A construction method for constructing a subway station from an open-cut subway station to a concealed-cut station
By reserved hidden excavation conditions during the construction of open excavation subway stations, and using enclosing piles and small conduit reinforcement technology to form a stress system, the problem of stress conversion and low construction efficiency at the junction of bright and dark excavation is solved, and the subway station is realized Improve the safety and efficiency of construction.
Patent Information
- Application Number
- CN202411095480.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-12
- Publication Date
- 2024-11-26
- Estimated Expiration
- 2044-08-12
AI Technical Summary
In the construction of subway stations, when the open excavation method is combined with the hidden excavation method, there are problems such as complex force conversion, poor safety, complex construction processes, high project cost, many abandoned projects and low construction efficiency, especially when the construction of open excavation subway stations is completed. Space is limited when secretly digging stations, and it is difficult to transport waste and feed waste.
A method of constructing a hidden excavation station from an open subway station is adopted, including implementing the main structure of the open excavation station and reserves some construction conditions for the hidden excavation, simultaneously erecting steel support from the earth excavation of the enclosing piles, and constructing open excavation end walls at the junction of the open excavation. and transport wells, the soil stability problem is solved through small conduits and grouting reinforcement, forming a vertical and horizontal stress system, excavating the soil layer by layer, and finally pouring the remaining end walls to complete the main structure of the hidden excavation station.
Improve construction safety and efficiency, reduce project cost, simplify construction processes, shorten construction period, solve the problems of force conversion and construction space limitations at the junction of light and dark excavation, and achieve low overall construction cost and simple construction process. Good safety effect.
Smart Images

Figure CN118639689B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of subway foundation construction, in particular to a method for constructing a dark-cut subway station from an open-cut subway station. Background Art
[0002] With the continuous development of urban construction in my country, the surrounding environment of urban subways is becoming more and more complex, and subway construction is restricted by more and more factors. Open-cut method and underground excavation method are two commonly used construction methods for subway stations. The open-cut method has the advantages of fast construction speed, high safety, low cost and short construction period, but at the same time, it has the problems of large impact on ground traffic, many pipeline relocations, more house demolitions, and large impact on residents' lives; underground excavation method has the advantages of small impact on ground traffic, less pipeline relocation, less house demolition, and small impact on residents' lives, but at the same time, it has the problems of high comprehensive cost, great construction difficulty, poor safety and long construction period.
[0003] Therefore, under certain conditions, the construction method of subway stations that combines open and dark excavation has unique advantages. However, the construction of subway stations by combining open and dark excavation methods still has the following problems: First, the force conversion between open and dark excavation construction is complex, the safety is poor, the construction process is complicated, the project cost is high, and there are many abandoned projects; second, the construction of subway stations from open excavation to dark excavation is limited in space, the transportation and feeding of slag is difficult, the construction efficiency is low, and the construction period is long.
[0004] Therefore, it is necessary to study a method of constructing a concealed excavation station from an open-cut subway station, which has reliable force conversion, better safety, simpler construction process, more economical cost, shorter construction period, and more controllable quality.
[0005] The significance of solving the above technical problems lies in that the method described in the present invention provides a new construction method for a subway station from an open-cut subway station to a dark-cut station. Compared with the traditional construction method of constructing the dark-cut part from an open-cut station, the method described in the present invention has the characteristics of simple construction process, good safety, short construction period, and easy to ensure construction quality. The overall comprehensive cost is low, and it has broad promotion prospects in the field of subway station construction. Summary of the invention
[0006] According to the above problems, the present invention proposes a method for constructing a dark-cut subway station from an open-cut subway station. The specific scheme is as follows:
[0007] A construction method for constructing a dark-cut subway station from an open-cut subway station comprises the following steps:
[0008] Step S1: construct the main structure of the open-cut station and reserve conditions for the construction of the dark-cut part;
[0009] After the retaining piles are constructed, the earthwork is excavated downwards and steel supports are erected simultaneously until the bottom of the foundation pit is exposed. Then, the open-cut station main structure, open-cut end wall and transport shaft at the junction of open and dark excavation are constructed;
[0010] The open-cut end wall is constructed to the upper side guide hole and the upper middle guide hole of the dark excavation, and the crossbeam is constructed;
[0011] The transport shaft is formed by partially expanding the retaining piles and is provided with a shaft wall structure;
[0012] Step S2: constructing a dark-cut lower side guide tunnel and a dark-cut lower middle guide tunnel from the open-cut station;
[0013] After the main structure of the open-cut station is completed, double rows of advanced small guide pipes are constructed between the retaining piles to reinforce the soil of the arch top of the lower side guide tunnel and the lower middle guide tunnel of the dark excavation. At the same time, grouting reinforcement is constructed between the lower and middle guide tunnels to reinforce the soil between the lower and middle guide tunnels of the dark excavation and ensure the stability of the soil between the small clear distance tunnels.
[0014] After the reinforcement is completed, the open-cut station main structure retaining piles within the scope of the dark-cut lower side guide tunnel and the dark-cut lower middle guide tunnel are removed, five first grid steel frames are connected and the steel bars in the retaining piles are welded firmly to the first grid steel frames, and then the dark-cut lower side guide tunnel and the dark-cut lower middle guide tunnel are excavated;
[0015] Step S3: constructing the lower layer inclined guide tunnel;
[0016] The first advance small pipe grouting reinforcement is carried out on the soil of the arch of the lower inclined guide tunnel, and the first steel support is set up above the arch. After completion, the initial support of the lower layer dark excavation guide tunnel within the range of the lower layer inclined guide tunnel is chiseled out, and the lower layer inclined guide tunnel is excavated. After entering the tunnel, three lower layer inclined guide tunnel grids are erected in succession. The lower layer inclined guide tunnel grids are placed perpendicular to the grids of the middle guide tunnel and the side guide tunnel;
[0017] Step S4: constructing a dark excavation upper side guide tunnel and a dark excavation upper middle guide tunnel from the open-cut station;
[0018] Double rows of small advance guide tubes are constructed between the retaining piles to reinforce the soil of the upper side guide tunnel and the upper middle guide tunnel arch. At the same time, grouting reinforcement is constructed between the upper and middle guide tunnels to reinforce the soil between the upper and middle guide tunnels and ensure the stability of the soil between the small clearance tunnels.
[0019] After the reinforcement is completed, the open-cut station main structure retaining piles within the range of the upper side guide tunnel and the upper middle guide tunnel are removed, five second grid steel frames are connected and the steel bars in the retaining piles are welded firmly to the second grid steel frames, and then the upper side guide tunnel and the upper middle guide tunnel are excavated;
[0020] Step S5: constructing an upper inclined guide tunnel;
[0021] The soil of the upper inclined guide tunnel vault is reinforced by the second advance small pipe grouting. The second steel brace is set above the vault. The initial support of the upper dark-cut guide tunnel within the range of the upper inclined guide tunnel is removed. The upper inclined guide tunnel is excavated. After entering the tunnel, three upper inclined guide tunnel grids are erected in succession. The upper inclined guide tunnel grids are placed perpendicular to the middle guide tunnel and side guide tunnel grids.
[0022] Step S6: Constructing the main structure of the station by dark excavation using the pile method;
[0023] According to the hole pile method process, a vertical force bearing system and a horizontal force bearing support system are formed in the dark excavation lower side guide hole, dark excavation lower middle guide hole, dark excavation upper side guide hole, and dark excavation upper middle guide hole;
[0024] Excavate the soil from top to bottom and construct the main structure of the underground station;
[0025] Step S7: construct the main structure of the remaining part of the open-cut end wall at the junction of the open-cut and dark-cut;
[0026] Remove the remaining retaining piles within the open-cut end wall, remove the shaft wall structure of the transport shaft, and cast the remaining end wall;
[0027] The remaining end wall includes the part within the range of the transport shaft and the part from under the beam to the upper part of the arch of the main structure of the underground station. The two parts are cast simultaneously and formed in one piece.
[0028] Preferably, the main structure of the open-cut station is first constructed from bottom to top in step S1 to cast and form the bottom plate, the middle plate of the second negative floor, the middle plate of the first negative floor, the top plate, side walls, open-cut end walls and pilasters. After the shaft wall structure of the transport shaft is removed in step S7, the casting is continued from bottom to top to form the bottom plate, the middle plate of the second negative floor, the middle plate of the first negative floor, the top plate, side walls and the remaining end walls within the range of the transport shaft, which are integrally formed with the bottom plate, the middle plate of the second negative floor, the middle plate of the first negative floor, the top plate, side walls and end walls cast in step S1.
[0029] More preferably, in step S1, a plurality of steel bar connectors are reserved at the shaft wall structure of the transport shaft. After the construction of the dark excavation section is completed and the shaft wall structure within the main structure of the open-cut station is chiseled out, the plurality of steel bar connectors are respectively connected to the main steel bars of the main structure of the open-cut station, and the bottom plate, side wall, negative second floor middle plate, negative first floor middle plate, and top plate within the range of the transport shaft are cast to form.
[0030] Preferably, in step S1, when constructing the crossbeam, a steel connector of the lower unconstructed portion is reserved for casting the remaining end wall from under the crossbeam to the upper portion of the arch of the main structure of the underground station.
[0031] Further preferably, in step S2, the bottoms of the lower side guide tunnel and the lower middle guide tunnel of the dark excavation are lower than the bottom plate, and after the lower side guide tunnel and the lower middle guide tunnel enter the dark excavation section, initial support for the lower layer of the dark excavation guide tunnel is first performed, and a temporary invert arch for the dark excavation guide tunnel is erected to form a closed primary support structure and a downward construction ramp; after the guide tunnel is constructed for a certain distance, the soil at the ramp is reversed to form a complete small guide tunnel grid, which is backfilled with medium-coarse sand to level the height difference with the bottom plate to form a construction and transportation channel.
[0032] Preferably, in step S2, grouting is performed from between the retaining piles into the soil between the lower and middle guide holes of the dark excavation to form grouting reinforcement between the lower and middle guide holes; in step S4, grouting is performed from between the retaining piles into the soil between the upper and middle guide holes of the dark excavation to form grouting reinforcement between the upper and middle guide holes.
[0033] Preferably, in step S2, the tunnel entry section of the underground middle guide tunnel is partially widened and then gradually becomes a standard width.
[0034] Preferably, in step S4, the tunnel entry section of the upper middle guide tunnel of the dark excavation is partially widened and then gradually becomes a standard width.
[0035] Preferably, in step S3 and step S5, the lower inclined guide tunnel is arranged between the lower side guide tunnel of the dark excavation and the lower middle guide tunnel of the dark excavation, and the upper inclined guide tunnel is arranged between the upper side guide tunnel of the dark excavation and the upper middle guide tunnel of the dark excavation.
[0036] The beneficial effects of the present invention are:
[0037] 1. The side wall of the main structure at the junction of the open-cut station and the underground excavation station is partially expanded outward to reserve an underground excavation construction transportation well, which solves the problem of underground excavation excavation channels. At the same time, the transportation well can be used as the internal support of the open-cut retaining structure, solving the temporary stability problem of the open-cut foundation pit, which saves more engineering costs than the previous use of steel supports;
[0038] 2. The open-cut end wall at the junction of the open-cut station and the underground excavation station has reserved beams above the underground excavation upper side guide hole and the underground excavation upper middle guide hole, which solves the problem of force conversion between open-cut construction and underground excavation construction;
[0039] 3. Before entering the small guide tunnel, the soil between the small guide tunnels is reinforced by grouting, which solves the construction problem of small clear distance guide tunnels and improves the safety of the project.
[0040] 4. The lower middle guide tunnel and the upper middle guide tunnel are partially widened during the tunnel entry section to avoid the impact of the existing open-cut main structure wall columns on the transportation of debris and materials, and provide a construction channel for the dark excavation construction.
[0041] After the lower side guide tunnel and the lower middle guide tunnel of the dark excavation enter the dark excavation section, the initial support is constructed first, and a temporary invert is erected to form a closed primary support structure. At the same time, a downward construction ramp is formed to reduce construction risks;
[0042] After the pilot tunnel is constructed forward for a certain distance, the soil at the slope is back-excavated to form a complete small pilot tunnel grid, and medium-coarse sand is backfilled to solve the height difference problem between the dark-cut pilot tunnel and the open-cut section bottom plate;
[0043] Setting up an inclined guide tunnel between the middle guide tunnel and the side guide tunnel creatively solves the problems of limited space, difficult transportation and feeding of debris, and low construction efficiency in constructing a concealed excavation subway station from an open-cut one. It can greatly improve construction efficiency, shorten construction period, and reduce project investment.
[0044] Therefore, the present invention has the characteristics of low comprehensive cost, simple construction process, good safety, short construction period and easy to ensure construction quality, and has broad promotion prospects in the field of subway station construction. BRIEF DESCRIPTION OF THE DRAWINGS
[0045] The technical solution of the present invention will be further described in detail below in conjunction with the accompanying drawings and embodiments, but it should be understood that these drawings are designed only for explanation purposes and are not intended to limit the scope of the present invention. In addition, unless otherwise specified, these drawings are intended only to conceptually illustrate the structural configurations described herein and are not necessarily drawn to scale.
[0046] Figure 1 It is a flow chart of the construction method provided in the present invention;
[0047] Figure 2 It is the elevation view of the dark excavation pilot tunnel in the present invention;
[0048] Figure 3 It is a plan view of the dark excavation upper middle guide tunnel, dark excavation upper side guide tunnel, open excavation station and connection points in the present invention;
[0049] Figure 4 It is a plan view of the dark-cut middle guide tunnel, dark-cut side guide tunnel, open-cut station and connection in the present invention;
[0050] Figure 5 It is a longitudinal section view of the dark excavation upper guide tunnel, dark excavation lower guide tunnel, open excavation station and the connection point in the present invention;
[0051] Figure 6 It is a longitudinal section view of the dark excavated upper middle guide tunnel, dark excavated lower middle guide tunnel, open excavated station and the connection point in the present invention;
[0052] Figure 7 It is a large-scale drawing of the reserved steel bar connector of the main structure of the open-cut station at the transport shaft in the present invention;
[0053] Figure 8 yes Figure 5 , Figure 6 A magnified view of the structure at point A of the entrance to the middle dark excavation pilot tunnel;
[0054] Fig. 9 yes Figure 5 , Figure 6 A magnified view of the structure B at the entrance of the middle dark excavation pilot tunnel;
[0055] Fig.10 It is a structural elevation view of the open-cut end wall at the junction of the open-cut and dark-cut in the present invention;
[0056] In the figure:
[0057] 1. Bottom plate; 2. Side wall; 3. Middle plate of the second negative floor; 4. Middle plate of the first negative floor; 5. Top plate; 6. Pilaster; 7. Open-cut end wall; 8. Crossbeam; 9. Guard pile; 10. Transport shaft; 11. Dark excavation of lower side guide hole; 12. Dark excavation of lower middle guide hole; 13. Dark excavation of upper side guide hole; 14. Dark excavation of upper middle guide hole; 15. Lower layer inclined guide hole; 16. Upper layer inclined guide hole; 17. Grouting reinforcement between lower middle guide hole; 18. Grouting reinforcement between upper middle guide hole; 19. Initial support of lower layer dark excavation guide hole; 20. Temporary invert of dark excavation guide hole; 21. Small guide hole grid; 22. Medium-coarse sand; 23. First advance small duct; 24. First steel brace; 25. Lower inclined guide tunnel grid; 26. Second advance small duct; 27. Second steel brace; 28. Upper inclined guide tunnel grid; 29. Initial support for upper underground excavation guide tunnel; 30. Shaft wall structure; 31. Steel bar connector; 32. Steel bars; 33. First grid steel frame; 34. Second grid steel frame; 35. Remaining end wall. DETAILED DESCRIPTION
[0058] First of all, it should be noted that the specific structure, features and advantages of the present invention will be specifically described below by way of example, but all descriptions are only for illustration and should not be understood as limiting the present invention in any way. In addition, any single technical feature described or implied in the embodiments mentioned herein, or any single technical feature displayed or implied in the drawings, can still be combined or deleted between these technical features to obtain more other embodiments of the present invention that may not be directly mentioned in this document. In addition, in order to simplify the drawings, the same or similar technical features may be marked only in one place in the same drawing.
[0059] In the present invention, unless otherwise clearly stipulated and limited, the terms such as "installation", "setting", "connection", "fixation" and "screw-on" should be understood in a broad sense. For example, it can be a fixed connection, a detachable connection, or an integral one; it can be a mechanical connection or an electrical connection; it can be a direct connection or an indirect connection through an intermediate medium; it can be the internal connection of two elements or the interaction relationship between two elements. Unless otherwise clearly defined, ordinary technicians in this field can understand the specific meanings of the above terms in the present invention according to the specific circumstances.
[0060] The following is combined with Figure 1 -Attached Fig.10 The present invention will be described in detail. Embodiment 1:
[0061] like Figure 1 to Figure 10 As shown, a construction method for constructing a dark excavation station from an open excavation subway station comprises the following steps:
[0062] Step S1: construct the main structure of the open-cut station and reserve conditions for the construction of the dark-cut part;
[0063] Construct retaining piles 9, excavate downwards and erect steel supports simultaneously after completion, until the bottom of the foundation pit is exposed, construct the open-cut station main structure, open-cut end wall 7 and transport shaft 10 at the junction of open and dark excavation;
[0064] The open-cut end wall 7 is constructed to the upper side guide hole 13 and the upper middle guide hole 14 of the dark excavation, and the crossbeam 8 is constructed;
[0065] The transport shaft 10 is formed by partially expanding the retaining piles 9 and is provided with a shaft wall structure 30;
[0066] Step S2: constructing a dark-cut lower side guide tunnel 11 and a dark-cut lower middle guide tunnel 12 from within the open-cut station;
[0067] After the main structure of the open-cut station is completed, a double row of advanced small guide pipes are constructed between the retaining piles 9 to reinforce the soil of the arch tops of the dark-cut lower side guide tunnel 11 and the dark-cut lower middle guide tunnel 12. At the same time, grouting reinforcement 17 between the lower middle guide tunnels is constructed to reinforce the soil between the dark-cut lower middle guide tunnels 12 to ensure the stability of the soil between the small clear distance tunnels.
[0068] After the reinforcement is completed, the open-cut station main structure retaining piles 9 within the range of the dark-cut lower side guide hole 11 and the dark-cut lower middle guide hole 12 are removed, five first grid steel frames 33 are connected, and the steel bars 32 in the retaining piles 9 are welded firmly to the first grid steel frames 33, and then the dark-cut lower side guide hole 11 and the dark-cut lower middle guide hole 12 are excavated;
[0069] Step S3: constructing the lower layer inclined guide tunnel 15;
[0070] The first advance small pipe 23 is used to reinforce the soil of the arch of the lower inclined guide tunnel 15, and the first steel support 24 is set above the arch. After completion, the lower layer dark excavation guide tunnel initial support 19 within the range of the lower inclined guide tunnel 15 is chiseled out, and the lower layer inclined guide tunnel 15 is excavated. After entering the tunnel, three lower layer inclined guide tunnel grids 25 are erected in succession. The lower layer inclined guide tunnel grids 25 are placed perpendicular to the grids of the middle guide tunnel and the side guide tunnel;
[0071] Step S4: constructing a dark excavation upper side guide tunnel 13 and a dark excavation upper middle guide tunnel 14 from the open-cut station;
[0072] A double row of advanced small guide pipes are constructed between the retaining piles 9 to reinforce the soil of the arch tops of the upper side guide tunnel 13 and the upper middle guide tunnel 14. At the same time, grouting reinforcement 18 between the upper middle guide tunnels is constructed to reinforce the soil between the upper middle guide tunnels 14 to ensure the stability of the soil between the small clearance tunnels.
[0073] After the reinforcement is completed, the open-cut station main structure retaining piles 9 within the range of the dark excavated upper side guide hole 13 and the dark excavated upper middle guide hole 14 are chiseled out, five second grid steel frames 34 are connected, and the steel bars 32 in the retaining piles 9 are welded firmly to the second grid steel frames 34, and then the dark excavated upper side guide hole 13 and the dark excavated upper middle guide hole 14 are excavated;
[0074] Step S5: constructing the upper inclined guide tunnel 16;
[0075] The soil of the upper inclined guide tunnel 16 vault is reinforced by grouting with a second advanced small guide tube 26, a second steel brace 27 is set above the vault, the upper layer dark excavation guide tunnel initial support 29 within the range of the upper inclined guide tunnel 16 is chiseled out, the upper layer inclined guide tunnel 16 is excavated, and three upper layer inclined guide tunnel grids 28 are erected after entering the tunnel. The upper layer inclined guide tunnel grids 28 are placed perpendicular to the middle guide tunnel and the side guide tunnel grids;
[0076] Step S6: Constructing the main structure of the station by dark excavation using the pile method;
[0077] According to the hole pile method process, a vertical force bearing system and a horizontal force bearing support system are formed in the dark excavation lower side guide hole 11, the dark excavation lower middle guide hole 12, the dark excavation upper side guide hole 13, and the dark excavation upper middle guide hole 14;
[0078] Excavate the soil from top to bottom and construct the main structure of the underground station;
[0079] Step S7: construct the remaining main structure of the open-cut end wall 7 at the junction of open-cut and dark-cut;
[0080] Chisel out the remaining retaining piles 9 within the range of the open-cut end wall 7, chisel out the shaft wall structure 30 of the transport shaft 10, and cast the remaining end wall 35;
[0081] The remaining end wall 35 includes the portion within the range of the transport shaft 10 and the portion from the bottom of the beam 8 to the upper portion of the arch of the main structure of the underground station. The two portions are cast simultaneously and formed in one piece.
[0082] In this embodiment, the side wall of the main structure at the junction of the open-cut station and the dark-cut station is partially expanded outward, and a dark-cut construction transportation shaft 10 is reserved, which solves the problem of dark-cut excavation passage. The open-cut station retaining piles 9 are partially expanded outward to form the spatial structure of the transportation shaft 10, and avoid the reverse excavation of the dark-cut primary support structure after the main structure of the open-cut station is completed. At the same time, the transportation shaft 10 can be used as the internal support of the open-cut retaining structure, solving the temporary stability problem of the open-cut foundation pit.
[0083] The open-cut end wall 7 at the junction of open and dark excavation is provided with a crossbeam 8 above the dark excavation upper side guide hole 13 and the dark excavation upper middle guide hole 14, which effectively ensures the stability of the open-cut end wall 7 structure during construction and solves the problem of force conversion between open-cut construction and dark excavation construction.
[0084] In step S6, the main structure of the underground station is constructed by the hole pile method. First, a pilot tunnel is excavated, and then strip (pile) foundations, bottom longitudinal beams, side piles, middle columns, crown beams, and top longitudinal beams are constructed in the pilot tunnel to form a vertical force system and a transverse force support system. Then, the initial support arch is excavated and constructed. After the initial support arch, the second lining of the arch top is poured to form a transverse force support system. Finally, the soil is excavated downward layer by layer in the support system formed by the pile-beam-arch and the internal structure is constructed.
[0085] In step S2 and step S4, after the longitudinal excavation of the dark excavated lower side guide hole 11 is not less than 15 m, the retaining piles 9 within the range of the dark excavated lower middle guide hole 12 are chiseled out to construct the dark excavated lower middle guide hole 12;
[0086] After the longitudinal excavation of the upper side guide hole 13 is not less than 15 m, the retaining piles 9 within the range of the upper middle guide hole 14 are chiseled out, and the upper middle guide hole 14 is constructed.
[0087] In order to prevent the main structure pilasters 6 of the open-cut station from affecting the transportation of slag and materials, the width of the guide tunnel within the 3m length of the entry section of the dark-cut middle guide tunnel 12 is widened to 3.5m, and then gradually changes to the standard width of 3m.
[0088] Furthermore, it can also be considered in the embodiments that the main structure of the open-cut station is first constructed from bottom to top in step S1 to cast and form the bottom plate 1, the middle plate 3 of the second negative floor, the middle plate 4 of the first negative floor, the top plate 5, the side walls 2, the open-cut end walls 7 and the pilasters 6; after the shaft wall structure 30 of the transport shaft 10 is chiseled out in step S7, the casting is continued from bottom to top to form the bottom plate 1, the middle plate 3 of the second negative floor, the middle plate 4 of the first negative floor, the top plate 5, the side walls 2 and the remaining end walls 35 within the range of the transport shaft 10, which are integrally formed with the bottom plate 1, the middle plate 3 of the second negative floor, the middle plate 4 of the first negative floor, the top plate 5, the side walls 2 and the open-cut end walls 7 cast in step S1.
[0089] The construction is carried out simultaneously with the pouring of each layer of slabs, and the construction order is: bottom slab, side walls of the third negative floor and middle slab of the second negative floor, side walls of the second negative floor and middle slab of the first negative floor, side walls of the first negative floor and top slab.
[0090] Furthermore, in the embodiments, it can also be considered that in the step S1, a plurality of steel bar connectors 31 are reserved at the shaft wall structure 30 of the transport shaft 10, and after the construction of the dark excavation section is completed and the shaft wall structure 30 within the main structure of the open-cut station is chiseled out, the plurality of steel bar connectors 31 are respectively connected to the main steel bars of the main structure of the open-cut station, and the bottom plate 1, side wall 2, negative second floor middle plate 3, negative first floor middle plate 4, and top plate 5 within the range of the transport shaft 10 are cast and formed.
[0091] Furthermore, in the embodiment, it can be considered that in the step S1, when constructing the crossbeam 8, a steel connector of the lower unconstructed portion is reserved for casting the remaining end wall 35 from the crossbeam 8 to the upper portion of the arch of the main structure of the underground station.
[0092] In this embodiment, during the construction of the main structure of the open-cut station, steel bar connectors 31 for the bottom plate 1, the middle plate 3 of the second negative floor, the middle plate 4 of the first negative floor, the top plate 5 and the side wall 2, and the remaining end wall 35 of the main structure of the open-cut station are reserved at the shaft wall structure 30 of the transport shaft 10. After the construction of the dark excavation section is completed, the shaft wall structure 30 of the transport shaft 10 within the scope of the main structure of the open-cut station is chiseled out, and after the steel bar connectors 31 are connected to the steel bars of the main structure of the open-cut station, the main structure layers and side walls 2 within the scope of the transport shaft 10 are poured.
[0093] At the same time, the remaining end wall 35 is cast, and the steel bars of the remaining end wall 35 are connected to the steel bar connector 31 reserved at the shaft wall structure 30 and the steel bar connector reserved at the cross beam 8 below the open-cut end wall 7 to form a whole. The part within the range of the transport shaft 10 and the part below the cross beam 8 to the upper part of the arch of the main structure of the dark-cut station are cast at the same time and formed into one piece. Fig.10 shown.
[0094] It should be noted that in the above embodiment, the construction of the side wall 2 is cast simultaneously with the pouring of each layer of slabs, and the construction order is: bottom slab 1, side wall 2 of the negative third floor and middle slab 3 of the negative second floor, side wall 2 of the negative second floor and middle slab 4 of the negative first floor, side wall 2 and top slab 5 of the negative first floor.
[0095] Furthermore, in the embodiment, it can also be considered that in the step S2, the bottom of the lower side guide tunnel 11 and the lower middle guide tunnel 12 are lower than the base plate 1, and after the lower side guide tunnel 11 and the lower middle guide tunnel 12 enter the dark excavation section, the initial support 19 of the lower layer of the dark excavation guide tunnel is first constructed, and a temporary invert 20 for the dark excavation guide tunnel is erected to form a closed initial support structure and a downward construction ramp. After the guide tunnel is constructed for a certain distance, the soil at the ramp is reversed to form a complete small guide tunnel grid 21, and medium-coarse sand 22 is backfilled to level the height difference with the base plate 1 to form a construction and transportation channel.
[0096] In this embodiment, after the lower side guide tunnel 11 and the lower middle guide tunnel 12 are cut into the dark excavation section, the lower layer of the dark excavation guide tunnel initial support 19 is constructed first, and a temporary invert is erected to form a closed initial support structure, and at the same time a downward construction ramp is formed, thereby reducing the construction risk;
[0097] After the guide tunnel is constructed forward for a certain distance, the soil at the slope is back-excavated to form a complete small guide tunnel grid 21, and medium-coarse sand 22 is backfilled, which solves the height difference problem between the dark-cut guide tunnel and the open-cut section bottom plate 1; an inclined guide tunnel is set between the middle guide tunnel and the side guide tunnel, which creatively solves the problems of limited space, difficult transportation and feeding of slag, and low construction efficiency in constructing a dark-cut subway station from an open-cut subway station, which can greatly improve construction efficiency, shorten construction period, and reduce project investment.
[0098] Furthermore, in the embodiments, it can also be considered that in the step S2, grouting is performed from between the retaining piles 9 into the soil between the lower and middle guide tunnels 12 to form a grouting reinforcement 17 between the lower and middle guide tunnels; and in the step S4, grouting is performed from between the retaining piles 9 into the soil between the upper and middle guide tunnels 14 to form a grouting reinforcement 18 between the upper and middle guide tunnels.
[0099] In this embodiment, grouting reinforcement is performed between the retaining piles 9 to the soil between the upper and lower middle guide tunnels 14 and 12 to ensure the stability of the soil between the small clearance tunnels.
[0100] Furthermore, it can also be considered in the embodiment that in the step S2, the tunnel entrance section of the dark-excavated lower middle guide tunnel 12 is partially widened and then gradually becomes a standard width.
[0101] Furthermore, it can also be considered in the embodiment that in the step S4, the tunnel entry section of the upper middle guide tunnel 14 is partially widened and then gradually becomes a standard width.
[0102] In this embodiment, in order to prevent the wall columns 6 of the open-cut main structure that have been constructed from affecting the transportation of debris and materials, the entrance sections of the 3m length of the concealed lower middle guide tunnel 12 and the concealed upper middle guide tunnel 14 are widened to 3.5m, and then gradually changed back to the standard width of 3m.
[0103] Furthermore, in the embodiment, it can also be considered that in the steps S3 and S5, the lower inclined guide tunnel 15 is arranged between the lower side guide tunnel 11 of the dark excavation and the lower middle guide tunnel 12 of the dark excavation, and the upper inclined guide tunnel 16 is arranged between the upper side guide tunnel 13 of the dark excavation and the upper middle guide tunnel 14 of the dark excavation.
[0104] The above embodiments describe the present invention in detail, but the contents are only preferred embodiments of the present invention and cannot be considered to limit the scope of the present invention. All equivalent changes and improvements made within the scope of the present invention should still fall within the scope of the present invention.
Claims
1. A construction method for constructing a dark-cut subway station from an open-cut subway station, characterized in that: The following steps are involved: Step S1: construct an open-cut subway station structure and reserve construction conditions for the dark-cut part; Construct retaining piles (9), and after completion, excavate downwards and simultaneously erect steel supports until the bottom of the foundation pit is reached, then construct the open-cut station main structure, open-cut end wall (7) and transport shaft (10) at the junction of open and dark excavation; The open-cut end wall (7) is constructed to the top of the dark-cut upper side guide hole (13) and the dark-cut upper middle guide hole (14), and the crossbeam (8) is constructed; The transport shaft (10) is formed by partially expanding the retaining piles (9) and is provided with a shaft wall structure (30); Step S2: constructing a dark-cut lower side guide tunnel (11) and a dark-cut lower middle guide tunnel (12) from within the open-cut station; After the main structure of the open-cut station is completed, a double row of advanced small guide pipes are constructed between the retaining piles (9) to reinforce the soil of the arch tops of the dark-cut lower side guide tunnel (11) and the dark-cut lower middle guide tunnel (12). At the same time, grouting reinforcement (17) between the lower middle guide tunnels is constructed to reinforce the soil between the dark-cut lower middle guide tunnels (12) to ensure the stability of the soil between the small clear distance tunnels. After the reinforcement is completed, the open-cut station main structure retaining piles (9) within the range of the dark-cut lower side guide hole (11) and the dark-cut lower middle guide hole (12) are removed, five first grid steel frames (33) are connected, and the steel bars (32) in the retaining piles (9) are welded firmly to the first grid steel frames (33), and then the dark-cut lower side guide hole (11) and the dark-cut lower middle guide hole (12) are excavated; Step S3: constructing a lower layer inclined guide tunnel (15); The first advance small pipe (23) is used to reinforce the soil of the arch of the lower inclined guide tunnel (15), and the first steel support (24) is set above the arch. After completion, the initial support (19) of the lower dark-excavated guide tunnel within the range of the lower inclined guide tunnel (15) is removed, and the lower inclined guide tunnel (15) is excavated. After entering the tunnel, three lower inclined guide tunnel grilles (25) are erected in succession. The lower inclined guide tunnel grilles (25) are placed perpendicular to the grilles of the middle guide tunnel and the side guide tunnels. Step S4: constructing a dark excavation upper side guide tunnel (13) and a dark excavation upper middle guide tunnel (14) from within the open-cut station; A double row of advanced small guide pipes are constructed between the retaining piles (9) to reinforce the soil of the arch tops of the upper side guide tunnel (13) and the upper middle guide tunnel (14) of the dark excavation, and at the same time, grouting reinforcement (18) is constructed between the upper middle guide tunnels to reinforce the soil between the upper middle guide tunnels (14) of the dark excavation to ensure the stability of the soil between the small clear distance tunnels; After the reinforcement is completed, the open-cut station main structure retaining piles (9) within the range of the dark excavated upper side guide hole (13) and the dark excavated upper middle guide hole (14) are removed, five second grid steel frames (34) are connected and the steel bars (32) in the retaining piles (9) are welded to the second grid steel frames (34) firmly, and then the dark excavated upper side guide hole (13) and the dark excavated upper middle guide hole (14) are excavated; Step S5: constructing an upper inclined guide tunnel (16); The soil of the vault of the upper inclined guide tunnel (16) is reinforced by grouting with a second advanced small guide tube (26), a second steel support (27) is set up above the vault, the initial support (29) of the upper dark-cut guide tunnel within the range of the upper inclined guide tunnel (16) is removed, the upper inclined guide tunnel (16) is excavated, and three upper inclined guide tunnel grids (28) are erected after entering the tunnel. The upper inclined guide tunnel grids (28) are placed perpendicular to the middle guide tunnel and the side guide tunnel grids; Step S6: Constructing the main structure of the station by dark excavation using the pile method; According to the hole pile method process, a vertical force bearing system and a horizontal force bearing support system are formed in the dark excavation lower side guide hole (11), the dark excavation lower middle guide hole (12), the dark excavation upper side guide hole (13), and the dark excavation upper middle guide hole (14); Excavate the soil from top to bottom and construct the main structure of the underground station; Step S7: construct the remaining main structure of the open-cut end wall (7) at the junction of open-cut and dark-cut; Chiseling away the retaining piles (9) within the range of the remaining open-cut end wall (7), chiseling away the shaft wall structure (30) of the transport shaft (10), and casting the remaining end wall (35); The remaining end wall (35) includes a portion within the range of the transport shaft (10) and a portion from the bottom of the crossbeam (8) to the upper portion of the arch of the main structure of the underground excavation station, and the two portions are cast simultaneously and formed in one piece; The main structure of the open-cut station is first constructed from bottom to top in step S1, by casting to form a bottom plate (1), a middle plate (3) of the second negative floor, a middle plate (4) of the first negative floor, a top plate (5), side walls (2), an open-cut end wall (7) and a pilaster (6); after the shaft wall structure (30) of the transport shaft (10) is removed in step S7, casting is continued from bottom to top to form a bottom plate (1), a middle plate (3) of the second negative floor, a middle plate (4) of the first negative floor, a top plate (5), side walls (2) and a remaining end wall (35) within the range of the transport shaft (10), which are integrally formed with the bottom plate (1), the middle plate (3) of the second negative floor, the middle plate (4) of the first negative floor, a top plate (5), side walls (2) and an open-cut end wall (7) cast in step S1; In the step S1, a plurality of steel bar connectors (31) are reserved at the shaft wall structure (30) of the transport shaft (10), and after the dark excavation section is completed and the shaft wall structure (30) within the main structure of the open-cut station is removed, the plurality of steel bar connectors (31) are respectively connected to the main steel bars of the main structure of the open-cut station, and the bottom plate (1), side wall (2), negative second floor middle plate (3), negative first floor middle plate (4), and top plate (5) within the range of the transport shaft (10) are cast; In the step S2, the bottoms of the lower side guide tunnel (11) and the lower middle guide tunnel (12) are lower than the bottom plate (1). After the lower side guide tunnel (11) and the lower middle guide tunnel (12) enter the dark excavation section, the lower layer of the dark excavation guide tunnel initial support (19) is firstly applied, and a temporary back arch (20) of the dark excavation guide tunnel is erected to form a closed initial support structure and a downward construction ramp. After the guide tunnel is constructed for a certain distance, the soil at the ramp is reversed to form a complete small guide tunnel grid (21), and medium-coarse sand (22) is backfilled to level the height difference with the bottom plate (1) to form a construction and transportation channel.
2. The method for constructing a dark-cut subway station from an open-cut subway station according to claim 1, characterized in that: In the step S1, when constructing the crossbeam (8), a steel bar connector of the lower unconstructed portion is reserved for casting the remaining end wall (35) from the crossbeam (8) to the upper portion of the arch of the main structure of the underground station.
3. The method for constructing a dark-cut subway station from an open-cut subway station according to claim 1, characterized in that: In the step S2, grouting is performed between the retaining piles (9) into the soil between the lower middle guide holes (12) dug secretly, thereby forming grouting reinforcement (17) between the lower middle guide holes; and in the step S4, grouting is performed between the retaining piles (9) into the soil between the upper middle guide holes (14) dug secretly, thereby forming grouting reinforcement (18) between the upper middle guide holes.
4. The method for constructing a dark-cut subway station from an open-cut subway station according to claim 1, characterized in that: In the step S2, the entrance section of the dark-excavated lower middle guide tunnel (12) is partially widened and then gradually becomes a standard width.
5. The construction method of constructing a dark-cut subway station from an open-cut subway station according to claim 1, characterized in that: In the step S4, the entrance section of the dark excavated upper middle guide tunnel (14) is partially widened and then gradually becomes a standard width.
6. The construction method of constructing a dark-cut subway station from an open-cut subway station according to claim 1, characterized in that: In the steps S3 and S5, the lower inclined guide hole (15) is arranged between the lower side guide hole (11) of the dark excavation and the lower middle guide hole (12), and the upper inclined guide hole (16) is arranged between the upper side guide hole (13) of the dark excavation and the upper middle guide hole (14).