A soft soil dry dock flood control system and its construction technology

By setting up a combination system of flood control walls and flood control embankments in dry dock construction, the flood control problem in weak soil layer construction is solved, effective blocking of river water and floods and improving the stability of the construction area, and is suitable for complex geological conditions. area.

CN118581916BActive Publication Date: 2024-11-22NO 1 ENG COMPANY CO LTD OF CCCC FIRST HARBOR ENG COMPANY +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411072427.2
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-08-06
Publication Date
2024-11-22
Estimated Expiration
2044-08-06

AI Technical Summary

Technical Problem

In immersed pipe tunnel projects, dry dock construction is greatly affected by hydrogeological conditions, especially in weak soil layers. The existing dry dock system is difficult to cope with complex geological construction needs, resulting in construction difficulties and poor flood control effects.

Method used

A combination of flood control walls and flood control embankments is adopted, including steel pipe pile walls, anti-seepage walls, concrete flood control walls and temporary embankments. These structures block river water and floods into the dry docks, and a temporary flood control cofferdam is added to the necessary areas and Joint protective walls to enhance structural stability and water stopping effect.

Benefits of technology

Effectively block river water and floods from entering the dry dock, improve the stability and flood control effect of the construction area. It is suitable for weak soil layers with low bearing capacity, especially in areas with complex geological conditions such as the Pearl River Delta, to ensure the safety and smooth progress of construction.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118581916B_ABST
    Figure CN118581916B_ABST
Patent Text Reader

Abstract

The present invention relates to a soft soil dry dock flood control system and a construction process thereof, and belongs to the technical field of immersed tube tunnel construction. The soft soil dry dock flood control system is suitable for soft soil areas with low bearing capacity, and includes a flood control wall and a flood control levee; the flood control wall is built at the intersection of the dry dock and the river channel, and is used to prevent river water from entering the dry dock; the flood control wall includes a steel pipe pile wall, an anti-seepage wall, an underground continuous wall extending along the river channel at both ends of the steel pipe pile wall, a concrete flood control wall built above the steel pipe pile wall and the underground continuous wall, and a steel sheet pile flood control wall connected to the concrete flood control wall and the underground continuous wall respectively; the flood control levee includes an existing levee and a temporary levee; the heights of the existing levee and the temporary levee are consistent. The flood control system effectively prevents river water and floods from entering the dry dock through the setting of the flood control wall and the flood control levee.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention belongs to the technical field of immersed tube tunnel construction, and in particular relates to a soft soil layer dry dock flood control system and a construction process thereof. Background Art

[0002] In immersed tube tunnel engineering, dry dock is one of the key processes. As the prefabrication site for immersed tube sections, the dry dock requires a stable support structure to ensure safety during construction, as well as a reliable water stop system and flood control system to prevent the impact of groundwater, river water and floods.

[0003] The construction of dry dock is greatly affected by hydrogeological conditions. The design and construction of dry dock flood control system need to be adapted to local conditions. The flood control work of dry dock runs through the process of dry dock construction, immersed tube segment prefabrication, immersed tube segment installation, etc., to ensure the smooth progress of immersed tube tunnel project. Dry dock construction needs to fully consider the regional characteristics of the project, especially the inland river immersed tube tunnel with more complex hydrogeological conditions, such as the project located in the Pearl River Delta region of my country. There is Shawan Fault Zone in this region, and the climate is mild, the rainfall is sufficient, and the soil layer distribution is complex, especially the soft soil layers such as silt and silty soil are widely distributed; the geological conditions in this region are complex, the soil layer has low bearing capacity, low permeability and high water content, which makes the construction of dry dock very difficult. At present, there is little construction experience in such areas. The existing dry dock system is difficult to cope with dry dock construction with such complex geology, and the dry dock flood control system is crucial to the success of dry dock construction.

[0004] Therefore, how to provide a dry dock flood protection system suitable for soft soil layers is a technical problem that urgently needs to be solved. Summary of the invention

[0005] In view of the deficiencies in the prior art, the present invention provides a soft soil dry dock flood prevention system and a construction process thereof, which effectively blocks river water and floods from entering the dry dock through the provision of flood prevention walls and flood prevention levees.

[0006] The present invention provides a soft soil dry dock flood control system, which is constructed near a river and is suitable for areas with soft soil layers with low bearing capacity, and comprises:

[0007] The flood wall is built at the intersection of the dry dock and the river channel to prevent river water from entering the dry dock; the flood wall includes a steel pipe pile wall at the dock entrance, an anti-seepage wall, an underground continuous wall extending along the river channel at both ends of the steel pipe pile wall, a concrete flood wall built above the steel pipe pile wall and the underground continuous wall, and a steel sheet pile flood wall connected to the concrete flood wall and the underground continuous wall respectively; the anti-seepage wall is built on the river side of the steel pipe pile wall;

[0008] The flood control levee is built around the dry dock to prevent floods from entering the dry dock. The flood control levee includes existing levees and temporary levees. Among them, the existing levees are dam structures that can continue to be used at the construction site, and temporary levees are built in locations where dams are lacking to meet flood control needs. The heights of the existing levees and temporary levees are kept consistent.

[0009] This technical solution effectively blocks river water and floods from entering the dry dock by setting up flood walls and flood levees.

[0010] In some of the embodiments, the soft soil dry dock flood protection system further includes a temporary flood protection cofferdam, which is constructed outside the flood protection wall and is used for temporary flood protection when the flood protection wall is constructed.

[0011] This technical solution provides temporary flood control measures through temporary flood control cofferdams, effectively blocking the entry of river water and floods and ensuring construction safety.

[0012] In some of the embodiments, the flood wall further includes a first joint protection wall, which is constructed on the river side of the connection between the steel sheet pile flood wall and the underground continuous wall.

[0013] This technical solution can effectively reinforce the joints and enhance the stability of the structure, while also playing a water-stopping role and preventing the liquid influence of soft soil layers.

[0014] In some of the embodiments, the flood wall further includes a second joint protection wall, which is constructed on both sides of the connection between the steel sheet pile flood wall and the concrete flood wall.

[0015] This technical solution can effectively strengthen the joints and enhance the stability of the structure.

[0016] Based on the above-mentioned soft soil layer dry dock flood control system, the present invention also provides a construction process of the soft soil layer dry dock flood control system, which is applied to the above-mentioned soft soil layer dry dock flood control system, and includes the following steps:

[0017] Bank protection construction steps: carry out the construction of underground continuous wall, steel pipe pile wall and anti-seepage wall in sequence;

[0018] The flood prevention construction steps are as follows: build a concrete flood wall above the steel pipe pile wall and the underground continuous wall; according to the design drawings, extend the underground continuous wall outward and build steel sheet piles as a steel sheet pile flood wall; construct the top of the concrete flood wall and the steel sheet pile flood wall to the first elevation;

[0019] The construction steps of the flood control levee are to build a temporary levee to extend the existing levee. The temporary levee foundation is constructed with three-axis cement mixing piles and clay soil is used for heightening construction; the top of the temporary levee foundation is constructed to the first elevation.

[0020] This technical solution fully considers the regional characteristics and hydrogeological conditions, and is especially suitable for areas with complex geological conditions such as the Pearl River Delta, improving the adaptability and reliability of dry dock construction.

[0021] In some of the embodiments, before the bank protection construction step, a temporary flood control cofferdam construction step is also included, the temporary flood control cofferdam is constructed using steel sheet piles, and the top of the temporary flood control cofferdam is constructed to a first elevation.

[0022] This technical solution forms a flood barrier in advance by constructing a temporary flood control cofferdam before the revetment construction to prevent the flood season from affecting the construction of the main project.

[0023] In some of the embodiments, after the flood control construction step, there is also a temporary flood control cofferdam removal step.

[0024] This technical solution restores the construction area to its original state by dismantling the temporary flood control cofferdam, reducing the impact of dry dock construction on the local environment, and is conducive to ecological balance and hydrological restoration.

[0025] In some of the embodiments, the flood prevention construction steps also include: using high-pressure rotary jet piles to construct a first joint protective wall, and the first joint protective wall is constructed on the river side of the connection between the steel sheet pile flood prevention wall and the underground continuous wall.

[0026] This technical solution improves the overall stability of the structure; moreover, the reinforcement on the river side helps to resist erosion and impact that may be caused by river water, thereby enhancing the flood control effect.

[0027] In some of the embodiments, the flood prevention construction steps also include: pouring concrete to construct a second joint protection wall, and the second joint protection wall is built on both sides of the connection between the steel sheet pile flood wall and the concrete flood wall.

[0028] This technical solution improves the overall strength of the flood wall and reduces potential damage and corresponding maintenance costs caused by floods through early reinforcement.

[0029] In some of the embodiments, in areas where construction height is restricted, temporary embankments are constructed using plastic concrete piles for foundation construction.

[0030] This technical solution can effectively support temporary levees and avoid safety risks such as collapse.

[0031] Based on the above scheme, the soft soil layer dry dock flood control system and its construction process in the embodiment of the present invention, through the construction of underground continuous walls, steel pipe pile walls and anti-seepage walls, can form a stable and firm structure in the soft soil layer, which can play a role of support and water stopping while preventing floods, effectively prevent soil loss and deformation during construction, and improve the overall stability of the dry dock; the construction of concrete flood walls and steel sheet pile flood walls strengthens the flood control system of the dry dock, and can ensure the dryness of the construction area even in areas with abundant rainfall, reducing the impact of floods and groundwater. In summary, the construction process of the soft soil layer dry dock flood control system provided in the embodiment of the present invention fully considers the regional characteristics and hydrogeological conditions, and is especially suitable for areas with complex geological conditions such as the Pearl River Delta, which improves the adaptability and reliability of dry dock construction. BRIEF DESCRIPTION OF THE DRAWINGS

[0032] The drawings described herein are used to provide a further understanding of the present invention and constitute a part of this application. The exemplary embodiments of the present invention and their descriptions are used to explain the present invention and do not constitute an improper limitation of the present invention. In the drawings:

[0033] Figure 1 It is a schematic diagram of the plan structure of the soft soil layer dry dock flood protection system according to an embodiment of the present invention;

[0034] Figure 2 for Figure 1 Schematic elevation of the flood wall in section A;

[0035] Figure 3 for Figure 2 Schematic diagram of the plane structure of part B;

[0036] Figure 4 for Figure 2 Schematic diagram of the plane structure of the C part;

[0037] Figure 5 It is a schematic diagram of the plan structure of the steel pipe pile wall of the soft soil layer dry dock flood protection system in an embodiment of the present invention;

[0038] Figure 6 It is a schematic diagram of the plan structure of a temporary levee foundation in a dry dock flood protection system for soft soil layers in an embodiment of the present invention;

[0039] Figure 7 It is a schematic diagram of the diversion road in the soft soil layer dry dock flood protection system in an embodiment of the present invention.

[0040] In the figure:

[0041] 1. Steel pipe pile wall; 2. Anti-seepage wall; 3. Underground continuous wall; 4. Concrete flood control wall; 5. Steel sheet pile flood control wall; 6. Existing levee; 7. Temporary levee; 701. Temporary levee foundation; 8. Temporary flood control cofferdam; 9. First joint protection wall; 10. Second joint protection wall; 11. Diversion road. DETAILED DESCRIPTION

[0042] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without making creative work are within the scope of protection of the present invention.

[0043] In the description of the present invention, it should be understood that the terms "center", "lateral", "longitudinal", "up", "down", "front", "back", "left", "right", "vertical", "horizontal", "top", "bottom", "inside", "outside" and the like indicate orientations or positional relationships based on the orientations or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore should not be understood as a limitation on the present invention.

[0044] The terms "first" and "second" are used for descriptive purposes only and should not be understood as indicating or implying relative importance or implicitly indicating the number of the indicated technical features. Thus, a feature defined as "first" or "second" may explicitly or implicitly include one or more of the features.

[0045] In the description of the present invention, it should be noted that, unless otherwise clearly specified and limited, the terms "installed", "connected", and "connected" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a direct connection, or an indirect connection through an intermediate medium, or it can be the internal communication of two components. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.

[0046] like Figure 1-Figure 6As shown, in one embodiment of the soft soil layer dry dock flood control system and its construction process of the present invention, the dry dock is built near the river. The soft soil layer dry dock flood control system is suitable for soft soil layer areas with low bearing capacity, and includes a flood control wall and a flood control levee; wherein the flood control wall is constructed at the intersection of the dry dock and the river channel to prevent river water from entering the dry dock; the flood control wall includes a steel pipe pile wall 1 at the dock entrance, an anti-seepage wall 2, an underground continuous wall 3 extending along the river channel at both ends of the steel pipe pile wall 1, and a continuous wall constructed above the steel pipe pile wall 1 and the continuous wall 3. A concrete flood wall 4 and a steel sheet pile flood wall 5 connected to the concrete flood wall 4 and the underground continuous wall 3; wherein, the anti-seepage wall 2 is built on the river side of the steel pipe pile wall 1; the flood control levee is built around the dry dock to prevent floods from entering the dry dock; the flood control levee includes an existing levee 6 and a temporary levee 7; wherein, the existing levee 6 is a dam structure that can continue to be used at the construction site, and a temporary levee 7 is built at a location where there is a lack of dams to meet flood control needs, and the heights of the existing levee 6 and the temporary levee 7 are kept consistent.

[0047] In the above-mentioned schematic embodiment, the flood wall and the flood levee are used to effectively prevent river water and floods from entering the dry dock; the flood wall includes an underground continuous wall 3 and a steel pipe pile wall 1, which can simultaneously play the role of support and water stopping, thereby reducing the cost of the entire dry dock construction; the temporary levee 7, as a part of the flood levee, can be built according to actual conditions to meet flood control needs; the heights of the existing levee 6 and the temporary levee 7 are kept consistent to ensure the overall flood control effect; and the construction of the flood wall and the flood levee takes into account the particularity of the soft soil layer and fully considers the geological conditions, especially for dry dock construction located in complex hydrogeological areas such as the Pearl River Delta. The system can cope with problems such as low soil bearing capacity, low permeability, and high water content to ensure the smooth progress of the construction.

[0048] Furthermore, the construction depth of the flood wall and the temporary levee 7 is determined according to the permeability coefficient and bearing capacity of the soft soil layer. Specifically, the flood wall should be constructed to a permeability coefficient of no more than 4.0*10 -4 cm / s, and the bearing capacity of the rock layer is not less than 2200kPa, and the temporary embankment 7 should be constructed to the rock layer with a bearing capacity of not less than 500kPa.

[0049] In some embodiments, Figure 1 As shown, the soft soil dry dock flood control system also includes a temporary flood control cofferdam 8, which is built outside the flood control wall and is used for temporary flood control when the flood control wall is built. The temporary flood control cofferdam 8 provides a temporary flood control measure to effectively block the entry of river water and flood water, ensuring construction safety.

[0050] Furthermore, the construction depth of the flood wall and the temporary flood cofferdam 8 is determined according to the permeability coefficient and bearing capacity of the soft soil layer. Specifically, the temporary flood cofferdam 8 should be constructed to a permeability coefficient of no more than 8.0*10-3 cm / s rock formation.

[0051] In some embodiments, Figure 3 As shown, the flood wall also includes a first joint protection wall 9, which is constructed on the river side of the connection between the steel sheet pile flood wall 5 and the underground continuous wall 3. The first joint protection wall 9 is located at the connection between the underground continuous wall 3 and the steel sheet pile flood wall 5, which can effectively reinforce the joint, enhance the stability of the structure, and ensure that the life of the flood wall can support flood control during the entire dry dock construction period; at the same time, it plays a role in stopping water and preventing the liquid influence of the soft soil layer.

[0052] In some embodiments, Figure 4 As shown, the flood wall also includes a second joint protection wall 10, which is constructed on both sides of the connection between the steel sheet pile flood wall 5 and the concrete flood wall 4. The second joint protection wall 10 is located at the connection between the concrete flood wall 4 and the steel sheet pile flood wall 5, which can effectively reinforce the joint, enhance the stability of the structure, and ensure that the life of the flood wall can support flood control during the entire dry dock construction period.

[0053] Based on the above-mentioned soft soil layer dry dock flood control system, the present invention also provides a construction process of the soft soil layer dry dock flood control system, which is applied to the above-mentioned soft soil layer dry dock flood control system, and includes the following steps:

[0054] Bank protection construction steps: Figure 1 As shown, the construction of underground continuous wall 3, steel pipe pile wall 1, and anti-seepage wall 2 is carried out in sequence. Figure 5 As shown, the construction is carried out with the cut-off wall 2 close to the steel pipe pile wall;

[0055] Flood control construction steps, such as Figure 2 As shown, a concrete flood wall 4 is built above the steel pipe pile wall 1 and the underground continuous wall 3; according to the design drawings, the underground continuous wall 3 is extended outward to build steel sheet piles as a steel sheet pile flood wall 5; the concrete flood wall 4 and the top of the steel sheet pile flood wall 5 are constructed to the first elevation;

[0056] Flood control embankment construction steps, such as Figure 6 As shown, a temporary levee 7 is constructed to extend the existing levee 6, and the temporary levee foundation 701 is constructed using three-axis cement mixing piles and clay soil for heightening; the top of the temporary levee foundation 701 is constructed to a first elevation.

[0057] In the above-mentioned schematic embodiments, the construction process of the dry dock flood control system for soft soil provided by the present invention can form a stable and firm structure in the soft soil layer through the construction of the underground continuous wall 3, the steel pipe pile wall 1 and the anti-seepage wall 2, which can play a role of support and water stopping while preventing floods, effectively prevent soil loss and deformation during construction, and improve the overall stability of the dry dock; the construction of the concrete flood wall 4 and the steel sheet pile flood wall 5 strengthens the flood control system of the dry dock, and can ensure the dryness of the construction area even in areas with abundant rainfall, reducing the impact of floods and groundwater. In summary, the construction process of the dry dock flood control system for soft soil provided in the embodiments of the present invention fully considers the regional characteristics and hydrogeological conditions, and is especially suitable for areas with complex geological conditions such as the Pearl River Delta, and improves the adaptability and reliability of dry dock construction.

[0058] In some embodiments, Figure 1 As shown, before the revetment construction step, the temporary flood cofferdam 8 construction step is also included. The temporary flood cofferdam 8 is constructed with steel sheet piles, and the top of the temporary flood cofferdam 8 is constructed to the first elevation. It should be noted that the first elevation is the lowest elevation that meets the flood control needs of the project location. By constructing the temporary flood cofferdam 8 before the revetment construction, a flood control barrier is formed in advance to prevent the flood season from affecting the construction of the main project; at the same time, the temporary flood cofferdam 8 is constructed with steel sheet piles, which can effectively avoid the infiltration of river water and ensure the stability and flood control effect of the temporary flood cofferdam 8.

[0059] In some embodiments, after the flood control construction step, there is also a step of removing the temporary flood control cofferdam 8. By removing the temporary flood control cofferdam 8, the construction area is restored to its original state, reducing the impact of dry dock construction on the local environment, which is beneficial to ecological balance and hydrological restoration; and timely removal of the temporary flood control cofferdam 8 can avoid long-term maintenance and management costs and reduce later maintenance expenses.

[0060] In some embodiments, Figure 1 As shown, the flood control construction steps also include: using high-pressure rotary jet grouting piles to construct the first joint protection wall 9, and the first joint protection wall 9 is built on the river side of the connection between the steel sheet pile flood control wall 5 and the underground continuous wall 3. The connection between the steel sheet pile flood control wall 5 and the underground continuous wall 3 is reinforced by the first joint protection wall 9 to improve the overall stability of the structure; and the reinforcement on the river side helps to resist the erosion and impact that may be caused by the river water, and enhance the flood control effect; the use of high-pressure rotary jet grouting piles that can extend into the soft soil layer for construction can form a solid protective wall, which is particularly suitable for areas with complex geological conditions and low soil bearing capacity.

[0061] In some embodiments, Figure 1As shown, the flood control construction steps also include: pouring concrete to construct the second joint protection wall 10, and the second joint protection wall 10 is built on both sides of the connection between the steel sheet pile flood wall 5 and the concrete flood wall 4. The second joint protection wall 10 is used to reinforce both sides of the connection between the steel sheet pile flood wall 5 and the concrete flood wall 4 to improve the overall strength of the flood wall; by reinforcing in advance, the potential damage caused by floods and the corresponding maintenance costs are reduced, ensuring that the flood wall can effectively protect the internal area under extreme weather conditions, such as floods or heavy rains.

[0062] In some embodiments, Figure 6 As shown, in the area with limited construction height, the temporary embankment 7 uses plastic concrete piles for foundation construction. The construction of plastic concrete piles is more flexible, which is convenient for construction in a highly restricted environment, and has good bearing capacity and stability, which can effectively support the temporary embankment 7 and avoid safety risks such as collapse.

[0063] Example 1

[0064] The construction process of the soft soil layer dry dock flood control system provided by the present invention is described below in conjunction with the dry dock construction of a certain inland river immersed tube tunnel project in the Pearl River Delta region:

[0065] The geological conditions at the location of the project in this embodiment are complex, and there are high-voltage lines passing through, making the project construction very difficult. The ground elevation on both sides of the river is 1.40~3.00m, the elevation of the embankment roads on both sides is 6.50~7.50m, and the riverbed elevation is -7.00~-1.50m; the first-level terrace terrain on both sides of the land is generally stable, mainly urban road areas, river beaches and basic farmland areas, with an elevation of 0.50~4.50m. After investigation, the soil layers in the site are distributed as follows: artificial fill, silt, silty clay, silty fine sand, fine sand, medium sand, strongly weathered muddy siltstone, and moderately weathered muddy siltstone; among them,

[0066] Artificial fill layer: layer thickness 0.50-5.00m, average layer thickness 1.65m, Class I loose soil;

[0067] Silt layer: layer thickness 1.00~18.30m, average layer thickness 7.29m, Class I loose soil;

[0068] Silty clay layer: burial depth 10.80-36.80m, layer thickness 0.80-13.90m, average layer thickness 4.44m, Class II ordinary soil;

[0069] Silt-like fine sand layer: burial depth 0.40~27.80m, layer thickness 2.20~24.50m, average layer thickness 9.87m, Class I loose soil;

[0070] Fine sand layer: burial depth 1.80~33.40m, layer thickness 2.20~32.10m, average layer thickness 10.22m, Class I loose soil;

[0071] Medium sand layer: burial depth 1.60~40.60m, layer thickness 1.70~17.30m, average layer thickness 6.01m, Class I loose soil;

[0072] Strongly weathered muddy siltstone layer: most of the buried depth is 17.40-38.70m, the layer thickness is 1.40-16.90m, the average layer thickness is 7.92m, some of the boreholes have not been exposed, and it is Class IV soft rock;

[0073] Moderately weathered muddy siltstone layer: The rock is relatively soft, RQD=40%~80%, buried at a depth of 20.40~45.60m, and this layer has not been exposed, it is a Grade V secondary hard rock.

[0074] According to the survey, the permeability coefficient of the above soft soil and rock layers from top to bottom is not greater than 8.0*10 -3 The rock layer with a permeability of less than 5.2*10 -4 The rock layer with a bearing capacity of not less than 500 kPa is a strongly weathered muddy siltstone layer with a permeability coefficient of not more than 4.0*10 -4 cm / s and the bearing capacity is not less than 2200kPa is a medium-weathered muddy siltstone layer.

[0075] The construction of the soft soil dry dock flood control system in this embodiment includes the following construction steps:

[0076] (1) Construction steps of temporary flood control cofferdam 8: Figure 1 As shown, the temporary flood control cofferdam 8 is constructed with steel sheet piles, and the bottom foundation construction permeability coefficient of the temporary flood control cofferdam 8 is not greater than 8.0*10 -3 cm / s rock layer, i.e., the fine sand layer in this embodiment, the top of the temporary flood control cofferdam 8 is constructed to the first elevation;

[0077] In this embodiment, the first elevation needs to reach 7m. Specifically, the temporary flood control system uses Larsen steel sheet piles, with a top elevation of 7m and a pile length of 12m. The geology driven into is fine sand, and a hydraulic vibrating pile driver is used for construction. The construction needs to be completed before the flood season.

[0078] (2) Bank protection construction steps: Figure 1 As shown, the underground continuous wall 3, steel pipe pile wall 1, and anti-seepage wall 2 are constructed in sequence. The underground continuous wall 3, steel pipe pile wall 1, and anti-seepage wall 2 are all constructed until the permeability coefficient is no more than 4.0*10 -4 cm / s, and a rock layer with a bearing capacity of not less than 2200 kPa, that is, a medium-weathered muddy siltstone layer in this embodiment;

[0079] In this embodiment, the underground continuous wall 3 adopts different structural forms according to the depth of the foundation pit. The construction direction of the underground continuous wall 3 is from the dock to both sides, and the construction on both sides can be carried out simultaneously; the groove walls on both sides of the underground continuous wall 3 are reinforced with φ850@600 three-axis cement soil mixing piles, and the groove forming machine + rotary drilling rig is used for groove forming construction; the maximum weight of a single steel cage is 46t, and a 250t crawler crane and a 150t crawler crane are used to lift the steel cage. The construction of the steel pipe pile wall 1 is carried out from the upstream of the river to the downstream of the river; a steel pipe pile with a diameter of 1500mm is used, the pile top elevation is 4.0m, and the pile bottom elevation is -28.57m. The steel pipe pile is inserted into the rock to the medium weathered muddy siltstone layer. A set of groove forming machines is used for the steel pipe pile construction, and the crawler crane lowers the steel pipe pile 200mm away from the bottom of the hole and positions it through a positioning frame. After the installation is completed, the catheter method is used to pour plain concrete for embedding. The anti-seepage wall 2 is constructed closely to the river side of the steel pipe pile wall 1 to protect the steel pipe pile wall 1. Specifically, the anti-seepage wall 2 is constructed with plastic concrete.

[0080] (3) Flood control construction steps, such as Figure 2 As shown in the figure, a concrete flood wall 4 is built above the steel pipe pile wall 1 and the underground continuous wall 3; according to the design drawings, the steel sheet piles are extended outward along the underground continuous wall 3 to build a steel sheet pile flood wall 5; the top of the concrete flood wall 4 and the steel sheet pile flood wall 5 are constructed to the first elevation; the bottom foundation of the steel sheet pile flood wall 5 is constructed to a permeability coefficient of no more than 4.0*10 -4 cm / s, and a rock layer with a bearing capacity of not less than 2200 kPa, that is, a medium-weathered muddy siltstone layer in this embodiment;

[0081] like Figure 3 As shown, high-pressure jet grouting piles are used to construct the first joint protection wall 9, and the first joint protection wall 9 is constructed on the river side of the connection between the steel sheet pile flood wall 5 and the underground continuous wall 3; Figure 4 As shown, pouring concrete is carried out to construct the second joint protection wall 10, and the second joint protection wall 10 is constructed on both sides of the connection between the steel sheet pile flood wall 5 and the concrete flood wall 4;

[0082] In this embodiment, the top elevation of the concrete flood wall 4 and the steel sheet pile flood wall 5 is 7.0 m; the casting length of the second joint protection wall 10 is 1 m, and 0.5 m is cast on each side of the joint.

[0083] (4) Steps for dismantling temporary flood control cofferdam 8.

[0084] (5) Construction steps of flood control embankments, such as Figure 6As shown, a temporary levee 7 is constructed to extend the existing levee 6. The temporary levee foundation 701 is constructed using triaxial cement mixing piles and is heightened using clay soil. The top of the temporary levee foundation 701 is constructed to a first elevation, and the bottom of the temporary levee foundation 701 is constructed to a rock layer with a bearing capacity of not less than 500 kPa, i.e., a strongly weathered muddy siltstone layer in this embodiment. In areas where the construction height is limited, the temporary levee 7 uses plastic concrete piles for foundation construction.

[0085] In this embodiment, the dry dock construction affects the traffic on local roads (rural roads), so the roads need to be diverted. Figure 7 As shown, the road in the construction area is diverted to the top of the temporary levee 7, and the elevation is basically consistent with the top elevation of the levee. The diverted road 11 must meet the anti-seepage requirements. After entering the diverted road 11, speed reduction signs and diversion prompts are set up 110-150m, and speed bumps are set up. Wave guardrails are set up on the diverted road 11 to ensure driving safety. The diversion of the road not only does not affect the dry dock construction, but also provides traffic convenience for the dry dock construction.

[0086] The foundation of the temporary levee 701 is reinforced with three rows of three-axis mixing piles. In areas with limited construction height, three rows of plastic concrete piles are used for construction. The inner side of the temporary levee 7 above the ground is a geomembrane, and the head of the three-axis mixing pile is equipped with a C20 concrete cap to connect the mixing pile and the geomembrane. The temporary levee 7 is filled with sand and clay excavated from the dry dock. The filling direction is from the river channel to the dry dock, and finally merged. Specifically, during construction, the temporary levee 7 is excavated and filled at the same time, and the layered filling and layered rolling method is adopted. The layered thickness of the levee filling is 30cm, and the slope ratio is controlled according to 1:2. Excavators and loaders are used to dig and load fillers, and dump trucks are used for transportation. Bulldozers are used for rough leveling, graders for fine leveling, and rollers for rolling and forming. The rollers are equipped with a CMV compaction degree intelligent monitoring system to carry out intelligent information construction management of earth backfilling and compaction operations, and strictly control the compaction degree. At the beginning of the embankment filling, embankment drainage ditches must be constructed to improve the drainage system as soon as possible.

[0087] Through the description of multiple embodiments of the soft soil layer dry dock flood control system and its construction process of the present invention, it can be seen that the soft soil layer dry dock flood control system and its construction process embodiments of the present invention have at least one or more of the following advantages:

[0088] 1. The soft soil dry dock flood control system provided by the present invention effectively blocks river water and flood from entering the dry dock through flood control walls and flood control levees;

[0089] 2. The soft soil layer dry dock flood control system provided by the present invention comprises an underground continuous wall 3 and a steel pipe pile wall 1. The underground continuous wall 3 and the steel pipe pile wall 1 can simultaneously play the role of support and water stopping, thereby reducing the cost of the entire dry dock construction;

[0090] 3. In the soft soil dry dock flood control system provided by the present invention, the temporary levee 7 is a part of the flood control levee and can be constructed according to the actual situation to meet the flood control needs; the heights of the existing levee 6 and the temporary levee 7 are kept consistent to ensure the overall flood control effect;

[0091] 4. The construction process of the soft soil dry dock flood control system provided by the present invention fully considers the geological conditions, especially for the dry dock construction in complex hydrogeological areas such as the Pearl River Delta, it can cope with the problems of low soil bearing capacity, low permeability, high water content, etc., and ensure the smooth progress of the construction.

[0092] Finally, it should be noted that: the various embodiments in this specification are described in a progressive manner, and each embodiment focuses on the differences from other embodiments. The same or similar parts between the various embodiments can be referenced to each other.

[0093] The above embodiments are only used to illustrate the technical solution of the present invention rather than to limit it. Although the present invention has been described in detail with reference to the preferred embodiments, ordinary technicians in the field should understand that the specific implementation methods of the present invention can still be modified or some technical features can be replaced by equivalents without departing from the spirit of the technical solution of the present invention, which should be included in the scope of the technical solution for protection of the present invention.

Claims

1. A soft soil dry dock flood control system, the dry dock is built near the river, characterized in that: Suitable for areas with soft soil with low bearing capacity, including: A flood wall is constructed at the intersection of a dry dock and a river channel to prevent river water from entering the dry dock. The construction depth of the flood wall is to a rock layer with a permeability coefficient of no more than 4.0*10-4cm / s and a bearing capacity of no less than 2200kPa. The flood wall includes a steel pipe pile wall at the dock entrance, an anti-seepage wall, an underground continuous wall extending along the river channel at both ends of the steel pipe pile wall, a concrete flood wall constructed above the steel pipe pile wall and the underground continuous wall, and a steel sheet pile flood wall connected to the concrete flood wall and the underground continuous wall respectively. The anti-seepage wall is constructed on the river side of the steel pipe pile wall and the anti-seepage wall is constructed using plastic concrete. The flood wall also includes a first joint protective wall, which is constructed using high-pressure rotary jet piles and is constructed on the river side of the connection between the steel sheet pile flood wall and the underground continuous wall. The flood wall also includes a second joint protective wall, which is constructed by pouring concrete and is constructed on both sides of the connection between the steel sheet pile flood wall and the concrete flood wall. The flood control levee is built around the dry dock to prevent floods from entering the dry dock. The flood control levee includes existing levees and temporary levees. The construction depth of the temporary levees is to the rock layer with a bearing capacity of not less than 500kPa. Among them, the existing levees are dam structures that can continue to be used at the construction site. Temporary levees are built in locations where dams are lacking to meet flood control needs. The heights of the existing levees and temporary levees are kept consistent.

2. The soft soil dry dock flood control system according to claim 1 is characterized in that: It also includes temporary flood control cofferdams, which are built outside the flood control wall and are used for temporary flood control when the flood control wall is being constructed.

3. A construction process for a soft soil dry dock flood control system as claimed in claim 1 or 2, characterized in that: The following steps are involved: Bank protection construction steps: carry out the construction of underground continuous wall, steel pipe pile wall and anti-seepage wall in sequence; The flood prevention construction steps are as follows: build a concrete flood wall above the steel pipe pile wall and the underground continuous wall; according to the design drawings, extend the underground continuous wall outward and build steel sheet piles as a steel sheet pile flood wall; construct the top of the concrete flood wall and the steel sheet pile flood wall to the first elevation; The construction steps of the flood control levee are to build a temporary levee to extend the existing levee. The temporary levee foundation is constructed with three-axis cement mixing piles and clay soil is used for heightening construction; the top of the temporary levee foundation is constructed to the first elevation.

4. The construction process of the soft soil dry dock flood control system according to claim 3 is characterized in that: Before the bank protection construction step, the temporary flood control cofferdam construction step is also included. The temporary flood control cofferdam is constructed with steel sheet piles, and the top of the temporary flood control cofferdam is constructed to the first elevation.

5. The construction process of the soft soil dry dock flood control system according to claim 4 is characterized in that: After the flood control construction step, the temporary flood control cofferdam dismantling step is also included.

6. The construction process of the soft soil dry dock flood control system according to claim 3 is characterized in that: The flood prevention construction steps also include: a first joint protection wall is constructed on the river side of the connection between the steel sheet pile flood prevention wall and the underground continuous wall.

7. The construction process of the soft soil dry dock flood control system according to claim 6 is characterized in that: The flood prevention construction steps also include: constructing a second joint protection wall on both sides of the connection between the steel sheet pile flood prevention wall and the concrete flood prevention wall.

8. The construction process of the soft soil dry dock flood control system according to claim 3 is characterized in that: In areas where construction height is restricted, temporary embankments use plastic concrete piles for foundation construction.