Construction method of cast-in-place multi-step independent foundation formwork reinforcing device
By using a multi-stage construction method in the independent foundation formwork reinforcement device, combined with the cooperation of square timber and diagonal brace units, the problems of poor support effect and low material efficiency are solved, and efficient concrete forming and reinforcement effects are achieved.
Patent Information
- Application Number
- CN202411159206.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-22
- Publication Date
- 2024-10-01
AI Technical Summary
The existing independent foundation formwork reinforcement device has poor support effect, resulting in poor concrete formation and low material usage efficiency, which easily leads to waste of time and cost in rework.
The construction method of the multi-stage independent foundation formwork reinforcement device is adopted. Square timbers are set outside the independent foundation formwork on the bottom and top floors, and connectors and diagonal brace units are installed. The main diagonal brace unit and the secondary diagonal brace unit cooperate with each other to adjust the support angle. and length to enhance the integrity and stability of the support structure.
It improves the concrete forming quality, enhances the reinforcement effect, reduces construction costs, reduces rework, and improves construction efficiency and material turnover rate.
Smart Images

Figure CN118727751A_ABST
Abstract
Description
Technical Field
[0001] The invention belongs to the technical field of template reinforcement, and specifically relates to a construction method for a cast-in-place multi-stage independent foundation template reinforcement device. Background Art
[0002] At present, most independent foundation formwork reinforcements are reinforced with square timber or steel pipes, and diagonal braces are also reinforced with square timber and steel pipes. Because when the independent foundation concrete is poured, the force structure is simple, and the formwork is mainly subjected to the impact force and horizontal force of the concrete. Only diagonal braces need to be added on the outside, but more square timber, formwork, steel pipes and other materials will be used. The reinforcement method is also one-time reinforcement with screws, which can easily damage the formwork and square timber, reduce the turnover rate of materials, and the strength and rigidity of the reinforced materials are not high, which can easily lead to poor stability of the formwork support, as well as problems such as concrete leakage and displacement of the finished concrete product, and waste time and cost in the later rework.
[0003] For example, a Chinese invention patent with application publication number CN108301415A discloses an integral reinforcement structure for a formwork for casting a stepped independent foundation. The integral reinforcement structure includes a plurality of reinforcement units stacked according to the structure of the stepped independent foundation and a car rod that fixes the reinforcement units into a whole. The reinforcement unit is retractable along the axial direction, one end of which is detachably fixed to the formwork, and the other end is fixed to the foundation or the wall of the foundation pit. A plurality of car rods are provided between the upper reinforcement units and the lower reinforcement units. The car rods are placed on the upper formwork, and the upper formwork is fixed on the car rods so that the bottom surface of the upper formwork and the upper surface of the lower formwork are on the same horizontal plane.
[0004] In the above-mentioned prior art, the independent foundation formwork is reinforced, but the wedge-shaped pad is bolted to the side wall of the foundation pit, and the soil of the side wall of the foundation pit is loose and easily slides, resulting in poor support effect of the support device and poor concrete forming.
[0005] Therefore, how to effectively solve the poor supporting effect of the supporting device and poor concrete forming is a technical problem that needs to be solved urgently. Summary of the invention
[0006] In view of the deficiencies in the above-mentioned background technology, the present invention proposes a construction method for a cast-in-place multi-stage independent foundation formwork reinforcement device, which solves the problems of poor supporting effect of the supporting device and poor concrete forming.
[0007] The technical solution of this application is: A construction method for a cast-in-place multi-stage independent foundation formwork reinforcement device comprises the following construction steps: S1: foundation pit excavation, cushion layer pouring construction and maintenance; S2: Support the bottom independent foundation formwork and set square timber outside the bottom independent foundation formwork; S3: erect supporting cross bars, support the top independent foundation formwork, and set square timber outside the top independent foundation formwork; S4: several connectors are installed along the circumference of the bottom independent foundation template and the top independent foundation template; S5: One end of the main diagonal bracing unit is hinged to the connecting piece connected to the top independent foundation formwork, and the other end of the main diagonal bracing unit is inserted into the foundation pit; S6: hinge one end of the secondary bracing unit to a connector connected to the bottom independent foundation formwork, and insert the other end of the secondary bracing unit into the main bracing unit; S7: Repeat steps S5-S6 to install the main diagonal bracing unit and the secondary diagonal bracing unit on a plurality of connecting members; or S1: foundation pit excavation, cushion layer pouring construction and maintenance; S2: Support the bottom independent foundation formwork and set square timber outside the bottom independent foundation formwork; S3: erect supporting cross bars, support the middle layer independent foundation formwork, and set square timber outside the middle layer independent foundation formwork; S4: erect supporting cross bars, set up the top independent foundation formwork, and set up square timber outside the top independent foundation formwork; S5: a plurality of connectors are installed along the circumference of the bottom layer independent foundation template, the middle layer independent foundation template, and the top layer independent foundation template; S6: One end of the main diagonal bracing unit is hinged to the connecting piece connected to the top independent foundation formwork, and the other end of the main diagonal bracing unit is inserted into the foundation pit; S7: hinge one end of the secondary bracing unit to the connecting pieces of the middle layer independent foundation formwork and the bottom layer independent foundation formwork respectively, and insert the other ends of the secondary bracing units into the main bracing unit; S8: Repeat steps S6-S7 to install the main diagonal bracing unit and the secondary diagonal bracing unit on a plurality of connecting members.
[0008] Furthermore, the connecting member includes a vertical plate provided with a plurality of holes 1, the top of the vertical plate is provided with a hook hung on the upper surface of the top layer independent foundation formwork or the middle layer independent foundation formwork or the bottom layer independent foundation formwork, the vertical plate is adjustably connected with a U-shaped plate, bolt 1 passes through hole 2 on the bottom plate of the U-shaped plate, hole 1 and is threadedly matched with nut 1 in sequence, and the main diagonal bracing unit is hinged to the U-shaped plate.
[0009] Furthermore, the main diagonal bracing unit comprises an internally threaded support rod and an externally threaded support rod that are threadedly matched, a sleeve 1 is provided on the top of the externally threaded support rod, and the sleeve 1 is hinged to the U-shaped plate.
[0010] Furthermore, the outer wall of the internally threaded support rod is pressed on the top of the vertical plate.
[0011] Furthermore, a strip hole is provided on the internal thread support rod, and one end of the secondary diagonal support unit passes through the strip hole and is positioned by a fixing piece.
[0012] Furthermore, the secondary diagonal bracing unit includes a screw rod 2 with a sleeve 2 at one end, the sleeve 2 is hinged to the U-shaped plate, the other end of the screw rod 2 passes through the strip hole, and the fixing part includes a double nut 2 that cooperates with the thread of the screw rod 2, and the inner surface of the double nut 2 is pressed on the internal thread support rod.
[0013] Furthermore, the bottom of the internally threaded support rod is provided with a pointed portion for inserting into the foundation pit.
[0014] Furthermore, a baffle plate spaced apart from the tip is provided on the internally threaded support rod, and the baffle plate cooperates with the foundation pit stopper.
[0015] Furthermore, a plurality of wooden blocks are arranged between the vertical board and the top layer independent foundation formwork, or between the vertical board and the other layer formworks, or between the vertical board and the middle layer independent foundation formworks.
[0016] Furthermore, the vertical plate is connected to the top layer independent foundation formwork or the other layer formwork or the middle layer independent foundation formwork through a bolt group.
[0017] The specific beneficial effects of the present invention include: 1. The main diagonal bracing unit can adjust the support angle according to the independent foundation structure of different sizes. It is practical. The internal thread support rod has high strength and rigidity, good reinforcement effect, and better concrete forming quality, which greatly improves the economic benefits of construction. At the same time, the length of the main diagonal bracing unit is adjustable and has a wide range of applications. 2. The main diagonal bracing units and the secondary diagonal bracing units cooperate with each other and complement each other, thus strengthening the integrity of the supporting structure and the connection between the components; 3. The side wall of the main diagonal bracing unit is pressed on the middle layer independent foundation formwork and / or the bottom layer independent foundation formwork, so that the middle layer independent foundation formwork and / or the bottom layer independent foundation formwork give support force to the main diagonal bracing unit, thereby enhancing stability and strengthening the reinforcement effect of the main diagonal bracing unit; 4. Easy to install and disassemble, can be used in a cyclical manner, and is convenient for storage and transportation; 5. It solves the difficulties and shortcomings of current conventional construction operations, which can not only meet the requirements of independent foundation formwork reinforcement, but also avoid the rework such as chiseling and repairing in the later stage of conventional construction, thereby improving construction efficiency and ensuring the construction quality of concrete. BRIEF DESCRIPTION OF THE DRAWINGS
[0018] In order to more clearly illustrate the embodiments of the present invention, the accompanying drawings required for use in the description of the embodiments will be briefly introduced below. Obviously, the accompanying drawings in the following description are only some embodiments of the present invention. For ordinary technicians in this field, other accompanying drawings can be obtained based on these accompanying drawings without paying any creative work.
[0019] Figure 1 This is a schematic diagram of the use status of Example 1 of the present invention; Figure 2 is a schematic diagram of embodiment 1 of the present invention; Figure 3 is a schematic diagram of embodiment 1 of the present invention; Figure 4 is a schematic diagram of a connecting member in the present invention; Figure 5 for Figure 2 Enlarged view of point A in the middle; Figure 6 for Figure 5 Enlarged view of point B in the middle; Figure 7 It is a schematic diagram of the assembly relationship among the connecting member, the main diagonal bracing unit and the secondary diagonal bracing unit in Example 2 of the present invention.
[0020] Description of Figure Numbers: 0. Intermediate layer independent foundation formwork; 1. Foundation pit; 2. Top layer independent foundation formwork; 3. Bottom independent foundation template; 4. Connectors; 5. Main diagonal bracing unit; 6. Secondary diagonal bracing unit; 11. Wooden square; 12. Bolt group; 41. vertical plate; 42. hook; 43. U-shaped plate; 44. bolt 1; 50. Internal thread support rod; 51. Sleeve 1; 52. Screw 1; 53. Nut 2; 54, tip; 55, baffle; 500, external thread support rod; 501, strip hole; 61. Sleeve 2; 62. Screw 2; 63. Screw three; 64. Nut three; 65. Double nut two. DETAILED DESCRIPTION
[0021] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0022] Example 1, a construction method for a cast-in-place multi-step independent foundation template reinforcement device, this embodiment is applicable to a double-step foundation, such as Figure 1 , Figure 2 As shown, the construction steps include the following: S1: Excavation of foundation pit 1, construction and maintenance of cushion layer; excavation of independent foundation pit is carried out according to the design drawings, and the excavation is expanded outward according to the corresponding design boundary line to reserve the corresponding working surface for independent foundation formwork and concrete pouring construction. After the foundation pit is excavated to the base elevation, the cushion layer is poured. After the pouring is completed, the cushion layer is poured and maintained in time; S2: Support the bottom independent foundation formwork 3, and set square wood 11 on the outside of the bottom independent foundation formwork 3; according to the independent foundation design size, lay out the bottom independent foundation formwork 3 on the cushion surface, and use square wood 11 to reinforce the outer side of the bottom independent foundation formwork 3 to enhance the formwork strength; S3: erect the support crossbar 7, support the top independent foundation formwork 2, and set the square wood 11 on the outside of the top independent foundation formwork 2; the support crossbar 7 is placed on the bottom independent foundation formwork 3, and the top independent foundation formwork 2 is pressed on the support crossbar 7. The support crossbar 7 is made of steel pipe. The formwork and the wood 11 are both light in weight. The steel pipe is set along the two sides of the formwork to play a supporting role; S4: Install a plurality of connectors 4 along the circumference of the bottom independent foundation template 3 and the top independent foundation template 2, and align the connectors 4 of the bottom independent foundation template 3 and the top independent foundation template 2 on each side so that they are located in the same straight line; S5: One end of the main diagonal bracing unit 5 is hinged to the connecting piece 4 connected to the top independent foundation formwork 2, and the other end of the main diagonal bracing unit 5 is inserted into the foundation pit 1; S6: hinge one end of the secondary bracing unit 6 to the connecting piece 4 connected to the bottom independent foundation formwork 3, and insert the other end of the secondary bracing unit 6 into the main bracing unit 5; S7: Repeat steps S5-S6, install the main diagonal bracing unit 5 and the secondary diagonal bracing unit 6 on several connecting members 4, and then recheck the reinforcement of the entire device, and adjust any loose parts in time.
[0023] Based on the above implementation, Figure 4 As shown, the connecting member 4 includes a vertical plate 41 provided with a plurality of holes 1, and the top of the vertical plate 41 is provided with a hook 42 hung on the upper surface of the top independent foundation formwork 2 or the bottom independent foundation formwork 3, and a U-shaped plate 43 is adjustably connected to the vertical plate 41, and a bolt 1 44 passes through the hole 2 on the bottom plate of the U-shaped plate 43 and the hole 1 in sequence and is threadedly matched with a nut 1, and the main diagonal bracing unit 5 is hinged to the U-shaped plate 43.
[0024] Specifically, eight connecting parts 4 are provided on the top independent foundation formwork 2 and the bottom independent foundation formwork 3. The top independent foundation formwork 2 and the bottom independent foundation formwork 3 are both rectangular, and two connecting parts 4 are provided on each side. The U-shaped plate 43 can be connected with different holes according to position requirements to reach the optimal supporting position, thereby strengthening the reinforcement and stability of the independent foundation.
[0025] Specifically, the U-shaped plate 43 is usually installed in the middle of the vertical plate 41. Since the excavation of the foundation pit edge may not be accurate, it may be adjusted according to the actual situation. Ideally, it only needs to be installed in the middle and the screws are tightened.
[0026] On the basis of the above-mentioned implementation mode, the main diagonal bracing unit 5 includes an internally threaded support rod 50 and an externally threaded support rod 500 that are threadedly matched. A sleeve 51 is provided on the top of the externally threaded support rod 500 , and the sleeve 51 is hinged to the U-shaped plate 43 .
[0027] Specifically, the sleeve 51 is arranged horizontally, and the side plates of the U-shaped plate 43 are each provided with a hole 3, the screw 52 passes through the hole 3, the sleeve 51 and is threadedly engaged with the nut 2 53, and the sleeve 51 takes the screw 52 as the rotation axis and can adjust the angle around the screw 52.
[0028] Based on the above implementation, the outer wall of the internal threaded support rod 50 is pressed on the top of the vertical plate 41, and the vertical plate 41 provides support force to the internal threaded support rod 50, which can enhance the stability of the main diagonal bracing unit and strengthen the reinforcement effect of the main diagonal bracing unit.
[0029] Based on the above implementation, Figure 5 As shown, a strip hole 501 is provided on the internal thread support rod 50, and one end of the secondary diagonal support unit 6 passes through the strip hole 501 and is positioned by a fixing member.
[0030] Based on the above implementation, Figure 6 As shown, the secondary bracing unit 6 includes a screw rod 62 with a sleeve 61 at one end, the sleeve 61 is hinged to the U-shaped plate 43, the other end of the screw rod 62 passes through the strip hole 501, and the fixing member includes a double nut 65 threadedly matched with the screw rod 62. Figure 7 As shown, the inner surface of the double nut 2 65 is pressed onto the internal thread support rod 50 .
[0031] On the basis of the above embodiment, the bottom of the internal thread support rod 50 is provided with a tip 54 for inserting into the foundation pit 1 .
[0032] On the basis of the above embodiment, a baffle 55 spaced apart from the tip 54 is provided on the internal thread support rod 50, and the baffle 55 cooperates with the foundation pit 1 to stop the baffle 55 so that the baffle 55 is stuck on the outer surface of the foundation pit 1 to enhance stability.
[0033] On the basis of the above-mentioned implementation mode, a plurality of wooden squares 11 are arranged between the vertical board 41 and the top independent foundation formwork 2 or between the vertical board 41 and the bottom independent foundation formwork 3 .
[0034] Preferably, the hook 42 on the top of the vertical board 41 is hung on the top independent foundation formwork 2 or the bottom independent foundation formwork 3, and a certain gap is formed between the top and the bottom of the vertical board 41 and the side wall of the formwork. Wooden squares 11 are inserted between the top of the vertical board 41 and the formwork, and between the bottom and the formwork to enhance the strength of the formwork.
[0035] Based on the above implementation, the vertical plate 41 is connected to the top independent foundation formwork 2 or the bottom independent foundation formwork 3 through a bolt group 12. The bolt group 12 passes through the wooden square 11 and the formwork in turn to fix it to prevent displacement between the connecting member 4 and the formwork.
[0036] Example 2, as a preferred implementation method of the construction method of the cast-in-place multi-stage independent foundation formwork reinforcement device, is different from Example 1 in that this embodiment is applicable to a three-stage foundation, such as Figure 3 As shown, the construction steps include the following: S1: Excavation of foundation pit 1, construction and maintenance of cushion layer; S2: Support the bottom independent foundation formwork 3, and set square wood 11 outside the bottom independent foundation formwork 3; S3: erecting the supporting crossbar 7, supporting the middle layer independent foundation formwork 0, and setting the square wood 11 outside the middle layer independent foundation formwork 0; S4: erecting the supporting crossbar 7, supporting the top independent foundation formwork 2, and setting the square wood 11 outside the top independent foundation formwork 2; S5: Install a plurality of connectors 4 along the circumference of the bottom independent foundation template 3, the middle independent foundation template 0, and the top independent foundation template 2; S6: One end of the main diagonal bracing unit 5 is hinged to the connecting piece 4 connected to the top independent foundation formwork 2, and the other end of the main diagonal bracing unit 5 is inserted into the foundation pit 1. S7: hinge one end of the secondary bracing unit 6 to the connecting pieces 4 of the middle layer independent foundation formwork 0 and the bottom layer independent foundation formwork 3, and insert the other end of the secondary bracing unit 6 into the main bracing unit 5; S8: Repeat steps S6-S7 to install the main diagonal bracing units 5 and the secondary diagonal bracing units 6 on a plurality of connecting members 4.
[0037] On the basis of the above embodiment, the connecting member 4 includes a vertical plate 41 provided with a plurality of holes 1, and the top of the vertical plate 41 is provided with a hook 42 hung on the upper surface of the top independent foundation formwork 2 or the bottom independent foundation formwork 3 or the middle independent foundation formwork 0, and a U-shaped plate 43 is adjustably connected to the vertical plate 41, and a bolt 1 44 passes through hole 2 on the bottom plate of the U-shaped plate 43 and hole 1 in sequence and cooperates with a nut 1 thread, and the main diagonal bracing unit 5 is hinged to the U-shaped plate 43.
[0038] Specifically, eight connecting parts 4 are provided on the top layer independent foundation template 2, the bottom layer independent foundation template 3, and the middle layer independent foundation template 0. The top layer independent foundation template 2, the bottom layer independent foundation template 3, and the middle layer independent foundation template 0 are all rectangular, and two connecting parts 4 are provided on each side. The U-shaped plate 43 can be connected to different holes according to position requirements to reach the optimal supporting position, thereby strengthening the reinforcement and stability of the independent foundation.
[0039] Specifically, the U-shaped plate 43 is usually installed in the middle of the vertical plate 41. Since the excavation of the foundation pit edge may not be accurate, it may be adjusted according to the actual situation. Ideally, it only needs to be installed in the middle and the screws are tightened.
[0040] On the basis of the above-mentioned implementation mode, the main diagonal bracing unit 5 includes an internally threaded support rod 50 and an externally threaded support rod 500 that are threadedly matched. A sleeve 51 is provided on the top of the externally threaded support rod 500 , and the sleeve 51 is hinged to the U-shaped plate 43 .
[0041] Specifically, the sleeve 51 is arranged horizontally, and the side plates of the U-shaped plate 43 are each provided with a hole 3, the screw 52 passes through the hole 3, the sleeve 51 and is threadedly engaged with the nut 2 53, and the sleeve 51 takes the screw 52 as the rotation axis and can adjust the angle around the screw 52.
[0042] On the basis of the above-mentioned implementation mode, the outer wall of the internally threaded support rod 50 is pressed on the top of the vertical plate 41 , and the vertical plate 41 provides supporting force for the internally threaded support rod 50 .
[0043] On the basis of the above-mentioned embodiment, a strip hole 501 is provided on the internal thread support rod 50 , and one end of the secondary diagonal support unit 6 passes through the strip hole 501 and is positioned by a fixing member.
[0044] Based on the above embodiment, the secondary diagonal bracing unit 6 includes a screw rod 62 with a sleeve 61 at one end, the sleeve 61 is hinged to the U-shaped plate 43, the other end of the screw rod 62 passes through the strip hole 501, and the fixing part includes a double nut 65 threadedly matched with the screw rod 62, and the inner surface of the double nut 65 is pressed on the internal threaded support rod 50.
[0045] On the basis of the above embodiment, the bottom of the internal thread support rod 50 is provided with a tip 54 for inserting into the foundation pit 1 .
[0046] On the basis of the above embodiment, a baffle 55 spaced apart from the tip 54 is provided on the internal thread support rod 50, and the baffle 55 cooperates with the foundation pit 1 to stop the baffle 55 so that the baffle 55 is stuck on the outer surface of the foundation pit 1 to enhance stability.
[0047] On the basis of the above-mentioned implementation mode, a plurality of wooden squares 11 are arranged between the vertical board 41 and the top layer independent foundation formwork 2 or between the vertical board 41 and the bottom layer independent foundation formwork 3 or between the vertical board 41 and the middle layer independent foundation formwork 0 .
[0048] Preferably, the hook 42 on the top of the vertical board 41 is hung on the top layer independent foundation formwork 2 or the bottom layer independent foundation formwork 3 or the middle layer independent foundation formwork 0, and a certain gap is formed between the top and the bottom of the vertical board 41 and the side wall of the formwork. Wooden squares 11 are inserted between the top of the vertical board 41 and the formwork, and between the bottom and the formwork to enhance the strength of the formwork.
[0049] Based on the above implementation, the vertical plate 41 is connected to the top independent foundation formwork 2 or the bottom independent foundation formwork 3 or the middle independent foundation formwork 0 through a bolt group 12. The bolt group 12 passes through the wooden beam 11 and the formwork in turn to fix it to prevent displacement between the connecting part 4 and the formwork.
[0050] Example 3 is a preferred implementation method of the construction method of a cast-in-place multi-step independent foundation formwork reinforcement device. It is different from Example 1 and Example 2 in that this example is suitable for foundations larger than three steps, and several layers of intermediate layer independent foundation formwork 0 can be set.
[0051] The details not described in detail in the present invention are all conventional technical means known to those skilled in the art.
[0052] The above content shows and describes the basic principles, main features and beneficial effects of the present invention. The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present invention shall be included in the protection scope of the present invention.
Claims
1. A construction method for a cast-in-place multi-stage independent foundation formwork reinforcement device, characterized in that: The construction steps include: S1: Excavation of foundation pit (1), construction and maintenance of cushion layer; S2: supporting the bottom independent foundation formwork (3), and setting square timber (11) outside the bottom independent foundation formwork (3); S3: erecting a supporting cross bar (7), supporting a top independent foundation formwork (2), and arranging square timbers (11) outside the top independent foundation formwork (2); S4: installing a plurality of connecting pieces (4) along the circumference of the bottom independent foundation template (3) and the top independent foundation template (2); S5: one end of the main diagonal bracing unit (5) is hinged to a connecting piece (4) connected to the top independent foundation formwork (2), and the other end of the main diagonal bracing unit (5) is inserted into the foundation pit (1); S6: hinge one end of the secondary bracing unit (6) to a connecting piece (4) connected to the bottom independent foundation formwork (3), and insert the other end of the secondary bracing unit (6) into the main bracing unit (5); S7: repeating steps S5-S6 to install the main diagonal bracing unit (5) and the secondary diagonal bracing unit (6) on a plurality of connecting members (4); or S1: Excavation of foundation pit (1), construction and maintenance of cushion layer; S2: supporting the bottom independent foundation formwork (3), and setting square timber (11) outside the bottom independent foundation formwork (3); S3: erecting a supporting cross bar (7), supporting an intermediate layer independent foundation formwork (0), and arranging square timbers (11) outside the intermediate layer independent foundation formwork (0); S4: erecting a supporting cross bar (7), supporting a top independent foundation formwork (2), and arranging square timbers (11) outside the top independent foundation formwork (2); S5: installing a plurality of connecting pieces (4) along the circumference of the bottom layer independent foundation template (3), the middle layer independent foundation template (0), and the top layer independent foundation template (2); S6: one end of the main diagonal bracing unit (5) is hinged to a connecting piece (4) connected to the top independent foundation formwork (2), and the other end of the main diagonal bracing unit (5) is inserted into the foundation pit (1); S7: hinge one end of the secondary bracing unit (6) to the connecting pieces (4) of the middle layer independent foundation formwork (0) and the bottom layer independent foundation formwork (3), and insert the other end of the secondary bracing unit (6) into the main bracing unit (5); S8: Repeat steps S6-S7 to install the main diagonal bracing unit (5) and the secondary diagonal bracing unit (6) on a plurality of connecting members (4).
2. The construction method of the cast-in-place multi-stage independent foundation formwork reinforcement device according to claim 1 is characterized in that: The connecting member (4) comprises a vertical plate (41) provided with a plurality of holes (1), a hook (42) is provided on the top of the vertical plate (41) for hanging on the upper surface of the top independent foundation template (2) or the middle independent foundation template (0) or the bottom independent foundation template (3), a U-shaped plate (43) is adjustably connected to the vertical plate (41), a bolt (44) passes through the hole (2) on the bottom plate of the U-shaped plate (43), the hole (1) and is threadedly engaged with a nut (1), and the main diagonal bracing unit (5) is hinged to the U-shaped plate (43).
3. The construction method of the cast-in-place multi-stage independent foundation formwork reinforcement device according to claim 2 is characterized in that: The main diagonal bracing unit (5) comprises an internally threaded support rod (50) and an externally threaded support rod (500) that are threadably matched, a sleeve one (51) being provided at the top of the externally threaded support rod (500), and the sleeve one (51) being hinged to the U-shaped plate (43).
4. The construction method of the cast-in-place multi-stage independent foundation formwork reinforcement device according to claim 3 is characterized in that: The outer wall of the internally threaded support rod (50) is pressed against the top of the vertical plate (41).
5. The construction method of the cast-in-place multi-stage independent foundation formwork reinforcement device according to claim 2 or 3, characterized in that: The internally threaded support rod (50) is provided with a strip-shaped hole (501), and one end of the secondary diagonal support unit (6) passes through the strip-shaped hole (501) and is positioned by a fixing member.
6. The construction method of the cast-in-place multi-stage independent foundation formwork reinforcement device according to claim 5 is characterized in that: The secondary bracing unit (6) comprises a screw rod (62) having a sleeve (61) at one end, the sleeve (61) being hinged to the U-shaped plate (43), the other end of the screw rod (62) passing through the strip hole (501), and the fixing member comprises a double nut (65) threadably matched with the screw rod (62), the inner surface of the double nut (65) being pressed onto the internally threaded support rod (50).
7. The construction method of the cast-in-place multi-stage independent foundation formwork reinforcement device according to any one of claims 2, 3 or 6, characterized in that: The bottom of the internally threaded support rod (50) is provided with a pointed portion (54) for inserting into the foundation pit (1).
8. The construction method of the cast-in-place multi-stage independent foundation formwork reinforcement device according to claim 7 is characterized in that: The internally threaded support rod (50) is provided with a baffle (55) spaced from the tip (54), and the baffle (55) is in blocking cooperation with the foundation pit (1).
9. The construction method of the cast-in-place multi-stage independent foundation formwork reinforcement device according to any one of claims 2 or 3, 6, and 8, characterized in that: A plurality of wooden planks (11) are arranged between the vertical board (41) and the top independent foundation formwork (2), or between the vertical board (41) and the other layer formworks (3), or between the vertical board (41) and the middle layer independent foundation formwork (0).
10. The construction method of the cast-in-place multi-stage independent foundation formwork reinforcement device according to any one of claims 2 or 3, 6, and 8, characterized in that: The vertical plate (41) is connected to the top independent foundation formwork (2) or the other layer formwork (3) or the middle layer independent foundation formwork (0) via a bolt group (12).