Electromagnetic compatibility test method and test system for industrial control power supply
By using the topological structure diagram of the production environment, EMI signal generator, and EMS sensor in the electromagnetic compatibility test of industrial control power supply to simulate the industrial environment for testing, it solves the problem that existing technology cannot accurately evaluate the electromagnetic compatibility of industrial control power supply in different application fields. problems, improving its reliability and stability in harsh environments.
Patent Information
- Application Number
- CN202410963979.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-18
- Publication Date
- 2024-10-29
- Estimated Expiration
- 2044-07-18
AI Technical Summary
The electromagnetic compatibility test of existing industrial control power supplies cannot effectively reflect its reliability and stability in different application fields, especially in harsh industrial environments, and cannot accurately evaluate its electromagnetic compatibility.
By importing the topology structure diagram of the production environment, analyze the location parameters, topological connection parameters and EMC parameters of the target equipment and environmental equipment, establish the location mapping relationship between the production environment and the test environment, arrange the EMI signal generator and EMS sensor, and simulate the power input signal With the load, perform EMC testing to more accurately evaluate the electromagnetic compatibility of industrial power supplies.
Provide test results more suitable for practical applications, optimize the design and performance of industrial control power supplies, and improve its reliability and stability in industrial environments.
Smart Images

Figure CN118518969B_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of electromagnetic compatibility testing, and in particular to an electromagnetic compatibility testing method and a testing system for an industrial control power supply. Background Art
[0002] Industrial control power supply is an important part of industrial control electronic equipment. The power supply quality and reliability of industrial control power supply directly affect the quality of the entire industrial control electronic equipment. Compared with other power supplies, the application environment of industrial control power supply is more severe, especially in industrial processing sites. The start and stop operation of various processing machinery and power equipment will generate a large number of electromagnetic interference signals, such as welding and electric spark processing, thyristor investigation, frequency conversion equipment, etc. These electromagnetic interferences are usually very destructive to power supply. In some special application environments, such as medical or data center application fields, the electromagnetic interference generated by the industrial control power supply itself also has a great impact on some equipment with high electromagnetic sensitivity. Therefore, the electromagnetic compatibility of industrial control power supply is one of the important indicators for evaluating the quality of industrial control power supply. In the prior art, the electromagnetic compatibility test of industrial control power supply is usually carried out in some general test environments such as laboratory environments such as radio darkrooms or shielded rooms to measure whether the electromagnetic compatibility indicators of industrial control power supply meet the standards. This test method can only simply reflect the electromagnetic compatibility indicators of industrial control power supply, but cannot effectively reflect its reliability and stability in different application fields. Summary of the invention
[0003] Based on the above problems, the present invention proposes an electromagnetic compatibility testing method and testing system for industrial control power supplies, which can more accurately evaluate the electromagnetic compatibility of industrial control power supplies, provide test results that are more suitable for practical applications, help optimize the design and performance of industrial control power supplies, and improve the reliability and stability of industrial control power supplies in actual industrial environments.
[0004] In view of this, a first aspect of the present invention provides an electromagnetic compatibility testing method for an industrial control power supply, comprising:
[0005] Importing at least one topological structure diagram of a production environment, wherein the topological structure diagram of the production environment is a topological structure diagram constructed based on a real production environment and used to describe the arrangement of industrial field devices in the production environment;
[0006] Parsing location parameters, topological connection parameters and EMC parameters of target devices and environment devices from the topological structure diagram of the production environment, wherein the EMC parameters include EMI parameters and EMS parameters;
[0007] Acquire indoor structural parameters of the test environment, wherein the indoor structural parameters of the test environment include indoor plane size parameters or indoor three-dimensional size parameters of the test environment;
[0008] Establishing a location mapping relationship between the production environment and the test environment;
[0009] Arranging an EMI signal generator for performing an EMS test on an industrial control power supply and / or an EMS sensor for performing an EMI test on an industrial control power supply in the test environment according to the position mapping relationship and the position parameters, topology connection parameters and EMC parameters of the environmental equipment, wherein the EMI signal generator is used to generate an EMI signal that matches the EMI parameters of the environmental equipment at the corresponding position, and the EMS parameters of the EMS sensor match the EMS parameters of the environmental equipment at the corresponding position;
[0010] Arranging the industrial control power supply to be tested in the test environment corresponding to the mapping position of the target device;
[0011] Connecting a simulated power input signal and a simulated load to the industrial control power supply to be tested, wherein the simulated power input signal matches the power signal connected to the target device in the production environment, and the simulated load matches the load state of the target device in the production environment;
[0012] Perform EMC testing on the industrial control power supply to be tested.
[0013] Furthermore, before the step of importing at least one topology diagram of the production environment, the method further includes:
[0014] Build a topology graph database for the production environment;
[0015] Configuring a topology diagram of a production environment corresponding to each application field in the topology diagram database;
[0016] The steps of importing at least one topology diagram of the production environment include:
[0017] Determine the target device type corresponding to the industrial control power supply to be tested;
[0018] Determine the application field corresponding to the industrial control power supply to be tested according to the target device type;
[0019] At least one topology diagram of the production environment of the application field is read from the topology diagram database.
[0020] Furthermore, the step of establishing a location mapping relationship between the production environment and the test environment specifically includes:
[0021] Parsing indoor structural parameters of the production environment from the topological structure diagram of the production environment, wherein the indoor structural parameters of the production environment include indoor plane size parameters or indoor three-dimensional size parameters of the production environment;
[0022] comparing indoor structural parameters of the test environment with indoor structural parameters of the production environment;
[0023] When any indoor dimension of the length, width, and height of the test environment is smaller than the corresponding indoor dimension of the production environment, calculating a mapping ratio between the test environment and the production environment;
[0024] Establishing a location mapping relationship between the production environment and the test environment according to the mapping ratio;
[0025] The EMC parameters of the environmental equipment are corrected according to the mapping ratio.
[0026] Furthermore, the indoor structural parameters of the production environment and the test environment are indoor plane size parameters, and the step of calculating the mapping ratio of the test environment to the production environment specifically includes:
[0027] Generate a first indoor plan view of the production environment and a second indoor plan view of the test environment based on indoor plan size parameters of the production environment and the test environment;
[0028] Determine a first center point position of the production environment on the first indoor plan and determine a second center point position of the test environment on the second indoor plan;
[0029] An original coordinate system of the production environment is constructed with the first center point as the origin, with the length of the first indoor plan view as the horizontal axis of the original coordinate system, and the width of the first indoor plan view as the vertical axis of the original coordinate system;
[0030] Constructing a mapping coordinate system of the test environment with the second center point as the origin, with the length of the second indoor plan view as the horizontal axis of the mapping coordinate system, and the width of the second indoor plan view as the vertical axis of the mapping coordinate system;
[0031] Determine the first maximum horizontal axis coordinate value on the first indoor plan and the first maximum vertical axis coordinate value , and the second maximum horizontal axis coordinate value on the second indoor plan and the second maximum vertical axis coordinate value ;
[0032] Calculate the length dimension difference between the first indoor plan and the second indoor plan:
[0033] ;
[0034] Calculate the width dimension difference between the first indoor plan and the second indoor plan:
[0035] ;
[0036] when When the mapping ratio between the test environment and the production environment is determined as:
[0037] ;
[0038] when When the mapping ratio between the test environment and the production environment is determined as:
[0039] .
[0040] Furthermore, before performing the step of performing the EMC test on the industrial control power supply to be tested, the method further includes:
[0041] Get the topology diagram of the production environment. Maximum conducted interference signal strength of an environmental device ,in 1 to A positive integer between The number of environment devices in the topology diagram of the production environment;
[0042] Determine the first minimum transmission path for the conducted interference signal of the environmental equipment to be transmitted to the target equipment under the test environment ;
[0043] Get the first minimum transmission path The first path length And the first minimum transmission path The number of first branch nodes on ;
[0044] The maximum conducted interference signal strength , the first minimum transmission path The first path length And the number of first branch nodes Input into the pre-trained conduction signal attenuation model to calculate the The first attenuated signal strength when the conducted interference signal of the environmental equipment is transmitted to the target device .
[0045] Furthermore, the conduction signal attenuation model is a supervised learning model, in which the maximum conduction interference signal strength , the first minimum transmission path The first path length And the number of first branch nodes Input into the pre-trained conduction signal attenuation model to calculate the The first attenuated signal strength when the conducted interference signal of the environmental equipment is transmitted to the target device Before the steps, also include:
[0046] Collect the maximum conducted interference signal strength of various industrial electrical equipment;
[0047] Constructing a plurality of power topology connection structures with different path lengths and branch node numbers, wherein the path length is the path length of the minimum transmission path from the industrial power equipment to the attenuation signal measurement point in the power topology connection structure, and the branch node number is the number of branch nodes on the minimum transmission path;
[0048] Measuring the attenuated signal strength of the conducted interference signal of the industrial electrical equipment at the attenuated signal measurement point under the power topology connection structure;
[0049] The maximum conduction interference signal strength, the path length, and the number of branch nodes are used as input sample data, and the attenuation signal strength is used as output sample data to train the conduction signal attenuation model.
[0050] Furthermore, the steps of performing the EMC test of the industrial control power supply to be tested specifically include:
[0051] Calculate the interference signal strength transmitted from the power network to the target device:
[0052] ,
[0053] in Other conducted disturbances introduced into the power network;
[0054] The interference signal strength is generated by a second EMI signal generator which is arranged adjacent to the industrial control power supply to be tested and is electrically connected to the industrial control power supply to be tested. conducted interference signal.
[0055] Furthermore, the steps of performing the EMC test of the industrial control power supply to be tested specifically include:
[0056] Get the load range of the target device ;
[0057] The size of the simulated load is changed from Gradually adjust to ;
[0058] In the process of adjusting the size of the simulated load, the first EMS sensor connected to the power input end of the industrial control power supply to be tested detects the strength of the conducted interference signal emitted by the industrial control power supply to be tested via the power input source. .
[0059] Furthermore, the strength of the conducted interference signal emitted by the industrial control power supply to be tested through the power input source is detected by a first EMS sensor connected to the power input end of the industrial control power supply to be tested. After the steps, it also includes:
[0060] Determine that the conducted interference signal of the target device is transmitted to the The second shortest transmission path of the surrounding devices ;
[0061] Get the second minimum transmission path The second path length And the second minimum transmission path The number of second branch nodes on ;
[0062] The conducted interference signal strength The second minimum transmission path The second path length And the number of second branch nodes The input is used to calculate the transmission rate of the target device's conducted interference signal to the first Second attenuation signal strength when there are 100 ambient devices .
[0063] A second aspect of the present invention provides an electromagnetic compatibility test system for an industrial power supply, comprising a plurality of EMI signal generators, a plurality of EMS sensors, an automated layout device and a control device, wherein the automated layout device comprises a carrying unit for carrying the EMI signal generator or the EMS sensor, a positioning unit for obtaining the real-time position of the automated layout device, a first communication unit for communicating with the control device, a second communication unit for communicating with the carried EMI signal generator or EMS sensor, a mobile unit for moving the EMI signal generator or EMS sensor on the automated layout device to a designated position in a test environment, and a control unit, wherein the control unit is electrically connected to the positioning unit, the first communication unit, the second communication unit and the mobile unit, and is used to obtain the real-time position of the automated layout device through the positioning unit, report the real-time position to the control device through the first communication unit, and configure the EMI parameters of the EMI signal generator, configure the EMS parameters of the EMS sensor, or control the EMI signal generator or EMS sensor on the automated layout device to move to a designated position in the test environment according to a control instruction sent by the control device, and the control device is configured to perform the electromagnetic compatibility test method for the industrial power supply described in any one of the first aspects of the present invention.
[0064] The present invention proposes an electromagnetic compatibility test method and a test system for an industrial control power supply. By parsing the position parameters, topological connection parameters and EMC parameters of a target device and an environmental device from a topological structure diagram of a production environment, an EMI signal generator and / or an EMS sensor are arranged in the test environment according to the position mapping relationship between the production environment and the test environment and the position parameters, topological connection parameters and EMC parameters of the environmental device, an industrial control power supply to be tested is arranged in the test environment at a mapping position corresponding to the target device, a simulated power input signal and a simulated load are connected to the industrial control power supply to be tested, and an EMC test of the industrial control power supply to be tested is performed. The electromagnetic compatibility of the industrial control power supply can be evaluated more accurately, and a test result that is more suitable for practical applications can be provided, which is helpful to optimize the design and performance of the industrial control power supply and improve the reliability and stability of the industrial control power supply in a practical industrial environment. BRIEF DESCRIPTION OF THE DRAWINGS
[0065] Figure 1 It is a flow chart of an electromagnetic compatibility testing method for an industrial control power supply provided by an embodiment of the present invention;
[0066] Figure 2 It is a schematic diagram of an electromagnetic compatibility testing system for an industrial control power supply provided by an embodiment of the present invention. DETAILED DESCRIPTION
[0067] In order to more clearly understand the above-mentioned purpose, features and advantages of the present invention, the present invention is further described in detail below in conjunction with the accompanying drawings and specific embodiments. It should be noted that the embodiments of the present application and the features in the embodiments can be combined with each other without conflict.
[0068] In the following description, many specific details are set forth to facilitate a full understanding of the present invention. However, the present invention may also be implemented in other ways different from those described herein. Therefore, the protection scope of the present invention is not limited to the specific embodiments disclosed below.
[0069] In the description of the present invention, the term "multiple" refers to two or more. Unless otherwise clearly defined, the orientation or positional relationship indicated by the terms "upper", "lower", etc. is based on the orientation or positional relationship shown in the drawings. It is only for the convenience of describing the present invention and simplifying the description, and does not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation. Therefore, it cannot be understood as a limitation of the present invention. The terms "connection", "installation", "fixed", etc. should be understood in a broad sense. For example, "connection" can be a fixed connection, a detachable connection, or an integral connection; it can be directly connected or indirectly connected through an intermediate medium. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to the specific circumstances. In addition, the terms "first", "second", etc. are only used for descriptive purposes, and cannot be understood as indicating or implying relative importance or implicitly indicating the number of technical features indicated. Therefore, the features defined as "first", "second", etc. can explicitly or implicitly include one or more of the features. In the description of the present invention, unless otherwise specified, the meaning of "multiple" is two or more.
[0070] In the description of this specification, the description of the terms "one embodiment", "some implementations", "specific embodiments", etc. means that the specific features, structures, materials or characteristics described in conjunction with the embodiment or example are included in at least one embodiment or example of the present invention. In this specification, the schematic representation of the above terms does not necessarily refer to the same embodiment or example. Moreover, the specific features, structures, materials or characteristics described can be combined in any one or more embodiments or examples in a suitable manner.
[0071] An electromagnetic compatibility testing method and testing system for an industrial control power supply provided according to some embodiments of the present invention will be described below with reference to the accompanying drawings.
[0072] like Figure 1 As shown, the first aspect of the present invention provides an electromagnetic compatibility test method for an industrial control power supply, comprising:
[0073] Importing at least one topological structure diagram of a production environment, wherein the topological structure diagram of the production environment is a topological structure diagram constructed based on a real production environment and used to describe the arrangement of industrial field devices in the production environment;
[0074] Parsing location parameters, topological connection parameters and EMC parameters of target devices and environment devices from the topological structure diagram of the production environment, wherein the EMC parameters include EMI parameters and EMS parameters;
[0075] Acquire indoor structural parameters of the test environment, wherein the indoor structural parameters of the test environment include indoor plane size parameters or indoor three-dimensional size parameters of the test environment;
[0076] Establishing a location mapping relationship between the production environment and the test environment;
[0077] Arranging an EMI signal generator for performing an EMS test on an industrial control power supply and / or an EMS sensor for performing an EMI test on an industrial control power supply in the test environment according to the position mapping relationship and the position parameters, topology connection parameters and EMC parameters of the environmental equipment, wherein the EMI signal generator is used to generate an EMI signal that matches the EMI parameters of the environmental equipment at the corresponding position, and the EMS parameters of the EMS sensor match the EMS parameters of the environmental equipment at the corresponding position;
[0078] Arranging the industrial control power supply to be tested in the test environment corresponding to the mapping position of the target device;
[0079] Connecting a simulated power input signal and a simulated load to the industrial control power supply to be tested, wherein the simulated power input signal matches the power signal connected to the target device in the production environment, and the simulated load matches the load state of the target device in the production environment;
[0080] Perform EMC testing on the industrial control power supply to be tested.
[0081] The production environment topology structure diagram is an electric power topology diagram of the industrial field environment, which is used to describe the electric power connection relationship of the industrial field equipment in the industrial field environment. The industrial field equipment includes various industrial electrical equipment arranged in the industrial field environment, especially high-power industrial electrical equipment or industrial electrical equipment with high electromagnetic sensitivity.
[0082] The target device is a field industrial device installed with an industrial control power supply to be tested, and the environmental device is other industrial field devices arranged in the same industrial field environment as the target device.
[0083] The location parameters are used to describe the on-site industrial equipment, including the location coordinates of the target equipment and the environmental equipment in the industrial field environment. The topology connection parameters are used to describe the power connection relationship between the on-site industrial equipment and the adjacent on-site industrial equipment in the industrial field environment. The EMC parameters include EMI parameters and EMS parameters. The EMI parameters are used to describe the electromagnetic interference characteristics of the on-site industrial equipment. The electromagnetic interference includes conducted interference and radiated interference. Similarly, the EMI signal includes conducted signals and radiated signals. The EMS parameters are used to describe the electromagnetic susceptibility of the on-site industrial equipment. Similarly, the electromagnetic susceptibility also includes sensitivity to conducted interference and sensitivity to radiated interference.
[0084] Before the step of obtaining the indoor structural parameters of the test environment, it also includes importing the indoor plan structure diagram or indoor three-dimensional structure diagram of the test environment, extracting the indoor plan size parameters of the test environment from the indoor plan structure diagram, or extracting the indoor three-dimensional size parameters of the test environment from the indoor three-dimensional structure diagram.
[0085] Depending on the type of the target device, the simulated load can be a static load or a dynamic load. That is, when the load size of the target device remains unchanged in the working state, the simulated load is a static load. When the load size of the target device changes dynamically in the working state, the simulated load is a dynamic load.
[0086] In the technical solutions of some embodiments of the present invention, the step of arranging an EMI signal generator for performing EMS testing on an industrial control power supply and / or an EMS sensor for performing EMI testing on an industrial control power supply in the test environment according to the position mapping relationship and the position parameters, topological connection parameters and EMC parameters of the environmental equipment includes arranging the power connection relationship between the industrial control power supply to be tested and the EMI signal generator according to the topological structure diagram of the production environment, and the conducted interference signal generated by the EMI signal generator is conducted to the industrial control power supply to be tested through the arranged power lines.
[0087] In the technical solutions of other embodiments of the present invention, the EMI signal generator includes a first EMI signal generator for generating a radiated interference signal and a second EMI signal generator for generating a conducted interference signal. In the step of arranging the EMI signal generator for performing EMS testing on the industrial control power supply and / or the EMS sensor for performing EMI testing on the industrial control power supply in the test environment according to the position mapping relationship and the position parameters, topological connection parameters and EMC parameters of the environmental equipment, the first EMI signal generator is arranged at the mapping position of the corresponding environmental equipment, and the second EMI signal generator is arranged at a position adjacent to the industrial control power supply to be tested so as to be electrically connected to the industrial control power supply to be tested. Preferably, the second EMI signal generator is also used to generate conducted interference signals generated by other factors besides the environmental equipment, such as conducted interference signals from an external power network and conducted interference signals generated in the power network due to reasons such as lightning.
[0088] Furthermore, before the step of importing at least one topology diagram of the production environment, the method further includes:
[0089] Build a topology graph database for the production environment;
[0090] Configuring a topology diagram of a production environment corresponding to each application field in the topology diagram database;
[0091] The steps of importing at least one topology diagram of the production environment include:
[0092] Determine the target device type corresponding to the industrial control power supply to be tested;
[0093] Determine the application field corresponding to the industrial control power supply to be tested according to the target device type;
[0094] At least one topology diagram of the production environment of the application field is read from the topology diagram database.
[0095] Since industrial control power supplies have the characteristics of high reliability and durability, they can be used in various harsh and complex environments. Therefore, they are widely used in various fields such as industrial automation, communications, medical treatment, data centers, and new energy. Different application fields usually have different electromagnetic environments. In some application scenarios, such as industrial automation applications, the environmental equipment will produce strong electromagnetic interference, which will have a certain impact on the operation of the industrial control power supply. In some application scenarios, the environmental equipment has a high sensitivity to electromagnetic interference and has high requirements for the electromagnetic interference intensity of the industrial control power supply. Specifically, in the step of configuring the topological structure diagram of the production environment corresponding to each application field in the topological structure diagram database, a large number of topological structure diagrams of different production environments are configured for each to meet the testing requirements of the industrial control power supply.
[0096] The target device type corresponding to the industrial control power supply to be tested refers to the type of target device installed by the industrial control power supply to be tested, and the target device referred to here refers to the device actually installed and used in the application scenario of the industrial control power supply to be tested after leaving the factory. In the technical scheme of some embodiments of the present invention, when the industrial control power supply to be tested is an industrial control power supply or its target device type is not specified / entered, a plurality of topological structure diagrams of production environments in different application fields are randomly extracted from the topological structure diagram database to perform electromagnetic compatibility testing on the industrial control power supply to be tested.
[0097] In the technical solutions of some embodiments of the present invention, after the step of configuring the topology structure diagram of the production environment corresponding to each application field in the topology structure diagram database, it also includes configuring the conducted interference score, the radiated interference score, the conducted sensitivity score and the radiated sensitivity score of the topology structure diagram of each production environment. The step of reading at least one topology structure diagram of the production environment of the application field from the topology structure diagram database specifically includes selecting the topology structure diagrams whose conducted interference score, the radiated interference score, the conducted sensitivity score and the radiated sensitivity score are distributed in different score intervals to ensure the reliability of the test results.
[0098] Furthermore, the step of establishing a location mapping relationship between the production environment and the test environment specifically includes:
[0099] Parsing indoor structural parameters of the production environment from the topological structure diagram of the production environment, wherein the indoor structural parameters of the production environment include indoor plane size parameters or indoor three-dimensional size parameters of the production environment;
[0100] comparing indoor structural parameters of the test environment with indoor structural parameters of the production environment;
[0101] When any indoor dimension of the length, width, and height of the test environment is smaller than the corresponding indoor dimension of the production environment, calculating a mapping ratio between the test environment and the production environment;
[0102] Establishing a location mapping relationship between the production environment and the test environment according to the mapping ratio;
[0103] The EMC parameters of the environmental equipment are corrected according to the mapping ratio.
[0104] Preferably, the indoor space of the test environment is a cubic space or a rectangular parallelepiped space, that is, among the edge lines of the indoor plan view or indoor stereo view of the test environment, adjacent edge lines are orthogonal to each other.
[0105] After the step of comparing the indoor structural parameters of the test environment with the indoor structural parameters of the production environment, the method further includes:
[0106] When any indoor dimension of the length, width, and height of the test environment is larger than the corresponding indoor dimension of the production environment, constructing a virtual fence in the test environment;
[0107] A mapping coordinate system is constructed with the virtual wall as a boundary.
[0108] In the technical solution of this implementation, since the indoor dimensions within the virtual fence are exactly the same as the indoor dimensions of the production environment, there is a one-to-one mapping relationship between the mapping coordinate system and the original coordinate system of the production environment, that is, the coordinate values of the target device and the environmental device in the original coordinate system of the production environment can be directly used as their mapping coordinate values in the mapping coordinate system.
[0109] Furthermore, the indoor structural parameters of the production environment and the test environment are indoor plane size parameters, and the step of calculating the mapping ratio of the test environment to the production environment specifically includes:
[0110] Generate a first indoor plan view of the production environment and a second indoor plan view of the test environment based on indoor plan size parameters of the production environment and the test environment;
[0111] Determine a first center point position of the production environment on the first indoor plan and determine a second center point position of the test environment on the second indoor plan;
[0112] An original coordinate system of the production environment is constructed with the first center point as the origin, with the length of the first indoor plan view as the horizontal axis of the original coordinate system, and the width of the first indoor plan view as the vertical axis of the original coordinate system;
[0113] Constructing a mapping coordinate system of the test environment with the second center point as the origin, with the length of the second indoor plan view as the horizontal axis of the mapping coordinate system, and the width of the second indoor plan view as the vertical axis of the mapping coordinate system;
[0114] Determine the first maximum horizontal axis coordinate value on the first indoor plan and the first maximum vertical axis coordinate value , and the second maximum horizontal axis coordinate value on the second indoor plan and the second maximum vertical axis coordinate value ;
[0115] Calculate the length dimension difference between the first indoor plan and the second indoor plan:
[0116] ;
[0117] Calculate the width dimension difference between the first indoor plan and the second indoor plan:
[0118] ;
[0119] when When the mapping ratio between the test environment and the production environment is determined as:
[0120] ;
[0121] when When the mapping ratio between the test environment and the production environment is determined as:
[0122] .
[0123] In the technical solution of the above implementation mode, the step of establishing the position mapping relationship between the production environment and the test environment according to the mapping ratio specifically includes:
[0124] Get the original location coordinates of the production environment , the original position coordinates may be the coordinates of the target device in the production environment or any environment device in the original coordinate system;
[0125] Calculate the coordinates of the original position in the mapping coordinate system based on the mapping ratio The corresponding mapping coordinates are:
[0126] .
[0127] Similarly, the step of correcting the EMC parameters of the environmental equipment according to the mapping ratio specifically includes:
[0128] Obtain the radiation interference parameters in the EMC parameters of the environmental equipment , the radiation interference parameter Including the radiation interference signal strength of the environmental equipment and the sensitivity to radiation interference;
[0129] Correct the radiation interference parameter of the environmental equipment based on the mapping ratio:
[0130] .
[0131] Since the conducted interference parameters in the EMC parameters are related to the conduction path of the conducted interference signal, and the power connection relationship of each industrial electrical equipment in the topological structure diagram of the production environment is usually complex, and the conducted interference signal will be affected by many attenuation factors during the transmission process of the power network, the conduction path of the conducted interference signal cannot be directly corrected by the mapping ratio, and the conducted signal strength in the second EMI signal generator needs to be calculated and corrected according to the specific conduction path length.
[0132] Furthermore, before performing the step of performing the EMC test on the industrial control power supply to be tested, the method further includes:
[0133] Get the topology diagram of the production environment. Maximum conducted interference signal strength of an environmental device ,in 1 to A positive integer between The number of environment devices in the topology diagram of the production environment;
[0134] Determine the first minimum transmission path for the conducted interference signal of the environmental equipment to be transmitted to the target equipment under the test environment ;
[0135] Get the first minimum transmission path The first path length And the first minimum transmission path The number of first branch nodes on ;
[0136] The maximum conducted interference signal strength , the first minimum transmission path The first path length And the number of first branch nodes Input into the pre-trained conduction signal attenuation model to calculate the The first attenuated signal strength when the conducted interference signal of the environmental equipment is transmitted to the target device .
[0137] The strength of the conducted interference signal emitted by each different industrial electrical equipment to the power network is often different. In the technical solution of the present invention, the range of the strength of the conducted interference signal emitted by different user equipment to the power network can be obtained through laboratory measurement. The maximum conducted interference signal strength It is the first in the topology diagram of the production environment. The maximum value of the range of conducted interference signal strength emitted by an environmental device to the power network.
[0138] The first minimum transmission path After the topological structure diagram of the production environment is mapped to the test environment, the electrical signal in the power network is The shortest transmission path from the environment device to the target device. Since the power network is usually a multi-branch structure, the first minimum transmission path The number of first branch nodes on The first minimum transmission path The number of nodes connecting other branch lines from the environment device to the target device.
[0139] Furthermore, the conduction signal attenuation model is a supervised learning model, in which the maximum conduction interference signal strength , the first minimum transmission path The first path length And the number of first branch nodes Input into the pre-trained conduction signal attenuation model to calculate the The first attenuated signal strength when the conducted interference signal of the environmental equipment is transmitted to the target device Before the steps, also include:
[0140] Collect the maximum conducted interference signal strength of various industrial electrical equipment;
[0141] Constructing a plurality of power topology connection structures with different path lengths and branch node numbers, wherein the path length is the path length of the minimum transmission path from the industrial power equipment to the attenuation signal measurement point in the power topology connection structure, and the branch node number is the number of branch nodes on the minimum transmission path;
[0142] Measuring the attenuated signal strength of the conducted interference signal of the industrial electrical equipment at the attenuated signal measurement point under the power topology connection structure;
[0143] The maximum conduction interference signal strength, the path length, and the number of branch nodes are used as input sample data, and the attenuation signal strength is used as output sample data to train the conduction signal attenuation model.
[0144] Specifically, the conduction signal attenuation model can be any one of a CNN (Convolutional Neural Network) model, an RNN (Recurrent Neural Network) model or an LTSM (Long Short-Term Memory) model.
[0145] Calculate the interference signal strength transmitted from the power network to the target device:
[0146] ,
[0147] in Other conducted disturbances introduced into the power network;
[0148] The interference signal strength is generated by a second EMI signal generator which is arranged adjacent to the industrial control power supply to be tested and is electrically connected to the industrial control power supply to be tested. conducted interference signal.
[0149] Specifically, the conducted interference generated by the environmental equipment is usually caused by transient impacts such as switching operations, start-stop operations, etc. In the power network, in addition to the conducted interference generated by the environmental equipment, there are other conducted interferences, such as voltage fluctuations in the power network caused by lightning strikes, short circuits, or other reasons.
[0150] Before performing the step of performing the EMC test on the industrial control power supply to be tested, the method further includes:
[0151] Get the topology diagram of the production environment. Maximum radiated interference signal strength of an environmental device ;
[0152] Calculate the radiation interference intensity received at the target device:
[0153] .
[0154] Likewise, Other radiation interference from the production environment. and is an empirical value, which can be configured as a corresponding value for different production environments as needed. Since electromagnetic radiation propagates in the air at a speed close to the speed of light, the change in its radiation intensity within the test environment scale can be ignored. Therefore, in the technical solution of the above implementation, the maximum radiation interference signal intensity of the environmental equipment is directly used. To calculate the radiation interference intensity received at the target device.
[0155] Furthermore, the steps of performing the EMC test of the industrial control power supply to be tested specifically include:
[0156] Get the load range of the target device ;
[0157] The size of the simulated load is changed from Gradually adjust to ;
[0158] In the process of adjusting the size of the simulated load, the first EMS sensor connected to the power input end of the industrial control power supply to be tested detects the strength of the conducted interference signal emitted by the industrial control power supply to be tested via the power input source. .
[0159] Further, when the size of the simulated load is changed from Gradually adjust to After the steps, it also includes:
[0160] In the process of adjusting the size of the simulated load, the intensity of the radiated interference signal emitted by the industrial control power supply to be tested is detected by a second EMS sensor arranged at a mapping position corresponding to the environmental equipment in the test environment.
[0161] Furthermore, the strength of the conducted interference signal emitted by the industrial control power supply to be tested through the power input source is detected by a first EMS sensor connected to the power input end of the industrial control power supply to be tested. After the steps, it also includes:
[0162] Determine that the conducted interference signal of the target device is transmitted to the The second shortest transmission path of the surrounding devices ;
[0163] Get the second minimum transmission path The second path length And the second minimum transmission path The number of second branch nodes on ;
[0164] The conducted interference signal strength The second minimum transmission path The second path length And the number of second branch nodes The input is used to calculate the transmission rate of the target device's conducted interference signal to the first Second attenuation signal strength when there are 100 ambient devices .
[0165] Similarly, the second minimum transmission path After the topological structure diagram of the production environment is mapped to the test environment, the electrical signal in the power network is transmitted from the target device to the The shortest transmission path for each environment device. Since the power network is usually a multi-branch structure, the second shortest transmission path The number of second branch nodes on The second minimum transmission path The number of nodes connecting other branch lines from the environment device to the target device.
[0166] like Figure 2 As shown, the second aspect of the present invention proposes an electromagnetic compatibility test system for an industrial power supply, comprising a plurality of EMI signal generators, a plurality of EMS sensors, an automated arrangement device and a control device, wherein the automated arrangement device comprises a carrying unit for carrying the EMI signal generator or the EMS sensor, a positioning unit for obtaining the real-time position of the automated arrangement device, a first communication unit for communicating with the control device, a second communication unit for communicating with the carried EMI signal generator or EMS sensor, and a moving unit for moving the EMI signal generator or EMS sensor on the automated arrangement device to a designated position in a test environment. The control unit comprises a positioning unit, a first communication unit, a second communication unit and a mobile unit, wherein the control unit is electrically connected to the positioning unit, the first communication unit, the second communication unit and the mobile unit, and is used to obtain the real-time position of the automated layout device through the positioning unit, report the real-time position to the control device through the first communication unit, and configure the EMI parameters of the EMI signal generator, configure the EMS parameters of the EMS sensor, or control the EMI signal generator or the EMS sensor on the automated layout device to move to a specified position in a test environment according to a control instruction sent by the control device. The control device is configured to execute the electromagnetic compatibility test method for an industrial control power supply as described in any one of the first aspects of the present invention.
[0167] Specifically, the carrying unit may be a carrying platform, a carrying cavity or a fixing fixture on the automated layout device, and the carrying unit may have a communication interface electrically connected to the second communication unit that matches the EMI signal generator or the EMS sensor; when the EMI signal generator or the EMS sensor is placed on the carrying unit, a communication connection is established with the control unit through the second communication unit connected to the communication interface.
[0168] The positioning unit is an indoor positioning unit, which can be an indoor positioning unit using any indoor positioning technology such as Bluetooth, infrared, RFID, ultrasonic or visual positioning, and is used to obtain the position of the EMI signal generator or EMS sensor on the automatic layout device in the indoor space of the test environment in real time.
[0169] The first communication unit and the second communication unit can be wired communication units or wireless communication units. Preferably, the second communication unit is a contact wired communication unit, that is, the communication interface for connecting the EMI signal generator or the EMS sensor with the second communication unit is a contact wired communication interface, and when the EMI signal generator or the EMS sensor is placed on the carrier unit, a communication connection is established directly with the control unit through the contact wired communication interface.
[0170] The mobile unit includes a mobile mechanism and a driving mechanism, and the driving mechanism drives the mobile mechanism to move so that the automated layout device moves in the indoor space of the test environment. The driving mechanism can be a mechanical device such as a driving motor. In the technical solutions of some embodiments of the present invention, the mobile mechanism includes a plurality of driving wheels, and the control unit controls the driving motor to drive the driving wheels to rotate at a speed and a direction to control the automated layout device to move in the indoor space of the test environment. In the technical solutions of other embodiments of the present invention, a sliding track is arranged in the indoor space of the test environment, and the mobile mechanism is a track pulley. The control unit controls the driving motor to drive the track pulley to slide on the sliding track to control the automated layout device to move in the indoor space of the test environment.
[0171] The step of arranging an EMI signal generator for performing EMS testing on an industrial control power supply and / or an EMS sensor for performing EMI testing on an industrial control power supply in the test environment according to the position mapping relationship and the position parameters, topology connection parameters and EMC parameters of the environmental equipment is specifically to arrange the EMI signal generator and the EMS sensor to the mapping position corresponding to the environmental equipment using an automated arrangement device corresponding to the number of the EMI signal generators and the EMS sensors.
[0172] Further, the EMI signal generator includes a first EMI signal generator for generating a radiated interference signal and a second EMI signal generator for generating a conducted interference signal, and the automated arrangement device arranges the first EMI signal generator at a mapping position of the corresponding environmental equipment, and arranges the second EMI signal generator at a position adjacent to the industrial control power supply to be tested so as to be electrically connected to the industrial control power supply to be tested. Preferably, the second EMI signal generator is also used to generate conducted interference signals generated by factors other than the environmental equipment, such as conducted interference signals from an external power network and conducted interference signals generated in the power network due to reasons such as lightning.
[0173] It should be noted that, in this article, relational terms such as first and second, etc. are only used to distinguish one entity or operation from another entity or operation, and do not necessarily require or imply any such actual relationship or order between these entities or operations. Moreover, the terms "include", "comprise" or any other variants thereof are intended to cover non-exclusive inclusion, so that a process, method, article or device including a series of elements includes not only those elements, but also other elements not explicitly listed, or also includes elements inherent to such process, method, article or device. In the absence of further restrictions, the elements defined by the statement "comprise a ..." do not exclude the presence of other identical elements in the process, method, article or device including the elements.
[0174] According to the embodiments of the present invention as described above, these embodiments do not describe all the details in detail, nor do they limit the invention to the specific embodiments described. Obviously, many modifications and changes can be made based on the above description. This specification selects and specifically describes these embodiments in order to better explain the principles and practical applications of the present invention, so that those skilled in the art can make good use of the present invention and the modified use based on the present invention. The present invention is limited only by the claims and their full scope and equivalents.
Claims
1. A method for testing electromagnetic compatibility of an industrial power supply, characterized in that: include: Importing at least one topological structure diagram of a production environment, wherein the topological structure diagram of the production environment is a topological structure diagram constructed based on a real production environment and used to describe the arrangement of industrial field devices in the production environment; Parsing location parameters, topological connection parameters and EMC parameters of target devices and environment devices from the topological structure diagram of the production environment, wherein the EMC parameters include EMI parameters and EMS parameters; Acquire indoor structural parameters of the test environment, wherein the indoor structural parameters of the test environment include indoor plane size parameters or indoor three-dimensional size parameters of the test environment; Establishing a location mapping relationship between the production environment and the test environment; An EMI signal generator for performing an EMS test on an industrial control power supply and an EMS sensor for performing an EMI test on an industrial control power supply are arranged in the test environment according to the position mapping relationship and the position parameters, topology connection parameters and EMC parameters of the environmental equipment, wherein the EMI signal generator is used to generate an EMI signal that matches the EMI parameters of the environmental equipment at the corresponding position, and the EMS parameters of the EMS sensor match the EMS parameters of the environmental equipment at the corresponding position; Arranging the industrial control power supply to be tested in the test environment corresponding to the mapping position of the target device; Connecting a simulated power input signal and a simulated load to the industrial control power supply to be tested, wherein the simulated power input signal matches the power signal connected to the target device in the production environment, and the simulated load matches the load state of the target device in the production environment; Perform EMC testing on the industrial control power supply to be tested.
2. The electromagnetic compatibility testing method of industrial power supply according to claim 1, characterized in that: Before the step of importing at least one topology diagram of the production environment, the following steps are also included: Build a topology graph database for the production environment; Configuring a topology diagram of a production environment corresponding to each application field in the topology diagram database; The steps of importing at least one topology diagram of the production environment include: Determine the target device type corresponding to the industrial control power supply to be tested; Determine the application field corresponding to the industrial control power supply to be tested according to the target device type; At least one topology diagram of the production environment of the application field is read from the topology diagram database.
3. The electromagnetic compatibility testing method of industrial power supply according to claim 2, characterized in that: The step of establishing a location mapping relationship between the production environment and the test environment specifically includes: Parsing indoor structural parameters of the production environment from the topological structure diagram of the production environment, wherein the indoor structural parameters of the production environment include indoor plane size parameters or indoor three-dimensional size parameters of the production environment; comparing indoor structural parameters of the test environment with indoor structural parameters of the production environment; When any indoor dimension of the length, width, and height of the test environment is smaller than the corresponding indoor dimension of the production environment, calculating a mapping ratio between the test environment and the production environment; Establishing a location mapping relationship between the production environment and the test environment according to the mapping ratio; The EMC parameters of the environmental equipment are corrected according to the mapping ratio.
4. The electromagnetic compatibility testing method of industrial power supply according to claim 3, characterized in that: The indoor structural parameters of the production environment and the test environment are indoor plane size parameters, and the step of calculating the mapping ratio of the test environment to the production environment specifically includes: Generate a first indoor plan view of the production environment and a second indoor plan view of the test environment based on indoor plan size parameters of the production environment and the test environment; Determine a first center point position of the production environment on the first indoor plan and determine a second center point position of the test environment on the second indoor plan; Constructing an original coordinate system of the production environment with the first center point as the origin, with the length direction of the first indoor plan view as the horizontal axis direction of the original coordinate system, and with the width direction of the first indoor plan view as the vertical axis direction of the original coordinate system; Constructing a mapping coordinate system of the test environment with the second center point as the origin, with the length direction of the second indoor plan view as the horizontal axis direction of the mapping coordinate system, and with the width direction of the second indoor plan view as the vertical axis direction of the mapping coordinate system; Determine the first maximum horizontal axis coordinate value on the first indoor plan respectively and the first maximum vertical axis coordinate value , and the second maximum horizontal axis coordinate value on the second indoor plan and the second maximum vertical axis coordinate value ; Calculate the length dimension difference between the first indoor plan and the second indoor plan: ; Calculate the width dimension difference between the first indoor plan and the second indoor plan: ; when When the mapping ratio between the test environment and the production environment is determined as: ; when When the mapping ratio between the test environment and the production environment is determined as: 。 5. The electromagnetic compatibility testing method of industrial power supply according to claim 1, characterized in that: Before performing the step of performing the EMC test on the industrial control power supply to be tested, the method further includes: Obtain the topology structure diagram of the test environment corresponding to the production environment. Maximum conducted interference signal strength of an environmental device ,in 1 to A positive integer between The number of environment devices in the topology diagram of the production environment; Determine the first minimum transmission path for the conducted interference signal of the environmental equipment to be transmitted to the target equipment under the test environment ; Get the first minimum transmission path The first path length And the first minimum transmission path The number of first branch nodes on ; The maximum conducted interference signal strength , the first minimum transmission path The first path length And the number of first branch nodes Input into the pre-trained conduction signal attenuation model to calculate the The first attenuated signal strength when the conducted interference signal of the environmental equipment is transmitted to the target device .
6. The electromagnetic compatibility testing method of industrial power supply according to claim 5, characterized in that: The conduction signal attenuation model is a supervised learning model. , the first minimum transmission path The first path length And the number of first branch nodes Input into the pre-trained conduction signal attenuation model to calculate the The first attenuated signal strength when the conducted interference signal of the environmental equipment is transmitted to the target device Before the steps, also include: Collect the maximum conducted interference signal strength of various industrial electrical equipment; Constructing a plurality of power topology connection structures with different path lengths and branch node numbers, wherein the path length is the path length of the minimum transmission path from the industrial power equipment to the attenuation signal measurement point in the power topology connection structure, and the branch node number is the number of branch nodes on the minimum transmission path; Measuring the attenuated signal strength of the conducted interference signal of the industrial electrical equipment at the attenuated signal measurement point under the power topology connection structure; The maximum conduction interference signal strength, the path length, and the number of branch nodes are used as input sample data, and the attenuation signal strength is used as output sample data to train the conduction signal attenuation model.
7. The electromagnetic compatibility testing method of industrial power supply according to claim 5, characterized in that: The EMI signal generator includes a first EMI signal generator for generating a radiated interference signal and a second EMI signal generator for generating a conducted interference signal. The steps of performing the EMC test of the industrial control power supply to be tested specifically include: Calculate the interference signal strength transmitted from the power network to the target device: , in Other conducted disturbances introduced into the power network; The interference signal strength is generated by a second EMI signal generator which is arranged adjacent to the industrial control power supply to be tested and is electrically connected to the industrial control power supply to be tested. conducted interference signal.
8. The electromagnetic compatibility testing method of industrial power supply according to claim 5, characterized in that: The EMS sensor includes a first EMS sensor for detecting the strength of a conducted interference signal emitted by the industrial control power supply to be tested via the power input source and a second EMS sensor for detecting the strength of a radiated interference signal emitted by the industrial control power supply to be tested. The steps of performing an EMC test on the industrial control power supply to be tested specifically include: Get the load range of the target device ; The size of the simulated load is changed from Gradually adjust to ; In the process of adjusting the size of the simulated load, the first EMS sensor connected to the power input end of the industrial control power supply to be tested detects the strength of the conducted interference signal emitted by the industrial control power supply to be tested via the power input source. .
9. The electromagnetic compatibility testing method of industrial power supply according to claim 8, characterized in that: The strength of the conducted interference signal emitted by the industrial control power supply to be tested through the power input source is detected by a first EMS sensor connected to the power input end of the industrial control power supply to be tested. After the steps, it also includes: Determine that the conducted interference signal of the target device is transmitted to the The second shortest transmission path of the surrounding devices ; Get the second minimum transmission path The second path length And the second minimum transmission path The number of second branch nodes on ; The conducted interference signal strength The second minimum transmission path The second path length And the number of second branch nodes The input is used to calculate the transmission rate of the target device's conducted interference signal to the first Second attenuation signal strength when there are 100 ambient devices .
10. An electromagnetic compatibility test system for industrial power supply, characterized in that: The invention comprises a plurality of EMI signal generators, a plurality of EMS sensors, an automated layout device and a control device, wherein the automated layout device comprises a carrying unit for carrying the EMI signal generator or the EMS sensor, a positioning unit for obtaining the real-time position of the automated layout device, a first communication unit for communicating with the control device, a second communication unit for communicating with the carried EMI signal generator or EMS sensor, a moving unit for moving the EMI signal generator or EMS sensor on the automated layout device to a designated position in a test environment, and a control unit, wherein the control unit is electrically connected to the positioning unit, the first communication unit, the second communication unit and the moving unit, and is used to obtain the real-time position of the automated layout device through the positioning unit, report the real-time position to the control device through the first communication unit, and configure the EMI parameters of the EMI signal generator, configure the EMS parameters of the EMS sensor, or control the EMI signal generator or EMS sensor on the automated layout device to move to a designated position in the test environment according to the control instruction sent by the control device, and the control device is configured to execute the electromagnetic compatibility test method for an industrial power supply according to any one of claims 1 to 9.
Citation Information
Patent Citations
Transmission shielding cable electromagnetic interference spatial distribution dynamic coupling test system and method
CN118033246A
Engine virtual test environment system and engine management system mapping method
US20200064229A1
EMC test system and EMC test method using lifi
US20210165031A1
Mobile terminal and device for improving EMC of a display screen thereof
WO2016173500A1