A missed alarm optimization system for FTTR equipment

By designing a missed alarm optimization system on the FTTR device, using the power-down sensing module and analysis module to detect temperature and voltage abnormalities, triggering alarm and maintenance operations, the problem of inability to report when the equipment is powered down is solved, and the equipment operation stability is improved Reporting success rate reduces hardware costs.

CN118713740BActive Publication Date: 2024-11-19SHENZHEN SUNRAY ELECTRONICS LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411183611.4
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-08-27
Publication Date
2024-11-19
Estimated Expiration
2044-08-27

AI Technical Summary

Technical Problem

The existing FTTR equipment uses components of the original home gateway unit type equipment in hardware design, which causes the onboard capacitor to fail to maintain sufficient discharge time when the device is powered off, resulting in the power down alarm message being unable to be sent, and hundreds or thousands of It is difficult for the equipment to report a power-off alarm at the same time, resulting in the bureau's equipment mistakenly thinking that it is still online.

Method used

An FTTR device leak-reporting alarm optimization system is designed, including inductor-deletion module, analysis module, controllable power supply module, alarm reporting module and offline maintenance module. The temperature and voltage of key components are collected at preset time intervals. Data, perform image fitting and prediction, detect temperature and voltage abnormalities, trigger power-down characteristic signals, automatic restart and POWERDOWN operations, ensure power distribution and alarm reporting, and optimize power distribution and maintenance.

Benefits of technology

It realizes alarm reporting and offline maintenance when FTTR equipment is powered off, improves equipment operation stability and reporting success rate, reduces hardware costs, and is suitable for scenarios with limited circuit board design area.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118713740B_ABST
    Figure CN118713740B_ABST
Patent Text Reader

Abstract

The present invention relates to the field of FTTR technology, and specifically to a missed alarm optimization system on FTTR equipment, comprising a power failure sensing module, an analysis module, a controllable power supply module, an alarm reporting module and an offline maintenance module; the present invention controls electric energy distribution through a controllable power supply module, and can realize power failure alarm reporting and offline maintenance without replacing a capacitor device with a larger capacity, thereby reducing hardware costs, and when a large number of FTTR equipment are powered off at the same time, the on-board capacitor can maintain a sufficient discharge time to prevent the power failure alarm message from being sent out; the power failure sensing module and the analysis module are used to accurately capture the occurrence of power failure, thereby ensuring that the FTTR equipment can achieve stable operation after power failure and reconnection; the success rate of reporting DG alarms when a large number of FTTR equipment are powered off is improved; the offline maintenance module and the alarm reporting module are used to optimize the electric energy distribution under power failure conditions, and the system is suitable for design scenarios with limited circuit board design area.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the field of FTTR technology, in particular to a missed report alarm optimization system for FTTR equipment. Background Art

[0002] FTTR technology is a new coverage mode for home networks in the gigabit era. It is a new networking solution that further lays optical fiber to every room on the basis of fiber to the building (FTTB) and fiber to the home (FTTH), realizing full coverage of Wi-Fi6 gigabit in the whole house. The core principle of FTTR technology is to extend optical fiber transmission to specific areas within the building, and realize it through the characteristics of optical fiber data transmission. It usually includes three main parts: optical fiber line terminal (OLT), optical fiber transmission network (FOTN) and user terminal (UE). The optical fiber line terminal extends to the user area through optical fiber, and the optical fiber transmission network smoothly transmits the signal to the user terminal device, thereby establishing a high-speed broadband connection. The FTTR architecture uses optical fiber as the transmission medium to provide high-speed and high-bandwidth network connections. Compared with traditional copper wire networks, optical fiber has faster transmission speeds and larger bandwidths, which can meet users' needs for large-capacity data transmission.

[0003] However, the existing fiber-to-the-building technology has significant deficiencies and limitations in many aspects. First, the city power supply system may experience sudden power outages or line maintenance. The existing FTTR equipment still uses the components and discharge capacitors of the original home gateway unit (HGU) in hardware design, ignoring the power consumption of the new hardware of the FTTR equipment; this results in the onboard capacitor not being able to maintain sufficient discharge time when the equipment loses power, resulting in the failure to send out the power-off alarm message.

[0004] In addition, it is difficult for hundreds or thousands of FTTR devices to simultaneously report power failure alarm messages to the central office equipment at the moment of power failure, thereby maintaining the offline state; this will cause the central office equipment to mistakenly believe that it is still online;

[0005] Therefore, it is necessary to propose a missed alarm optimization system on FTTR equipment to solve the above problems. Summary of the invention

[0006] The purpose of the present invention is to solve the problems existing in the background technology and to propose a missed alarm optimization system on FTTR equipment;

[0007] The purpose of the present invention can be achieved through the following technical solutions: a missed alarm optimization system on FTTR equipment, including a power failure sensing module, an analysis module, a controllable power supply module, an alarm reporting module and an offline maintenance module.

[0008] At every preset time interval △t, the power failure sensing module performs a series of key data collection tasks in the FTTR device, including:

[0009] For each key component, accurately record its temperature Ti and voltage Ui, where i is the component number, i=1, 2, 3, ..., n; n is the total number of components.

[0010] As a preferred embodiment of the present invention, the collected data is visualized and function-fitted, with time as the horizontal axis and device temperature and voltage as the vertical axes, to dynamically generate two sets of images: a temperature-time change graph and a voltage-time change graph. By continuously adding newly collected data points to the image, it is ensured that the image presents a trend of dynamic extension, and that the image intuitively reflects the real-time changes of the temperature and voltage data of the key components.

[0011] In the temperature-time variation graph, the function Ti=f(t) is used for image fitting. In particular, for the latest data point on the rightmost side of the image, the left derivative f+′(ti) at this point is calculated. The temperature prediction value f(ti+△t) after the next time interval △t is predicted and calculated by the function f(ti+△t)=f(ti)+f+′(ti)×△t.

[0012] When the next preset time node is reached, the actual equipment temperature Ti is recorded and compared with the temperature prediction value. If the preset judgment conditions are met at the same time When , it is deemed that a specific operating abnormality or potential risk is detected based on the temperature criterion, and a power-off characteristic signal 1 is generated; where TiMAX is the preset maximum temperature threshold, δ1 is the preset deviation factor, and f (ti + △t) is the temperature prediction value;.

[0013] As a preferred embodiment of the present invention, in the voltage-time variation diagram, the function Ui=g(t) is used for image fitting. An abnormal voltage perception operation is performed in the image, and two voltage fluctuation thresholds are preset: the maximum threshold Umax and the minimum threshold Umin. When there is a voltage value in the image that is higher than the maximum threshold or lower than the minimum threshold, the voltage value is marked as an abnormal voltage, otherwise it is marked as a normal voltage. Subsequently, the voltage abnormality parameter operation and the trigger condition analysis of the power-off characteristic signal 2 are performed, and the moment when the abnormal voltage appears is used as the recording starting point. The time occupied by the abnormal voltage t1 and the time occupied by the normal voltage t2 are obtained, and the voltage abnormality parameter e is calculated by the formula e=t1 / t2. When the voltage abnormality parameter e is greater than the preset threshold, a signal trigger is executed to generate the power-off characteristic signal 2.

[0014] Furthermore, once the power-off characteristic signal 2 is triggered, the abnormal voltage sensing operation process is automatically restarted. When the abnormal voltage is detected next time, the recording starting point is reset, that is, the time when the new abnormal voltage appears is used as the recording starting point, and the voltage abnormality parameter calculation and the trigger condition analysis phase of the power-off characteristic signal 2 are performed again.

[0015] As a preferred method of the present invention, disconnection sensing is performed for each gateway and network terminal in the FTTR device, and a heartbeat packet is uniformly sent to each gateway and network terminal in the FTTR device at a preset time interval △t, and the heartbeat packet traverses the entire FTTR device along the optical fiber network. After receiving the heartbeat packet, each gateway and network terminal replies a response packet to the power failure sensing module, indicating that it has received the heartbeat packet. If the power failure sensing module does not receive a response packet from a gateway or network terminal within the specified preset response time, it is considered that the other party is offline or the connection has been disconnected.

[0016] After each heartbeat packet is sent, the number of response packets n received within the preset response time t1=△t+t2 is counted, and the power-off characteristic parameter E is obtained by the formula E=n / N. Where N is the preset standard value of the number of response packets. In the preset response time, △t is the preset time interval, and t2 is the preset buffer time.

[0017] As a preferred embodiment of the present invention, the analysis module comprehensively considers the power-off characteristic parameters and the power-off characteristic signal to determine whether to generate a DyingGasp signal, specifically:

[0018] When the power-off characteristic parameter E is greater than the preset threshold, the power-off characteristic signal is analyzed. If power-off characteristic signal 1 or power-off characteristic signal 2 is generated at this time, the DyingGasp signal is triggered and the DyingGasp signal is sent to the controllable power supply module and the alarm reporting module.

[0019] The controllable power supply module distributes the electric energy to each component in the FTTR device according to the rated power when the DyingGasp signal is not received. The controllable power supply module performs the POWERDOWN operation after receiving the DyingGasp signal. The POWERDOWN operation specifically stops the power supply to the gateway and network terminal leading to each network user in the FTTR device, and opens the onboard capacitor at the same time to provide targeted power supply to the alarm line and maintenance line. The alarm line includes the alarm reporting module and the hardware equipment controlled by it, and the maintenance line includes the offline maintenance module and the hardware equipment controlled by it.

[0020] After the alarm reporting module senses the DyingGasp signal, it sends a DG alarm message to the local OLT.

[0021] The local OLT specifically refers to the central control device directly connected to the FTTR device that generates the DyingGasp signal, which is responsible for managing and coordinating the entire fiber access network including multiple FTTR devices. These FTTR devices, as terminal nodes in the network, exchange information and alarm notifications with each other through the local OLT. In addition to the FTTR device that triggers the alarm, all FTTR devices connected through the same local OLT are regarded as other FTTR devices, which together constitute the components of this fiber access network.

[0022] The DG alarm message includes the device number, IP address and alarm time of the FTTR device.

[0023] As a preferred embodiment of the present invention, after the offline maintenance module senses the generation of the DyingGasp signal, it executes the power-off preparation and waiting for power-off operations in sequence, wherein the power-off preparation operation is specifically as follows:

[0024] Obtain the number m of onboard capacitors in the FTTR device, and obtain the voltage Vj and capacitance Cj across each onboard capacitor, where j is the onboard capacitor number, j=1, 2, 3, ..., m. By formula Calculate the preparation coefficient Φ, where α is the preset weight factor, μ is the preset exponential factor, β is the preset bias factor, and E is the power-off characteristic parameter. If the preparation coefficient Φ is greater than the preset threshold, save the configuration files of each key component and network connection and execute the waiting power-off operation. If not, send the DyingGasp signal to other FTTR devices.

[0025] As a preferred embodiment of the present invention, the waiting for power failure operation is specifically as follows: after completing the power failure preparation operation, the DG alarm message sent by other FTTR devices is obtained, the device number contained therein is analyzed, and it is marked as a low-preparation device. The remaining power of the onboard capacitor of the FTTR device itself is supplied to the low-preparation device.

[0026] When the offline maintenance module senses that the DyingGasp signal disappears, it performs a system reset operation, retrieves the configuration files of key components and network connections saved in advance, restarts the service and restores the network connection.

[0027] Compared with the prior art, the present invention has the following beneficial effects:

[0028] (1) The present invention controls the distribution of electric energy through a controllable power supply module, and can realize power-off alarm reporting and offline maintenance without replacing capacitors with larger capacity, thereby reducing hardware costs. When a large number of FTTR devices are powered off at the same time, the on-board capacitors can maintain sufficient discharge time to prevent the power-off alarm message from being sent out.

[0029] (2) The present invention accurately captures the occurrence of power failure through the power failure sensing module and the analysis module, ensuring that the FTTR equipment can achieve stable operation after power failure and reconnection; and improves the success rate of reporting DG alarms when a batch of FTTR equipment loses power;

[0030] (3) The present invention optimizes the power distribution in the case of power failure through the offline maintenance module and the alarm reporting module, and can achieve the power failure maintenance effect without replacing a larger capacity capacitor component, which is suitable for design scenarios with limited circuit board design area. BRIEF DESCRIPTION OF THE DRAWINGS

[0031] In order to facilitate understanding by those skilled in the art, the present invention is further described below with reference to the accompanying drawings:

[0032] Figure 1 It is a system block diagram of the present invention. DETAILED DESCRIPTION

[0033] The technical solution of the present invention will be clearly and completely described below in conjunction with the embodiments. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0034] See also Figure 1 As shown, a missed alarm optimization system for FTTR equipment includes a power failure sensing module, an analysis module, a controllable power supply module, an alarm reporting module and an offline maintenance module.

[0035] At every preset time interval △t, the power failure sensing module performs a series of key data collection tasks in the FTTR device, including:

[0036] For each key component, accurately record its temperature Ti and voltage Ui, where i is the component number, i=1, 2, 3, ..., n; n is the total number of components.

[0037] It should be noted that the key components include optical fiber, optical network interface chip, ONU chip, modulation and resolution chip, network interface chip, network processor chip, Ethernet switching chip, wireless local area network (Wi-Fi) chip, security chip, storage chip and other core components of FTTR equipment.

[0038] The collected data are visualized and function-fitted, with time as the horizontal axis and device temperature and voltage as the vertical axes, to dynamically generate two sets of images: a temperature-time change graph and a voltage-time change graph. By continuously adding newly collected data points to the image, it is ensured that the image presents a trend of dynamic extension and that the image intuitively reflects the real-time changes of the temperature and voltage data of the key components.

[0039] In the temperature-time variation graph, the function Ti=f(t) is used for image fitting. In particular, for the latest data point on the rightmost side of the image, the left derivative f+′(ti) at this point is calculated. The temperature prediction value f(ti+△t) after the next time interval △t is predicted and calculated by the function f(ti+△t)=f(ti)+f+′(ti)×△t.

[0040] When the next preset time node is reached, the actual equipment temperature Ti is recorded and compared with the temperature prediction value. If the preset judgment conditions are met at the same time When , it is deemed that a specific operating abnormality or potential risk is detected on the temperature criterion, and a power-off characteristic signal 1 is generated. Wherein TiMAX is the preset maximum temperature threshold, δ1 is the preset deviation factor, and f (ti + △ t) is the temperature prediction value. In the voltage-time variation diagram, the function Ui = g (t) is used for image fitting. The perception operation of abnormal voltage is performed in the image, and two voltage fluctuation thresholds are preset: the maximum threshold Umax and the minimum threshold Umin. When there is a voltage value in the image that is higher than the maximum threshold or lower than the minimum threshold, the voltage value is marked as an abnormal voltage, otherwise it is marked as a normal voltage. Subsequently, the voltage abnormality parameter calculation and the trigger condition analysis of the power-off characteristic signal 2 are performed, and the moment when the abnormal voltage appears is used as the recording starting point. The time occupied by the abnormal voltage t1 and the time occupied by the normal voltage t2 are obtained, and the voltage abnormality parameter e is calculated by the formula e = t1 / t2. When the voltage abnormality parameter e is greater than the preset threshold, the signal trigger is executed to generate the power-off characteristic signal 2.

[0041] Furthermore, once the power-off characteristic signal 2 is triggered, the abnormal voltage sensing operation process is automatically restarted. When the abnormal voltage is detected next time, the recording starting point is reset, that is, the time when the new abnormal voltage appears is used as the recording starting point, and the voltage abnormality parameter calculation and the trigger condition analysis phase of the power-off characteristic signal 2 are performed again.

[0042] Disconnection sensing is performed for each gateway and network terminal in the FTTR device, and a heartbeat packet is uniformly sent to each gateway and network terminal in the FTTR device at a preset time interval △t. The heartbeat packet traverses the entire FTTR device along the optical fiber network. After receiving the heartbeat packet, each gateway and network terminal replies a response packet to the power failure sensing module, indicating that it has received the heartbeat packet. If the power failure sensing module does not receive a response packet from a gateway or network terminal within the specified preset response time, it is considered that the other party is offline or the connection has been disconnected.

[0043] After each heartbeat packet is sent, the number of response packets n received within the preset response time t1=△t+t2 is counted, and the power-off characteristic parameter E is obtained by the formula E=n / N. Where N is the preset standard value of the number of response packets.

[0044] It should be noted that, in the preset response time, Δt is the preset time interval, and t2 is the preset buffer time. The setting of the buffer time increases the fault tolerance rate for transmission delays caused by network delays, system loads, etc., and avoids misjudgments caused by short delays. Both work together in the timeout mechanism of the heartbeat packet to ensure the stability and reliability of the connection between the client and the server.

[0045] The analysis module comprehensively considers the power-off characteristic parameters and the power-off characteristic signals to determine whether a DyingGasp signal is generated, specifically:

[0046] When the power-off characteristic parameter E is greater than the preset threshold, the power-off characteristic signal is analyzed. If power-off characteristic signal 1 or power-off characteristic signal 2 is generated at this time, the DyingGasp signal is triggered and the DyingGasp signal is sent to the controllable power supply module and the alarm reporting module.

[0047] The controllable power supply module distributes the electric energy to each component in the FTTR device according to the rated power when the DyingGasp signal is not received. When the controllable power supply module receives the DyingGasp signal, the POWERDOWN operation is performed.

[0048] It should be noted that the POWERDOWN operation specifically stops powering the gateways and network terminals leading to various network users in the FTTR equipment, and at the same time opens the onboard capacitor to provide targeted power to the alarm line and maintenance line. The alarm line includes the alarm reporting module and the hardware equipment controlled by it, and the maintenance line includes the offline maintenance module and the hardware equipment controlled by it. The purpose of the POWERDOWN operation is to reserve enough power for the FTTR equipment to send DG alarm messages, perform system reset and wait for power-off operations by reducing power consumption and extending discharge time.

[0049] After the alarm reporting module senses the DyingGasp signal, it sends a DG alarm message to the local OLT.

[0050] It should be noted that the OLT refers specifically to the central control device directly connected to the FTTR device that generates the DyingGasp signal, which is responsible for managing and coordinating the entire fiber access network including multiple FTTR devices. These FTTR devices, as terminal nodes in the network, exchange information and alarms with each other through the OLT.

[0051] It should be further explained that, except for the FTTR device itself that triggered the alarm, all FTTR devices connected through the same OLT are regarded as other FTTR devices, which together constitute the component of this fiber optic access network.

[0052] The DG alarm message includes the device number, IP address and alarm time of the FTTR device.

[0053] After the offline maintenance module senses the generation of the DyingGasp signal, it executes the power-off preparation and waiting for power-off operations in sequence, where the power-off preparation operation is specifically as follows:

[0054] Obtain the number m of onboard capacitors in the FTTR device, and obtain the voltage Vj and capacitance Cj across each onboard capacitor, where j is the onboard capacitor number, j=1, 2, 3, ..., m. By formula Calculate the preparation coefficient Φ, where α is the preset weight factor, μ is the preset exponential factor, β is the preset bias factor, and E is the power-off characteristic parameter. If the preparation coefficient Φ is greater than the preset threshold, save the configuration files of each key component and network connection and execute the waiting power-off operation. If not, send the DyingGasp signal to other FTTR devices.

[0055] The waiting for power failure operation is as follows: after completing the power failure preparation operation, obtain the DG alarm message sent by other FTTR devices, analyze the device number contained therein, and mark it as a low-preparation device. Supply the remaining power of the onboard capacitor of the FTTR device itself to the low-preparation device.

[0056] When the offline maintenance module senses that the DyingGasp signal disappears, it performs a system reset operation, retrieves the configuration files of key components and network connections saved in advance, restarts the service and restores the network connection.

[0057] It should be understood that the terms "include" and "comprising" used in the specification and claims of the present disclosure indicate the presence of described features, integers, steps, operations, elements and / or components, but do not exclude the presence or addition of one or more other features, integers, steps, operations, elements, components and / or collections thereof.

[0058] It should also be understood that the terms used in this disclosure are only for the purpose of describing specific embodiments and are not intended to limit the disclosure. As used in this disclosure and claims, the singular forms "a", "an", and "the" are intended to include plural forms unless the context clearly indicates otherwise. It should also be further understood that the term "and / or" used in this disclosure and claims refers to any combination of one or more of the associated listed items and all possible combinations, and includes these combinations;

[0059] The preferred embodiments of the present invention disclosed above are only used to help explain the present invention. The preferred embodiments do not describe all the details in detail, nor do they limit the invention to only specific implementation methods. Obviously, many modifications and changes can be made according to the content of this specification. This specification selects and specifically describes these embodiments in order to better explain the principles and practical applications of the present invention, so that those skilled in the art can understand and use the present invention well. The present invention is limited only by the claims and their full scope and equivalents.

Claims

1. A system for optimizing missed alarms on FTTR equipment, comprising a power failure sensing module, an analysis module and a controllable power supply module, characterized in that: The power-off sensing module performs a series of key data collection tasks in the FTTR device at preset time intervals, accurately records the temperature and voltage of each key component, visualizes and performs function fitting processing on the collected data, and determines whether power-off characteristic signal 1 and power-off characteristic signal 2 are generated through calculation; With time as the horizontal axis and device temperature and voltage as the vertical axes, two sets of images are dynamically generated: temperature-time change graph and voltage-time change graph. By continuously adding newly collected data to the image, it is ensured that the image presents a dynamic extension trend and ensures that the image intuitively reflects the real-time changes of the temperature and voltage data of each key component; In the temperature-time variation diagram, the function Ti=f(t) is used for image fitting; for the latest data point on the rightmost side of the image, the left derivative f+′(ti) at the point is calculated; the temperature prediction value f(ti+△t) after the next time interval △t is predicted and calculated by the function f(ti+△t)=f(ti)+f+′(ti)×△t; When the next preset time node is reached, the actual equipment temperature Ti is recorded and compared with the temperature prediction value. If the preset judgment conditions are met at the same time When , it is deemed that a specific operating abnormality or potential risk is detected based on the temperature criterion, and a power-off characteristic signal 1 is generated; Where TiMAX is the preset maximum temperature threshold, δ1 is the preset deviation factor, and f(ti+△t) is the temperature prediction value; In the voltage-time variation diagram, the function Ui=g(t) is used for image fitting; the abnormal voltage perception operation is performed in the image, and two voltage fluctuation thresholds are preset: the maximum threshold Umax and the minimum threshold Umin. When there is a voltage value in the image that is higher than the maximum threshold or lower than the minimum threshold, the voltage value is marked as an abnormal voltage, otherwise it is marked as a normal voltage; then, the voltage abnormality parameter operation and the trigger condition analysis of the power-off characteristic signal 2 are performed, and the time when the abnormal voltage appears is taken as the recording starting point, and the time occupied by the abnormal voltage t1 and the time occupied by the normal voltage t2 are obtained, and the voltage abnormality parameter e is calculated by the formula e=t1 / t2; when the voltage abnormality parameter e is greater than the preset threshold, a signal trigger is executed to generate the power-off characteristic signal 2; Once the power-off characteristic signal 2 is triggered, the abnormal voltage sensing and calculation process is automatically restarted; when the abnormal voltage is detected next time, the time when the new abnormal voltage appears is used as the recording starting point, and the voltage abnormality parameter calculation and the triggering condition analysis phase of the power-off characteristic signal 2 are performed again; the disconnection sensing is performed for each gateway and network terminal in the FTTR equipment to determine whether the DyingGasp signal is generated; The analysis module comprehensively considers the power-off characteristic parameter and the power-off characteristic signal to determine whether to generate a DyingGasp signal. When the power-off characteristic parameter E is greater than a preset threshold, the power-off characteristic signal is analyzed. If a power-off characteristic signal 1 or a power-off characteristic signal 2 is generated, the DyingGasp signal is triggered and sent to the controllable power supply module and the alarm reporting module. When the controllable power supply module does not receive the DyingGasp signal, it distributes the electric energy to each component in the FTTR device according to the rated power. When the controllable power supply module receives the DyingGasp signal, it performs the POWERDOWN operation, specifically: in the FTTR device, it stops supplying power to the gateway and network terminals leading to each network user, and at the same time opens the on-board capacitor to provide targeted power supply to the alarm line and maintenance line.

2. According to claim 1, a system for optimizing missed alarms on FTTR equipment, characterized in that: It also includes an alarm reporting module and an offline maintenance module; After the alarm reporting module senses the DyingGasp signal, it sends a DG alarm message to the local OLT; the local OLT specifically refers to the central control device directly connected to the FTTR device that generates the DyingGasp signal; the DG alarm message contains the device number, IP address and alarm time of the FTTR device; After the offline maintenance module senses the DyingGasp signal, it executes the power-off preparation and waiting for power-off operations in sequence; when the offline maintenance module senses that the DyingGasp signal disappears, it executes the system reset operation, calls the configuration files of key components and network connections saved in advance, restarts the service and restores the network connection.

3. The system for optimizing missed alarms on FTTR equipment according to claim 1, characterized in that: The specific process of determining whether a DyingGasp signal is generated through calculation is as follows: A heartbeat packet is sent to each gateway and network terminal in the FTTR device at a preset time interval △t. The heartbeat packet traverses the entire FTTR device along the optical fiber network. After receiving the heartbeat packet, each gateway and network terminal replies with a response packet to the power failure sensing module, indicating that it has received the heartbeat packet. If the power failure sensing module does not receive a response packet from a gateway or network terminal within the specified preset response time, it is considered that the other party is offline or the connection has been disconnected. After each heartbeat packet is sent, the number of response packets n received within the preset response time t1=△t+t2 is counted, and the power-off characteristic parameter E is obtained by the formula E=n / N; Wherein N is a preset standard value of the number of response packets; in the preset response time, Δt is a preset time interval, and t2 is a preset buffer time.

4. The system for optimizing missed alarms on FTTR equipment according to claim 1, characterized in that: The specific power-off preparation operations are as follows: Obtain the number m of onboard capacitors in the FTTR device, and obtain the voltage Vj and capacitance value Cj across each onboard capacitor, where j is the onboard capacitor number, j=1, 2, 3, ..., m; By formula Calculate the preparation coefficient Φ, where α is a preset weight factor, μ is a preset exponential factor, β is a preset bias factor, and E is a power-off characteristic parameter; If the preparation coefficient Φ is greater than the preset threshold, the configuration files of each key component and network connection are saved and the waiting for power failure operation is executed; if not, a DyingGasp signal is sent to other FTTR devices.

5. The system for optimizing missed alarms on FTTR equipment according to claim 1, characterized in that: The specific operation of waiting for power failure is as follows: Obtain the DG alarm message sent by other FTTR devices, analyze the device number contained therein, and mark it as a low-readiness device; supply the remaining power of the FTTR device's own onboard capacitor to the low-readiness device.