Horizontal grouting construction structure and method for large-size bearing plate

By arranging hard plastic rubber strips, grouting holes and vents on the pressure-bearing plate, and using a grouting pressure-maintaining device, the problem that traditional grouting technology cannot achieve high density of large-sized pressure-bearing plates is solved, and efficient grouting density is achieved. degree and construction quality improved.

CN118727593APending Publication Date: 2024-10-01CCCC SHEC FOURTH ENG +3
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202410974645.9
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-07-19
Publication Date
2024-10-01

AI Technical Summary

Technical Problem

The traditional grouting process for connecting the pressure-bearing plate and the tower base cannot meet the needs of large-sized pressure-bearing plates, and the grouting density is insufficient to achieve a high-density grouting effect.

Method used

Use hard plastic rubber strips to separate the pressure-bearing plates, set grouting holes and exhaust holes, and use a grouting pressure maintaining device, including the first angle steel and the second angle steel to form a Z-shaped structure, combined with multiple grouting grooves and channel steel, to achieve step-by-step Maintain pressure during grouting to ensure grouting density.

Benefits of technology

Horizontal grouting of large-sized pressure-bearing plates has been achieved, and the grouting density has reached more than 95%, which reduces the use of construction machinery, lowers costs, and improves the grouting quality and the overall safety performance of the steel tower.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118727593A_ABST
    Figure CN118727593A_ABST
Patent Text Reader

Abstract

The invention discloses a large-size bearing plate horizontal grouting construction structure and method, a bearing plate is provided with hard plastic rubber strips, the hard plastic rubber strips divide the bearing plate to form subareas, the bearing plate is further provided with grouting holes and exhaust holes, grouting grooves are formed in the peripheries of the grouting holes, the side portion of the bearing plate is provided with a grouting pressure maintaining device, and the exhaust holes are communicated with the grouting grooves. By the adoption of the large-size bearing plate horizontal grouting construction structure and method, horizontal grouting of the large-size bearing plate is achieved, and the grouting compactness is high.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention belongs to the technical field of construction, and in particular relates to a large-size pressure plate horizontal grouting construction structure and method. Background Art

[0002] The grouting of the pressure plate is the key to the connection between the tower base and the steel tower. At present, the traditional connection between the pressure plate and the tower base adopts direct contact after grinding or high-position funnel grouting. However, there are limitations: the pressure plate is directly connected to the tower base after grinding, which has high requirements for the flatness of the tower base and the manufacturing requirements of the pressure plate, and is not applicable to large-area pressure plates and large bridges; the traditional high-position funnel grouting method sets a large grouting hole, the contact area between the pressure plate and the tower base is small, the construction process is relatively simple, and it cannot meet the grouting needs of large-size pressure plates.

[0003] The utility model patent with announcement number CN212336008U was disclosed on January 12, 2021. The name is a new type of prefabricated pressure plate. The new type of prefabricated pressure plate consists of a bottom pressure plate, a pair of triangular side plates, a rectangular side plate and a cover plate. The pair of triangular side plates are fixed to the front and rear sides of the bottom pressure plate, the rectangular side plate is fixed to the right side of the bottom pressure plate and is fixedly connected with the pair of triangular side plates to form a wedge-shaped structure, the cover plate is fixed to the top of the wedge-shaped structure and the left end of the cover plate is fixed to the bottom pressure plate; an anchor cable pulling hole is opened at the center of the cover plate, a grouting hole is opened to the upper right of the anchor cable pulling hole and a grouting pipe is fixed on the grouting hole, and an anchor cable through hole is opened at the center of the bottom pressure plate. The new type of prefabricated pressure plate cannot realize horizontal grouting of large-sized pressure plates and cannot improve the grouting density. Summary of the invention

[0004] The purpose of the present invention is to address the deficiencies in the prior art and to provide a large-size pressure plate horizontal grouting construction structure and method for achieving large-size pressure plate horizontal grouting with high grouting density.

[0005] In order to achieve the above object, the technical solution adopted by the present invention is:

[0006] The large-size pressure plate horizontal grouting construction structure has a hard plastic rubber strip on the pressure plate, which divides the pressure plate into partitions. The pressure plate is also provided with grouting holes and exhaust holes. Grouting grooves are arranged around the grouting holes. A grouting pressure maintaining device is provided on the side of the pressure plate.

[0007] The grouting pressure maintaining device includes a first angle steel, which is fixedly connected to the side of the short side of the pressure plate. A second angle steel is arranged in the tower base, and the first angle steel is fixedly connected to the end of the second angle steel. A channel steel is arranged on one side of the long side of the pressure plate.

[0008] The first angle steel and the second angle steel are in contact with each other to form a Z-shaped structure, and fillet welds are provided at both ends of the first angle steel.

[0009] The grouting groove is formed by welding steel plates, and the grouting hole is located in the middle of the lower part of the grouting groove.

[0010] The exhaust holes are evenly distributed on the pressure plate.

[0011] The partitions are provided with 12 blocks, and each partition is provided with three grouting holes.

[0012] The pressure plate is provided with anchor holes evenly distributed around the steel tower.

[0013] The large-size bearing plate horizontal grouting construction method comprises the following steps:

[0014] Step 1: Partition the pressure plate;

[0015] Step 2: Arrange grouting holes and exhaust holes;

[0016] Step 3: roughening the tower base;

[0017] Step 4: Grouting trough construction;

[0018] Step 5: Lower the first section of the steel tower;

[0019] Step 6: Setting a grouting pressure-maintaining device;

[0020] Step 7: Grouting construction.

[0021] The step 7 comprises the following steps: plugging the first grouting hole of each partition with a wooden plug or a steel plate, opening the outlet valve of the grouting barrel, and removing the wooden plug or the steel plate after the slurry flows into the grouting groove and the liquid level rises by 20 cm; observing the position of the slurry flow through the exhaust hole, and when the slurry reaches the adjacent grouting holes, using the plug removal method to complete the grouting of the second and third grouting grooves in sequence, so that the three grouting holes are grouted at the same time; when the slurry flows out of the long side of the pressure plate, the three grouting holes continue to be grouted to maintain pressure; when the slurry on the long side of the pressure plate overflows from the channel steel, the grouting operation is completed.

[0022] The step 6 comprises the following steps: angle steel is arranged on the short side of the pressure plate and is close to the pressure plate, and channel steel is arranged 20 cm outside the long side of the pressure plate.

[0023] The technical effect of the present invention is as follows: the large-size pressure plate horizontal grouting construction structure and method of the present invention can realize the horizontal grouting of large-size pressure plates, overcoming the shortcoming that the traditional grouting process cannot realize the high density requirements of large-size pressure plates. The setting of the grouting pressure-maintaining device ensures the sufficiency of grouting, reduces the use of other machinery for grouting construction, saves costs, reduces construction costs, and combines multiple grouting holes and exhaust holes, adopts the construction steps of grouting in sequence, and performs pressure-maintaining grouting in steps. The grouting density of the pressure plate reaches more than 95%, so that the pressure plate of the steel tower is in full contact with the base, ensuring the quality of grouting construction and improving the overall safety performance of the steel tower. BRIEF DESCRIPTION OF THE DRAWINGS

[0024] This specification includes the following drawings, which show the following contents:

[0025] Figure 1 It is a layout diagram of grouting holes and vent holes on the pressure plate of the present invention;

[0026] Figure 2 It is a schematic diagram of the partitioning of the pressure plate of the present invention;

[0027] Figure 3 yes Figure 1 A partial enlarged view of

[0028] Figure 4 is a schematic diagram of the connection of the first angle steel of the present invention;

[0029] Figure 5 yes Figure 4 Structural view in the Ⅰ-Ⅰ direction;

[0030] Figure 6 yes Figure 4 Structural view in the II-II direction. DETAILED DESCRIPTION

[0031] The specific implementation methods of the present invention are further explained in detail below by describing the embodiments with reference to the accompanying drawings, with the aim of helping those skilled in the art to have a more complete, accurate and in-depth understanding of the inventive concept and technical solution of the present invention and facilitating their implementation.

[0032] like Figures 1 to 6 As shown, the large-size pressure plate horizontal grouting construction structure has a hard plastic rubber strip on the pressure plate, which separates the pressure plate into partitions. The pressure plate is also provided with grouting holes and exhaust holes, and grouting grooves are arranged around the grouting holes. A grouting pressure maintaining device is provided on the side of the pressure plate.

[0033] According to the size and structure of the pressure plate, the pressure plate is divided into 12 areas of roughly the same shape and area. The areas are separated by hard plastic rubber strips. When grouting, operations can be carried out simultaneously on each area, which can meet the grouting needs of large-sized pressure plates, ensure sufficient grouting of large-sized grouting areas, and improve grouting efficiency; the pressure plate is grouted in different areas, and steel plates of the same size are made in each area. Grouting tests are carried out on the steel plates to determine the grouting material material, water-cement ratio and curing grouting process; by setting up a grouting pressure maintaining device, the grouting density and grouting construction quality can be effectively improved, while the use of other mechanical equipment in grouting construction can be reduced, thereby reducing construction costs.

[0034] like Figure 4 As shown, the grouting pressure-maintaining device includes a first angle steel, which is fixedly connected to the side of the short side of the pressure plate, a second angle steel is arranged in the tower base, and the second angle steel, the first angle steel and the second angle steel end are fixedly connected, and a channel steel is arranged on one side of the long side of the pressure plate. A pair of angle steels are arranged on the short side of the pressure plate to form a closed barrier to ensure that there is no leakage of slurry. At the same time, a channel steel is arranged at the long side of the pressure plate. The channel steel uses a 30-type channel steel. Since the slurry will reach the long side of the pressure plate one step later after flowing, the channel steel is arranged 20 cm outside the long side of the pressure plate. By judging whether there is slurry overflowing from the channel steel, it can be judged whether the grouting is sufficient, so as to achieve the function of grouting pressure maintenance and improve the density of the grouting.

[0035] like Figure 4 As shown, the first angle steel and the second angle steel contact to form a Z-shaped structure, and fillet welds are provided at both ends of the first angle steel. A pair of angle steels are fixed to form a Z-shape, which makes full use of the contact area of ​​the angle steels and improves stability. The fillet weld at the upper end of the first angle steel is used to fix it to the short side of the pressure plate, and the fillet weld at the lower end of the first angle steel is used to fix it to the second angle steel. The first angle steel uses two fillet welds to reinforce the short side of the pressure plate. When the slurry enters the bottom of the pressure plate from the grouting hole, the first angle steel forms a blocking effect on the slurry. The slurry will not overflow from the short side of the pressure plate after flowing. The slurry will gradually accumulate to make the pressure plate fully contact with the platform, and the density of the slurry will be improved, thereby improving the construction quality.

[0036] The grouting groove is constructed by welding steel plates, and the grouting hole is located in the middle of the lower part of the grouting groove. Above the grouting hole of the pressure plate, a 50cm×50cm rectangular groove is welded with steel plates to keep the grouting process at the same speed, prevent the grouting speed from being too fast, resulting in the failure to discharge the gas in time, or the grouting speed from being too slow, resulting in the entry of air, ensuring the reliability of the construction process, reducing defects such as bubbles and honeycomb surfaces, and thus improving the quality of grouting construction.

[0037] like Figure 1 As shown in FIG. 1 , the exhaust holes are evenly distributed on the pressure plate. The evenly distributed exhaust holes can fully discharge the gas inside the pressure plate during grouting, thereby improving the density of the grouting.

[0038] like Figure 2 As shown, there are 12 partitions, and each partition is provided with three grouting holes. The three grouting holes correspond to the three outlets of the grouting bucket, so as to realize the distributed pressure-maintaining grouting construction. Multiple grouting holes and exhaust holes are set, and the pressure-maintaining grouting is carried out in steps. The grouting density of the pressure plate can reach more than 95%, so that the pressure plate of the steel tower is in full contact with the cap, which ensures the quality of the grouting construction and improves the overall safety performance of the steel tower.

[0039] like Figure 1 As shown, the pressure plate is evenly distributed with anchor holes around the steel tower. Anchor holes are installed around the steel tower to reinforce the concrete structure of the steel tower and the pressure plate through the longitudinal tension of the anchor rod body.

[0040] The large-size bearing plate horizontal grouting construction method comprises the following steps:

[0041] Step 1: Partition the pressure plate;

[0042] Step 2: Arrange grouting holes and exhaust holes;

[0043] Step 3: roughening the tower base;

[0044] Step 4: Grouting trough construction;

[0045] Step 5: Lower the first section of the steel tower;

[0046] Step 6: Setting a grouting pressure-maintaining device;

[0047] Step 7: Grouting construction.

[0048] Step 7 includes the following steps: plug the first grouting hole of each partition with a wooden plug or a steel plate, open the outlet valve of the grouting barrel, and remove the wooden plug or the steel plate after the slurry flows into the grouting groove and the liquid level rises by 20 cm; observe the position of the slurry flow through the exhaust hole, and when the slurry reaches the adjacent grouting holes, use the plug-pulling method to complete the grouting of the second and third grouting grooves in turn, so that the three grouting holes are grouted at the same time; when the slurry flows out of the long side of the pressure plate, the three grouting holes continue to be grouted to maintain pressure; when the slurry on the long side of the pressure plate overflows from the channel steel, the grouting operation is completed.

[0049] Step 6 includes the following steps: setting angle steel on the short side of the pressure plate and keeping it close to the pressure plate, and setting channel steel 20 cm outward on the long side of the pressure plate.

[0050] The specific construction process of the large-size bearing plate horizontal grouting construction method is as follows:

[0051] Grouting process test: Grout the pressure plate in different areas, make steel plates of the same size in different areas, conduct grouting tests on the steel plates, and determine the grouting material, water-cement ratio, and curing grouting process;

[0052] Pressure plate partitioning: According to the size and structure of the pressure plate, the pressure plate is divided into 12 areas of roughly the same shape and area. Adjacent areas are isolated by hard plastic rubber strips;

[0053] Arrangement of grouting holes and vent holes: Carry out grouting process tests according to the partitions of the pressure plate, and determine the size and position of grouting holes and vent holes in each grouting partition based on multiple test results;

[0054] Grouting groove construction: above the grouting hole of the pressure plate, a 50cm×50cm rectangular groove is welded with steel plates;

[0055] Roughening of the tower base: After the tower base concrete reaches the required strength, the grouting area will be roughened, and hard plastic rubber strips will be set and fixed at the partitioned positions;

[0056] Lowering the first section of the steel tower: Place the first section of the steel tower on the hard plastic rubber strip and use jacks and pads to adjust its position and elevation to the designed position;

[0057] Grouting pressure-maintaining device setting: Angle steel is set on the short side of the pressure plate and is close to the pressure plate to ensure that there is no leakage of grout. A groove 30 steel is set 20 cm outside the long side of the pressure plate for grouting pressure maintenance;

[0058] Preparation for grouting construction: Mix the grouting material according to the water-cement ratio and store the mixed grouting material in a grouting bucket. The grouting bucket is provided with three outlets corresponding to the three grouting holes of the pressure plate. The outlet of the grouting bucket is connected to the grouting hole of the pressure plate through a steel wire hose, that is, one end of the steel wire hose is tightly connected to the outlet of the grouting bucket, and the other end is placed in the grouting tank. A PVC pipe is set on the exhaust hole for extension. After the grouting material in the grouting bucket is left to stand for two minutes, the grouting construction can begin;

[0059] like Figure 3 As shown, the grouting construction process is as follows: plug the grouting hole 1 with a wooden plug or a steel plate, open the valve of the grouting bucket outlet 1, and the slurry flows into the grouting tank 1 through the steel wire hose. After the slurry level rises by 20 cm, pull out the wooden plug or steel plate to make the slurry pour into the pressure plate at the same speed.

[0060] Observe the position of slurry flow through the exhaust hole. When the slurry reaches grouting hole 2, that is, grouting hole 2 has slurry overflowing, open the valve at the outlet of the grouting bucket, and the slurry flows into the grouting groove 2 through the steel hose. The same plug-pulling method is used for grouting. At this time, grouting holes 1 and 2 are grouted at the same time; when the slurry reaches grouting hole 3, that is, grouting hole 3 has slurry overflowing, open the valve at the outlet of the grouting bucket, and the slurry flows into the grouting groove 3 through the steel hose. The same plug-pulling method is used for grouting. At this time, grouting holes 1, 2, and 3 are grouted at the same time; when the slurry flows out of the long side of the pressure plate, the grouting holes 1, 2, and 3 continue to be grouted to maintain pressure. When the slurry at the long side of the pressure plate overflows from the groove 30 steel, the grouting operation can be terminated and completed.

[0061] The large-size pressure plate horizontal grouting construction structure and method can realize the horizontal grouting of large-size pressure plates, overcoming the shortcoming that the traditional grouting process cannot realize the high density requirements of large-size pressure plates. The setting of the grouting pressure-maintaining device ensures the sufficiency of grouting, reduces the use of other machinery for grouting construction, saves costs, reduces construction costs, and combines multiple grouting holes and exhaust holes, adopts the construction steps of grouting in sequence, and performs pressure-maintaining grouting in steps. The grouting density of the pressure plate reaches more than 95%, so that the pressure plate of the steel tower is in full contact with the foundation, ensuring the quality of grouting construction and improving the overall safety performance of the steel tower.

[0062] The present invention is described above by way of example in conjunction with the accompanying drawings. Obviously, the specific implementation of the present invention is not limited to the above-mentioned methods. As long as various non-substantial improvements are made using the method concept and technical solution of the present invention; or the above concept and technical solution of the present invention are directly applied to other occasions without improvement, they are all within the protection scope of the present invention.

Claims

1. A large-size bearing plate horizontal grouting construction structure, characterized in that: The pressure plate is provided with a hard plastic rubber strip, which divides the pressure plate into partitions. The pressure plate is also provided with grouting holes and exhaust holes. Grouting grooves are arranged around the grouting holes. A grouting pressure maintaining device is arranged on the side of the pressure plate.

2. The large-size bearing plate horizontal grouting construction structure according to claim 1 is characterized in that: The grouting pressure maintaining device includes a first angle steel, which is fixedly connected to the side of the short side of the pressure plate. A second angle steel is arranged in the tower base, and the first angle steel is fixedly connected to the end of the second angle steel. A channel steel is arranged on one side of the long side of the pressure plate.

3. The large-size bearing plate horizontal grouting construction structure according to claim 2 is characterized in that: The first angle steel and the second angle steel are in contact with each other to form a Z-shaped structure, and fillet welds are provided at both ends of the first angle steel.

4. The horizontal grouting construction method for large-size pressure-bearing plates according to claim 2 is characterized in that: The grouting groove is formed by welding steel plates, and the grouting hole is located in the middle of the lower part of the grouting groove.

5. The large-size bearing plate horizontal grouting construction method according to claim 4 is characterized in that: The exhaust holes are evenly distributed on the pressure plate.

6. The large-size bearing plate horizontal grouting construction method according to claim 5 is characterized in that: The partitions are provided with 12 blocks, and each partition is provided with three grouting holes.

7. The large-size bearing plate horizontal grouting structure according to claim 6 is characterized in that: The pressure plate is provided with anchor holes evenly distributed around the steel tower.

8. A large-size bearing plate horizontal grouting construction method, characterized in that: The following steps are involved: Step 1: Partition the pressure plate; Step 2: Arrange grouting holes and exhaust holes; Step 3: roughening the tower base; Step 4: Grouting trough construction; Step 5: Lower the first section of the steel tower; Step 6: Setting a grouting pressure-maintaining device; Step 7: Grouting construction.

9. The large-size bearing plate horizontal grouting construction method according to claim 8 is characterized in that: The step 7 comprises the following steps: Use a wooden plug or steel plate to plug the first grouting hole in each partition, open the outlet valve of the grouting bucket, and remove the wooden plug or steel plate after the slurry flows into the grouting tank and the liquid level rises by 20 cm; The position where the slurry flows is observed through the vent hole. When the slurry reaches the adjacent grouting hole, the plug-pulling method is used to complete the grouting of the second and third grouting grooves in sequence, so that the three grouting holes are grouted at the same time. When the grout flows out of the long side of the pressure plate, the three grouting holes continue to be grouted to maintain the pressure; When the slurry on the long side of the pressure plate overflows from the channel steel, the grouting operation is completed.

10. The large-size bearing plate horizontal grouting construction method according to claim 8, characterized in that: The step 6 comprises the following steps: angle steel is arranged on the short side of the pressure plate and is close to the pressure plate, and channel steel is arranged 20 cm outside the long side of the pressure plate.