A container loading and unloading system and method based on gantry crane

Through real-time three-dimensional data collection and obstacle identification, the optimal hoisting path is generated, realizing automated container loading and unloading of gantry cranes, solving the problem of manual operation being difficult to achieve the shortest path, and improving efficiency and safety.

CN118479263BActive Publication Date: 2024-10-01ZHANGJIAGANG BONDED PORT AREA HARBOR CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202410950385.1
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-07-16
Publication Date
2024-10-01
Estimated Expiration
2044-07-16

AI Technical Summary

Technical Problem

In the existing technology, it is difficult for manually operated gantry cranes to achieve the shortest operating path, it is not efficient enough for container loading and unloading, and there are potential safety hazards when working at night.

Method used

The three-dimensional model data of the container is stored and scanned in real time through the preset storage module and acquisition module. The identification and determination module identifies obstacles, the path simulation module generates the optimal hoisting path, and the central control processing module controls the gantry crane to perform automated loading and unloading operations.

Benefits of technology

It realizes automated loading and unloading of containers, reduces safety hazards, improves the operating efficiency of gantry cranes, and ensures fast and safe loading and unloading of goods.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118479263B_ABST
    Figure CN118479263B_ABST
Patent Text Reader

Abstract

The present invention relates to the technical field of container hoisting operations, and in particular to a container loading and unloading system based on a gantry crane, comprising a first storage module, a second storage module, a collection module, an identification and determination module, a path simulation module, an execution module and a central control processing module. The present invention simulates and counts the real-time storage volume and storage location of existing containers in a storage yard through the cooperation of the first storage module and the second storage module, scans and identifies the path information between the container to be loaded and unloaded and the required loading and unloading point through the collection module and the identification and determination module, and simulates and models the container to be loaded and unloaded according to the scanned obstacle information through the path simulation module, generates a corresponding path, and compares and determines the generated path through the central control processing module, calculates and obtains the optimal path, realizes the automated loading and unloading operation of the container to be loaded and unloaded, reduces safety hazards and improves the operation efficiency of the gantry crane.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of container hoisting operations, and in particular to a container loading and unloading system and method based on a gantry crane. Background Art

[0002] With the continuous growth of global trade, ports, as important gateways for international trade, have seen a significant increase in cargo throughput. Containers, as the main carrier of modern logistics, can effectively reduce the risk of cargo loss. Their standardized design greatly simplifies the cargo loading and unloading process, improves port operation efficiency, and enables containers to be compactly stacked in ports or on transport vehicles, improving space utilization. Due to the size and weight of the containers themselves, the prior art often uses manually operated gantry cranes and other mechanical equipment to load and unload containers at ports, making cargo loading and unloading faster and easier.

[0003] Although gantry cranes have become key equipment to meet this demand with their efficient and stable container handling capabilities, in actual use, due to the limitations of manual operation, it is difficult to load and unload goods in the shortest possible operating path. When encountering scenarios where work needs to be done at night, there may be misjudgments or misoperations due to reasons such as light. In addition, since the machinery itself and the container itself have a large weight, it is difficult to ensure manual safety once an error occurs. Summary of the invention

[0004] To this end, the present invention provides a container loading and unloading system and method based on a gantry crane, so as to overcome the problem in the prior art that it is difficult to achieve an optimal path when manually operating a gantry crane.

[0005] To achieve the above-mentioned object, the present invention provides a container loading and unloading system based on a gantry crane, comprising: a first storage module, which stores real-time three-dimensional model data in a storage yard through a preset first storage hardware, so as to simulate and count the real-time storage quantity and storage position of existing containers in the storage yard;

[0006] The second storage module stores the three-dimensional model data of the container trucks and the containers to be loaded and unloaded at the port or the yard through the preset second storage hardware, so as to match and retrieve the real-time data of the container trucks and the containers to be loaded and unloaded collected by the collection module;

[0007] The acquisition module scans the three-dimensional data of the container truck and the container to be loaded and unloaded entering the port or the yard through a real-time scanning unit, and scans and records the real-time scene between the container to be loaded and unloaded and the required loading and unloading point, so as to obtain the loading and unloading path information between the container to be loaded and unloaded and the required loading and unloading point;

[0008] an identification and determination module, which identifies and retrieves obstacle information in the loading and unloading path through a set identification unit as a scanning obstacle for determination, and identifies and determines the maximum longitudinal height of the scanning obstacle according to a preset maximum lifting height value, and the identification and determination module can convert the longitudinal determination unit into a lateral determination unit when determining that the maximum longitudinal height of the scanning obstacle is greater than the maximum lifting height value;

[0009] A path simulation module simulates and models the container to be loaded and unloaded according to a preset lifting value and the determined information of the scanned obstacle, and simulates and generates a lifting path between the container to be loaded and unloaded and a required loading and unloading point according to the generated modeling data;

[0010] An execution module drives the container to be loaded and unloaded to move to a required loading and unloading point according to the final generated path;

[0011] A central control processing module, wherein the central control processing module is connected to the first storage module, the second storage module, the acquisition module, the identification and determination module, the path simulation module and the execution module respectively. When it is determined that the maximum longitudinal height of the scanning obstacle is greater than a preset second height value preset in the central control processing module, the central control processing module can control the path simulation module to generate a simulation model at the corresponding position of the scanning obstacle, and perform a determination and calculation on the simulation path generated by the path simulation module to determine a final generated path, and control the gantry crane to perform loading and unloading operations on the container to be loaded and unloaded.

[0012] Further, the identification and determination module includes a longitudinal determination unit, and the longitudinal determination unit compares and determines the maximum longitudinal height of the scanned obstacle according to a preset maximum lifting height value;

[0013] The path simulation module can perform simulation modeling and path generation for the container to be loaded and unloaded according to a preset lifting value when the maximum longitudinal height of the scanned obstacle is less than or equal to the maximum lifting height value.

[0014] Furthermore, the path simulation module performs lifting simulation on the starting position and the end position of the container to be loaded and unloaded according to the preset lifting value, selects any point at the lowest side of the container to be loaded and unloaded closest to the scanning obstacle as a reference calculation point, simulates and generates the shortest spatial straight line path between the two points after lifting as the initial longitudinal lifting path of the container to be loaded and unloaded, and obtains the preset longitudinal lifting path value according to the preset lifting value;

[0015] Among them, L1'=h1×2+l1, L1' is the preset longitudinal lifting path value, h1 is the preset lifting value, and l1 is the initial longitudinal lifting path value of the container to be loaded and unloaded.

[0016] Furthermore, the central control processing module can compare and determine the longitudinal height of the highest point of the scanned obstacle with the longitudinal height of the corresponding position in the preset longitudinal lifting path.

[0017] If the longitudinal height at the highest point of the scanned obstacle is less than the longitudinal height at the corresponding position in the preset longitudinal lifting path, the central control processing module will directly execute the preset longitudinal lifting path to lift the container to be loaded and unloaded to the required loading and unloading point.

[0018] Furthermore, a preset second height value is also provided in the central control processing module. If the longitudinal height at the highest point of the scanned obstacle is greater than or equal to the longitudinal height at the corresponding position in the preset longitudinal lifting path, the central control processing module will call the preset second height value and compare it with the longitudinal height at the highest point of the scanned obstacle for determination.

[0019] The path simulation module can simulate and model a point at the highest point of the scanning obstacle that is closest to the container to be loaded and unloaded and a point that is farthest from the container to be loaded and unloaded, and simulate and generate the shortest spatial straight line path between any two adjacent points when the longitudinal height at the highest point of the scanning obstacle is less than or equal to a preset second height value, and obtain two oblique spatial paths and one lateral spatial path, and compare and determine the longitudinal heights of the remaining obstacles on both sides of the highest point of the scanning obstacle according to the two oblique spatial paths.

[0020] Further, the central control processing module can calculate and obtain the actual longitudinal hoisting path value according to the preset lifting value when the longitudinal heights of the remaining obstacles on both sides of the highest point of the scanned obstacle are all less than the longitudinal height at the corresponding position of a corresponding oblique spatial path, and obtain the preset longitudinal hoisting path corresponding to the preset longitudinal hoisting path value;

[0021] Among them, L1=S1+S2+S3+h1×2, L1 is the actual longitudinal lifting path value, S1 is the oblique space path value of the scanning obstacle close to the container to be loaded and unloaded, S2 is the transverse space path value, S3 is the oblique space path value of the scanning obstacle close to the required loading and unloading point, and h1 is the preset lifting value.

[0022] Further, if the longitudinal height of the remaining obstacles at the highest point of the scanning obstacle close to the container to be loaded and unloaded is greater than the oblique spatial path value S1 of the scanning obstacle close to the container to be loaded and unloaded, the path simulation module continues to simulate and model the point at the highest position of the second scanning obstacle closest to the container to be loaded and unloaded, and obtains a second oblique spatial path value and a third oblique spatial path value again;

[0023] If the longitudinal height of the remaining obstacles at the highest point of the scanning obstacle close to the required loading and unloading point is greater than the third scanning obstacle of the oblique spatial path value S3 at the side of the scanning obstacle close to the required loading and unloading point, then continue to simulate and model the point at the highest position of the third scanning obstacle closest to the required loading and unloading point through the path simulation module, and obtain a fourth oblique spatial path value and a fifth oblique spatial path value again;

[0024] The longitudinal heights of other obstacles on the side of the second scanning obstacle close to the container to be loaded and unloaded and on the side of the third scanning obstacle close to the required loading and unloading point are compared and determined according to the second oblique spatial path value and the fifth oblique spatial path value respectively, until the longitudinal heights of the other obstacles do not exceed the longitudinal heights of the corresponding spatial path values, and the actual longitudinal lifting path value L1 is obtained and calculated;

[0025] Among them, L1=S1+S2+S3+h1×2, S1=S1'+S1'', S3=S3'+S3'', S1' is the second oblique space path value, S1'' is the third oblique space path value, S3' is the fourth oblique space path value, and S3'' is the fifth oblique space path value.

[0026] Furthermore, the identification and determination module is also provided with a maximum lateral transfer value. If the maximum longitudinal height of the scanned obstacle is greater than the maximum lifting height value, the central control processing module will retrieve the maximum lateral transfer value and compare the maximum lateral distance value of the scanned obstacle.

[0027] The central control processing module can issue an alarm when the maximum lateral distance value of the scanned obstacle is also greater than the maximum lateral transfer value.

[0028] Furthermore, the identification and determination module also includes a horizontal determination unit.

[0029] The central control processing module can convert the longitudinal determination unit into the lateral determination unit when the maximum lateral distance value of the scanned obstacle is less than or equal to the maximum lateral transfer value, and simulate the generation of the lateral lifting path of the scanned obstacle in the generation mode of the actual longitudinal lifting path value, and calculate and obtain the actual lateral lifting path value;

[0030] The central control processing module can simultaneously obtain and calculate the actual horizontal lifting path value and the actual longitudinal lifting path value when the longitudinal height at the highest point of the scanned obstacle is greater than the preset second height value, and compare the actual horizontal lifting path value with the actual longitudinal lifting path value to select the optimal path as the final generated path.

[0031] The present invention also provides a loading and unloading method of a container loading and unloading system based on a gantry crane according to any one of the above items, comprising:

[0032] Step S1, scanning and recording the real-time scene between the container to be loaded and unloaded and the required loading and unloading point through the acquisition module, and obtaining the loading and unloading path between the container to be loaded and unloaded and the loading and unloading point;

[0033] Step S2, identifying and determining the maximum longitudinal height of the highest obstacle on the loading and unloading path obtained by scanning through the identification and determination module;

[0034] Step S3: if the maximum longitudinal height of the scanned obstacle is less than or equal to the maximum lifting height value, then proceed to step S4; if the maximum longitudinal height of the scanned obstacle is greater than the maximum lifting height value, then directly proceed to step S9;

[0035] In step S4, a path simulation module is used to simulate and generate a running path between the container to be loaded and unloaded and the required loading and unloading point, and an initial longitudinal lifting path and a preset longitudinal lifting path of the container to be loaded and unloaded are calculated and obtained.

[0036] Step S5, compare the preset longitudinal lifting path with the longitudinal position of the highest point of the scanned obstacle through the central control processing module. If the longitudinal height at the highest point of the scanned obstacle is less than the longitudinal height at the corresponding position of the preset longitudinal lifting path, the preset longitudinal lifting path is used as the final generated path to directly execute step S8. If the longitudinal height at the highest point of the scanned obstacle is greater than or equal to the longitudinal height at the corresponding position in the preset longitudinal lifting path, continue to execute step S6.

[0037] In step S6, a path simulation module is used to simulate and model the container to be loaded and unloaded at the corresponding position of the highest point of the scanned obstacle, and the shortest spatial straight path between any two adjacent simulation models is simulated and generated, and the remaining obstacles on the corresponding side are judged according to the longitudinal height of the generated path. If there are remaining obstacles exceeding the longitudinal height of the corresponding generated path, step S7 is continued to be executed. If there are no remaining obstacles exceeding the longitudinal height of the corresponding generated path, this generated path is used as the final generated path and step S8 is directly executed.

[0038] The step S7 continues to simulate and model at the corresponding position of the highest point of the remaining obstacles that exceed the longitudinal height of the corresponding generated path, and continues to compare and determine the generated path with the highest point of the corresponding remaining obstacles. If there is still an excess part, step S7 is repeated until there is no remaining obstacle exceeding the longitudinal height of the corresponding generated path, then all generated paths are added together as the final generated path and step S8 is executed.

[0039] In step S8, the central control processing module controls the execution module to drive the container to be loaded and unloaded to be hoisted according to the final generated path generated by the path simulation module, and hoist it to the required loading and unloading point for loading and unloading.

[0040] In step S9, the maximum lateral distance value of the scanned obstacle is compared and determined according to the maximum lateral transfer value. If the maximum lateral distance value of the scanned obstacle is also greater than the maximum lateral transfer value, an alarm is directly issued. If the maximum lateral distance value of the scanned obstacle is less than or equal to the maximum lateral transfer value, the longitudinal determination data is replaced with the lateral determination data and steps S4 to S8 are continued.

[0041] Compared with the prior art, the beneficial effect of the present invention lies in that, through the coordinated setting of the first storage module and the second storage module, the real-time storage capacity and storage position of the existing containers in the yard are simulated and counted, so as to facilitate relevant personnel to quickly retrieve the real-time storage capacity of the corresponding yard, and avoid the problem that the actual storage capacity exceeds the maximum storage capacity, thereby causing congestion and difficulty in loading and unloading of goods. The acquisition module and the identification and judgment module are used to scan and identify the path information between the container to be loaded and unloaded and the required loading and unloading point, and the corresponding data is quickly retrieved to facilitate the simulation and judgment of the maximum longitudinal height of the scanned obstacles in the loading and unloading path, and the path simulation module is used to simulate and model the container to be loaded and unloaded according to the obstacle information after scanning and judgment, so as to quickly generate the corresponding path, and the generated path is judged and compared according to the central control processing module, and the optimal path is calculated to realize the automated loading and unloading operation of the container to be loaded and unloaded, reduce safety hazards and improve the operating efficiency of the gantry crane.

[0042] Furthermore, the maximum longitudinal height of the scanned obstacle is compared with the preset maximum lifting height value by the longitudinal determination unit in the identification and determination module, so as to quickly determine whether there are longitudinal obstacles in the loading and unloading path that exceed the maximum lifting stroke of the gantry crane, and determine whether the container to be loaded and unloaded can be directly lifted to the required loading and unloading point by longitudinal lifting.

[0043] In particular, the path simulation module simulates and models the lifting starting point position of the container to be loaded and unloaded and the lifting end point position at the required loading and unloading point according to the preset lifting value, thereby simulating and generating the shortest spatial path between the two, and determines whether this path can be used as the final execution path in the loading and unloading path based on the scanned obstacle information, so that the container to be loaded and unloaded can be loaded and unloaded along the shortest path.

[0044] In particular, when the central control processing module determines that the longitudinal height at the highest point of the scanned obstacle is greater than the longitudinal height at the corresponding position of the preset longitudinal lifting path, the longitudinal height at the highest point of the scanned obstacle is compared with the preset second height value to determine whether it is necessary to simultaneously generate the longitudinal movement path and the lateral movement path of the container to be loaded and unloaded.

[0045] Furthermore, when the central control processing module determines that the longitudinal height of the highest point of the scanned obstacle is less than or equal to the preset second height value, models are generated on the corresponding sides of the highest point of the scanned obstacle for the container to be loaded and unloaded, that is, modeling is performed so that the box body of the container to be loaded and unloaded can completely cross the two sides of the scanned obstacle laterally, and its running path is simulated and generated at the corresponding reference points according to all the generated simulation models, and the generated path is compared and determined with the longitudinal heights of the remaining obstacles on both sides of the highest point of the scanned obstacle to determine whether this path can be used as the final generated path.

[0046] In particular, when the central control processing module determines that the longitudinal heights of the remaining obstacles on both sides of the highest point of the scanned obstacle are still greater than the generated path on the corresponding side, the container to be loaded and unloaded will be simulated and modeled again according to the corresponding positions of the remaining obstacles on the corresponding side, and its running path will be simulated and generated again according to the corresponding reference points of all the generated simulation models, and the regenerated path will be compared with the longitudinal heights of the remaining obstacles to determine whether this path can be used as the final generated path.

[0047] Furthermore, when the identification and determination module determines that the maximum longitudinal height of the scanned obstacle is greater than the maximum lifting height value, the maximum lateral distance value of the scanned obstacle is compared with the maximum lateral transfer value to quickly determine whether there are lateral obstacles in the loading and unloading path that exceed the maximum lateral travel of the gantry crane, and determine whether the container to be loaded and unloaded can be lifted to the desired loading and unloading point through lateral lifting.

[0048] In particular, when the identification and judgment module determines that the maximum lateral distance value of the scanned obstacle is less than the maximum lateral transfer value, the lateral lifting path is simulated and generated according to the generation method of the longitudinal lifting path, and the simulated path is judged by the central control processing module until the final generated path is determined.

[0049] Furthermore, when the central control processing module determines that the longitudinal height at the highest point of the scanned obstacle is greater than the preset second height value, its transverse lifting path and longitudinal lifting path are calculated at the same time, and the final generated path values ​​generated by its longitudinal lifting path and transverse lifting path are compared and determined to determine the optimal loading and unloading path. BRIEF DESCRIPTION OF THE DRAWINGS

[0050] Figure 1 is a schematic diagram of a container loading and unloading system based on a gantry crane in this embodiment;

[0051] Figure 2 This is a schematic diagram of the structure of the identification and determination module in this embodiment;

[0052] Figure 3 This is a flow chart of the container loading and unloading method based on the gantry crane in this embodiment;

[0053] Figure 4 It is a schematic diagram of an actual longitudinal lifting path generated by the path simulation module in this embodiment according to obstacle information simulation. DETAILED DESCRIPTION

[0054] In order to make the objects and advantages of the present invention more clearly understood, the present invention is further described below in conjunction with embodiments; it should be understood that the specific embodiments described herein are only used to explain the present invention and are not used to limit the present invention.

[0055] The preferred embodiments of the present invention are described below with reference to the accompanying drawings. It should be understood by those skilled in the art that these embodiments are only used to explain the technical principles of the present invention and are not intended to limit the protection scope of the present invention.

[0056] It should be noted that, in the description of the present invention, terms such as "up", "down", "left", "right", "inside" and "outside" indicating directions or positional relationships are based on the directions or positional relationships shown in the drawings. This is merely for the convenience of description and does not indicate or imply that the device or element must have a specific orientation, be constructed and operated in a specific orientation. Therefore, it cannot be understood as a limitation on the present invention.

[0057] In addition, it should be noted that in the description of the present invention, unless otherwise clearly specified and limited, the terms "installed", "connected", and "connected" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection, or it can be indirectly connected through an intermediate medium, or it can be the internal communication of two components. For those skilled in the art, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.

[0058] See also Figure 1 to Figure 2 As shown, Figure 1 is a schematic diagram of a container loading and unloading system based on a gantry crane in this embodiment, Figure 2 This is a schematic diagram of the structure of the identification and determination module in this embodiment;

[0059] This embodiment provides a container loading and unloading system based on a gantry crane, comprising a first storage module, which stores real-time three-dimensional model data in a storage yard through a preset first storage hardware, so as to simulate and count the real-time storage quantity and storage location of existing containers in the storage yard;

[0060] The second storage module stores the three-dimensional model data of the container trucks and containers to be loaded and unloaded at the port or yard through the preset second storage hardware, so as to match and retrieve the real-time data of the container trucks and containers to be loaded and unloaded collected by the collection module;

[0061] The acquisition module scans the three-dimensional data of the container trucks and containers to be loaded and unloaded at the port or yard through the real-time scanning unit, and scans and records the real-time scenes between the containers to be loaded and unloaded and the required loading and unloading points, and obtains the loading and unloading path information between the containers to be loaded and unloaded and the required loading and unloading points;

[0062] The identification and determination module identifies and retrieves obstacle information in the loading and unloading path through a set identification unit as a scanning obstacle for determination, and identifies and determines the maximum longitudinal height of the scanning obstacle according to a preset maximum lifting height value, and the identification and determination module can convert the longitudinal determination unit into a lateral determination unit when determining that the maximum longitudinal height of the scanning obstacle is greater than the maximum lifting height value;

[0063] The path simulation module simulates and models the container to be loaded and unloaded according to the preset lifting value and the information of the determined scanned obstacles, and simulates and generates the lifting path between the container to be loaded and unloaded and the required loading and unloading point according to the generated modeling data;

[0064] The execution module drives the containers to be loaded and unloaded to move to the required loading and unloading points according to the final generated path;

[0065] The central control processing module is connected to the first storage module, the second storage module, the acquisition module, the identification and determination module, the path simulation module and the execution module respectively. When it is determined that the maximum longitudinal height of the scanning obstacle is greater than the preset second height value preset in the central control processing module, the central control processing module can control the path simulation module to generate simulation modeling at the corresponding position of the scanning obstacle, and perform judgment calculation on the simulation path generated by the path simulation module to determine the final generated path, and control the gantry crane to perform loading and unloading operations on the containers to be loaded and unloaded.

[0066] Through the coordinated setting of the first storage module and the second storage module, the real-time storage capacity and storage position of the existing containers in the yard are simulated and counted, so as to facilitate the relevant personnel to quickly retrieve the real-time storage capacity of the corresponding yard, and avoid the actual storage capacity exceeding the maximum storage capacity, thereby causing congestion and jam of goods, and difficult loading and unloading problems. The acquisition module and the identification and judgment module are used to scan and identify the path information between the container to be loaded and unloaded and the required loading and unloading point, and the corresponding data is quickly retrieved to facilitate the simulation and judgment of the maximum longitudinal height of the scanned obstacles in the loading and unloading path. The path simulation module is used to simulate and model the container to be loaded and unloaded according to the obstacle information after scanning and judgment, so as to quickly generate the corresponding path, and the generated path is judged and compared according to the central control processing module, and the optimal path is calculated to realize the automated loading and unloading operation of the container to be loaded and unloaded, reduce safety hazards and improve the operating efficiency of the gantry crane.

[0067] In this embodiment, the first storage module and the second storage module can both scan and record the real-time number of containers at the yard and the port through corresponding existing facilities such as a panoramic scanner or an ultrasonic scanner, and record and store the three-dimensional model data of the real-time scene after the scan according to corresponding algorithms such as a Monte Carlo algorithm, a voxel modeling algorithm and other commonly used algorithms, so as to facilitate the subsequent retrieval and judgment of the scene. The path simulation module can perform three-dimensional modeling of the scanned objects at the corresponding positions through corresponding algorithms such as a reverse engineering algorithm, so as to facilitate the simulation and generation of the spatial path between the containers to be loaded and unloaded and the required loading and unloading points.

[0068] Specifically, the identification and determination module includes a longitudinal determination unit, which compares and determines the maximum longitudinal height of the scanned obstacle according to a preset maximum lifting height value;

[0069] The path simulation module can simulate modeling and generate paths for containers to be loaded and unloaded according to preset lifting values ​​when the maximum longitudinal height of the scanned obstacle is less than or equal to the maximum lifting height value.

[0070] The longitudinal determination unit in the identification and determination module compares the maximum longitudinal height of the scanned obstacle with the preset maximum lifting height value hmax, so as to quickly determine whether there are longitudinal obstacles in the loading and unloading path that exceed the maximum lifting stroke of the gantry crane, and determine whether the container to be loaded and unloaded can be directly lifted to the required loading and unloading point by longitudinal lifting.

[0071] The maximum lifting height value hmax set in this embodiment should be selected accordingly according to the maximum lifting stroke of the gantry crane actually used. For example, the gantry crane used in this embodiment selects a gantry crane with a maximum lifting height of 35 meters to meet the loading and unloading needs of the port, and its maximum lifting height value hmax should be less than or equal to 35 meters.

[0072] Specifically, the path simulation module performs lifting simulation on the starting position and the end position of the container to be loaded and unloaded according to the preset lifting value, selects any point at the lowest side of the container to be loaded and unloaded closest to the scanned obstacle as the reference calculation point, simulates and generates the shortest spatial straight line path between the two points after lifting as the initial longitudinal lifting path of the container to be loaded and unloaded, and obtains the preset longitudinal lifting path value according to the preset lifting value, and obtains the preset longitudinal lifting path corresponding to the preset longitudinal lifting path value;

[0073] Among them, L1'=h1×2+l1, L1' is the preset longitudinal lifting path value, h1 is the preset lifting value, and l1 is the initial longitudinal lifting path value of the container to be loaded and unloaded.

[0074] The path simulation module simulates and models the lifting starting point position of the container to be loaded and unloaded and the lifting end point position at the required loading and unloading point according to the preset lifting value h1, thereby simulating and generating the shortest spatial path between the two, and determines whether this path can be used as the final execution path in the loading and unloading path based on the scanned obstacle information, so that the container to be loaded and unloaded can be loaded and unloaded along the shortest path.

[0075] That is, when it is determined that the longitudinal height of the highest point of the scanned obstacle information does not exceed the shortest spatial path generated, it means that there are no stacked containers or other obstacles in the preset longitudinal lifting path generated according to the preset lifting value h1 that may hinder the lifting of the container to be loaded and unloaded. This path can be directly used as the optimal loading and unloading path for lifting and unloading.

[0076] The preset lifting value h1 set in the present embodiment should be selected according to the actual size of the gantry crane, the container to be loaded and unloaded, and the transport container truck. It serves as a pre-lifting value of the simulation path to reduce the possibility of collision with obstacles at the bottom of the yard during the lifting process to a certain extent. At the same time, it serves as a pre-observation value to facilitate relevant facilities or personnel to observe its status after lifting. In case of strong winds or extremely unstable center of gravity of the cargo, which causes the container to be loaded and unloaded to shake significantly after lifting, the loading and unloading operation can be stopped in time to avoid safety problems. Therefore, the preset lifting value h1 set in the present embodiment should not be greater than 0.7 meters and should not be less than 0.3 meters.

[0077] Specifically, the central control processing module can compare and determine the longitudinal height of the highest point of the scanned obstacle with the longitudinal height of the corresponding position in the preset longitudinal lifting path.

[0078] If the longitudinal height at the highest point of the scanned obstacle is less than the longitudinal height at the corresponding position in the preset longitudinal lifting path, the central control processing module will directly execute the preset longitudinal lifting path and lift the container to be loaded and unloaded to the required loading and unloading point.

[0079] When the central control processing module determines that the longitudinal height at the highest point of the scanned obstacle is greater than the longitudinal height at the corresponding position of the preset longitudinal lifting path, the longitudinal height at the highest point of the scanned obstacle is compared with the preset second height value h2 to determine whether it is necessary to generate the longitudinal movement path and the lateral movement path of the container to be loaded and unloaded at the same time.

[0080] The preset second height value h2 set in the present embodiment should also be selected and set according to the gantry crane actually used, and is set to half of the maximum stroke of the gantry crane used. Even when the container to be loaded and unloaded reaches this height, whether it reaches the maximum lifting stroke upward or reaches the lowest point on the ground downward, the value of the hoisting path is the same. Within this range, it means that there is no need to consider the relative position relationship between the required loading and unloading point and the highest point of the scanned obstacle, and the longitudinal hoisting is the optimal path. If the rising height of the container to be loaded and unloaded exceeds the preset second height value h2, it is necessary to consider the size of the final value of the horizontal hoisting path and the final value of the longitudinal hoisting path to determine the optimal path.

[0081] Specifically, a preset second height value is also set in the central control processing module. If the longitudinal height at the highest point of the scanned obstacle is greater than or equal to the longitudinal height at the corresponding position in the preset longitudinal lifting path, the central control processing module will call the preset second height value and compare it with the longitudinal height at the highest point of the scanned obstacle for determination.

[0082] The path simulation module can simulate and model the point at the highest point of the scanning obstacle that is closest to the container to be loaded and unloaded and the point farthest from the container to be loaded and unloaded, and simulate and generate the shortest spatial straight line path between any two adjacent points when the longitudinal height at the highest point of the scanning obstacle is less than or equal to a preset second height value, and obtain two oblique spatial paths and one lateral spatial path, and compare and determine the longitudinal heights of the remaining obstacles on both sides of the highest point of the scanning obstacle according to the two oblique spatial paths.

[0083] When the central control processing module determines that the longitudinal height of the highest point of the scanned obstacle is less than or equal to the preset second height value h2, the container to be loaded and unloaded is modeled on the corresponding two sides of the highest point of the scanned obstacle, that is, the container body to be loaded and unloaded is modeled so that it can completely cross the two sides of the scanned obstacle laterally, and the running path of the container is simulated and generated at the corresponding reference points of all the generated simulation models, and the generated path is compared with the longitudinal heights of the remaining obstacles on both sides of the highest point of the scanned obstacle to determine whether this path can be used as the final generated path.

[0084] Please continue reading Figure 4 As shown, it is a schematic diagram of an actual longitudinal lifting path generated by the path simulation module according to obstacle information simulation in this embodiment;

[0085] Among them, 100 is the container to be loaded and unloaded, 200 is the simulation modeling generated by the path simulation module at the lifting starting point of the container to be loaded and unloaded according to the preset lifting value, 300 is the simulation modeling generated by the path simulation module at the lifting end point of the required loading and unloading point according to the preset lifting value, 400 and 500 are respectively the simulation modeling generated by the path simulation module at the corresponding two sides of the highest scanning obstacle, 600 is the highest scanning obstacle in the scanned loading and unloading path, 101 is the oblique space path of the scanning obstacle close to the container to be loaded and unloaded, 102 is the lateral space path, 103 is the oblique space path of the scanning obstacle close to the required loading and unloading point, and 104 is the preset lifting path lifted by the path simulation module according to the preset lifting value;

[0086] Specifically, the central control processing module can calculate and obtain the actual longitudinal hoisting path value according to the preset lifting value when the longitudinal heights of the remaining obstacles on both sides of the highest point of the scanned obstacle are all less than the longitudinal height at the corresponding position of a corresponding oblique space path;

[0087] Among them, L1=S1+S2+S3+h1×2, L1 is the actual longitudinal lifting path value, S1 is the oblique space path value of the scanning obstacle close to the container to be loaded and unloaded, S2 is the transverse space path value, S3 is the oblique space path value of the scanning obstacle close to the required loading and unloading point, and h1 is the preset lifting value.

[0088] This means that except for the highest obstacle scanned, there are no other obstacles on both sides of the generated path that will hinder the process of lifting and unloading the container to be loaded and unloaded along this path. It is the optimal path under the current state and the loading and unloading operation can be performed.

[0089] Specifically, when the longitudinal height of the remaining obstacles at the highest point of the scanning obstacle close to the container to be loaded and unloaded is greater than the second scanning obstacle of the oblique spatial path of the scanning obstacle close to the container to be loaded and unloaded, the path simulation module can continue to simulate and model the point at the highest position of the second scanning obstacle closest to the container to be loaded and unloaded, and obtain the second oblique spatial path and the third oblique spatial path again;

[0090] The path simulation module can continue to simulate and model a point at the highest position of the third scanning obstacle closest to the required loading and unloading point when the longitudinal height of the remaining obstacles at the highest position of the scanning obstacle close to the required loading and unloading point is greater than the third scanning obstacle of the oblique spatial path close to the required loading and unloading point, and obtain the fourth oblique spatial path and the fifth oblique spatial path again;

[0091] The central control processing module can continue to compare and determine the longitudinal heights of other obstacles on the side of the second scanning obstacle close to the container to be loaded and unloaded and on the side of the third scanning obstacle close to the required loading and unloading point according to the second oblique spatial path and the fifth oblique spatial path respectively. The central control processing module will obtain and calculate the actual longitudinal lifting path value when the longitudinal heights of other obstacles do not exceed the longitudinal height of the corresponding spatial path;

[0092] Among them, L1=S1+S2+S3+h1×2, S1=S1'+S1'', S3=S3'+S3'', S1' is the second oblique space path value, S1'' is the third oblique space path value, S3' is the fourth oblique space path value, and S3'' is the fifth oblique space path value.

[0093] When the central control processing module determines that the longitudinal heights of the remaining obstacles on both sides of the highest point of the scanned obstacle are still greater than the generated path on the corresponding side, the container to be loaded and unloaded will be simulated and modeled again according to the corresponding positions of the remaining obstacles on the corresponding side, and its running path will be simulated and generated again according to the corresponding reference points of all the generated simulation models, and the regenerated path will be compared with the longitudinal heights of the remaining obstacles to determine whether this path can be used as the final generated path.

[0094] Specifically, the identification and determination module is also provided with a maximum lateral transfer value. If the maximum longitudinal height of the scanned obstacle is greater than the maximum lifting height value, the central control processing module will retrieve the maximum lateral transfer value and compare it with the maximum lateral distance value of the scanned obstacle.

[0095] The central control processing module can issue an alarm when the maximum lateral distance value of the scanned obstacle is also greater than the maximum lateral transfer value;

[0096] This means that the scanning obstacles in the loading and unloading path at this time exceed both the maximum lifting stroke and the maximum lateral stroke of the gantry crane, and the container loading and unloading operations can no longer be carried out normally. At this time, an alarm is issued to request manual intervention to determine whether the obstacle needs to be moved first;

[0097] The maximum lateral transfer value lmax set in this embodiment should also be selected in the same manner as the maximum lifting height value hmax according to the maximum lateral movement stroke of the gantry crane actually used;

[0098] When the identification and judgment module determines that the maximum longitudinal height of the scanned obstacle is greater than the maximum lifting height value hmax, the maximum lateral distance value of the scanned obstacle is compared with the maximum lateral transfer value lmax to quickly determine whether there are lateral obstacles in the loading and unloading path that exceed the maximum lateral travel of the gantry crane, and determine whether the container to be loaded and unloaded can be lifted to the required loading and unloading point through lateral lifting.

[0099] Specifically, the recognition and determination module also includes a horizontal determination unit.

[0100] The central control processing module can convert the longitudinal determination unit into a transverse determination unit when the maximum transverse distance value of the scanned obstacle is less than or equal to the maximum transverse transfer value, and simulate the transverse lifting path generation of the scanned obstacle in the generation mode of the actual longitudinal lifting path value, and calculate and obtain its actual transverse lifting path value;

[0101] When the longitudinal height at the highest point of the scanned obstacle is greater than the preset second height value, the central control processing module can simultaneously obtain and calculate the actual horizontal lifting path value and the actual longitudinal lifting path value, and compare the actual horizontal lifting path value with the actual longitudinal lifting path value to select the optimal path as the final generated path.

[0102] That is, when the maximum longitudinal height of the scanned obstacle exceeds the maximum lifting stroke of the gantry crane, and the maximum lateral distance value of the scanned obstacle does not exceed the maximum lateral stroke of the gantry crane, it means that it can only be loaded and unloaded by lateral lifting. At this time, the path simulation module and the central control processing module will simulate and generate its lateral lifting path through the lateral data.

[0103] Please continue reading Figure 3 As shown, it is a flow chart of the container loading and unloading method based on the gantry crane in this embodiment;

[0104] This embodiment also provides a loading and unloading method of a container loading and unloading system based on a gantry crane based on any one of the above items, comprising:

[0105] Step S1, scanning and recording the real-time scene between the container to be loaded and unloaded and the required loading and unloading point through the acquisition module, and obtaining the loading and unloading path between the container to be loaded and unloaded and the loading and unloading point;

[0106] Step S2, identifying and determining the maximum longitudinal height of the highest obstacle on the loading and unloading path obtained by scanning through the identification and determination module;

[0107] Step S3: if the maximum longitudinal height of the scanned obstacle is less than or equal to the maximum lifting height value, then proceed to step S4; if the maximum longitudinal height of the scanned obstacle is greater than the maximum lifting height value, then directly proceed to step S9;

[0108] Step S4, simulating and generating the running path between the container to be loaded and unloaded and the required loading and unloading point through the path simulation module, and calculating and obtaining the initial longitudinal lifting path and the preset longitudinal lifting path of the container to be loaded and unloaded.

[0109] Step S5, compare the preset longitudinal lifting path with the longitudinal position of the highest point of the scanned obstacle through the central control processing module. If the longitudinal height at the highest point of the scanned obstacle is less than the longitudinal height at the corresponding position of the preset longitudinal lifting path, the preset longitudinal lifting path is used as the final generated path to directly execute step S8. If the longitudinal height at the highest point of the scanned obstacle is greater than or equal to the longitudinal height at the corresponding position in the preset longitudinal lifting path, continue to execute step S6.

[0110] Step S6, simulate and model the corresponding position of the container to be loaded and unloaded at the highest point of the scanned obstacle through the path simulation module, and simulate and generate the shortest spatial straight path between any two adjacent simulation models, and judge the remaining obstacles on the corresponding side according to the longitudinal height of the generated path. If there are remaining obstacles exceeding the longitudinal height of the corresponding generated path, continue to step S7. If there are no remaining obstacles exceeding the longitudinal height of the corresponding generated path, this generated path is used as the final generated path and step S8 is directly executed.

[0111] Step S7, continue to simulate and model at the corresponding position of the highest point of the remaining obstacles that exceed the longitudinal height of the corresponding generated path, and continue to compare and determine its generated path with the highest point of the corresponding remaining obstacles. If there is still an excess part, continue to repeat step S7 until there are no remaining obstacles exceeding the longitudinal height of the corresponding generated path, then add up all the generated paths as the final generated path and execute step S8.

[0112] Step S8, the central control processing module controls the execution module to drive the container to be loaded and unloaded to be hoisted according to the final generated path generated by the path simulation module, and hoist it to the required loading and unloading point for loading and unloading.

[0113] Step S9, comparing and judging the maximum lateral distance value of the scanned obstacle according to the maximum lateral transfer value, if the maximum lateral distance value of the scanned obstacle is also greater than the maximum lateral transfer value, directly alarming, if the maximum lateral distance value of the scanned obstacle is less than or equal to the maximum lateral transfer value, then replacing the longitudinal determination data with the lateral determination data and continuing to execute steps S4 to S8.

[0114] Specifically, the container loading and unloading system based on the gantry crane provided by the embodiment of the present invention can achieve the same technical effect by executing the above-mentioned loading and unloading method, which will not be described in detail here.

[0115] So far, the technical solutions of the present invention have been described in conjunction with the preferred embodiments shown in the accompanying drawings. However, it is easy for those skilled in the art to understand that the protection scope of the present invention is obviously not limited to these specific embodiments. Without departing from the principle of the present invention, those skilled in the art can make equivalent changes or substitutions to the relevant technical features, and the technical solutions after these changes or substitutions will fall within the protection scope of the present invention.

[0116] The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. For those skilled in the art, the present invention may have various modifications and variations. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present invention shall be included in the protection scope of the present invention.

Claims

1. A container loading and unloading system based on a gantry crane, characterized in that: include, A first storage module, which is used to store the real-time three-dimensional model data in the yard through a preset first storage hardware, so as to simulate and count the real-time storage quantity and storage location of the existing containers in the yard; A second storage module is used to store the three-dimensional model data of the container trucks and the containers to be loaded and unloaded entering the port or the yard through a preset second storage hardware, so as to match and retrieve the real-time data of the container trucks and the containers to be loaded and unloaded collected by the collection module; The acquisition module scans the three-dimensional data of the container truck and the container to be loaded and unloaded entering the port or the yard through a real-time scanning unit, and scans and records the real-time scene between the container to be loaded and unloaded and the required loading and unloading point, so as to obtain the loading and unloading path information between the container to be loaded and unloaded and the required loading and unloading point; an identification and determination module, which identifies and retrieves obstacle information in the loading and unloading path through a set identification unit as a scanning obstacle for determination, and identifies and determines the maximum longitudinal height of the scanning obstacle according to a preset maximum lifting height value, and the identification and determination module can convert the longitudinal determination unit into a lateral determination unit when determining that the maximum longitudinal height of the scanning obstacle is greater than the maximum lifting height value; A path simulation module simulates and models the container to be loaded and unloaded according to a preset lifting value and the determined information of the scanned obstacle, and simulates and generates a lifting path between the container to be loaded and unloaded and a required loading and unloading point according to the generated modeling data; An execution module is used to drive the container to be loaded and unloaded to move to the required loading and unloading point according to the final generated path; a central control processing module, wherein the central control processing module is connected to the first storage module, the second storage module, the acquisition module, the identification and determination module, the path simulation module and the execution module respectively, and when it is determined that the maximum longitudinal height of the scanning obstacle is greater than a preset second height value preset in the central control processing module, the central control processing module can control the path simulation module to generate a simulation model at a corresponding position of the scanning obstacle, and perform a determination calculation on the simulation path generated by the path simulation module to determine a final generated path, and control the gantry crane to perform loading and unloading operations on the container to be loaded and unloaded; The identification and determination module includes a longitudinal determination unit, which compares and determines the maximum longitudinal height of the scanned obstacle according to a preset maximum lifting height value; The path simulation module can simulate modeling and generate a path for the container to be loaded and unloaded according to a preset lifting value when the maximum longitudinal height of the scanned obstacle is less than or equal to the maximum lifting height value; The path simulation module performs lifting simulation on the starting position and the end position of the container to be loaded and unloaded according to the preset lifting value, selects any point at the lowest side of the container to be loaded and unloaded closest to the scanning obstacle as a reference calculation point, simulates and generates the shortest spatial straight line path between the two points after lifting as the initial longitudinal lifting path of the container to be loaded and unloaded, and obtains the preset longitudinal lifting path value according to the preset lifting value, and obtains the preset longitudinal lifting path corresponding to the preset longitudinal lifting path value; Among them, L1'=h1×2+l1, L1' is the preset longitudinal lifting path value, h1 is the preset lifting value, and l1 is the initial longitudinal lifting path value of the container to be loaded and unloaded; The central control processing module can compare and determine the longitudinal height of the highest point of the scanned obstacle with the longitudinal height of the corresponding position in the preset longitudinal lifting path. If the longitudinal height at the highest point of the scanned obstacle is less than the longitudinal height at the corresponding position in the preset longitudinal lifting path, the central control processing module will directly execute the preset longitudinal lifting path to lift the container to be loaded and unloaded to the required loading and unloading point.

2. The container loading and unloading system based on the gantry crane according to claim 1, characterized in that: If the longitudinal height at the highest point of the scanned obstacle is greater than or equal to the longitudinal height at the corresponding position in the preset longitudinal lifting path, the central control processing module will retrieve the preset second height value and compare it with the longitudinal height at the highest point of the scanned obstacle. The path simulation module can simulate and model a point at the highest point of the scanning obstacle that is closest to the container to be loaded and unloaded and a point that is farthest from the container to be loaded and unloaded, and simulate and generate the shortest spatial straight line path between any two adjacent points when the longitudinal height at the highest point of the scanning obstacle is less than or equal to a preset second height value, and obtain two oblique spatial paths and one lateral spatial path, and compare and determine the longitudinal heights of the remaining obstacles on both sides of the highest point of the scanning obstacle according to the two oblique spatial paths.

3. The container loading and unloading system based on the gantry crane according to claim 2 is characterized in that: The central control processing module can calculate and obtain the actual longitudinal hoisting path value according to the preset lifting value when the longitudinal heights of the remaining obstacles on both sides of the highest point of the scanned obstacle are all less than the longitudinal height of the corresponding position of a corresponding oblique spatial path; Among them, L1=S1+S2+S3+h1×2, L1 is the actual longitudinal lifting path value, S1 is the oblique space path value of the scanning obstacle close to the container to be loaded and unloaded, S2 is the transverse space path value, and S3 is the oblique space path value of the scanning obstacle close to the required loading and unloading point.

4. The container loading and unloading system based on the gantry crane according to claim 3 is characterized in that: The path simulation module can continue to simulate and model a point at the highest position of the second scanning obstacle closest to the container to be loaded and unloaded, and obtain the second oblique spatial path and the third oblique spatial path again when the longitudinal height of the remaining obstacles at the highest position of the scanning obstacle close to the container to be loaded and unloaded is greater than the second scanning obstacle of the oblique spatial path of the scanning obstacle close to the container to be loaded and unloaded; The path simulation module can continue to simulate and model a point at the highest position of the third scanning obstacle closest to the required loading and unloading point when the longitudinal height of the remaining obstacles at the highest position of the scanning obstacle close to the required loading and unloading point is greater than the third scanning obstacle of the oblique spatial path at the side of the scanning obstacle close to the required loading and unloading point, and obtain the fourth oblique spatial path and the fifth oblique spatial path again; The central control processing module can continue to compare and determine the longitudinal heights of other obstacles on the side of the second scanning obstacle close to the container to be loaded and unloaded and on the side of the third scanning obstacle close to the required loading and unloading point according to the second oblique spatial path and the fifth oblique spatial path, respectively. When the longitudinal heights of the other obstacles do not exceed the longitudinal heights of the corresponding spatial paths, the central control processing module obtains and calculates the actual longitudinal lifting path value; Among them, L1=S1+S2+S3+h1×2, S1=S1'+S1'', S3=S3'+S3'', S1' is the second oblique space path value, S1'' is the third oblique space path value, S3' is the fourth oblique space path value, and S3'' is the fifth oblique space path value.

5. The container loading and unloading system based on a gantry crane according to claim 1, characterized in that: The identification and determination module is also provided with a maximum lateral transfer value. If the maximum longitudinal height of the scanned obstacle is greater than the maximum lifting height value, the central control processing module will retrieve the maximum lateral transfer value and compare the maximum lateral distance value of the scanned obstacle. The central control processing module can issue an alarm when the maximum lateral distance value of the scanned obstacle is also greater than the maximum lateral transfer value.

6. The container loading and unloading system based on the gantry crane according to claim 5, characterized in that: The identification and determination module also includes a horizontal determination unit. The central control processing module can convert the longitudinal determination unit into the lateral determination unit when the maximum lateral distance value of the scanned obstacle is less than or equal to the maximum lateral transfer value, and simulate the generation of the lateral lifting path of the scanned obstacle in the generation mode of the actual longitudinal lifting path value, and calculate and obtain the actual lateral lifting path value; The central control processing module can simultaneously obtain and calculate the actual horizontal lifting path value and the actual longitudinal lifting path value when the longitudinal height at the highest point of the scanned obstacle is greater than the preset second height value, and compare the actual horizontal lifting path value with the actual longitudinal lifting path value to select the optimal path as the final generated path.

7. A loading and unloading method of a container loading and unloading system based on a gantry crane according to any one of claims 1 to 6, characterized in that: include, Step S1, scanning and recording the real-time scene between the container to be loaded and unloaded and the required loading and unloading point through the acquisition module, and obtaining the loading and unloading path between the container to be loaded and unloaded and the loading and unloading point; Step S2, identifying and determining the maximum longitudinal height of the highest obstacle on the loading and unloading path obtained by scanning through the identification and determination module; Step S3: if the maximum longitudinal height of the scanned obstacle is less than or equal to the maximum lifting height value, then proceed to step S4; if the maximum longitudinal height of the scanned obstacle is greater than the maximum lifting height value, then directly proceed to step S9; In step S4, a path simulation module is used to simulate and generate a running path between the container to be loaded and unloaded and the required loading and unloading point, and an initial longitudinal lifting path and a preset longitudinal lifting path of the container to be loaded and unloaded are calculated and obtained; Step S5, comparing the preset longitudinal hoisting path with the longitudinal position of the highest point of the scanned obstacle through the central control processing module, if the longitudinal height at the highest point of the scanned obstacle is less than the longitudinal height at the corresponding position of the preset longitudinal hoisting path, then directly executing step S8 using the preset longitudinal hoisting path as the final generated path, if the longitudinal height at the highest point of the scanned obstacle is greater than or equal to the longitudinal height at the corresponding position in the preset longitudinal hoisting path, then continuing to execute step S6; In step S6, a path simulation module is used to simulate and model the container to be loaded and unloaded at the corresponding position of the highest point of the scanned obstacle, and the shortest spatial straight path between any two adjacent simulation models is simulated and generated, and the remaining obstacles on the corresponding side are determined according to the longitudinal height of the generated path. If there are remaining obstacles exceeding the longitudinal height of the corresponding generated path, step S7 is continued to be executed. If there are no remaining obstacles exceeding the longitudinal height of the corresponding generated path, the generated path is used as the final generated path and step S8 is directly executed; The step S7 continues to simulate and model the corresponding position of the highest point of the remaining obstacles that exceed the longitudinal height of the corresponding generated path, and continues to compare and determine the generated path with the highest point of the corresponding remaining obstacles. If there is still an excess part, the step S7 is repeated until there is no remaining obstacle that exceeds the longitudinal height of the corresponding generated path, then all the generated paths are added together as the final generated path and the step S8 is executed; In step S8, the central control processing module controls the execution module to drive the container to be loaded and unloaded to be hoisted according to the final generated path generated by the path simulation module, and hoist it to the required loading and unloading point for loading and unloading; In step S9, the maximum lateral distance value of the scanned obstacle is compared and determined according to the maximum lateral transfer value. If the maximum lateral distance value of the scanned obstacle is also greater than the maximum lateral transfer value, an alarm is directly issued. If the maximum lateral distance value of the scanned obstacle is less than or equal to the maximum lateral transfer value, the longitudinal determination data is replaced with the lateral determination data and steps S4 to S8 are continued.