Automatic laser cutting production line for pipes
By designing an automated laser cutting production line for pipes and using three-dimensional storage and automatic scheduling technology, the problem of existing equipment being unable to achieve unattended automated production was solved, efficient pipe cutting and management was achieved, operating costs were reduced, and product quality was ensured.
Patent Information
- Application Number
- CN202410809371.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-06-21
- Publication Date
- 2024-10-01
- Estimated Expiration
- 2044-06-21
AI Technical Summary
Existing laser cutting equipment cannot realize unattended automated production throughout the entire process, resulting in high labor costs, high safety requirements, multiple tasks, and high operating costs. It is also unable to meet the growing demand for output quantity and ensure product quality and concurrency. Qualitative.
An automated laser cutting production line for pipes is designed, including a three-dimensional storage device, a laser cutting device and a retrieval device. The pre-storage, automatic scheduling and cutting of pipes are realized through the lifting mechanism, stacking mechanism and transfer mechanism, combined with pipe detection and sorting. Palletizing device realizes multi-process unattended automated production.
It realizes the pre-storage, automatic scheduling and cutting of pipes, reduces the number of labor and costs, improves production efficiency and management efficiency, and ensures product quality and homogeneity.
Smart Images

Figure CN118720439A_ABST
Abstract
Description
Technical Field
[0001] The present application relates to the field of laser cutting technology, and in particular to an automated laser cutting production line for pipes. Background Art
[0002] With the rapid growth of the output and consumption of metal pipes in my country, in order to meet the market demand of the industry, various laser processing equipment products for pipe workpiece cutting have successively attracted the attention of users and are also widely used in more and more industries. The advantages of laser cutting are: small thermal deformation, high cutting accuracy, low noise, no pollution, easy to achieve automatic cutting, wide application range, flexible process, high processing accuracy, good quality, clean production process, and improved product quality and labor productivity.
[0003] In actual processing and manufacturing, since the purchased pipes are generally long, they need to be cut according to the designed length. Considering the requirements for the flatness of the cut, laser pipe cutting machines are generally selected for cutting. The current related equipment mainly uses a small trailer to drag the long pipe, and the laser pipe cutting machine does not move. The small trailer drives the long pipe to move toward the laser cutting head of the laser pipe cutting machine to adjust the length of the cut. With the concepts of "unmanned operation", "autonomous production" and "smart factory" sweeping the laser industry, the demand for automated production in the laser pipe cutting machine market is high, but the existing laser cutting equipment cannot achieve unmanned automated production throughout the entire process. There are still defects such as high labor costs, high safety requirements, more harmful tasks to enterprise workers, and high operating costs. In addition, the low-efficiency production of a single machine cannot meet the growing demand for output quantity and ensure the quality and homogeneity of the products. Summary of the invention
[0004] The present application aims to solve the technical problems in the above-mentioned technologies to at least a certain extent, and to overcome the technical problems that the existing laser cutting equipment cannot realize unattended automated production including the entire process, and still has high labor costs, high safety requirements, many work tasks that are harmful to enterprise workers, high operating costs, and cannot meet the growing output quantity demand and ensure product quality and homogeneity, and to solve the shortcomings and deficiencies in the existing technology. This application provides an automated laser cutting production line for pipes.
[0005] The technical solution adopted in this application is:
[0006] An automated laser cutting production line for pipes comprises: a three-dimensional storage device, the three-dimensional storage device comprises a three-dimensional frame, a lifting mechanism and a stacking mechanism, the three-dimensional frame has a plurality of pipe storage stations arranged in sequence along the vertical direction, each pipe storage station is provided with a corresponding pipe storage structure for storing pipes, the lifting mechanism can drive the stacking mechanism to rotate between a discharge station and a transfer station corresponding to the pipe storage station, so that the stacking mechanism can obtain the pipe storage structure located at the pipe storage station at the transfer station and transfer it to the discharge station; at least one laser cutting device, each laser cutting device comprises a laser cutting head, a material transport guide rail and a pipe A material positioning mechanism, the pipe positioning mechanism can transfer the pipe from a material receiving station to a cutting station along the material transport guide rail, and the laser cutting head performs a cutting action on the pipe located at the cutting station; a material picking device, the material picking device includes a material picking guide rail, a moving component and a material picking component, the material picking component is arranged on the moving component, and the moving component can drive the material picking component to rotate between the material picking station corresponding to the discharging station and the unloading station corresponding to the material receiving station along the material picking guide rail, so that the material picking component can unload the pipe to the pipe positioning mechanism located at the material receiving station at the unloading station after obtaining the pipe from the pipe storage structure at the material picking station.
[0007] The automatic laser cutting production line for pipes provided in this application also includes the following additional technical features:
[0008] The lifting mechanism can drive the stacking mechanism to rotate between the transfer station and a transit station, so that the stacking mechanism can obtain the pipe storage structure located at the pipe storage station at the transfer station and transfer it to the transfer station, and the stacking mechanism can transfer the pipe storage structure from the transfer station to a cache platform; the three-dimensional storage device also includes a loading structure, which includes a loading platform and a transfer mechanism installed on the loading platform, and the transfer mechanism can drive the pipe storage structure to rotate between the cache platform and the loading platform.
[0009] The transfer mechanism includes a first motor and at least one first transmission unit, the first transmission unit includes a first driving sprocket, a plurality of first driven sprockets and a first transmission chain connecting the first driving sprocket and the plurality of first driven sprockets, the first driving sprocket is transmission-connected to the output shaft of the first motor, and the first transmission chain is provided with a first pull rod for pulling the pipe storage structure to move.
[0010] The feeding structure and the stacking mechanism are respectively located on both sides of the three-dimensional frame, the cache platform is located between the feeding structure and the stacking mechanism, the feeding platform is equipped with a buffer component, the buffer component is provided with an elastic buffer body, and when the transfer mechanism moves the pipe storage structure to the feeding platform, the pipe storage structure is abutted against the elastic buffer body.
[0011] The stacking mechanism includes a stacking bracket and a second motor and a second transmission unit respectively installed on the stacking bracket, the second transmission unit includes a second driving sprocket, a plurality of second driven sprockets and a second transmission chain connecting the second driving sprocket and the plurality of second driven sprockets, the second driving sprocket is transmission-connected to the output shaft of the second motor, the second transmission chain is provided with a second pull rod for pulling the pipe storage structure to move, and the lifting mechanism drives the stacking bracket to move up and down.
[0012] The lifting mechanism includes a third motor, a third driving sprocket, a plurality of third driven sprockets, a lifting sprocket, and a third transmission chain connecting the third driving sprocket, the plurality of third driven sprockets, and the lifting sprocket. The third motor is installed on the three-dimensional frame, the third driving sprocket is transmission-connected to the output shaft of the third motor, the lifting sprocket is fixed to the stacking bracket, and the third transmission chain drives the stacking bracket to move up and down through the lifting sprocket.
[0013] The three-dimensional frame is provided with a vertical guide rail extending in a vertical direction, and the stacking bracket is in sliding or rolling cooperation with the vertical guide rail.
[0014] The pipe storage structure includes a vehicle-mounted platform and rollers arranged below the vehicle-mounted platform. The vehicle-mounted platform is used to store pipes. The pipe storage station is provided with a horizontal guide rail. The pipe storage structure enters and exits the pipe storage station by rolling the rollers along the horizontal guide rail.
[0015] A plurality of blocking rods extending in a vertical direction are arranged on two opposite sides of the vehicle-mounted platform so as to limit the pipe on the vehicle-mounted platform through the blocking rods.
[0016] The material picking device includes two parallel arranged support frames, the support frames extend between the three-dimensional storage device and the laser cutting device, the material picking guide rail is arranged on the top of the support frames, the moving component is constructed as a moving beam perpendicular to the two support frames, the material picking component includes a first manipulator and a second manipulator, the first manipulator can be vertically slidably arranged at one end of the moving component, and the second manipulator can slide horizontally along the moving component and can slide vertically relative to the moving component.
[0017] The moving component drives the picking component to move from the picking station to the unloading station and can transfer at an inspection station; the laser cutting production line also includes a pipe detection device, and the pipe detection device includes a camera component and a fill light component. The fill light component can emit light to the pipe located at the inspection station. The camera component obtains the structural information of the pipe by photographing the pipe located at the inspection station, and transmits the structural information to the control unit of the laser cutting production line, so that the control unit controls the picking device and the laser cutting device according to the structural information to perform actions matching the structural information; the structural information at least includes the contour information and size information of the pipe.
[0018] The pipe positioning mechanism includes a supporting component, a first chuck and a second chuck. The supporting component supports the pipe unloaded by the material picking component at the material receiving station. The first chuck and the second chuck clamp the two ends of the pipe at the material receiving station and transfer the pipe from the material receiving station to the cutting station along the material transport guide rail.
[0019] The laser cutting device also includes a short material receiving plate that can be flipped up and down, a long material receiving plate that can be flipped up and down, and a material unloading structure for unloading the pipes cut by the laser cutting head. The material unloading structure can transfer the pipes cut by the laser cutting head to the first unloading station or the second unloading station along the material transport guide rail. The material unloading structure unloads short pipes less than or equal to a preset length onto the short material receiving plate at the first unloading station, and unloads long pipes greater than the preset length onto the long material receiving plate at the second unloading station. The material unloading structure includes a third chuck and a fourth chuck.
[0020] The production line also includes a sorting and stacking device, which includes a material drop chute, a material drop platform and a sorting mechanism. The material drop chute is correspondingly arranged on one side of the short material receiving plate to receive the short pipes that are flipped and unloaded by the short material receiving plate. The material drop platform is correspondingly arranged on one side of the long material receiving plate to receive the long pipes that are flipped and unloaded by the long material receiving plate. The sorting mechanism is used to count the long pipes on the material drop platform and transfer them to another preset position.
[0021] The sorting mechanism includes two sorting brackets arranged in parallel, the sorting brackets are provided with sorting guide rails, the sorting guide rails are provided with sorting beams, the sorting beams are provided with sorting axes that can move in the vertical direction, the sorting axes extend horizontally and a plurality of electromagnets are arranged at intervals along the axial direction so that the long pipes on the blanking platform can be sucked by the electromagnets, and the sorting beams can move on the horizontal plane along the sorting guide rails so as to transfer the long pipes sucked by the electromagnets to the preset positions.
[0022] The production line also includes a transport track and a material transport trolley that can move back and forth on the transport track, and the sorting mechanism can transfer the pipes on the drop platform to the material transport trolley.
[0023] The laser cutting device also includes a shield covering the laser cutting head, and a coding device is installed on the outer side of the shield, and the coding device is used to perform coding operations on the pipe cut by the laser cutting head.
[0024] Due to the adoption of the above technical solution, the technical effects achieved by this application include at least:
[0025] 1. In the present invention, the three-dimensional storage device provides pre-storage and pipe scheduling functions for pipe workpieces to be processed. Before the production line is operated, a corresponding number of pipes to be processed can be stored in all pipe storage structures in advance. The pipe storage structure is placed in the pipe storage station so that the lifting mechanism can drive the stacking mechanism to lift and lower so that the stacking mechanism can schedule the pipe storage structure from the pipe storage station to the discharging station one by one, so as to provide a source of pipes for the material taking device. When the pipes in a pipe storage structure are taken out at the discharging station and are empty, the stacking mechanism and the lifting mechanism can be used to reset the pipe storage structure from the discharging station to the pipe storage station where it was originally located, and then go to other pipe storage stations to schedule the pipe storage structure storing the pipes to be processed. All pipe storage stations are arranged in sequence along the vertical direction of the three-dimensional frame. Compared with the horizontal arrangement, the vertical arrangement allows the three-dimensional frame to store a large number of pipes to be processed in the height direction on the basis of a smaller footprint. Therefore, after replenishing materials to all pipe storage structures at one time, the production line can achieve unattended automatic operation for a long time. The material collection guide provides a running track for the moving parts to circulate between the material collection station and the unloading station, so that the moving parts can drive the material collection parts to obtain the pipes to be processed from the pipe storage structure and then unload the pipes to be processed onto the pipe positioning mechanism, so that the pipe positioning mechanism carries the pipes to be processed to the cutting station, and the pipes to be processed are cut into finished pipes that meet the requirements by the laser cutting head at the cutting station according to the preset program. Therefore, the production line provided by the technical solution realizes the pre-storage of pipe workpieces to be processed, automatic scheduling of pipes by lifting and stacking mechanisms, automatic transfer of pipes from the three-dimensional storage device to the laser cutting device by the material taking device, and automatic cutting of the pipes after they reach the laser cutting. It realizes a multi-process unattended automated production mode, and the cutting system and the production line intelligent scheduling control system are deeply integrated and controlled, automatically scheduling and allocating production plans, and automatically feeding the laser cutting device without interruption, which greatly improves production efficiency and management efficiency, reduces labor quantity and costs, has higher safety performance, and can effectively guarantee product quality and the homogeneity of processing of pipes of the same specifications.
[0026] 2. The stacking mechanism can transfer the pipe storage structure from the pipe storage station to the transfer station and then to the cache platform, so that the transfer mechanism can transfer the pipe storage structure from the cache platform to the loading platform, which is suitable for loading the empty pipe storage structure. Therefore, through the operation and coordination of the lifting mechanism, the stacking mechanism and the transfer mechanism, the empty pipe storage structure in the pipe storage station can be dispatched to the loading platform, so that the pipe workpieces to be processed can be added to the pipe storage structure on the loading platform, which greatly improves the convenience of replenishing pipe raw materials. After the pipes are replenished, the lifting mechanism, the stacking mechanism and the transfer mechanism are used to restore the pipe storage structure to its original pipe storage station, so that one-click warehousing can be achieved.
[0027] 3. The material picking component includes a first manipulator and a second manipulator. The first manipulator can be vertically slidably arranged at one end of the moving component, and the second manipulator can slide horizontally along the moving component and can slide vertically relative to the moving component. Firstly, the first manipulator and the second manipulator can both realize vertical movement, and the cooperation of the two can clamp and obtain the pipes stacked at different heights on the pipe storage structure, so that the material picking component can obtain the pipes to be processed one by one from high to low; secondly, the second manipulator can slide horizontally along the moving component, and the horizontal distance between it and the first manipulator changes during the sliding process. Therefore, by horizontally sliding the second manipulator, the distance between the first manipulator and the second manipulator can be adjusted to a distance that matches the length of the pipe, thereby improving the adaptability to pipes of different length specifications.
[0028] 4. The moving component drives the picking component to move from the picking station to the unloading station and transfers to an inspection station. After the picking component obtains the pipe to be processed from the pipe storage structure at the picking station, the moving component can drive the picking component to move to the inspection station. At this time, the camera component can photograph the pipe to be processed to obtain the structural information of the pipe to be processed and transmit the structural information to the control unit. After obtaining the relevant structural information, the control unit can analyze it through the corresponding algorithm to obtain the contour size and phase relationship of the pipe to be processed, and transmit the final execution command to the picking device and the laser cutting device, so that the picking device automatically adjusts the clamping force of the first manipulator and the second manipulator on the pipe, and the laser cutting device automatically adjusts the clamping force of the pipe positioning mechanism and the unloading structure on the pipe, so that the clamping force adapts to the thickness of the pipe to prevent the pipe from being piled up and deformed due to excessive clamping force. The laser cutting device can also be controlled to automatically call the cutting process library to achieve automatic cutting.
[0029] 5. The laser cutting device can realize automatic unloading and automatic sorting of the pipes after cutting through the unloading structure. Short pipes are unloaded onto the short material receiving plate, and long pipes are unloaded onto the long material receiving plate, which is convenient for the classification and management of finished pipes.
[0030] 6. The sorting and stacking device collects and organizes the short pipes that fall from the short material receiving plate through the material drop chute, and collects and organizes the long pipes that fall from the long material receiving plate through the material drop platform. The sorting mechanism is used to count the long pipes on the material drop platform and transfer them to another preset position, realizing automatic sorting, transfer and stacking, and improving management efficiency and production efficiency.
[0031] 7. The production line also includes a transport track and a material transport trolley that can move back and forth on the transport track. The finished pipes sorted by the sorting mechanism can be stacked in the material transport trolley. After stacking to a specified number, the material transport trolley is transported to a specified warehouse location via the transport track or returned to the finished product layer in the three-dimensional storage device through the return function.
[0032] 8. The coding device is used to code the finished pipes after cutting by the laser cutting head. It can realize product management conveniently and quickly, effectively improve economic benefits, and can be connected to the enterprise network system to realize network management and unattended operation. BRIEF DESCRIPTION OF THE DRAWINGS
[0033] The drawings described herein are used to provide a further understanding of the present application and constitute a part of the present application. The illustrative embodiments of the present application and their descriptions are used to explain the present application and do not constitute an improper limitation on the present application. In the drawings:
[0034] Figure 1 Schematic diagram of the structure of the pipe automatic laser cutting production line provided in the embodiment of the present application Figure 1 ;
[0035] Figure 2 Schematic diagram of the structure of the pipe automatic laser cutting production line provided in the embodiment of the present application Figure 2 ;
[0036] Figure 3 A schematic diagram of the structure of the three-dimensional storage device provided in the embodiment of the present application Figure 1 ;
[0037] Figure 4 A schematic diagram of the structure of the three-dimensional storage device provided in the embodiment of the present application Figure 2 ;
[0038] Figure 5 for Figure 4 A partial enlarged view of the structure at A in the middle;
[0039] Figure 6 A schematic diagram of the structure of the stacking mechanism provided in the embodiment of the present application;
[0040] Figure 7 for Figure 1 A partial enlarged view of the structure at point B in the middle.
[0041] List of parts and reference numerals:
[0042] 1 three-dimensional storage device, 11 three-dimensional frame, 111 pipe storage station, 112 left column, 113 right column, 114 connecting column, 115 vertical guide rail, 116 horizontal guide rail, 12 lifting mechanism, 121 third motor, 122 third driving sprocket, 123 third driven sprocket, 124 lifting sprocket, 125 third transmission chain, 13 stacking mechanism, 131 stacking bracket, 132 second motor, 133 second driving sprocket, 134 a second driven sprocket, 135 a second transmission chain, 136 a second pull rod, 14 a pipe storage structure, 141 a vehicle-mounted platform, 142 a roller, 143 a blocking rod, 15 a buffer platform, 16 a feeding structure, 161 a feeding platform, 162 a transfer mechanism, 1621 a first motor, 1622 a first driving sprocket, 1623 a first driven sprocket, 1624 a first transmission chain, 1625 a first pull rod, 163 a buffer component, 1631 an elastic buffer body;
[0043] 2 laser cutting device, 21 laser cutting head, 22 material transport guide rail, 23 pipe positioning mechanism, 231 supporting component, 232 first chuck, 233 second chuck, 24 short material receiving plate, 25 long material receiving plate, 26 unloading structure, 261 third chuck, 262 fourth chuck, 27 shield;
[0044] 3 material picking device, 31 material picking guide rail, 32 moving component, 33 material picking component, 331 first manipulator, 332 second manipulator, 34 support frame;
[0045] 4 pipe inspection device, 41 camera component, 42 fill light component;
[0046] 5 sorting and stacking device, 51 material dropping chute, 52 material dropping platform, 53 sorting mechanism, 531 sorting bracket, 532 sorting guide rail, 533 sorting beam, 534 sorting shaft, 535 electromagnet;
[0047] 6 transport tracks;
[0048] 7Material transport trolley;
[0049] 8. Coding device. DETAILED DESCRIPTION
[0050] In order to more clearly illustrate the overall concept of the present application, a detailed description is given below in an illustrative manner in conjunction with the accompanying drawings.
[0051] In the following description, many specific details are set forth to facilitate a full understanding of the present application. However, the present application may also be implemented in other ways different from those described herein. Therefore, the scope of protection of the present application is not limited to the specific embodiments disclosed below.
[0052] In addition, in the description of the present application, it should be understood that the terms "upper", "lower", "top", "bottom", "inside", "outside", "axial", "radial", "circumferential", "lateral", "longitudinal", etc., indicating orientations or positional relationships are based on the orientations or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present application and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore should not be understood as a limitation on the present application.
[0053] In this application, unless otherwise clearly specified and limited, the terms "installed", "connected", "connected", "fixed" and the like should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection, an electrical connection, or a communication; it can be a direct connection, or an indirect connection through an intermediate medium, it can be the internal connection of two elements or the interaction relationship between two elements. For ordinary technicians in this field, the specific meanings of the above terms in this application can be understood according to specific circumstances.
[0054] In the present application, unless otherwise clearly specified and limited, a first feature "above" or "below" a second feature may be that the first and second features are in direct contact, or the first and second features are in indirect contact through an intermediate medium. In the description of this specification, the description with reference to the terms "one embodiment", "some embodiments", "example", "specific example", or "some examples" means that the specific features, structures, materials or characteristics described in conjunction with the embodiment or example are included in at least one embodiment or example of the present application. In this specification, the schematic representation of the above terms does not necessarily refer to the same embodiment or example. Moreover, the specific features, structures, materials or characteristics described may be combined in an appropriate manner in any one or more embodiments or examples.
[0055] In the embodiments of the present application, an automatic laser cutting production line for pipes is provided. For the convenience of explanation and understanding, the following contents provided in the present application are all described based on the illustrated product structure. Of course, those skilled in the art can understand that the above structure is only used as a specific example and schematic description, and cannot constitute a specific limitation on the technical solution provided in the present application.
[0056] like Figures 1 to 7As shown, the present application provides an automated laser cutting production line for pipes, comprising a three-dimensional storage device 1, at least one laser cutting device 2 and a material taking device 3, wherein: the three-dimensional storage device 1 comprises a three-dimensional frame 11, a lifting mechanism 12 and a stacking mechanism 13, the three-dimensional frame 11 has a plurality of pipe storage stations 111 arranged in sequence along the vertical direction, each pipe storage station 111 is correspondingly provided with a pipe storage structure 14 for storing pipes, the lifting mechanism 12 can drive the stacking mechanism 13 to rotate between a discharge station and a transfer station corresponding to the pipe storage station 111, so that the stacking mechanism 13 can obtain the pipe storage structure 14 located at the pipe storage station 111 at the transfer station and transfer it to the discharge station; each laser cutting device 2 comprises a laser The optical cutting head 21, the material transport guide rail 22 and the pipe positioning mechanism 23, the pipe positioning mechanism 23 can transfer the pipe from a material receiving station to a cutting station along the material transport guide rail 22, and the laser cutting head 21 performs a cutting action on the pipe located at the cutting station; the material picking device 3 includes a material picking guide rail 31, a moving component 32 and a material picking component 33, the material picking component 33 is arranged on the moving component 32, and the moving component 32 can drive the material picking component 33 to rotate between the material picking station corresponding to the discharging station and the unloading station corresponding to the material receiving station along the material picking guide rail 31, so that the material picking component 33 can unload the pipe to the pipe positioning mechanism 23 located at the material receiving station at the unloading station after obtaining the pipe from the pipe storage structure 14 at the material picking station.
[0057] In the present invention, the three-dimensional storage device 1 provides pre-storage and pipe scheduling functions for the pipe workpieces to be processed. Before the production line is operated, a corresponding number of pipes to be processed ( Figure 3 and Figure 4The figure shows the state in which the pipe storage structure 14 stores pipes), the pipe storage structure 14 is placed in the pipe storage station 111, so that the lifting mechanism 12 can drive the stacking mechanism 13 to lift and lower so that the stacking mechanism 13 can dispatch the pipe storage structure 14 from the pipe storage station 111 to the discharging station one by one, so as to provide a source of pipes for the material taking device 3. When the pipes in a pipe storage structure 14 are taken out at the discharging station and are empty, the stacking mechanism 13 and the lifting mechanism 12 can be used to reset the pipe storage structure 14 from the discharging station to the pipe storage station 111 where it was originally located, and then go to other pipe storage stations 111 to dispatch the pipe storage structure 14 that stores the pipes to be processed. All pipe storage stations 111 are arranged in sequence along the vertical direction of the three-dimensional frame 11. Compared with the horizontal arrangement, the vertical arrangement allows the three-dimensional frame 11 to store a large amount of pipes to be processed in the height direction on the basis of a smaller footprint. Therefore, after replenishing materials to all pipe storage structures 14 at a time, the production line can achieve unattended automatic operation for a long time. In addition, multiple pipe storage stations 111 can also be used to store pipes in a classified manner. Pipes to be processed of different specifications can be distributed in different pipe storage stations 111, which is convenient for management and reduces management and operation costs. The material collection guide rail 31 provides a running track for the moving component 32 to circulate between the material collection station and the unloading station, so that the moving component 32 can drive the material collection component 33 to obtain the pipes to be processed from the pipe storage structure 14 and then unload the pipes to be processed onto the pipe positioning mechanism 23, so that the pipe positioning mechanism 23 carries the pipes to be processed to the cutting station, and the pipes to be processed are cut into finished pipes that meet the requirements by the laser cutting head 21 at the cutting station according to a preset program. Therefore, the production line provided by the present technical solution realizes the pre-storage of pipe workpieces to be processed, the automatic scheduling of pipes by the lifting mechanism 12 and the stacking mechanism 13, the automatic transfer of pipes from the three-dimensional storage device 1 to the laser cutting device 2 by the material taking device 3, and the automatic cutting of the pipes after they arrive at the laser cutting, thereby realizing a multi-process unattended automated production mode, in which the cutting system and the production line intelligent scheduling control system are deeply integrated and controlled, the production plan is automatically scheduled and allocated, and the laser cutting device 2 is automatically fed with materials without interruption, which greatly improves production efficiency and management efficiency, reduces the number of labor and costs, has higher safety performance, and can effectively guarantee product quality and the homogeneity of processing of pipes of the same specifications.
[0058] Regarding the structure of the three-dimensional frame 11, in a preferred embodiment, it can be formed by welding a metal structure, for example, it can be formed by welding steel materials, specifically, as shown in FIG. Figure 3As shown, the three-dimensional frame 11 includes a left column 112 and a right column 113 and a connecting column 114 connected between the left column 112 and the right column 113. The left column 112 and the right column 113 constitute a vertical support. The connecting column 114 can be arranged on the top and the rear side of the left column 112 and the right column 113 to connect the left column 112 and the right column 113 as a whole, thereby ensuring the structural strength of the three-dimensional frame 11.
[0059] The present application does not limit the number of laser cutting devices 2. For example, Figure 1 The figure schematically illustrates an embodiment in which two laser cutting devices 2 are arranged side by side. The two laser cutting devices 2 can work simultaneously to realize multi-machine parallel connection. A single stereo frame 11 storage warehouse can take care of the loading tasks of multiple laser cutting devices 2 and support the loading of various pipes to the designated laser cutting device 2, thereby improving production efficiency.
[0060] As a preferred implementation of the present application, Figure 1As shown, the lifting mechanism 12 can drive the stacking mechanism 13 to rotate between the transfer station and a transit station, so that the stacking mechanism 13 can obtain the pipe storage structure 14 located at the pipe storage station 111 at the transfer station and transfer it to the transit station, and the stacking mechanism 13 can transfer the pipe storage structure 14 from the transit station to a cache platform 15; the three-dimensional storage device 1 also includes a loading structure 16, and the loading structure 16 includes a loading platform 161 and a transfer mechanism 162 installed on the loading platform 161, and the transfer mechanism 162 can drive the pipe storage structure 14 to rotate between the cache platform 15 and the loading platform 161. Those skilled in the art can understand that the stacking mechanism 13 can transfer the pipe storage structure 14 from the pipe storage station 111 to the transfer station and then to the cache platform 15, so that the transfer mechanism 162 can transfer the pipe storage structure 14 from the cache platform 15 to the loading platform 161, which is suitable for loading the empty pipe storage structure 14. Therefore, through the operation and coordination of the lifting mechanism 12, the stacking mechanism 13 and the transfer mechanism 162, the empty pipe storage structure 14 in the pipe storage station 111 can be dispatched to the loading platform 161, so that the pipe workpiece to be processed can be added to the pipe storage structure 14 on the loading platform 161, which greatly improves the convenience of replenishing pipe raw materials. After the pipes are replenished, the lifting mechanism 12, the stacking mechanism 13 and the transfer mechanism 162 are used to restore the pipe storage structure 14 to its original location in the pipe storage station 111, so that one-click warehousing can be achieved. In addition, the present application sets up a cache platform 15 to facilitate the suspension of the pipe storage structure 14 there. The stacking mechanism 13 can transport the pipe storage structure 14 to the cache platform 15 and then leave. The pipe storage structure 14 can wait for the transfer mechanism 162 to transfer it to the loading platform 161. Moreover, through the transfer cache of the cache platform 15, the loading platform 161 is as far away from the three-dimensional frame 11 as possible to obtain a wider loading space, thereby improving the convenience of replenishing materials into the pipe storage structure 14.
[0061] Regarding the specific form of the transfer mechanism 162, in a preferred embodiment, as Figure 4 and Figure 5As shown, the transfer mechanism 162 includes a first motor 1621 and at least one first transmission unit, the first transmission unit includes a first driving sprocket 1622, a plurality of first driven sprockets 1623, and a first transmission chain 1624 connecting the first driving sprocket 1622 and the plurality of first driven sprockets 1623, the first driving sprocket 1622 is in driving connection with the output shaft of the first motor 1621, and the first transmission chain 1624 is provided with a first pull rod 1625 for pulling the pipe storage structure 14 to move. The present application depicts an embodiment in which the transfer mechanism 162 includes two sets of first transmission units, the two sets of first transmission units are arranged at both ends of the loading platform 161, and the two sets of first transmission units are synchronously operated through the first motor 1621 to improve the reliability of transfer. Specifically, when the first motor 1621 is running, it drives the first driving sprocket 1622 to rotate, and during the rotation of the first driving sprocket 1622, it drives the first transmission chain 1624 to rotate. The first driving sprocket 1622 and the plurality of first driven sprockets 1623 jointly support the first transmission chain 1624 to rotate. During the rotation of the first transmission chain 1624, the first pull rod 1625 arranged thereon can pull the pipe storage structure 14 to move, and the pipe storage structure 14 can be pulled from the buffer platform 15 to the loading platform 161 and from the loading platform 161 to the buffer platform 15 by the forward and reverse rotation of the first motor 1621. In order to facilitate the first pull rod 1625 to pull the pipe storage structure 14, a hook can be arranged on the pipe storage structure 14 so that the first pull rod 1625 cooperates with the hook.
[0062] More preferably, if Figures 3 to 5 As shown, the feeding structure 16 and the stacking mechanism 13 are respectively located on both sides of the three-dimensional frame 11, the buffer platform 15 is located between the feeding structure 16 and the stacking mechanism 13, the feeding platform 161 is installed with a buffer component 163, and the buffer component 163 is provided with an elastic buffer body 1631. When the transfer mechanism 162 moves the pipe storage structure 14 to the feeding platform 161, the pipe storage structure 14 is abutted against the elastic buffer body 1631. For example, the feeding structure 16 can be located at the rear side of the three-dimensional frame 11 as a whole, and the stacking mechanism 13 can be located at the front side of the three-dimensional frame 11, so as to realize the arrangement of rear-side feeding and front-side laser cutting processing, reasonably utilize the site space, and facilitate the feeding and processing in different areas. The buffer component 163 can stop, position and buffer the pipe storage structure 14 when the transfer mechanism 162 moves the pipe storage structure 14 to the loading platform 161, thereby preventing the pipe storage structure 14 from falling off the loading platform 161 due to inertia.
[0063] Regarding the specific form of the stacking mechanism 13, as a preferred embodiment, Figure 3 and Figure 6As shown, the stacking mechanism 13 includes a stacking bracket 131, a second motor 132 and a second transmission unit respectively mounted on the stacking bracket 131, the second transmission unit includes a second driving sprocket 133, a plurality of second driven sprockets 134, and a second transmission chain 135 connecting the second driving sprocket 133 and the plurality of second driven sprockets 134, the second driving sprocket 133 is in driving connection with the output shaft of the second motor 132, the second transmission chain 135 is provided with a second pull rod 136 for pulling the pipe storage structure 14 to move, and the lifting mechanism 12 drives the stacking bracket 131 to move up and down. Specifically, a set of second transmission units can be arranged at each end of the stacking bracket 131 to ensure operational reliability. The stacking bracket 131 is used to support the pipe storage structure 14, and the second transmission unit is used to transfer the pipe storage structure 14 between different positions, so as to realize the transfer of the pipe storage structure 14 from other positions such as the pipe storage station 111 and the cache platform 15 to the stacking bracket 131 or from the stacking bracket 131 to other positions. Specifically, when the second motor 132 is running, it drives the second driving sprocket 133 to rotate, and during the rotation of the second driving sprocket 133, it drives the second transmission chain 135 to rotate. The second driving sprocket 133 and multiple second driven sprockets 134 jointly support the rotation of the second transmission chain 135. During the rotation of the second transmission chain 135, the second pull rod 136 arranged thereon can pull the pipe storage structure 14 to move. The forward and reverse rotation of the second motor 132 can realize pulling the pipe storage structure 14 from the pipe storage station 111 to the stacking bracket 131 or pulling the pipe storage structure 14 from the stacking bracket 131 to the pipe storage station 111, and pulling the pipe storage structure 14 from the stacking bracket 131 to the cache platform 15 or pulling the pipe storage structure 14 from the cache platform 15 to the stacking bracket 131. To facilitate the second pull rod 136 to pull the pipe storage structure 14, a hook can be set on the pipe storage structure 14 so that the second pull rod 136 can cooperate with the hook. Therefore, hooks can be set on both the front and rear sides of the pipe storage structure 14 to facilitate the pulling of the first pull rod 1625 and the second pull rod 136.
[0064] Furthermore, if Figure 3 and Figure 4As shown, the lifting mechanism 12 includes a third motor 121, a third driving sprocket 122, a plurality of third driven sprockets 123, a lifting sprocket 124, and a third transmission chain 125 connecting the third driving sprocket 122, the plurality of third driven sprockets 123, and the lifting sprocket 124. The third motor 121 is installed on the three-dimensional frame 11. The third driving sprocket 122 is connected to the output shaft of the third motor 121 by transmission. The lifting sprocket 124 is fixed to the stacking bracket 131. The third transmission chain 125 drives the stacking bracket 131 to move up and down through the lifting sprocket 124. Specifically, when the third motor 121 is running, it drives the third driving sprocket 122 to rotate. During the rotation of the third driving sprocket 122, it drives the lifting sprocket 124 to move up and down during the turnover of the second transmission chain 135. Since the lifting sprocket 124 is fixed to the stacking bracket 131, the stacking bracket 131 can be lifted and lowered. The present application does not limit the specific arrangement of the third active sprocket 122, the third driven sprocket 123 and the third transmission chain 125, and the arrangement may refer to the existing sprocket chain transmission mechanism, as long as it can drive the lifting sprocket 124 to move up and down during operation.
[0065] Furthermore, if Figure 3 As shown, the three-dimensional frame 11 is provided with a vertical guide rail 115 extending in the vertical direction, and the stacking bracket 131 slides or rolls with the vertical guide rail 115. When the lifting mechanism 12 drives the stacking mechanism 13 to move up and down, the vertical guide rail 115 can guide and limit the stacking bracket 131 to ensure the stability of its lifting movement.
[0066] Regarding the specific form of the pipe storage structure 14, in a preferred embodiment, as Figure 4As shown, the pipe storage structure 14 includes a vehicle-mounted platform 141 and a roller 142 arranged below the vehicle-mounted platform 141. The vehicle-mounted platform 141 is used to store pipes. The pipe storage station 111 is provided with a horizontal guide rail 116. The pipe storage structure 14 moves in and out of the pipe storage station 111 by rolling the roller 142 along the horizontal guide rail 116. The pipe storage structure 14 is composed of the vehicle-mounted platform 141 and the roller 142 to form a pipe storage trolley. The pipe storage station 111 is provided with a horizontal guide rail 116 to facilitate the pipe storage structure 14 to move in and out of the pipe storage station 111, making it easier for the stacking mechanism 13 to pull the pipe storage structure 14. In addition, in order to facilitate the stacking mechanism 13 to pull the pipe storage structure 14 onto the stacking bracket 131, a guide rail structure adapted to the horizontal guide rail 116 can also be provided on the stacking bracket 131, so that the roller 142 of the pipe storage structure 14 can also roll on the stacking bracket 131. In addition, in order to facilitate the stacking mechanism 13 to pull the pipe storage structure 14 onto the buffer platform 15, a guide rail structure can also be provided on the buffer platform 15, so that the roller 142 of the pipe storage structure 14 can also roll on the buffer platform 15.
[0067] Furthermore, if Figure 4 As shown, a plurality of baffles 143 extending in the vertical direction are provided on two opposite sides of the vehicle-mounted platform 141 , so that the pipes can be confined on the vehicle-mounted platform 141 through the baffles 143 , thereby effectively preventing the pipes from rolling off the vehicle-mounted platform 141 .
[0068] Regarding the specific structure of the material taking device 3, in a preferred embodiment, as Figure 1 and Figure 2As shown, the material picking device 3 includes two parallel arranged support frames 34, and the support frames 34 extend between the three-dimensional storage device 1 and the laser cutting device 2. The material picking guide rail 31 is arranged on the top of the support frame 34. The moving component 32 is constructed as a moving beam perpendicular to the two support frames 34. The material picking component 33 includes a first manipulator 331 and a second manipulator 332. The first manipulator 331 can be vertically slidably arranged at one end of the moving component 32, and the second manipulator 332 can slide horizontally along the moving component 32 and can slide vertically relative to the moving component 32. First, the first manipulator 331 and the second manipulator 332 can both move in the vertical direction. The cooperation between the two can clamp and obtain the pipes stacked at different heights on the pipe storage structure 14, so that the material-picking component 33 can obtain the pipes to be processed one by one from high to low; secondly, the second manipulator 332 can slide horizontally along the moving component 32, and the horizontal distance between it and the first manipulator 331 changes during the sliding process. Therefore, by sliding the second manipulator 332 horizontally, the distance between the first manipulator 331 and the second manipulator 332 can be adjusted to a distance that matches the length of the pipe, so that the pipes of different lengths can be clamped, and the adaptability to pipes of different length specifications can be improved. Specifically, the first manipulator 331 and the second manipulator 332 can slide in the vertical direction respectively through the guide rail structure, and the second manipulator 332 and the moving beam can also slide horizontally through the guide rail structure. The moving beam can be driven by a cylinder, an oil cylinder, a telescopic cylinder, etc. to move along the material-picking guide rail 31.
[0069] As a preferred embodiment of the present application, the moving component 32 drives the picking component 33 to move from the picking station to the unloading station and can be transferred in a detection station; Figure 1 and Figure 7As shown, the laser cutting production line also includes a tube detection device 4, and the tube detection device 4 includes a camera component 41 and a fill light component 42. The fill light component 42 can emit light to the tube located at the detection station, and the camera component 41 obtains the structural information of the tube by photographing the tube located at the detection station, and transmits the structural information to the control unit of the laser cutting production line, so that the control unit controls the material picking device 3 and the laser cutting device 2 according to the structural information to perform actions matching the structural information; the structural information at least includes the contour information and size information of the tube. Those skilled in the art can understand that the moving component 32 drives the picking component 33 to move from the picking station to the unloading station and transfers at an inspection station. After the picking component 33 obtains the pipe to be processed from the pipe storage structure 14 at the picking station, the moving component 32 can drive the picking component 33 to move to the inspection station. At this time, the camera component 41 can photograph the pipe to be processed to obtain the structural information of the pipe to be processed and transmit the structural information to the control unit. After obtaining the relevant structural information, the control unit can analyze it through the corresponding algorithm to obtain the contour size of the pipe to be processed, and transmit the final execution command to the picking device 3 and the laser cutting device 2, so that the picking device 3 automatically adjusts the clamping force of the first manipulator 331 and the second manipulator 332 on the pipe, and the laser cutting device 2 automatically adjusts the clamping force of the pipe positioning mechanism 23 and the unloading structure 26 on the pipe, so that the clamping force adapts to the thickness of the pipe to prevent the pipe from being piled up and deformed due to excessive clamping force. The laser cutting device 2 can also be controlled to automatically call the cutting process library to achieve automatic cutting. Specifically, the present application does not limit the specific location of the detection station, as long as it is set on the path from the material picking station to the material unloading station. For example, the material picking component 33 can be used as the detection station to take the pipe from the pipe storage structure 14 and move it to the highest position that the material picking component 33 can reach. In addition, the camera component 41 can also be used to photograph the pipes in the pipe storage structure 14 to obtain the phase relationship of each pipe, so that the control unit can control the moving component 32 and the material picking component 33 to move in phase to the material picking station to grab the corresponding pipe from the pipe storage structure 14. When the camera component 41 cannot clearly obtain the pipe structure information due to too dark light, fill light can be used by the fill light component 42. The camera component 41 can use an industrial camera, and the fill light component 42 can use a light source panel. Specifically, the pipe detection device 4 can be installed on the support frame 34.
[0070] Regarding the specific structure of the pipe positioning mechanism 23, in a preferred embodiment, as shown in FIG. Figure 1 and Figure 2As shown, the pipe positioning mechanism 23 includes a supporting component 231, a first chuck 232 and a second chuck 233. The supporting component 231 supports the pipe unloaded by the material taking component 33 at the material receiving station. The first chuck 232 and the second chuck 233 clamp the two ends of the pipe at the material receiving station, and transfer the pipe from the material receiving station to the cutting station along the material transport guide 22. Specifically, the pipe clamped by the material taking component 33 can be placed on the supporting component 231 in advance and supported by the supporting component 231. At this time, the material taking component 33 can leave the unloading station, and the first chuck 232 and the second chuck 233 adjust the corresponding distance to clamp the two ends of the pipe, and then move along the material transport guide 22 to the cutting station.
[0071] Regarding the specific structure of the laser cutting device 2, in a preferred embodiment, as shown in FIG. Figure 1 and Figure 2 As shown, it also includes a short material receiving plate 24 that can be flipped up and down, a long material receiving plate 25 that can be flipped up and down, and a material unloading structure 26 for unloading the pipe cut by the laser cutting head 21. The material unloading structure 26 can transfer the pipe cut by the laser cutting head 21 to the first unloading station or the second unloading station along the material transport guide rail 22. The material unloading structure 26 unloads short pipes less than or equal to a preset length onto the short material receiving plate 24 at the first unloading station, and the material unloading structure 26 unloads long pipes greater than the preset length onto the long material receiving plate 25 at the second unloading station. The material unloading structure 26 includes a third chuck 261 and a fourth chuck 262. The third chuck 261 and the fourth chuck 262 are used to clamp and transfer the finished pipe cut by the laser cutting head 21, and move to the first unloading station or the second unloading station according to the length of the finished pipe. For example, when the preset length is 1.5 meters, when the length of the finished pipe after cutting is less than or equal to 1.5 meters, the unloading structure 26 is moved to the first unloading station and the finished pipe is placed on the short material receiving plate 24. When the length of the finished pipe after cutting is greater than 1.5 meters, the unloading structure 26 is moved to the second unloading station and the finished pipe is placed on the long material receiving plate 25. The laser cutting device 2 can realize automatic unloading and automatic sorting of the pipes after cutting through the unloading structure 26. The short pipes are unloaded to the short material receiving plate 24, and the long pipes are unloaded to the long material receiving plate 25, which is convenient for the classification and management of the finished pipes. The short material receiving plate 24 and the long material receiving plate 25 can both be turned upside down, so the finished pipes received by the short material receiving plate 24 and the long material receiving plate 25 can be unloaded to a designated position by turning upside down. Specifically, the short material receiving plate 24 and the long material receiving plate 25 can be respectively hinged on the corresponding seat body and driven by a cylinder to turn upside down.
[0072] Furthermore, if Figure 1 and Figure 2As shown, the production line also includes a sorting and stacking device 5, which includes a material drop chute 51, a material drop platform 52 and a sorting mechanism 53. The material drop chute 51 is correspondingly arranged on one side of the short material receiving plate 24 to receive the short pipes that are turned over and unloaded by the short material receiving plate 24, and the material drop platform 52 is correspondingly arranged on one side of the long material receiving plate 25 to receive the long pipes that are turned over and unloaded by the long material receiving plate 25; the sorting mechanism 53 is used to count the long pipes on the material drop platform 52 and transfer them to another preset position. The sorting and stacking device 5 collects and organizes the short pipes that are turned over by the short material receiving plate 24 through the material drop chute 51, and collects and organizes the long pipes that are turned over by the long material receiving plate 25 through the material drop platform 52. The sorting mechanism 53 is used to count the long pipes on the material drop platform 52 and transfer them to another preset position, so as to realize automatic sorting, transfer and stacking, and improve management efficiency and production efficiency.
[0073] Regarding the specific structure of the sorting mechanism 53, in a preferred embodiment, as shown in FIG. Figure 1 and Figure 2 As shown, the sorting mechanism 53 includes two sorting brackets 531 arranged in parallel, the sorting brackets 531 are provided with sorting guide rails 532, the sorting guide rails 532 are provided with sorting beams 533, and the sorting beams 533 are provided with sorting shafts 534 movable in the vertical direction, the sorting shaft 534 extends horizontally and a plurality of electromagnets 535 are arranged at intervals along the axial direction, so that the long pipes on the blanking platform 52 can be sucked by the electromagnets 535, and the sorting beams 533 can move on the horizontal plane along the sorting guide rails 532 to transfer the long pipes sucked by the electromagnets 535 to the preset positions. Specifically, the sorting beam 533 drives the sorting shaft 534 to move during its movement along the sorting guide rail 532. When the sorting shaft 534 moves to the top of the long tube on the blanking platform 52, the sorting shaft 534 is controlled to move downward and the electromagnet 535 is energized to generate suction, so that the long tube can be adsorbed on the electromagnet 535. Then, the sorting shaft 534 is controlled to move upward, and the long tube is transferred to the top of the preset position by the movement of the sorting beam 533 along the sorting guide rail 532. Then, after the electromagnet 535 is powered off, the long tube can fall off the electromagnet 535 and fall to the designated position. Of course, after the long tube is transferred to the top of the preset position, the sorting shaft 534 can be moved downward again to slowly place the long tube to the designated position to avoid damage to the tube due to free fall.
[0074] Furthermore, if Figure 1 and Figure 2As shown, the production line also includes a transport track 6 and a material transport trolley 7 that can move back and forth on the transport track 6, and the sorting mechanism 53 can transfer the pipes on the drop platform 52 to the material transport trolley 7. The finished pipes sorted by the sorting mechanism 53 can be stacked in the material transport trolley 7. After stacking to a specified number, the material transport trolley 7 is transported to a specified warehouse location through the transport track 6 or returned to the finished product layer in the three-dimensional storage device 1 through the return function.
[0075] As a preferred implementation of the present application, Figure 2 As shown, the laser cutting device 2 also includes a shield 27 for covering the laser cutting head 21, and a coding device 8 is installed on the outer side of the shield 27, and the coding device 8 is used to implement coding operation on the pipe cut by the laser cutting head 21. Coding the finished pipe after cutting by the coding device 8 can realize product management conveniently and quickly, effectively improve economic benefits, and can be connected to the enterprise network system to realize network management and realize unattended operation.
[0076] The present invention is described in further detail below through specific embodiments:
[0077] The automatic laser cutting production line for pipes of the present invention can realize the round-trip transmission of bundled raw material pipes (pipes to be processed) and finished material pipes, and realize automatic reception, intelligent allocation, task scheduling, and flexible processing and production. When all the raw material pipes in the three-dimensional frame 11 are cut, it is necessary to fill the warehouse, that is, put the raw material pipes into the pipe storage structure 14, the lifting mechanism 12 lifts the stacking mechanism 13 to the designated transfer station, the stacking mechanism 13 pulls the pipe storage structure 14 out to the stacking bracket 131, and the lifting mechanism 12 transports the stacking mechanism 13 downward to the transfer station, and then the stacking mechanism 13 drags the pipe storage structure 14 in reverse to the cache platform 15, and the transfer mechanism 162 pulls the pipe storage structure 14 to the loading platform 161. At this time, the operator puts the raw material pipes into the pipe storage structure 14 and clicks the feed warehouse button. The system controls the transfer mechanism 162, the stacking mechanism 13 and the lifting mechanism 12 to operate and transport the pipe storage structure 14 back to the pipe storage station 111 where it was originally located, and repeats the above operations until all pipe storage structures 14 are filled with raw material pipes. When the central dispatching system assigns a task requiring cutting of raw material pipes, the specific location of the raw material pipes to be cut is first confirmed based on the raw material pipe data information in the pipe storage stations 111 on each layer. The system controls the lifting mechanism 12 and the stacking mechanism 13 to transport the selected pipe storage structure 14 to the unloading station. The mobile beam moves the first manipulator 331 and the second manipulator 332 to the material picking station and grabs the raw material pipes in the pipe storage structure 14 by moving the second manipulator 332 left and right and the first manipulator 331 and the second manipulator 332 up and down. Then, the raw material pipes are transported to the inspection station by the movement of the mobile beam so that the pipe inspection device 4 can inspect the raw material pipes, fill in the light through the fill-in light component 42, and take pictures through the camera component 41. The structural information after taking the pictures is transmitted to the control unit, so that the control The unit analyzes the raw material pipe through the corresponding algorithm to obtain the outline size and phase relationship, and transmits the final execution command to the material picking device 3 and the laser cutting device 2. The raw material pipe after detection by the pipe detection device 4 is transported to the supporting component 231 by the first manipulator 331 and the second manipulator 332. The first manipulator 331 and the second manipulator 332 release the raw material pipe and leave the laser cutting device 2. The first chuck 232 and the second chuck 233 move to the end position of the raw material pipe and clamp the pipe and then transport it to the laser cutting head 21. The laser cutting head 21 cuts the raw material pipe to obtain the finished pipe. After the coding device 8 performs coding operation on the cut finished pipe, the finished pipe is transported to the first unloading station or the second unloading station for unloading through the third chuck 261 and the fourth chuck 262.After unloading, the short pipes are unloaded by the short material receiving plate 24 to the blanking trough 51 for storage, and the long pipes are unloaded by the long material receiving plate 25 to the blanking platform 52. The sorting and stacking device 5 counts the long pipes and stacks them into the material transport trolley 7. After the long pipes in the material transport trolley 7 are stacked to a specified number, the material transport trolley 7 transports the long pipes to a specified warehouse location via the transport track 6 or returns them to the finished product layer of the three-dimensional storage device 1 through the return function.
[0078] Anything not described in this application can be achieved by adopting or drawing on existing technologies.
[0079] The various embodiments in this specification are described in a progressive manner, and the same or similar parts between the various embodiments can be referenced to each other, and each embodiment focuses on the differences from other embodiments.
[0080] The above is only the embodiment of the present application and is not intended to limit the present application. For those skilled in the art, the present application may have various changes and variations. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present application should be included in the scope of the claims of the present application.
Claims
1. An automatic laser cutting production line for pipes, characterized in that: include: A three-dimensional storage device, the three-dimensional storage device comprises a three-dimensional frame, a lifting mechanism and a stacking mechanism, the three-dimensional frame has a plurality of pipe storage stations arranged in sequence along the vertical direction, each pipe storage station is provided with a corresponding pipe storage structure for storing pipes, the lifting mechanism can drive the stacking mechanism to rotate between a discharge station and a transfer station corresponding to the pipe storage station, so that the stacking mechanism can obtain the pipe storage structure located at the pipe storage station at the transfer station and transfer it to the discharge station; At least one laser cutting device, each laser cutting device comprising a laser cutting head, a material transport guide rail and a pipe positioning mechanism, wherein the pipe positioning mechanism is capable of transferring the pipe from a material receiving station to a cutting station along the material transport guide rail, and the laser cutting head performs a cutting action on the pipe located at the cutting station; A material picking device, the material picking device includes a material picking guide rail, a moving component and a material picking component, the material picking component is arranged on the moving component, the moving component can drive the material picking component to rotate between the material picking station corresponding to the material discharging station and the unloading station corresponding to the material receiving station along the material picking guide rail, so that the material picking component can unload the pipe to the pipe positioning mechanism located at the material receiving station at the unloading station after obtaining the pipe from the pipe storage structure at the material picking station.
2. The automatic laser cutting production line for pipes according to claim 1 is characterized in that: The lifting mechanism can drive the stacking mechanism to rotate between the transfer station and a transit station, so that the stacking mechanism can obtain the pipe storage structure located at the pipe storage station at the transfer station and transfer it to the transfer station, and the stacking mechanism can transfer the pipe storage structure from the transfer station to a cache platform; the three-dimensional storage device also includes a loading structure, which includes a loading platform and a transfer mechanism installed on the loading platform, and the transfer mechanism can drive the pipe storage structure to rotate between the cache platform and the loading platform.
3. The automatic laser cutting production line for pipes according to claim 2 is characterized in that: The transfer mechanism includes a first motor and at least one first transmission unit, the first transmission unit includes a first driving sprocket, a plurality of first driven sprockets and a first transmission chain connecting the first driving sprocket and the plurality of first driven sprockets, the first driving sprocket is transmission-connected to the output shaft of the first motor, and the first transmission chain is provided with a first pull rod for pulling the pipe storage structure to move.
4. The automatic laser cutting production line for pipes according to claim 3 is characterized in that: The feeding structure and the stacking mechanism are respectively located on both sides of the three-dimensional frame, the cache platform is located between the feeding structure and the stacking mechanism, the feeding platform is equipped with a buffer component, the buffer component is provided with an elastic buffer body, and when the transfer mechanism moves the pipe storage structure to the feeding platform, the pipe storage structure is abutted against the elastic buffer body.
5. The automatic laser cutting production line for pipes according to claim 1 is characterized in that: The stacking mechanism includes a stacking bracket and a second motor and a second transmission unit respectively installed on the stacking bracket, the second transmission unit includes a second driving sprocket, a plurality of second driven sprockets and a second transmission chain connecting the second driving sprocket and the plurality of second driven sprockets, the second driving sprocket is transmission-connected to the output shaft of the second motor, the second transmission chain is provided with a second pull rod for pulling the pipe storage structure to move, and the lifting mechanism drives the stacking bracket to move up and down.
6. The automatic laser cutting production line for pipes according to claim 5 is characterized in that: The lifting mechanism includes a third motor, a third driving sprocket, a plurality of third driven sprockets, a lifting sprocket, and a third transmission chain connecting the third driving sprocket, the plurality of third driven sprockets, and the lifting sprocket. The third motor is installed on the three-dimensional frame, the third driving sprocket is transmission-connected to the output shaft of the third motor, the lifting sprocket is fixed to the stacking bracket, and the third transmission chain drives the stacking bracket to move up and down through the lifting sprocket.
7. The automatic laser cutting production line for pipes according to claim 6 is characterized in that: The three-dimensional frame is provided with a vertical guide rail extending in a vertical direction, and the stacking bracket is in sliding or rolling cooperation with the vertical guide rail.
8. The automatic laser cutting production line for pipes according to claim 1 is characterized in that: The pipe storage structure includes a vehicle-mounted platform and rollers arranged below the vehicle-mounted platform. The vehicle-mounted platform is used to store pipes. The pipe storage station is provided with a horizontal guide rail. The pipe storage structure enters and exits the pipe storage station by rolling the rollers along the horizontal guide rail.
9. The automatic laser cutting production line for pipes according to claim 8, characterized in that: A plurality of blocking rods extending in a vertical direction are arranged on two opposite sides of the vehicle-mounted platform so as to limit the pipe on the vehicle-mounted platform through the blocking rods.
10. The automatic laser cutting production line for pipes according to claim 1, characterized in that: The material picking device includes two parallel arranged support frames, the support frames extend between the three-dimensional storage device and the laser cutting device, the material picking guide rail is arranged on the top of the support frames, the moving component is constructed as a moving beam perpendicular to the two support frames, the material picking component includes a first manipulator and a second manipulator, the first manipulator can be vertically slidably arranged at one end of the moving component, and the second manipulator can slide horizontally along the moving component and can slide vertically relative to the moving component.
11. The automatic laser cutting production line for pipes according to claim 1, characterized in that: The moving component drives the material taking component to move from the material taking station to the material discharging station and can transfer in a detection station; The laser cutting production line also includes a tube detection device, which includes a camera component and a fill light component. The fill light component can emit light to the tube located at the detection station. The camera component obtains the structural information of the tube by photographing the tube located at the detection station, and transmits the structural information to the control unit of the laser cutting production line, so that the control unit controls the material picking device and the laser cutting device according to the structural information to perform actions matching the structural information; the structural information at least includes the contour information and size information of the tube.
12. The automatic laser cutting production line for pipes according to claim 1, characterized in that: The pipe positioning mechanism includes a supporting component, a first chuck and a second chuck. The supporting component supports the pipe unloaded by the material picking component at the material receiving station. The first chuck and the second chuck clamp the two ends of the pipe at the material receiving station and transfer the pipe from the material receiving station to the cutting station along the material transport guide rail.
13. The automatic laser cutting production line for pipes according to claim 1, characterized in that: The laser cutting device also includes a short material receiving plate that can be flipped up and down, a long material receiving plate that can be flipped up and down, and a material unloading structure for unloading the pipes cut by the laser cutting head. The material unloading structure can transfer the pipes cut by the laser cutting head to the first unloading station or the second unloading station along the material transport guide rail. The material unloading structure unloads short pipes less than or equal to a preset length onto the short material receiving plate at the first unloading station, and unloads long pipes greater than the preset length onto the long material receiving plate at the second unloading station. The material unloading structure includes a third chuck and a fourth chuck.
14. The automatic laser cutting production line for pipes according to claim 13, characterized in that: It also includes a sorting and stacking device, which includes a material drop trough, a material drop platform and a sorting mechanism. The material drop trough is correspondingly arranged on one side of the short material receiving plate to receive the short pipes that are flipped and unloaded by the short material receiving plate. The material drop platform is correspondingly arranged on one side of the long material receiving plate to receive the long pipes that are flipped and unloaded by the long material receiving plate. The sorting mechanism is used to count the long pipes on the material drop platform and transfer them to another preset position.
15. The automatic laser cutting production line for pipes according to claim 14, characterized in that: The sorting mechanism includes two sorting brackets arranged in parallel, the sorting brackets are provided with sorting guide rails, the sorting guide rails are provided with sorting beams, the sorting beams are provided with sorting axes that can move in the vertical direction, the sorting axes extend horizontally and a plurality of electromagnets are arranged at intervals along the axial direction so that the long pipes on the blanking platform can be sucked by the electromagnets, and the sorting beams can move on the horizontal plane along the sorting guide rails so as to transfer the long pipes sucked by the electromagnets to the preset positions.
16. The automatic laser cutting production line for pipes according to claim 15, characterized in that: It also includes a transport track and a material transport trolley that can move back and forth on the transport track, and the sorting mechanism can transfer the pipes on the drop platform to the material transport trolley.
17. The automatic laser cutting production line for pipes according to claim 1, characterized in that: The laser cutting device also includes a shield covering the laser cutting head, and a coding device is installed on the outer side of the shield, and the coding device is used to perform coding operations on the pipe cut by the laser cutting head.
Citation Information
Patent Citations
Pipe recognition method and device based on laser pipe cutting device
CN111421226A
Intelligent production method of automobile seat armrests
CN112276355A
Intelligent profile machining system, method and device and electronic equipment
CN113199255A
Laser cutting automatic production system and production method
CN115091056A
Four-chuck laser pipe cutting system
CN117900623A
Cited By
Blank cutting and conveying automatic connection equipment for steel pipe production line
CN119260074A
Pipe feeding and discharging system
CN120942779A
Transferring and discharging device of laser cutting machine
CN121799929A