Photovoltaic field energy storage optimization configuration method and system

By periodically obtaining and clustering battery status parameters, the charging sequence and power distribution of the photovoltaic field energy storage system are optimized, and the problem of changes in battery capacity and charging speed is solved, the stability and adaptability of the system are improved, and more efficient Energy storage management.

CN118659423BActive Publication Date: 2024-11-15ELECTRIC POWER RESEARCH INSTITUTE OF STATE GRID QINGHAI ELECTRIC POWER COMPANY +2
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202410681364.4
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-05-29
Publication Date
2024-11-15
Estimated Expiration
2044-05-29

AI Technical Summary

Technical Problem

In the energy storage management of existing photovoltaic field energy storage systems, there are problems in the problem that the changes in battery capacity and charging speed are difficult to accurately measure, the battery usage cannot be optimized, and the energy storage speed is lower than the power generation speed.

Method used

By periodically obtaining the state parameters of energy storage batteries, clustering the battery packs, determining the capacity and charging speed of each battery, and optimizing the charging sequence and power allocation based on the predicted power generation and external power, ensuring the battery using the charging priority model charging efficiency and safety.

Benefits of technology

It improves the stability and reliability of the system, balances charge and discharge, reduces fluctuations in the system operation, improves the ability to adapt to changes in the external environment, and maximizes the utilization rate of the battery.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118659423B_ABST
    Figure CN118659423B_ABST
Patent Text Reader

Abstract

The present invention belongs to the field of image processing, and provides a method and system for optimizing the configuration of energy storage in a photovoltaic field, including: periodically obtaining the state parameters of energy storage batteries; clustering the energy storage batteries according to the state parameters to obtain multiple battery groups; at the beginning of each cycle, charging any battery in each of the battery groups, obtaining the capacity and charging speed of the charged battery, and determining the capacity and charging speed of the charged battery as the capacity and charging speed of the battery in the corresponding battery group; predicting the photovoltaic power generation and external transmission power within a preset time; determining the order of the charging batteries and the charging power within the preset time according to the predicted power generation, external transmission power and the capacity and charging speed of each battery. The above scheme can accurately optimize the configuration of energy storage batteries.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention belongs to the field of photovoltaic field energy storage, and in particular relates to a photovoltaic field energy storage optimization configuration method and system. Background Art

[0002] Photovoltaic field energy storage refers to the integration of energy storage equipment in the photovoltaic power generation system to store the electricity generated by photovoltaic power generation during the day and release the electricity when needed, thereby realizing the dispatch and management of electricity. Photovoltaic field energy storage systems are usually composed of photovoltaic battery groups, energy storage control systems and distribution systems.

[0003] When there is sufficient sunlight during the day, the photovoltaic array converts solar energy into direct current, supplies it to the load, and transmits excess electricity to the grid. At this stage, the photovoltaic array will generate a lot of electricity, but due to grid demand and load restrictions, it may not be possible to fully utilize all the generated electricity.

[0004] During the peak period of photovoltaic power generation or the low period of grid demand, the photovoltaic field energy storage system stores excess electricity in energy storage devices such as lithium batteries, sodium sulfur batteries, supercapacitors, etc. This can avoid the waste caused by the photovoltaic power generation system because the electricity cannot be used in time.

[0005] However, there are still many problems with the existing photovoltaic field energy storage. On the one hand, the existing photovoltaic field usually uses batteries for energy storage, but as the battery is used, the battery capacity and charging speed will change, and the battery capacity and charging speed can only be accurately measured during charging, and it is difficult to accurately obtain them before charging, resulting in the energy storage system being unable to accurately assess the energy that can be charged and whether the energy storage can be completed in time. On the other hand, the existing energy storage management system cannot fully consider the capacity, charging speed and number of cycles of different batteries. Each time, the batteries are fully charged in turn, and it is impossible to efficiently complete energy storage with minimal damage to the battery, which may cause the energy storage speed to be lower than the power generation speed. Summary of the invention

[0006] In order to solve the problems in the prior art, the present invention provides a photovoltaic field energy storage optimization configuration method, comprising the following steps: periodically obtaining state parameters of energy storage batteries; clustering the energy storage batteries according to the state parameters to obtain multiple battery groups; at the beginning of each cycle, charging any one battery in each of the battery groups, obtaining the capacity and charging speed of the charged battery, and determining the capacity and charging speed of the charged battery as the capacity and charging speed of the battery in the corresponding battery group; predicting the photovoltaic power generation power and external transmission power within a preset time; determining the charging battery sequence and charging power within the preset time according to the predicted power generation power, external transmission power and the capacity and charging speed of each battery.

[0007] Further, determining the order of charging batteries and charging power within the preset time according to the predicted power generation, external transmission power, and the capacity and charging speed of each battery includes:

[0008] Define a charging priority P i

[0009]

[0010] in

[0011] α and β are weight parameters used to adjust the impact of charge and discharge times and time intervals. i is the number of charge and discharge times of battery i, T i is the time when battery i was last charged and discharged, and t is the current time;

[0012] Maximize the sum of charging priorities of all batteries:

[0013]

[0014] Where E i is the charging capacity of the allocated battery i, N is the total number of batteries;

[0015] Capacity constraint: the charge of each battery cannot exceed its capacity and the remaining charge:

[0016] 0≤E i ≤C i ·(1-SOC i )

[0017] Among them C i is the capacity of battery i, SOC i is the current state of charge of battery i;

[0018] The total power generation constraint states that the total charge allocated to all batteries cannot exceed the total available power generation:

[0019] Charging rate constraint: the charging power of each battery cannot exceed its maximum charging rate:

[0020] E i ≤r i ·C i

[0021] where r i It represents the ratio of the amount of electricity that can be safely charged into the battery per hour relative to its capacity; the charging speed constraint, the charging speed needs to be no less than the photovoltaic power generation speed, then

[0022] Where Δt is the time step, P solar is the predicted power of photovoltaic power generation, Pout is the external power output; the whole model is:

[0023]

[0024] Optimization goals

[0025] 0≤E i ≤C i ·(1-SOC i )

[0026]

[0027] E i ≤r i ·C i

[0028]

[0029] By solving the above model, we can get the charging priority and charging capacity of each battery.

[0030] Furthermore, the last charge / discharge power, internal resistance, number of cycles, and open circuit voltage.

[0031] Furthermore, the period is one month.

[0032] Furthermore, the preset time is 1 hour.

[0033] Another aspect of the present invention is to provide a photovoltaic field energy storage optimization configuration system, which includes the following modules:

[0034] An acquisition module, used to periodically acquire state parameters of the energy storage battery;

[0035] A clustering model, used for clustering the energy storage batteries according to the state parameters to obtain a plurality of battery groups;

[0036] A measuring module, used for charging any battery in each of the battery packs at the beginning of each cycle, obtaining the capacity and charging speed of the charged battery, and determining the capacity and charging speed of the charged battery as the capacity and charging speed of the battery in the corresponding battery pack;

[0037] Prediction module, used to predict photovoltaic power generation and external transmission power within a preset time;

[0038] The configuration module is used to determine the order of charging batteries and the charging power within the preset time according to the predicted power generation, external transmission power, and the capacity and charging speed of each battery.

[0039] The present invention can produce the following beneficial effects through the above technical solution:

[0040] By periodically acquiring the state parameters of the energy storage battery and clustering the batteries into multiple battery groups based on these parameters, the state and characteristics of the battery can be better understood. Then, at the beginning of each cycle, a battery in the battery group is charged and tested, and the capacity and charging speed of the battery group are determined based on the test results. This can effectively evaluate the state of each battery group and determine the charging order based on its capacity and charging speed, maximizing the utilization of the battery.

[0041] By periodically monitoring the battery status and optimizing the charging strategy, the stability and reliability of the system can be improved. Reasonable charging sequence and charging power distribution can balance the charge and discharge of the system, reduce fluctuations during system operation, and improve the system's adaptability to changes in the external environment.

[0042] Under the premise of determining the different capacity speeds of each battery, determine the charging order and charging amount of each battery, and ensure that batteries with low cycle times are charged first, while ensuring that no battery is not charged for too long. BRIEF DESCRIPTION OF THE DRAWINGS

[0043] In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings required for use in the embodiments will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.

[0044] Figure 1 is a flow chart of the method of the present invention. DETAILED DESCRIPTION

[0045] Below, the invention is preferably described in conjunction with the accompanying drawings and specific implementation methods.

[0046] This embodiment solves the above problem through the following steps:

[0047] In one embodiment, reference Figure 1 The present invention provides a method for optimizing the configuration of photovoltaic field energy storage.

[0048] The state parameters of the battery reflect the capacity and charging speed of the battery. In the prior art, the state parameters of the battery are usually detected to determine the capacity and charging speed of the battery by fitting or machine learning. However, the capacity and charging speed are also affected by the environment, especially parameters such as temperature. In addition, a large amount of known data is required to establish a prediction model, otherwise the prediction model will have a large error.

[0049] In this embodiment, in order to determine the capacity and charging speed of the battery, the state parameters of the energy storage battery are first periodically obtained. For example, once a month. The relevant parameters include the last charge / discharge power (Charge / Discharge Power), internal resistance, number of cycles and open circuit voltage.

[0050] These status parameters can be monitored and obtained in real time through the battery management system (BMS). BMS is a key component of the photovoltaic field energy storage system, responsible for monitoring, controlling and managing the battery charging and discharging process to ensure the safety, performance and reliability of the battery.

[0051] The energy storage batteries are clustered according to the state parameters to obtain a plurality of battery groups.

[0052] Clustering energy storage batteries can help identify battery groups with similar characteristics and classify them according to their state parameters. Use clustering algorithms (such as K-means clustering) to divide batteries into multiple groups, each with similar state characteristics. Such classification can make the batteries in each battery group have similar capacity and charging speed.

[0053] This embodiment selects the last charge / discharge power, internal resistance, number of cycles and open circuit voltage as features. A clustering algorithm is used to cluster the batteries according to these features. The goal of the clustering algorithm is to divide the samples into several groups so that the samples in the same group have a high similarity, while the samples in different groups have a low similarity. In this way, multiple battery groups can be obtained, each with similar capacity and charging speed.

[0054] At the beginning of each cycle, any battery in each of the battery packs is charged, the capacity and charging speed of the charged battery are obtained, and the capacity and charging speed of the charged battery are determined as the capacity and charging speed of the battery in the corresponding battery pack. In this way, the state of the entire battery pack can be estimated by testing the state of the battery, and used for subsequent operation and optimization.

[0055] For example, during the first energy storage process of each month, in order to determine the status of each battery group, a battery in each battery group is randomly selected as a test battery and a charging test is performed.

[0056] Through such periodic testing and updating, the status of each battery pack can be understood in a timely manner, and the system operation and optimization can be carried out according to the latest status parameters. This method helps to better manage and maintain the energy storage system, improve the performance and reliability of the system, and avoid the prediction errors caused by the prediction algorithms in the existing technology.

[0057] Predict the photovoltaic power generation and transmission power within the preset time.

[0058] Use weather forecast data and the characteristics of photovoltaic power plants (such as photovoltaic panel area, tilt angle, orientation, etc.) to predict photovoltaic power generation within a preset time. Common prediction methods include statistical methods that combine meteorological data with historical power generation data, physical model methods based on meteorological data and photovoltaic system characteristics, and data-driven methods based on machine learning algorithms (such as neural networks, support vector machines, etc.).

[0059] The specific prediction method is not the focus of the present invention, and this embodiment does not limit the prediction method. Those skilled in the art can use any method in the prior art to perform prediction.

[0060] This embodiment uses 1 hour as the step size in the subsequent optimization process. For synchronization, the preset time is preferably 1 hour.

[0061] Transmission power refers to the power output to the grid, which is usually determined by the photovoltaic power generation system and the energy storage system. To predict transmission power, factors such as grid demand, grid capacity, and the operation strategy of the energy storage system need to be considered. Similar methods can be used to predict transmission power, such as statistical methods based on historical data and grid demand, physical model methods based on grid load forecasting, and data-driven methods based on machine learning algorithms.

[0062] After deducting the external transmission power, the remaining power is the power to be stored, which can be calculated by the difference between the photovoltaic power generation power and the external transmission power.

[0063] The order of charging the batteries and the charging power within the preset time are determined according to the predicted power generation, external transmission power, the capacity of each battery, and the charging speed.

[0064] According to the characteristics of energy storage batteries, the more times a battery is charged and discharged, the more it decays. At the same time, batteries cannot be left unused for a long time. Therefore, in order to give priority to batteries with fewer charge and discharge times and ensure that no battery is not charged or discharged for too long, a charging priority P is defined. i The priority is calculated based on the number of charge and discharge times and the last charge and discharge time.

[0065]

[0066] in

[0067] α and β are weight parameters used to adjust the impact of charge and discharge times and time intervals. i is the number of charge and discharge times of battery i, T i is the time (timestamp) when battery i was last charged and discharged, and t is the current time (timestamp).

[0068] It is hoped that under the constraint of the total available power generation E, the sum of the charging priorities of all batteries can be maximized, that is,

[0069]

[0070] Where E i is the charging capacity of the allocated battery i, N is the total number of batteries.

[0071] The following constraints should also be met:

[0072] Capacity constraint: the charge of each battery cannot exceed its capacity and the remaining charge:

[0073] 0≤E i ≤C i ·(1-SOC i )

[0074] Among them C i is the capacity of battery i, SOC i The total power generation capacity constraint for the current state of charge (power percentage) of battery i is that the total charge capacity allocated to all batteries cannot exceed the total available power generation capacity:

[0075]

[0076] Charging rate constraint: the charging power of each battery cannot exceed its maximum charging rate: To ensure that the charging power of the battery does not exceed its maximum charging rate, it is necessary to ensure

[0077]

[0078] where p i is the charging power of battery i, r i It indicates the ratio of the amount of electricity that can be safely charged into the battery per hour relative to its capacity. For example, if a battery has a capacity of 1000Wh and a maximum charging rate of 0.5C, then it can charge a maximum of 0.5×1000=500W per hour.

[0079] Δt is the time step, which is 1 hour in this embodiment, and the unit of power is watt, so the charging rate constraint is simplified to:

[0080] E i ≤r i ·C i

[0081] Charging speed constraint: the charging speed needs to be no less than the photovoltaic power generation speed, then

[0082]

[0083] Where Δt is the time step, which is 1 hour in this embodiment, P solar is the predicted power of photovoltaic power generation, P out is the external output power.

[0084] To sum up, the whole model is:

[0085]

[0086] Optimization goals

[0087] 0≤E i ≤C i ·(1-SOC i )

[0088]

[0089] E i ≤r i ·C i

[0090]

[0091] The above model as a whole is a linear programming problem. By solving the above problem (such as using linprog in the Matlab toolbox to solve it), the charging priority and charging amount of each battery can be obtained.

[0092] The above method can determine the charging order and charging amount of each battery under the premise of determining the different capacity speed of each battery, and ensure that batteries with low cycle times are charged first, while ensuring that no battery is not charged for too long.

[0093] This implementation can better understand the state and characteristics of the battery by periodically acquiring the state parameters of the energy storage battery and clustering the batteries into multiple battery groups based on these parameters. Then, at the beginning of each cycle, a battery in the battery group is charged and tested, and the capacity and charging speed of the battery group are determined based on the test results. This can effectively evaluate the state of each battery group and determine the charging order based on its capacity and charging speed to maximize the utilization of the battery.

[0094] By periodically monitoring the battery status and optimizing the charging strategy, the stability and reliability of the system can be improved. Reasonable charging sequence and charging power distribution can balance the charge and discharge of the system, reduce fluctuations during system operation, and improve the system's adaptability to changes in the external environment.

[0095] On the other hand, the present invention also provides a photovoltaic field energy storage optimization configuration system, comprising:

[0096] An acquisition module, used to periodically acquire state parameters of the energy storage battery;

[0097] A clustering model, used for clustering the energy storage batteries according to the state parameters to obtain a plurality of battery groups;

[0098] A measuring module, used for charging any battery in each of the battery packs at the beginning of each cycle, obtaining the capacity and charging speed of the charged battery, and determining the capacity and charging speed of the charged battery as the capacity and charging speed of the battery in the corresponding battery pack;

[0099] Prediction module, used to predict photovoltaic power generation and external transmission power within a preset time;

[0100] The configuration module is used to determine the order of charging batteries and the charging power within the preset time according to the predicted power generation, external transmission power, and the capacity and charging speed of each battery.

[0101] Furthermore, the specific implementation methods of the above-mentioned photovoltaic field energy storage optimization configuration system are the same as a photovoltaic field energy storage optimization configuration method, and all further technical solutions in a photovoltaic field energy storage optimization configuration method are completely introduced into a photovoltaic field energy storage optimization configuration system.

[0102] Finally, it should be noted that the above embodiments are only used to illustrate the technical solutions of the present invention rather than to limit it. Although the present invention has been described in detail with reference to the above embodiments, ordinary technicians in the relevant field should understand that the specific implementation methods of the present invention can still be modified or replaced by equivalents. Any modification or equivalent replacement that does not depart from the spirit and scope of the present invention should be covered within the scope of protection of the claims of the present invention.

[0103] The present invention does not particularly specify the structure of some modules, which shall be subject to the contents recorded in the prior art. The prior art mentioned in the above background technology section and the specific embodiment section of the present invention can be used as part of the present invention to understand the meaning of some technical features or parameters. The scope of protection of the present invention shall be subject to the contents actually recorded in the claims.

Claims

1. A photovoltaic field energy storage optimization configuration method, Features: Periodically obtain status parameters of the energy storage battery; Clustering the energy storage batteries according to the state parameters to obtain a plurality of battery groups; At the beginning of each cycle, any one battery in each of the battery packs is charged, the capacity and charging speed of the charged battery are obtained, and the capacity and charging speed of the charged battery are determined as the capacity and charging speed of the battery in the corresponding battery pack; Predict photovoltaic power generation and external transmission within a preset time; Determining the order of charging batteries and charging power within the preset time according to the predicted power generation, external transmission power, and the capacity and charging speed of each battery; The step of determining the order of charging batteries and the charging power within the preset time according to the predicted power generation, external transmission power, and the capacity and charging speed of each battery includes: Define a charging priority P i in α and β are weight parameters used to adjust the impact of charge and discharge times and time intervals. i is the number of charge and discharge times of battery i, T i is the time when battery i was last charged and discharged, and t is the current time; Maximize the sum of charging priorities of all batteries: Where E i is the charging capacity of the allocated battery i, N is the total number of batteries; Capacity constraint: the charge of each battery cannot exceed its capacity and the remaining charge: 0≤E i ≤C i ·(1-SOC i ) Among them C i is the capacity of battery i, SOC i is the current state of charge of battery i; The total power generation constraint states that the total charge allocated to all batteries cannot exceed the total available power generation E: Charging rate constraint: the charging power of each battery cannot exceed its maximum charging rate: AND i ≤r i ·C i where r i It indicates the ratio of the amount of electricity that can be safely charged into the battery per hour relative to its capacity; Charging speed constraint: the charging speed needs to be no less than the photovoltaic power generation speed, then Where Δt is the time step, P solar is the predicted power of photovoltaic power generation, P out is the external output power; The entire model is: Optimization goals 0≤E i ≤C i ·(1-SOC i ) AND i ≤r i ·C i By solving the above model, we can get the charging priority and charging capacity of each battery.

2. A photovoltaic field energy storage optimization configuration method according to claim 1, Features The state parameters include: last charge / discharge power, internal resistance, number of cycles, and open circuit voltage.

3. A photovoltaic field energy storage optimization configuration method according to claim 1, Features The period is one month.

4. A photovoltaic field energy storage optimization configuration method according to claim 1, Features The preset time is 1 hour.

5. A photovoltaic field energy storage optimization configuration system, Features The system includes the following modules: An acquisition module, used to periodically acquire state parameters of the energy storage battery; A clustering model, used for clustering the energy storage batteries according to the state parameters to obtain a plurality of battery groups; A measuring module, used for charging any battery in each of the battery packs at the beginning of each cycle, obtaining the capacity and charging speed of the charged battery, and determining the capacity and charging speed of the charged battery as the capacity and charging speed of the battery in the corresponding battery pack; Prediction module, used to predict photovoltaic power generation and external transmission power within a preset time; A configuration module, used to determine the order of charging batteries and charging power within the preset time according to the predicted power generation, external transmission power, and the capacity and charging speed of each battery; The configuration module uses the following method to implement configuration: Define a charging priority P i in α and β are weight parameters used to adjust the impact of charge and discharge times and time intervals. i is the number of charge and discharge times of battery i, T i is the time when battery i was last charged and discharged, and t is the current time; Maximize the sum of charging priorities of all batteries: Where E i is the charging capacity of the allocated battery i, N is the total number of batteries; Capacity constraint: the charge of each battery cannot exceed its capacity and the remaining charge: 0≤E i ≤C i ·(1-SOC i ) Among them C i is the capacity of battery i, SOC i is the current state of charge of battery i; The total power generation constraint states that the total charge allocated to all batteries cannot exceed the total available power generation E: Charging rate constraint: the charging power of each battery cannot exceed its maximum charging rate: AND i ≤r i ·C i where r i It indicates the ratio of the amount of electricity that can be safely charged into the battery per hour relative to its capacity; Charging speed constraint: the charging speed needs to be no less than the photovoltaic power generation speed, then Where Δt is the time step, P solar is the predicted power of photovoltaic power generation, P out is the external output power; The entire model is: Optimization goals 0≤E i ≤C i ·(1-SOC i ) AND i ≤r i ·C i By solving the above model, we can get the charging priority and charging capacity of each battery.

6. A photovoltaic field energy storage optimization configuration system according to claim 5, Features The state parameters include: last charge / discharge power, internal resistance, number of cycles, and open circuit voltage.

7. A photovoltaic field energy storage optimization configuration system according to claim 5, Features The period is one month.

8. A photovoltaic field energy storage optimization configuration system according to claim 5, Features The preset time is 1 hour.