Construction and installation method of floating production storage and offloading (FPSO) upper module buttress
Through the method of tire frame sealing and inspection while installing, the problems of welding deformation and large errors in the construction of FPSO upper module buttresses are solved, the size and installation accuracy of the buttresses are improved, and the levelness and positional accuracy of the buttresses are ensured. .
Patent Information
- Application Number
- CN202410972914.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-19
- Publication Date
- 2024-10-01
- Estimated Expiration
- 2044-07-19
AI Technical Summary
The FPSO upper module buttresses are prone to welding deformation during the construction and installation process, and due to the beam arch on the main deck of the hull, the buttress construction errors are large, making it difficult to meet the accuracy requirements.
The top panel of the buttress is prefabricated with a tire frame, and is sealed by pressing and sealing the tire plate. It is inspected during installation, and the welding process and real-time monitoring are strictly implemented to ensure the size and installation accuracy of the buttress.
Through the method of tire frame sealing and inspection while installing, the deformation of the top panel of the buttress is reduced, the size and installation accuracy of the buttress are improved, and the levelness and position accuracy of the buttress are ensured.
Smart Images

Figure CN118723008A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of manufacturing FPSO upper module buttresses, and in particular to a method for constructing and installing FPSO upper module buttresses. Background Art
[0002] In the construction of FPSO, the pier is the connection hub between the upper module and the hull, which is used to effectively and smoothly transfer the load of the upper module to the ship deck and evenly distribute it to the hull. However, the construction and installation of the pier is prone to welding deformation due to the huge amount of welding between the module pier panel and the cross reinforcement plate and the coaming. At the same time, since the main deck of the hull has a 0.9m high beam arch in the ship width direction, and the upper surface of the module pier is required to be horizontal, this puts higher requirements on the construction of the module pier. In actual construction, the error of the pier is large, and the construction and installation of the pier needs to be improved to meet the actual construction requirements. Summary of the invention
[0003] The object of the present invention is to provide a method for constructing and installing piers of an upper module of an FPSO, which method greatly improves the dimensional accuracy and installation accuracy of the piers.
[0004] In order to solve the above technical problems, the technical solution adopted by the present invention is:
[0005] A method for constructing and installing a FPSO upper module buttress, characterized in that it comprises the following steps:
[0006] Step 1: Tire frame production: The produced tire frame is used for prefabrication of module piers; the horizontality of the upper surface of the tire frame is required to be no more than 1mm;
[0007] Step 2, fix the top panel of the pier and mark the installation position of the components: after the size inspection of the top panel of the pier is qualified, hoist it onto the tire frame, adjust the horizontality of the top panel of the pier to make the top panel of the pier fit closely with the surface of the tire frame, align the center line of the top panel of the pier with the cross center ground line, and seal the top panel of the pier to the surface of the tire frame by using the pressure code and the tire sealing plate;
[0008] Step 3: Marking of component installation positions: The components include the pier cross reinforcement plate and the surrounding plates around the pier. Mark the pier cross reinforcement plate installation line, pier surrounding plate installation line and 100mm inspection line on the surface of the pier top panel;
[0009] Step 4, install the pier cross reinforcement plate: hoist the pier cross reinforcement plate to the pier cross reinforcement plate installation line on the surface of the pier top panel, use a 100mm inspection line to check the position installation accuracy of the pier cross reinforcement plate, use a right-angle ruler to measure and control the verticality of the pier cross reinforcement plate, and then weld the pier cross reinforcement plate to the pier top panel;
[0010] Step 5, install the panels around the pier: The panels around the cross reinforcement plate of the pier are installed by symmetrical welding. One panel is hoisted to the pier panel installation line on the surface of the pier top panel and the position and installation accuracy of the panel is checked with a 100mm inspection line. After welding the panel to the cross reinforcement plate of the pier and the top panel of the pier, install the panel on the opposite side of the panel.
[0011] Step 6, pier measurement: After the surrounding panels are installed, select 9 inspection points, of which 5 inspection points are the center point and 4 edge endpoints of the pier cross reinforcement plate, and the other 4 inspection points are the 4 corner connections surrounded by the four panels;
[0012] Step 7: Marking of installation positions of each pier: According to the theoretical dimensions of the deck sections and module piers, the installation position identification lines and inspection lines of the cross reinforcement plates and coamings corresponding to each pier are marked on the FPSO hull deck;
[0013] Step 8, welding of each pier: hoist each pier onto the FPSO's hull deck, align the surrounding plates and the pier cross reinforcement plates with the installation position marking lines marked on the deck, and use a 100mm inspection line to check the position and installation accuracy of the coamings and pier cross reinforcement plates; weld each pier onto the FPSO's hull deck;
[0014] Step 9: Position accuracy inspection of each pier: After the welding of each pier under an upper module is completed, measurement should be carried out, and the positions that do not meet the accuracy requirements should be trimmed, and then the horizontality and height data of each pier panel should be measured.
[0015] Furthermore, in step 4, the verticality error of the pier cross reinforcement plate is less than 1 mm.
[0016] Furthermore, in step 9, a reference pole is erected on the FPSO's hull deck. The reference pole is made of a square steel pipe, and four total station reference light targets are attached to the four sides of the square steel pipe. All total station reference light targets are calibrated to ensure that they are at the same horizontal height.
[0017] Furthermore, in step 8, the deviation between the center line of the pier cross reinforcement plate on each pier and the installation position marking line of the cross reinforcement plate of each pier on the hull deck of the FPSO is ≤±4mm.
[0018] Furthermore, in step 8, the deviation between the center line of the surrounding panels on each pier and the marking line of the panel installation position of each pier on the hull deck of the FPSO is ≤±6mm.
[0019] Furthermore, in step 9, the horizontality of the top panel of each pier is ≤3 mm.
[0020] Furthermore, in step 9, the center height deviation of the pier top panel of each pier is ≤4mm.
[0021] Furthermore, in step 9, the deviation of each pier along the length and width of the ship is ≤±6mm.
[0022] The beneficial effects of the present invention are:
[0023] The present invention seals the top panel of the pier by means of a tire frame, and when the cross reinforcement plate and the enclosure plate are welded, the top panel of the pier has a very small deformation, thereby ensuring the horizontality of the top panel of the pier and the dimensional accuracy of the pier; the present invention adopts a method of simultaneous installation and detection, strictly implements the welding process and monitors the welding in real time, and once a deviation is found, timely adjustment should be made immediately, thereby greatly improving the dimensional accuracy and installation accuracy of the pier. BRIEF DESCRIPTION OF THE DRAWINGS
[0024] The present invention is further described with the aid of the accompanying drawings, but the embodiments in the accompanying drawings do not constitute any limitation to the present invention. A person skilled in the art can obtain other accompanying drawings according to the following drawings without creative work:
[0025] Figure 1 is a flow chart of the present invention;
[0026] Figure 2 This is a schematic diagram of the structure after the installation of the cross reinforcement plate of the pier;
[0027] Figure 3 This is the layout diagram of the 9 inspection points after the installation of the hoarding;
[0028] Figure 4 A schematic diagram showing the marking of the installation positions of the various piers on the deck surface;
[0029] Figure 5 This is the detection layout diagram of the reference pole and reference light target. DETAILED DESCRIPTION
[0030] In order to enable those skilled in the art to better understand the technical solution of the present invention, the present invention is further described in detail below in conjunction with the accompanying drawings and specific embodiments. It should be noted that the embodiments of the present application and the features therein can be combined with each other without conflict.
[0031] In the description of the present invention, it should be understood that the terms "center", "longitudinal", "lateral", "length", "width", "thickness", "upper surface", "lower surface", "front", "back", "left", "right", "vertical", "horizontal", "top", "bottom", "inside", "outside", "forward", "reverse", "axial", "radial", "circumferential" and the like indicate orientations or positional relationships based on the orientations or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present invention and simplifying the description, and do not indicate or imply that the referred device or element must have a specific orientation, be constructed and operated in a specific orientation, and therefore should not be understood as limiting the present invention.
[0032] like Figure 1 As shown, a method for constructing and installing a FPSO upper module buttress is characterized by comprising the following steps:
[0033] Step 1, tire frame production: the produced tire frame is used for prefabrication of module piers; the horizontality of the upper surface of the tire frame is required to be no more than 1mm.
[0034] Step 2, fix the top panel of the pier: after the size inspection of the top panel of the pier is passed, hoist it onto the tire frame, adjust the horizontality of the top panel of the pier to make the top panel of the pier fit closely with the surface of the tire frame, align the center line of the top panel of the pier with the cross center ground line, and then use the pressure code and tire sealing plate to seal the top panel of the pier to the surface of the tire frame.
[0035] Step 3: Marking of component installation positions: The components include the pier cross reinforcement plate and the surrounding plates around the pier. Mark the pier cross reinforcement plate installation line, pier surrounding plate installation line and 100mm inspection line on the surface of the pier top panel.
[0036] Step 4, install the pier cross reinforcement plate: hoist the pier cross reinforcement plate 1 to the pier cross reinforcement plate installation line on the surface of the pier top panel 2, use the 100mm inspection line to check the position and installation accuracy of the pier cross reinforcement plate, use the right-angle ruler 3 to measure and control the verticality of the pier cross reinforcement plate, and then weld the pier cross reinforcement plate to the pier top panel; the verticality error of the pier cross reinforcement plate is less than 1mm, such as Figure 2 shown.
[0037] Step 5. Install the panels around the pier: The panels around the cross reinforcement plate of the pier are installed by symmetrical welding. Hoist one panel to the pier panel installation line on the surface of the pier top panel and use a 100mm inspection line to check the position and installation accuracy of the panel. After welding the panel to the pier cross reinforcement plate and the pier top panel, install the panel on the opposite side of the panel.
[0038] Due to the huge amount of welding between the module pier panel, the pier cross reinforcement plate and the enclosure, welding deformation is easy to occur, affecting the horizontality of the panel. Therefore, in addition to reducing the welding current, slowing down the welding speed, and reasonably using conventional methods such as back-welding and symmetrical welding to reduce welding deformation, the welding sequence should be arranged reasonably.
[0039] Step 6, pier measurement: After the surrounding panels 4 are installed, select 9 detection points, namely P1, P2, P3, P4, P5, P6, P7, P8, and P9. Among the 5 detection points, P5 is the center point of the pier cross reinforcement plate, and P2, P4, P6, and P8 are the 4 edge endpoints. The other 4 detection points P1, P3, P7, and P9 are the 4 corner connections surrounded by the four panels; Figure 3 shown.
[0040] Step 7: Marking of installation positions of each pier: According to the theoretical size of the deck sections and module piers, the installation position identification lines and inspection lines of the cross reinforcement plates and coamings corresponding to each pier are marked on the FPSO hull deck; Figure 4 As shown in the figure, the spacing of the six piers at the intersection of the a, b, c axes and the e, f axes is checked by the reverse marking of each pier on the deck surface, and the spacing of the center lines of the pier cross reinforcement plates at the six piers at the intersection of the a, b, c axes and the e, f axes is measured to ensure that the deviations of the center lines of the pier cross reinforcement plates at the six piers in the length and width directions meet the requirements.
[0041] Step 8, welding of each pier: hoist each pier onto the FPSO's hull deck, align the surrounding plates and the pier cross reinforcement plates with the installation position marking lines marked on the deck, and use a 100mm inspection line to check the position and installation accuracy of the coamings and pier cross reinforcement plates; weld each pier onto the FPSO's hull deck.
[0042] The deviation between the center line of the cross reinforcement plate on each pier and the installation position marking line of the cross reinforcement plate of each pier on the hull deck of the FPSO is ≤±4mm.
[0043] The deviation between the center line of the surrounding panels on each pier and the installation position marking line of the panels of each pier on the FPSO hull deck is ≤±6mm.
[0044] Step 9: Position accuracy test of each pier: After welding of each pier under an upper module is completed, measurement should be carried out, and the positions that do not meet the accuracy requirements should be trimmed, and then the horizontality and height data of each pier panel should be measured. Figure 5 As shown, a reference pole is erected on the hull deck of the FPSO. The reference pole is made of a square steel pipe. Four total station reference light targets are attached to the four sides of the square steel pipe. All total station reference light targets are calibrated to ensure that they are at the same horizontal height.
[0045] Working principle: The present invention seals the top panel of the pier through the tire frame. When the cross reinforcement plate and the enclosure plate are welded, the top panel of the pier has a very small deformation, thereby ensuring the horizontality of the top panel of the pier and the dimensional accuracy of the pier; the present invention adopts the method of simultaneous installation and detection, strictly implements the welding process and monitors the welding in real time. Once the deviation is found, it should be adjusted immediately, which greatly improves the dimensional accuracy and installation accuracy of the pier. The horizontality of the top panel of each pier is ≤3mm. The center height deviation of the top panel of each pier is ≤4mm. The deviation of each pier along the length and width of the ship is ≤±6mm.
[0046] In addition, those skilled in the art may combine and combine the different embodiments or examples and the features of the different embodiments or examples described in this specification without contradiction. Although the embodiments of the present invention have been shown and described above, it is understood that the above embodiments are exemplary and cannot be understood as limiting the present invention. Those skilled in the art may change, modify, replace and modify the above embodiments within the scope of the present invention.
Claims
1. A method for constructing and installing a FPSO upper module buttress, characterized in that: The following steps are involved: Step 1: Tire frame production: The produced tire frame is used for prefabrication of module piers; the horizontality of the upper surface of the tire frame is required to be no more than 1mm; Step 2, fix the top panel of the pier and mark the installation position of the components: after the size inspection of the top panel of the pier is qualified, hoist it onto the tire frame, adjust the horizontality of the top panel of the pier to make the top panel of the pier fit closely with the surface of the tire frame, align the center line of the top panel of the pier with the cross center ground line, and seal the top panel of the pier to the surface of the tire frame by using the pressure code and the tire sealing plate; Step 3: Marking of component installation positions: The components include the pier cross reinforcement plate and the surrounding plates around the pier. Mark the pier cross reinforcement plate installation line, pier surrounding plate installation line and 100mm inspection line on the surface of the pier top panel; Step 4, install the pier cross reinforcement plate: hoist the pier cross reinforcement plate to the pier cross reinforcement plate installation line on the surface of the pier top panel, use a 100mm inspection line to check the position installation accuracy of the pier cross reinforcement plate, use a right-angle ruler to measure and control the verticality of the pier cross reinforcement plate, and then weld the pier cross reinforcement plate to the pier top panel; Step 5, install the panels around the pier: The panels around the cross reinforcement plate of the pier are installed by symmetrical welding. One panel is hoisted to the pier panel installation line on the surface of the pier top panel and the position and installation accuracy of the panel is checked with a 100mm inspection line. After welding the panel to the cross reinforcement plate of the pier and the top panel of the pier, install the panel on the opposite side of the panel. Step 6, pier measurement: After the surrounding panels are installed, select 9 inspection points, of which 5 inspection points are the center point and 4 edge endpoints of the pier cross reinforcement plate, and the other 4 inspection points are the 4 corner connections surrounded by the four panels; Step 7: Marking of installation positions of each pier: According to the theoretical dimensions of the deck sections and module piers, the installation position identification lines and inspection lines of the cross reinforcement plates and coamings corresponding to each pier are marked on the FPSO hull deck; Step 8, welding of each pier: hoist each pier onto the FPSO's hull deck, align the surrounding plates and the pier cross reinforcement plates with the installation position marking lines marked on the deck, and use a 100mm inspection line to check the position and installation accuracy of the coamings and pier cross reinforcement plates; weld each pier onto the FPSO's hull deck; Step 9: Position accuracy inspection of each pier: After the welding of each pier under an upper module is completed, measurement should be carried out, and the positions that do not meet the accuracy requirements should be trimmed, and then the horizontality and height data of each pier panel should be measured.
2. The method for constructing and installing the FPSO upper module buttress according to claim 1, characterized in that: In step 4, the verticality error of the pier cross reinforcement plate is less than 1 mm.
3. The method for constructing and installing the FPSO upper module buttress according to claim 1, characterized in that: In step 9, a reference pole is erected on the FPSO's hull deck. The reference pole is made of a square steel pipe, and four total station reference light targets are attached to the four sides of the square steel pipe. All total station reference light targets are calibrated to ensure that they are at the same horizontal height.
4. The method for constructing and installing the FPSO upper module buttress according to claim 1, characterized in that: In step 8, the deviation between the center line of the pier cross reinforcement plate on each pier and the installation position marking line of the cross reinforcement plate of each pier on the hull deck of the FPSO is ≤±4mm.
5. The method for constructing and installing the FPSO upper module buttress according to claim 1, characterized in that: In step 8, the deviation between the center line of the surrounding panels on each pier and the marking line of the panel installation position of each pier on the hull deck of the FPSO is ≤±6mm.
6. The method for constructing and installing the FPSO upper module buttress according to claim 1, characterized in that: In step 9, the horizontality of the top panel of each pier is ≤3 mm.
7. The method for constructing and installing the FPSO upper module buttress according to claim 1, characterized in that: In step 9, the center height deviation of the pier top panel of each pier is ≤4mm.
8. The method for constructing and installing the FPSO upper module buttress according to claim 1, characterized in that: In step 9, the deviation of each pier along the length and width of the ship is ≤±6mm.
Citation Information
Patent Citations
Method for improving installation precision in construction process of large ship upper module buttress anchorages
CN108438142A
FPSO module and integrated installation process
CN110937075A
Method for optimizing module buttress structure by using total station
CN112131666A
FPSO (Floating Production Storage and Offloading) module support manufacturing and mounting precision control method
CN117360722A
Manufacturing and installing method of FPSO module buttress based on precise positioning and machining amount optimization
CN118205684A