Optimization method for improving available flexibility of power system considering electricity-carbon coupling constraints
By establishing the system's total carbon energy consumption and green certificate constraint model, and combining the correlation between carbon energy consumption and thermal power unit energy consumption, the flexibility of the power system is optimized, solving the problem of high flexibility in the existing technology that it is difficult to reduce carbon emissions, and achieving flexible Improvement of sex and environmental protection.
Patent Information
- Application Number
- CN202410996044.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-24
- Publication Date
- 2024-10-29
- Estimated Expiration
- 2044-07-24
AI Technical Summary
The existing power system that takes into account the electricity-carbon coupling constraints is difficult to effectively reduce carbon emissions when achieving high flexibility, and the system scheduling is difficult, and carbon emissions cannot be effectively controlled, mainly due to the lack of comprehensive consideration of carbon energy consumption and green certificate constraints, as well as the lack of thermal power The operating flexibility of the unit is insufficient and the volatility of new energy sources is high.
By establishing a system total carbon energy consumption model and a green certificate constraint model, and combining the relationship between carbon energy consumption and thermal power unit energy consumption, an optimization model for improving available flexibility is established to limit carbon dioxide emissions and maximize system availability during the optimization process. Flexibility to ensure carbon energy consumption and green certificate constraints are met.
It improves the flexibility and environmental protection of the system, reduces carbon emissions, ensures the consumption of new energy, and improves the flexibility and availability of system scheduling.
Smart Images

Figure CN118539435B_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the field of renewable energy power generation access to electric power technology, and in particular to an optimization method for improving the available flexibility of an electric power system taking into account electricity-carbon coupling constraints. Background Art
[0002] The optimization method for improving the available flexibility of the power system taking into account the electricity-carbon coupling constraints aims to maximize the available flexibility of the system and reduce carbon emissions. By establishing a carbon energy consumption constraint model and a green certificate constraint model, it optimizes the combined operation of thermal power units and new energy units to achieve the goal of improving system flexibility and environmental protection.
[0003] The existing available flexibility technology for power systems taking into account the constraints of electricity-carbon coupling has a trade-off problem between flexibility and environmental protection. In addition, due to the lack of comprehensive consideration of carbon energy consumption and green certificate constraints, as well as the insufficient operating flexibility of thermal power units and the high volatility of new energy, it will be difficult for the system to effectively reduce carbon emissions while achieving high flexibility, and the system will be difficult to dispatch and carbon emissions cannot be effectively controlled. Therefore, an optimization method for improving the available flexibility of power systems taking into account the constraints of electricity-carbon coupling is provided. Summary of the invention
[0004] The purpose of the present invention is to provide an optimization method for improving the available flexibility of an electric power system taking into account the constraints of electricity-carbon coupling, so as to solve the problems raised in the above background technology that the lack of comprehensive consideration of carbon energy consumption and green certificate constraints, the insufficient operating flexibility of thermal power units and the high volatility of new energy will make it difficult for the system to effectively reduce carbon emissions while achieving high flexibility, as well as the system scheduling difficulties and the inability to effectively control carbon emissions.
[0005] To achieve the above object, the present invention aims to provide an optimization method for improving the available flexibility of a power system taking into account the electric-carbon coupling constraint, comprising the following steps:
[0006] S1. Use the system total carbon energy consumption model and associate the carbon energy consumption with the energy consumption of thermal power units to establish a carbon energy consumption constraint model;
[0007] S2. Calculate the total demand for green certificates according to the green certificate ratio constraint model, and calculate the total supply of green certificates according to the green certificate total quantity calculation model, and establish a green certificate constraint model in combination with the total demand for green certificates and the total supply of green certificates;
[0008] S3. Establish an optimization model for improving the available flexibility of the power system taking into account the constraints of electricity-carbon coupling, with the goal of maximizing the available flexibility of the system and limiting the emission of carbon dioxide during the optimization process;
[0009] S4. Add the green certificate constraint and carbon energy consumption constraint to the available flexibility optimization model of the power system, and solve the unit combination scheme with the maximum available flexibility of the system. As a further improvement of this technical solution, the mathematical model formula involved in the total carbon energy consumption model of the system in S1 is as follows:
[0010]
[0011] in, E represents the carbon energy consumption of the system; n Indicates the unit serial number; N g Indicates the number of units; t Indicates the current moment; T Represents the optimization cycle; a 2 , b 2 , c 2 For each unit n The carbon energy consumption coefficient, P n ( t ) indicates the unit n exist t Active power output at any time.
[0012] As a further improvement of the technical solution, in S1, the carbon energy consumption is associated with the energy consumption of the thermal power unit to establish a carbon energy consumption constraint model for the process of improving available flexibility. The specific steps involved are as follows:
[0013] S1.1. Set an upper limit on total carbon energy consumption: ;
[0014] S1.2 Comprehensively consider the energy consumption of thermal power units in the system , set comprehensive carbon energy consumption limits:
[0015]
[0016] S1.3. Detailed calculation of energy consumption of thermal power units , used to ensure that the energy consumption calculation in the carbon energy consumption constraint model is based on the unit output power and energy consumption coefficient:
[0017]
[0018] The specific mathematical model formula of the carbon energy consumption constraint model is as follows:
[0019]
[0020] in, E 1It represents the carbon energy consumption obtained by the system at the next level; E 0 Indicates the system carbon energy consumption target value; E g1 Indicates the energy consumption of thermal power units in the system; Indicates the obtained carbon energy consumption coupling coefficient; Indicates the coupling coefficient for obtaining green certificate; C b Indicates the number of green certificates obtained; Indicates the floating coefficient; E g0 Indicates the system energy consumption target value.
[0021] As a further improvement of the technical solution, the mathematical model formula involved in the green certificate ratio constraint model in S2 is as follows:
[0022]
[0023] in, Indicates the green certificate ratio coefficient; C Indicates the total amount of green certificates; h Indicates the running time period; Indicates the unit At the moment The output active power of is the total number of time periods; is the number of traditional energy units.
[0024] As a further improvement of the technical solution, the mathematical model formula involved in the green certificate total amount calculation model in S2 is as follows:
[0025]
[0026] in, r Indicates the serial number of the new energy unit; N r Indicates the number of new energy units; C r ( t ) indicates new energy units r exist t Green certificates generated at all times; is the total number of time periods; h Indicates the running time period; The number of green certificates already in the system.
[0027] As a further improvement of the technical solution, the green certificate constraint model for the available flexibility improvement process is established in S2 in combination with the total demand for green certificates and the total supply of green certificates. The specific steps involved are as follows:
[0028] S2.1. Set a green certificate ratio coefficient ;
[0029] S2.2. Calculate the total green certificate demand using the green certificate ratio constraint model formula;
[0030] S2.3. Calculate the total supply of green certificates using the green certificate total calculation model formula;
[0031] S2.4. Combine the model formula of green certificate demand and total green certificate supply to construct constraint conditions:
[0032]
[0033] The mathematical model formula involved in the green certificate constraint model is as follows:
[0034]
[0035] As a further improvement of the technical solution, the specific steps involved in establishing the optimization model for improving the available flexibility of the power system taking into account the electricity-carbon coupling constraint in S3 are as follows:
[0036] S3.1. Calculate the ascent flexibility at each moment and decreased flexibility , increasing flexibility at every moment and flexibility loss value The difference between the two is accumulated to obtain the total available flexibility of the system during the entire optimization period.
[0037] S3.2. Establish the objective function of the optimization model for improving the available flexibility of the power system;
[0038] S3.3. Use equations (9) to (12) to establish general constraints for the optimization model.
[0039] As a further improvement of the technical solution, the specific steps and mathematical formula involved in calculating the total amount of available flexibility in S3.1 are as follows:
[0040] S3.1.1 Computer Group n exist t Upward climbing power at the moment , calculate the difference between the maximum output power and the actual output power of each unit , and find the unit in t Maximum flexibility value at any time , combined with the remaining transmission capacity of the network at time t ,Pick and The minimum value in is taken as the moment Increased flexibility :
[0041]
[0042]
[0043] in, R 1 ( t ) indicates that the unit is t Maximum flexibility value at any moment; R 2 ( t ) represents the remaining transmission capacity of the network at time t; R u,n ( t ) indicates the unit n exist t Upward climbing power at any moment; P max,n Indicates the unit n Maximum output power; For the crew n At the moment t The actual output power;
[0044] S3.1.2 Calculation of flexibility loss value by power transfer distribution factor :
[0045]
[0046] in, For the moment The flexibility loss value; It is a collection of all nodes that need to shed load or abandon wind and solar power; For Node At the moment Power; For Node The power transfer distribution factor of
[0047] S3.1.3. Add up the difference between the increased flexibility and the flexibility loss value at each moment to obtain the total available flexibility of the system during the entire optimization cycle. :
[0048]
[0049] in, F It indicates the available flexibility value of the system; F 0 ( t ) indicates that the system is t Maximum flexibility value at any moment; F 1( t ) indicates that the system is t Moment flexibility loss value.
[0050] As a further improvement of the technical solution, the objective function of the optimization model for improving the available flexibility of the power system in S3.2 is as follows:
[0051]
[0052] in, Obj Represents the optimization model objective function.
[0053] As a further improvement of the technical solution, the conventional constraints of the optimization model established in S3.3 include power balance constraints, thermal power unit operation constraints, thermal power unit ramp constraints and system spare capacity constraints;
[0054] The mathematical formula involved in the power balance constraint is as follows:
[0055]
[0056] in, For the moment Thermal power units Output power; P D ( t ) is the time t Load power demand; For the moment t New energy units Output power;
[0057] The mathematical formulas involved in the operation constraints of the thermal power unit are as follows:
[0058]
[0059] in, v n ( t ) represents the operating status of the thermal power unit, which is a binary variable, and its status change is affected by the start and stop time; P min,n and P max,n Respectively represent thermal power units n The minimum and maximum output active power; T on,n and T off,n Respectively represent thermal power units n Start and stop time; T min,on,n and T min,off,n Respectively represent thermal power units n Minimum allowed start and stop time;
[0060] The mathematical formula involved in the thermal power unit ramp constraint is as follows:
[0061]
[0062] in, P n ( t +1) indicates thermal power unit n Output active power at the next time state; R u,n and R d,n Respectively represent thermal power units n Up and down climbing power;
[0063] The mathematical formula involved in the system spare capacity constraint is as follows:
[0064]
[0065] in, P r ( t ) indicates new energy units r exist t Active power output at all times; S u ( t ) and S d ( t ) represent the positive and negative reserve capacities required by the system at time t respectively.
[0066] Compared with the prior art, the present invention has the following beneficial effects:
[0067] 1. In the optimization method for improving the available flexibility of the power system taking into account the electricity-carbon coupling constraint, a carbon energy consumption constraint model and a green certificate constraint model are established for the process of improving available flexibility. By limiting the carbon energy consumption in the process of improving flexibility and associating it with the energy consumption of thermal power units, the low carbon nature and new energy consumption in the process of improving flexibility are guaranteed.
[0068] 2. In the optimization method for improving the available flexibility of the power system taking into account the electricity-carbon coupling constraints, an optimization model for improving the available flexibility of the power system taking into account the electricity-carbon coupling constraints is proposed, with the goal of maximizing the available flexibility of the system. During the optimization process, carbon dioxide emissions are limited and the consumption of new energy is guaranteed, thereby improving the flexibility and environmental protection of the system. BRIEF DESCRIPTION OF THE DRAWINGS
[0069] Figure 1 is a flow chart of the overall method of the present invention;
[0070] Figure 2Flowchart of optimization method for improving available flexibility of power system considering electricity-carbon coupling constraints;
[0071] Figure 3 It is the new energy and load prediction output curve in the embodiment of the present invention;
[0072] Figure 4 Provides a comparison for the flexibility of the embodiments of the present invention. DETAILED DESCRIPTION
[0073] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0074] Example
[0075] See also Figures 1 to 4 As shown, this embodiment provides an optimization method for improving the available flexibility of a power system taking into account the electricity-carbon coupling constraint, comprising the following steps:
[0076] S1. Use the system total carbon energy consumption model and associate the carbon energy consumption with the energy consumption of thermal power units to establish a carbon energy consumption constraint model;
[0077] The mathematical model formula involved in the total carbon energy consumption model of the system in S1 is as follows:
[0078]
[0079] in, E represents the carbon energy consumption of the system; n Indicates the unit serial number; N g Indicates the number of units; t Indicates the current moment; T Represents the optimization cycle; a 2 , b 2 , c 2 For each unit n The carbon energy consumption coefficient, P n ( t ) indicates the unit n exist t Active power output at any time.
[0080] In S1, carbon energy consumption is associated with the energy consumption of thermal power units to establish a carbon energy consumption constraint model for the process of improving available flexibility. The specific steps involved are as follows:
[0081] S1.1. Set an upper limit on total carbon energy consumption: ;
[0082] S1.2 Comprehensively consider the energy consumption of thermal power units in the system , set comprehensive carbon energy consumption limits:
[0083]
[0084] S1.3. Detailed calculation of energy consumption of thermal power units , used to ensure that the energy consumption calculation in the carbon energy consumption constraint model is based on the unit output power and energy consumption coefficient:
[0085]
[0086] The specific mathematical model formula of the carbon energy consumption constraint model is as follows:
[0087]
[0088] in, E 1 It represents the carbon energy consumption obtained by the system at the next level; E 0 Indicates the system carbon energy consumption target value; E g1 Indicates the energy consumption of thermal power units in the system; Indicates the obtained carbon energy consumption coupling coefficient; Indicates the coupling coefficient for obtaining green certificate; C b Indicates the number of green certificates obtained; Indicates the floating coefficient; E g0 Indicates the system energy consumption target value.
[0089] S2. Calculate the total demand for green certificates according to the green certificate ratio constraint model, and calculate the total supply of green certificates according to the green certificate total quantity calculation model, and establish a green certificate constraint model in combination with the total demand for green certificates and the total supply of green certificates;
[0090] The mathematical model formula involved in the green certificate ratio constraint model in S2 is as follows:
[0091]
[0092] in, Indicates the green certificate ratio coefficient; C Indicates the total amount of green certificates; h Indicates the running time period; Indicates the unit At the moment The output active power of is the total number of time periods; is the number of traditional energy units.
[0093] The mathematical model formula involved in the green certificate total amount calculation model in S2 is as follows:
[0094]
[0095] in, r Indicates the serial number of the new energy unit; N r Indicates the number of new energy units; C r ( t ) indicates new energy units r exist t Green certificates generated at all times; is the total number of time periods; h Indicates the running time period; C b The number of green certificates already in the system.
[0096] In S2, a green certificate constraint model for the process of improving available flexibility is established by combining the total demand for green certificates and the total supply of green certificates. The specific steps involved are as follows:
[0097] S2.1. Set a green certificate ratio coefficient ;
[0098] S2.2. Calculate the total green certificate demand using the green certificate ratio constraint model formula;
[0099] S2.3. Calculate the total supply of green certificates using the green certificate total calculation model formula;
[0100] S2.4. Combine the model formula of green certificate demand and total green certificate supply to construct constraint conditions:
[0101]
[0102] The mathematical model formula involved in the green certificate constraint model is as follows:
[0103]
[0104] S3. Establish an optimization model for improving the available flexibility of the power system taking into account the constraints of electricity-carbon coupling, with the goal of maximizing the available flexibility of the system and limiting the emission of carbon dioxide during the optimization process;
[0105] The specific steps involved in establishing the optimization model for improving the available flexibility of the power system taking into account the electricity-carbon coupling constraint in S3 are as follows:
[0106] S3.1. Calculate the ascent flexibility at each moment and decreased flexibility , increasing flexibility at every moment and flexibility loss value The difference between the two is accumulated to obtain the total available flexibility of the system during the entire optimization period.
[0107] S3.2. Establish the objective function of the optimization model for improving the available flexibility of the power system;
[0108] S3.3. Use equations (9) to (12) to establish general constraints for the optimization model.
[0109] The specific steps and mathematical formula involved in calculating the total amount of available flexibility in S3.1 are as follows:
[0110] S3.1.1 Computer Group n exist t Upward climbing power at the moment , calculate the difference between the maximum output power and the actual output power of each unit , and find the unit in t Maximum flexibility value at any time , combined with the remaining transmission capacity of the network at time t ,Pick and The minimum value in is taken as the moment Increased flexibility :
[0111]
[0112]
[0113] in, R 1 ( t ) indicates that the unit is t Maximum flexibility value at any moment; R 2 ( t ) represents the remaining transmission capacity of the network at time t; R u,n ( t ) indicates the unit n exist t Upward climbing power at any moment; P max,n Indicates the unit n Maximum output power; For the crew n At the moment t The actual output power;
[0114] S3.1.2 Calculation of flexibility loss value by power transfer distribution factor :
[0115]
[0116] in, For the moment The flexibility loss value; It is a collection of all nodes that need to shed load or abandon wind and solar power; For Node At the moment Power; For Node The power transfer distribution factor of
[0117] S3.1.3. Add up the difference between the increased flexibility and the flexibility loss value at each moment to obtain the total available flexibility of the system during the entire optimization cycle. :
[0118]
[0119] in, F It indicates the available flexibility value of the system; F 0 ( t ) indicates that the system is t Maximum flexibility value at any moment; F 1 ( t ) indicates that the system is t Moment flexibility loss value.
[0120] The objective function of the optimization model for improving the available flexibility of the power system in S3.2 is as follows:
[0121]
[0122] in, Obj Represents the optimization model objective function.
[0123] The conventional constraints of the optimization model established in S3.3 include power balance constraints, thermal power unit operation constraints, thermal power unit ramp constraints and system reserve capacity constraints;
[0124] The mathematical formula involved in the power balance constraint is as follows:
[0125]
[0126] in, For the moment Thermal power units nOutput power; P D ( t ) is the time t Load power demand; For the moment t New energy units Output power;
[0127] The mathematical formulas involved in the operation constraints of the thermal power unit are as follows:
[0128]
[0129] in, v n ( t ) represents the operating status of the thermal power unit, which is a binary variable, and its status change is affected by the start and stop time; P min,n and P max,n Respectively represent thermal power units n The minimum and maximum output active power; T on,n and T off,n Respectively represent thermal power units n Start and stop time; T min,on,n and T min,off,n Respectively represent thermal power units n Minimum allowed start and stop time;
[0130] The mathematical formula involved in the thermal power unit ramp constraint is as follows:
[0131]
[0132] in, P n ( t +1) indicates thermal power unit n Output active power at the next time state; R u,n and R d,n Respectively represent thermal power units n Up and down climbing power;
[0133] The mathematical formula involved in the system spare capacity constraint is as follows:
[0134]
[0135] in, P r ( t ) indicates new energy units r exist tActive power output at all times; S u ( t ) and S d ( t ) represent the positive and negative reserve capacities required by the system at time t respectively.
[0136] S4. Add green certificate constraints and carbon energy consumption constraints to the power system available flexibility optimization model to solve the unit combination plan when the system available flexibility is maximized.
[0137] The experiment to verify the present invention "a method for improving the available flexibility of power systems taking into account the constraints of electricity-carbon coupling" mainly includes the following steps:
[0138] 1) The test system is composed of 12 thermal power units and a new energy power generation unit with a total installed capacity of 600MW. The new energy power generation types are wind power and photovoltaic power.
[0139] The operation and energy consumption parameters of thermal power units are shown in Table 1:
[0140] Table 1 Operation and energy consumption parameters of thermal power units
[0141]
[0142] The system operating parameters of the power system taking into account the electricity-carbon coupling constraints are shown in Table 2:
[0143] Table 2 System operating parameters
[0144] <![CDATA[Carbon energy consumption coupling coefficient λ 1 > 1.1 <![CDATA[Coupling coefficient of green certificate λ 2 > 1 <![CDATA[System carbon energy consumption target value E 0 > 49500 Floating coefficient 1.02 <![CDATA[System energy consumption target value E g0 > 59500 Green certificate ratio coefficient σ 0.3
[0145] System load and new energy output curves are as follows: Figure 3 shown.
[0146] 2) It is now proved that the power system available flexibility optimization model taking into account the electricity-carbon coupling constraints proposed in the present invention can improve the system available flexibility and limit the system carbon emissions. The unit combination scheme obtained by solving the embodiment is shown in Table 3. In comparison, the maximum available flexibility under the traditional unit combination model is 437MW, the sum of available flexibility during the dispatching period is 7676MW, and the carbon emissions are 49735kg. The maximum available flexibility of the system only for the improvement of available flexibility is 822MW, the sum of available flexibility during the dispatching period is 12346MW, and the carbon emissions are 50200kg. The power system available flexibility optimization model taking into account the electricity-carbon coupling constraints proposed in the present invention has a maximum available flexibility of 742MW, the sum of available flexibility during the dispatching period is 12100MW, and the carbon emissions are 49114kg. Compared with the traditional unit combination model, the peak and total available flexibility are significantly improved, and the carbon emissions are reduced by 621kg. The unit combination scheme is shown in Table 3:
[0147] Table 3 Unit combination scheme
[0148]
[0149] 3) It is now proven that the power system available flexibility optimization model proposed by the present invention taking into account the electricity-carbon coupling constraint can ensure the availability of flexible resources. The hourly flexibility supply obtained by solving the traditional flexibility improvement model and the model proposed by the present invention is as follows: Figure 4 By comparison, it is found that the system flexibility supply and the actual available flexibility are not equivalent. The reason for this phenomenon is usually the insufficient capacity of the system transmission network, which makes it impossible to transmit all the flexibility resources to the target node. The initial deviation between the theoretical supply value and the actual available value also proves that the model proposed in this invention can guarantee the availability of flexibility resources and ensure the accuracy of the calculation of power system flexibility improvement.
[0150] Table 4 shows the changes in the three indicators of the unit combination model only for improving available flexibility and the model proposed in the present invention compared with the traditional model. It can be seen from the table that although the unit combination model only for improving available flexibility has a slight increase in flexibility, it also increases carbon emissions. The model proposed in the present invention significantly reduces carbon dioxide emissions when the improvement in available flexibility is not much different, which proves the effectiveness of the model proposed in the present invention.
[0151] Table 4 Parameter change comparison table
[0152]
[0153] To sum up, the optimization method for improving the available flexibility of the power system taking into account the electricity-carbon coupling constraints proposed in the present invention limits the carbon energy consumption in the process of flexibility improvement and associates it with the energy consumption of thermal power units. At the same time, it uses green certificate constraints to couple the new energy consumption and carbon emission reduction, improves the flexibility and environmental protection of the system unit combination operation plan, ensures the availability of flexibility resources, and has practical engineering application value.
[0154] The above shows and describes the basic principles, main features and advantages of the present invention. Those skilled in the art should understand that the present invention is not limited by the above embodiments, and the above embodiments and descriptions are only preferred examples of the present invention, and are not intended to limit the present invention. Without departing from the spirit and scope of the present invention, the present invention may have various changes and improvements, and these changes and improvements all fall within the scope of the present invention to be protected.
Claims
1. An optimization method for improving the available flexibility of a power system taking into account the constraints of electricity-carbon coupling, comprising the following steps: S1. Use the system total carbon energy consumption model and associate the carbon energy consumption with the energy consumption of thermal power units to establish a carbon energy consumption constraint model; S2. Calculate the total demand for green certificates according to the green certificate ratio constraint model, and calculate the total supply of green certificates according to the green certificate total quantity calculation model, and establish a green certificate constraint model in combination with the total demand for green certificates and the total supply of green certificates; S3. Establish an optimization model for improving the available flexibility of the power system taking into account the constraints of electricity-carbon coupling, with the goal of maximizing the available flexibility of the system and limiting the emission of carbon dioxide during the optimization process; S4. Add green certificate constraints and carbon energy consumption constraints to the power system available flexibility optimization model to solve the unit combination plan with the maximum available flexibility of the system; Features: In S1, carbon energy consumption is associated with the energy consumption of thermal power units to establish a carbon energy consumption constraint model for the process of improving available flexibility. The specific steps involved are as follows: S1.
1. Set an upper limit on total carbon energy consumption: ; S1.2 Comprehensively consider the energy consumption of thermal power units in the system , set comprehensive carbon energy consumption limits: S1.
3. Detailed calculation of energy consumption of thermal power units , used to ensure that the energy consumption calculation in the carbon energy consumption constraint model is based on the unit output power and energy consumption coefficient: The specific mathematical model formula of the carbon energy consumption constraint model is as follows: Among them, E1 represents the carbon energy consumption obtained by the system at the previous level; E0 represents the system carbon energy consumption target value; E g1 Indicates the energy consumption of thermal power units in the system; Indicates the obtained carbon energy consumption coupling coefficient; Indicates the coupling coefficient of obtaining green certificate; C b Indicates the number of green certificates obtained; Indicates the floating coefficient; E g0 Indicates the system energy consumption target value.
2. The method for optimizing the available flexibility of a power system taking into account the constraints of electricity-carbon coupling according to claim 1, characterized in that: The mathematical model formula involved in the total carbon energy consumption model of the system in S1 is as follows: Where E represents the carbon energy consumption of the system; n represents the unit number; N g represents the number of units; t represents the current time; T represents the optimization period; a2, b2, c2 are the carbon energy consumption coefficients of unit n, P n (t) represents the active power output by unit n at time t.
3. The method for optimizing the available flexibility of a power system taking into account the constraints of electricity-carbon coupling according to claim 1, characterized in that: The mathematical model formula involved in the green certificate ratio constraint model in S2 is as follows: in, represents the green certificate ratio coefficient; C represents the total amount of green certificates; h represents the operating period; Indicates the unit At the moment The output active power of is the total number of time periods; is the number of traditional energy units.
4. The method for optimizing the available flexibility of a power system taking into account the constraints of electricity-carbon coupling according to claim 1, characterized in that: The mathematical model formula involved in the green certificate total amount calculation model in S2 is as follows: Among them, r represents the serial number of the new energy unit; N r Indicates the number of new energy units; C r (t) represents the green certificate generated by the new energy unit r at time t; is the total number of time periods; h represents the operating time period; The number of green certificates already in the system.
5. The method for optimizing the available flexibility of a power system taking into account the constraints of electricity-carbon coupling according to claim 1, characterized in that: In S2, a green certificate constraint model for the process of improving available flexibility is established by combining the total demand for green certificates and the total supply of green certificates. The specific steps involved are as follows: S2.
1. Set a green certificate ratio coefficient ; S2.
2. Calculate the total green certificate demand using the green certificate ratio constraint model formula; S2.
3. Calculate the total supply of green certificates using the green certificate total calculation model formula; S2.
4. Combine the model formula of green certificate demand and total green certificate supply to construct constraint conditions: The mathematical model formula involved in the green certificate constraint model is as follows: 。 6. The method for optimizing the available flexibility of a power system taking into account the constraints of electricity-carbon coupling according to claim 1, characterized in that: The specific steps involved in establishing the optimization model for improving the available flexibility of the power system taking into account the electricity-carbon coupling constraint in S3 are as follows: S3.
1. Calculate the ascent flexibility at each moment and decreased flexibility , increasing flexibility at every moment and flexibility loss value The difference between the two is accumulated to obtain the total available flexibility of the system during the entire optimization period. S3.
2. Establish the objective function of the optimization model for improving the available flexibility of the power system; S3.
3. Use equations (9) to (12) to establish general constraints for the optimization model.
7. The method for optimizing the available flexibility of the power system taking into account the electricity-carbon coupling constraint according to claim 6 is characterized by: The specific steps and mathematical formula involved in calculating the total amount of available flexibility in S3.1 are as follows: S3.1.
1. The upward climbing power of computer group n at time t , calculate the difference between the maximum output power and the actual output power of each unit , and find the maximum flexibility value of the unit at time t , combined with the remaining transmission capacity of the network at time t ,Pick and The minimum value in is taken as the moment Increased flexibility : Among them, R1(t) represents the maximum flexibility value of the unit at time t; R2(t) represents the remaining transmission capacity of the system network at time t; R u,n (t) represents the upward climbing power of unit n at time t; P max,n Indicates the maximum output power of unit n; is the actual output power of unit n at time t; S3.1.2 Calculation of flexibility loss value by power transfer distribution factor : in, For the moment The flexibility loss value; It is a collection of all nodes that need to shed load or abandon wind and solar power; For Node At the moment Power; For Node The power transfer distribution factor of S3.1.
3. Add up the difference between the increased flexibility and the flexibility loss value at each moment to obtain the total available flexibility of the system during the entire optimization cycle. : Among them, F represents the available flexibility value of the system; F0(t) represents the maximum flexibility value of the system at time t; F1(t) represents the flexibility loss value of the system at time t.
8. The method for optimizing the available flexibility of the power system taking into account the electricity-carbon coupling constraint according to claim 6, characterized in that: The objective function of the optimization model for improving the available flexibility of the power system in S3.2 is as follows: Among them, Obj represents the objective function of the optimization model.
9. The method for optimizing the available flexibility of the power system taking into account the electricity-carbon coupling constraint according to claim 6, characterized in that: The conventional constraints of the optimization model established in S3.3 include power balance constraints, thermal power unit operation constraints, thermal power unit ramp constraints and system reserve capacity constraints; The mathematical formula involved in the power balance constraint is as follows: in, For the moment Thermal power units Output power; P D (t) is the load power demand at time t; The new energy unit at time t Output power; The mathematical formulas involved in the operation constraints of the thermal power unit are as follows: Among them, v n (t) represents the operating state of the thermal power unit, which is a binary variable. The change of its state is affected by the start and stop time; P min,n and P max,n Respectively represent the minimum and maximum output active power of thermal power unit n; T on,n and T off,n Respectively represent the start and stop time of thermal power unit n; T min,on,n and T min,off,n They represent the minimum start and stop time allowed for thermal power unit n respectively; The mathematical formula involved in the thermal power unit ramp constraint is as follows: Among them, P n (t+1) represents the output active power of thermal power unit n at the next time state; R u,n and R d,n They represent the upward and downward climbing powers of thermal power unit n respectively; The mathematical formula involved in the system spare capacity constraint is as follows: Among them, P r (t) represents the active power output of the new energy unit r at time t; S u (t) and S d (t) represent the positive and negative reserve capacities required by the system at time t respectively.
Citation Information
Patent Citations
Multi-target dispatching method considering wind electricity output for electrical power system
CN107370188A
Electricity, heat and gas conversion optimization operation configuration method considering carbon emission and storage medium
CN113131513A
Wind power-containing electric power system unit combination robust optimization method considering comprehensive flexibility constraint
CN114880851A
Power system multi-time scale optimization method considering flexibility demand
CN115001035A
Virtual power plant day-ahead optimization scheduling method considering electricity-carbon-green certificate combined transaction
CN115660309A