Tunnel grating steel frame modular integration and rapid and accurate installation technology thereof

By processing large-size steel mesh sheets and completing modular integration in steel structure processing plants, combined with an improved arch installation machine and a 7-point laser positioning tool, the problem of poor installation accuracy of the grille steel frame was solved and the tunnel grille was realized. The rapid and precise installation of steel frames improves construction quality and efficiency.

CN118728443AActive Publication Date: 2024-10-01CHINA TIESIJU CIVIL ENGINEERING GROUP CO LTD +1
View PDF 9 Cites 0 Cited by

Patent Information

Application Number
CN202410701952.X
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-05-31
Publication Date
2024-10-01
Estimated Expiration
2044-05-31

AI Technical Summary

Technical Problem

During the installation process, the grid steel frame is highly flexible and easy to deform, resulting in poor installation accuracy and low efficiency, which limits the application of the arch installation machine in the construction of the grid steel frame.

Method used

By processing large-sized steel mesh sheets, adding differentiated spacing control gear discs, adjusting the blanking length, realizing the control size of the modular integrated unit, and completing the integration of steel mesh sheets, steel frames and connecting bars in the steel structure processing plant Integrated welding, using an improved arch installation machine and 7-point laser positioning tooling to ensure precise installation.

Benefits of technology

It improves the installation accuracy, reduces material waste and on-site operation complexity, reduces construction risks, realizes rapid and accurate installation of tunnel grid steel frames, improves construction quality and efficiency, and reduces costs.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118728443A_ABST
    Figure CN118728443A_ABST
Patent Text Reader

Abstract

The invention relates to the technical field of tunnel steel frame installation, in particular to a tunnel grating steel frame modular integration and rapid and accurate installation technology which comprises the following steps that large-specification steel bar meshes are machined, differential spacing control fluted discs are increased, a steel bar mesh bearing platform is lengthened, and the blanking length is adjusted; the production spacing difference and the modular integration of the reinforcing mesh with the size controlled by the unit are realized; the grid steel frame is reasonably divided into sections, each section does not exceed 9 m, integrated welding of the reinforcing meshes, the steel frame and the connecting ribs of the matched sizes is completed in a steel structure machining factory, and through machining of the large-specification reinforcing meshes, material waste is reduced, and production efficiency and economic benefits are improved. And secondly, due to the design of the modular integration unit, the steel frame, the reinforcing mesh and the connecting ribs can be integrated in a factory, the complexity and time of field operation are reduced, and meanwhile the construction risk is reduced.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of tunnel steel frame installation, and in particular to a tunnel grid steel frame modular integration and rapid and accurate installation technology. Background Art

[0002] With the rapid development of transportation construction such as high-speed railways and highways in my country, the number of tunnels is increasing and the scale of construction is getting larger and larger. As one of the most basic methods for tunnel construction, the New Austrian Tunneling Method is the most widely used. Its characteristics make full use of the self-bearing capacity of the surrounding rock and the spatial constraint of the excavation surface, and use anchor rods and shotcrete as the main support means. In the construction of tunnel anchor spraying support, the steel arch frame hanging mesh anchor spraying support type is mainly used for the surrounding rock of grade IV and grade V. The steel arch frame is divided into two forms: grid steel arch frame and steel arch frame. When the surrounding rock is relatively good (less landslides and relatively less backfill concrete), the grid arch frame is used; when the surrounding rock is relatively poor (when encountering large landslides, backfilling with large amounts of shotcrete, and the need for steel arch frame to increase the bearing capacity in the early stage is large), the steel arch frame is used.

[0003] In my country, traditional arch frame installation and construction mainly adopts excavation scaffolding to assist manual construction. Arch frames, meshes, and connecting bars are all scattered, and each segment unit needs to be assembled on site in fragments. Because this installation method requires a large number of construction personnel, high labor intensity, low operating efficiency, and high construction risks. Therefore, arch frame installation machines are becoming more and more widely used. The steel arch frame has large mass, high hardness, and relatively large rigidity. The use of arch frame installation machines in the installation and construction of steel arch frames can effectively improve the operating efficiency and installation accuracy. However, because the grid steel frame is highly flexible and easy to deform, the installation accuracy and installation efficiency are low during the use of the steel frame installation frame. When the arch frame installation machine installs the grid arch frame, it is easy to deform the grid arch frame, thereby restricting the application of the arch frame installation machine in the construction of the grid steel frame. In order to solve the above problems, China Railway Fourth Bureau has carried out research on the modular integrated rapid and precise installation method of the grid steel frame to ensure that the arch frame installation is accurate, stable, and fast, so as to achieve the goals of high quality, economy, and efficiency. Summary of the invention

[0004] The present invention is proposed in view of the problems in the above or prior art that the grid steel frame is highly flexible and easily deformed, and the installation accuracy and efficiency are poor during the use of the steel frame installation frame. The grid arch frame is easily deformed when the arch frame installation machine installs the grid arch frame, thereby restricting the application of the arch frame installation machine in the grid steel frame construction.

[0005] Therefore, the object of the present invention is to provide a tunnel grid steel frame modular integration and rapid and accurate installation technology.

[0006] In order to solve the above technical problems, the present invention provides the following technical solutions: comprising the following steps, processing large-size steel meshes, by adding differentiated spacing control toothed discs, lengthening the steel mesh receiving platform, and adjusting the cutting length, so as to realize the production of steel meshes with differentiated spacing and modular integrated unit controlled size; the grid steel frame is reasonably divided into sections, each section not exceeding 9m, and the integrated welding of matching size steel meshes, steel frames and connecting bars is completed in the steel structure processing plant.

[0007] As a preferred solution for the modular integrated rapid and precise installation technology of the tunnel grid steel frame of the present invention, the processing of the large-size steel mesh further includes the requirement that the overlap length of two meshes must be no less than one grid.

[0008] As a preferred solution of the modular integrated rapid and accurate installation technology of the tunnel grid steel frame of the present invention, the modular integrated unit is completed in a steel structure processing plant to reduce the overlap loss of steel mesh and connecting bars and optimize the on-site assembly process.

[0009] As a preferred solution of the modular integrated rapid and precise installation technology of the tunnel grid steel frame of the present invention, a transverse lifting beam is improved and installed on the forearm below the grabbing head of the two side arms of the arch frame installation machine, and a bearing rotating hook is installed on the grabbing head side.

[0010] As a preferred solution of the modular integrated rapid and precise installation technology of the tunnel grid steel frame of the present invention, a bolt clip-on tooling and a laser pen are installed on the formed grid steel frame to form a 7-point laser positioning.

[0011] As a preferred solution of the modular integrated rapid and precise installation technology of the tunnel grid steel frame of the present invention, it includes the following steps: completing the modular integrated grid steel frame in the steel structure processing plant; installing the seven-point laser positioning tooling; using the total station to lay out the laser positioning points; installing the grid steel frame modular units in sequence from top to bottom; welding the connecting ribs with the front loop; setting the locking feet and welding; and retracting the 7-point laser positioning.

[0012] As a preferred solution of the modular integrated rapid and accurate installation technology of the tunnel grid steel frame of the present invention, the following steps are performed: strengthening the accuracy review of the erection frame; retesting the installation accuracy of the last steel frame in each cycle; cleaning the loose slag at the arch foot and padding it with concrete pads.

[0013] As a preferred solution of the modular integrated rapid and accurate installation technology of the tunnel grid steel frame of the present invention, the following steps are performed: digging drainage ditches to timely pump out accumulated water; and adhering to the tunnel construction principles.

[0014] As a preferred solution of the modular integrated rapid and accurate installation technology of the tunnel grid steel frame of the present invention, the processing accuracy of the steel frame of the steel structure factory is reviewed every week and corrected in time.

[0015] As a preferred solution of the modular integrated rapid and accurate installation technology of the tunnel grid steel frame of the present invention, the modular steel frame units are transported by a truck crane, deformation caused by violent loading and unloading is prohibited, and the steel frame protection is strengthened to prevent rust.

[0016] The beneficial effects of the modular integrated rapid and precise installation technology of the tunnel grid steel frame of the present invention are as follows: through the processing of large-size steel mesh, not only the material waste is reduced, but also the production efficiency and economic benefits are improved. Secondly, the design of the modular integrated unit allows the steel frame, steel mesh and connecting ribs to be integrated in the factory, reducing the complexity and time of on-site operations, while reducing construction risks. In addition, the application of modified lifting beams and bearing rotating hooks optimizes the installation method of the arch frame, avoids the deformation of the grid steel frame, and improves the installation accuracy. The use of the 7-point laser positioning tooling of the bolt-on arch frame further improves the accuracy of the frame and ensures the construction quality. Overall, this technology realizes the rapid and precise installation of the tunnel grid steel frame, which not only speeds up the construction progress, but also improves the construction quality and reduces the construction cost, providing an efficient and reliable solution for the modern construction of tunnel projects. BRIEF DESCRIPTION OF THE DRAWINGS

[0017] In order to more clearly illustrate the technical solutions of the embodiments of the present invention, the accompanying drawings required for use in the description of the embodiments will be briefly introduced below. Obviously, the accompanying drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other accompanying drawings can be obtained based on these accompanying drawings without paying creative work.

[0018] Figure 1 Schematic diagram of seven-point laser positioning

[0019] Figure 2 Process flow chart for fast and accurate installation of grid steel frame modular integration

[0020] Figure 3 Schematic diagram for fast and accurate installation of modular integration of grid steel frame

[0021] Figure 4 Schematic diagram for laser positioning

[0022] Figure 5 This is a schematic diagram of locking pin welding. DETAILED DESCRIPTION

[0023] In order to make the above-mentioned objects, features and advantages of the present invention more obvious and easy to understand, the specific implementation methods of the present invention are described in detail below in conjunction with the accompanying drawings.

[0024] In the following description, many specific details are set forth to facilitate a full understanding of the present invention, but the present invention may also be implemented in other ways different from those described herein, and those skilled in the art may make similar generalizations without violating the connotation of the present invention. Therefore, the present invention is not limited to the specific embodiments disclosed below.

[0025] Secondly, the term "one embodiment" or "embodiment" as used herein refers to a specific feature, structure, or characteristic that may be included in at least one implementation of the present invention. The term "in one embodiment" that appears in different places in this specification does not necessarily refer to the same embodiment, nor does it refer to a separate or selective embodiment that is mutually exclusive with other embodiments.

[0026] Example 1, reference Figures 1 to 5 , which is the first embodiment of the present invention, provides a modular integration of a tunnel grid steel frame and its rapid and precise installation technology. First, a differentiated spacing control toothed disc is set in the steel structure processing plant to adjust the spacing of the steel mesh to meet the needs of different tunnel sections. Then, the processing flow of the steel mesh is optimized by lengthening the steel mesh receiving platform. By adjusting the cutting length, ensure that the size of the steel mesh matches the modular integrated unit. During the processing, pay special attention to the overlap length of the two meshes to ensure that it is not less than one grid to reduce material waste and improve work efficiency.

[0027] Example 2, reference Figures 1 to 5 , which is the second embodiment of the present invention. In this embodiment, the grid steel frame is reasonably divided into sections, and the length of each section is controlled between 4-5 meters to avoid deformation during transportation due to excessive weight of a single section. In the steel structure processing plant, multiple steel frames are modularly integrated for each segment to complete the integrated welding of matching-sized steel mesh, steel frames and connecting bars. During the welding process, appropriate exposed and overlapping parts are reserved to facilitate rapid installation on site. The completed modular units are transported to the tunnel construction site by a truck crane and stacked using brackets to prevent deformation caused by chaotic stacking of modules.

[0028] Example 3, reference Figures 1 to 5, which is the third embodiment of the present invention. Different from the previous embodiment, this embodiment provides a modular integrated rapid and precise installation technology for tunnel grid steel frames. In this embodiment, firstly, bolt clip-on tooling and laser pen are installed on the grid steel frame that has been formed in the upper cycle, and the positions are respectively positioned at the main arch, 10 cm on the arch waist connecting plate, 10 cm on the side wall connecting plate, and 70 cm on the arch foot. Use the total station to release the laser layout points according to the cross-section of the steel frame, and fix the laser pen. Use the 7-point laser positioning as the reference benchmark for the frame erection, and perform real-time precise control and adjustment of the steel frame to ensure accurate erection. Subsequently, the grid steel frame modular units are installed from top to bottom, starting from the arch module and symmetrically installed downwards, and the bolt connections are installed in sequence. After the arch foot module is installed, the steel frame is precisely positioned and all bolts are tightened to complete the one-time splicing of multiple grid steel frames.

[0029] Importantly, it should be noted that the construction and arrangement of the present application shown in a plurality of different exemplary embodiments are only exemplary. Although only a few embodiments are described in detail in this disclosure, it should be readily understood by those who refer to this disclosure that many modifications are possible (e.g., the size, scale, structure, shape and proportion of various elements, and parameter values ​​(e.g., temperature, pressure, etc.), installation arrangement, use of materials, color, directional changes, etc.) without substantially departing from the novel teachings and advantages of the subject matter described in the application. For example, the element shown as integrally formed can be composed of multiple parts or elements, the position of the element can be inverted or otherwise changed, and the nature or number or position of the discrete element can be changed or changed. Therefore, all such modifications are intended to be included in the scope of the present invention. The order or sequence of any process or method steps can be changed or reordered according to alternative embodiments. In the claims, any "device plus function" clause is intended to cover the structure of performing the function described herein, and is not only structurally equivalent but also equivalent structure. Without departing from the scope of the present invention, other replacements, modifications, changes and omissions can be made in the design, operating conditions and arrangement of the exemplary embodiments. Therefore, the invention is not limited to a specific embodiment, but extends to numerous modifications still falling within the scope of the appended claims.

[0030] Additionally, in order to provide a concise description of exemplary embodiments, all features of an actual embodiment (ie, those features that are not relevant to the best mode presently contemplated for carrying out the invention or those that are not relevant to implementing the invention) may not be described.

[0031] It will be appreciated that in the development of any actual implementation, as in any engineering or design project, numerous implementation-specific decisions may be made. Such a development effort may be complex and time-consuming, but will be a routine task of design, fabrication, and production for those of ordinary skill having the benefit of this disclosure without undue experimentation.

[0032] It should be noted that the above embodiments are only used to illustrate the technical solutions of the present invention rather than to limit it. Although the present invention has been described in detail with reference to the preferred embodiments, those skilled in the art should understand that the technical solutions of the present invention may be modified or replaced by equivalents without departing from the spirit and scope of the technical solutions of the present invention, which should all be included in the scope of the claims of the present invention.

Claims

1. A tunnel grid steel frame modular integration and rapid and accurate installation technology, characterized by: The following steps are involved: Processing large-size steel mesh, by adding differentiated spacing control toothed discs, lengthening the steel mesh receiving platform, and adjusting the material cutting length, to achieve production of steel mesh with differentiated spacing and modular integrated unit controlled size; The grid steel frame is reasonably divided into sections, with each section not exceeding 9m, and the integrated welding of matching size steel mesh, steel frame and connecting bars is completed in the steel structure processing plant.

2. A tunnel grid steel frame modular integrated rapid and accurate installation technology as claimed in claim 1, characterized in that The processing of the large-size steel mesh further includes the requirement that the overlap length of two meshes must be no less than one mesh.

3. A tunnel grid steel frame modular integrated rapid and accurate installation technology as claimed in claim 1, characterized in that The modular integrated unit is completed in a steel structure processing plant to reduce the overlap loss of steel mesh and connecting bars and optimize the on-site assembly process.

4. A modified lifting beam used in the modular integration of tunnel grid steel frame and its rapid and accurate installation technology, characterized in that A transverse lifting beam is improved and installed on the small arm below the grabbing head of the two side arms of the arch frame installation machine, and a bearing rotating hook is installed on the grabbing head side.

5. A bolt-clip arch frame 7-point laser positioning tool used in the modular integration of tunnel grid steel frame and its rapid and accurate installation technology, characterized in that Install bolt-on fixtures and laser pen on the formed grid steel frame to form 7-point laser positioning.

6. A modular integrated rapid and accurate installation process for tunnel grid steel frames, characterized in that The following steps are involved: Complete modular integrated grid steel frame in the steel structure processing plant; Install the seven-point laser positioning tooling; Use a total station to stake out laser positioning points; Install the grid steel frame modular units sequentially from top to bottom; Weld the connecting ribs to the front loop; Set the locking pins and weld them; Retract the 7-point laser positioning.

7. A quality control measure in the modular integration of tunnel grid steel frame and its rapid and accurate installation technology, characterized in that include: Strengthen the review of the accuracy of the stand; Re-test the installation accuracy of the last steel frame in each cycle; Clean the loose debris at the arch foot and fill it with concrete pads.

8. A quality control measure as claimed in claim 7, characterized in that Further including: Dig drainage ditches and pump out the accumulated water in time; Adhere to the principles of tunnel construction.

9. A quality control measure in the modular integration of tunnel grid steel frame and its rapid and accurate installation technology, characterized in that The steel frame processing accuracy of the steel structure factory is reviewed weekly and corrections are made in a timely manner.

10. A quality control measure in the modular integration of tunnel grid steel frame and its rapid and accurate installation technology, characterized in that Modular steel frame units are transported using a truck-mounted crane. Violent loading and unloading that may cause deformation is prohibited, and steel frame protection is strengthened to prevent rust.

Citation Information

Patent Citations

  • Installation construction method of tunnel arch frame

    CN103470274A

  • Steel grating assisted diversion tunnel preliminary bracing structure and method

    CN105781593A

  • Mounting method of tunnel arch

    CN106761854A

  • Two-layer primary support construction method based on small-distance tunnel

    CN110847932A

  • Segmented integrated casting tunnel steel arch frame structure and supporting method thereof

    CN111456767A