A smart gas construction supervision method, Internet of Things system and storage medium

Through smart gas construction supervision methods and Internet of Things systems, the impact of new projects on the gas pipeline network is evaluated and the pressure regulation instructions are generated, which solves the problem of abnormal gas supply and reduces the gas operating costs.

CN118608105BActive Publication Date: 2024-11-05CHENGDU QINCHUAN IOT TECH CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411080666.2
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-08-08
Publication Date
2024-11-05
Estimated Expiration
2044-08-08

AI Technical Summary

Technical Problem

When the existing gas construction project introduces new projects, it fails to effectively evaluate its impact on the original gas pipeline network, resulting in abnormal gas supply and increased operating costs.

Method used

Smart gas construction supervision methods and Internet of Things systems are adopted to evaluate the degree of project impact and estimated completion time by monitoring image data, and generate pressure regulation instructions to adjust the pressure of the gas pipeline and optimize the gas supply system.

Benefits of technology

Reduced abnormal gas supply in other areas around the new project, reduced gas operation costs, and improved overall system operation efficiency.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118608105B_ABST
    Figure CN118608105B_ABST
Patent Text Reader

Abstract

The embodiments of this specification provide a smart gas construction supervision method, an Internet of Things system, and a storage medium. The method is executed based on a processor of a government supervision management platform of a smart gas construction supervision Internet of Things system, including: obtaining monitoring image data from a gas supervision device; determining the project impact degree and the estimated project completion time of a gas construction project based on the monitoring image data; determining the supervision parameters based on the project impact degree and the estimated project completion time and sending them to a gas equipment object platform; obtaining pipeline pressure from a gas pressure regulating device; calculating fluctuation characteristics or pressure difference distribution characteristics based on pipeline pressure; and generating a pressure regulating instruction based on the supervision parameters, and fluctuation characteristics or pressure difference distribution characteristics. This method can optimize the operation of the overall gas supply system and reduce gas operation costs when introducing new gas construction projects.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the field of gas construction technology, and in particular to a smart gas construction supervision method, an Internet of Things system and a storage medium. Background Art

[0002] New residential areas or commercial buildings in cities are usually accompanied by new or expanded gas supply facilities projects, as well as gas pipeline renovation projects (hereinafter collectively referred to as gas construction projects). When there are multiple gas construction projects in a certain area, it may have an impact on the original gas supply plan. For example, it may cause problems such as intermittent gas supply shortages in some areas. The current solution is to take corresponding countermeasures after discovering gas problems based on monitoring data.

[0003] CN109670795B proposes a project management system based on big data. The system can analyze the collected image data and the progress reports uploaded by the project leaders based on the processing power of big data, so as to realize real-time monitoring of the construction progress. It can be seen that the system does not involve the problem of introducing a new gas construction project, treating the gas pipeline network as a whole, and solving the gas supply problem in the construction area where the new gas construction project is located, while considering whether other potential hidden dangers will be introduced, which will lead to abnormal gas supply in other existing normal gas supply areas around the new gas construction project, resulting in unnecessary increase in gas operation costs.

[0004] Therefore, it is hoped to provide a smart gas construction supervision method, an Internet of Things system and a storage medium. When a new gas construction project is introduced, the gas pipeline network is taken as a whole, and the impact of the newly introduced gas construction project on the original gas pipeline is promptly evaluated to generate appropriate pressure regulation instructions to the corresponding gas pressure regulating equipment, and to regulate the pressure of at least one group of gas pipelines, thereby optimizing the operation of the overall gas supply system and reducing the gas operation cost. Summary of the invention

[0005] One or more embodiments of this specification provide a smart gas construction supervision method, which is executed by a processor of a government supervision management platform of a smart gas construction supervision Internet of Things system. The method includes: obtaining monitoring image data of a construction area where a gas construction project is located from a gas monitoring device; determining the project impact degree and the estimated project completion time of the gas construction project based on the monitoring image data, and sending the project impact degree to a gas company management platform, and sending the estimated project completion time to a citizen user platform for announcement and display; determining monitoring parameters based on the project impact degree and the estimated project completion time, and sending the monitoring parameters to a gas equipment object platform via the gas company management platform and the gas company sensor network platform, the gas equipment object platform including a gas pressure regulating device, and the monitoring parameters including pressure regulating parameters of at least one group of gas pipelines; obtaining the pipeline pressure of the at least one group of gas pipelines from the gas pressure regulating device; calculating fluctuation characteristics or pressure difference distribution characteristics based on the pipeline pressure; and generating a pressure regulating instruction based on the monitoring parameters, the fluctuation characteristics or the pressure difference distribution characteristics, and sending the pressure regulating instruction to the corresponding gas pressure regulating device, and the gas pressure regulating device regulates the pressure of the at least one group of gas pipelines based on the pressure regulating instruction.

[0006] One or more embodiments of the present specification provide a smart gas construction supervision Internet of Things system, including a citizen user platform, a government supervision service platform, a government supervision management platform, a government supervision sensor network platform, a government supervision object platform, a gas company sensor network platform, a gas equipment object platform, a gas user service platform and a gas user platform. The government supervision service platform includes a government safety supervision service platform; the government supervision management platform includes a government safety supervision management platform; the government supervision sensor network platform includes a government safety supervision sensor network platform; the government supervision object platform includes the gas company management platform; the citizen user platform obtains user evaluation information and sends it to the government supervision service platform, and receives project information uploaded by the government supervision service platform and the estimated completion time of the project; the government supervision service platform is configured to interact with the citizen user platform and the government safety supervision management platform; the government supervision management platform is configured to interact with the government safety supervision service platform and the government safety supervision sensor network platform; the government supervision sensor network platform is configured to interact with the gas company management platform, the government safety supervision management platform and the gas user service platform; the government supervision object platform is configured to interact with the gas company sensor network platform, the government safety supervision sensor network platform and the gas user service platform; the gas equipment object platform is configured to interact with the gas company sensor network platform; and the gas user platform is configured to interact with the gas user service platform.

[0007] One or more embodiments of the present specification provide a computer-readable storage medium, which stores computer instructions. When a computer reads the computer instructions in the storage medium, the computer executes the aforementioned smart gas construction supervision method.

[0008] By using the smart gas construction supervision method or the Internet of Things system, when a new gas construction project is introduced, the gas pipeline network is taken as a whole, and the impact of the newly introduced gas construction project on the original gas pipeline is evaluated in a timely manner to generate appropriate pressure regulation instructions to the corresponding gas pressure regulating equipment, and regulate the pressure of at least one group of gas pipelines, thereby optimizing the operation of the overall gas supply system, reducing the occurrence of abnormal gas supply in other existing normal gas supply areas around the new gas construction project, and reducing gas operation costs. BRIEF DESCRIPTION OF THE DRAWINGS

[0009] This specification will be further described in the form of exemplary embodiments, which will be described in detail by the accompanying drawings. These embodiments are not restrictive, and in these embodiments, the same number represents the same structure, wherein:

[0010] Figure 1is a schematic diagram of a smart gas construction supervision Internet of Things system according to some embodiments of this specification;

[0011] Figure 2 is an exemplary flow chart of a smart gas construction supervision method according to some embodiments of this specification;

[0012] Figure 3 is an exemplary flow chart for determining the project impact level and the estimated project completion time of a gas construction project according to some embodiments of this specification;

[0013] Figure 4 is an exemplary flow chart for determining the project impact level of a gas construction project according to some embodiments of this specification;

[0014] Figure 5 is an exemplary flow chart for determining pressure regulation parameters of at least one group of gas pipelines according to some embodiments of this specification;

[0015] Figure 6 It is an exemplary flow chart for evaluating the probability of potential problems in an area where a gas construction project is located according to some embodiments of the present specification. DETAILED DESCRIPTION

[0016] In order to more clearly illustrate the technical solutions of the embodiments of this specification, the following is a brief introduction to the drawings required for the description of the embodiments. Obviously, the drawings described below are only some examples or embodiments of this specification. For ordinary technicians in this field, this specification can also be applied to other similar scenarios based on these drawings without creative work. Unless it is obvious from the language environment or otherwise explained, the same reference numerals in the figures represent the same structure or operation.

[0017] It should be understood that the "system", "device", "unit" and / or "module" used herein are a method for distinguishing different components, elements, parts, portions or assemblies at different levels. However, if other words can achieve the same purpose, the words can be replaced by other expressions.

[0018] As shown in this specification and claims, unless the context clearly indicates an exception, the words "a", "an", "an" and / or "the" do not refer to the singular and may also include the plural. Generally speaking, the terms "comprise" and "include" only indicate the inclusion of the steps and elements that have been clearly identified, and these steps and elements do not constitute an exclusive list. The method or device may also include other steps or elements.

[0019] Flowcharts are used in this specification to illustrate the operations performed by the system according to the embodiments of this specification. It should be understood that the preceding or following operations are not necessarily performed precisely in order. Instead, the steps may be processed in reverse order or simultaneously. At the same time, other operations may also be added to these processes, or one or more operations may be removed from these processes.

[0020] Figure 1 It is an exemplary schematic diagram of a smart gas construction supervision Internet of Things system according to some embodiments of this specification. It should be noted that the following embodiments are only used to explain this specification and do not constitute a limitation of this specification.

[0021] like Figure 1 As shown, the smart gas construction supervision Internet of Things system 100 may include a citizen user platform 110, a government supervision service platform 120, a government supervision management platform 130, a government supervision sensor network platform 140, a government supervision object platform 150, a gas company sensor network platform 160, a gas equipment object platform 170, a gas user service platform 190 and a gas user platform 180.

[0022] The citizen user platform 110 refers to a platform for interacting with users. In some embodiments, the citizen user platform 110 may be configured to obtain user evaluation information and send it to the government supervision service platform 120, and receive project information and estimated project completion time uploaded by the government supervision service platform 120.

[0023] The government supervision service platform 120 refers to a platform that provides supervision services for the government. In some embodiments, the government supervision service platform 120 may include a government security supervision service platform 121. The government security supervision service platform 121 may be a platform that provides security supervision services for the government.

[0024] The gas equipment object platform 170 is a functional platform that can sense information generation and control information execution.

[0025] In some embodiments, the gas equipment object platform 170 may include at least one of a gas pressure regulating device, a gas monitoring device, and the like.

[0026] Gas pressure regulating equipment refers to equipment used to adjust or collect pipeline pressure in gas pipelines.

[0027] The gas pressure regulating device may be deployed on the gas pipeline. In some embodiments, the gas pressure regulating device may regulate the pressure of at least one group of gas pipelines based on the pressure regulating instruction issued by the gas object platform 170 .

[0028] Gas monitoring devices refer to devices used to monitor the progress of gas construction projects. For example, drones, cameras, video recorders, etc. For a description of gas construction projects, see Figure 2 Description in step 210.

[0029] In some embodiments, the gas monitoring device can be deployed in the construction area. The gas monitoring device can upload the monitoring image data to the gas company management platform 151 based on the gas company sensor network platform 160. For more information about monitoring image data, please refer to Figure 2 and its related description.

[0030] In some embodiments, the gas monitoring device can be configured to collect monitoring image data of the construction area where the gas construction project is located. For a description of the construction area and monitoring image data, see Figure 2 Description in step 210.

[0031] The government supervision management platform 130 refers to a platform for the government to perform supervision and management. In some embodiments, the government supervision management platform 120 may include a government security supervision management platform 131. The government security supervision management platform 131 may be a platform for the government to perform security supervision and management.

[0032] In some embodiments, the government security supervision management platform 131 can interact bidirectionally with the government supervision service platform 120. In some embodiments, the government security supervision management platform 131 can interact bidirectionally with the government supervision sensor network platform 140.

[0033] In some embodiments, the gas equipment object platform 170 includes a gas monitoring device, and the government monitoring management platform 130 may include a processor and a communication device, and the processor is located on the user terminal.

[0034] The communication device refers to a device for communication within the smart gas construction supervision IoT system and between the smart gas construction supervision IoT system and the outside. In some embodiments, the communication device is configured for communication between the gas supervision device and the processor. For example, the processor can upload the monitoring image data obtained by the gas supervision device to the gas company management platform 151 through the communication device.

[0035] In some embodiments, the communication device may be configured for communication between the gas supervision device and the processor.

[0036] User terminal refers to the terminal used for users to interact with the smart gas construction supervision Internet of Things system.

[0037] In some embodiments, the user terminal may include at least one of a mobile device, a tablet computer, a laptop computer, a desktop computer, etc.

[0038] In some embodiments, the processor is configured to obtain monitoring image data from the gas monitoring device and upload it to the gas company sensor network platform 160 through the communication device. The processor is also configured to determine the project impact degree and the project estimated completion time of the gas construction project based on the monitoring image data, and send the project impact degree to the gas company management platform 151, and send the project estimated completion time to the citizen user platform 110 for announcement and display.

[0039] The processor is further configured to determine the supervision parameters based on the project impact and the estimated completion time of the project, and send the supervision parameters to the gas equipment object platform 170 via the gas company management platform 151 and the gas company sensor network platform 160. The gas equipment object platform includes a gas pressure regulating device, and the supervision parameters include at least one group of gas pipeline pressure regulating parameters. The processor is further configured to obtain the pipeline pressure of at least one group of gas pipelines from the gas pressure regulating device.

[0040] The processor is also configured to calculate fluctuation characteristics or pressure difference distribution characteristics based on pipeline pressure; and generate a pressure regulation instruction based on regulatory parameters and the fluctuation characteristics or pressure difference distribution characteristics, and send the pressure regulation instruction to the corresponding gas pressure regulating device, and the gas pressure regulating device regulates the pressure of at least one group of gas pipelines based on the pressure regulation instruction.

[0041] In some embodiments, the project impact is also related to the current monitoring results and the last monitoring project progress of the gas construction project by the gas supervision personnel, and the current monitoring results and the last monitoring project progress are obtained from the government supervision service platform. The processor is further configured to: determine the project information of the gas construction project based on the monitoring image data, the current monitoring results and the last monitoring project progress; determine the estimated project completion time of the gas construction project based on the project information; and determine the project impact of the gas construction project based on the project information and the estimated project completion time.

[0042] In some embodiments, the pressure regulation parameters are also related to the arrangement of gas regulatory personnel, and the arrangement of gas regulatory personnel is obtained based on the government regulatory management platform. The processor is further configured to: determine the pressure regulation parameters of at least one group of gas pipelines based on the project impact, the estimated completion time of the project, and the arrangement of gas regulatory personnel.

[0043] In some embodiments, the supervision parameters further include adjusted arrangements for gas supervision personnel. The processor is further configured to: determine adjusted arrangements for gas supervision personnel based on the project impact level and the project estimated completion time.

[0044] In some embodiments, the processor is further configured to: evaluate the probability of potential problems in the area where the gas construction project is located based on the project impact level, the estimated project completion time and the arrangement of gas regulatory personnel; and determine the adjusted arrangement of gas regulatory personnel based on the probability of potential problems.

[0045] In some embodiments, the processor is further configured to: evaluate the probability of potential problems in the project area through a problem probability determination model based on the project impact, estimated project completion time, and gas regulatory personnel arrangements, and the problem probability determination model is a machine learning model.

[0046] For more information about the processor, see Figure 2-Figure 6 Instructions in .

[0047] The government supervision sensor network platform 140 refers to a connection platform for realizing interaction between the government supervision management platform 130 and the government supervision object platform 150, and is configured as a communication network and a gateway. In some embodiments, the government supervision sensor network platform 140 may include a government safety supervision sensor network platform 141. The government safety supervision sensor network platform 141 may be a connection platform for realizing interaction between the government safety supervision management platform 131 and the gas company management platform 151.

[0048] In some embodiments, the government supervision sensor network platform 140 is configured to interact with the gas company management platform, the government safety supervision management platform, and the gas user service platform. For example, the government supervision object platform 150 can upload the monitoring image data of the construction area to the government supervision sensor network platform 140. For more information about this part, please refer to Figure 2 and its related description.

[0049] The government regulatory object platform 150 may be a functional platform for sensing information generation and controlling information execution.

[0050] In some embodiments, the government regulation sensor network platform 140 and the government regulation object platform 150 may exchange information.

[0051] In some embodiments, the government supervision object platform 150 may include a gas company management platform 151. The gas company management platform 151 may be a platform for sensing information generation and controlling information execution. For example, the gas company management platform 151 may obtain supervision parameters. For another example, the gas company management platform 151 may transmit pressure regulation parameters to the gas user service platform 190.

[0052] The gas company sensor network platform 160 can be a connection platform for realizing interaction between the gas company management platform 151 and the gas equipment object platform 170, and is configured as a communication network and a gateway. For example, the gas company sensor network platform 160 can send the supervision parameters determined by the processor of the government supervision management platform 130 to the gas equipment object platform 170.

[0053] The gas user platform 180 may be a user-oriented platform that can be used to interact with gas users. In some embodiments, the gas user platform is configured to interact with a gas user service platform 190 .

[0054] The gas user service platform 190 may be a platform for receiving and transmitting data and / or information. For example, the gas user service platform 190 is used to receive demands of gas users.

[0055] Some embodiments of this specification, based on the smart gas construction supervision Internet of Things system 100, can coordinate and operate regularly under the unified management of the gas company management platform 151 to optimize the operation of the overall gas supply system.

[0056] In some embodiments, the platform in the smart gas construction supervision IoT system 100 can be divided into a smart gas primary network and a smart gas secondary network. Among them, the smart gas primary network refers to the network where government users supervise the operation of the gas pipeline network, and the smart gas secondary network includes the network where the gas pipeline network is operated. In some embodiments, the same platform in the smart gas construction supervision IoT system 100 can assume different platform roles in the smart gas primary network and the smart gas secondary network.

[0057] In some embodiments, the smart gas primary network may include at least a smart gas primary network user platform, a smart gas primary network service platform, a smart gas primary network management platform, a smart gas primary network sensor network platform, and a smart gas primary network object platform. Among them, the smart gas primary network user platform may include a citizen user platform 110, the smart gas primary network service platform may include a government supervision service platform 120, the smart gas primary network management platform may include a government supervision management platform 130, the smart gas primary network sensor network platform may include a government supervision sensor network platform 140, and the smart gas primary network object platform may include a government supervision object platform 150.

[0058] In some embodiments, the smart gas secondary network may include at least a smart gas secondary network user platform, a smart gas secondary network service platform, a smart gas secondary network management platform, a smart gas secondary network sensor network platform, and a smart gas secondary network object platform. Among them, the smart gas secondary network user platform may include a gas user platform 180, the smart gas secondary network service platform may include a gas user service platform 190, the smart gas secondary network management platform may include a gas company management platform 151, the smart gas secondary network sensor network platform may include a gas company sensor network platform 160, and the smart gas secondary network object platform may include a gas equipment object platform 170.

[0059] For more information about the execution functions of the smart gas construction supervision IoT system 100, please refer to this manual Figure 2-Figure 6 Related description in .

[0060] It should be noted that the above description of the smart gas construction supervision Internet of Things system 100 is only for the convenience of description and cannot limit this specification to the scope of the embodiments cited.

[0061] Figure 2 is an exemplary flow chart of a smart gas construction supervision method according to some embodiments of this specification. In some embodiments, process 200 may be executed by a processor of the government supervision management platform 130 of the smart gas construction supervision IoT system. Figure 2 As shown, the process 200 includes the following steps 210 to 250.

[0062] Step 210, obtaining monitoring image data of the construction area where the gas construction project is located from the gas monitoring device.

[0063] For instructions on gas monitoring devices, see Figure 1 See the relevant instructions in .

[0064] Gas construction projects refer to projects related to gas pipeline construction and / or gas equipment installation. Gas equipment may include gas meters, gas stoves, water heaters, etc. For example, gas construction projects may include new gas facility projects, gas pipeline renovation projects, etc.

[0065] The construction area refers to the administrative area where the gas construction project is located. For example, the construction area can be the administrative area where the gas construction project is located: District B, City A.

[0066] The monitoring image data refers to the video data of the construction area where the gas construction project is located. In some embodiments, the monitoring image data may include multiple frames of monitoring image images. The multiple frames of monitoring image images may reflect the construction situation of the construction area where the gas construction project is located.

[0067] In some embodiments, the processor may obtain monitoring image data through a gas monitoring device.

[0068] Step 220, based on the monitoring image data, determine the project impact level and project estimated completion time of the gas construction project, and send the project impact level to the gas company management platform, and send the project estimated completion time to the citizen user platform for announcement and display.

[0069] The project impact refers to the impact of the current construction progress of the gas construction project on the existing gas pipeline network in the construction area. In some embodiments, the project impact can be expressed as a percentage, and the larger the percentage, the greater the project impact.

[0070] For example, the gas pipeline network in Area 1 of District B of City A needs to be repaired for a fault, and some pipelines around Area 1 may also have gas pipelines in Area 1 due to the gas transportation layout. In this case, the impact of the fault repair of Area 1 on the gas supply around Area 1 is the project impact.

[0071] The estimated project completion time refers to the estimated time required to complete the gas construction project.

[0072] In some embodiments, the processor can upload the monitoring image data to the government supervision service platform through the communication device, and the supervisor can evaluate the monitoring image data to obtain the project impact degree and project estimated completion time of the gas construction project. For instructions on communication equipment and government supervision service platform, please refer to Figure 1 See the relevant instructions in .

[0073] In some embodiments, the project impact is also related to the gas supervision personnel's current inspection results and the progress of the previous inspection project. The current inspection results and the progress of the previous inspection project are obtained from the government supervision service platform. The processor can also use Figure 3 The method shown in the figure is used to determine the project impact and estimated completion time of the gas construction project. For details, see Figure 3 Instructions in .

[0074] For instructions on the gas company management platform and the citizen user platform, see Figure 1 See the relevant instructions in .

[0075] In some embodiments, the processor may send the estimated completion time of the project to the citizen user platform, and announce and display it through a display device (eg, a display screen) on the citizen user platform.

[0076] Step 230, based on the project impact and the estimated project completion time, determine the supervision parameters, and send the supervision parameters to the gas equipment object platform via the gas company management platform and the gas company sensor network platform.

[0077] In some embodiments, the gas equipment object platform may include gas pressure regulating equipment.

[0078] For more information about gas pressure regulating equipment, gas company sensor network platform, and gas equipment object platform, see Figure 1 See the relevant instructions in .

[0079] Regulatory parameters refer to the parameters used to control gas construction projects.

[0080] In some embodiments, the regulatory parameters may include at least one set of gas pipeline pressure regulation parameters. The pressure regulation parameters refer to parameters for adjusting the gas supply pressure of different gas pipelines. The gas pipeline is a gas pipeline connecting a gas transmission station and a user, not a gas pipeline entering a household.

[0081] In some embodiments, the processor may determine, based on the project impact level and the project estimated completion time, a gas construction project whose project impact level is greater than a project impact level threshold and whose project estimated completion time is greater than a project time requirement threshold. The processor may also determine the supervision parameter through a first preset comparison table based on the project impact level of the gas construction project and the difference between the project estimated completion time and the project time requirement threshold.

[0082] The first preset comparison table includes the reference project impact level, the reference project estimated completion time and the difference between the reference project time requirement threshold, and the reference supervision parameter. The first preset comparison table can be constructed based on prior knowledge or historical data.

[0083] The project impact threshold refers to the critical value of the project impact. The project time requirement threshold refers to the critical value of the estimated completion time of the project. The project impact threshold and the project time requirement threshold can be preset by those skilled in the art based on experience.

[0084] In some embodiments, the pressure regulation parameters are also related to the arrangement of gas regulatory personnel, and the arrangement of gas regulatory personnel is obtained based on the government regulatory management platform. The processor can also determine the pressure regulation parameters of at least one group of gas pipelines based on the project impact, the estimated completion time of the project, and the arrangement of gas regulatory personnel.

[0085] The arrangement of gas supervisory personnel refers to the number of supervisory personnel arranged for the gas pipeline network in the construction area of ​​each gas construction project.

[0086] In some embodiments, the processor may send the project impact, estimated completion time, and gas regulatory personnel arrangements to a government regulatory service platform, and the regulators may determine at least one set of pressure regulation parameters for the gas pipeline.

[0087] In some embodiments, the processor determines a specific implementation method of at least one set of gas pipeline pressure regulation parameters based on the project impact, the estimated project completion time, and the arrangement of gas regulatory personnel. Figure 5 The method shown is implemented, see Figure 5 Instructions in .

[0088] In some embodiments, the supervision parameters further include adjusted arrangements for gas supervision personnel. The processor may determine the adjusted arrangements for gas supervision personnel based on the project impact level and the estimated completion time of the project.

[0089] In some embodiments, the processor determines a specific implementation method for adjusting the arrangement of gas supervisors based on the project impact and the estimated completion time of the project, which can be implemented by the following steps 711 to 713:

[0090] Step 711, sorting the project impacts, screening gas construction projects with greater project impacts and gas construction projects with less project impacts that meet preset conditions, as a group. The preset condition may be that the traffic distance between the gas construction project with less project impact and the gas construction project with greater project impact is within a preset value.

[0091] A high project impact level means that the project impact level is greater than a project impact level threshold. In some embodiments, there may be one or more gas construction projects with a high project impact level.

[0092] The project impact threshold refers to the critical value of the project impact, which can be preset by technical personnel in this field based on experience.

[0093] Traffic distance refers to the distance between the construction areas of two gas construction projects.

[0094] In some embodiments, the processor may use the straight-line distance between the centers of the construction areas where two gas construction projects are located as the traffic distance.

[0095] The preset value refers to a preset traffic distance threshold value. The preset value can be preset by those skilled in the art based on experience.

[0096] Step 712: For different groups, based on the number of projects in the group, the degree of project impact, and the estimated completion time of the project, a weighted sum is taken to determine the number of gas supervisors.

[0097] The number of projects within a group refers to the number of gas construction projects within the same group.

[0098] The number of gas supervision personnel refers to the number of personnel required to supervise gas construction projects in each group.

[0099] In some embodiments, the processor may use the following personnel quantity determination algorithm to determine the number of gas supervision personnel:

[0100] The number of gas supervisors in group h = a1 The number of gas construction projects in group h + a2 sum{the impact degree of gas construction project i in group h}+a2 avg{estimated completion time of gas construction project i in group h}, where a1, a2 and a3 are any numbers greater than 0 and less than 1, which can be preset by technicians in this field based on experience, and h and i are any positive integers.

[0101] Step 713, based on the number of supervisors, determine the adjusted arrangement of gas supervisors.

[0102] In some embodiments, the processor may adjust the arrangement of the supervisors in the current group based on the number of gas supervisors to obtain an adjusted arrangement of the gas supervisors. For example, if the processor determines the number of gas supervisors based on the personnel number determination algorithm and the number of gas supervisors actually arranged in the current group is greater than the number of gas supervisors actually arranged in the current group, the processor directly increases the number of gas supervisors in the current group based on the difference between the number of gas supervisors obtained by the personnel number determination algorithm and the number of gas supervisors actually arranged in the current group to obtain an adjusted arrangement of gas supervisors.

[0103] In some embodiments, the processor may also evaluate the probability of potential problems in the area where the gas construction project is located based on the project impact, estimated project completion time, and gas regulatory personnel arrangements; and determine adjusted gas regulatory personnel arrangements based on the potential problem probability.

[0104] The probability of potential problems in the area where the gas construction project is located refers to the probability of problems occurring after the gas construction project is put into use.

[0105] In some embodiments, the processor may evaluate the probability of potential problems in the construction area where the gas construction project is located through vector matching based on the project impact, the estimated project completion time, and the arrangement of gas regulatory personnel.

[0106] The processor can construct a clustering vector based on the project impact degree, project estimated completion time, gas supervision personnel arrangement, and actual problem probability of the construction area of ​​the gas construction project in the historical database; perform clustering based on the clustering vector to form a preset number of cluster centers; determine the project impact degree, project estimated completion time, and gas supervision personnel arrangement of at least one gas construction project corresponding to the cluster center as a standard vector;

[0107] For each gas construction project, a matching vector for the gas construction project is constructed based on the project impact level, estimated project completion time and gas regulatory personnel arrangement of the current gas construction project; and the similarity between the matching vector and the standard vector is calculated, and the actual problem probability of the construction area corresponding to the standard vector with the highest similarity is used as the potential problem probability of the construction area where the gas construction project is located.

[0108] In some embodiments, the processor may monitor the construction area where the gas construction project is located for a preset time, count the frequency or duration of actual problems, and determine the actual problem probability. For example, the processor may monitor the construction area where the gas construction project is located for 24 hours. If the frequency of problems in the construction area is determined to be once in 24 hours, the actual problem probability may be 1 / 24.

[0109] In some embodiments, the processor evaluates the probability of potential problems in the area where the gas construction project is located based on the project impact, the estimated completion time of the project, and the arrangement of gas supervision personnel. Figure 6 The method shown is implemented, see Figure 6 Instructions in .

[0110] In some embodiments, the processor may determine, based on the potential problem probability, a gas construction project whose potential problem probability is greater than a problem probability threshold, and increase the number of gas supervisors in the construction area where the gas construction project whose potential problem probability is greater than the problem probability threshold is located, thereby obtaining an adjusted arrangement of gas supervisors. The problem probability threshold may be preset by a person skilled in the art based on experience.

[0111] In some embodiments, the processor can determine the number of gas regulatory personnel based on the probability of potential problems and the construction area where the corresponding gas construction project is located through a second preset comparison table; and compare the number of gas regulatory personnel with the current gas regulatory personnel arrangement in the construction area where the gas construction project is located to determine the number of gas regulatory personnel that need to be increased, thereby obtaining an adjusted gas regulatory personnel arrangement.

[0112] The second preset comparison table includes the reference potential problem probability and its corresponding reference gas construction project construction area and the reference gas supervision personnel number. The second preset comparison table can be constructed based on prior knowledge or historical data.

[0113] For example, when constructing the second preset comparison table, after arranging different numbers of gas supervision personnel for the construction area where the gas construction project corresponding to the potential problem probability is located, the construction area is monitored for a preset time period (such as 24 hours, etc.), and the frequency of subsequent actual problems corresponding to different numbers of gas supervision personnel is counted, and the number of gas supervision personnel with the lowest probability of problems is counted in the second preset comparison table. Among them, the frequency of actual problems can be the probability of subsequent pipeline problems.

[0114] In some embodiments of the present specification, the adjusted arrangement of gas supervisors is determined by the probability of potential problems. For gas construction projects with a higher probability of potential problems, the number of gas supervisors can be appropriately increased, thereby improving the rationality of the final adjusted arrangement of gas supervisors.

[0115] Step 240: Obtain the pipeline pressure of at least one group of gas pipelines from the gas pressure regulating equipment.

[0116] Pipeline pressure refers to the force applied inside the gas pipeline.

[0117] In some embodiments, the processor may obtain, through the gas pressure regulating device, the pipeline pressure of at least one group of gas pipelines supervised by the gas pressure regulating device.

[0118] Step 250, based on the pipeline pressure, calculate the fluctuation characteristics or the pressure difference distribution characteristics.

[0119] Fluctuation characteristics are those related to the fluctuation of pipeline pressure over time.

[0120] In some embodiments, the processor may use the ratio of the standard deviation to the average value of the pipeline pressure at different locations in the gas pipeline in the gas construction project as the fluctuation feature. The pipeline pressure at different locations may be obtained through a gas pressure regulating device.

[0121] The pressure difference distribution characteristics refer to the characteristics related to the pressure difference distribution between two different pressure measurement points in the pipeline.

[0122] In some embodiments, the processor may first calculate the average value of pipeline pressures at different locations in the gas pipeline in the gas construction project; based on the average value, calculate the difference between the pipeline pressures at different locations and the average value, and statistically calculate the difference between the pipeline pressures at different locations and the average value to obtain pressure difference distribution characteristics. The statistical method may include at least one of a tabulation method, a classification method, and a graphical method.

[0123] The fluctuation characteristics or pressure difference distribution characteristics can reflect the tolerance range of the gas pipeline for gas pressure. If the pipeline pressure fluctuates within this tolerance range, it means that the gas pipeline is normal. Once the gas pressure suddenly increases or decreases and exceeds the tolerance range of the gas pipeline for gas pressure, it means that there is a dangerous situation that may cause the gas pipeline to rupture.

[0124] Step 260, based on the supervision parameters, and the fluctuation characteristics or pressure difference distribution characteristics, a pressure regulation instruction is generated, and the pressure regulation instruction is sent to the corresponding gas pressure regulating device, and the gas pressure regulating device regulates the pressure of at least one group of gas pipelines based on the pressure regulation instruction.

[0125] The pressure regulation instruction is an instruction used to regulate the pressure in the pipeline.

[0126] In some embodiments, the processor can determine whether the regulatory parameters of the gas pipeline are within the fluctuation characteristics or the pressure difference distribution characteristics based on the regulatory parameters. In response to the regulatory parameters of the gas pipeline being within the fluctuation characteristics or the pressure difference distribution characteristics, the regulatory parameters of the gas pipeline are retained, and based on the regulatory parameters, a pressure regulation instruction is generated and sent to the corresponding gas pipeline that needs pressure regulation; if the regulatory parameters are not within the fluctuation characteristics or the pressure difference distribution characteristics, the regulatory parameters are abandoned and the pressure regulation is not performed.

[0127] For example, if the pressure regulation parameter calculated based on the monitoring image data of the construction area where the gas construction project is located is to increase the pipeline pressure by 100Pa, the limit value of the pipeline pressure is 500Pa, and the pipeline pressure data obtained based on the gas pressure regulating equipment, the calculated fluctuation characteristics are that the pressure in the pipeline fluctuates between 200Pa and 400Pa. The pipeline pressure fluctuation is relatively large, but it is lower than the limit value of the pipeline pressure. If the pipeline pressure is increased by 100Pa according to the calculated pressure regulation parameter, the adjusted pipeline pressure fluctuates between 300Pa and 500Pa. Although the average value of the adjusted pipeline pressure is 400Pa, it does not reach the dangerous limit value of 500Pa. However, in more extreme fluctuations, the extreme limit value of 500Pa may be reached, causing the gas pipeline to rupture. Therefore, after considering the fluctuation characteristics of the pressure in the pipeline, the regulatory parameter is abandoned and the pressure is not adjusted.

[0128] In some embodiments of the present specification, when a new gas construction project is introduced, the gas pipeline network is taken as a whole, and the impact of the newly introduced gas construction project on the original gas pipeline is promptly evaluated to generate appropriate pressure regulation instructions to the corresponding gas pressure regulating equipment, and the pressure of at least one group of gas pipelines is regulated, thereby optimizing the operation of the overall gas supply system, reducing the occurrence of abnormal gas supply in other existing normal gas supply areas around the new gas construction project, and reducing gas operation costs.

[0129] Figure 3 This is an exemplary flow chart for determining the project impact degree and project estimated completion time of a gas construction project according to some embodiments of this specification. In some embodiments, process 300 can be executed by a processor of the government supervision management platform 130 of the smart gas construction supervision Internet of Things system. Figure 2 As shown, the process 300 includes the following steps 310 to 330.

[0130] Step 310, determining the project information of the gas construction project based on the monitoring image data, the current monitoring results and the progress of the last monitoring project.

[0131] For a description of monitoring image data, see Figure 2 Description in step 210.

[0132] The inspection result refers to the information related to the gas construction project obtained in this inspection. For example, the inspection result may include the damage of the gas pipelines around the gas construction project, the type of construction, and the location of the gas construction project. The gas pipelines around the gas construction project may be gas pipelines within a preset radius with the construction area where the gas construction project is located as the center. The size of the preset radius may be preset by those skilled in the art based on experience.

[0133] In some embodiments, the processor may obtain the monitoring results through the government regulatory service platform 120 .

[0134] The last audited project progress refers to the progress of the previous audited project adjacent to the current audit. The current audited project progress refers to the current construction progress of the gas construction project obtained from the audit.

[0135] In some embodiments, each gas construction project may correspond to a last inspected project progress. If the current inspected project progress is the first inspection, the last inspected project progress may be 0.

[0136] In some embodiments, the processor may obtain the progress of the last monitoring project multiple times at preset time intervals through the government supervision service platform 120. The preset time interval may be preset by those skilled in the art based on experience.

[0137] Project information refers to information related to the gas construction project. For example, the project information may include the type, location, construction scope, current monitoring project progress, and the distribution of existing gas facilities in the surrounding area and the construction time.

[0138] In some embodiments, the project information includes the current monitoring project progress. The processor can perform noise filtering on the monitoring image data based on the monitoring image data. The processor can also randomly extract a frame of monitoring image image from the monitoring image data after the noise filtering process as the first frame of monitoring image image. The processor can also extract at least one preset number of monitoring image images from the monitoring image data after the noise filtering process according to a preset frame number difference, and together with the first frame of monitoring image image, form a monitoring image sequence. The processor can also calculate the pixel difference between each adjacent monitoring image in the monitoring image sequence to form a monitoring image pixel difference sequence. The processor can also determine the current monitoring project progress through the vector database based on the monitoring image pixel difference sequence, the current monitoring results and the progress of the last monitoring project.

[0139] In some embodiments, the processor may determine the first target feature vector based on the monitoring image pixel difference sequence, the current monitoring result, and the last monitoring project progress. The processor may also determine the first associated feature vector through the vector database based on the first target feature vector. The processor may also determine the reference monitoring project progress at the historical second time point corresponding to the first associated feature vector as the reference current monitoring project progress of the gas construction project.

[0140] The vector database includes a plurality of first reference feature vectors, wherein each first reference feature vector has a corresponding reference monitoring project progress at a second historical time point. The first reference feature vector is a feature vector constructed based on a historical monitoring impact pixel difference sequence, historical monitoring results, and monitoring project progress at a first historical time point. The first historical time point is earlier than the second historical time point.

[0141] In some embodiments, the processor may determine, based on the first target feature vector, a first reference feature vector that meets a preset condition in a vector database, and determine the first reference feature vector that meets the preset condition as a first associated feature vector. In some embodiments, the preset condition may include a minimum vector distance with the first target feature vector, etc. In some embodiments, the processor may determine, based on the reference monitoring project progress at the historical second historical time point corresponding to the determined first associated feature vector, the reference current monitoring project progress of the gas construction project.

[0142] Step 320, based on the project information, determine the estimated completion time of the gas construction project.

[0143] The estimated project completion time refers to the estimated time required to complete the gas construction project. For example, the estimated completion time can be 1 year.

[0144] In some embodiments, the processor determines the specific implementation method of the estimated completion time of the gas construction project based on the project information, which can be implemented by the following steps 810-811:

[0145] Step 810, based on the construction type, construction location and current monitoring project progress in the project information, determine the estimated construction period and standard construction time.

[0146] Standard construction time refers to the time required to complete a gas construction project that is planned in advance.

[0147] The estimated construction period refers to the estimated time required to complete the entire gas construction project.

[0148] In some embodiments, the processor can determine the estimated construction period and standard construction time through a third preset comparison table based on the construction type, construction location and current monitoring project progress of the gas construction project. The third preset comparison table includes the corresponding relationship between the reference construction type, reference construction location and reference monitoring project progress of the gas construction project and the reference construction period and reference standard construction time. The third preset comparison table can be constructed according to the preliminary planning of the gas construction project.

[0149] Step 811, based on the expected construction period, standard construction time and construction time, estimate the estimated completion time of the gas construction project.

[0150] The construction time refers to the time that the gas construction project has been under construction. The processor can obtain the construction time of the gas construction project from the government supervision service platform 120.

[0151] For example only, the processor may obtain the estimated completion time according to the following first algorithm:

[0152] ;

[0153] in, Indicates the construction time. Indicates the standard construction time. Indicates the estimated construction period, Indicates the estimated completion time.

[0154] Step 330, based on the project information, the results of this inspection and the estimated completion time of the project, determine the project impact of the gas construction project.

[0155] For an explanation of the project's impact, see Figure 2 Description of step 220.

[0156] In some embodiments, the processor determines the project impact of the gas construction project based on the project information, the current inspection results, and the estimated completion time of the project, which can be implemented by the following steps 910 to 912:

[0157] Step 910, based on the construction type, construction location and current monitoring project progress in the project information, determine the estimated construction period and standard construction time.

[0158] For more information about step 910 , please refer to the above description of step 810 .

[0159] Step 911, based on the damage of the gas pipelines around the gas construction project in the inspection results, determine at least one gas pipeline impact area through a fourth preset comparison table.

[0160] In some embodiments, the damage condition of the gas pipeline may include a damaged gas pipeline.

[0161] The pipeline affected area refers to the gas supply area affected by the damaged gas pipeline.

[0162] The fourth preset comparison table includes a correspondence between damage conditions of gas pipelines around a reference gas construction project and at least one reference gas pipeline impact area. The fourth preset comparison table can be constructed based on the gas pipeline layout of the gas construction project planned in the early stage.

[0163] Step 912, determining the project impact degree of the gas construction project based on the project estimated completion time, the expected construction period, the standard construction time and at least one gas pipeline impact area of ​​the gas construction project.

[0164] In some embodiments, the processor can determine the project impact time of the gas construction project based on the estimated completion time, expected construction period and standard construction time of the gas construction project through the following second algorithm; determine the time impact factor based on the project impact time through the following third algorithm; and determine the project impact degree of the gas construction project based on the time impact factor and at least one gas pipeline impact area.

[0165] The time impact factor can be used to characterize the numerical value of the project impact degree of the gas construction project.

[0166] Just as an example, the second algorithm may be: project impact time of the gas construction project = estimated project completion time - (estimated construction period - standard construction time).

[0167] As an example only, the third algorithm may be: time impact factor of gas construction project = project impact time of gas construction project / impact time threshold. The impact time threshold may be preset by those skilled in the art based on experience.

[0168] In some embodiments, the processor may use a combination of the time impact factor and its corresponding at least one gas pipeline impact area to represent the project impact degree of the gas construction project, wherein the value of the time impact factor represents the project impact degree of the gas construction project.

[0169] In some embodiments, the processor determines the specific implementation method of the project impact degree of the gas construction project based on the project information and the estimated completion time of the project, and can also use Figure 4 The method shown is implemented, see Figure 4 Description of the section.

[0170] In some embodiments of the present specification, comprehensive project information of the gas construction project is determined through comprehensive analysis of the monitoring image data of the gas construction project, the current monitoring results and the progress of the previous monitoring project, thereby improving the accuracy of the project impact degree and the estimated project completion time of the determined gas construction project, so as to better optimize the operation of the overall gas supply system and reduce the gas operation cost.

[0171] Figure 4 is an exemplary flow chart for determining the project impact of a gas construction project according to some embodiments of this specification. In some embodiments, process 400 may be executed by a processor of the government supervision management platform 130 of the smart gas construction supervision IoT system. Figure 4 As shown, process 400 includes the following steps 410 to 430.

[0172] Step 410, sending the project information and the estimated completion time of the project to the citizen user platform.

[0173] For project information and estimated completion time, see Figure 3 For instructions on the citizen user platform, see Figure 1 See the relevant instructions in .

[0174] In some embodiments, the processor may send the project information and the estimated completion time of the project to the citizen user platform.

[0175] Step 420, obtaining user evaluation information based on the citizen user platform.

[0176] User evaluation information refers to the user's evaluation of the impact of the gas construction project on the gas supply in the gas area where the user is located. In some embodiments, the user evaluation information may include multiple levels, such as three levels: no impact, moderate impact, and great impact.

[0177] In some embodiments, the user may input user evaluation information through the citizen user platform, and the processor may obtain the user evaluation information through the citizen user platform.

[0178] Step 430, based on the user evaluation information, the results of this inspection, the project information and the estimated completion time of the project, determine the project impact level of the gas construction project.

[0179] For an explanation of the project's impact, see Figure 3 Description of step 330.

[0180] In some embodiments, the processor may use the following steps 1010 to 1012 to determine the project impact of the gas construction project:

[0181] Step 1010, based on the project information, the results of this inspection and the estimated completion time of the project, determine the time impact factor and at least one pipeline impact area of ​​the gas construction project.

[0182] The process of determining the time impact factor of the gas construction project and at least one pipeline impact area in this step is similar to Figure 3 The process in step 910 to step 912 is similar, see Figure 3 The description in steps 910-912 in .

[0183] Step 1011, based on the user evaluation information, determine the evaluation impact factor through the fifth preset comparison table.

[0184] The fifth preset comparison table includes a correspondence between reference user evaluation information and reference evaluation impact factors. The fifth preset comparison table can be constructed based on the standard of the constructed user evaluation system. The user evaluation system standard refers to the construction standard of the evaluation level in the user evaluation information. The evaluation system standard can be preset by those skilled in the art based on experience.

[0185] The evaluation impact factor can be used to characterize the impact of user evaluation on gas construction projects.

[0186] Step 1012, determining the project impact degree of the gas construction project based on the time impact factor, at least one pipeline impact area, and the evaluation impact factor.

[0187] In some embodiments, the processor can determine the impact size based on the time impact factor and the evaluation impact factor through a fourth algorithm; and determine the project impact degree of the gas construction project based on the impact size and at least one pipeline impact area.

[0188] As an example only, the fourth algorithm may be: influence size = k1 Time impact factor of gas construction project +k2 The average evaluation impact factor of the gas construction project, k1 and k2, is greater than 0 and less than 1, and can be preset by those skilled in the art based on experience. The average evaluation impact factor can be the average value of the evaluation impact factors of multiple users on the same gas construction project.

[0189] In some embodiments, the processor may use the impact size and at least one pipeline impact area to jointly represent the project impact level of the gas construction project.

[0190] In some embodiments, the project impact degree is also related to the interference degree of the pressure regulating parameters of at least one group of gas pipelines. The processor can also determine the project impact degree of the gas construction project based on the interference degree of the pressure regulating parameters of at least one group of gas pipelines, user evaluation information, the results of this inspection, project information and the estimated completion time of the project.

[0191] The degree of interference refers to the degree of interference of pressure regulation parameters on existing gas-related production and life activities.

[0192] For instructions on how to determine the level of interference, see Figure 5 See the relevant instructions in .

[0193] In some embodiments, the processor may use the following steps 1110 to 1113 to determine the project impact of the gas construction project:

[0194] Step 1110, based on the project information, the results of this inspection and the estimated completion time of the project, determine the time impact factor and at least one pipeline impact area of ​​the gas construction project.

[0195] For more information about this step, see Figure 3 The description in steps 910-912 in .

[0196] Step 1111, based on the user evaluation information, determine the evaluation impact factor through the fifth preset comparison table.

[0197] For more information about this step, see Figure 4 The instructions in step 1011 in .

[0198] Step 1112: Using the interference degree of the pressure regulation parameters of at least one group of gas pipelines as a pressure regulation influencing factor.

[0199] In some embodiments, the processor can determine the interference degree of the pressure regulation parameters of the gas construction project, the project impact, the estimated completion time of the project, and the arrangement of gas supervision personnel through the interference degree determination model. For a description of the interference degree determination model, please refer to Figure 5 Instructions in .

[0200] The pressure regulation influence factor may be used to characterize the interference degree of the pressure regulation parameters of at least one group of gas pipelines.

[0201] Step 1113, determining the project impact degree of the gas construction project based on the time impact factor, at least one pipeline impact area, the evaluation impact factor, and the pressure regulation impact factor.

[0202] For a description of the time impact factor and pipeline impact area, see Figure 3 For a description of the evaluation impact factor, see Figure 4 Instructions in step 1011.

[0203] In some embodiments, the processor can determine the impact size based on the time impact factor, the evaluation impact factor and the pressure regulation impact factor through a fifth algorithm; and determine the project impact degree of the gas construction project based on the impact size and at least one pipeline impact area.

[0204] Just as an example, the fifth algorithm may be: influence size = k1 Time impact factor of gas construction project +k2 Average evaluation impact factor of gas construction projects + k3 The pressure regulation impact factors of the gas construction project, k1, k2 and k3, are greater than 0 and less than 1, and can be preset by those skilled in the art based on experience. For an explanation of the average evaluation impact factor, please refer to the above description.

[0205] In some embodiments, the processor may use the impact size and at least one pipeline impact area together to represent the project impact level of the gas construction project.

[0206] In some embodiments of the present specification, user evaluation information is also considered in the process of determining the project impact degree of the gas construction project, which can further improve the accuracy of the determined project impact degree of the gas construction project, and then generate appropriate pressure regulation instructions to the corresponding gas pressure regulating equipment based on the accurate project impact degree, and regulate the pressure of at least one group of gas pipelines, thereby optimizing the operation of the overall gas supply system, reducing gas operating costs, and improving user satisfaction.

[0207] In addition, in the process of determining the project impact degree of the gas construction project, the interference degree of the pressure regulation parameters of at least one group of gas pipelines is also considered to minimize the impact of the pressure regulation parameters on existing gas-related production and life activities, thereby further improving the accuracy of the determined project impact degree of the gas construction project.

[0208] Figure 5is an exemplary flow chart for determining the pressure regulation parameters of at least one group of gas pipelines according to some embodiments of this specification. In some embodiments, process 500 can be executed by a processor of the government supervision management platform 130 of the smart gas construction supervision Internet of Things system. Figure 5 As shown, process 500 includes the following steps 510 to 520.

[0209] Step 510, based on the candidate pressure regulation parameters, the project impact level, the estimated project completion time and the arrangement of gas regulatory personnel, the interference level of the candidate pressure regulation parameters is determined through an interference level determination model.

[0210] For details on the project impact 510-2, the estimated project completion time 510-3, and the gas regulatory personnel arrangement 510-4, please refer to Figure 2 and its related contents.

[0211] In some embodiments, the interference level determination model 511 may be a machine learning model. In some embodiments, the types of interference level determination models may include neural network models (NN) and convolutional neural network models (CNN).

[0212] In some embodiments, the interference level determination model 520 may be trained by a large number of first training samples with first training labels.

[0213] In some embodiments, each group of first training samples in the first training samples may include pressure regulation parameters, project impact, project estimated completion time, and gas supervision personnel arrangement of historical sample gas construction projects. In some embodiments, the first training samples may be obtained based on historical data.

[0214] In some embodiments, the first training label may be the interference degree of the pressure regulating parameters of the historical sample gas construction project. In some embodiments, the processor may determine the interference degree of the candidate pressure regulating parameters of the historical sample gas construction project based on the actual gas supply problems in the subsequent construction process corresponding to the first training sample. The gas supply problems may include insufficient gas supply and gas outage.

[0215] In some embodiments, the processor can count the frequencies of various actual gas supply problems, perform weighted summation, and determine the degree of interference of the pressure regulating parameters of the historical sample gas construction projects. For example, if the actual gas supply problems in the subsequent construction process corresponding to the first training sample include insufficient gas supply and gas outage. The processor obtains the frequency of insufficient gas supply and gas outage in historical data from the government safety supervision service platform. Then the processor can use the following weighted summation algorithm to determine the degree of interference of the pressure regulating parameters of the historical sample gas construction projects:

[0216] ,in, and are the weights corresponding to insufficient gas supply and gas outage, and Greater than 0 and less than 1.

[0217] In some embodiments, the weights corresponding to different questions can be preset manually or set by system default according to the severity of the question.

[0218] In some embodiments, the processor may input a plurality of first training samples with first training labels into the initial interference degree confirmation model, construct a loss function through the first training labels and the results of the initial interference degree confirmation model, and iteratively update the parameters of the initial interference degree confirmation model based on the loss function through gradient descent or other methods. When the preset conditions are met, the model training is completed and a trained interference degree confirmation model is obtained. The preset conditions may be that the loss function converges, the number of iterations reaches a threshold, etc.

[0219] In some embodiments, the processor may input candidate pressure regulation parameters 510-1, project impact level 510-2, project estimated completion time 510-3, and gas regulatory personnel arrangement 510-4 into a trained interference degree determination model 511 to determine the interference degree 512 of the candidate pressure regulation parameters.

[0220] Step 520, based on the interference degree 512 of the candidate pressure regulation parameters, determine at least one group of gas pipeline pressure regulation parameters 521.

[0221] For a description of the voltage regulation parameter 521, see Figure 2 Description of step 230.

[0222] In some embodiments, for each group of candidate pressure regulation parameters of gas pipelines, the processor may sum the interference degrees of the candidate pressure regulation parameters of all gas pipelines in each group of gas pipelines to obtain a group of candidate pressure regulation parameters of gas pipelines with the smallest total interference degree as the pressure regulation parameters of the gas pipelines.

[0223] In some embodiments of the present specification, the interference degree of each group of candidate pressure regulating parameters can be evaluated more accurately and quickly through the interference degree determination model, and then a group of candidate pressure regulating parameters of the gas pipeline with the smallest total interference degree is selected as the pressure regulating parameters of the gas pipeline for the operation of the gas supply system, thereby ensuring the stability of the gas supply under different construction conditions when a new gas construction project is introduced.

[0224] Figure 6 is an exemplary flow chart of evaluating the probability of potential problems in the area where the project is located according to some embodiments of this specification. In some embodiments, Figure 6 It can be executed by the processor of the government supervision management platform 130 of the smart gas construction supervision Internet of Things system.

[0225] In some embodiments, the processor may evaluate the potential problem probability 640 of the area where the gas construction project is located through a problem probability determination model 620 based on the project impact level 510 - 2 , the estimated project completion time 510 - 3 , and the gas regulatory personnel arrangement 510 - 4 .

[0226] For a description of the project impact 510-2, the estimated project completion time 510-3, the arrangement of gas regulatory personnel 510-4, and the probability of potential problems 640, please refer to Figure 2 See the relevant instructions in .

[0227] In some embodiments, the problem probability determination model 620 is a machine learning model. In some embodiments, the type of the problem probability determination model 620 may include a neural network model (NN).

[0228] In some embodiments, the problem probability determination model 620 may be trained by a large number of second training samples with second training labels.

[0229] In some embodiments, each group of second training samples in the second training samples may include the project impact degree, project estimated completion time, and gas supervision personnel arrangement of historical sample gas construction projects.

[0230] In some embodiments, the second training label may be the probability of a gas pipeline failure actually occurring after the historical sample gas construction project. For example, the second training label may be 0 or 1, where 0 represents that no gas pipeline failure occurred within a preset time period (e.g., 24 hours) after the completion of the historical sample gas construction project, and 1 represents that a gas pipeline failure occurred within a preset time period after the completion of the historical sample gas construction project.

[0231] In some embodiments, the second training sample and the second training label may be acquired based on historical data.

[0232] In some embodiments, the problem probability determination model 620 may include a feature extraction layer 620 - 1 and a problem probability prediction layer 620 - 2 , and both the feature extraction layer 620 - 1 and the problem probability prediction layer 620 - 2 are neural network models.

[0233] In some embodiments, the feature extraction layer 620 - 1 may be used to process the project impact level 510 - 2 , the project estimated completion time 510 - 3 , and the gas supervisor arrangement 510 - 4 to determine a gas feature vector 630 .

[0234] The gas characteristic vector 630 refers to a vector composed of the project impact degree 510 - 2 , the project estimated completion time 510 - 3 , and the gas regulatory personnel arrangement 510 - 4 .

[0235] In some embodiments, the problem probability prediction layer 620 - 2 can be used to process the gas feature vector 630 output by the feature extraction layer 620 - 1 to determine the potential problem probability 640 of the area where the gas construction project is located.

[0236] In some embodiments, the problem probability determination model can be obtained by joint training of the feature extraction layer and the problem probability prediction layer based on a large number of third training samples with third labels.

[0237] In some embodiments, each group of third training samples in the third training samples may include the project impact degree, project estimated completion time, and gas supervision personnel arrangement of the historical sample gas construction project. The third label may be the probability of subsequent actual gas pipeline failure in the construction area where the historical sample gas construction project is located. In some embodiments, the third label may be obtained through historical data acquisition or manual annotation.

[0238] In some embodiments, the processor may monitor the construction area where the historical sample gas construction project is located for a preset time, count the frequency or duration of actual gas pipeline failures, and determine the probability of actual gas pipeline failures. For example, the processor may count the construction area where the historical sample gas construction project is located 24 hours after completion. If the frequency of gas pipeline failures is once in 24 hours, the actual probability of gas pipeline failures is 1 / 24. For another example, the processor may count the construction area where the historical sample gas construction project is located 24 hours after completion. If the duration of the gas pipeline failure is 1 hour, the actual probability of the problem is 1 / 24.

[0239] In some embodiments, the project impact degree, estimated project completion time and gas regulatory personnel arrangement of the historical sample gas construction project in the third training sample with a third label can be input into the initial feature extraction layer, and then the gas feature vector output by the initial feature extraction layer can be input into the initial problem probability prediction layer. A loss function is constructed through the prediction results of the third label and the initial problem probability prediction layer, and the parameters of the initial feature extraction layer and the problem probability prediction layer are iteratively updated based on the loss function until the loss function converges, the number of iterations reaches a threshold, etc., the training is completed, and a trained problem probability determination model is obtained.

[0240] In some embodiments, the training process of the problem probability determination model may include at least a first stage of training. The first stage of training may sequentially include training based on a first training set, validation based on a first validation set, and testing based on a first test set.

[0241] The first training set refers to a training sample set used to train the initial problem probability determination model. In some embodiments, the processor can use the first training set as the third training sample to perform model training on the initial problem probability determination model to obtain a trained problem probability determination model.

[0242] The first validation set refers to a training sample set used to adjust the hyperparameters of the trained problem probability determination model. Hyperparameters refer to parameters that need to be set manually.

[0243] In some embodiments, the processor can input the first validation set into a trained problem probability determination model with multiple sets of hyperparameter settings, and then determine the quality of the model prediction results based on the problem probabilities with different hyperparameter settings, and determine which set of hyperparameters has the best performance. For example, the more accurate the prediction result, the better the corresponding hyperparameter performance.

[0244] The first test set refers to a training sample set used to verify the performance of the problem probability model after adjusting the hyperparameters. In some embodiments, the processor may input the first test set into the problem probability model after adjusting the hyperparameters to verify the accuracy of the prediction results of the problem probability model after adjusting the hyperparameters. The verification may be to input the training samples in the first test set into the problem probability model after adjusting the hyperparameters, and compare the obtained output with the corresponding label in the first test set. The closer the output is to the corresponding label in the first test set, the more accurate the prediction results of the problem probability model after adjusting the hyperparameters are.

[0245] In some embodiments, the first training set, the first test set, and the first validation set are data sets extracted from historical data and are composed of the project impact degree, project estimated completion time, and gas regulatory personnel arrangement of the gas construction project. The data volume of the first training set, the first test set, and the first validation set constitutes a first preset ratio, and there is no data overlap among the first training set, the first test set, and the first validation set. The sample statistical difference of the first training set is greater than a preset difference threshold, and the preset difference threshold is related to the average construction time of historical gas construction projects.

[0246] The first preset ratio refers to the ratio of the data volume of the first training set, the first test set, and the first validation set. For example, the first preset ratio may be: the data volume of the first training set: the data volume of the first test set: the data volume of the first validation set = 8:1:1.

[0247] Data crossover means that the same training sample can only exist in one of the training set, test set, and validation set.

[0248] The sample statistical difference refers to the diversity between the training samples in the first training set. In some embodiments, the greater the diversity between the training samples in the first training set, the greater the sample statistical difference.

[0249] In some embodiments, the processor can quantify the "project impact level", "project estimated completion time" and "gas regulatory personnel arrangement" of the historical sample gas construction projects of each training sample in the first training set into numbers, that is, each training sample corresponds to a digital vector; calculate the vector distance (for example, cosine distance) between each pair of training samples in the first training set; calculate the variance of the multiple vector distances obtained; and determine the sample statistical difference based on the variance, for example, the larger the variance, the greater the sample statistical difference.

[0250] In some embodiments, the processor may quantize each training sample in the first training set into a number through a sixth preset comparison table based on the first training set. The sixth preset comparison table includes a correspondence between reference training samples and reference quantization numbers corresponding to the reference training samples. The sixth preset comparison table may be constructed based on prior knowledge or historical data. For example, if an element of a training sample is a number itself, then the quantization number of the element may be directly equal to the number of the element itself.

[0251] The preset difference threshold refers to a preset critical value of the sample statistical difference. In some embodiments, the preset difference threshold is related to the average construction time of historical gas construction projects.

[0252] In some embodiments, the processor can obtain the construction duration of multiple historical gas construction projects through the government supervision and management platform, and then calculate the average construction duration of the multiple historical gas construction projects to obtain the average construction duration of the historical gas construction projects.

[0253] In some embodiments, the longer the average construction time of historical gas construction projects, the larger the preset difference threshold.

[0254] In some embodiments of the present specification, by using a problem probability determination model to evaluate the potential problem probability of the area where the gas construction project is located, it is possible to quickly prepare to evaluate the potential problem probability of the area where the gas construction project is located.

[0255] At the same time, during the training process of the problem probability determination model, by introducing sample statistical differences and setting the sample statistical differences of the first training set to be greater than the preset difference threshold, the problem probability determination model obtained through training is made more robust, thus preventing the problem probability determination model obtained through training from overfitting.

[0256] In addition, the preset difference threshold is related to the average construction time of historical gas construction projects. When the average construction time is longer, it means that the construction situation is usually more complicated and involves more potential impacts. Therefore, the preset difference threshold can be increased to allow the problem probability determination model to learn from a wider distribution of training samples, thereby improving the accuracy of the problem probability determination model prediction obtained by training.

[0257] The basic concepts have been described above. Obviously, for those skilled in the art, the above detailed disclosure is only for example and does not constitute a limitation of this specification. Although not explicitly stated here, those skilled in the art may make various modifications, improvements and corrections to this specification. Such modifications, improvements and corrections are suggested in this specification, so such modifications, improvements and corrections still belong to the spirit and scope of the exemplary embodiments of this specification.

[0258] At the same time, this specification uses specific words to describe the embodiments of this specification. For example, "one embodiment", "an embodiment", and / or "some embodiments" refer to a certain feature, structure or characteristic related to at least one embodiment of this specification. Therefore, it should be emphasized and noted that "one embodiment" or "an embodiment" or "an alternative embodiment" mentioned twice or more in different positions in this specification does not necessarily refer to the same embodiment. In addition, certain features, structures or characteristics in one or more embodiments of this specification can be appropriately combined.

[0259] In addition, unless explicitly stated in the claims, the order of the processing elements and sequences described in this specification, the use of alphanumeric characters, or the use of other names are not intended to limit the order of the processes and methods of this specification. Although the above disclosure discusses some invention embodiments that are currently considered useful through various examples, it should be understood that such details are only for illustrative purposes, and the attached claims are not limited to the disclosed embodiments. On the contrary, the claims are intended to cover all modifications and equivalent combinations that are consistent with the essence and scope of the embodiments of this specification. For example, although the system components described above can be implemented by hardware devices, they can also be implemented only by software solutions, such as installing the described system on an existing server or mobile device.

[0260] Similarly, it should be noted that in order to simplify the description disclosed in this specification and thus help understand one or more embodiments of the invention, in the above description of the embodiments of this specification, multiple features are sometimes combined into one embodiment, figure or description thereof. However, this disclosure method does not mean that the features required by the subject matter of this specification are more than the features mentioned in the claims. In fact, the features of the embodiments are less than all the features of the single embodiment disclosed above.

[0261] In some embodiments, numbers describing the number of components and attributes are used. It should be understood that such numbers used in the description of the embodiments are modified by the modifiers "about", "approximately" or "substantially" in some examples. Unless otherwise specified, "about", "approximately" or "substantially" indicate that the numbers are allowed to vary by ±20%. Accordingly, in some embodiments, the numerical parameters used in the specification and claims are approximate values, which may change according to the required features of individual embodiments. In some embodiments, the numerical parameters should take into account the specified significant digits and adopt the general method of retaining the digits. Although the numerical domains and parameters used to confirm the breadth of the range in some embodiments of this specification are approximate values, in specific embodiments, the setting of such numerical values ​​is as accurate as possible within the feasible range.

[0262] Each patent, patent application, patent application publication, and other materials, such as articles, books, specifications, publications, documents, etc., cited in this specification is hereby incorporated by reference in its entirety. Except for application history documents that are inconsistent with or conflicting with the contents of this specification, documents that limit the broadest scope of the claims of this specification (currently or later attached to this specification) are also excluded. It should be noted that if the descriptions, definitions, and / or use of terms in the materials attached to this specification are inconsistent or conflicting with the contents described in this specification, the descriptions, definitions, and / or use of terms in this specification shall prevail.

[0263] Finally, it should be understood that the embodiments described in this specification are only used to illustrate the principles of the embodiments of this specification. Other variations may also fall within the scope of this specification. Therefore, as an example and not a limitation, alternative configurations of the embodiments of this specification may be considered consistent with the teachings of this specification. Accordingly, the embodiments of this specification are not limited to the embodiments explicitly introduced and described in this specification.

Claims

1. A smart gas construction supervision method, characterized in that: The method is executed based on a processor of a government supervision management platform of a smart gas construction supervision Internet of Things system, and the method includes: Obtain monitoring image data of the construction area where the gas construction project is located from the gas monitoring device; Based on the monitoring image data, determine the project impact degree and the estimated project completion time of the gas construction project, and send the project impact degree to the gas company management platform, and send the estimated project completion time to the citizen user platform for announcement and display; wherein, the project impact degree is also related to the current monitoring result of the gas construction project by the gas supervision personnel and the progress of the previous monitoring project, and the current monitoring result and the progress of the previous monitoring project are obtained from the government supervision service platform; the determination of the project impact degree and the estimated project completion time of the gas construction project based on the monitoring image data includes: Determine the project information of the gas construction project based on the monitoring image data, the current monitoring result and the progress of the last monitoring project; Determining the estimated project completion time of the gas construction project based on the project information; and Determine the project impact of the gas construction project based on the project information, the results of this inspection and the estimated completion time of the project; Based on the project impact and the estimated completion time of the project, the regulatory parameters are determined, and the regulatory parameters are sent to the gas equipment object platform via the gas company management platform and the gas company sensor network platform, the gas equipment object platform includes a gas pressure regulating device, and the regulatory parameters include at least one set of pressure regulating parameters of the gas pipeline; wherein the pressure regulating parameters are also related to the arrangement of gas regulatory personnel, and the arrangement of gas regulatory personnel is obtained based on the government regulatory management platform; the regulatory parameters determined based on the project impact and the estimated completion time of the project include: Determining the pressure regulating parameters of the at least one group of gas pipelines based on the impact degree of the project, the estimated completion time of the project and the arrangement of the gas regulatory personnel; Obtaining the pipeline pressure of the at least one group of gas pipelines from the gas pressure regulating device; Based on the pipeline pressure, calculating a fluctuation characteristic or a pressure difference distribution characteristic; and Based on the supervision parameters, and the fluctuation characteristics or the pressure difference distribution characteristics, a pressure regulation instruction is generated, and the pressure regulation instruction is sent to the corresponding gas pressure regulating device. The gas pressure regulating device regulates the pressure of the at least one group of gas pipelines based on the pressure regulation instruction.

2. The method according to claim 1, characterized in that The smart gas construction supervision Internet of Things system also includes the citizen user platform, the government supervision service platform, the government supervision sensor network platform, the government supervision object platform, the gas company sensor network platform, the gas equipment object platform, the gas user service platform and the gas user platform; The government supervision service platform includes a government security supervision service platform; The government supervision and management platform includes a government security supervision and management platform; The government supervision sensor network platform includes a government security supervision sensor network platform; The government supervision object platform includes the gas company management platform; The citizen user platform is configured to obtain user evaluation information and send it to the government supervision service platform, and receive project information and estimated completion time of the project uploaded by the government supervision service platform; The government supervision service platform is configured to interact with the citizen user platform and the government security supervision management platform; The government supervision management platform is configured to interact with the government security supervision service platform and the government security supervision sensor network platform; The government regulatory sensor network platform is configured to interact with the gas company management platform and the government safety regulatory management platform; The government supervision object platform is configured to interact with the gas company sensor network platform, the government safety supervision sensor network platform and the gas user service platform; The gas equipment object platform is configured to interact with the gas company sensor network platform; The gas user platform is configured to interact with the gas user service platform.

3. The method according to claim 2, characterized in that The gas equipment object platform includes a gas supervision device, the government supervision management platform includes the processor and the communication device, and the processor is located on the user terminal; The gas monitoring device is configured to collect monitoring image data of the construction area where the gas construction project is located; The communication device is configured for communication between the gas monitoring apparatus and the processor.

4. The method according to claim 1, characterized in that: The regulatory parameters also include the adjusted arrangement of gas regulatory personnel; the regulatory parameters determined based on the project impact and the estimated completion time of the project also include: Based on the impact of the project and the estimated completion time of the project, the adjusted arrangement of the gas regulatory personnel is determined.

5. A smart gas construction supervision Internet of Things system, characterized in that: Including citizen user platform, government supervision service platform, government supervision management platform, government supervision sensor network platform, government supervision object platform, gas company sensor network platform, gas equipment object platform, gas user service platform and gas user platform; The government supervision service platform includes a government security supervision service platform; The government supervision and management platform includes a government security supervision and management platform; The government supervision sensor network platform includes a government security supervision sensor network platform; The government supervision object platform includes the gas company management platform; The citizen user platform obtains user evaluation information and sends it to the government supervision service platform, and receives project information and estimated completion time of the project uploaded by the government supervision service platform; The government supervision service platform is configured to interact with the citizen user platform and the government security supervision management platform; The government supervision management platform is configured to interact with the government security supervision service platform and the government security supervision sensor network platform; The government supervision sensor network platform is configured to interact with the gas company management platform, the government safety supervision management platform and the gas user service platform; The government supervision object platform is configured to interact with the gas company sensor network platform, the government safety supervision sensor network platform and the gas user service platform; The gas equipment object platform is configured to interact with the gas company sensor network platform; The gas user platform is configured to interact with the gas user service platform; The gas equipment object platform includes a gas monitoring device, a processor, a communication device and a user terminal, and the processor is located on the user terminal; The gas monitoring device is configured to collect monitoring image data of the construction area where the gas construction project is located; The communication device is configured for communication between the gas monitoring device and the processor; The processor is configured to: Acquire the monitoring image data from the gas monitoring device and upload it to the gas company management platform through the communication device; Based on the monitoring image data, determine the project impact degree and the estimated project completion time of the gas construction project, and send the project impact degree to the gas company management platform, and send the project estimated completion time to the citizen user platform for announcement and display; wherein, the project impact degree is also related to the current monitoring result of the gas construction project by the gas supervision personnel and the progress of the previous monitoring project, and the current monitoring result and the progress of the previous monitoring project are obtained from the government supervision service platform; the determination of the project impact degree and the estimated project completion time of the gas construction project based on the monitoring image data includes: Determine the project information of the gas construction project based on the monitoring image data, the current monitoring result and the progress of the last monitoring project; Determining the estimated project completion time of the gas construction project based on the project information; and Determine the project impact of the gas construction project based on the project information, the results of this inspection and the estimated completion time of the project; Based on the project impact and the estimated completion time of the project, the regulatory parameters are determined, and the regulatory parameters are sent to the gas equipment object platform via the gas company management platform and the gas company sensor network platform, the gas equipment object platform includes a gas pressure regulating device, and the regulatory parameters include at least one set of pressure regulating parameters of the gas pipeline; wherein the pressure regulating parameters are also related to the arrangement of gas regulatory personnel, and the arrangement of gas regulatory personnel is obtained based on the government regulatory management platform; the regulatory parameters determined based on the project impact and the estimated completion time of the project include: Determining the pressure regulating parameters of the at least one group of gas pipelines based on the impact degree of the project, the estimated completion time of the project and the arrangement of the gas regulatory personnel; Obtaining pipeline pressure of at least one group of gas pipelines from the gas pressure regulating device; Based on the pipeline pressure, calculating a fluctuation characteristic or a pressure difference distribution characteristic; and Based on the supervision parameters, and the fluctuation characteristics or the pressure difference distribution characteristics, a pressure regulation instruction is generated, and the pressure regulation instruction is sent to the corresponding gas pressure regulating device. The gas pressure regulating device regulates the pressure of the at least one group of gas pipelines based on the pressure regulation instruction.

6. A computer-readable storage medium, characterized in that: The storage medium stores computer instructions. When the computer reads the computer instructions in the storage medium, the computer executes the smart gas construction supervision method as described in any one of claims 1-4.