outside of the equipment cabinet (2) and the bottom of the hollow column (1) in sequence, and the interior of the blast pipe (15) is connected to the interior of the hollow column (1).