Aluminum mold mounting method for high-rise fabricated building
Through the aluminum formwork installation method, the flatness deviation and deformation problems of wooden formwork construction in high-rise prefabricated buildings are solved, efficient and safe concrete pouring and construction efficiency are improved, the process is simplified, the cost is reduced, and green practices are practiced Environmentally friendly construction concept.
Patent Information
- Application Number
- CN202410960068.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-17
- Publication Date
- 2024-10-01
AI Technical Summary
High-rise prefabricated buildings have flatness deviation and deformation problems in traditional wooden formwork construction, resulting in poor concrete pouring quality, and the wood formwork materials occupy space and pose safety hazards.
The aluminum formwork installation method is adopted, including dividing the aluminum formwork into partitions, pre-embedding reinforced steel bars, installing the aluminum formwork, hoisting the laminated panels, concrete pouring and aluminum formwork dismantling. Through the high stiffness of the aluminum formwork and the precise pre-embedding of water and wire troughs and fire boxes, reducing grout leakage and cumbersome processes to improve construction efficiency and safety.
It effectively reduces the problems of concrete deformation and slurry leakage, improves construction efficiency and safety, simplifies the process, reduces construction costs, and achieves reusable and environmentally friendly construction of aluminum molds.
Smart Images

Figure CN118728057A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of building construction, and in particular to an aluminum formwork installation method for a high-rise assembled building. Background Art
[0002] With the development of construction technology, prefabricated buildings are being used in more and more scenarios. Prefabricated buildings can transfer a large amount of on-site work in traditional construction methods to factories. Building components and accessories (such as floor slabs, wall panels, stairs, balconies, etc.) are processed and manufactured in factories, transported to construction sites, and assembled and installed on site through reliable connection methods, which greatly improves the construction speed and reduces production costs.
[0003] Prefabricated building components include prefabricated composite panels. The upper and lower surfaces of the composite panels are flat, which is convenient for finishing layer decoration. They are suitable for high-rise buildings and large-span buildings that require high overall rigidity. When constructing the main structure of existing high-rise prefabricated residential buildings, wooden formwork is usually used. Since the prefabricated composite panels themselves have a flatness deviation of about 3-5mm when they leave the factory, and the traditional wooden formwork is easily deformed by exposure to hot weather during construction, the combination of the two results in a large gap between the prefabricated composite panels and the wooden formwork surface during installation. When pouring concrete, leakage will occur in this area, making the quality of concrete pouring impossible to guarantee, and manual chiseling and trimming are required later; at the same time, the horizontal height difference of the ceiling and floor is too large, which affects the net height of the room.
[0004] On the other hand, traditional wooden formwork materials must be laid on the ground, and a formwork stacking area must be set up on site. Wooden formwork materials include debris such as mud and waste nails, as well as some flammable materials, which poses a major safety hazard. Summary of the invention
[0005] The object of the present invention is to provide an aluminum formwork installation method for high-rise prefabricated buildings to at least solve one of the above-mentioned technical problems.
[0006] In order to achieve the above-mentioned invention object, the technical solution adopted by the present invention is as follows:
[0007] A method for installing an aluminum formwork for a high-rise assembled building comprises the following steps:
[0008] S1. Divide the aluminum mold into zones: Divide the aluminum mold according to the structural unit type in the construction drawings and number them by area;
[0009] S2. Deepen the aluminum formwork installation nodes and draw the aluminum formwork installation diagram;
[0010] S3. Prepare aluminum molds and accessories: prepare corresponding components according to the size of the building;
[0011] S4, pre-embedded reinforcement steel bars: according to the aluminum formwork installation drawing drawn in step S2, pre-embed the reinforcement steel bars of the aluminum formwork in the floor slab;
[0012] S5. Install aluminum formwork for wall columns, beams and panels;
[0013] S6. Lifting of prefabricated composite panels: Use hangers, long steel cables and movable pulleys to ensure that each lifting point is balanced when lifting the prefabricated composite panels;
[0014] S7, concrete pouring and curing;
[0015] S8. Remove the aluminum formwork of walls and columns and the aluminum formwork of beams and slabs.
[0016] Through such an arrangement, the aluminum molds are numbered and stacked by area, which improves the construction efficiency of installation and dismantling. On the other hand, since the rigidity of the aluminum mold is better than that of the wooden mold, the aluminum mold and the prefabricated composite slab have a better fit, which can effectively reduce the deformation and leakage of the prefabricated composite slab when pouring concrete.
[0017] Preferably, in step S2, the pre-buried water and electricity cable ducts and the pre-buried fire extinguisher boxes are deeply embedded in the aluminum mold installation diagram, and the pre-buried water and electricity cable ducts and the pre-buried fire extinguisher boxes are formed in one step.
[0018] With such arrangement, the pre-buried water and electricity cable ducts and the fire extinguishing box are formed in one step, with good forming quality and precise positioning.
[0019] Preferably, in step S2, the structural columns, special-shaped columns and lintels of the secondary structure door edges and brick walls are deepened into the aluminum formwork installation drawing.
[0020] With this arrangement, the structural columns, special-shaped columns and lintels of the secondary structure door sides and brick walls are formworked, installed and poured with concrete together with the main structure, and are formed in one step, eliminating a series of tedious processes such as embedding reinforcement, supporting formwork, pouring concrete and plastering of structural columns and special-shaped columns during the secondary structure construction, thereby simplifying the process, saving construction costs and ensuring construction quality.
[0021] Preferably, in step S3, a site is selected for stacking components, and the prefabricated components are stored and numbered through pads and fixed brackets according to type, specification, used position, lifting sequence, prefabricated component stress state, and inspection state.
[0022] Preferably, in step S3, the component includes an aluminum mold, a C-groove and angle aluminum.
[0023] Preferably, between step S2 and step S3, a reinforcement scheme is also designed, the reinforcement scheme includes adding an aluminum mold reinforcement module, the aluminum mold reinforcement module includes a K plate, and the component prepared in step S3 includes the K plate.
[0024] Preferably, after step S5, the K-board is installed on the top of the wall column and 50 mm above the floor, and in step S8, the K-board is not removed.
[0025] In this way, the K-plate is used to connect with the aluminum formwork of the upper wall column to ensure the verticality of the exterior wall column. At the same time, the calculated and designed aluminum formwork reinforcement module can ensure that there will be no mold bursting when pouring concrete.
[0026] More preferably, between step S5 and step S6, C-grooves and angle aluminum are installed at the overlap between the prefabricated composite slab and the cast-in-place wall to receive the prefabricated composite slab.
[0027] Preferably, in step S5, sponge rubber strips are pasted between the wall columns and the aluminum molds, between the beams and the aluminum molds, between the plates and the aluminum molds, and at the overlapping tongues and grooves between the assembled composite plates and the aluminum molds.
[0028] With this arrangement, the sponge strips can effectively seal the gaps and reduce the problem of leakage.
[0029] Preferably, the reinforcement scheme further includes, in step S7, pre-embedding reinforcing steel bars before pouring each layer of concrete, for the oblique support reinforcement of the next layer of wall columns.
[0030] With this arrangement, by pre-embedding reinforcing steel bars, the oblique supports of the next layer of wall columns can be reinforced to ensure the reinforcement quality of the aluminum mold to avoid mold explosion.
[0031] Beneficial effects:
[0032] The invention discloses an aluminum formwork installation method for a high-rise assembled building, comprising the following steps: dividing the aluminum formwork into zones; deepening the aluminum formwork installation nodes and drawing an aluminum formwork installation diagram; preparing the aluminum formwork and accessories; pre-embedding reinforcing steel bars; installing the aluminum formwork of wall columns, beams and panels; hoisting the assembled composite panels; pouring and curing concrete, and removing the column aluminum formwork and the beam and panel aluminum formwork. The aluminum formwork is numbered and stacked according to the area, thereby improving the construction efficiency of installation and removal. On the other hand, since the rigidity of the aluminum formwork is better than that of the wooden formwork, the aluminum formwork and the assembled composite panel have a better fitting effect, which can effectively Reduce deformation and leakage of prefabricated composite slabs during concrete pouring; pre-buried water and electricity cable ducts and fire extinguisher boxes are formed in one step, with good molding quality and precise position; the structural columns, special-shaped columns, and lintels of the secondary structure door edges and brick walls are supported and installed together with the main structure for concrete pouring, and are formed in one step, eliminating a series of tedious processes such as reinforcing bars, supporting formwork, pouring concrete, and plastering for structural columns and special-shaped columns during secondary structure construction, simplifying the process, saving construction costs, and ensuring construction quality; after the aluminum mold is removed, there is no debris and flammable materials such as mud and waste nails on site, which improves safety. BRIEF DESCRIPTION OF THE DRAWINGS
[0033] Figure 1 is a flow chart of an embodiment of the present invention. DETAILED DESCRIPTION
[0034] In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the specific implementation methods of the present invention will be described below with reference to the accompanying drawings. Obviously, the accompanying drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other drawings and other implementation methods can be obtained based on these drawings without creative work.
[0035] The technical solution of the present invention is described in detail below with specific embodiments.
[0036] The present invention provides an aluminum formwork installation method for a high-rise assembled building, comprising the following steps:
[0037] S1. Divide the aluminum mold into zones: Divide the aluminum mold according to the structural unit type in the construction drawings and number them by zone;
[0038] S2. Deepen the aluminum formwork installation nodes and draw the aluminum formwork installation diagram;
[0039] S3. Prepare aluminum molds and accessories: prepare corresponding components according to the size of the building;
[0040] S4, pre-embedded reinforcement steel bars: according to the aluminum formwork installation drawing drawn in step S2, pre-embed the reinforcement steel bars of the aluminum formwork in the floor slab;
[0041] S5. Install aluminum formwork for wall columns, beams and panels;
[0042] S6. Lifting of prefabricated composite panels: Use hangers, long steel cables and movable pulleys to ensure that each lifting point is balanced when lifting the prefabricated composite panels;
[0043] S7, concrete pouring and curing;
[0044] S8. Remove the aluminum formwork of wall columns and the aluminum formwork of beams and slabs.
[0045] Compared with the wooden formwork in the existing technology, the cost per square meter of aluminum formwork is higher, but the construction efficiency of aluminum formwork is high, the concrete is flat and smooth, the appearance is good, and the plastering cost is greatly reduced. Except for the first assembly, it does not occupy vertical transportation equipment and does not occupy material partitioning site. It is very suitable for high-rise prefabricated residential building projects with small initial site and tight construction period. According to actual calculations, when the standard floors of the high-rise prefabricated building to be constructed reach 23 floors or above, the construction cost of using aluminum formwork is lower than that of wooden formwork.
[0046] In step S2, the pre-buried water and electricity cable ducts and the pre-buried fire extinguisher boxes are deeply embedded in the aluminum mold installation diagram. The pre-buried water and electricity cable ducts and the pre-buried fire extinguisher boxes are formed in one step, with good molding quality and accurate position.
[0047] Preferably, in step S2, the structural columns, special-shaped columns and lintels of the secondary structure door sides and brick walls are also deepened into the aluminum mold installation diagram. In this way, the structural columns, special-shaped columns and lintels of the secondary structure door sides and brick walls are supported by formwork and installed together with the main structure to cast concrete, and are formed in one step, thereby eliminating a series of tedious processes such as planting reinforcement, supporting formwork, pouring concrete, and plastering of structural columns and special-shaped columns during secondary structure construction, simplifying the process, saving construction costs, and ensuring construction quality.
[0048] Furthermore, in order to do a good job in waterproofing the exterior wall, the drip lines and structural water retaining line frames of the exterior wall doors and windows and balcony cantilever beams are deepened into the aluminum mold installation drawing and poured together with the main structure concrete. The molding is done in one go with good molding quality and straight lines. Finally, the structure of the joints between the structural shear wall columns, structural beams and brick walls is deepened, and plastering interfaces are reserved so that the structural shear wall columns and beams of the brick wall can be better closed when the secondary structure is plastered.
[0049] In step S3, a site is selected for stacking components. The prefabricated components are stored and numbered through pads and fixed brackets according to their type, specification, location used, lifting sequence, stress state of the prefabricated components, and inspection state. A flat, solid site with good drainage measures is preferably used for stacking components. The components include aluminum molds, C grooves and angle aluminum. Between step S5 and step S6, a circle of C grooves and angle aluminum is installed at the overlap of the prefabricated composite slab and the cast-in-place wall to receive the prefabricated composite slab.
[0050] Specifically, when customizing an aluminum mold from an aluminum mold manufacturer, the details of the aluminum mold assembly and installation nodes are formed into an aluminum mold installation drawing according to each partition, and the assembled aluminum mold is numbered according to the installation location, and the corresponding installation QR code is affixed. By scanning the QR code, you can find the installation partition and location to which the aluminum mold belongs.
[0051] Between step S2 and step S3, a reinforcement scheme is also designed. The reinforcement scheme includes adding an aluminum mold reinforcement module. The aluminum mold reinforcement module includes a K plate. The components prepared in step S3 include a K plate. After step S5, the K plate is installed on the top of the wall column and is 50 mm higher than the floor. In step S8, the K plate is not removed. In this way, the K plate is used to connect with the aluminum mold of the wall column of the upper layer to ensure the verticality of the outer wall column. At the same time, the aluminum mold reinforcement module designed by calculation can ensure that there will be no mold explosion during concrete pouring. More specifically, the reinforcement scheme also includes adding a support system. The support system includes three sets of floor bottom supports, three sets of beam bottom supports and four sets of cantilever structure bottom supports. In the vertical pole support system, the floor adopts an aluminum tube single rod support with a spacing of 1300*1300mm, the beam adopts an aluminum tube single rod support with a spacing of 1200mm, and the ladder plate bottom support is encrypted with a spacing of 1000mm. The single rod support is made of aluminum alloy. While meeting the stress requirements, the advantages of quick disassembly and assembly of aluminum molds are brought into play, saving material investment and costs as much as possible.
[0052] In step S5, sponge rubber strips are pasted between the wall columns and the aluminum molds, between the beams and the aluminum molds, between the plates and the aluminum molds, and at the overlapping tongues and grooves between the assembled composite plates and the aluminum molds. The sponge rubber strips can effectively seal the gaps and reduce the problem of slurry leakage.
[0053] Preferably, fiberglass cloth can be hung at the tongue and groove to smooth the finished surface of the structure to prevent cracking.
[0054] In step S6, since the mold itself has a certain degree of flatness and dimensional deviation when the prefabricated composite panels are cast, the flatness of the prefabricated composite panels will have a deviation of 3-5mm when they leave the factory. In order to prevent the prefabricated composite panels from deformation or cracking due to improper lifting methods during lifting, the lifting method of the prefabricated composite panels is optimized, and the lifting is carried out using hangers, long steel cables and movable pulleys. This can ensure that each lifting point is subjected to balanced force when the prefabricated composite panels are lifted, thereby avoiding cracks during lifting.
[0055] The reinforcement scheme also includes, in step S7, before pouring each layer of concrete, pre-embedded reinforcing steel bars are used to reinforce the oblique supports of the next layer of wall columns, which can reinforce the oblique supports of the next layer of wall columns and ensure the reinforcement quality of the aluminum mold to avoid mold explosion.
[0056] In summary, the aluminum formwork installation method for high-rise prefabricated buildings provided by the present invention can solve some of the drawbacks of the traditional wooden formwork construction technology of high-rise prefabricated buildings in the past, effectively improve the construction efficiency of high-rise prefabricated buildings, shorten the construction period, and thus save construction costs. Since the aluminum formwork can be recycled and reused many times, it can also practice the concept of green, environmentally friendly and sustainable development of construction, and reduce the demand and damage to natural resources; the aluminum formwork is numbered and stacked according to the area, which improves the construction efficiency of installation and dismantling; on the other hand, since the rigidity of the aluminum formwork is better than that of the wooden formwork, the aluminum formwork and the prefabricated The composite slabs have a better fitting effect, which can effectively reduce the deformation and leakage of prefabricated composite slabs when pouring concrete; the pre-buried water and electricity cable ducts and fire extinguisher boxes are pre-buried and formed in one step, with good molding quality and precise position; the structural columns, special-shaped columns, and lintels of the secondary structure door edges and brick walls are supported and installed together with the main structure to cast concrete, and are formed in one step, eliminating a series of tedious processes such as reinforcing bars, supporting molds, pouring concrete, and plastering for structural columns and special-shaped columns during secondary structure construction, simplifying the process, saving construction costs, and ensuring construction quality; after the aluminum mold is removed, there is no debris and flammable materials such as mud and waste nails on site, which improves safety.
[0057] The above is a detailed description of an embodiment of an aluminum formwork installation method for a high-rise prefabricated building provided by the present invention. Specific examples are used herein to illustrate the principles and implementation methods of the present invention, and the description of the above embodiments is only used to help understand the core idea of the present invention. It should be pointed out that for ordinary technicians in this technical field, without departing from the principles of the present invention, several improvements and modifications can be made to the present invention, and these improvements and modifications also fall within the scope of protection of the claims of the present invention.
Claims
1. A method for installing an aluminum formwork for a high-rise prefabricated building, characterized in that: The steps include: S1. Divide the aluminum mold into zones: Divide the aluminum mold according to the structural unit type in the construction drawings and number them by area; S2. Deepen the aluminum formwork installation nodes and draw the aluminum formwork installation diagram; S3. Prepare aluminum molds and accessories: prepare corresponding components according to the size of the building; S4, pre-embedded reinforcement steel bars: according to the aluminum formwork installation drawing drawn in step S2, pre-embed the reinforcement steel bars of the aluminum formwork in the floor slab; S5. Install aluminum formwork for wall columns, beams and panels; S6. Lifting of prefabricated composite panels: Use hangers, long steel cables and movable pulleys to ensure that each lifting point is balanced when lifting the prefabricated composite panels; S7, concrete pouring and curing; S8. Remove the aluminum formwork of wall columns and the aluminum formwork of beams and slabs.
2. The aluminum mold installation method according to claim 1, characterized in that: In step S2, the pre-buried water and electricity cable ducts and the pre-buried fire extinguisher boxes are deeply embedded in the aluminum mold installation diagram, and the pre-buried water and electricity cable ducts and the pre-buried fire extinguisher boxes are formed in one step.
3. The aluminum mold installation method according to claim 1, characterized in that: In step S2, the structural columns, special-shaped columns and lintels of the secondary structure door side and brick wall are deepened into the aluminum formwork installation drawing.
4. The aluminum mold installation method according to claim 1, characterized in that: In step S3, a site is selected for stacking components, and the prefabricated components are stored and numbered through pads and fixed brackets according to type, specification, used position, lifting sequence, prefabricated component stress state, and inspection state.
5. The aluminum mold installation method according to claim 1, characterized in that: In step S3, the components include an aluminum mold, a C-channel and angle aluminum.
6. The aluminum mold installation method according to claim 1, characterized in that: Between step S2 and step S3, a reinforcement scheme is also designed, wherein the reinforcement scheme includes adding an aluminum mold reinforcement module, wherein the aluminum mold reinforcement module includes a K plate, and the component prepared in step S3 includes the K plate.
7. The aluminum mold installation method according to claim 6, characterized in that: After step S5, the K-board is installed on the top of the wall column and 50 mm above the floor, and in step S8, the K-board is not removed.
8. The aluminum mold installation method according to claim 5, characterized in that: Between step S5 and step S6, C-grooves and angle aluminum are installed at the overlap between the assembled composite slab and the cast-in-place wall to receive the assembled composite slab.
9. The aluminum mold installation method according to claim 1, characterized in that: In step S5, sponge rubber strips are pasted between the wall column and the aluminum formwork, between the beam and the aluminum formwork, between the plate and the aluminum formwork, and at the overlapping tongue and groove of the assembled composite plate and the aluminum formwork.
10. The aluminum mold installation method according to claim 6, characterized in that: The reinforcement scheme also includes, in step S7, pre-embedding reinforcement steel bars before pouring concrete for each layer, for the oblique support reinforcement of the next layer of wall columns.
Citation Information
Patent Citations
Aluminum alloy formwork construction method applied to fabricated engineering
CN111946050A
Integrated aluminum mold molding method
CN111962857A
Aluminum alloy formwork construction method for variable-story-height building
CN112196257A
Fabricated building aluminum alloy formwork construction technology
CN112854745A
Composite floor slab construction method based on aluminum alloy formwork support
CN113719116A
Cited By
Fabricated laminated slab construction method
CN119266560A
Supporting structure capable of adjusting alignment after placement of laminated slabs
CN223634407U