A hoisting and positioning method for BIM modular prefabrication construction
Through the lifting positioning method of BIM modular prefabricated construction, conflict detection and sequence adjustment are used using IFC standards and independent boundary coordinate information, the problem of control of lifting order and splicing position in modular prefabricated construction is solved, and automatic splicing and precise construction are realized. Reduced labor and time costs.
Patent Information
- Application Number
- CN202410977558.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-22
- Publication Date
- 2024-11-08
- Estimated Expiration
- 2044-07-22
AI Technical Summary
During the modular prefabricated construction process, the control of the module lifting sequence and splicing position is difficult, resulting in problems such as prefabricated module collision and lifting position deviation. The existing methods increase labor costs and time, affecting technology promotion.
The lifting positioning method of BIM modular prefabricated construction is adopted, and the prefabricated module space is established based on the IFC standard, independent boundary coordinate information is obtained, conflict detection and sequence adjustment are performed, and automatic splicing is realized.
Through the lifting and positioning method of BIM modular prefabricated construction, digital control and precise construction of modular prefabricated construction are realized, which reduces manual intervention costs and improves construction efficiency and quality controllability.
Smart Images

Figure CN118495355B_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of modular construction, and in particular to a hoisting and positioning method for BIM modular prefabricated construction. Background Art
[0002] Modular prefabrication can significantly improve the efficiency of engineering construction and effectively improve the controllability of engineering construction quality. However, in the actual production process, the control requirements for module hoisting sequence and splicing position are relatively high, which leads to a series of problems such as prefabricated module collision and module hoisting position deviation.
[0003] In the current production process, high-precision measurement and forced manual intervention are generally used to ensure the accuracy of module prefabrication. However, these methods increase labor costs and time costs, resulting in the loss of the advantages of modular prefabrication construction solutions and hindering the promotion and application of related technologies. Summary of the invention
[0004] The invention discloses a hoisting and positioning method for BIM modular prefabrication construction, so as to overcome the above technical problems.
[0005] In order to achieve the above object, the technical solution of the present invention is:
[0006] A method for hoisting and positioning of BIM modular prefabricated construction comprises the following steps:
[0007] S1: Based on the IFC standard of BIM modular prefabrication, a prefabricated module space for providing a storage space for prefabricated modules is established: including a physical unit space for providing storage of geometric information of the prefabricated modules and an attribute information space for providing storage of attribute information of the prefabricated modules; wherein the attribute information stored in the attribute information space corresponds to the geometric information of the prefabricated modules stored in the physical unit space;
[0008] The geometric information includes the length of the boundary of the prefabricated module and the angle of the boundary of the prefabricated module;
[0009] The attribute information includes independent boundary coordinate information based on the independent coordinate system of the prefabricated module, construction sequence node information of the prefabricated module, and global boundary coordinate information of the prefabricated module;
[0010] S2: Based on the geometric information of the prefabricated module stored in the entity unit space, independent boundary coordinate information of the prefabricated module based on the independent coordinate system of the prefabricated module is obtained;
[0011] S3: According to the initial construction sequence node information of the prefabricated module stored in the attribute information space and the boundary coordinate information of the prefabricated module based on the independent coordinate system, k Prefabricated modules are hoisted;
[0012] S4: According to the prefabricated module conflict detection method, determine k prefabricated modules and the first, ..., k -1 Whether there are conflicts between prefab modules;
[0013] S5: If k prefabricated modules and the first, ..., k - If there is a conflict between 1 prefab modules, swap the k - 1 prefabricated module and k The construction sequence of the prefabricated modules is updated, and the construction sequence node information is updated; and S6 is executed;
[0014] S6: Based on the updated construction sequence node information, repeat S3-S5 until the first K When prefabricated modules are K prefabricated modules and the first, ..., K -When there is no conflict between any of the prefabricated modules, the construction sequence node information at this time is recorded as the final construction sequence node information; S7 is executed;
[0015] in, k An index number representing the construction sequence of the prefabricated module in the construction sequence node information of the prefabricated module; K Indicates the total number of prefabricated modules;
[0016] S7: hoisting the prefabricated modules according to the final construction sequence node information to complete the automatic splicing of the prefabricated modules.
[0017] Furthermore, the method used to obtain the independent boundary coordinate information of the independent coordinate system based on the prefabricated module is as follows:
[0018] S21: Obtain the coordinates of the boundary reference point on the boundary of the prefabricated module ;
[0019] Among them, the boundary reference points satisfy:
[0020] Where: Represents any point on the prefabricated module in the prefabricated module independent coordinate system x Coordinates in the axis direction; Represents any point on the prefabricated module in the prefabricated module independent coordinate system y Coordinates in the axis direction; Represents any point on the prefabricated module in the prefabricated module independent coordinate system z Coordinates in the axis direction; The boundary reference points are located in the independent coordinate system of the prefabricated module. x The coordinates of the axis direction, yThe coordinates of the axis direction, z Coordinates in the axis direction;
[0021] S22: According to the geometric information of the prefabricated module, the boundary coordinate information of the prefabricated module based on the independent coordinate system is obtained as follows:
[0022]
[0023] Where: x b,m The first coordinate system of the prefabricated module represents the b On the border m Points in x Coordinates on the axis; y b,m The first coordinate system of the prefabricated module represents the b On the border m Points in y Coordinates on the axis; z b,m The first coordinate system of the prefabricated module represents the b On the border m Points in z Coordinates on the axis; l b Indicates the first b The length of the border; Indicates the first b The border and x The angle of the axis; Indicates the first b The border and y The angle of the axis; Indicates the first b The border and z The angle of the axis; b An index number representing the boundary of the prefabricated module; m The index number of the point on the boundary.
[0024] Furthermore, for k The method of hoisting a prefabricated module is as follows:
[0025] S31: Obtain the construction sequence node information based on the current prefabricated module. k Independent boundary coordinate information of each prefabricated module;
[0026] S32: According to k The independent boundary coordinate information of each prefabricated module is obtained based on the coordinate conversion formula. k The global boundary coordinate information of each prefabricated module;
[0027] S33: According to k The global boundary coordinate information of the prefabricated module is k Prefabricated modules are hoisted;
[0028] in, k Represents the index number of the prefabricated module construction sequence in the prefabricated module construction sequence node information.
[0029] Furthermore, the independent coordinate system conversion calculation formula of the prefabricated module is as follows:
[0030]
[0031] Where: X 22 , Y 22 , Z 22 Represents points in independent coordinate systems x Axis coordinates, y Axis coordinates and z Axis coordinates; It is the basic origin of the global coordinate system; k ' is the magnification factor of the prefabricated module; The points in the independent coordinate system are clockwise to x , y , z The angle of the axis; Indicates cosine value calculation; X 11 , Y 11 , Z 11 Respectively represent the points after conversion to the global coordinate system x Axis coordinates, y Axis coordinates and z Axis coordinates.
[0032] Furthermore, in S4, the prefabricated module conflict detection method is:
[0033] If there is i The boundary point on the first prefabricated module and the j The boundary points on the prefabricated modules satisfy:
[0034]
[0035] Where: x j Indicates j The boundary points on the prefabricated module are in the global coordinate system x Axis coordinates; y j Indicatesj The boundary points on the prefabricated module are in the global coordinate system y Axis coordinates; z j Indicates j The boundary points on the prefabricated module are in the global coordinate system z Axis coordinates; x i,m Indicates i The first prefabricated module m The boundary points in the global coordinate system x Axis coordinates; y i,m Indicates i The first prefabricated module m The boundary points in the global coordinate system y Axis coordinates; z i,m Indicates i The first prefabricated module m The boundary points in the global coordinate system z Axis coordinates; x i,n Indicates i The first prefabricated module n The boundary points in the global coordinate system x Axis coordinates; y i,n Indicates i The first prefabricated module n The boundary points in the global coordinate system y Axis coordinates; z i,n Indicates i The first prefabricated module n The boundary points in the global coordinate system z Axis coordinates; i , j All are numbers of prefabricated modules; m , n They are all index numbers of points on the boundary;
[0036] The first i The prefabricated modules and j There are conflicts between prefabricated modules;
[0037] Otherwise there is no conflict.
[0038] Beneficial effects: The hoisting and positioning method of a BIM modular prefabricated construction of the present invention is based on the IFC standard of BIM modular prefabricated construction, and a prefabricated module space for providing storage space for prefabricated modules is established. Based on this, the geometric information of the prefabricated modules stored in the entity unit space is used to obtain the independent boundary coordinate information of the prefabricated modules based on the independent coordinate system of the prefabricated modules, and then hoisting is performed. During the hoisting process, conflict detection is performed on the prefabricated modules after each hoisting, and finally the final construction sequence node information is determined to complete the automatic splicing of the prefabricated modules. In the prefabrication and assembly process of the present invention, the IFC standard of BIM is used to manage entity and attribute information, thereby realizing digital control and precise construction of modular prefabricated construction. BRIEF DESCRIPTION OF THE DRAWINGS
[0039] In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the following briefly introduces the drawings required for use in the embodiments or the description of the prior art. Obviously, the drawings described below are some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative labor.
[0040] Figure 1 One of the flow charts of the hoisting and positioning method of the prefabricated construction of the present invention;
[0041] Figure 2 This is a second flow chart of the hoisting and positioning method for prefabricated construction according to an embodiment of the present invention;
[0042] Figure 3 It is a spatial structure expansion diagram of a BIM module according to an embodiment of the present invention;
[0043] Figure 4 It is an expanded diagram of the spatial structure of a solid unit according to an embodiment of the present invention;
[0044] Figure 5 This is a modular prefabricated hoisting effect diagram in a real-time example of the present invention. DETAILED DESCRIPTION
[0045] In order to make the purpose, technical solution and advantages of the embodiments of the present invention clearer, the technical solution in the embodiments of the present invention will be clearly and completely described below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0046] This embodiment discloses a method for hoisting and positioning of BIM modular prefabricated construction, as follows Figure 1 and Figure 2As shown, the following steps are included:
[0047] S1: Based on the IFC standard of BIM modular prefabricated construction, a prefabricated module space for providing storage space for prefabricated modules is established: including a physical unit space for storing geometric information of prefabricated modules and an attribute information space for storing attribute information of prefabricated modules; wherein the attribute information stored in the attribute information space corresponds to the geometric information of the prefabricated modules stored in the physical unit space; that is, the attribute information is obtained based on the geometric information of the prefabricated modules stored in the physical unit space.
[0048] The geometric information includes the length of the boundary of the prefabricated module and the angle of the boundary of the prefabricated module;
[0049] The attribute information includes independent boundary coordinate information based on the independent coordinate system of the prefabricated module and construction sequence node information of the prefabricated module;
[0050] Specifically, spatial collision check is one of the core technical advantages of BIM (Building Information Modeling). Using BIM to manage the data of prefabricated modules and, on this basis, to carry out coordinate management in aspects such as spatial collision check, construction sequence definition, automatic lifting and splicing control in the prefabricated construction process is expected to effectively solve the aforementioned key problems.
[0051] Specifically, in this embodiment, a flexible IFC data management rule is established to perform standardized management of geometric information and attribute information of prefabricated modules, wherein the attribute information includes but is not limited to independent boundary coordinate information based on an independent coordinate system of the prefabricated modules, construction time sequence node information of the prefabricated modules, and coordinate system conversion information of the prefabricated modules in a hoisting main body environment, i.e., global boundary coordinate information, etc.;
[0052] Specifically, this embodiment is based on the IFC4 standard, and defines the IFCPrefabricatedModule prefabricated module space under the IfcSpatial-StructureElement (spatial structure element) parent class. The newly defined prefabricated module space is a parallel subclass with IfcBuilding, IfcSite, IfcSpace, etc. in the IFC4 standard. At the same time, enumeration type definitions are performed under the prefabricated module space IFCPrefabricatedModule, including but not limited to IfcModeltypeEnum, IfcModelFunctionEnum, etc. The prefabricated module space provides space for IFC storage of prefabricated building modules. The expanded spatial structure is as follows Figure 3 shown.
[0053] Specifically, this embodiment also defines a new entity unit space IfcPrefabricatedElement under the IfcElement parent class based on the IFC4 standard for storing geometric information of prefabricated modules. The entity unit space contains basic geometric model information of prefabricated building modules, including the length of the boundary of the prefabricated module, the angle of the boundary of the prefabricated module, etc., which is used to generate the entity model. Figure 4 shown.
[0054] Specifically, this embodiment defines the attribute information set of the expanded new entity based on the prefabricated modules stored in the entity unit space. The attribute information includes but is not limited to the independent boundary coordinate information of the independent coordinate system based on the prefabricated module, the construction time sequence node information attribute set of this module, and the coordinate system conversion information attribute set of the independent prefabricated module in the main body lifting environment.
[0055] Taking the boundary coordinate information attribute set as an example, its definition is shown in Table 1.
[0056]
[0057] In this embodiment, the prefabricated module space provides storage space for the prefabricated module entity, and the entity unit space provides a geometric model for the attribute information of the prefabricated module in the attribute information space, thereby realizing the data standard management of modular prefabricated construction. Among them, the content stored in the entity unit space and the attribute information space of this embodiment is not limited to the types listed in this embodiment, but can be flexibly expanded according to actual needs and the method shown in this embodiment.
[0058] S2: Based on the geometric information of the prefabricated module stored in the entity unit space, obtaining independent boundary coordinate information based on the independent coordinate system of the prefabricated module;
[0059] Preferably, the method used to obtain the independent boundary coordinate information of the independent coordinate system based on the prefabricated module is as follows:
[0060] S21: Obtain the coordinates of the boundary reference point on the boundary of the prefabricated module , that is, obtaining the endpoint coordinates on the boundary of the prefabricated module;
[0061] Among them, the boundary reference points satisfy:
[0062] Where: Represents any point on the prefabricated module in the prefabricated module independent coordinate system x Coordinates in the axis direction; Represents any point on the prefabricated module in the prefabricated module independent coordinate system y Coordinates in the axis direction; Represents any point on the prefabricated module in the prefabricated module independent coordinate system z Coordinates in the axis direction; The boundary reference points are located in the independent coordinate system of the prefabricated module. x The coordinates of the axis direction, y The coordinates of the axis direction, z Coordinates in the axis direction;
[0063] S22: According to the geometric information of the prefabricated module, the boundary coordinate information of the prefabricated module based on the independent coordinate system is obtained as follows:
[0064]
[0065] Where: x b,m The first coordinate system of the prefabricated module represents the b On the border m Points in x Coordinates on the axis; y b,m The first coordinate system of the prefabricated module represents the b On the border m The coordinate of a point on the y-axis; z b,m The first coordinate system of the prefabricated module represents the b On the border m Points in z Coordinates on the axis; l b Indicates the first b The length of the border; Indicates the first b The border and x The angle of the axis; Indicates the first b The border and y The angle of the axis; Indicates the first b The border and z The angle of the axis; b An index number representing the boundary of the prefabricated module; m The index number of the point on the boundary.
[0066] Based on the above method, the coordinates of all boundary points can be calculated.
[0067] Specifically, in this embodiment, when the prefabricated module entity is stored in the prefabricated module space, the geometric information of the prefabricated module is stored in the entity unit space, and based on the prefabricated module geometric information stored in the entity unit space, the independent boundary coordinate information of the prefabricated module based on the independent coordinate system of the prefabricated module is obtained.
[0068] Specifically, in one embodiment of the present invention, the geometric information of the prefabricated module is parsed to obtain the independent boundary coordinate information of the prefabricated module based on the independent coordinate system of the prefabricated module as follows:
[0069] The IFC geometric entity expression of the rectangular prefabricated module BIM is:
[0070] #1010= IFCPRODUCTDEFINITIONSHAPE ($,$,(#1020));
[0071] #1020= IFCSHAPEREPRESENTATION (#202,'Body','SurfaceModel',(#1021));
[0072] #1021= IFCFACEBASEDSURFACEMODEL ((#1022));
[0073] #1022= IFCCONNECTEDFACESET ((#1110,#1120,#1130,#1140,#1150,#1160));
[0074] #1110= IFCFACE ((#1111));
[0075] #1111= IFCFACEOUTERBOUND (#1112,.T.);
[0076] #1112= IFCPOLYLOOP ((#1201,#1202,#1206,#1205));
[0077] #1201= IFCCARTESIANPOINT ((-500.,-500.,0.));
[0078] Use "IFCSHAPEREPRESENTATION" as the index identifier to search for the "SurfaceModel" character, that is, line #1020. According to the string number it references, enter the corresponding IFC statement to obtain geometric information. That is, from line #1020, index into line #1021 → line #1022.
[0079] Using "IFCCONNECTEDFACESET" as the index identifier, we can get all the statements of the model's surface components, parse each surface statement separately, and obtain the key coordinate point information. #1022 means that the model consists of 6 surfaces, namely: #1110, #1120, #1130, #1140, #1150, #1160.
[0080] Enter a certain face statement, obtain the lines and points that make up the face in turn, and capture them in an independent coordinate system x Axis direction or y Axis direction or z The maximum value of the coordinates in the axis direction is used to obtain the reference point of the boundary point. This process is repeated to retrieve all the surface statements and obtain the coordinates of all the boundary points of the prefabricated model. The obtained boundary point coordinates are stored in the boundary coordinate information attribute set expanded in S13.
[0081] Specifically, in another embodiment of the present invention, the coordinates of the boundary reference point are to enter a certain surface statement, obtain the lines and points of the surface in sequence, and capture them in an independent coordinate system. x Axis direction or y Axis direction or z The method of finding the minimum value of the coordinates in the axis direction is used to obtain the boundary reference point.
[0082] S3: According to the initial construction sequence node information of the prefabricated module stored in the attribute information space and the independent boundary coordinate information of the prefabricated module based on the independent coordinate system of the prefabricated module, k Prefabricated modules are hoisted;
[0083] Preferably, k The method of hoisting a prefabricated module is as follows:
[0084] S31 obtains the first node information of the construction sequence based on the current prefabricated module. k Independent boundary coordinate information of each prefabricated module;
[0085] S32: According to k The independent boundary coordinate information of each prefabricated module is obtained based on the coordinate conversion formula. k The global boundary coordinate information of each prefabricated module;
[0086] S33: According to k The global boundary coordinate information of the prefabricated module is k Prefabricated modules are hoisted.
[0087] Preferably, the independent coordinate system conversion calculation formula of the prefabricated module is as follows:
[0088] Specifically, when performing conflict checking, the independent coordinate system of the prefabricated module needs to be converted into the overall coordinate system of the engineering structure, and the coordinates of the reference origin in the overall coordinate system are used as the control basis to automatically and accurately splice the prefabricated modules;
[0089] Specifically, in this embodiment, the independent coordinate system of the prefabricated module defaults to (0,0,0) as the basic origin. , and its transformation to the global coordinate system is:
[0090] (1)
[0091] Where: X 22 , Y 22 , Z 22 Represents points in independent coordinate systems x Axis coordinates, y Axis coordinates and z Axis coordinates; It is the basic origin of the global coordinate system; k ' is the magnification factor of the prefabricated module; The points in the independent coordinate system are clockwise to x , y , z The angle of the axis; Indicates cosine value calculation; X 11 , Y 11 , Z 11 Respectively represent the points after conversion to the global coordinate system x Axis coordinates, y Axis coordinates and z Axis coordinates.
[0092] Among them, the matrix calculation form of formula (3) is:
[0093] (2)
[0094] For common linear models, the conversion formula can also be used:
[0095] (3)
[0096] S4: According to the prefabricated module conflict detection method, determine k prefabricated modules and the first, ..., k -1 Whether there is a conflict between prefabricated modules; k The first prefabricated module and the first one that has been hoisted, ...,k -1 Collision check of spaces between prefab modules;
[0097] S5: If k prefabricated modules and the first, ..., k - If there is a conflict between 1 prefab modules, swap the k - 1 prefabricated module and k The construction sequence of the prefabricated modules is updated, and the construction sequence node information is updated; and S6 is executed;
[0098] Specifically, in this embodiment, if it is detected that there is no conflict, the first k +1 prefabricated module for hoisting;
[0099] S6: Based on the updated construction sequence node information, repeat S3-S5 until the first K When the number of prefabricated modules is K prefabricated modules and the first, ..., K -When there is no conflict between any of the prefabricated modules, the construction sequence node information at this time is recorded as the final construction sequence node information; S7 is executed;
[0100] Specifically, in an embodiment of the present invention, if re-hoisting is performed based on the updated construction sequence node information, if a conflict still occurs between the hoisting of two prefabricated modules that have exchanged construction sequence nodes, the entire prefabricated construction needs to be manually redesigned.
[0101] S7: hoisting the prefabricated modules according to the final construction sequence node information to complete automatic and accurate splicing of the prefabricated modules.
[0102] Preferably, in S4, the prefabricated module conflict detection method is:
[0103] If there is i The boundary point on the first prefabricated module and the j The boundary points on the prefabricated modules satisfy:
[0104]
[0105] Where: x j Indicates j The boundary points on the prefabricated module are in the global coordinate system x Axis coordinates; y j Indicates j The boundary points on the prefabricated module are in the global coordinate system y Axis coordinates; z jIndicates j The boundary points on the prefabricated module are in the global coordinate system z Axis coordinates; x i,m Indicates i The first prefabricated module m The boundary points in the global coordinate system x Axis coordinates; y i,m Indicates i The first prefabricated module m The boundary points in the global coordinate system y Axis coordinates; z i,m Indicates i The first prefabricated module m The boundary points in the global coordinate system z Axis coordinates; x i,n Indicates i The first prefabricated module n The boundary points in the global coordinate system x Axis coordinates; y i,n Indicates i The first prefabricated module n The boundary points in the global coordinate system y Axis coordinates; z i,n Indicates i The first prefabricated module n The boundary points in the global coordinate system z Axis coordinates; i , j All are numbers of prefabricated modules; m , n They are all index numbers of points on the boundary;
[0106] The first i The prefabricated modules and j There are conflicts between prefabricated modules;
[0107] Otherwise there is no conflict.
[0108] in, .
[0109] This embodiment uses an exhaustive form to cyclically detect whether all boundaries of the prefabricated modules have conflicts, thereby completing the conflict check between two prefabricated modules.
[0110] Specifically, in one embodiment of the present invention:
[0111] One of the boundary line endpoints of prefabricated module 1 is:
[0112] [A(40,40,40),B(75,80,100)] (5)
[0113] For a boundary point C(50,100100) of prefabricated module 2, it is found that:
[0114] 40<50<75 and 40<100=100 (6)
[0115] That is, prefabricated module 1 and prefabricated module 2 conflict on the X boundary, and their Z boundaries are close to each other. It is necessary to adjust the relative positions of the two before lifting and construction.
[0116] In an exhaustive manner, all boundary points of prefabricated module 2 and all boundaries of prefabricated module 1 are cyclically retrieved to complete the conflict check between the two modules.
[0117] A specific embodiment of the present invention is as follows:
[0118] The independent coordinate system of the prefabricated module defaults to (0,0,0) as the base origin. For the random point B (75,80,100) in this coordinate system, when it is transformed to the global coordinate system with (10,20,10) as the base origin, the magnification factor of the prefabricated module is 1.7. x,y,z The stretch coefficients in the directions are 1.1, 1.0, and 1.3 respectively. Then, the coordinates of the prefabricated module in the global coordinate system after conversion are:
[0119] (7)
[0120] After conversion, we get: After completing the conversion of all coordinate points, accurate hoisting and splicing work can be carried out, and the construction effect is as follows: Figure 5 shown.
[0121] The embodiments of the present invention include the following beneficial effects:
[0122] (1) IFC standardized management and flexible expansion of module prefabrication information. In response to practical problems encountered in the modular prefabrication construction process, an IFC flexible expansion method is proposed, which can not only realize the standardized storage and management of module prefabrication information, but also provide complete expansion rules, so that the optimization and innovation work in other aspects of modular prefabrication can also achieve standard management of data according to this method. The standardized storage and management of module prefabrication information enables prefabricated modules to achieve lossless information exchange between BIM platforms, providing a solid data foundation for the coordination and cooperation of different departments in the actual production process;
[0123] (2) Acquisition of module boundary coordinate information. The boundary information of prefabricated modules is the basis for collision checking and precise hoisting and splicing. The method of this embodiment enables users to obtain module boundary information in real time, quickly and accurately, without being restricted by traditional text transmission methods. It effectively avoids problems such as information loss and information transmission errors, and provides accurate coordinate guarantees for modular prefabrication. The proposed method for acquiring the coordinates of the boundary points of prefabricated modules effectively solves problems such as collision of prefabricated modules and deviation of module hoisting positions;
[0124] (3) Collision check based on boundary coordinates. Compared with the previous three-dimensional entity collision check, the collision detection method of this embodiment has lower power consumption and faster calculation speed in boundary coordinate calculation, and can quickly and accurately find potential collision points, thereby effectively improving the efficiency of collision checking;
[0125] (4) Conversion calculation from independent coordinate system to global coordinate system. The global coordinate system position that the current independent prefabricated module should be in during the splicing process is calculated by coordinate conversion. This can make the splicing position more controllable when the independent prefabricated modules are assembled in different hoisting environments, and can effectively improve the hoisting splicing accuracy.
[0126] Finally, it should be noted that the above embodiments are only used to illustrate the technical solutions of the present invention, rather than to limit it. Although the present invention has been described in detail with reference to the aforementioned embodiments, those skilled in the art should understand that they can still modify the technical solutions described in the aforementioned embodiments, or replace some or all of the technical features therein with equivalents. However, these modifications or replacements do not cause the essence of the corresponding technical solutions to deviate from the scope of the technical solutions of the embodiments of the present invention.
Claims
1. A method for hoisting and positioning of BIM modular prefabricated construction, characterized in that: The steps include: S1: Based on the IFC standard of BIM modular prefabrication, a prefabricated module space for providing a storage space for prefabricated modules is established: including a physical unit space for providing storage of geometric information of the prefabricated modules and an attribute information space for providing storage of attribute information of the prefabricated modules; wherein the attribute information stored in the attribute information space corresponds to the geometric information of the prefabricated modules stored in the physical unit space; The geometric information includes the length of the boundary of the prefabricated module and the angle of the boundary of the prefabricated module; The attribute information includes independent boundary coordinate information based on the independent coordinate system of the prefabricated module, construction sequence node information of the prefabricated module, and global boundary coordinate information of the prefabricated module; S2: Based on the geometric information of the prefabricated module stored in the entity unit space, independent boundary coordinate information of the prefabricated module based on the independent coordinate system of the prefabricated module is obtained; The method used to obtain the independent boundary coordinate information of the independent coordinate system based on the prefabricated module is as follows: S21: Obtain the coordinates of the boundary reference point on the boundary of the prefabricated module ; Among them, the boundary reference points satisfy: Where: Represents any point on the prefabricated module in the prefabricated module independent coordinate system x Coordinates in the axis direction; Represents any point on the prefabricated module in the prefabricated module independent coordinate system y Coordinates in the axis direction; Represents any point on the prefabricated module in the prefabricated module independent coordinate system z Coordinates in the axis direction; The boundary reference points are located in the independent coordinate system of the prefabricated module. x The coordinates of the axis direction, y The coordinates of the axis direction, z Coordinates in the axis direction; S22: According to the geometric information of the prefabricated module, the boundary coordinate information of the prefabricated module based on the independent coordinate system is obtained as follows: Where: x b,m The first coordinate system of the prefabricated module represents the b On the border m Points in x Coordinates on the axis; y b,m The first coordinate system of the prefabricated module represents the b On the border m Points in y Coordinates on the axis; z b,m The first coordinate system of the prefabricated module represents the b On the border m Points in z Coordinates on the axis; l b Indicates the first b The length of the border; Indicates the first b The border and x The angle of the axis; Indicates the first b The border and y The angle of the axis; Indicates the first b The border and z The angle of the axis; b An index number representing the boundary of the prefabricated module; m The index number of the point on the boundary; S3: According to the initial construction sequence node information of the prefabricated module stored in the attribute information space and the boundary coordinate information of the prefabricated module based on the independent coordinate system, k Prefabricated modules are hoisted; S4: According to the prefabricated module conflict detection method, determine k prefabricated modules and the first, ..., k -1 Whether there are conflicts between prefab modules; S5: If k prefabricated modules and the first, ..., k - If there is a conflict between 1 prefab modules, swap the k - 1 prefabricated module and k The construction sequence of the prefabricated modules is updated, and the construction sequence node information is updated; and S6 is executed; S6: Based on the updated construction sequence node information, repeat S3-S5; until the first K When prefabricated modules are K prefabricated modules and the first, ..., K -When there is no conflict between any of the prefabricated modules, the construction sequence node information at this time is recorded as the final construction sequence node information; S7 is executed; in, k An index number representing the construction sequence of the prefabricated module in the construction sequence node information of the prefabricated module; K Indicates the total number of prefabricated modules; S7: hoisting the prefabricated modules according to the final construction sequence node information to complete the automatic splicing of the prefabricated modules.
2. A method for hoisting and positioning of BIM modular prefabricated construction according to claim 1, characterized in that: For k The method of hoisting a prefabricated module is as follows: S31: Obtain the construction sequence node information based on the current prefabricated module. k Independent boundary coordinate information of each prefabricated module; S32: According to k The independent boundary coordinate information of each prefabricated module is obtained based on the coordinate conversion formula. k The global boundary coordinate information of each prefabricated module; S33: According to k The global boundary coordinate information of the prefabricated module k Prefabricated modules are hoisted; in, k Represents the index number of the prefabricated module construction sequence in the prefabricated module construction sequence node information.
3. The method for hoisting and positioning of BIM modular prefabricated construction according to claim 2 is characterized in that: The independent coordinate system conversion calculation formula of the prefabricated module is as follows: Where: X 22 , Y 22 , Z 22 Represents points in independent coordinate systems x Axis coordinates, y Axis coordinates and z Axis coordinates; It is the basic origin of the global coordinate system; k ' is the magnification factor of the prefabricated module; The points in the independent coordinate system are clockwise to x , y , z The angle of the axis; Indicates cosine value calculation; X 11 , Y 11 , Z 11 Respectively represent the points after conversion to the global coordinate system x Axis coordinates, y Axis coordinates and z Axis coordinates.
4. The method for hoisting and positioning of BIM modular prefabricated construction according to claim 1, characterized in that: In S4, the prefabricated module conflict detection method is: If there is i The boundary point on the first prefabricated module and the j The boundary points on the prefabricated modules satisfy: Where: x j Indicates j The boundary points on the prefabricated module are in the global coordinate system x Axis coordinates; y j Indicates j The boundary points on the prefabricated module are in the global coordinate system y Axis coordinates; z j Indicates j The boundary points on the prefabricated module are in the global coordinate system z Axis coordinates; x i,m Indicates i The first prefabricated module m The boundary points in the global coordinate system x Axis coordinates; y i,m Indicates i The first prefabricated module m The boundary points in the global coordinate system y Axis coordinates; z i,m Indicates i The first prefabricated module m The boundary points in the global coordinate system z Axis coordinates; x i,n Indicates i The first prefabricated module n The boundary points in the global coordinate system x Axis coordinates; y i,n Indicates i The first prefabricated module n The boundary points in the global coordinate system y Axis coordinates; z i,n Indicates i The first prefabricated module n The boundary points in the global coordinate system z Axis coordinates; i , j All are numbers of prefabricated modules; m , n They are all index numbers of points on the boundary; The first i The prefabricated modules and j There are conflicts between prefabricated modules; Otherwise there is no conflict.