A smart gas pipeline network construction monitoring method and Internet of Things system
Through the smart gas pipeline construction monitoring method and the Internet of Things system, combined with construction information, environmental data and gas use data, transportation and gas supply regulation instructions are generated, which solves the problems of low construction efficiency and unstable supply in traditional gas pipeline management. It achieves smooth construction, stable gas supply and safe effects.
Patent Information
- Application Number
- CN202411114079.0
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-14
- Publication Date
- 2024-11-05
- Estimated Expiration
- 2044-08-14
AI Technical Summary
Traditional gas pipeline management lacks the judgment of potential construction factors and the consideration of the impact of gas supply, resulting in inefficient construction and unstable gas supply.
Using smart gas pipeline construction monitoring methods and Internet of Things system, by obtaining construction information, environmental data and gas usage data, generating material transportation and gas supply regulation instructions, controlling transportation equipment and gas supply parameters, adjusting monitoring parameters and data storage partitions, Optimize resource allocation and processing priorities.
Ensure the smooth progress of construction, ensure normal use of gas users, reduce gas safety risks, promptly discover and solve construction problems, avoid data loss, and improve data processing efficiency.
Smart Images

Figure CN118627765B_ABST
Abstract
Description
Technical Field
[0001] This specification relates to the field of gas pipeline network operation, and in particular to a smart gas pipeline network construction monitoring method and an Internet of Things system. Background Art
[0002] With the accelerated development of urbanization, gas, as an indispensable energy source in urban life and industrial production, is often not as well-prepared as expected during the construction of gas pipelines due to the influence of traffic, material allocation, weather, etc. The construction of gas pipelines also affects traffic and gas supply.
[0003] In traditional gas pipeline network management, there is often a lack of judgment on potential factors that affect construction, and the impact of gas pipeline construction on gas supply is not considered, which may lead to low construction efficiency and even affect the stability of gas supply.
[0004] In view of this, it is desired to provide a smart gas pipeline network construction monitoring method and an Internet of Things system to better monitor the gas pipeline network construction. Summary of the invention
[0005] In order to better monitor the construction of gas pipeline networks, it is hoped to provide a smart gas pipeline network construction monitoring method and an Internet of Things system.
[0006] The invention content includes a smart gas pipeline construction monitoring method, which is executed by a smart gas government supervision management platform of a smart gas pipeline construction monitoring Internet of Things system, including: obtaining the update status of construction information corresponding to the construction pipeline in the construction supervision area, and in response to the update of the construction information, obtaining supervision data for the construction supervision area; storing the supervision data in a government supervision comprehensive database of the smart gas government supervision management platform according to preset rules, and the government supervision comprehensive database is configured as a memory; wherein the supervision data includes the construction information, the environmental data of the construction supervision area, and the gas usage data corresponding to the pipeline to be constructed in the construction supervision area; determining the construction status of the construction pipeline; in response to the construction status meeting the first condition: generating a material transportation instruction for the construction pipeline based on the construction information and the environmental data; sending the material transportation instruction to the transportation equipment to control the transportation equipment to follow The material transportation parameters transport materials; in response to the construction status meeting the second condition: based on at least one of the construction information, the environmental data, and the gas usage data, generate a gas supply adjustment instruction for the construction supervision area; send the gas supply adjustment instruction to the smart gas equipment object platform corresponding to the construction supervision area to control the gas supply parameters of the construction supervision area; obtain the first update frequency corresponding to the material transportation instruction and the second update frequency corresponding to the gas supply adjustment instruction from the government supervision comprehensive database; based on the first update frequency and the second update frequency, adjust the current monitoring parameters of the smart gas equipment object platform; based on the adjusted monitoring parameters, allocate the storage partition size occupied by the supervision data and the gas safety data in the government supervision comprehensive database; and determine the processor of the smart gas government supervision management platform to calculate the priority of resource allocation when processing different types of data.
[0007] The invention content also includes a smart gas pipeline construction monitoring Internet of Things system, including a smart gas government supervision management platform, a smart gas government supervision sensor network platform, a smart gas government supervision object platform, a smart gas company sensor network platform, and a smart gas equipment object platform; the smart gas government supervision management platform includes a government supervision comprehensive database; the smart gas government supervision object platform includes a smart gas company management platform; the smart gas government supervision management platform is configured to: obtain the update of the construction information corresponding to the construction pipeline in the construction supervision area, and in response to the update of the construction information, obtain the supervision data for the construction supervision area; store the supervision data in the government supervision comprehensive database of the smart gas government supervision management platform according to preset rules, and the government supervision comprehensive database is configured as a memory; wherein the supervision data includes the construction information, the environmental data of the construction supervision area, and the gas usage data corresponding to the pipeline to be constructed in the construction supervision area; determine the construction status of the construction pipeline; in response to the construction status meeting the first condition: based on the construction information , the environmental data, generate material transportation instructions for the construction pipeline; send the material transportation instructions to the transportation equipment to control the transportation equipment to transport materials according to the material transportation parameters; in response to the construction status meeting the second condition: based on the construction information, the environmental data, and at least one of the gas usage data, generate a gas supply adjustment instruction for the construction supervision area; send the gas supply adjustment instruction to the smart gas equipment object platform corresponding to the construction supervision area to control the gas supply parameters of the construction supervision area; obtain the first update frequency corresponding to the material transportation instruction and the second update frequency corresponding to the gas supply adjustment instruction from the government supervision comprehensive database; adjust the current monitoring parameters of the smart gas equipment object platform based on the first update frequency and the second update frequency; allocate the storage partition size occupied by the supervision data and the gas safety data in the government supervision comprehensive database based on the adjusted monitoring parameters; and determine the priority of computing resource allocation when the processor of the smart gas government supervision management platform processes different types of data.
[0008] Through the above method and the Internet of Things system, when the construction pipeline is in the waiting stage, the transportation equipment is controlled to transport materials on time to ensure the smooth progress of the construction; when the construction pipeline is in the construction stage, other gas supply equipment is controlled to replace the construction pipeline for gas supply, which can ensure the normal gas use of gas users and reduce gas safety risks; by adjusting the monitoring parameters, problems arising in the construction process can be discovered and solved in time; the storage partition size of different types of data is adjusted based on the monitoring parameters to avoid data loss caused by the amount of data exceeding the storage space; different types of data are processed according to priority, which enables the processor to process the data in time before the data is overwritten. BRIEF DESCRIPTION OF THE DRAWINGS
[0009] This specification will be further described in the form of exemplary embodiments, which will be described in detail by the accompanying drawings. These embodiments are not restrictive, and in these embodiments, the same number represents the same structure, wherein:
[0010] Figure 1 It is a schematic diagram of the platform structure of the smart gas network construction monitoring Internet of Things system shown in some embodiments of this specification;
[0011] Figure 2 is an exemplary flow chart of a smart gas network construction monitoring method according to some embodiments of this specification;
[0012] Figure 3 is a schematic diagram of determining material transportation instructions according to some embodiments of the present specification;
[0013] Figure 4 is a schematic diagram of determining and updating a construction plan according to some embodiments of this specification;
[0014] Figure 5 It is a schematic diagram of determining gas supply adjustment instructions according to some embodiments of this specification.
[0015] Explanation of the reference numerals: 100-smart gas network construction monitoring IoT system; 110-smart gas government supervision management platform; 111-government supervision comprehensive database; 120-smart gas government supervision sensor network platform; 130-smart gas government supervision object platform; 131-smart gas company management platform; 140-smart gas company sensor network platform; 150-smart gas equipment object platform; 160-smart gas company service platform; 170-gas user platform; 310-construction information; 311-construction Time; 312-safety risk node; 320-environmental data; 321-people flow data; 322-vehicle flow data; 330-traffic impact risk; 340-material transportation instructions; 410-construction pipeline network map; 420-construction adjustment model; 430-update construction plan; 510-gas usage data; 520-gas construction risk; 521-gas supply loss risk; 522-safety loss risk; 530-safety risk vector; 540-second risk control condition; 550-emergency gas supply parameters; 560-gas supply adjustment instructions. DETAILED DESCRIPTION
[0016] In order to more clearly illustrate the technical solutions of the embodiments of this specification, the following is a brief introduction to the drawings required for the description of the embodiments. Obviously, the drawings described below are only some examples or embodiments of this specification. For ordinary technicians in this field, this specification can also be applied to other similar scenarios based on these drawings without creative work. Unless it is obvious from the language environment or otherwise explained, the same reference numerals in the figures represent the same structure or operation.
[0017] It should be understood that the "system", "device", "unit" and / or "module" used herein are a method for distinguishing different components, elements, parts, portions or assemblies at different levels. However, if other words can achieve the same purpose, the words can be replaced by other expressions.
[0018] Unless the context clearly indicates an exception, the words "a", "an", "an" and / or "the" do not refer to the singular and may also include the plural. Generally speaking, the terms "include" and "comprise" only indicate the inclusion of the steps and elements that have been clearly identified, and these steps and elements do not constitute an exclusive list. The method or device may also include other steps or elements.
[0019] Flowcharts are used in this specification to illustrate the operations performed by the system according to the embodiments of this specification. It should be understood that the preceding or following operations are not necessarily performed precisely in order. Instead, the steps may be processed in reverse order or simultaneously. At the same time, other operations may also be added to these processes, or one or more operations may be removed from these processes.
[0020] Figure 1 This is a schematic diagram of the platform structure of the smart gas network construction monitoring Internet of Things system shown in some embodiments of this specification. The smart gas network construction monitoring Internet of Things system involved in the embodiments of this specification will be described in detail below. It should be noted that the following embodiments are only used to explain this specification and do not constitute a limitation on this specification.
[0021] In some embodiments, Figure 1 As shown, the smart gas pipeline construction monitoring Internet of Things system 100 includes a smart gas government supervision management platform 110, a smart gas government supervision sensor network platform 120, a smart gas government supervision object platform 130, a smart gas company sensor network platform 140, and a smart gas equipment object platform 150 which interact in sequence.
[0022] The smart gas government supervision and management platform 110 is a platform for government departments to supervise the gas pipeline network. The supervision content includes but is not limited to gas pipeline construction, etc. The government department can be the superior administrative department of the gas operation entity (such as the Housing and Urban-Rural Development Bureau), etc.
[0023] In some embodiments, the smart gas government supervision management platform 110 can exchange data with the smart gas government supervision sensor network platform 120. For example, the smart gas government supervision management platform 110 can obtain environmental data of the construction supervision area through the smart gas government supervision sensor network platform 120.
[0024] In some embodiments, the smart gas government regulatory management platform 110 may include a government regulatory comprehensive database 111 .
[0025] The government supervision integrated database 111 can be used to store and manage various data generated in the process of government users supervising the gas pipeline network. For example, information related to gas pipeline construction. In some embodiments, the government supervision integrated database 111 can be configured as a storage device for storing data related to gas pipeline construction. For example, construction information, environmental data of the construction supervision area, etc. In some embodiments, the government supervision integrated database 111 is only open to government users.
[0026] In some embodiments, the smart gas government supervision management platform 110 may also include a processor. The processor is used to process data related to the smart gas pipeline network construction monitoring Internet of Things system 100. In some embodiments, the processor can be configured to: obtain the update of the construction information corresponding to the construction pipeline in the construction supervision area, and in response to the update of the construction information, obtain the supervision data for the construction supervision area; store the supervision data in the government supervision comprehensive database of the smart gas government supervision management platform according to preset rules; determine the construction status of the construction pipeline; in response to the construction status meeting the first condition, based on the construction information and environmental data, generate material transportation instructions for the construction pipeline, and send the material transportation instructions to the transportation equipment to control the transportation equipment to transport materials according to the material transportation parameters; in response to the construction status meeting the second condition, based on the construction information, environmental data, gas usage At least one item in the data generates a gas supply adjustment instruction for the construction supervision area, and sends the gas supply adjustment instruction to the smart gas equipment object platform corresponding to the construction supervision area to control the gas supply parameters of the construction supervision area; obtains the first update frequency corresponding to the material transportation instruction and the second update frequency corresponding to the gas supply adjustment instruction from the government supervision comprehensive database; adjusts the current monitoring parameters of the smart gas equipment object platform based on the first update frequency and the second update frequency; allocates the storage partition size occupied by the supervision data and gas safety data in the government supervision comprehensive database based on the adjusted monitoring parameters; determines the priority of computing resource allocation when the processor processes different types of data.
[0027] The smart gas government supervision sensor network platform 120 may be a functional platform for managing sensor communication. In some embodiments, the smart gas government supervision sensor network platform 120 may realize the functions of sensing information sensor communication and controlling information sensor communication.
[0028] In some embodiments, the smart gas government regulatory sensor network platform 120 can be used to interact with the smart gas government regulatory management platform 110 and the smart gas company management platform 131.
[0029] The smart gas government regulatory object platform 130 can be a functional platform for generating government regulatory information and controlling the execution of information.
[0030] In some embodiments, the smart gas government regulatory object platform 130 may include a smart gas company management platform 131 .
[0031] The smart gas company management platform 131 is a platform for gas companies to manage gas pipeline networks. In some embodiments, each gas company corresponds to a smart gas company management platform 131.
[0032] In some embodiments, the smart gas company management platform 131 may interact with the smart gas government supervision sensor network platform 120 and the smart gas company sensor network platform 140. For example, the smart gas company management platform 131 may obtain material transportation instructions based on the smart gas government supervision sensor network platform 120; the smart gas company management platform 131 may also obtain gas usage data based on the smart gas company sensor network platform 140.
[0033] In some embodiments, the smart gas company management platform 131 includes a smart gas data center.
[0034] The smart gas data center can be used to store and manage information related to gas pipeline construction. In some embodiments, the smart gas data center can be configured as a storage device for storing data related to gas pipeline construction, such as regulatory data, gas safety data, etc.
[0035] The smart gas company sensor network platform 140 may be a functional platform for managing sensor communication. In some embodiments, the smart gas company sensor network platform 140 may implement the functions of sensing information sensor communication and controlling information sensor communication.
[0036] In some embodiments, the smart gas company sensor network platform 140 can be used to interact with the smart gas company management platform 131 and the smart gas equipment object platform 150 .
[0037] The smart gas equipment object platform 150 can be configured as various types of gas pipe network equipment and monitoring equipment. For example, the gas pipe network equipment may include outdoor gas pipelines, valve control equipment, gas storage tanks, pressure regulating equipment, gas meters, indoor gas pipelines, etc.; monitoring equipment may include gas flow meters, pressure sensors, temperature sensors, etc.
[0038] In some embodiments, the smart gas pipeline construction monitoring IoT system 100 may also include a smart gas company service platform 160 and a gas user platform 170 .
[0039] The smart gas company service platform 160 may be a platform for communicating gas users' needs and control information.
[0040] The gas user platform 170 may be a platform for interacting with gas users. In some embodiments, the gas user platform 170 may be configured as a terminal device.
[0041] Some embodiments of this specification are based on the smart gas pipeline network construction monitoring Internet of Things system 100, in which various functional platforms coordinate and operate regularly to form an information operation closed loop, thereby realizing the informatization and intelligence of smart gas pipeline network construction supervision.
[0042] It should be noted that the above description of the smart gas pipeline construction monitoring Internet of Things system 100 and its modules is for convenience of description only and does not limit this specification to the scope of the embodiments cited.
[0043] Figure 2 is an exemplary flow chart of a smart gas network construction monitoring method according to some embodiments of this specification. Figure 2 As shown, the process 200 includes the following steps. In some embodiments, the process 200 can be executed by a processor of the smart gas government supervision management platform 110.
[0044] Step 210: Obtain supervision data for the construction supervision area.
[0045] In some embodiments, the processor may obtain update status of construction information corresponding to the construction pipeline in the construction supervision area, and obtain supervision data for the construction supervision area in response to updates to the construction information.
[0046] The construction supervision area refers to the area where gas pipeline construction is supervised by the smart gas government supervision and management platform.
[0047] In some embodiments, the construction supervision area can be determined in a variety of ways. For example, the processor can divide the construction supervision area based on administrative divisions. For another example, each gas company can correspond to a smart gas company management platform. The smart gas company management platform can obtain the construction status of the gas pipelines that the company is responsible for, and upload it to the smart gas government supervision management platform through the smart gas government supervision sensor network platform. The processor can divide the construction supervision area based on the construction status of the gas pipelines that each gas company is responsible for.
[0048] Construction information refers to information related to the construction of the construction pipeline. For example, the construction information may include the construction pipeline code, location, construction quantity (such as the length of the construction pipeline, etc.), construction plan, construction progress, etc.
[0049] In some embodiments, the processor may obtain construction information of the construction pipeline by accessing a government regulatory comprehensive database.
[0050] In some embodiments, due to policy adjustments or unexpected situations during construction, the gas company needs to adjust the construction information and upload the adjusted construction information to the government supervision comprehensive database to update the construction information. The construction information update may include construction plan update, construction progress update, etc.
[0051] In some embodiments, the processor may determine whether the construction information is updated based on the reading and writing status of the construction information related data in the government supervision integrated database.
[0052] In some embodiments, when the construction information is updated, the pipeline network construction monitoring also needs to be updated synchronously to meet the supervision requirements of the latest construction status of the construction pipeline.
[0053] Supervision data refers to data obtained by supervising the gas pipelines in the construction supervision area. In some embodiments, the supervision data includes construction information, environmental data of the construction supervision area, and gas usage data corresponding to the gas pipelines in the construction supervision area.
[0054] Environmental data refers to data related to the environment around the construction pipeline, such as weather data, vehicle flow data, and human flow data around the construction pipeline. In some embodiments, the processor can obtain vehicle flow data and human flow data around the construction pipeline through monitoring equipment in the construction supervision area, and obtain weather data around the construction pipeline by communicating with a weather station.
[0055] The gas usage data refers to the gas usage data of the gas pipeline at different time periods. For example, the gas usage data includes the gas usage time period, gas usage, etc. In some embodiments, the processor can obtain the gas usage data corresponding to the gas pipeline through a gas flow meter.
[0056] Step 220: store the supervision data according to preset rules.
[0057] In some embodiments, the processor may store the regulatory data in the government regulatory comprehensive database of the smart gas government regulatory management platform according to preset rules.
[0058] In some embodiments, in order to facilitate the management of regulatory data, the regulatory data needs to be stored in the government regulatory comprehensive database according to preset rules. For example, the processor can store the regulatory data in the government regulatory comprehensive database in chronological order.
[0059] Step 230, determining the construction status of the construction pipeline.
[0060] The construction status refers to the construction stage of the construction pipeline. In some embodiments, the construction status can be divided into the waiting stage and the construction stage. The construction stage can be further subdivided into the current process stage, for example, trench excavation, pipeline installation welding, trench backfilling and other process stages.
[0061] In some embodiments, the processor may read the current construction progress and determine the construction status of the construction pipeline based on the current construction information of the construction pipeline.
[0062] Step 241, in response to the construction status meeting the first condition, generating a material transportation instruction for the construction pipeline based on the construction information and environmental data.
[0063] The first condition is that the construction pipeline is in the waiting stage. In the waiting stage, the staff needs to transport the relevant materials to the designated location in advance. In order to ensure the smooth construction of the construction pipeline, it is necessary to set a suitable material transportation period. Transporting materials too early may cause problems such as material storage, site occupation, and traffic obstruction; transporting materials too late will delay the construction progress.
[0064] The material transportation instruction refers to an instruction for adjusting the material transportation. In some embodiments, the material transportation instruction may include a transportation period, a material transportation amount, etc. For example, the material transportation instruction may be: transport 5 tons of stone to a designated location at 4 am tomorrow.
[0065] In some embodiments, the processor may determine the material transportation instructions based on the construction information of the construction pipeline. For example, the processor may select a period when the environmental data meets the transportation requirements as the transportation period based on the construction plan of the construction pipeline and the material transportation distance; calculate the material transportation volume based on the construction volume of the construction pipeline; and generate the material transportation instructions based on the transportation period and the material transportation volume. The environmental data meeting the transportation requirements may include: the weather data does not affect the transportation, and the vehicle flow data and the pedestrian flow data are less than the preset threshold.
[0066] In some embodiments, the processor may determine the material transportation volume based on the product of the construction volume of the construction pipeline and a preset coefficient, wherein the preset coefficient is a value not less than 1 and may be determined based on historical experience or actual construction needs.
[0067] In some embodiments, the processor may also determine material transportation instructions based on the traffic impact risk of the construction pipeline. For more information on traffic impact risk, see Figure 3 And related instructions.
[0068] Step 242, sending the material transportation instruction to the transportation equipment to control the transportation equipment to transport the material according to the material transportation parameters.
[0069] Transportation equipment refers to equipment that transports materials to a designated location, such as trucks, railway trucks, cargo ships, air transport equipment, and pipeline equipment.
[0070] Material transportation parameters refer to parameters related to the transportation of materials by transportation equipment. For example, material transportation parameters may include material transportation period, material transportation volume, etc.
[0071] In some embodiments, the smart gas government supervision management platform can send the material transportation instruction to the smart gas company management platform through the smart gas government supervision sensor network platform. The smart gas company management platform then sends the material transportation instruction to the transportation equipment in the smart gas equipment object platform through the smart gas company sensor network platform to control the transportation equipment to transport materials according to the material transportation parameters.
[0072] Step 243, in response to the construction status meeting the second condition, generating a gas supply adjustment instruction for the construction supervision area based on at least one of the construction information, environmental data, and gas usage data.
[0073] The second condition refers to the construction pipeline being in the construction stage. Construction of the construction pipeline cannot be stopped after it starts. During the construction process, there may be risks such as gas outage and gas safety, which can only be reduced by adjusting the gas supply parameters. For example, the processor can adjust the gas supply parameters to allow other gas supply equipment to replace the construction pipeline to supply gas, thereby reducing the risk of gas outage; by adjusting the gas pressure and gas flow of the gas supply equipment, the gas safety risk can be reduced.
[0074] Gas supply adjustment instructions refer to instructions for adjusting parameters of different gas supply equipment in the gas pipeline network. In some embodiments, the gas supply adjustment instructions may include alternative gas supply equipment, alternative gas supply period, gas supply pressure, gas supply flow, etc. Among them, alternative gas supply equipment refers to equipment that replaces the construction pipeline to supply gas to gas users, such as gas pipelines, gas stations, etc. The alternative gas supply period refers to the period when the alternative gas supply equipment replaces the construction pipeline to supply gas to gas users.
[0075] In some embodiments, the processor can use the gas supply equipment that is connected to the affected gas users and can supply gas to the affected gas users as the alternative gas supply equipment based on the pipeline network information (including pipeline network connection information, station gas supply information, etc.). When the construction pipeline cannot supply gas to the gas users during construction, the processor can use the construction period in the construction plan as the alternative gas supply period based on the construction information of the construction pipeline; and generate a gas supply adjustment instruction for controlling the alternative gas supply equipment to perform alternative gas supply through at least one alternative gas supply equipment during the alternative gas supply period.
[0076] In some embodiments, the processor may also estimate the demand for alternative gas supply during the construction period based on the gas usage data of the construction pipeline in multiple periods of historical time; determine the gas supply flow and pressure of the alternative gas supply equipment based on the alternative gas supply demand during the construction period, thereby determining the gas supply adjustment instruction. Among them, the alternative gas supply demand refers to the demand related to the gas supply of the alternative gas supply equipment to the gas user. In some embodiments, the higher the alternative gas supply demand, the greater the gas supply flow and pressure of the alternative gas supply equipment.
[0077] In some embodiments, the processor may also determine a gas supply adjustment instruction based on the gas construction risk. For more information about gas construction risks, see Figure 5 and related descriptions.
[0078] Step 244, sending the gas supply adjustment instruction to the smart gas equipment object platform corresponding to the construction supervision area to control the gas supply parameters of the construction supervision area.
[0079] Gas supply parameters refer to parameters related to the gas supply of gas supply equipment in the construction supervision area, such as gas supply flow rate, gas pressure, etc.
[0080] In some embodiments, the smart gas government supervision management platform can send gas supply adjustment instructions to the smart gas company management platform through the smart gas government supervision sensor network platform. The smart gas company management platform then sends material transportation instructions to the gas supply equipment in the smart gas equipment object platform through the smart gas company sensor network platform to control the gas supply parameters in the construction supervision area.
[0081] Step 250, obtaining a first update frequency corresponding to the material transportation instruction and a second update frequency corresponding to the gas supply regulation instruction from the government regulatory integrated database.
[0082] The first update frequency refers to the frequency of updating the material transportation instructions, for example, the update frequency of the material transportation instructions corresponding to at least one construction pipeline in the construction supervision area.
[0083] The second update frequency refers to the frequency of updating the gas supply adjustment instruction, for example, the frequency of adjusting one or more gas supply equipment parameters in the construction supervision area.
[0084] In some embodiments, the processor can obtain the material transportation instructions received by a construction pipeline within a period of time through the government supervision comprehensive database, and calculate the number of material transportation instructions received by the construction pipeline per unit time as the second update frequency corresponding to the construction pipeline. The second update frequency is determined in a similar manner to the first update frequency.
[0085] Step 260: Adjust the current monitoring parameters of the smart gas equipment object platform based on the first update frequency and the second update frequency.
[0086] The monitoring parameter refers to the frequency at which the monitoring device monitors to obtain relevant data. In some embodiments, the monitoring device may include a gas safety monitoring device, a gas usage detection device, a field construction monitoring device, and the like.
[0087] Gas safety monitoring equipment is a device used to obtain gas safety data. For example, gas safety monitoring equipment may include a gas detector, a gas alarm, and the like.
[0088] Gas safety data refers to data that reflects the safety of gas pipelines, such as whether there is a gas leak in the gas pipeline.
[0089] The gas usage detection device is a device for obtaining gas usage data, for example, the gas usage detection device may include a gas meter, a gas pressure sensor, etc. For relevant descriptions of the gas usage data, refer to the relevant description above.
[0090] On-site construction monitoring equipment is equipment used to obtain construction monitoring data. For example, on-site construction monitoring equipment may include cameras, television monitoring systems, and the like.
[0091] Construction monitoring data refers to data obtained by monitoring the construction supervision area. For example, construction monitoring data may include videos and images of the construction site.
[0092] In some embodiments, when the first update frequency is higher than a first preset frequency threshold, the processor may increase monitoring parameters of the on-site construction monitoring equipment to strengthen monitoring of the construction progress and ensure on-time completion. The first preset frequency threshold may be determined based on historical experience.
[0093] When the second update frequency is higher than the second preset frequency threshold, the processor can increase the monitoring parameters of the gas safety monitoring equipment and the gas usage detection equipment to avoid aggravated gas leakage and insufficient gas supply due to frequent updates of the gas supply parameters. The second preset frequency threshold can be determined based on historical experience.
[0094] Step 270, based on the adjusted monitoring parameters, allocate the storage partition size occupied by the regulatory data and gas safety data in the government regulatory comprehensive database.
[0095] In some embodiments, the higher the monitoring parameters of a monitoring device, the more data the monitoring device acquires. In order to avoid data loss caused by the amount of data exceeding the storage space, the processor can allocate a larger storage partition for the data corresponding to the monitoring device with higher monitoring parameters, and allocate a smaller storage partition for the data corresponding to the monitoring device with lower monitoring parameters, thereby achieving rational use of storage space.
[0096] Step 280, determine the priority of computing resource allocation when the processor of the smart gas government supervision and management platform processes different types of data.
[0097] When the processor processes the data of the government supervision comprehensive database, due to the limitation of computing resources, it can only perform limited processing tasks at the same time, such as processing at most 3 types of data at the same time. Therefore, it is necessary to set priorities for different types of data so that the processor can process the data of higher priority types first.
[0098] In some embodiments, the processor can calculate the time when the amount of data reaches the storage partition warning line based on the storage partition size of different types of data, the current memory space occupied, and the data write rate. The earlier the amount of data of a certain type reaches the storage partition warning line, the higher the priority of computing resource allocation for this type of data. In some embodiments, the storage partition warning line can be set manually, for example, the storage partition warning line can be 75% of the storage partition capacity.
[0099] In some embodiments, due to the continuous adjustment of monitoring parameters, the storage partition size and data write rate of different types of data are also constantly changing, and the time when the data volume reaches the storage partition warning line is not fixed. Therefore, the processor needs to dynamically determine the priority of different types of data.
[0100] In some embodiments of the present specification, when a construction pipeline is in the waiting stage, controlling the transportation equipment to transport materials on time can ensure smooth construction; when the construction pipeline is in the construction stage, controlling other gas supply equipment to replace the construction pipeline for gas supply can ensure normal gas use by gas users and reduce gas safety risks; by adjusting monitoring parameters, problems arising during the construction process can be discovered and resolved in a timely manner; adjusting the storage partition size of different types of data based on monitoring parameters can avoid data loss due to the amount of data exceeding the storage space; processing different types of data according to priority can enable the processor to process the data in a timely manner before the data is overwritten.
[0101] It should be noted that the above description of the process 200 is only for example and explanation, and does not limit the scope of application of this specification. For those skilled in the art, various modifications and changes can be made to the process 200 under the guidance of this specification.
[0102] Figure 3 Schematic diagram of determining material transportation instructions according to some embodiments of this specification. Figure 3 As shown, in some embodiments, the smart gas government regulatory management platform 110 can evaluate the traffic impact risk 330 of the construction pipeline based on the construction information 310 and the environmental data 320; and determine the material transportation instructions 340 based on the traffic impact risk 330.
[0103] Traffic impact risk represents the impact of traffic factors on the timeliness of material transportation. In some embodiments, traffic impact risk can be represented by a numerical value, and the larger the number, the higher the traffic impact risk. In some embodiments, traffic impact risk can also be represented by other means, such as no risk, low risk, high risk, etc.
[0104] In some embodiments, the processor can determine the traffic congestion during the material transportation period based on the construction information 310 of the construction pipeline and the environmental data 320 of the construction supervision area. The more serious the traffic congestion, the greater the traffic impact risk 330. For example, a batch of materials needs to be transported to a designated location 3 hours before construction. The processor determines that the traffic congestion 3 to 5 hours before construction is more serious based on the environmental data. The processor can set the traffic impact risk to a higher value (for example, level 2). For more information about construction information and environmental data, see Figure 2 And related instructions.
[0105] In some embodiments, the processor may generate candidate transportation parameters based on the construction information; and determine, through a risk assessment model, the traffic impact risk of the current construction pipeline when transportation is performed based on the candidate transportation parameters.
[0106] Candidate transportation parameters refer to the material transportation parameters provided in advance for selection. They include material transportation period, material transportation volume, transportation configuration, etc. For more information about material transportation parameters, see Figure 2 And related instructions.
[0107] In some embodiments, the candidate transportation parameters may include material transportation parameters that can be selected when transporting materials to the current construction pipeline.
[0108] In some embodiments, the processor may select a time period during which materials can be transported as a material transport time period in the candidate transport parameters according to the construction plan and construction progress in the construction information. For example, the processor may select one or more time periods before the planned construction time as the transport time period in the candidate transport parameters.
[0109] In some embodiments, the processor may determine the material demand as the material transportation quantity in the candidate transportation parameters according to the construction plan in the construction information.
[0110] In some embodiments, the processor may determine the transportation configuration among the candidate transportation parameters according to the currently dispatchable transportation resources (the total number of transportation vehicles, the total number of workers) and the material transportation volume.
[0111] In some embodiments, when the transport configuration is low, it may take multiple round trips to transport the materials. The more times the transport is made, the higher the risk of traffic impact. Therefore, in order to reduce the risk of traffic impact, a higher transport configuration may be selected as much as possible.
[0112] The risk assessment model is a model used to assess the traffic impact risk of the construction pipeline. In some embodiments, the risk assessment model can be a machine learning model, such as a deep neural network model (Deep Neural Network, DNN) and the like.
[0113] The input of the risk assessment model may include candidate transportation parameters, construction information and environmental data. The output of the risk assessment model is the traffic impact risk of the construction pipeline under the candidate transportation parameters.
[0114] In some embodiments, the input of the risk assessment model also includes resource information corresponding to dispatchable transportation resources and demand information corresponding to material transportation demand.
[0115] Dispatched transportation resources refer to resources that can be used for material transportation. For example, dispatchable transportation resources may include transport vehicles, lifting equipment, workers, etc.
[0116] The resource information corresponding to the dispatchable transport resources refers to information related to the dispatchable transport resources, such as the number of idle transport vehicles, the number of idle workers, etc.
[0117] The material transportation demand refers to the requirements that need to be met for material transportation. The demand information corresponding to the material transportation demand refers to information related to the material transportation demand. In some embodiments, the demand information corresponding to the material transportation demand includes information of materials to be transported.
[0118] The information of materials to be transported refers to the relevant information such as the amount of materials to be transported, the transport time, the transport destination, etc. corresponding to the dispatchable transport resources. For example, the information of materials to be transported may include relevant information of a transport task to be transported of a transport team.
[0119] In some embodiments, the processor may train the initial risk assessment model based on a plurality of first training samples with first labels to obtain a risk assessment model. For example, the processor may input the first training sample into the initial risk assessment model, construct a loss function based on the output of the initial risk assessment model and the first label, iteratively update the parameters of the initial risk assessment model based on the loss function, and when the loss function meets the preset conditions, the model training is completed to obtain a trained risk assessment model. The preset conditions may be that the loss function converges, the number of iterations reaches a threshold, etc.
[0120] In some embodiments, the first training sample may include sample transportation parameters, sample construction information, sample environmental data, resource information corresponding to sample dispatchable transportation resources, and demand information corresponding to sample material transportation demand. The first training sample may be obtained based on historical data.
[0121] The first label may include the traffic impact risk corresponding to the first training sample. The first label may be determined based on the actual material delivery time and the specified time corresponding to the first training sample.
[0122] In some embodiments, the later the actual material delivery time is than the specified time, the higher the corresponding traffic impact risk level.
[0123] Some embodiments of this specification determine traffic impact risks by combining resource information corresponding to dispatchable transportation resources and demand information corresponding to material transportation demands, thereby making overall arrangements for the transportation of various materials, making full use of dispatchable transportation resources, and improving material transportation efficiency.
[0124] In some embodiments of this specification, a risk assessment model is used to perform an assessment from multiple aspects to obtain traffic impact risk, which can accurately reflect the pros and cons of different candidate transportation parameters, and help to subsequently determine more appropriate material transportation instructions, making material transportation more timely.
[0125] In some embodiments, the processor may determine the material transportation instructions by querying a first preset table based on the level of traffic impact risk, advancing the material transportation period and improving the transportation configuration. The first preset table includes a correspondence between the level of traffic impact risk and the advance time of the material transportation period and the increment of the transportation configuration, which may be determined based on historical experience.
[0126] In some embodiments, the processor may further determine candidate transportation parameters that meet preset conditions as target transportation parameters; and determine material transportation instructions based on the target transportation parameters.
[0127] The target transportation parameter refers to the material transportation parameter used for actual material transportation. In some embodiments, the processor may determine the candidate transportation parameter with the smallest traffic impact risk as the target transportation parameter.
[0128] In some embodiments of the present specification, by determining the candidate transportation parameters with the lowest traffic impact risk as the target transportation parameters, the risk of material transportation failing to be delivered on time can be minimized to the greatest extent possible, thereby ensuring smooth construction.
[0129] In some embodiments of this specification, material transportation instructions are determined based on traffic impact risks, which can fully consider the impact of traffic factors on material transportation. By selecting transportation parameters with lower risks to transport materials, materials can be allocated more reasonably to avoid slow construction progress due to late transportation.
[0130] Figure 4 Schematic diagram of determining and updating a construction plan according to some embodiments of this specification. Figure 4 As shown, the process 400 of determining an updated construction plan includes the following contents. In some embodiments, determining an updated construction plan may be performed by a smart gas government supervision and management platform.
[0131] In some embodiments, in response to the traffic impact risk not satisfying the first control condition, the smart gas government supervision and management platform can adjust the current construction plan of the construction pipeline based on the traffic impact risk and gas usage data, and determine to update the construction plan.
[0132] The first control condition refers to a condition for determining whether the material transportation can arrive in time. In some embodiments, the traffic impact risk may include whether the material transportation can arrive on time. If the material transportation cannot arrive on time, it indicates that the traffic impact risk does not meet the first control condition.
[0133] In some embodiments, the first control condition may also include that at least one of the traffic impact risks corresponding to the material transportation period in the plurality of candidate transportation parameters is less than a delay risk threshold. For detailed descriptions of the material transportation period, traffic impact risk and delay risk threshold, please refer to this specification. Figure 3 Related description in .
[0134] Updating the construction plan refers to updating the construction plan of at least one construction arrangement in the construction information of the gas pipeline. In some embodiments, updating the construction plan may include updating the project and the updated information of the project.
[0135] In some embodiments, the smart gas government regulatory management platform can determine and update the construction plan through various methods based on traffic impact risks and gas usage data.
[0136] In some embodiments, in response to the traffic impact risk not satisfying the first risk control condition, the smart gas government supervision and management platform can determine multiple alternative time periods in which gas usage is less than a preset value based on historical gas usage data; evaluate the traffic impact risks corresponding to each of the multiple alternative time periods through a risk assessment model, and use the alternative time period in which the traffic impact risk satisfies the first risk control condition as a new transportation time period; calculate the updated estimated arrival time of materials based on the new material transportation time period, determine the updated construction time based on the updated estimated arrival time of materials, and then determine the updated construction plan.
[0137] For a detailed description of the risk assessment model, please refer to this manual Figure 2 See the relevant instructions in .
[0138] In some embodiments, the smart gas government supervision and management platform can obtain the associated construction pipelines of the current construction pipeline and the material transportation risks of the corresponding candidate transportation parameters; construct a construction pipeline network map 410 based on the associated construction information and associated construction data of the associated construction pipelines; based on the construction pipeline network map 410, through the construction adjustment model 420, determine the updated construction plan 430.
[0139] Associated construction pipelines refer to other construction pipelines connected to the current construction pipeline.
[0140] In some embodiments, the smart gas government supervision and management platform can obtain the associated construction pipelines of the current construction pipeline through construction information.
[0141] In some embodiments, the smart gas government safety management platform can build a construction pipeline network map based on the construction information and construction data of the current construction pipeline, as well as the associated construction information and associated construction data of the associated construction pipeline.
[0142] The associated construction information refers to the construction information corresponding to the associated construction pipeline, including but not limited to at least one of the code, location, construction volume (such as the length of the construction pipeline, etc.), construction plan, and construction progress of the associated construction pipeline.
[0143] The associated construction data refers to the construction data corresponding to the associated construction pipeline, including but not limited to the current construction progress.
[0144] The construction network map can be used to indicate the construction scope and status of the gas network.
[0145] In some embodiments, the construction pipeline network graph includes nodes and edges.
[0146] The node may represent a construction pipeline. In some embodiments, the node may include a node representing the current construction pipeline and a node representing an associated construction pipeline.
[0147] The nodes in the construction pipeline network map have node features. In some embodiments, the node features corresponding to the nodes include traffic impact risks of multiple candidate transportation parameters corresponding to the construction pipeline, gas usage data of the gas outage area caused by the construction pipeline, and gas pipeline construction information.
[0148] When adjusting the construction pipeline network, it is necessary to comprehensively consider the traffic impact risks that multiple construction pipelines may encounter under their respective candidate transportation parameters. By setting multiple candidate transportation parameters, it is not only possible to optimize the execution plan of a single construction project, but also to ensure the smoothness and safety of the entire construction pipeline network during transportation and construction, ensure that the construction progress is carried out as planned, and effectively reduce traffic interference and construction costs.
[0149] The method of obtaining multiple candidate transportation parameters can refer to Figure 3 Description.
[0150] The edge may represent the temporal relationship of the construction of different construction pipelines. In some embodiments, the edge includes a connection line between the construction pipelines connected in the construction sequence, and the direction of the edge is from the first construction to the last construction.
[0151] The edges in the construction pipeline network graph have edge features. In some embodiments, the edge features may include the planned construction time difference between the construction pipelines corresponding to the two nodes connected by the edge.
[0152] The planned construction time difference is the difference in the estimated start time between two consecutive construction activities scheduled according to the construction plan. For example, if one construction task is scheduled to start on Monday and the next task is scheduled to start on Wednesday, the planned construction time difference is two days.
[0153] When the traffic impact risk caused by pipeline construction is greater than the preset value, it is necessary to adjust the material transportation time and planned construction time to reduce the traffic impact risk and ensure the normal progress of construction. By constructing a construction pipeline network map, the construction sequence between different construction pipelines can be fully considered when adjusting the material transportation time and planned construction time to ensure that the traffic impact risk of the current construction pipeline is reduced while avoiding affecting the normal construction of other pipelines, which is conducive to the overall construction plan being completed on time.
[0154] In some embodiments, the smart gas government supervision and management platform can determine and update the construction plan based on the construction pipeline network map and through the construction adjustment model.
[0155] In some embodiments, the construction adjustment model may be a machine learning model, such as a graph neural network (GNN) model.
[0156] In some embodiments, the input of the construction adjustment model may include a construction network map, and the output may include an updated construction plan corresponding to the node.
[0157] In some embodiments, the smart gas government supervision management platform can store the aforementioned updated construction plan to the smart gas company management platform through the smart gas government supervision sensor network platform.
[0158] In some embodiments, the construction adjustment model can be trained by the initial adjustment model.
[0159] In some embodiments, the training samples used in the training may include a sample construction pipe network map, the sample construction pipe network map is constructed based on historical construction data, and the labels corresponding to the training samples include construction arrangement adjustment information corresponding to the sample construction pipe network map. The labels may be obtained in a variety of ways.
[0160] In some embodiments, the smart gas government supervision and management platform can determine the actual construction arrangement adjustment information corresponding to the sample construction pipeline network map based on historical construction data, and use it as a training label.
[0161] In some embodiments, the smart gas government supervision and management platform can obtain the historical adjustment plan and historical construction information corresponding to the sample construction pipeline network map; determine the adjustment impact of the historical adjustment plan based on the historical construction information; optimize the historical adjustment plan based on the adjustment impact to obtain an optimized plan; determine the training label based on the optimized plan.
[0162] Adjustment impact refers to the impact on the overall construction of the construction pipeline after the construction schedule is adjusted. Adjustment of the construction schedule may disrupt the original tight schedule, thereby affecting the overall pipeline construction. For example, due to delays in material transportation, the construction time of a certain process is adjusted to a later time, which may cause the subsequent construction to be delayed, and the materials cannot arrive in time, resulting in idle workers. For example, if the delay of a process forces other processes that use the same resources (such as transportation vehicles or construction teams) to be delayed simultaneously, this also constitutes an adjustment impact because it may lead to waste of resources and idle workers, thereby reducing overall construction efficiency.
[0163] In some embodiments, the adjustment impact can be determined based on one of the delay time, worker idle time, and equipment idle time of the historical construction pipeline. In some embodiments, the longer the delay time, the greater the adjustment impact, and the longer the worker idle time and the longer the equipment idle time, the greater the adjustment impact.
[0164] In some embodiments, the extension time can be determined based on the difference between the actual completion time and the planned completion time. Both the actual completion time and the planned completion time can be obtained based on historical actual construction information; the workers' idle time and the equipment's idle time can be obtained based on the actual construction information.
[0165] In some embodiments, the smart gas government regulatory management platform may process historical adjustment plans based on the adjustment impacts of the historical adjustment plans to determine training labels.
[0166] In some embodiments, for historical adjustment plans whose adjustment impact is less than the impact threshold, no adjustment may be made and the plan may be directly used as a training label for training the initial adjustment model. The impact threshold may include at least one of a time threshold for overall construction delay after adjustment based on the historical adjustment plan, a time threshold for worker idle time, and a time threshold for equipment idle time. The specific value may be determined based on historical experience or actual construction needs.
[0167] When the adjustment impact is greater than the aforementioned impact threshold, it indicates that the overall progress of the construction will be significantly affected after adjustments are made based on the historical adjustment plan, and the historical adjustment plan needs to be further optimized.
[0168] In some embodiments, when the adjustment impact of the historical adjustment plan is greater than the impact threshold, the smart gas government supervision and management platform can optimize the historical adjustment plan through S1~S3 to obtain an optimized plan.
[0169] S1, generates all possible optional adjustment information under the constraints of the necessary order requirements.
[0170] Necessary sequence requirements mean that the sequence of processes cannot be changed, for example, the pipeline can only be installed after trenching. In addition, the necessary sequence requirements cannot be disrupted when generating optional adjustment information.
[0171] All possible optional adjustment information refers to all feasible construction arrangement adjustments. For example, the materials of construction pipeline A can be transported first and then the materials of B, or the materials of B can be transported first and then the materials of A. All possible transportation sequences of AB materials are all possible optional adjustment information when transporting AB materials.
[0172] In some embodiments, under the constraints of the necessary order requirements, all possible optional adjustment information can be obtained by:
[0173] The smart gas government supervision and management platform obtains multiple unconstrained construction arrangements based on permutations and combinations; the construction arrangements that do not meet the necessary sequence requirements are eliminated, and what remains are all possible optional adjustment information.
[0174] S2, according to the time requirements of different processes during pipeline construction, calculate the estimated construction completion time corresponding to each optional adjustment information.
[0175] In some embodiments, the time requirements for each process may be accumulated in sequence to obtain an estimated construction completion time.
[0176] S3, taking the optional adjustment information with the earliest estimated construction completion time as the optimized construction arrangement adjustment information, so as to serve as the training label of the initial adjustment model.
[0177] By adjusting the current construction plan of the construction pipeline based on traffic impact risks and gas usage data, the updated construction plan can flexibly adapt to actual changes in traffic and social needs, effectively improving the adaptability and flexibility of the construction plan, reducing the interference of construction activities on traffic and daily social life, while optimizing the allocation and utilization of resources and improving construction efficiency and safety.
[0178] Figure 5 FIG. 1 is a schematic diagram of determining a gas supply adjustment instruction according to some embodiments of this specification. Figure 5 As shown, process 500 includes the following steps. In some embodiments, process 500 can be executed by a smart gas government supervision and management platform.
[0179] In some embodiments, the smart gas government supervision and management platform can evaluate the gas construction risk 520 based on at least one of the construction information 310 , environmental data 320 , and gas usage data 510 .
[0180] Gas construction risks refer to the risks that may arise during the construction of gas pipelines. In some embodiments, gas construction risks may include gas supply loss risks and safety loss risks.
[0181] Gas supply loss risk refers to the risk of gas supply loss caused by gas pipeline construction, for example, loss caused by gas outage.
[0182] Safety loss risk refers to the risk of loss in gas safety caused by gas pipeline construction, such as the risk of loss in gas leakage, etc. In some embodiments, the safety loss risk may include the loss caused by the consequences of leakage (such as the loss caused by explosion), or the loss caused by solving the leakage problem itself (such as the loss caused by investigating and plugging the leakage).
[0183] In some embodiments, the smart gas government supervision and management platform can determine the construction time 311 based on the construction information 310; based on the construction time 311 and the gas usage data 510, determine the gas supply loss value corresponding to the construction time, and use the gas supply loss value as the gas supply loss risk 521.
[0184] Construction time refers to the period of gas pipeline construction determined based on the actual construction progress.
[0185] In some embodiments, the construction time can be determined based on the actual construction situation in the construction information. For example, the construction time can be obtained based on the actual construction progress in the gas pipeline construction information and the estimated construction time of different processes. For example, if a construction project includes three main processes: excavation, pipeline installation, and backfilling, where excavation is expected to take 3 days, pipeline installation is expected to take 5 days, and backfilling is expected to take 2 days, then the entire construction time is from the first day of excavation to the last day of backfilling. If the construction project starts on the 1st of the month, the construction time is from the 1st to the 10th, a total of 10 days.
[0186] In some embodiments, the gas usage data can be obtained by querying the gas usage corresponding to the construction time in the gas usage data. For example, the smart gas government supervision and management platform can query the gas usage during the preset time interval from 2:00 p.m. to 6:00 p.m. in the historical gas usage data, determine the average daily gas usage based on the average value of the aforementioned gas usage, and determine the gas usage during the construction time based on the average daily gas usage and the construction time.
[0187] In some embodiments, the smart gas government supervision and management platform may use the gas usage during the construction period as the gas supply loss value.
[0188] In some embodiments, the risk of gas supply loss is also related to the risk of traffic impact. The smart gas government supervision and management platform can determine the transportation delay information based on the traffic impact risk; determine the estimated gas outage time based on the transportation delay information; and determine the risk of gas supply loss based on the estimated gas outage time and gas usage data.
[0189] Transportation delay information refers to the delay in material transportation. For example, if a supply chain route is often delayed due to traffic control and the average delay time is 30 minutes, the 30-minute delay can be recorded as the transportation delay information of the route.
[0190] In some embodiments, the smart gas government supervision and management platform can query the historical delay time of the corresponding material transportation in the historical data according to the traffic impact risk, and use the historical delay time as the transportation delay information.
[0191] Detailed description of traffic impact risks and their determination can be found in this instruction manual Figure 3 Related description in .
[0192] The estimated gas outage time refers to the estimated time period of gas outage caused by the failure of the gas pipeline to work properly. In some embodiments, the estimated gas outage time may include the suspension of gas supply due to ongoing construction, and the suspension of gas supply due to the suspension of construction caused by material delays and the failure of the gas pipeline to ventilate normally at this time.
[0193] In some embodiments, a delayed construction period may be predicted based on the transportation delay information and the construction time, and the delayed construction period may be used as the estimated gas outage time.
[0194] Among them, the delayed construction period refers to the construction time after the delay caused by delayed material transportation.
[0195] In some embodiments, the gas usage corresponding to the estimated gas outage time can be queried in the historical gas usage data, and the gas usage at the estimated gas outage time can be used as the gas supply loss risk. The method for determining the gas usage during the estimated gas outage time is similar to the method for determining the gas usage during the construction time, which can be seen in the previous description.
[0196] The estimated gas outage time is determined based on the traffic impact risk, and then the gas supply loss risk is determined. This can fully consider the impact of untimely material transportation on the construction time, thereby more accurately determining the gas supply loss risk.
[0197] In some embodiments, the smart gas government supervision and management platform can determine the safety risk node 312 of the gas pipeline based on the construction information 310; determine the pedestrian flow data 321 and vehicle flow data 322 during the construction period based on the environmental data 320; and determine the safety loss risk 522 by matching the safety risk node 312, the pedestrian flow data 321 and the vehicle flow data 322 in the security database.
[0198] In some embodiments, the safety risk node refers to a point and / or process where there is a safety risk, for example, the interface between a newly installed pipeline and an old pipeline, a pipeline welding point, etc.
[0199] In some embodiments, the safety risk attributes of at least one point in the construction gas pipeline can be pre-set based on historical experience, and the smart gas government supervision and management platform can automatically determine the safety risk node according to the pre-set safety risk attributes.
[0200] Safety risk attributes refer to the characteristics used to determine whether there are safety risks at points in the gas pipeline. If a point has safety risk characteristics, there is a safety risk. For example, if the safety risk characteristics include welding operations and newly installed pipelines connected to the pipeline network, then the processes and points where welding operations have been performed and newly installed pipelines have been connected to the pipeline network are safety risk nodes.
[0201] The pedestrian flow data refers to the number of pedestrians passing by the construction pipeline per unit time during the construction period.
[0202] Traffic flow data refers to the number of vehicles passing near the construction pipeline per unit time during the construction period.
[0203] In some embodiments, the smart gas government supervision and management platform can determine pedestrian flow data and vehicle flow data based on environmental data. The environmental data refers to data obtained by monitoring the surrounding environment of the gas pipeline, including but not limited to the number of pedestrians and vehicles passing by. The environmental data can be obtained through sensors set in the smart gas equipment object platform.
[0204] In some embodiments, the smart gas government supervision and management platform can determine the safety loss risk by vector matching. For example, the smart gas government supervision and management platform can construct a safety risk vector 530 based on the safety risk node 312, the flow of people data 321, and the flow of vehicles data 322 corresponding to the construction pipeline, search in the security database based on the safety risk vector 530, find the reference vector closest to the safety risk vector as the target reference vector, and use the corresponding reference safety loss as the safety loss risk of the construction pipeline.
[0205] The safety database includes at least one reference vector and a reference safety loss corresponding to each reference vector. The reference vector is constructed based on historical safety risk nodes, historical pedestrian flow data, and historical vehicle flow data in historical data.
[0206] The reference safety loss refers to the loss caused by actual safety problems in historical data, such as at least one of gas loss, economic loss, and processing cost loss.
[0207] In some embodiments, the smart gas government regulatory management platform can determine at least one similar reference vector through a security database; and determine the safety loss risk 522 based on the reference weight corresponding to each of the at least one similar reference vector.
[0208] In some embodiments, the smart gas government regulatory management platform can match the security risk vector in the security database, and use the reference vectors with high similarity ranking (such as top five, top ten, etc.) or with similarity exceeding the similarity threshold as similar reference vectors, and determine the safety loss risk based on the reference weight corresponding to at least one similar reference vector.
[0209] The similarity can be represented by the vector distance between the safety wind vector and the reference vector, and the similarity threshold can be a distance threshold. The closer the vector distance is, the higher the similarity between the two is. In some embodiments, the similarity threshold can be determined based on historical experience and / or actual needs.
[0210] In some embodiments, the reference weight can be determined based on the similarity between the similar reference vector and the security risk vector, and the security incident level corresponding to the similar reference vector. The higher the similarity between the similar reference vector and the security risk vector, and the higher the security incident level corresponding to the similar reference vector, the greater the corresponding reference weight.
[0211] In some embodiments, the safety loss risk may be determined by weighted summing the reference safety losses corresponding to a plurality of similar reference vectors according to reference weights.
[0212] By determining multiple similar reference vectors and performing weighted summation based on reference weights to determine the safety loss risk corresponding to the construction pipeline, the safety loss risk can be evaluated more accurately, thereby providing a more reliable reference for determining the gas supply regulation instructions.
[0213] In some embodiments, the smart gas government regulatory management platform can determine the gas supply adjustment instructions 560 based on the gas construction risk 520.
[0214] The gas supply adjustment instruction refers to an instruction to adjust the gas supply in the gas pipeline, for example, to increase the gas supply or reduce the gas supply.
[0215] In some embodiments, the smart gas government regulatory management platform can determine the gas supply adjustment instructions by comparing the risk of gas supply loss and the risk of safety loss.
[0216] In some embodiments, if the high gas usage during the construction period causes the risk of gas supply loss to be greater than the risk of safety loss, the smart gas government supervision and management platform can generate an emergency gas supply instruction as a gas supply adjustment instruction, wherein the emergency gas supply instruction can include emergency gas supply to users through an emergency gas supply vehicle.
[0217] In some embodiments, if the risk of safety loss is greater than the risk of gas supply loss, the smart gas government supervision and management platform can lower the gas pressure and other parameters of nearby gas pipelines during the construction period to reduce gas leakage, or stop gas supply during non-gas peak hours (i.e., lower the gas pressure to zero) to prevent an increase in gas leakage from the leakage point due to the high gas pressure in the gas pipeline, thereby reducing safety hazards.
[0218] In some embodiments, in response to the gas construction risk 520 not meeting the second risk control condition 540, the smart gas government supervision and management platform can determine the emergency gas supply parameters 550 based on the gas pipeline network information; based on the emergency gas supply parameters 550, determine the gas supply adjustment instructions 560.
[0219] The second risk control condition refers to the condition for determining whether backup gas supply needs to be arranged, for example, if at least one of the gas supply loss risk and the safety loss risk exceeds the corresponding risk threshold, the second risk control condition is met. The risk threshold can be determined based on historical experience and / or actual demand.
[0220] Emergency gas supply parameters refer to gas supply parameters used to reduce the risk of gas construction, such as adjusting the gas supply pressure, gas supply flow rate, gas supply period, gas supply method, etc. Among them, the gas supply method may include emergency gas supply vehicle, emergency gas supply tank, etc.
[0221] In some embodiments, when the risk of gas supply loss meets the second risk control condition, the emergency gas supply parameters may include increasing the gas supply parameters of the parallel gas pipelines / stations, such as increasing the gas pressure, flow rate, flow rate, etc., and supplying gas to the affected area through the parallel gas pipelines / stations to restore the gas supply to normal in the affected area.
[0222] Parallel gas pipelines / stations refer to gas pipelines / stations that are parallel to and connected to construction pipelines. When the construction pipelines are unable to supply gas, the gas from the parallel gas pipelines / stations can be used as a substitute or supplement to ensure gas supply to gas users in the affected area.
[0223] In some embodiments, when the safety loss risk meets the second risk control condition, the gas supply parameters of the nearby gas pipelines are adjusted, such as reducing the gas pressure, flow rate, flow rate, etc., to reduce gas leakage and reduce the safety loss risk.
[0224] In some embodiments, the smart gas government supervision and management platform can adjust the second risk control condition based on changes in the construction arrangements of each construction pipeline in the updated construction plan.
[0225] The construction schedule change refers to the change of the construction schedule after the construction pipeline is updated compared with the original planned construction schedule. In some embodiments, the construction schedule change includes at least one of the changes in the construction time period of different processes, the changes in the construction duration, and the changes in the completion time.
[0226] In some embodiments, the smart gas government supervision and management platform can adjust at least one of the gas supply loss risk threshold and the safety loss risk threshold in the second risk control condition according to construction changes.
[0227] In some embodiments, when the construction period is adjusted from a low-peak gas consumption period to a peak gas consumption period, the smart gas government supervision and management platform can lower the safety loss risk threshold to strengthen risk control over gas safety.
[0228] As the construction period is adjusted to the peak period, the possibility of gas leakage increases. The large flow rate and high gas pressure lead to an increase in gas leakage. At the same time, the flow of people is large. The smart gas government supervision and management platform ensures that the safety risk is controlled within a lower range by lowering the safety loss risk threshold.
[0229] In some embodiments, when the construction time becomes longer and the completion time is delayed, the smart gas government supervision and management platform can lower the gas supply loss risk threshold to control the growth of gas supply loss as much as possible.
[0230] As the construction time becomes longer and the completion time is delayed, the impact on gas supply will be prolonged. At this time, the smart gas government supervision and management platform can lower the gas supply loss threshold and ensure user gas supply by timely arranging backup gas supply.
[0231] By assessing gas construction risks based on construction information, environmental data and gas usage data, gas supply adjustment instructions are generated for the construction supervision area. This enables the gas supply system to accurately respond to the risks brought by construction activities. This not only ensures the safety and stability of gas supply during construction, but also adjusts the gas supply volume and gas supply strategy according to actual conditions, effectively avoiding excess or insufficient gas supply and improving the efficiency and economy of gas supply.
[0232] The basic concepts have been described above. Obviously, for those skilled in the art, the above detailed disclosure is only for example and does not constitute a limitation of this specification. Although not explicitly stated here, those skilled in the art may make various modifications, improvements and corrections to this specification. Such modifications, improvements and corrections are suggested in this specification, so such modifications, improvements and corrections still belong to the spirit and scope of the exemplary embodiments of this specification.
[0233] At the same time, this specification uses specific words to describe the embodiments of this specification. For example, "one embodiment", "an embodiment", and / or "some embodiments" refer to a certain feature, structure or characteristic related to at least one embodiment of this specification. Therefore, it should be emphasized and noted that "one embodiment" or "an embodiment" or "an alternative embodiment" mentioned twice or more in different positions in this specification does not necessarily refer to the same embodiment. In addition, certain features, structures or characteristics in one or more embodiments of this specification can be appropriately combined.
[0234] Similarly, it should be noted that in order to simplify the description disclosed in this specification and thus help understand one or more embodiments of the invention, in the above description of the embodiments of this specification, multiple features are sometimes combined into one embodiment, figure or description thereof. However, this disclosure method does not mean that the features required by the subject matter of this specification are more than the features mentioned in the claims. In fact, the features of the embodiments are less than all the features of the single embodiment disclosed above.
[0235] Finally, it should be understood that the embodiments described in this specification are only used to illustrate the principles of the embodiments of this specification. Other variations may also fall within the scope of this specification. Therefore, as an example and not a limitation, alternative configurations of the embodiments of this specification may be considered consistent with the teachings of this specification. Accordingly, the embodiments of this specification are not limited to the embodiments explicitly introduced and described in this specification.
Claims
1. A smart gas pipeline network construction monitoring method, characterized in that: The smart gas government supervision and management platform of the smart gas pipeline network construction monitoring IoT system is implemented, including: Acquire update status of construction information corresponding to the construction pipeline in the construction supervision area, and in response to the construction information being updated, acquire supervision data for the construction supervision area; The regulatory data is stored in the government regulatory comprehensive database of the smart gas government regulatory management platform according to preset rules, and the government regulatory comprehensive database is configured as a memory; wherein, The supervision data includes the construction information, environmental data of the construction supervision area, and gas usage data corresponding to the pipeline to be constructed in the construction supervision area; determining a construction status of the construction pipeline; In response to the construction status meeting a first condition, wherein the first condition refers to the construction pipeline being in a stage of waiting for construction: Generating a material transportation instruction for the construction pipeline based on the construction information and the environmental data, including: Based on the construction information and the environmental data, the traffic impact risk of the construction pipeline is evaluated; wherein the traffic impact risk represents the impact of traffic factors on the timeliness of material transportation; Determining the material transportation instructions based on the traffic impact risk; In response to the traffic impact risk not satisfying the first control condition, based on the traffic impact risk and the gas usage data, adjusting the current construction plan of the construction pipeline to determine an updated construction plan; wherein the first control condition refers to a condition for determining whether material transportation can arrive in time; Storing the updated construction plan in the smart gas company management platform; sending the material transport instruction to the transport equipment to control the transport equipment to transport the material according to the material transport parameters; In response to the construction status meeting a second condition, wherein the second condition refers to the construction pipeline being in a construction stage: Based on at least one of the construction information, the environmental data, and the gas usage data, generating a gas supply adjustment instruction for the construction supervision area, including: Based on at least one of the construction information, the environmental data, and the gas usage data, assess the gas construction risk, wherein the gas construction risk includes at least one of a gas supply loss risk and a safety loss risk; Based on the gas construction risk, determining the gas supply adjustment instruction; In response to the gas construction risk not meeting the second risk control condition, determining emergency gas supply parameters based on the gas pipeline network information; wherein the second risk control condition refers to a condition for determining whether a backup gas supply needs to be arranged; Based on the emergency gas supply parameter, determining the gas supply adjustment instruction; Sending the gas supply adjustment instruction to the smart gas equipment object platform corresponding to the construction supervision area to control the gas supply parameters of the construction supervision area; Obtaining, from the government regulatory integrated database, a first update frequency corresponding to the material transportation instruction and a second update frequency corresponding to the gas supply regulation instruction, wherein the first update frequency refers to a frequency of updating the material transportation instruction, and the second update frequency refers to a frequency of updating the gas supply regulation instruction; Based on the first update frequency and the second update frequency, adjust the current monitoring parameters of the smart gas equipment object platform; Based on the adjusted monitoring parameters, allocating the storage partition size occupied by the regulatory data and the gas safety data in the government regulatory comprehensive database; and, Determine the processor of the smart gas government supervision and management platform and the priority of computing resource allocation when processing different types of data.
2. A smart gas pipeline network construction monitoring Internet of Things system, characterized in that: Including smart gas government supervision management platform, smart gas government supervision sensor network platform, smart gas government supervision object platform, smart gas company sensor network platform, smart gas equipment object platform; The smart gas government supervision and management platform includes a government supervision comprehensive database; The smart gas government supervision object platform includes a smart gas company management platform; The smart gas government supervision and management platform is configured as follows: Acquire update status of construction information corresponding to the construction pipeline in the construction supervision area, and in response to the construction information being updated, acquire supervision data for the construction supervision area; The regulatory data is stored in the government regulatory comprehensive database of the smart gas government regulatory management platform according to preset rules, and the government regulatory comprehensive database is configured as a memory; wherein, The supervision data includes the construction information, environmental data of the construction supervision area, and gas usage data corresponding to the pipeline to be constructed in the construction supervision area; determining a construction status of the construction pipeline; In response to the construction status meeting a first condition, wherein the first condition refers to the construction pipeline being in a stage of waiting for construction: Generating a material transportation instruction for the construction pipeline based on the construction information and the environmental data, including: Based on the construction information and the environmental data, the traffic impact risk of the construction pipeline is evaluated; wherein the traffic impact risk represents the impact of traffic factors on the timeliness of material transportation; Determining the material transportation instructions based on the traffic impact risk; In response to the traffic impact risk not satisfying the first control condition, based on the traffic impact risk and the gas usage data, adjusting the current construction plan of the construction pipeline to determine an updated construction plan; wherein the first control condition refers to a condition for determining whether material transportation can arrive in time; Storing the updated construction plan in the smart gas company management platform; sending the material transport instruction to the transport equipment to control the transport equipment to transport the material according to the material transport parameters; In response to the construction status meeting a second condition, wherein the second condition refers to the construction pipeline being in a construction stage: Based on at least one of the construction information, the environmental data, and the gas usage data, generating a gas supply adjustment instruction for the construction supervision area, including: Based on at least one of the construction information, the environmental data, and the gas usage data, assess the gas construction risk, wherein the gas construction risk includes at least one of a gas supply loss risk and a safety loss risk; Based on the gas construction risk, determining the gas supply adjustment instruction; In response to the gas construction risk not meeting the second risk control condition, determining emergency gas supply parameters based on the gas pipeline network information; wherein the second risk control condition refers to a condition for determining whether a backup gas supply needs to be arranged; Based on the emergency gas supply parameter, determining the gas supply adjustment instruction; Sending the gas supply adjustment instruction to the smart gas equipment object platform corresponding to the construction supervision area to control the gas supply parameters of the construction supervision area; Obtaining, from the government regulatory integrated database, a first update frequency corresponding to the material transportation instruction and a second update frequency corresponding to the gas supply regulation instruction, wherein the first update frequency refers to a frequency of updating the material transportation instruction, and the second update frequency refers to a frequency of updating the gas supply regulation instruction; Based on the first update frequency and the second update frequency, adjust the current monitoring parameters of the smart gas equipment object platform; Based on the adjusted monitoring parameters, allocating the storage partition size occupied by the regulatory data and the gas safety data in the government regulatory comprehensive database; and, Determine the processor of the smart gas government supervision and management platform and the priority of computing resource allocation when processing different types of data.