Energy base distribution robust optimization scheduling method based on contract electric quantity decomposition

Through the method based on contract electricity decomposition, a two-stage distribution robust optimization scheduling model was constructed, which solved the problem of difficult to describe the uncertainty of renewable energy in large energy bases, and achieved feasibility and resource utilization in uncertain scenarios. Improvement ensures the completion of the contract power.

CN118970949APending Publication Date: 2024-11-15NORTH CHINA BRANCH OF STATE GRID CORPORATION OF CHINA
View PDF 0 Cites 2 Cited by

Patent Information

Application Number
CN202411192286.8
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-28
Publication Date
2024-11-15

AI Technical Summary

Technical Problem

In the optimization scheduling of large energy bases, it is difficult to accurately characterize the uncertainty of renewable energy, resulting in the scheduling strategy not having sufficient feasibility in uncertain scenarios, low resource utilization and high operating costs.

Method used

Using a robust optimization scheduling method for distribution of energy bases based on contract electricity decomposition, a two-stage distribution robust optimization scheduling model is constructed by obtaining the uncertainty set of renewable energy output distribution, and using the strong dual theorem to convert it into a mixed integer linear linear programming. Model, decision-making is made to optimize output of thermal power units and energy storage equipment to ensure the completion of contract electricity.

Benefits of technology

Effectively portray the uncertainty of renewable energy output in large-scale energy bases, improve the feasibility of scheduling strategies, make full use of historical data, reduce the conservatism of scheduling strategies, improve the efficiency of new energy consumption, and ensure the completion of contract electricity. .

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118970949A_ABST
    Figure CN118970949A_ABST
Patent Text Reader

Abstract

The invention relates to the technical field of control and scheduling of an energy system, and relates to an energy base distribution robust optimization scheduling method based on contract electric quantity decomposition, which comprises the following steps: acquiring a renewable energy output distribution uncertainty set; the method comprises the following steps of: constructing a two-stage distributed robust optimization scheduling model: in the first stage, configuring to decide a start-stop state and an operation state of a generator set by taking minimization of start-stop cost and operation cost of a thermal power generating unit as a target; in the second stage, under the worst renewable energy output error probability distribution scene, the optimal actual output of the thermal power generating unit and the energy storage equipment is decided with the goal of ensuring that contract electric quantity is completed; and converting the two-stage distribution robust optimization scheduling model into a mixed integer linear programming model based on a strong dual theorem, and solving to obtain an optimal scheduling strategy. The uncertainty of renewable energy output of a large energy base is described, the feasibility of a scheduling strategy in an uncertain factor scene is improved, and completion of contract decomposition electric quantity is guaranteed.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of control and dispatching of energy systems, and in particular to an energy base distributed robust optimization dispatching method based on contract electricity decomposition. Background Art

[0002] The share of renewable energy such as wind power in the power system has increased significantly. In recent years, my country has established large-scale integrated energy bases in deserts, Gobi and desert areas. These bases usually combine renewable energy power generation facilities such as wind and solar power and supporting coal-fired power plants, and are equipped with energy storage systems to improve the flexibility of the entire system. For such large energy bases, the problem of optimal scheduling is particularly critical. It is not only related to the stability and economy of the power system, but also directly related to the effective absorption of renewable energy.

[0003] At present, the existing technologies mainly adopt methods for optimizing the scheduling of large energy bases, including stochastic optimization, robust optimization, and distributed robust optimization. Among them, stochastic optimization relies on the assumption of probability distribution and predicts future operation through a large number of scenario simulations. However, due to the limited historical operation data of large energy bases, the accuracy of probability distribution estimation is not high; secondly, although robust optimization does not require specific probability distribution information of uncertainty, its solution is often too conservative, which may lead to low resource utilization and increase the operating cost of the system; distributed robust optimization attempts to further consider the uncertainty of probability distribution on the basis of robust optimization. However, with the diversification of uncertainty, the existing technology cannot accurately characterize the uncertainty of renewable energy in large energy bases, and in the face of highly uncertain scenarios, the existing scheduling strategies may not be sufficiently feasible. To this end, a distributed robust optimization scheduling method for energy bases based on contract power decomposition is proposed. Summary of the invention

[0004] In order to characterize the uncertainty of renewable energy output of large energy bases, improve the feasibility of scheduling strategies under uncertain scenarios, and ensure the completion of contract decomposition of electricity, the present invention provides an energy base distribution robust optimization scheduling method based on contract electricity decomposition, and the technical solutions adopted are as follows: Obtain the uncertainty set of renewable energy output distribution; Construct a two-stage distributed robust optimization scheduling model, including: In the first stage, the configuration is to minimize the start-up and shutdown costs and operating costs of thermal power units, and decide on the start-up and shutdown states and operating states of the power generation units; In the second stage, the worst renewable energy output error probability distribution scenario is configured to ensure the completion of the contracted electricity and determine the optimal actual output of thermal power units and energy storage equipment; Based on the strong duality theorem, the two-stage distributed robust optimization scheduling model is transformed into a mixed integer linear programming model, and the optimal scheduling strategy is obtained by solving it.

[0005] Furthermore, obtaining the uncertainty set of renewable energy output distribution includes: Extract output error prediction data based on historical prediction data of renewable energy output and historical actual output data; Constructing the empirical distribution of output error prediction data based on the Dirac test; The Wasserstein distance between the true distribution and the empirical distribution is calculated with the goal of minimizing the integral joint distribution. Calculate the fuzzy set radius and extract the fuzzy set based on the Wasserstein distance, the expression is:

[0006] In the formula, represents a fuzzy set; represents the true distribution; Indicates is the true distribution and empirical distribution set of the support set; represents the empirical distribution; Represents the fuzzy set radius.

[0007] Furthermore, the calculation of the fuzzy set radius is as follows:

[0008]

[0009]

[0010] In the formula, Represents the empirical distribution With the true distribution The probability that the Wasserstein distance between them is less than the radius of the fuzzy set; represents the number of samples; represents a constant; Indicates confidence; represents the sample mean; represents the decision variable; Indicates Historical sample data.

[0011] Furthermore, the expression of the objective function of the first stage is:

[0012] In the formula, Indicates time period; Indicates the number of time periods; Indicates the number of thermal power units; Indicates Thermal power units in The start action variable of the time period, when the value is 1, it means that the thermal power unit is started, and when the value is 0, it means that the thermal power unit maintains the original operating state; Indicates Thermal power units in The shutdown action variable of the time period, when the value is 1, it means the unit is shut down, and when the value is 0, it means the unit maintains the original operating status; Indicates Thermal power units in The operation status variable of the time period, when the value is 1, it means the unit is running, and when the value is 0, it means the unit is not running; and They represent the startup cost and shutdown cost of thermal power units respectively; Indicates The no-load cost of operating a thermal power unit.

[0013] Furthermore, in the first stage, the configuration is to minimize the start-up and shutdown costs and operating costs of thermal power units, and the decision-making of the start-up and shutdown states and operating states of the power generating units also includes at least: unit start-up and shutdown action and state constraints, unit minimum start-up and shutdown time constraints, thermal power unit output constraints, unit climbing power constraints, thermal power contract deviation power constraints, energy storage station operation constraints, external transmission line power and standard transmission curve constraints; The expression of the thermal power contract deviation quantity constraint is:

[0014] In the formula, Indicates The deviation between the power generation of each thermal power unit and the contracted power; Indicates The medium- and long-term contractual electricity volume of each thermal power unit broken down into days; Indicates Thermal power units in Output during the time period; The constraints of the transmission line power and the standard transmission curve are expressed as:

[0015]

[0016]

[0017]

[0018]

[0019]

[0020]

[0021]

[0022]

[0023] In the formula, Indicates New energy sites The predicted output for the time period; express Total power bundled and transmitted by new energy bases during the period; It represents the ratio of the transmission power of the inter-provincial tie line standard curve in period t to the transmission power in the peak period; Indicates the external power during peak hours; and Respectively represent the delivered power of AC line and DC line; and Respectively represent the maximum and minimum external power of the AC line; and Respectively represent the maximum up-slope and down-slope powers of the DC line; A 0-1 variable indicating whether the DC line power is adjusted. When the value is 1, it means that the DC line power is adjusted. When the value is 0, it means that the DC line power is the same as the previous period. is the constant operating time of the DC line; and Respectively represent Energy storage stations The charging power and discharging power of each time period.

[0024] Furthermore, the configuration is to ensure the completion of the contracted electricity under the worst renewable energy output error probability distribution scenario, and the optimal actual output of the thermal power unit and the energy storage device is also determined by: The radiation adjustment strategy is used to linearly adjust the output of thermal power units and energy storage equipment based on the adjustment coefficient to compensate for the impact of renewable energy prediction errors.

[0025] Furthermore, under the worst renewable energy output error probability distribution scenario, with the goal of ensuring the completion of the contracted electricity, the optimal actual output of thermal power units and energy storage equipment also includes: Minimize the penalty cost of the contract power deviation, minimize the deviation between the actual power generation of the thermal power unit and the contract power by deciding the deviation between the power generation of the thermal power unit and the contract power, and minimize the cost caused by the deviation penalty coefficient between the actual power generation of the thermal power unit and the contract power; Determine the optimal output of the thermal power unit by making decisions on the output of the thermal power unit and minimize the variable cost of the thermal power unit; By deciding the charging power and discharging power of the energy storage station, the optimal charging and discharging power of the energy storage station is determined, minimizing the charging and discharging cost of the energy storage station.

[0026] Furthermore, the expression of the second stage objective function is:

[0027] In the formula, It means to find the true distribution that maximizes the internal expected value in the fuzzy set; represents the expected value of the true distribution; Indicates the number of thermal power units; Indicates the number of energy storage sites; Indicates the penalty coefficient for the deviation between the actual power generation of the thermal power unit and the contracted power generation; Indicates The deviation between the power generation of each thermal power unit and the contracted power; Indicates The variable cost of operating each thermal power unit; Indicates Thermal power units in Output during the time period; and Respectively represent The charging and discharging costs of each energy storage station; and Respectively represent Energy storage stations The charging power and discharging power of each time period.

[0028] Furthermore, the output of thermal power units and energy storage devices is linearly adjusted based on the adjustment coefficient using the radiation adjustment strategy to compensate for the impact of renewable energy forecast errors. Define the total forecast error of renewable energy, which is expressed as:

[0029] In the formula, represents the total forecast error of renewable energy; Indicates New energy sites The actual output during the time period; Indicates New energy sites The predicted output for the time period; The output adjustment of thermal power units is expressed as:

[0030] In the formula, Indicates Thermal power units in The actual output during the time period; Indicates Thermal power units in Output during the time period; Indicates Thermal power units in The adjustment factor of the time period; The output adjustment of energy storage station is expressed as:

[0031]

[0032] In the formula, Indicates Energy storage stations The actual charging power during the time period; Indicates Energy storage stations Charging power during the time period; Indicates Energy storage stations Charging power adjustment factor for each time period; Indicates Energy storage stations The actual discharge power of the time period; Indicates Energy storage stations The charging power and discharging power of the time period; Indicates Energy storage stations Discharge power regulation coefficient of the time period; The regulation coefficient constraints of thermal power units and energy storage stations are expressed as follows:

[0033]

[0034]

[0035] In the formula, Indicates the number of thermal power units; Indicates the number of energy storage sites; Indicates Thermal power units in The adjustment factor of the time period; The spare capacity constraint is expressed as:

[0036]

[0037]

[0038] In the formula, Indicates Thermal power units in The lower reserve capacity of the time period, that is, the maximum output that can be reduced while ensuring the basic load of the thermal power unit; Indicates Thermal power units in The upper reserve capacity of the time period, that is, the maximum output that the thermal power unit can increase while ensuring the basic load; Indicates Energy storage stations Minimum charging power for the time period; Indicates Energy storage stations Maximum charging power during the time period; Indicates Energy storage stations Minimum discharge power in the time period; Indicates Energy storage stations The maximum discharge power during a time period.

[0039] Furthermore, the mixed integer linear programming model is specifically:

[0040] In the formula, express; represents the dual variable for solving the inequality constraints in the worst distribution problem in fuzzy sets; Represents auxiliary variables; express; express; express; express; express; express; express; express; represents the upper limit vector of renewable energy forecast error; represents the lower bound vector of renewable energy prediction error; Represents the cost coefficient in the second stage objective function.

[0041] The present invention has the following beneficial effects: The energy base distributed robust optimization scheduling method based on contract electricity decomposition provided by the present invention obtains the uncertainty set of renewable energy output distribution, establishes a two-stage distributed robust optimization scheduling model considering the contract electricity decomposition, and transforms the two-stage distributed robust optimization scheduling model into a solvable linear optimization problem based on the duality theory; it can effectively characterize the uncertainty of renewable energy output of large energy bases, thereby effectively smoothing the impact of such uncertainty, ensuring that the optimal scheduling strategy finally solved can be feasible for large energy bases under uncertain factor scenarios, making full use of limited historical data, avoiding overly conservative scheduling strategies, and achieving the goal of effectively smoothing the uncertainty of new energy, promoting the consumption of new energy, and ensuring that even when the output of renewable energy is insufficient, the output of thermal power units and energy storage equipment can be adjusted to achieve the goal of contract electricity decomposition. BRIEF DESCRIPTION OF THE DRAWINGS

[0042] In order to more clearly illustrate the technical solutions and advantages in the embodiments of the present invention or the prior art, the drawings required for use in the embodiments or the prior art descriptions are briefly introduced below. Obviously, the drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.

[0043] Figure 1 A method flow chart of a method for optimizing energy base distribution and scheduling based on contract power decomposition provided by an embodiment of the present invention; Figure 2 A flow chart of a method for constructing a two-stage distributed robust optimization scheduling model provided by an embodiment of the present invention. DETAILED DESCRIPTION

[0044] In order to further explain the technical means and effects adopted by the present invention to achieve the predetermined purpose of the invention, the specific implementation method, structure, characteristics and effects of the energy base distribution and optimization scheduling method based on the decomposition of contract electricity proposed by the present invention are described in detail as follows in combination with the accompanying drawings and preferred embodiments. In the following description, different "one embodiment" or "another embodiment" does not necessarily refer to the same embodiment. In addition, specific features, structures or characteristics in one or more embodiments may be combined in any suitable form.

[0045] Unless defined otherwise, all technical and scientific terms used herein have the same meaning as commonly understood by one of ordinary skill in the art to which this invention belongs.

[0046] The specific scheme of the energy base distributed robust optimization scheduling method based on contract electricity decomposition provided by the present invention is described in detail below with reference to the accompanying drawings.

[0047] Large energy bases mainly participate in inter-provincial medium- and long-term transactions. One of their key tasks is to decompose medium- and long-term contracts on an hourly basis to form a time-sharing power supply curve, and to execute the next day's dispatch plan accordingly. Different from the traditional medium- and long-term contract decomposition, the power supply curve of large energy bases needs to match the load characteristics of the receiving provinces, while ensuring that the total output of renewable energy and coal-fired power generation meets the requirements of the inter-provincial standard power transmission curve. These constraints significantly increase the complexity of medium- and long-term contract decomposition, especially when dealing with the uncertainty of renewable energy output. The decomposition of the contract curve of thermal power supporting large energy bases needs to comprehensively consider the constraints of multiple factors such as ensuring the consumption of renewable energy, smoothing the uncertainty of renewable energy, and the completion of medium- and long-term thermal power contracts. Therefore, it is of great significance to study the optimization dispatching method of large energy bases under uncertainty scenarios, formulate a method of decomposing medium- and long-term thermal power contracts that can cope with various renewable energy fluctuation scenarios, and finally obtain an overall transmission power curve that meets the needs of inter-provincial standard power transmission curves, which is of great significance for improving the economic performance and supply guarantee of large energy bases and the consumption of renewable energy.

[0048] See also Figure 1 , which shows a method flow chart of a method for optimizing energy base distribution and scheduling based on contract power decomposition provided by an embodiment of the present invention, the method comprising: Step S100: obtaining a renewable energy output distribution uncertainty set; Step S100 specifically includes: Step S110: Extract output error prediction data based on historical prediction data and historical actual output data of renewable energy; specifically, collect historical prediction data and actual observation data of renewable energy output within a certain period of time, and for each time point, calculate the difference between the prediction value and the actual observation value, that is, the output error, and form the output errors at all time points into a sequence or data set as the basis for the next step of constructing an empirical distribution.

[0049] Step S120: construct an empirical distribution of output error prediction data based on the Dirac test; specifically, the prediction error random variable of the renewable energy output of the large energy base is preset as , its true distribution Unknown, through historical sample data Constructing Experience Distribution Close to the true distribution, the expression is: (1) In formula (1), Represents the empirical distribution of output error prediction data; Indicates the number of historical data samples; Indicates Historical sample data; express Dirac test; By constructing an empirical distribution of output errors, the uncertainty of renewable energy output can be quantified. The use of the Dirac function makes the construction of the empirical distribution simple and direct, without the need for complex mathematical derivation or assumed distribution form. Compared with the approach of relying entirely on predicted values, this method of constructing empirical distribution based on historical data can reduce the conservatism of the dispatch strategy and avoid the cost increase caused by excessive reserve capacity; Step S130: Calculate the Wasserstein distance between the true distribution and the empirical distribution with the goal of minimizing the integral joint distribution; specifically, the preset includes all empirical distributions and the true distribution The support set of , Wasserstein distance is defined as follows: (2) In formula (2), Represents the empirical distribution and the true distribution Wasserstein distance between them; represents an arbitrary norm, and in this embodiment, the norm is 1; yes and The joint probability distribution of is defined as follows: (3) In formula (3), represents the total number of time periods considered in the optimization scheduling problem; and are the upper and lower bounds of renewable energy forecast errors, respectively; by calculating the Wasserstein distance between the true distribution and the empirical distribution, the difference between the two is evaluated to better understand the uncertainty of renewable energy output.

[0050] Step S140: Calculate the fuzzy set radius and extract the fuzzy set based on the Wasserstein distance, the expression is: (4) In formula (4), represents a fuzzy set; represents the true distribution; Indicates is the true distribution and empirical distribution set of the support set; represents the empirical distribution; represents the radius of the fuzzy set; specifically, a fuzzy set is an empirically distributed is the center and the fuzzy set radius is The Wasserstein sphere contains The Wasserstein distance is less than or equal to All probability distributions of ; the fuzzy set radius has an important influence on the performance of the distributed robust model based on Wasserstein distance. and is the sample size N and the confidence level function, and with It is a linear relationship. Specifically, the calculation of the fuzzy set radius is: (5) (6) (7) In formulas (5), (6), and (7), Represents the empirical distribution With the true distribution The probability that the Wasserstein distance between them is less than the radius of the fuzzy set; represents the number of samples; represents a constant; Indicates confidence; represents the sample mean; Represents decision variables, used to optimize the calculation constant ; Indicates By extracting fuzzy sets based on Wasserstein distance, a robust optimization model containing all empirical distributions is provided. The Wasserstein distance is less than or equal to The probability distribution set of , makes the model more stable in the face of uncertainty.

[0051] See also Figure 2 Step S200: construct a two-stage distributed robust optimization scheduling model, including: Step S210: In the first stage, the configuration is to determine the start-up and stop states and the operating states of the power generation units with the goal of minimizing the start-up and stop costs and the operating costs of the thermal power generation units; Step S210 specifically includes: Step S211: Define the expression of the first stage objective function as: (8) In formula (8), Indicates time period; Indicates the number of time periods; Indicates the number of thermal power units; Indicates Thermal power units in The start action variable of the time period, when the value is 1, it means that the thermal power unit is started, and when the value is 0, it means that the thermal power unit maintains the original operating state; Indicates Thermal power units in The shutdown action variable of the time period, when the value is 1, it means the unit is shut down, and when the value is 0, it means the unit maintains the original operating status; Indicates Thermal power units in The operation status variable of the time period, when the value is 1, it means the unit is running, and when the value is 0, it means the unit is not running; and They represent the startup cost and shutdown cost of thermal power units respectively; Indicates The no-load cost of each thermal power unit; by solving the above objective function, the optimal start-stop state and operating state of the thermal power unit can be found to minimize the total start-stop cost and operating cost; The first stage also includes at least: unit start-stop action and state constraints, unit minimum start-stop time constraints, thermal power unit output constraints, unit ramp power constraints, thermal power contract deviation power constraints, energy storage station operation constraints, external transmission line power and standard transmission curve constraints: The unit start-stop action and state constraints are expressed as: (9) (10) Formula (9) ensures that Thermal power units in Start action of time period Minus stop action Equal to the next moment running state Subtract the current running status , which ensures that the change of the unit state is consistent with the start-stop action; in formula (10), it ensures that in the same period, Thermal power units in It is not possible to start and stop at the same time during the period, that is, the start action and shutdown action The sum cannot exceed 1; The minimum start-stop time constraint of the unit is expressed as: (11) (12) (13) (14) in, and Respectively represent The minimum start-up time and minimum shutdown time of each thermal power unit.

[0052] The output constraint of thermal power units is expressed as: (15) (16) In the formula, and Respectively represent The lower reserve capacity and upper reserve capacity of each thermal power unit; and Respectively represent The lower and upper limits of the output of each thermal power unit.

[0053] The unit climbing power constraint is expressed as: (17) (18) In the formula, and Respectively represent The maximum up-ramp power and the maximum down-ramp power of each thermal power unit during operation; and Respectively represent The maximum up-climbing power when the thermal power unit is started and the maximum down-climbing power when it is shut down ensure that the output change of the thermal power unit does not exceed the climbing power limit; The expression of thermal power contract deviation quantity constraint is: (19) In the formula, Indicates The deviation between the power generation of each thermal power unit and the contracted power; Indicates The medium- and long-term contractual electricity volume of each thermal power unit broken down into days; Indicates Thermal power units in The output of the time period ensures that the deviation between the actual power generation of the thermal power unit and the contracted power generation does not exceed a certain limit, ensuring the completion of the contracted power generation; The constraints of the transmission line power and the standard transmission curve are expressed as: (20) (twenty one) (twenty two) (twenty three) (twenty four) (25) (26) (27) In the formula, Indicates New energy sites The predicted output for the time period; express Total power bundled and transmitted by new energy bases during the period; It represents the ratio of the transmission power of the inter-provincial tie line standard curve in period t to the transmission power in the peak period; Indicates the external power during peak hours; and Respectively represent the delivered power of AC line and DC line; and Respectively represent the maximum and minimum external power of the AC line; and Respectively represent the maximum up-slope and down-slope powers of the DC line; A 0-1 variable indicating whether the DC line power is adjusted. When the value is 1, it means that the DC line power is adjusted. When the value is 0, it means that the DC line power is the same as the previous period. is the constant operating time of the DC line; and Respectively represent Energy storage stations Charging power and discharging power in each time period; The operation constraints of energy storage stations are expressed as: (28) (29) (30) (31) (32) (33) (34) In the above formula, and Respectively represent Energy storage stations Charging power and discharging power in each time period; and Respectively represent Energy storage stations 0-1 variable for the period; and Respectively represent Energy storage stations Maximum charging power and maximum discharging power during a time period; and Respectively represent Energy storage stations The lower and upper reserve capacities reserved for charging in the time period; and Respectively represent Energy storage stations The lower reserve capacity and upper reserve capacity reserved for discharge in the time period; To indicate the The initial energy of each energy storage station; and Respectively represent The charging and discharging efficiency of each energy storage station; and Respectively represent The minimum / maximum storage capacity of each energy storage station; The above constraints can ensure that the dispatch plan can make more efficient use of resources while meeting various technical and economic constraints. By considering constraints such as the minimum start-up and shutdown time of thermal power units, ramp power limits, and operating limits of energy storage equipment, the robustness of the dispatch strategy is improved, enabling it to better cope with various uncertainties.

[0054] Step S220: In the second stage, the worst renewable energy output error probability distribution scenario is configured to ensure the completion of the contracted electricity volume, and to determine the optimal actual output of the thermal power unit and the energy storage device; specifically, the output of the thermal power unit and the energy storage device is linearly adjusted based on the adjustment coefficient using the radiation adjustment strategy to compensate for the impact of the renewable energy prediction error; Step S220 specifically includes: Step S221: Minimize the penalty cost of the contract power deviation, minimize the deviation between the actual power generation of the thermal power unit and the contract power by deciding the deviation between the power generation of the thermal power unit and the contract power, and minimize the cost caused by the deviation penalty coefficient between the actual power generation of the thermal power unit and the contract power; Step S222: determining the optimal output of the thermal power unit by deciding the output of the thermal power unit, minimizing the variable cost of the thermal power unit; Step S223: determining the optimal charging and discharging power of the energy storage station by deciding the charging power and discharging power of the energy storage station, thereby minimizing the charging and discharging cost of the energy storage station; The expression of the second stage objective function is: (35) In the formula, It means to find the true distribution that maximizes the internal expected value in the fuzzy set; represents the expected value of the true distribution; Indicates the number of thermal power units; Indicates the number of energy storage sites; Indicates the penalty coefficient for the deviation between the actual power generation of the thermal power unit and the contracted power generation; Indicates The deviation between the power generation of each thermal power unit and the contracted power; Indicates The variable cost of operating each thermal power unit; Indicates Thermal power units in Output during the time period; and Respectively represent The charging and discharging costs of each energy storage station; and Respectively represent Energy storage stations The entire objective function comprehensively considers the penalty cost of contract power deviation, the variable cost of thermal power units, and the charging and discharging cost of energy storage stations, aiming to find the optimal strategy that can minimize these costs under the worst renewable energy output error scenario; ensure that the contract power is completed with the minimized penalty cost under the worst renewable energy output error scenario, and minimize the deviation of the contract power by adjusting the output of thermal power units, thereby minimizing the deviation penalty cost; Define the total forecast error of renewable energy, which is expressed as: (36) In the formula, represents the total forecast error of renewable energy; Indicates New energy sites The actual output during the time period; Indicates New energy sites The predicted output for the time period; The output adjustment of thermal power units is expressed as: (37) In the formula, Indicates Thermal power units in The actual output during the time period; Indicates Thermal power units in Output during the time period; Indicates Thermal power units in The adjustment coefficient of the time period; the actual output of the thermal power unit will be adjusted according to the forecast error of renewable energy to cope with the uncertainty of renewable energy output; The output adjustment of energy storage station is expressed as: (38) (39) In the formula, Indicates Energy storage stations The actual charging power during the time period; Indicates Energy storage stations Charging power during the time period; Indicates Energy storage stations Charging power adjustment factor for each time period; Indicates Energy storage stations The actual discharge power of the time period; Indicates Energy storage stations The charging power and discharging power of the time period; Indicates Energy storage stations The discharge power adjustment coefficient of the time period; the actual charging and discharging power of the energy storage device will be adjusted according to the renewable energy forecast error to cope with the uncertainty of renewable energy output; The regulation coefficient constraints of thermal power units and energy storage stations are expressed as follows: (40) (41) (42) In the formula, Indicates the number of thermal power units; Indicates the number of energy storage sites; Indicates Thermal power units in The regulation coefficient of the time period ensures the regulation coefficient of thermal power units and energy storage stations , , The value range is between 0 and 1, which ensures the rationality of the regulation coefficient; the sum of the regulation coefficients of all thermal power units and energy storage stations is equal to 1, that is, all equipment involved in the regulation jointly undertakes the task of adjusting the renewable energy prediction error, ensuring the balance of the regulation.

[0055] The spare capacity constraint is expressed as: (43) (44) (45) In the formula, Indicates Thermal power units in The lower reserve capacity of the time period, that is, the maximum output that can be reduced while ensuring the basic load of the thermal power unit; Indicates Thermal power units in The upper reserve capacity of the time period, that is, the maximum output that the thermal power unit can increase while ensuring the basic load; Indicates Energy storage stations Minimum charging power for the time period; Indicates Energy storage stations Maximum charging power during the time period; Indicates Energy storage stations Minimum discharge power in the time period; Indicates Energy storage stations Maximum discharge power during a time period; In summary, the expression of the overall objective function of the two-stage distributed robust optimization scheduling model is:

[0056] (46) The overall objective function minimizes the overall cost by comprehensively considering the start-up and shutdown costs and operating costs of thermal power units, the penalty costs of contract electricity deviations, the variable costs of thermal power units, and the charging and discharging costs of energy storage stations; by formulating strategies under the worst renewable energy output error scenarios, it ensures that the scheduling strategy is highly robust to uncertainty.

[0057] By rationally dispatching thermal power units and energy storage equipment, we ensure that these power resources can be fully absorbed during periods of higher renewable energy output, thereby improving the utilization rate of new energy; by minimizing the penalty cost of contractual electricity deviation, we ensure that the deviation between the actual power generation of thermal power units and the contractual electricity is minimized, thereby better completing the contractual electricity.

[0058] Step S300: Based on the strong duality theorem, the two-stage distributed robust optimization scheduling model is converted into a mixed integer linear programming model, and the optimal scheduling strategy is obtained by solving it.

[0059] Step S300 specifically includes: Step S310: The distributed robust optimization scheduling model is difficult to solve directly. For the sake of simplicity, the overall objective function of the two-stage distributed robust optimization scheduling model is written as the following compact form: (47) In the formula, Represents the cost coefficient in the second-stage objective function, including the contract power deviation penalty coefficient, the thermal power unit variable cost coefficient, and the energy storage station charging and discharging cost coefficient The coefficient matrix representing the constraint correlation between the first-stage decision variables and the second-stage decision variables; The coefficient matrix representing the second-stage decision variables and the second-stage constraints; represents the vector related to renewable energy forecast error in the second stage constraints; represents the first-stage decision variables; represents the second-stage decision variable; represents the renewable energy forecast error; Step S320: The significance of the distributed robust optimization second-stage model is to solve the expected value of the second-stage operating cost under the worst probability distribution. According to the strong duality theorem, it can be converted into the following form: (48) In the formula, To find the dual variables of inequality constraints in solving the worst distribution problem in fuzzy sets; represents the objective function of the second stage; Step S330: By introducing auxiliary variables , can be transformed into: (49) (50) Step S340: Convert the original two-stage optimization scheduling model into the following form: (51) In the formula, represents the objective function of the first stage; Step S350: The mixed integer linear programming model is specifically: (52) In the formula, represents the objective function of the first stage, i.e., minimizing the start-up and shutdown costs and operating costs of thermal power units; represents the dual variable for solving the inequality constraints in the worst distribution problem in fuzzy sets; Represents auxiliary variables; Indicates that the second stage objective function is given a historical sample The cost of It represents the upper limit of the forecast error of renewable energy in the second stage objective function The cost of It indicates that the second stage objective function is the lower limit of the renewable energy prediction error The cost of represents the first stage constraints; The constraints of the second stage are the upper limit of the renewable energy forecast error Down; The constraints of the second stage are the lower limit of the renewable energy prediction error Down.; represents the upper limit vector of renewable energy forecast error; represents the lower bound vector of renewable energy prediction error; represents the cost coefficient in the second-stage objective function; by converting to a mixed integer linear programming model, the original two-stage distributed robust optimization scheduling model can be simplified, making it easier to solve. Using mature solvers (such as CPLEX, Gurobi, etc.) can efficiently solve the mixed integer linear programming model and quickly find the optimal solution.

[0060] In summary, the energy base distributed robust optimization scheduling method based on the decomposition of contracted electricity provided in this application, by constructing a two-stage distributed robust optimization scheduling model, especially considering the worst renewable energy output error probability distribution scenario in the second stage, ensures that the scheduling strategy has strong robustness to uncertainty; fuzzy sets and Wasserstein distance are used to quantify the degree of uncertainty, so that the scheduling strategy can adapt to a wide range of uncertainty scenarios. Through the objective function of the second stage, it is ensured that the deviation between the actual power generation of the thermal power unit and the contracted electricity is minimized, so as to better complete the contracted electricity. By adjusting the output of the thermal power unit and the energy storage equipment to compensate for the impact of the renewable energy forecast error, the completion of the contracted electricity is ensured. Ultimately, the scheduling efficiency of the power system is effectively improved, the cost is reduced, the robustness is enhanced, and the optimal allocation of resources is promoted, so as to achieve a more economical and efficient power system operation. This method is not only suitable for the current power market environment, but also provides a feasible technical solution for future power systems with a higher proportion of renewable energy access.

[0061] It should be noted that the sequence of the above embodiments of the present invention is only for description and does not represent the advantages and disadvantages of the embodiments. The processes depicted in the accompanying drawings do not necessarily require the specific order or continuous order shown to achieve the desired results. In some embodiments, multitasking and parallel processing are also possible or may be advantageous.

[0062] The various embodiments in this specification are described in a progressive manner, and the same or similar parts between the various embodiments can be referenced to each other, and each embodiment focuses on the differences from other embodiments.

Claims

1. Energy base distributed robust optimization scheduling method based on contract power decomposition, It is characterized in that The method comprises: Obtain the uncertainty set of renewable energy output distribution; Construct a two-stage distributed robust optimization scheduling model, including: In the first stage, the configuration is to minimize the start-up and shutdown costs and operating costs of thermal power units, and decide on the start-up and shutdown states and operating states of the power generation units; In the second stage, the worst renewable energy output error probability distribution scenario is configured to ensure the completion of the contracted electricity and determine the optimal actual output of thermal power units and energy storage equipment; Based on the strong duality theorem, the two-stage distributed robust optimization scheduling model is transformed into a mixed integer linear programming model, and the optimal scheduling strategy is obtained by solving it.

2. The energy base distribution and robust optimization scheduling method based on contract power decomposition according to claim 1, It is characterized in that Obtaining the uncertainty set of renewable energy output distribution includes: Extract output error prediction data based on historical prediction data of renewable energy output and historical actual output data; Constructing the empirical distribution of output error prediction data based on the Dirac test; The Wasserstein distance between the true distribution and the empirical distribution is calculated with the goal of minimizing the integral joint distribution. Calculate the fuzzy set radius and extract the fuzzy set based on the Wasserstein distance, the expression is: In the formula, represents a fuzzy set; represents the true distribution; Indicates is the true distribution and empirical distribution set of the support set; represents the empirical distribution; Represents the fuzzy set radius.

3. The energy base distribution and optimization scheduling method based on contract power decomposition according to claim 2, It is characterized in that The calculation of the fuzzy set radius is as follows: In the formula, Represents the empirical distribution With the true distribution The probability that the Wasserstein distance between them is less than the radius of the fuzzy set; represents the number of samples; represents a constant; Indicates confidence; represents the sample mean; represents the decision variable; Indicates Historical sample data.

4. The energy base distribution and robust optimization scheduling method based on contract power decomposition according to claim 1, It is characterized in that The expression of the objective function of the first stage is: In the formula, Indicates time period; Indicates the number of time periods; Indicates the number of thermal power units; Indicates Thermal power units in The start action variable of the time period, when the value is 1, it means that the thermal power unit is started, and when the value is 0, it means that the thermal power unit maintains the original operating state; Indicates Thermal power units in The shutdown action variable of the time period, when the value is 1, it means the unit is shut down, and when the value is 0, it means the unit maintains the original operating status; Indicates Thermal power units in The operation status variable of the time period, when the value is 1, it means the unit is running, and when the value is 0, it means the unit is not running; and They represent the startup cost and shutdown cost of thermal power units respectively; Indicates The no-load cost of operating a thermal power unit.

5. The energy base distribution and robust optimization scheduling method based on contract power decomposition according to claim 4, It is characterized in that In the first stage, the configuration is to minimize the start-up and shutdown costs and operating costs of thermal power units. The decision-making of the start-up and shutdown status and operating status of the generator unit also includes at least: unit start-up and shutdown action and state constraints, unit minimum start-up and shutdown time constraints, thermal power unit output constraints, unit climbing power constraints, thermal power contract deviation power constraints, energy storage station operation constraints, external transmission line power and standard transmission curve constraints; The expression of the thermal power contract deviation quantity constraint is: In the formula, Indicates The deviation between the power generation of each thermal power unit and the contracted power; Indicates The medium- and long-term contractual electricity volume of each thermal power unit broken down into days; Indicates Thermal power units in Output during the time period; The constraints of the transmission line power and the standard transmission curve are expressed as: In the formula, Indicates New energy sites The predicted output for the time period; express Total power bundled and transmitted by new energy bases during the period; It represents the ratio of the transmission power of the inter-provincial tie line standard curve in period t to the transmission power in the peak period; Indicates the external power during peak hours; and Respectively represent the delivered power of AC line and DC line; and Respectively represent the maximum and minimum external power of the AC line; and Respectively represent the maximum up-slope and down-slope powers of the DC line; A 0-1 variable indicating whether the DC line power is adjusted. When the value is 1, it means that the DC line power is adjusted. When the value is 0, it means that the DC line power is the same as the previous period. is the constant operating time of the DC line; and Respectively represent Energy storage stations The charging power and discharging power of each time period.

6. The energy base distribution and optimization scheduling method based on contract power decomposition according to any one of claims 1 to 5, It is characterized in that The configuration is to ensure the completion of the contracted electricity under the worst renewable energy output error probability distribution scenario. The optimal actual output of thermal power units and energy storage equipment also includes: The radiation adjustment strategy is used to linearly adjust the output of thermal power units and energy storage equipment based on the adjustment coefficient to compensate for the impact of renewable energy prediction errors.

7. The energy base distribution and optimization scheduling method based on contract power decomposition according to claim 6, It is characterized in that In the worst renewable energy output error probability distribution scenario, with the goal of ensuring the completion of the contracted electricity, the optimal actual output of thermal power units and energy storage equipment also includes: Minimize the penalty cost of the contract power deviation, minimize the deviation between the actual power generation of the thermal power unit and the contract power by deciding the deviation between the power generation of the thermal power unit and the contract power, and minimize the cost caused by the deviation penalty coefficient between the actual power generation of the thermal power unit and the contract power; Determine the optimal output of the thermal power unit by making decisions on the output of the thermal power unit and minimize the variable cost of the thermal power unit; By deciding the charging power and discharging power of the energy storage station, the optimal charging and discharging power of the energy storage station is determined, minimizing the charging and discharging cost of the energy storage station.

8. The energy base distribution and optimization scheduling method based on contract power decomposition according to claim 7, It is characterized in that The expression of the second stage objective function is: In the formula, It means to find the true distribution that maximizes the internal expected value in the fuzzy set; represents the expected value of the true distribution; Indicates the number of thermal power units; Indicates the number of energy storage sites; Indicates the penalty coefficient for the deviation between the actual power generation of the thermal power unit and the contracted power generation; Indicates The deviation between the power generation of each thermal power unit and the contracted power; Indicates The variable cost of operating each thermal power unit; Indicates Thermal power units in Output during the time period; and Respectively represent The charging and discharging costs of each energy storage station; and Respectively represent Energy storage stations The charging power and discharging power of each time period.

9. The energy base distribution optimization scheduling method according to claim 8, It is characterized in that Using the radiation adjustment strategy, the output of thermal power units and energy storage equipment is linearly adjusted based on the adjustment coefficient to compensate for the impact of renewable energy forecast errors. Define the total forecast error of renewable energy, which is expressed as: In the formula, represents the total forecast error of renewable energy; Indicates New energy sites The actual output during the time period; Indicates New energy sites The predicted output for the time period; The output adjustment of thermal power units is expressed as: In the formula, Indicates Thermal power units in The actual output during the time period; Indicates Thermal power units in Output during the time period; Indicates Thermal power units in The adjustment factor of the time period; The output adjustment of energy storage station is expressed as: In the formula, Indicates Energy storage stations The actual charging power during the time period; Indicates Energy storage stations Charging power during the time period; Indicates Energy storage stations Charging power adjustment factor for each time period; Indicates Energy storage stations The actual discharge power of the time period; Indicates Energy storage stations The charging power and discharging power of the time period; Indicates Energy storage stations Discharge power regulation coefficient of the time period; The regulation coefficient constraints of thermal power units and energy storage stations are expressed as follows: In the formula, Indicates the number of thermal power units; Indicates the number of energy storage sites; Indicates Thermal power units in The adjustment factor of the time period; The spare capacity constraint is expressed as: In the formula, Indicates Thermal power units in The lower reserve capacity of the time period, that is, the maximum output that can be reduced while ensuring the basic load of the thermal power unit; Indicates Thermal power units in The upper reserve capacity of the time period, that is, the maximum output that the thermal power unit can increase while ensuring the basic load; Indicates Energy storage stations Minimum charging power for the time period; Indicates Energy storage stations Maximum charging power during the time period; Indicates Energy storage stations Minimum discharge power in the time period; Indicates Energy storage stations The maximum discharge power during a time period.

10. The energy base distribution robust optimization scheduling method based on contract power decomposition according to claim 8, It is characterized in that The mixed integer linear programming model is specifically: In the formula, express; represents the dual variable for solving the inequality constraints in the worst distribution problem in fuzzy sets; Represents auxiliary variables; express; express; express; express; express; express; express; express; represents the upper limit vector of renewable energy forecast error; represents the lower bound vector of renewable energy prediction error; Represents the cost coefficient in the second stage objective function.

Citation Information

Cited By

  • Park micro-grid variable monitoring method and system based on embedded system

    CN119341206A

  • A campus microgrid variable monitoring method and system based on embedded system

    CN119341206B