A digital integrated system and management and control platform based on BIM technology
Through the digital integrated system based on BIM technology, the problem of information dispersed storage and management in traditional project management is solved, and the efficient integration and management of information is realized, the efficiency of project management and control and construction accuracy are improved, and the visibility and Real-time dynamic control.
Patent Information
- Application Number
- CN202411189087.1
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-28
- Publication Date
- 2024-11-26
- Estimated Expiration
- 2044-08-28
AI Technical Summary
In traditional project management, different information of the same device is stored scattered, and the information stored in each location is not related, resulting in chaotic information management, low retrieval efficiency, and an island effect, which affects the efficiency of operation and maintenance management, and increases the risk of information loss, leading to system maintenance. High cost.
Adopt a digital integrated system based on BIM technology, data is collected and stored in the BIM model database to integrate and mine data, and combine GIS technology to build a BIM-GIS integration model to realize three-dimensional display and dynamic management of data, supporting multiple projects Position management.
It realizes efficient information management, avoids the island effect, improves project control efficiency, reduces the risk of information loss, reduces the cost of building space information, improves construction accuracy, and provides visibility and real-time dynamic control.
Smart Images

Figure CN118691236B_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the field of integrated management and control technology, and specifically to a digital intelligent integration system and a management and control platform based on BIM technology. Background Art
[0002] At present, in the traditional project management process, different information of the same equipment is stored in a scattered manner, and the information stored in each location is not associated, making it difficult to achieve efficient information management. The scattered storage method not only causes management confusion, but also has low information retrieval efficiency. There is an island effect between various types of information and they cannot be used for each other, which affects the overall work efficiency of building operation and maintenance management. In addition, scattered storage and management will increase the risk of information loss, and it is very easy to have incomplete information, resulting in high system maintenance costs. Based on the traditional different system management platforms, it is impossible to manage the project comprehensively; therefore, it does not meet the existing needs. For this reason, we propose a digital integrated system and management and control platform based on BIM technology. Summary of the invention
[0003] The purpose of the present invention is to provide a digital integration system and a management and control platform based on BIM technology. The system stores the data collected by each data collector in a BIM model database, integrates the data in the BIM model database and other data in the data interaction management and control platform, mines and analyzes the integrated data, and performs interactive data management on the integrated data after mining and analysis. Then, based on BIM technology and GIS technology, a BIM-GIS integration model is constructed to read and call the integrated data in the BIM model database, and three-dimensionally display the BIM model database data based on the BIM-GIS integration model, so as to achieve all-round management of the project's design, investment, quality, safety, progress, personnel and environment, and achieve visual, real-time dynamic management and control. Users can access the system through PCs, mobile devices and AR terminals, which solves the problems raised in the above-mentioned background technology.
[0004] To achieve the above object, the present invention provides the following technical solution: a digital intelligent integration system based on BIM technology, including a data layer, an integration layer, a service layer, an application layer and an access layer:
[0005] The data layer is used to:
[0006] Collect data and store it in the BIM model database, and confirm and process the building data in the BIM model database;
[0007] The integration layer is used to:
[0008] Provide a unified data interface, provide interfaces and shared BIM model databases for the service layer and application layer, integrate data in the BIM model database and other data in the data interaction management and control platform, and mine and analyze the integrated data;
[0009] The service layer is used to:
[0010] The data mined and analyzed at the integration layer is automatically transmitted to the model components through the Internet of Things. Based on BIM technology and GIS technology, a BIM-GIS integration model is constructed, and the BIM-GIS integration model is displayed in the integrated management and control platform through the application layer;
[0011] The application layer is used to:
[0012] The integrated data is called uniformly, by reading and calling the integrated data in the BIM model database, and displaying the BIM model database data in three dimensions based on the BIM-GIS integration model;
[0013] The BIM-GIS integrated model is linked to the BIM model database data to reflect the multi-faceted management of the project’s design, investment, quality, safety, progress, personnel and environment. When an abnormality or alarm occurs, the digital integration system automatically locates the corresponding BIM-GIS integrated model so that management and control personnel can respond in a timely manner.
[0014] The access layer is used to:
[0015] Users log in and access the digital integration system based on PCs, mobile devices and AR terminals. Users include construction units, design units, supervision units, construction units and operation and maintenance units.
[0016] Furthermore, the data layer is specifically:
[0017] Using each data collector to perform real-time monitoring to collect data monitored in real time by each data collector;
[0018] The data collected by each data collector is collected centrally through 5G communication technology, and then the various data collected centrally are transmitted to the BIM model database for storage through 5G communication technology;
[0019] Confirm the BIM model database, confirm the building data in the BIM model database, and process the confirmed building data.
[0020] Furthermore, the integration layer is specifically:
[0021] Integrate the data in the BIM model database and other data in the interactive management and control platform based on data interface and middleware technology;
[0022] Mining and analyzing the integrated data through artificial intelligence algorithms;
[0023] Among them, artificial intelligence algorithms use machine learning algorithms for data mining;
[0024] Data mining, including:
[0025] Data preprocessing: Before data mining, data is preprocessed to provide a basis for subsequent analysis, including data cleaning and data transformation processes;
[0026] Feature selection and extraction: Through feature selection, predictive features are selected from the preprocessed data center. Through feature extraction, features that are helpful for modeling are extracted from the preprocessed data. Feature selection and extraction provide the basis for subsequent model construction.
[0027] Conduct interactive data management and control on the integrated data after mining and analysis;
[0028] Among them, interactive data management includes project management, risk management, schedule management, quality management and cost management.
[0029] Furthermore, the application layer includes:
[0030] Design management module for:
[0031] Carry out design management, coordinate, control and supervise the entire design process of construction projects, including the preparation of design plans, design review and management of design changes;
[0032] Investment management module for:
[0033] Carry out investment management and conduct scientific and reasonable control over the investment of construction projects, including investment budget preparation, investment source selection, fund planning and control, risk management and decision support;
[0034] Quality management module for:
[0035] Carry out quality management, and scientifically and reasonably control the quality of construction projects, which is divided into quality management in the construction stage and quality management in the acceptance stage;
[0036] Security management module, used to:
[0037] Conduct safety management for workers involved in the project. The video surveillance system is connected to the safety management module so that the video screen can be switched at any time, and alarm information can be popped up and recorded in real time.
[0038] Schedule management module for:
[0039] Carry out progress management, formulate a progress plan for the work content, work procedures, duration and connection relationship of each stage of the construction project, and implement the progress plan. During the implementation process, check whether the actual progress is in accordance with the requirements of the progress plan, analyze the reasons for any deviations, and manage by taking remedial measures or adjusting and modifying the original progress plan;
[0040] Personnel management module for:
[0041] Carry out personnel management, scientifically and reasonably control the personnel of construction projects, and ensure that workers carry out construction according to the established schedule;
[0042] Environment management module for:
[0043] Carry out environmental management in accordance with air quality standards and green building standards, arrange air quality sensors for temperature and humidity, carbon dioxide, carbon monoxide, formaldehyde, PM2.5 and PM10, monitor and display indicators in real time, alarm when air quality exceeds the standard and link the ventilation and air conditioning system for processing.
[0044] Furthermore, the quality management module includes:
[0045] Quality management during the construction phase: Quality management during the construction phase of a construction project, including construction site management and quality inspection management;
[0046] Quality management during the acceptance phase: Quality management is carried out during the acceptance phase of construction projects, with a comprehensive assessment and inspection of the construction process and results, including quality assessment and testing as well as problem rectification and warranty period management.
[0047] Furthermore, the access layer includes:
[0048] Authentication module for:
[0049] Authentication is performed on the account that logs into the digital integration system. If the account verification passes, the user successfully logs into the digital integration system for access. If the account verification fails, an alarm message is sent to the integrated management and control platform.
[0050] Furthermore, the integration layer integrates the data in the BIM model database and other data in the data interaction management and control platform, including:
[0051] The first computing module is used for:
[0052] Perform n1 data analyses on the data in the BIM model database to obtain n1 first data analysis results; perform n2 data analyses on other data in the data interaction management and control platform to obtain n2 second data analysis results;
[0053] The first data analysis result and the second data analysis result are numerically processed, and the difference between the data in the BIM model database and other data in the data interaction management and control platform is calculated according to the numerically processed first data analysis result and the second data analysis result:
[0054] ;
[0055] in, It is the difference between the data in the BIM model database and other data in the data interaction management and control platform. is the sum of the n1 first data analysis results, is the sum of n2 second data analysis results, The sum of the squares of the n1 first data analysis results is calculated; The squares of n2 second data analysis results are summed;
[0056] Comparison module for:
[0057] The difference value is compared with a preset difference value; when it is determined that the difference value is greater than or equal to the preset difference value, a coarse matching strategy is adopted to perform data integration;
[0058] When it is determined that the difference value is less than the preset difference value, data feature extraction processing is performed on the data in the BIM model database to obtain a first feature vector;
[0059] Perform data feature extraction on other data in the data interaction management and control platform to obtain a second feature vector;
[0060] Calculate the similarity between the first feature vector and the preset feature vector in the standard database, and standardize the first feature vector according to the first preset feature vector corresponding to the maximum similarity to obtain a first target vector;
[0061] ;
[0062] Wherein, S is the similarity between the first feature vector and the preset feature vector; is the first eigenvector feature components; is the first feature vector of the preset feature components; is the number of characteristic components of the first characteristic vector, which is also the number of characteristic components of the preset characteristic vector, and the two are equal;
[0063] Calculate the similarity between the second feature vector and the preset feature vector in the standard database, and standardize the second feature vector according to the second preset feature vector corresponding to the maximum similarity to obtain a second target vector;
[0064] A fine matching strategy is adopted according to the first target vector and the second target vector to perform data integration.
[0065] Furthermore, the security management module includes:
[0066] An acquisition module, used to acquire monitoring images of workers participating in the project based on a video monitoring system;
[0067] An enhancement module is used to enhance the monitoring image to obtain an enhanced image;
[0068] Feature extraction module for:
[0069] Grayscale processing is performed on the enhanced image, and color space standardization processing is performed on the enhanced image after grayscale processing based on the Gamma correction method to obtain a processed image;
[0070] Calculate the gradient information of each pixel in the image;
[0071] Divide the processed image according to the gradient information to obtain several sub-processed images;
[0072] Counting the gradient histogram and the number of different gradients of each sub-processed image to form sub-features of the sub-processed image;
[0073] The sub-features of each sub-processed image are fused to obtain the HOG feature parameters of the processed image;
[0074] Matching modules for:
[0075] Determine the human characteristics of the workers participating in the project according to the HOG feature parameters, analyze and process the human characteristics, and determine the behavioral information of the workers participating in the project;
[0076] The behavior information is matched with the preset violation behavior information. When it is determined that the match degree is greater than the preset match degree threshold, an alarm message is popped up and recorded in real time.
[0077] Furthermore, the enhancement module includes:
[0078] The first determination module is used to:
[0079] Inputting the monitoring image into the filter to perform convolution operation and determine the first target image;
[0080] Performing image enhancement processing on the first target image according to the histogram enhancement method, performing feature extraction on the first target image after the image enhancement processing to obtain a first feature; performing clustering processing according to the first feature to obtain a first clustering center of the first target image;
[0081] The second determination module is used for:
[0082] Performing image difference processing on the monitoring image and the first target image to obtain a second target image;
[0083] Obtain the pixel values of each pixel in the second target image in the R channel, the G channel, and the B channel, and compare them to determine the minimum value of the same pixel in the three channels as the feature value of the pixel;
[0084] Generate a feature map based on the feature values of the pixels;
[0085] Set a sliding window with a size of m*m; determine the area with the largest average eigenvalue in the feature map as the target area; and use other areas in the feature map except the target area as areas to be adjusted;
[0086] Sliding the sliding window in the area to be adjusted to obtain a sub-area to be adjusted; calculating the distance between the central pixel point of the sub-area to be adjusted and the central pixel point of the target area; determining the first eigenvalue of the central pixel point of the target area;
[0087] The second computing module is used for:
[0088] According to the distance and the first eigenvalue, a preset distance-first eigenvalue-second eigenvalue data table is searched to determine a preset second eigenvalue of the central pixel of the sub-region to be adjusted;
[0089] Obtain the actual eigenvalue of the central pixel of the sub-region to be adjusted, calculate the difference between the second eigenvalue and the actual eigenvalue; calculate the ratio of the difference to the actual eigenvalue as the enhancement coefficient;
[0090] Performing image enhancement on other pixel points in the sub-region to be adjusted based on the enhancement coefficient, extracting features from the second target image after the image enhancement process to obtain a second feature; performing clustering process according to the second feature to obtain a second cluster center of the second target image;
[0091] The distance information between the first cluster center and the second cluster center is calculated, a preset data table is queried according to the distance information, a corresponding fusion strategy is determined, and image fusion processing is performed on the first target image and the second target image based on the fusion strategy to obtain an enhanced image.
[0092] A digital integrated management and control platform based on BIM technology, including:
[0093] BIM model database for:
[0094] Store the data collected by each data collector, integrate the stored data with other data in the interactive management and control platform, and the integrated data set provides data support for building the model;
[0095] Integrated management and control platform for:
[0096] Provide users with a three-dimensional display platform to display BIM model database data in three dimensions based on the BIM-GIS integrated model. Users can access the integrated management and control platform through PCs, mobile devices and AR terminals.
[0097] Compared with the prior art, the present invention has the following beneficial effects:
[0098] The data layer of the present invention collects data from various data collectors and stores them in the BIM model database. The integration layer can integrate the data in the BIM model database and other data in the data interaction management and control platform. Through data integration, the island effect between various types of data can be avoided and they cannot be used for each other. Complete and accurate data support is provided for the service layer and the application layer. The integrated data is mined and analyzed, and the integrated data after mining and analysis is interactively managed. Then, based on BIM technology and GIS technology, the service layer automatically transmits the data mined and analyzed by the integration layer to the model component through the Internet of Things, and a BIM-GIS integrated model can be constructed and displayed. BIM technology can provide accurate height, appearance size and internal space information of the building, etc., and combined with GIS technology, it can share building space information and surrounding geographical environment, reduce the cost of building space information, and help evaluate the construction accuracy of the project. The application layer can perform three-dimensional display of BIM model database data based on the BIM-GIS integrated model, thereby managing the design, investment, quality, safety, progress, personnel and environment of the project in all directions, and users can access it through PCs, mobile devices and AR terminals, so as to achieve visual and real-time dynamic management and control. BRIEF DESCRIPTION OF THE DRAWINGS
[0099] Figure 1 It is a structural schematic diagram of the digital intelligent integration system based on BIM technology of the present invention;
[0100] Figure 2 It is a schematic diagram of the structure of the application layer of the present invention. DETAILED DESCRIPTION
[0101] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0102] In order to solve the problem that different information of the same device is stored in a scattered manner in the existing project management and control process, and the information stored in each location is not associated, it is difficult to achieve efficient information management. The scattered storage method has an island effect between various types of information and cannot be used by each other, which affects the overall work efficiency of project management and control. In addition, scattered storage and management will increase the risk of information loss, and it is very easy to have incomplete information, resulting in high system maintenance costs. Please refer to Figure 1-Figure 2 , this embodiment provides the following technical solutions:
[0103] A digital and intelligent integration system based on BIM technology, including data layer, integration layer, service layer, application layer and access layer:
[0104] Data layer, used for:
[0105] Collect data and store it in the BIM model database, and confirm and process the building data in the BIM model database;
[0106] Integration layer for:
[0107] Provide a unified data interface, provide an interface and a shared BIM model database for the service layer and application layer, integrate the data in the BIM model database and other data in the data interaction management and control platform, and mine and analyze the integrated data;
[0108] The service layer is used to:
[0109] The data mined and analyzed at the integration layer is automatically transmitted to the model components through the Internet of Things. Based on BIM technology and GIS technology, a BIM-GIS integration model is constructed, and the BIM-GIS integration model is displayed in the integrated management and control platform through the application layer;
[0110] Application layer, used for:
[0111] The integrated data is called uniformly, by reading and calling the integrated data in the BIM model database, and displaying the BIM model database data in three dimensions based on the BIM-GIS integration model;
[0112] The BIM-GIS integrated model is linked to the BIM model database data to reflect the multi-faceted management of the project’s design, investment, quality, safety, progress, personnel and environment. When an abnormality or alarm occurs, the digital integration system automatically locates the corresponding BIM-GIS integrated model so that management and control personnel can respond in a timely manner.
[0113] Access layer, used for:
[0114] Users log in and access the digital integration system based on PCs, mobile devices and AR terminals. Users include construction units, design units, supervision units, construction units and operation and maintenance units.
[0115] The technical effects of the above content are as follows: the data layer collects data through various data collectors and stores it in the BIM model database. The integration layer can integrate the data in the BIM model database and other data in the data interaction management and control platform, and mine and analyze the integrated data, and perform interactive data management on the integrated data after mining and analysis. Then, the service layer, based on BIM technology and GIS technology, automatically transmits the data mined and analyzed by the integration layer to the model components through the Internet of Things, and can build and display a BIM-GIS integrated model. The application layer can display the BIM model database data in three dimensions based on the BIM-GIS integrated model, thereby achieving all-round management of the project's design, investment, quality, safety, progress, personnel and environment, and users can access it through PCs, mobile devices and AR terminals, thereby achieving visual and real-time dynamic management and control.
[0116] The data layer is as follows:
[0117] Using each data collector to perform real-time monitoring to collect data monitored in real time by each data collector;
[0118] The data collected by each data collector is collected centrally through 5G communication technology, and then the various data collected centrally are transmitted to the BIM model database for storage through 5G communication technology;
[0119] Confirm the BIM model database, confirm the building data in the BIM model database, and process the confirmed building data.
[0120] The technical effect of the above content is: the data layer uses various data collectors for real-time monitoring, so as to collect the data monitored by each data collector in real time. The data collected by each data collector can be collected through 5G communication technology. After the collection is completed, the concentrated multiple data are transmitted to the BIM model database for storage through 5G communication technology. By centralizing and storing multiple data, the island effect between different types of data can be avoided and they cannot be used for each other.
[0121] Integration layer, specifically:
[0122] Integrate the data in the BIM model database and other data in the interactive management and control platform based on data interface and middleware technology;
[0123] Mining and analyzing the integrated data through artificial intelligence algorithms;
[0124] Among them, artificial intelligence algorithms use machine learning algorithms for data mining, data mining, including:
[0125] Data preprocessing: Before data mining, data is preprocessed to provide a basis for subsequent analysis, including data cleaning and data transformation processes;
[0126] Feature selection and extraction: Through feature selection, predictive features are selected from the preprocessed data center. Through feature extraction, features that are helpful for modeling are extracted from the preprocessed data. Feature selection and extraction provide the basis for subsequent model construction.
[0127] Conduct interactive data management and control on the integrated data after mining and analysis;
[0128] Among them, interactive data management includes project management, risk management, schedule management, quality management and cost management.
[0129] The technical effects of the above contents are as follows: the integration layer provides a unified data interface for the service layer and the application layer, provides an interface and a shared BIM model database for the service layer and the application layer, and can integrate the data in the BIM model database with other data in the interactive management and control platform according to the data interface and middleware technology. Through data integration, the island effect between various types of data can be avoided and they cannot be used for each other, and complete and accurate data support is provided for the service layer and the application layer, thereby improving the overall work efficiency of project management and control. After data integration, the integrated data is mined and analyzed through artificial intelligence algorithms, and before data mining, the data is cleaned and transformed to ensure the reliability of the data, providing a basis for subsequent analysis, and feature selection and extraction are performed on the pre-processed data. By selecting and extracting representative features in the data, a basis is provided for subsequent model construction, making modeling more accurate. Finally, the integrated data after mining and analysis is interactively managed, and interactive data management includes project management, risk management, schedule management, quality management and cost management.
[0130] Application layer, including:
[0131] Design management module for:
[0132] Carry out design management, coordinate, control and supervise the entire design process of construction projects, including the preparation of design plans, design review and management of design changes;
[0133] Design plan preparation: Before carrying out a project, it is necessary to clearly define the design goals and then prepare a design plan, including the clarification of project requirements, functional requirements, style requirements, etc. By clarifying the design goals, the design work can be carried out in a targeted manner; Design review: Through the review of the design plan, problems and deficiencies in the design can be discovered, and reasonable improvement measures can be proposed to ensure the quality of the design plan; Design changes: Manage the changes in the design plan. The design plans before and after the change need to be fully compared and evaluated to ensure that the changed plan can meet the requirements of the project;
[0134] Investment management module for:
[0135] Carry out investment management and conduct scientific and reasonable control over the investment of construction projects, including investment budget preparation, investment source selection, fund planning and control, risk management and decision support;
[0136] Preparation of investment budget: Before a construction project is started, an investment budget must be prepared. The investment budget is a detailed measurement and analysis of the project to determine the project's cost and funding needs. It is the economic basis of the construction project. When preparing the investment budget, it is necessary to consider many factors such as the scale of the construction project, construction period, construction materials and construction technology. Through rational analysis and preparation of plans, the scientific rationality of fund allocation can be ensured; Selection of investment sources: It is an important part of the investment management of construction projects. Investment can be obtained from multiple channels such as the government, banks, enterprises, and social capital. The nature and risk level of funds from different investment sources are different, so a comprehensive evaluation and comparison are required to select the appropriate one for the project in actual operation. Sources of investment; Funding planning and control: During the implementation of construction projects, it is necessary to establish a scientific and reasonable funding planning and control mechanism, and constantly adjust the funding use plan and progress according to the actual situation to ensure that the project can be completed on time and with quality; Risk management: Including market risk, financial risk, technical risk and other factors. In view of these risks, it is necessary to establish a sound risk management mechanism to reduce various risks through early prediction, analysis and control; Decision support: In the investment management of construction projects, through the study of market trends, in-depth analysis of the project's funding needs, profit expectations and cost control is carried out, and various information and reports required by decision makers are provided to help decision makers make well-thought-out decisions;
[0137] Quality management module for:
[0138] Carry out quality management, and scientifically and reasonably control the quality of construction projects, which is divided into quality management in the construction stage and quality management in the acceptance stage;
[0139] Among them, the quality management module includes:
[0140] Quality management during the construction phase: Quality management during the construction phase of a construction project, including construction site management and quality inspection management;
[0141] Construction site management: including material management, personnel management, construction machinery management, etc., to ensure the cleanliness and orderliness of the construction site; Quality inspection management: comprehensive quality control and inspection of the construction process, including inspection and acceptance of raw materials, inspection and acceptance of construction procedures, spot check and acceptance of construction quality, etc. For projects that fail to meet the inspection quality standards, timely corrective and rectification measures shall be taken;
[0142] Quality management during the acceptance phase: Quality management is carried out during the acceptance phase of construction projects, and comprehensive evaluation and inspection of the construction process and results are carried out, including quality evaluation and inspection, problem rectification and warranty period management;
[0143] Quality assessment and testing: Conduct comprehensive quality assessment and testing of construction projects, including structural safety assessment, decoration effect testing, equipment and facility operation testing, etc. The assessment and testing results should be compared with the requirements of the design plan to ensure that the quality of the building meets expectations; Problem rectification and warranty period management: For problems found during acceptance, timely rectification and resolution should be carried out. At the same time, quality warranty period management of construction projects is also an important task. During the warranty period, quality problems that arise need to be handled and resolved in a timely manner;
[0144] Security management module, used to:
[0145] Conduct safety management for workers involved in the project. The video surveillance system is connected to the safety management module so that the video screen can be switched at any time, and alarm information can be popped up and recorded in real time.
[0146] Schedule management module for:
[0147] Carry out progress management, formulate a progress plan for the work content, work procedures, duration and connection relationship of each stage of the construction project, and implement the progress plan. During the implementation process, check whether the actual progress is in accordance with the requirements of the progress plan, analyze the reasons for any deviations, and manage by taking remedial measures or adjusting and modifying the original progress plan;
[0148] Personnel management module for:
[0149] Conduct personnel management, scientifically and reasonably control the personnel of construction projects, ensure that workers carry out construction according to the established schedule, and thus ensure the progress of the project;
[0150] Environment management module for:
[0151] Carry out environmental management in accordance with air quality standards and green building standards, arrange air quality sensors for temperature and humidity, carbon dioxide, carbon monoxide, formaldehyde, PM2.5 and PM10, monitor and display indicators in real time, alarm when air quality exceeds the standard and link the ventilation and air conditioning system for processing.
[0152] Technical effects of the above contents: Based on BIM technology and GIS technology, the service layer automatically transmits the data mined and analyzed by the integration layer to the model components through the Internet of Things, so as to build a BIM-GIS integrated model. BIM technology can provide the precise height, appearance size and internal space information of the building. Combined with GIS technology, it can share building space information and the surrounding geographical environment, reduce the cost of building space information, and help evaluate the construction accuracy of the project. The BIM-GIS integrated model is displayed in the integrated management and control platform through the application layer, and the application layer can read and call the integrated data in the BIM model database. Combined with the BIM-GIS integrated model, the BIM model database data can be displayed in three dimensions, thereby realizing all-round management of the project design, investment, quality, safety, progress, personnel, environment and other aspects, and achieving visual and real-time dynamic management and control.
[0153] Access layer, including:
[0154] Authentication module for:
[0155] Authentication is performed on the account that logs into the digital integration system. If the account verification passes, the user successfully logs into the digital integration system for access. If the account verification fails, an alarm message is sent to the integrated management and control platform.
[0156] The technical effect of the above content is as follows: users log in to the integrated management and control platform through their accounts, and based on the three-dimensional display of the BIM model database data based on the BIM-GIS integrated model, realize the user's visual and real-time dynamic management, thereby achieving all-round management of the project's design, investment, quality, safety, progress, personnel and environment. When the user logs in, the user's identity will be verified through the verification module to obtain the user's identity information. Only after the account verification is successful can the user successfully log in to the integrated management and control platform for access. If the account verification fails, an alarm message will be sent to the integrated management and control platform to remind the manager to pay attention, thereby ensuring the security of the integrated management and control platform.
[0157] Furthermore, the integration layer integrates the data in the BIM model database and other data in the data interaction management and control platform, including:
[0158] The first computing module is used for:
[0159] Perform n1 data analyses on the data in the BIM model database to obtain n1 first data analysis results; perform n2 data analyses on other data in the data interaction management and control platform to obtain n2 second data analysis results;
[0160] The first data analysis result and the second data analysis result are numerically processed, and the difference between the data in the BIM model database and other data in the data interaction management and control platform is calculated according to the numerically processed first data analysis result and the second data analysis result:
[0161] ;
[0162] in, It is the difference between the data in the BIM model database and other data in the data interaction management and control platform. is the sum of the n1 first data analysis results, is the sum of n2 second data analysis results, The sum of the squares of the n1 first data analysis results is calculated; The squares of n2 second data analysis results are summed;
[0163] Comparison module for:
[0164] The difference value is compared with a preset difference value; when it is determined that the difference value is greater than or equal to the preset difference value, a coarse matching strategy is adopted to perform data integration;
[0165] When it is determined that the difference value is less than the preset difference value, data feature extraction processing is performed on the data in the BIM model database to obtain a first feature vector;
[0166] Perform data feature extraction on other data in the data interaction management and control platform to obtain a second feature vector;
[0167] Calculate the similarity between the first feature vector and the preset feature vector in the standard database, and standardize the first feature vector according to the first preset feature vector corresponding to the maximum similarity to obtain a first target vector;
[0168] ;
[0169] Wherein, S is the similarity between the first feature vector and the preset feature vector; is the first eigenvector feature components; is the first feature vector of the preset feature components; is the number of characteristic components of the first characteristic vector, which is also the number of characteristic components of the preset characteristic vector, and the two are equal;
[0170] Calculate the similarity between the second feature vector and the preset feature vector in the standard database, and standardize the second feature vector according to the second preset feature vector corresponding to the maximum similarity to obtain a second target vector;
[0171] A fine matching strategy is adopted according to the first target vector and the second target vector to perform data integration.
[0172] Working principle of the above technical solution: In this embodiment, when the integration layer integrates the data in the BIM model database and other data in the data interaction management and control platform, it is necessary to perform several data analyses on the data in the BIM model database and other data in the data interaction management and control platform respectively. The data analysis includes descriptive statistical analysis: describing the distribution and characteristics of the data by calculating indicators such as mean, median, and standard deviation. Inferential statistical analysis: using sample data to infer overall characteristics, such as hypothesis testing, confidence intervals, etc. Visual analysis: intuitively displaying data through charts, graphs, etc., to help people better understand the information behind the data. Data mining algorithms: using machine learning, deep learning and other algorithms to mine hidden patterns and associations in data, such as cluster analysis, classification analysis, association rule mining, etc. Predictive analysis: predicting future trends based on historical data, such as time series analysis, regression analysis, etc.
[0173] In this embodiment, the difference value between the data in the BIM model database and other data in the data interaction management and control platform is accurately calculated, and the difference value is compared with the preset difference value based on the comparison module; when it is determined that the difference value is greater than or equal to the preset difference value, it means that the data in the BIM model database and other data in the data interaction management and control platform have few data overlap types, and only rough matching can be performed to achieve approximate data integration.
[0174] In this embodiment, when it is determined that the difference value is less than the preset difference value, it means that the data in the BIM model database and other data in the data interaction management and control platform have many types of data overlap, and often refined data integration is required. First, the data in the BIM model database and other data in the data interaction management and control platform are respectively subjected to data feature extraction processing to obtain corresponding feature vectors. Based on the calculation of the similarity between the first feature vector and the preset feature vector in the standard database, the first feature vector is standardized according to the first preset feature vector corresponding to the maximum similarity to obtain the first target vector; the standardized processing of the first feature vector is realized. The method for standardizing the second feature vector is consistent with the method for standardizing the first feature vector. Based on the first target vector and the second target vector after standardization, it is convenient to improve the efficiency and accuracy of data integration.
[0175] The beneficial effects of the above technical solution are as follows: the difference between the data in the BIM model database and other data in the data interaction management and control platform is calculated, and different data integration strategies are adopted according to the comparison results between the difference and the preset difference. When it is determined that the difference is less than the preset difference, refined data integration is achieved, and the feature vectors when the difference is less than the preset difference are extracted and standardized, so as to improve the efficiency and accuracy of data integration.
[0176] Furthermore, the security management module includes:
[0177] An acquisition module, used to acquire monitoring images of workers participating in the project based on a video monitoring system;
[0178] An enhancement module is used to enhance the monitoring image to obtain an enhanced image;
[0179] Feature extraction module for:
[0180] Grayscale processing is performed on the enhanced image, and color space standardization processing is performed on the enhanced image after grayscale processing based on the Gamma correction method to obtain a processed image;
[0181] Calculate the gradient information of each pixel in the image;
[0182] Divide the processed image according to the gradient information to obtain several sub-processed images;
[0183] Counting the gradient histogram and the number of different gradients of each sub-processed image to form sub-features of the sub-processed image;
[0184] The sub-features of each sub-processed image are fused to obtain the HOG feature parameters of the processed image;
[0185] Matching modules for:
[0186] Determine the human characteristics of the workers participating in the project according to the HOG feature parameters, analyze and process the human characteristics, and determine the behavioral information of the workers participating in the project;
[0187] The behavior information is matched with the preset violation behavior information. When it is determined that the match degree is greater than the preset match degree threshold, an alarm message is popped up and recorded in real time.
[0188] Working principle of the above technical solution: In this embodiment, the enhanced image after grayscale processing is standardized in color space based on the Gamma correction method, mainly to adjust the contrast of the image, reduce the impact of local shadows and lighting changes in the image, and suppress noise interference.
[0189] In this embodiment, the gradient information of each pixel in the image is calculated and processed, including: for each pixel in the image ( x , y ), whose gradient can be expressed as a vector ∇ I ( x , y )=[ Gx , Gy ],in Gx and Gy are the gradient values of the point in the x direction and y direction respectively.
[0190] The Sobel operator is a discrete differential operator for edge detection that combines Gaussian smoothing and differential derivation. The Sobel operator contains two sets of 3x3 matrices, one for calculating the horizontal gradient and the other for calculating the horizontal gradient. Gx , and another one for calculating the vertical gradient Gy .
[0191] ;
[0192] Where ∗ represents the convolution operation and I is the original image.
[0193] The magnitude and direction of the gradient can be calculated using the following formula:
[0194] ;
[0195] The gradient information of each pixel is determined based on the magnitude and direction of the gradient.
[0196] In this embodiment, first, the processed image is divided into several small, overlapping or non-overlapping sub-regions (cells). The size and degree of overlap of these sub-regions can be adjusted according to the specific task. For example, in pedestrian detection, the commonly used sub-region size is 8x8 pixels, and they are usually non-overlapping. The gradient direction is usually quantized into a limited number of directions (such as 0-360 degrees is quantized into 9 or 18 directions). Gradient histogram: For each sub-region, according to the quantized gradient direction, the sum of the gradient magnitudes in each direction in the region is counted. In this way, each sub-region forms a gradient histogram, and the number of bins of the histogram is equal to the number of quantized gradient directions. Normalization: In order to improve the robustness of the HOG feature, the gradient histograms of several adjacent sub-regions are usually normalized. Normalization can reduce the impact of factors such as illumination changes and shadows on the features. The normalized region (block) can be a rectangular block composed of multiple sub-regions, and these blocks can overlap. Feature fusion: The gradient histograms of all normalized sub-regions are connected in series to form the HOG feature vector of the entire image. This feature vector contains the gradient information of all sub-regions in the image and has been optimized through a normalization step.
[0197] In this embodiment, a pre-trained human detection model (such as YOLO, SSD, Faster R-CNN, etc.) is used to locate the workers in the image. Feature vector construction: The HOG feature vector of each worker is used as the basis of its behavior features. Behavior classification: HOG features are classified using machine learning or deep learning models (such as SVM, random forest, CNN, etc.) to identify the worker's behavior (such as standing, walking, carrying, illegal operation, etc.). Behavior sequence analysis: If more complex behaviors (such as continuous illegal operations) need to be identified, it is necessary to analyze the behavior changes in a series of frames. Preset illegal behavior library: Establish a database or rule set containing various illegal behaviors. Matching degree calculation: Compare the identified behavior with the preset illegal behavior and calculate the matching degree. Threshold judgment: If the matching degree is greater than the preset matching degree threshold, it is considered that the illegal behavior is detected. Real-time alarm: Once a violation is detected, the system should be able to pop up an alarm message in real time to notify relevant personnel. Record log: Record the time, location, violation type and possible video clips of the violation for subsequent analysis and processing.
[0198] The beneficial effects of the above technical solution are: accurately determining the HOG feature parameters corresponding to the monitoring images of the workers participating in the project; determining the human features of the workers participating in the project based on the HOG feature parameters, analyzing and processing the human features, and determining the behavior information of the workers participating in the project; matching the behavior information with the preset violation behavior information, and when it is determined that the matching degree is greater than the preset matching degree threshold, popping up an alarm message in real time and recording it, thereby realizing safe monitoring of the workers' behavior.
[0199] Furthermore, the enhancement module includes:
[0200] The first determination module is used to:
[0201] Inputting the monitoring image into the filter to perform convolution operation and determine the first target image;
[0202] Performing image enhancement processing on the first target image according to the histogram enhancement method, performing feature extraction on the first target image after the image enhancement processing to obtain a first feature; performing clustering processing according to the first feature to obtain a first clustering center of the first target image;
[0203] The second determination module is used for:
[0204] Performing image difference processing on the monitoring image and the first target image to obtain a second target image;
[0205] Obtain the pixel values of each pixel in the second target image in the R channel, the G channel, and the B channel, and compare them to determine the minimum value of the same pixel in the three channels as the feature value of the pixel;
[0206] Generate a feature map based on the feature values of the pixels;
[0207] Set a sliding window with a size of m*m; determine the area with the largest average eigenvalue in the feature map as the target area; and use other areas in the feature map except the target area as areas to be adjusted;
[0208] Sliding the sliding window in the area to be adjusted to obtain a sub-area to be adjusted; calculating the distance between the central pixel point of the sub-area to be adjusted and the central pixel point of the target area; determining the first eigenvalue of the central pixel point of the target area;
[0209] The second computing module is used for:
[0210] According to the distance and the first eigenvalue, a preset distance-first eigenvalue-second eigenvalue data table is searched to determine a preset second eigenvalue of the central pixel of the sub-region to be adjusted;
[0211] Obtain the actual eigenvalue of the central pixel of the sub-region to be adjusted, calculate the difference between the second eigenvalue and the actual eigenvalue; calculate the ratio of the difference to the actual eigenvalue as the enhancement coefficient;
[0212] Performing image enhancement on other pixel points in the sub-region to be adjusted based on the enhancement coefficient, extracting features from the second target image after the image enhancement process to obtain a second feature; performing clustering process according to the second feature to obtain a second cluster center of the second target image;
[0213] The distance information between the first cluster center and the second cluster center is calculated, a preset data table is queried according to the distance information, a corresponding fusion strategy is determined, and image fusion processing is performed on the first target image and the second target image based on the fusion strategy to obtain an enhanced image.
[0214] The working principle of the above technical solution: In this embodiment, the monitoring image is input into the filter for convolution operation to determine the first target image for feature extraction. The selected filter is operated on the image as a sliding window (convolution kernel) to calculate the convolution result at each position. The convolution operation is usually to multiply the filter with the corresponding area in the image and then sum the results, and then assign the results to the corresponding positions in the output image. This process needs to be performed for each pixel of the image (or most of the pixels, depending on the size of the filter and the boundary processing method).
[0215] In this embodiment, histogram equalization is performed to calculate the histogram of the first target image. The cumulative distribution function (CDF) is used to perform nonlinear stretching on the pixel values of the image so that the histogram distribution of the image is more uniform. This method can enhance the contrast of the image and make the details of the image clearer.
[0216] In this embodiment, the features of the first target image include: edge features, shape features and texture features.
[0217] In this embodiment, the extracted features are input into a selected clustering algorithm, and the clustering algorithm outputs the center of each cluster (for K-Means, the mean of all points in the cluster).
[0218] In this embodiment, the difference between the monitoring image and the first target image is found by comparing them, that is, the changed area. The monitoring image and the first target image are subtracted at the pixel level to obtain the second target image. The highlighted part in the second target image represents the difference between the two images. The minimum value of the RGB channel is extracted as the feature value. In order to simplify the feature processing, the minimum value is selected from the three RGB channels of each pixel of the second target image as the feature value of the pixel. Each pixel of the second target image is traversed, and the pixel values of the three R, G, and B channels are compared, and the minimum value is selected as the feature value of the pixel. The feature values of each pixel are organized into a new image, that is, a feature map. The feature value of each pixel is assigned to the pixel at the corresponding position in the feature map to generate a feature map of the same size as the second target image. The target area and the area to be adjusted are determined, and the area with the most significant change (i.e., the largest average feature value) is found in the feature map as the target area, and the remaining areas are used as the area to be adjusted. Use a sliding window (size of m*m) to traverse the feature map and calculate the average value of the feature value in each window. Determine the area with the largest average feature value as the target area. Mark the other parts of the feature map except the target area as the area to be adjusted. Calculate the enhancement coefficient (based on the sliding window and distance-eigenvalue mapping), and determine how to adjust the eigenvalues of these sub-areas to enhance the image by calculating the relationship between each sub-area in the area to be adjusted and the central pixel of the target area. Use the sliding window to traverse the area to be adjusted to obtain each sub-area to be adjusted. Calculate the distance between the central pixel of each sub-area to be adjusted and the central pixel of the target area. Determine the first eigenvalue of the central pixel of the target area. Query the preset "distance-first eigenvalue-second eigenvalue" data table based on the distance and the first eigenvalue to obtain the corresponding preset second eigenvalue. Calculate the difference between the actual eigenvalue of the central pixel of the sub-area to be adjusted and the preset second eigenvalue, and calculate the ratio of the difference to the actual eigenvalue as the enhancement coefficient. Apply the enhancement coefficient and use the calculated enhancement coefficient to adjust the eigenvalue of the pixel in the area to be adjusted to achieve the purpose of enhancing the image.
[0219] In this embodiment, the previously calculated enhancement coefficient is used to adjust the value of each pixel in the sub-region to be adjusted to enhance the features of these regions. Each sub-region in the region to be adjusted is traversed. For each sub-region, the values of all pixels in the sub-region are adjusted according to the enhancement coefficient of its central pixel. The adjustment method can be a simple multiplication (if the enhancement coefficient is a proportional factor). The pixel values of the corresponding region in the second target image are updated. Feature extraction is performed on the enhanced second target image, and new features are extracted from the enhanced second target image for subsequent clustering processing. Clustering is performed according to the second feature, and the pixels or feature points in the second target image are grouped according to their similarity. The extracted second feature is clustered using an appropriate clustering algorithm (such as K-Means, DBSCAN, etc.). The number or parameters of clusters are determined to generate a second cluster center. The distance information between the first cluster center and the second cluster center is calculated to evaluate the similarity or difference between the first target image and the second target image (or its features). A certain distance metric (such as Euclidean distance, Manhattan distance, etc.) between the first cluster center and the second cluster center is calculated. This distance information will be used to determine the fusion strategy later. According to the distance information, the preset data table is queried to determine the fusion strategy, and the most appropriate image fusion strategy is selected based on the distance between the cluster centers. A data table is preset, which contains the mapping of different distance ranges and corresponding fusion strategies. The data table is queried to find the corresponding fusion strategy according to the calculated distance information. The first target image and the second target image are subjected to image fusion processing based on the fusion strategy, and the first target image and the second target image (or their features) are merged into an enhanced image, which combines the advantages of both. According to the selected fusion strategy, the first target image and the second target image are fused. The fusion method can be a simple weighted average, multi-resolution fusion (such as pyramid fusion), feature-based fusion, etc. Factors such as image registration, illumination consistency, and color balance are considered in the fusion process. Finally, an enhanced image is generated, which retains the important features of the first target image while also incorporating new information or enhanced features in the second target image.
[0220] The beneficial effects of the above technical solution are as follows: the first target image and the second target image are determined according to the monitoring image, different image enhancement processing methods are adopted respectively, after image enhancement processing, feature extraction is performed, the first cluster center of the first target image and the second cluster center of the second target image are determined, the distance information of the first cluster center and the second cluster center is calculated, the preset data table is queried according to the distance information, the corresponding fusion strategy is determined, and the image fusion processing is performed on the first target image and the second target image based on the fusion strategy to obtain an enhanced image. It is convenient to obtain an accurate enhanced image.
[0221] A digital integrated management and control platform based on BIM technology, including:
[0222] BIM model database for:
[0223] Store the data collected by each data collector, integrate the stored data with other data in the interactive management and control platform, and the integrated data set provides data support for building the model;
[0224] Integrated management and control platform for:
[0225] Provide users with a three-dimensional display platform to display BIM model database data in three dimensions based on the BIM-GIS integrated model. Users can access the integrated management and control platform through PCs, mobile devices and AR terminals.
[0226] Working principle: The data layer collects data from various data collectors and stores them in the BIM model database. The integration layer can integrate the data in the BIM model database and other data in the data interaction management and control platform. Through data integration, the island effect between various types of data can be avoided and they cannot be used for each other. Complete and accurate data support is provided for the service layer and the application layer, thereby improving the overall work efficiency of project management and control. The integrated data is mined and analyzed, and the integrated data after mining and analysis is interactively managed. Then, based on BIM technology and GIS technology, the service layer automatically transmits the data mined and analyzed by the integration layer to the model component through the Internet of Things, and can build a BIM-GIS integrated model and display it. BIM technology combined with GIS technology can share building space information and surrounding geographical environment, reduce the cost of building space information, and help evaluate the construction accuracy of the project. The application layer can display the BIM model database data in three dimensions based on the BIM-GIS integrated model, thereby managing the design, investment, quality, safety, progress, personnel and environment of the project in all directions, and users can access it through PCs, mobile devices and AR terminals, so as to achieve visual and real-time dynamic management and control.
[0227] It should be noted that, in this article, relational terms such as first and second, etc. are only used to distinguish one entity or operation from another entity or operation, and do not necessarily require or imply any such actual relationship or order between these entities or operations. Moreover, the terms "include", "comprise" or any other variants thereof are intended to cover non-exclusive inclusion, so that a process, method, article or device including a series of elements includes not only those elements, but also other elements not explicitly listed, or also includes elements inherent to such process, method, article or device.
[0228] While the embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that many changes, modifications, substitutions and variations can be made to the embodiments without departing from the principles and spirit of the invention.
Claims
1. A digital intelligent integration system based on BIM technology, characterized in that: include: Data layer, used for: Collect data and store them in the BIM model database, and confirm and process the building data in the BIM model database; Integration layer for: Provide a unified data interface, provide interfaces and shared BIM model databases for the service layer and application layer, integrate data in the BIM model database and other data in the data interaction management and control platform, and mine and analyze the integrated data; The service layer is used to: The data mined and analyzed at the integration layer is automatically transmitted to the model components through the Internet of Things. Based on BIM technology and GIS technology, a BIM-GIS integration model is constructed, and the BIM-GIS integration model is displayed in the integrated management and control platform through the application layer; Application layer, used for: The integrated data is called uniformly, by reading and calling the integrated data in the BIM model database, and displaying the BIM model database data in three dimensions based on the BIM-GIS integration model; The BIM-GIS integrated model is linked to the BIM model database data to reflect the multi-faceted management of the project’s design, investment, quality, safety, progress, personnel and environment. When an abnormality or alarm occurs, the digital integrated system automatically locates the corresponding BI MG IS integrated model so that management and control personnel can respond in a timely manner. Access layer, used for: Users log in and access the digital integration system based on PCs, mobile devices and AR terminals. Users include construction units, design units, supervision units, construction units and operation and maintenance units. The integration layer integrates the data in the BIM model database and other data in the data interaction management and control platform, including: The first computing module is used for: Perform n1 data analyses on the data in the BIM model database to obtain n1 first data analysis results; perform n2 data analyses on other data in the data interaction management and control platform to obtain n2 second data analysis results; The first data analysis result and the second data analysis result are numerically processed, and the difference between the data in the BIM model database and other data in the data interaction management and control platform is calculated according to the numerically processed first data analysis result and the second data analysis result: Where λ is the difference between the data in the BIM model database and other data in the data interaction management and control platform, ΣX1 is the sum of n1 first data analysis results, ∑X2 is the sum of n2 second data analysis results, ∑X1 2 is the sum of the squares of the n1 first data analysis results; ∑X2 2 The squares of n2 second data analysis results are summed; Comparison module for: The difference value is compared with a preset difference value; when it is determined that the difference value is greater than or equal to the preset difference value, a coarse matching strategy is adopted to perform data integration; When it is determined that the difference value is less than the preset difference value, data feature extraction processing is performed on the data in the BIM model database to obtain a first feature vector; Perform data feature extraction on other data in the data interaction management and control platform to obtain a second feature vector; Calculate the similarity between the first feature vector and the preset feature vector in the standard database, and standardize the first feature vector according to the first preset feature vector corresponding to the maximum similarity to obtain a first target vector; Where S is the similarity between the first feature vector and the preset feature vector; x i is the i-th eigencomponent of the first eigenvector; y i is the i-th characteristic component of the preset characteristic vector; n is the number of characteristic components of the first characteristic vector, which is also the number of characteristic components of the preset characteristic vector, and the two are equal; Calculate the similarity between the second feature vector and the preset feature vector in the standard database, and standardize the second feature vector according to the second preset feature vector corresponding to the maximum similarity to obtain a second target vector; A fine matching strategy is adopted according to the first target vector and the second target vector to perform data integration.
2. According to claim 1, a digital intelligent integration system based on BIM technology is characterized by: The data layer is specifically: Using each data collector to perform real-time monitoring to collect data monitored in real time by each data collector; The data collected by each data collector is collected centrally through 5G communication technology, and then the various data collected centrally are transmitted to the BIM model database for storage through 5G communication technology; Confirm the BIM model database, confirm the building data in the BIM model database, and process the confirmed building data.
3. According to claim 1, a digital intelligent integration system based on BIM technology is characterized by: The integration layer is specifically: Integrate the data in the BIM model database and other data in the interactive management and control platform based on data interface and middleware technology; Mining and analyzing the integrated data through artificial intelligence algorithms; Among them, artificial intelligence algorithms use machine learning algorithms for data mining; Data mining, including: Data preprocessing: Before data mining, data is preprocessed to provide a basis for subsequent analysis, including data cleaning and data transformation processes; Feature selection and extraction: Perform feature selection and extraction on the preprocessed data, and provide a basis for subsequent model construction by selecting and extracting representative features in the data; Conduct interactive data management and control on the integrated data after mining and analysis; Among them, data management includes project management, risk management, schedule management, quality management and cost management.
4. According to claim 1, a digital intelligent integration system based on BIM technology is characterized by: The application layer includes: Design management module for: Carry out design management, coordinate, control and supervise the entire design process of construction projects, including the preparation of design plans, design review and management of design changes; Investment management module for: Carry out investment management and conduct scientific and reasonable control over the investment of construction projects, including investment budget preparation, investment source selection, fund planning and control, risk management and decision support; Quality management module for: Carry out quality management, and scientifically and reasonably control the quality of construction projects, which is divided into quality management in the construction stage and quality management in the acceptance stage; Security management module, used to: Conduct safety management for workers involved in the project. The video surveillance system is connected to the safety management module so that the video screen can be switched at any time, and alarm information can be popped up and recorded in real time. Schedule management module for: Carry out progress management, formulate a progress plan for the work content, work procedures, duration and connection relationship of each stage of the construction project, and implement the progress plan. During the implementation process, check whether the actual progress is in accordance with the requirements of the progress plan, analyze the reasons for any deviations, and manage by taking remedial measures or adjusting and modifying the original progress plan; Personnel management module for: Carry out personnel management, scientifically and reasonably control the personnel of construction projects, and ensure that workers carry out construction according to the established schedule; Environment management module for: Carry out environmental management in accordance with air quality standards and green building standards, arrange air quality sensors for temperature and humidity, carbon dioxide, carbon monoxide, formaldehyde, PM2.5 and PM10, monitor and display indicators in real time, alarm when air quality exceeds the standard and link the ventilation and air conditioning system for processing.
5. According to claim 4, a digital intelligent integration system based on BIM technology is characterized in that: The quality management module comprises: Quality management during the construction phase: Quality management during the construction phase of a construction project, including construction site management and quality inspection management; Quality management during the acceptance phase: Quality management is carried out during the acceptance phase of construction projects, with a comprehensive assessment and inspection of the construction process and results, including quality assessment and testing as well as problem rectification and warranty period management.
6. According to claim 1, a digital intelligent integration system based on BIM technology is characterized by: The access layer comprises: Authentication module, used to: Authentication is performed on the account that logs into the digital integration system. If the account verification passes, the user successfully logs into the digital integration system for access. If the account verification fails, an alarm message is sent to the integrated management and control platform.
7. The digital intelligent integration system based on BIM technology according to claim 4 is characterized by: The security management module comprises: An acquisition module, used to acquire monitoring images of workers participating in the project based on a video monitoring system; An enhancement module is used to enhance the monitoring image to obtain an enhanced image; Feature extraction module for: Grayscale processing is performed on the enhanced image, and color space standardization processing is performed on the enhanced image after grayscale processing based on the Gamma correction method to obtain a processed image; Calculate the gradient information of each pixel in the image; Divide the processed image according to the gradient information to obtain several sub-processed images; Counting the gradient histogram and the number of different gradients of each sub-processed image to form sub-features of the sub-processed image; The sub-features of each sub-processed image are fused to obtain the HOG feature parameters of the processed image; Matching modules for: Determine the human characteristics of the workers participating in the project according to the HOG feature parameters, analyze and process the human characteristics, and determine the behavioral information of the workers participating in the project; The behavior information is matched with the preset violation behavior information. When it is determined that the match degree is greater than the preset match degree threshold, an alarm message is popped up and recorded in real time.
8. The digital intelligent integration system based on BIM technology according to claim 7 is characterized in that: The enhancement module comprises: The first determination module is used to: Inputting the monitoring image into the filter to perform convolution operation and determine the first target image; Performing image enhancement processing on the first target image according to the histogram enhancement method, performing feature extraction on the first target image after the image enhancement processing to obtain a first feature; performing clustering processing according to the first feature to obtain a first clustering center of the first target image; The second determination module is used for: Performing image difference processing on the monitoring image and the first target image to obtain a second target image; Obtain the pixel values of each pixel in the second target image in the R channel, the G channel, and the B channel, and compare them to determine the minimum value of the same pixel in the three channels as the feature value of the pixel; Generate a feature map based on the feature values of the pixels; Set a sliding window with a size of m*m; determine the area with the largest average eigenvalue in the feature map as the target area; and use other areas in the feature map except the target area as areas to be adjusted; Sliding the sliding window in the area to be adjusted to obtain a sub-area to be adjusted; calculating the distance between the central pixel point of the sub-area to be adjusted and the central pixel point of the target area; determining the first eigenvalue of the central pixel point of the target area; The second computing module is used for: According to the distance and the first eigenvalue, a preset distance-first eigenvalue-second eigenvalue data table is searched to determine a preset second eigenvalue of the central pixel of the sub-region to be adjusted; Obtain the actual eigenvalue of the central pixel of the sub-region to be adjusted, calculate the difference between the second eigenvalue and the actual eigenvalue; calculate the ratio of the difference to the actual eigenvalue as the enhancement coefficient; Performing image enhancement on other pixel points in the sub-region to be adjusted based on the enhancement coefficient, extracting features from the second target image after the image enhancement process to obtain a second feature; performing clustering process according to the second feature to obtain a second cluster center of the second target image; The distance information between the first cluster center and the second cluster center is calculated, a preset data table is queried according to the distance information, a corresponding fusion strategy is determined, and image fusion processing is performed on the first target image and the second target image based on the fusion strategy to obtain an enhanced image.
9. A digital integrated management and control platform based on BIM technology, characterized by: The platform is used to implement a digital intelligent integration system based on BIM technology as described in any one of claims 1 to 8, and the platform includes: BIM model database for: Store the data collected by each data collector, integrate the stored data with other data in the interactive management and control platform, and the integrated data set provides data support for building the model; Integrated management and control platform for: Provide users with a three-dimensional display platform to display BIM model database data in three dimensions based on the BIM-GIS integrated model. Users can access the integrated management and control platform through PCs, mobile devices and AR terminals.