Open caisson engineering attitude balancing system

By setting up a balance base and mechanical control unit in the caisson project, and using tension synchronization jacks and force sensors to monitor the shaft sinking process, the problem of sudden sinking and tilt of the shaft in the three-dimensional parking garage was solved, and the smooth sinking and construction of the shaft were achieved. Improved security.

CN118727754APending Publication Date: 2024-10-01HANGZHOU NEWSTON UNDERGROUND SPACE TECH CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202310329628.5
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2023-03-29
Publication Date
2024-10-01

AI Technical Summary

Technical Problem

In the caisson project, the wellbore of the three-dimensional parking garage is prone to sudden sinking and tilt accidents caused by geological influences. It is difficult to effectively avoid these accidents with existing technology and ensure the smooth and safe sinking of the wellbore.

Method used

Design a posture balance system for caisson engineering, which includes setting a balance base and multiple sets of mechanical control units outside the wellbore. It uses a tension synchronized jack and a force sensor to detect the change in tension during the sinking process of the wellbore. Through uniformly distributed mechanical control units and Synchronized tension synchronized jacks achieve balanced sinking of the wellbore and are monitored by force sensors to prevent tilting.

Benefits of technology

It effectively avoids sudden sinking accidents of the wellbore caused by geological factors, and constantly monitors and prevents tilting, ensuring that the wellbore sinks smoothly during the sinking process, and improving construction safety.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118727754A_ABST
    Figure CN118727754A_ABST
Patent Text Reader

Abstract

The invention discloses a posture balance system in an open caisson project. On one hand, sudden sinking accidents of an open caisson body in the open caisson process can be avoided. And on the other hand, it can be guaranteed that the open caisson body is always kept perpendicular in the open caisson process, and inclination accidents are prevented. An open caisson engineering posture balance system comprises a balance base, the balance base is arranged on the outer side of a shaft, three or more sets of mechanical control units are arranged on the balance base and evenly distributed in the circumferential direction of the shaft, each set of mechanical control unit comprises a connecting mechanism, and the connecting mechanisms are arranged on tension synchronous numerical control jacks in a penetrating mode; the connecting end of the connecting mechanism is connected with the lower end of the shaft; and the tension synchronous numerical control jack transmits acquired data to the control unit.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention belongs to the technical field of underground engineering construction, and specifically relates to safety and technical measures for an ultra-deep caisson project, and a control system for ensuring the balance of the caisson posture using key node technology. Background Art

[0002] The underground space of a city is a valuable land resource of a city. In order to save and intensively utilize land resources, engineering and technical personnel are constantly exploring how to develop and utilize underground space, especially deep underground space, more quickly, efficiently and economically. In this context, CNC caisson technology came into being.

[0003] To build a vertical shaft, a currently feasible construction method is to set a blade foot structure at the lower end of the shaft wall, insert the blade foot into the soil layer, and use the shaft's own gravity to sink. During the sinking of the shaft, earth is excavated in the area corresponding to the shaft.

[0004] Since the diameter of the shaft of a three-dimensional parking garage is relatively large, unlike the relatively small diameter shaft used for pile foundations, the shaft of a three-dimensional parking garage is very susceptible to geological influences. During the construction process, the shaft of a three-dimensional parking garage is very prone to sudden sinking and tilting. In this regard, how to avoid sudden sinking and tilting in caisson projects and ensure that ultra-deep caisson projects can sink smoothly and safely is a technical problem that urgently needs to be solved by people in this field. Summary of the invention

[0005] The purpose of the present invention is to provide a caisson engineering posture balancing system, which can prevent the shaft of a three-dimensional parking garage from sinking suddenly during the caisson engineering, and can also prevent the shaft of a three-dimensional parking garage from tilting during the caisson engineering.

[0006] In order to solve the above technical problems, the technical solution adopted by the present invention is:

[0007] A caisson engineering posture balancing system is characterized by comprising a balancing base, the balancing base is arranged on the outside of the wellbore, more than three groups of mechanical control units are arranged on the balancing base, the mechanical control units are evenly distributed in the circumferential direction of the wellbore, each group of mechanical control units includes a connecting mechanism, the connecting mechanism is passed through a tension synchronization jack, and the connecting end on the connecting mechanism is connected to the lower end of the wellbore; the tension synchronization jack transmits the collected data to the control unit.

[0008] On the basis of the above scheme and as a preferred scheme of the above scheme: all the tension synchronization jacks work synchronously, each tension synchronization jack is correspondingly configured with a force sensor, the force sensor is used to detect the tension of the wire rope between the tension synchronization jack and the connection end, each force sensor is connected to the control unit, the control unit receives the tension information transmitted by the force sensor, and when the tension transmitted by each force sensor is inconsistent with each other, it is determined that the wellbore is inclined.

[0009] On the basis of the above scheme and as a preferred scheme of the above scheme: the outer diameter of the cutting foot of the wellbore is greater than the outer diameter of the wellbore wall of the wellbore.

[0010] On the basis of the above scheme and as a preferred scheme of the above scheme: the steel wire rope extends from a position above the top surface of the blade foot to the inner side of the blade foot and is fixed to the blade foot.

[0011] On the basis of the above scheme and as a preferred scheme of the above scheme: it also includes a wire drum, and the free end of the wire rope is wound on the wire drum.

[0012] On the basis of the above scheme and as a preferred scheme of the above scheme: all the tension synchronization jacks are synchronously controlled by a group of oil cylinder pump groups.

[0013] On the basis of the above scheme and as a preferred scheme of the above scheme: the balancing base is provided with a pipeline trench.

[0014] On the basis of the above scheme and as a preferred scheme of the above scheme: the balance base is reinforced concrete or a steel structure.

[0015] On the basis of the above solution and as a preferred solution of the above solution: a pile foundation or a composite foundation is arranged under the balancing base.

[0016] On the basis of the above scheme and as a preferred scheme of the above scheme: a channel for the steel wire rope to pass through is provided on the balancing base.

[0017] Compared with the prior art, the present invention has the following outstanding and beneficial technical effects:

[0018] The caisson engineering posture balancing system of the present invention, by setting a mechanical control unit structure, allows the wellbore to sink under a pulling state, which can effectively prevent the wellbore from suddenly sinking due to geological factors and effectively avoid sudden sinking accidents.

[0019] On the other hand, each wire rope uses a force sensor to detect the stress, which forms a whole as a data reference to determine whether the wellbore tilts during the sinking process. All the tension synchronization jacks work synchronously, and the wellbore sinking process can be monitored at all times, which can effectively avoid tilting accidents and ensure the smooth sinking of the wellbore. BRIEF DESCRIPTION OF THE DRAWINGS

[0020] Figure 1 It is a structural schematic diagram of the present invention.

[0021] Figure 2 It is a structural schematic diagram of the present invention.

[0022] Figure 3 It is a partial structural diagram of the present invention.

[0023] Figure 4 It is a partial structural diagram of the present invention.

[0024] In the figure, 1, wellbore; 11, well wall; 12, blade foot; 2, balance base; 3, mechanical control unit; 31, wire rope; 32, tension synchronization jack; 33, wire drum; 34, force sensor; 121, top surface of blade foot; 122, inner side of blade foot; 21, pipeline trench; 22, channel. DETAILED DESCRIPTION

[0025] In order to make the purpose, technical solution and advantages of this application clearer, the technical solution in the embodiment will be clearly and completely described below in conjunction with the drawings in the embodiment. Obviously, the described embodiment is only a part of the embodiment of this application, not all embodiments. Based on the given embodiments, all other embodiments obtained by ordinary technicians in this field without making creative work are within the scope of protection of this application.

[0026] In the description of the present application, it should be understood that the terms "upper", "lower", etc. indicate orientations or positional relationships based on the orientations or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present application and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore should not be understood as a limitation on the present application.

[0027] In the description of this application, the terms "first", "second", etc. are used for descriptive purposes only and cannot be understood as indicating or implying relative importance or implicitly indicating the number of the indicated technical features.

[0028] In the description of the present application, the term "above" includes the present number.

[0029] The caisson engineering posture balancing system of the present invention is applied in the caisson engineering of the three-dimensional parking garage shaft 1. It should be pointed out that the diameter of the three-dimensional parking garage shaft 1 is relatively large, and it is designed and planned to park cars, and even designed and planned to park buses.

[0030] As shown in the figure, the shaft 1 of the three-dimensional parking garage includes a shaft wall 11 and a blade foot 12 arranged at the lower end of the shaft wall 11. During the caisson construction, soil is taken from the inner side of the shaft 1, and the blade foot 12 cuts the soil under the deadweight of the blade foot 12 and the shaft wall 11, thereby achieving the purpose of caissoning the shaft 1.

[0031] The caisson engineering posture balancing system of the present invention can prevent the shaft of a three-dimensional parking garage from sinking suddenly during the caisson engineering, and can also prevent the shaft of a three-dimensional parking garage from tilting during the caisson engineering.

[0032] A caisson engineering posture balancing system of the present invention includes a balancing base 2, and the balancing base 2 is arranged on the outside of the shaft 1. The balancing base 2 is arranged at the cross intersection of the caisson engineering and the ground. Usually, the structural material of the balancing base 2 can be selected from reinforced concrete or steel structure. In specific applications, the structural form of the balancing base 2 is designed and selected based on the shape, load, and engineering geological conditions of the caisson engineering. According to the engineering geological conditions, the balancing base 2 can also adopt a pile foundation or a composite foundation.

[0033] Usually, the shape of the balance base 2 is consistent with the outer shape of the wellbore 1, and is generally a variety of shapes such as round, rectangular or polygonal. The outer diameter of the wellbore is smaller than the inner diameter of the balance base.

[0034] More than three groups of mechanical control units 3 are arranged on the balancing base 2, and the mechanical control units 3 are evenly distributed in the circumferential direction of the wellbore 1. By adopting the evenly distributed structure, the pulling force on the wellbore 1 in the circumferential direction is balanced. As shown in the figure, in this embodiment, four groups of mechanical control units 3 are arranged on the balancing base 2.

[0035] As shown in the figure, each group of mechanical control units 3 includes a steel wire rope 31, which can also be called a steel strand. The steel wire rope 31 is passed through a tension synchronization jack 32, which can also be called a steel strand jack, and is dedicated to pulling the steel wire rope 31. The connecting end on the steel wire rope 31 is connected to the lower end of the wellbore 1. In specific applications, the tension synchronization jack 32 is hydraulically controlled to gradually and slowly lower the steel wire rope 31, and the wellbore 1 is controlled to sink within the range of the lowering of the steel wire rope 31. It should be pointed out that the tension synchronization jack 32 belongs to the prior art, and the specific structure of the tension synchronization jack 32 will not be repeated here. Usually, as shown in the figure, the free end of the steel wire rope 31 is wound on a wire drum 33. The wire drum 33 is rotatably arranged on the balance base 2.

[0036] The tension synchronization jack 32 in the mechanical control unit 3 is connected to the cylinder pump group and is controlled by the cylinder pump group to release a fixed length of the wire rope 31. It should be noted that the cylinder pump group can be configured as one group, or the tension synchronization jack 32 can be configured with one group of cylinder pump groups.

[0037] In specific applications, the oil cylinder pump group controls the tension synchronous jack 32 to work, the wire rope 31 is released by the tension synchronous jack 32 to a fixed length, and the wellbore sinks under its own gravity. After the wellbore sinks for a round, the oil cylinder pump group controls the tension synchronous jack to work again, and the wellbore enters a new round of sinking. During this period, soil is taken from the inside of the wellbore.

[0038] In this embodiment, by setting up the structure of the mechanical control unit 3, the wellbore 1 is allowed to sink under the pulling state, which can effectively prevent the wellbore 1 from sinking suddenly due to the influence of geological factors and effectively avoid sudden sinking accidents.

[0039] In one embodiment, the tension synchronization jack 32 is controlled by the oil cylinder pump group, and all the tension synchronization jacks 32 work synchronously. That is to say, all the tension jacks lower the wire rope 31 at the same time, and the lengths lowered are equal. Usually, the tension synchronization jacks 32 in each mechanical control unit 3 use tension synchronization jacks 32 of the same specifications. As shown in the figure, each tension synchronization jack 32 is correspondingly configured with a force sensor 34, and the force sensor 34 is used to detect the tension of the wire rope 31 between the tension synchronization jack 32 and the connection end. Each force sensor 34 is connected to the control unit, and the control unit receives the tension information transmitted by the force sensor 34. When the tension information transmitted by each force sensor 34 is inconsistent, it is determined that the wellbore 1 is tilted. It should be pointed out that the tension information can be manually determined to be consistent, and the control unit can also be used to process and compare the collected tension information. When the tension information transmitted by each force sensor 34 is inconsistent, it is determined that the wellbore 1 is tilted, and the control unit issues a prompt.

[0040] In this embodiment, the force sensor 34 is used to detect the stress of the steel wire rope 31, and the stress of each steel wire rope 31 is detected, which forms a whole as a data reference for judging whether the wellbore 1 is tilted during the sinking process. In specific applications, if the wellbore 1 is tilted, the difference value of each force sensor 34 exceeds the normal range, and soil is taken at the corresponding position until the difference value of each force sensor 34 is within the normal range, thereby correcting the tilt of the wellbore 1. Since all the tension synchronization jacks 32 work synchronously, the wellbore 1 can be monitored at all times during the sinking process, which can effectively avoid tilting accidents and ensure that the wellbore 1 sinks smoothly.

[0041] The outer diameter of the blade foot 12 is greater than the outer diameter of the well wall 11. By setting this structure, a space for accommodating the wire rope 31 is formed on the outer side of the well wall 11, so as to prevent the wire rope 31 from being stuck and affecting the force detection.

[0042] In this embodiment, the steel wire rope 31 extends from the upper position of the top surface 121 of the blade foot to the inner side 122 of the blade foot and is fixed to the blade foot. This structure enables the steel wire rope 31 to be reliably fixed to the wellbore 1, while also ensuring the strength of the blade foot 12.

[0043] As shown in the figure, the balancing base 2 is provided with a pipeline groove 21, and the pipeline groove 21 is for the pipeline connected to the tension synchronization jack 32 to pass through. By providing the structure of the pipeline groove 21, the oil supply pipeline of the tension jack can be effectively protected. The line of the force sensor 34 can also pass through the pipeline groove 21 to protect the line.

[0044] The balancing base 2 is provided with a channel 22 for the steel wire rope 31 to pass through. By adopting this structure, the tension synchronization jack 32 can be vertically arranged and can bear a larger force.

[0045] The above embodiments are only preferred embodiments of the present invention and are not intended to limit the protection scope of the present invention. Therefore, any equivalent changes made based on the structure, shape, and principle of the present invention should be included in the protection scope of the present invention.

Claims

1. A caisson engineering posture balance system, characterized by: It includes a balancing base, which is arranged on the outside of the wellbore. More than three groups of mechanical control units are arranged on the balancing base. The mechanical control units are evenly distributed in the circumferential direction of the wellbore. Each group of mechanical control units includes a connecting mechanism. The connecting mechanism is passed through the tension synchronization jack. The connecting end on the connecting mechanism is connected to the lower end of the wellbore. The tension synchronization jack transmits the collected data to the control unit.

2. The caisson engineering posture balancing system according to claim 1 is characterized by: All the tension synchronization jacks work synchronously. Each tension synchronization jack is correspondingly configured with a force sensor. The force sensor is used to detect the tension of the wire rope between the tension synchronization jack and the connection end. Each force sensor is connected to the control unit. The control unit receives the tension information transmitted by the force sensor. According to the tension information transmitted by each force sensor, the system analyzes the state of the wellbore.

3. The caisson engineering posture balancing system according to claim 1 or 2, characterized in that: The outer diameter of the blade foot of the wellbore is greater than the outer diameter of the wellbore wall of the wellbore.

4. The caisson engineering posture balancing system according to claim 3 is characterized by: The steel wire rope extends from a position above the top surface of the blade foot toward the inner side of the blade foot and is fixed to the blade foot.

5. The caisson engineering posture balancing system according to claim 1 is characterized by: Also included is a wire drum on which the free end of the wire rope is wound.

6. The caisson engineering posture balancing system according to claim 1 is characterized by: All the tension synchronous jacks are synchronously controlled by a group of cylinder pump groups.

7. The caisson engineering posture balancing system according to claim 1 is characterized by: The balancing base is provided with a pipeline trench.

8. The caisson engineering posture balancing system according to claim 1 is characterized by: The balance base is made of reinforced concrete or a steel structure.

9. The caisson engineering posture balancing system according to claim 8 is characterized by: A pile foundation or a composite foundation is arranged below the balancing base.

10. The caisson engineering posture balancing system according to claim 1, characterized in that: The balancing base is provided with a channel for the steel wire rope to pass through.