Construction technology of clean operating room purification air-conditioning system
Through the systematic construction technology of clean operating room purification air-conditioning system, the problems of construction complexity and unstable quality are solved, efficient construction process and high-quality purification effect are achieved, and the safety of the medical environment is improved.
Patent Information
- Application Number
- CN202410765941.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-06-14
- Publication Date
- 2024-10-01
AI Technical Summary
The construction of the purification air conditioning system in clean operating rooms is complex and lacks unified construction operation regulations, resulting in unstable construction quality and long construction period, which affects the safety of the medical environment.
Provide a construction technology for clean operating room purification air conditioning system, including air duct production, detection and installation, static pressure box installation, functional unit installation, decoration and effect testing, and ensure construction quality through strict quality control standards.
It improves the operability and production efficiency of construction, saves disinfection and dust removal costs, improves the cleanliness level of the medical engineering purification area, simplifies the construction process, and reduces the construction period.
Smart Images

Figure CN118729432A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of construction of air conditioning systems in medical purification areas, and in particular to a construction process of a purification air conditioning system in a clean operating room. Background Art
[0002] With the development of medical technology and the continuous improvement of people's demand for medical conditions, the cleanliness requirements for medical operating rooms are also getting higher and higher. One of the main means to solve the cleanliness of operating rooms is to equip the operating room with a good air treatment system (i.e., purification air conditioning system). Clean operating rooms usually use a circulating air plus fresh air supply method. This method collects the air in the operating room, mixes it with the treated fresh air, and then returns it to the operating room after wet heat treatment to achieve air recycling.
[0003] The design and construction of clean operating rooms are an important part of hospital buildings, and the clean operating room purification and air conditioning system is one of the key projects. With the continuous improvement of the medical technology system, higher requirements are also put forward for the safety of the medical environment. The rational design of the clean operating room purification and air conditioning system can effectively reduce cross infection during surgery and avoid postoperative sequelae in patients. By sorting out the key points of construction quality control of the purification and air conditioning system and improving the reliability of construction results, it plays an important role in improving the working environment of medical staff and the treatment environment of patients. However, due to the high construction complexity and the lack of unified construction operation regulations during the construction of the clean operating room purification and air conditioning system, the construction quality is greatly affected by the sense of responsibility of the construction personnel, the quality is unstable, and the construction period is long. Summary of the invention
[0004] In view of the above-mentioned prior art, the purpose of the present invention is to provide a construction process for a clean operating room purification air conditioning system.
[0005] To achieve the above object, the present invention adopts the following technical solution:
[0006] A first aspect of the present invention provides a construction process for providing a clean operating room purification air conditioning system, comprising the following steps:
[0007] Step 1: Production, inspection and installation of air ducts:
[0008] Step 101, clean the plate, use a joint angle bite to form the bite seam of the air duct, and connect the air duct with the flange;
[0009] Step 102, check whether the air duct has light leakage, and the air duct that has no light leakage can be installed;
[0010] Step 103: installing the air duct;
[0011] Step 2: Static pressure box installation:
[0012] The four corners of the static pressure box are hoisted in the center of the operating room. The length of the static pressure box should be consistent with the length of the operating table. The static pressure box and the air supply duct should be connected with a flexible joint. After the static pressure box is hoisted and connected to the air duct, it should be sealed.
[0013] Step 3: Installation of functional units. Functional units include circulation units and fresh air units. Circulation units include filtration and disinfection units. The specific installation steps are as follows:
[0014] Step 301: Before installing the fresh air unit, check whether the configuration of each section of the unit is consistent with the design. The floor of the equipment room of the fresh air unit should be waterproofed and equipped with a condensate discharge port;
[0015] Step 302, the filtration and disinfection unit is set in the ceiling, and the foundation platform is welded with No. 12 channel steel. The foundation should be flat, without distortion, and the flatness should not be greater than 2mm / 2m. Spring shock absorbers must be installed on the hanging rods. The four corners of the filtration and disinfection unit should be limited by angle steel blocks. All foundations must be treated with anti-corrosion after welding;
[0016] Step 303, the fresh air unit includes a deep pretreatment unit, a filter unit and a fresh air preliminary pretreatment unit, and the filter unit includes a primary filter, a medium filter and a high efficiency filter; before installing the high efficiency filter, the system fresh air preliminary pretreatment unit and the system deep pretreatment unit should be installed and operational; the air duct should be installed after air blowing for 10-14 hours, and the filter unit should be cleaned and installed after the air blowing is completed;
[0017] Step 4: Decoration and final construction:
[0018] Carry out decoration construction on the clean operating room, install air supply and exhaust louvers, and use aluminum alloy louvers with medium-efficiency filters;
[0019] Step 5: Installation effect test, including wind speed and volume test, high-efficiency filter leak detection, interval pressure difference test, cleanliness test, temperature and humidity test and noise test.
[0020] Furthermore, in step 103, when the air duct is installed, the tightening torque of each bolt on the flange should be consistent and tightened symmetrically and gradually, and the flange bolts should face the direction of air flow.
[0021] Furthermore, when installing the air duct, the flexible short tube should be installed without distortion, and the flexible short tube installed in the negative pressure section should be in a taut state. The length is generally 150-300mm. The flexible short tube must not be used as a connecting tube or reducer for leveling and alignment. The flexible short tube should be made of double-layer material, and the inner and outer surfaces should be smooth.
[0022] Furthermore, when the air duct passes through fire-proof, explosion-proof walls or floor partitions, a pre-buried pipe or protective sleeve should be installed. The thickness of the steel plate of the pre-buried pipe or protective sleeve should not be less than 1.6mm. The gap between the air duct and the sleeve should be sealed with non-combustible flexible material and then sealed with sealant. The surface should finally be decorated.
[0023] Furthermore, in step 2, when the static pressure box is hoisted, the height difference of the four corners is no more than 2 mm.
[0024] Further, in step 5, the wind speed and air volume test includes the following steps:
[0025] Step 501: First, use a hot-bulb anemometer to confirm that the wind speed and air volume of the air outlet of the high-efficiency filter in each area meet the requirements, and the air outlet of each air outlet in the interval is uniform;
[0026] Step 502: The measuring point of the operating area of the Class I clean operating room and the Class I clean auxiliary room is the cross-sectional wind speed and speed unevenness of the working surface 1.2m above the ground. The average wind speed in the working area is 0.2-0.25m / s, and the speed unevenness should be less than or equal to 0.24.
[0027] Step 503, the measuring point range should be the area within 0.12m of the boundary of the concentrated cover projection area, evenly distributed, and the measuring point plane layout measuring point height is 1.2m from the ground, there should be no operating table or work surface blocking, the measuring point spacing should not be greater than 0.3m, and the arithmetic mean of the wind speed readings at all measuring points is taken as the average wind speed.
[0028] Further, in step 5, the high efficiency filter leak detection includes the following steps:
[0029] Remove the diffuser plate and scan the seals of the entire high-efficiency filter, the filter and the frame, the frames and the frame and the high-efficiency static pressure box; when scanning, the sampling head is about 2 to 3 cm away from the filter surface of the high-efficiency filter, and the scanning speed does not exceed 5 cm / s; the scan is carried out back and forth in a straight line, and the lines should overlap; if there is an alarm during the detection process, indicating a leak, the leak should be plugged with silicone or tightened before scanning and inspection.
[0030] Furthermore, when checking for leaks on a high-efficiency filter, its leakage rate should be less than or equal to 0.01%. If the leakage rate at all points on the high-efficiency filter does not exceed 0.01% during the test, it is qualified. If one point is judged to be unqualified, that point should be marked and needs to be repaired or replaced. Special glue is allowed to be used to repair the leakage of the filter material of the high-efficiency filter, but the area of a single leakage point cannot be greater than 1% of the total area, and the area of all leakage points cannot be greater than 5% of the total area.
[0031] Preferably, in step 5, the interval pressure difference test includes the following steps:
[0032] According to the design value of pressure difference in each room, adjust the opening degree and response speed of each indoor return air valve, so that the pressure difference of each indoor area is maintained within the design range; during the test, the air conditioning system operates normally, and the air volume of the air supply outlet is balanced; the exhaust system operates normally, and the air volume of the exhaust outlet is balanced; use a micro differential pressure gauge or a digital micro differential pressure gauge to measure the pressure difference relative to atmospheric pressure at one point in each independent area;
[0033] The static pressure difference should be measured when the doors of all rooms are closed. When there is exhaust, it should be carried out under the condition of maximum exhaust volume, and the pressure difference of adjacent connected rooms should be measured from the innermost room on the plane to the outside in sequence until the pressure difference between the clean area and the non-clean area and the outdoor environment is measured. For unidirectional flow clean rooms with cleanliness level 5 or better, the height of the indoor working surface 0.6m away from the door should also be measured when the door is open. For clean rooms with non-closable openings that connect to adjacent rooms, the flow rate and direction at the openings should also be measured.
[0034] Preferably, in step 5, the cleanliness test includes the following steps:
[0035] When using a dust particle counter for sampling testing, there should be no less than 3 sampling points in each controlled environment; the sampling points should be evenly distributed throughout the clean room and located at the height of the work area. When the work area is distributed at different heights, more than one measurement surface should be set; when measuring unidirectional flow, the sampling head should be aligned with the airflow; when measuring non-unidirectional flow, the sampling head should always be upward;
[0036] When the air supply outlets are arranged in a centralized manner, the operating area and the surrounding areas shall be inspected separately; the minimum sampling volume of the particle counter each time shall be 8.6L in the Level 5 area and 2.83L in the areas below; the measuring points shall be arranged on a plane 0.8m above the ground; there shall be no operating table when inspecting the operating area; when the operating table is fixed, the measuring point on the table shall be 0.25m above the table; when inspecting in the Level 5 area, the sampling port shall face the direction of the airflow; when inspecting in areas of other levels, the sampling ports shall all face upward; when inspecting the dust concentration, all operating room lights except the shadowless lamp shall be turned on.
[0037] Preferably, in step 5, the temperature and humidity test includes the following steps:
[0038] During the test, the air conditioning unit operates normally for at least 12 hours; the air volume at the supply and exhaust outlets is adjusted to within the design requirements; the air conditioning water system is debugged and the cold and heat sources can meet the supply; the automatic control system (design temperature and humidity part) is adjusted and the system is set according to the temperature and humidity design parameters of each room; after the system starts automatic control, observe the actual control effect, and if there is any abnormal situation, adjust the system in time to ensure that the system reaches the best control state.
[0039] The instantaneous measurement value of temperature and humidity, the instrument display value is the measurement value of the measuring point, the measuring point is arranged at the same height of more than 0.5m from the outer wall surface and 0.8m from the ground, the room area is 50m 2 Measure 5 points within the room; each increase of 20 to 50m 2 Add 3 to 5 measuring points; the maximum value of each temperature deviation from the control point reached by more than 90% of the measuring points is the room temperature fluctuation range of the room, which should not exceed the design requirements; the deviation value between the average temperature of each measuring point and the lowest or highest temperature of each measuring point reached by more than 90% of the measuring points is the regional temperature difference of the room, which should not exceed the design requirements.
[0040] Preferably, in step 5, the noise test includes the following steps:
[0041] Use a sound level meter to measure directly. The minimum scale of the sound level meter should not be lower than 0.2dB. The instrument display value is the measured value of the measuring point. There should be no reflective objects within 1m of the measuring point. The test height is 1.1m from the ground and the area is 15m 2 For clean rooms below 15m, only the center point can be measured. 2 In addition to the central point, the above clean rooms should also measure 4 diagonal points, each 1m away from the side wall, and the measuring points should be directed toward each corner. When it is a mixed flow clean room, the noise in the unidirectional flow area and non-unidirectional flow area should be measured separately.
[0042] Beneficial effects of the present invention:
[0043] The construction process of the present invention adopts prefabricated construction, the construction process is easy to operate, the production efficiency is high, the cost of manual disinfection and dust removal is saved, the cleanliness level of the medical engineering purification area is improved, and it has broad promotion and application prospects in the construction of medical engineering purification areas. BRIEF DESCRIPTION OF THE DRAWINGS
[0044] Figure 1 : A schematic diagram of a clean operating room purification air conditioning system of the present invention;
[0045] Figure 2 : Construction process flow chart of the clean operating room purification air conditioning system of the present invention;
[0046] Figure 3 : Schematic diagram of air duct light leakage detection of the present invention. DETAILED DESCRIPTION
[0047] It should be noted that the following detailed descriptions are illustrative and are intended to provide further explanation of the present application. Unless otherwise specified, all technical and scientific terms used herein have the same meanings as those commonly understood by those skilled in the art to which the present application belongs.
[0048] In order to enable those skilled in the art to more clearly understand the technical solution of the present application, the technical solution of the present application will be described in detail below in conjunction with specific embodiments.
[0049] The test materials used in the examples of the present invention are all conventional test materials in the art and can be purchased through commercial channels.
[0050] The construction process quality control standards of the clean operating room purification air conditioning system of the present invention are GB50333-2013: Technical Specifications for Hospital Clean Operating Room Construction and GB50243-2016: Ventilation and Air Conditioning Engineering Construction Quality Acceptance Specifications.
[0051] Example: Construction technology of clean operating room purification air conditioning system
[0052] Step 1: Production, inspection and installation of air ducts:
[0053] Step 101. There should be a dedicated site for the production of air ducts. The site should be clean and preferably closed. Construction workers should wear clean work clothes and soft work shoes. When making roll plates or flat plates, non-toxic neutral cleaning liquid should be applied and the surface should be cleaned with clean water. There should be no coating powdering phenomenon. Non-oiled plates can be washed with warm water at about 40°C. After drying, they should be wiped clean with long-filament white textile materials that do not lose fibers. The forming bite seam of the rectangular air duct adopts a joint angle bite, and the bite seam is sealed with glue. When the air duct is connected to the angle iron flange, the air duct flange should be flat and close to the flange. The width should not be less than 7mm, and the overlapping part should be cut off. The cracks and holes at the flange should be coated with sealant.
[0054] Step 102: Check if the air duct is leaking. If it is not leaking, you can install it. The specific detection method is as follows: Figure 3 shown.
[0055] Step 103: Air duct installation:
[0056] The tightening torque of each bolt on the flange should be consistent in size, and should be tightened symmetrically and gradually. There should be no uneven tightening after installation; the flange bolts should face the direction of air flow. The installation of the flexible short pipe should be moderately tight and without distortion. The flexible short pipe installed in the negative pressure section should be in a taut state and should not be flattened. The length is generally 150-300mm. The flexible short pipe shall not be used as a connecting pipe or reducer for leveling and alignment. The flexible short pipe should be made of double-layer material, and the inner and outer surfaces should be smooth. When the air duct passes through fireproof, explosion-proof walls or floor partitions, a pre-buried pipe or protective sleeve should be installed. The thickness of the steel plate of the pre-buried pipe or protective sleeve should not be less than 1.6mm. The gap between the air duct and the sleeve should be sealed with harmless non-combustible flexible materials, and then sealed with sealant. The surface should be decorated at last.
[0057] Step 2: Static pressure box installation:
[0058] The four corners of the static pressure box are hoisted in the center of the operating room, using hanging rod spring washers and double nuts for hoisting. The height difference of the four corners is no more than 2mm. The length direction of the static pressure box should be consistent with the length direction of the operating bed. The connection between the static pressure box and the air supply duct should be flexible. The outer surface of the static pressure box and the inner surface of the inspection hole of the shadowless lamp must be insulated. When installing the top plate of the operating room, the static pressure box should be lifted as a whole to avoid affecting the top plate welding. After the static pressure box is hoisted and connected to the air duct, it should be sealed.
[0059] Step 3: Installation of functional units. Functional units include circulation units and fresh air units. Circulation units include filtration and disinfection units. The specific installation steps are as follows:
[0060] Step 301: Before installing the fresh air unit, check whether the configuration of each section of the unit is consistent with the design. The floor of the equipment room of the fresh air unit should be waterproofed and equipped with a condensate discharge port;
[0061] Step 302, the filtration and disinfection unit is installed in the suspended ceiling. The basic platform is welded with No. 12 channel steel. The foundation should be flat, without distortion, and the flatness should not be greater than 2mm / 2m. Spring shock absorbers must be installed on the suspension rods. The four corners of the filtration and disinfection unit should have limited angle steel blocks. All foundations must be treated with anti-corrosion after welding; a certain amount of maintenance and maintenance space should be reserved for the air-conditioning equipment in the suspended ceiling. An inspection port for easy access of personnel should be set near the suspended ceiling outside the clean room, and lighting facilities should be provided; the suspended ceiling with air-conditioning equipment should not be directly connected to the outdoors;
[0062] Step 303, the fresh air unit includes a deep pretreatment unit, a filtering unit and a fresh air preliminary pretreatment unit, and the filtering unit includes a primary filter, a medium filter and a high efficiency filter; before installing the high efficiency filter, the system fresh air preliminary pretreatment unit and the system deep pretreatment unit should be installed and operational; the installation space and air duct of the clean room air conditioning equipment should be thoroughly cleaned, and the air duct should be air-blown for 12 hours before installation; after the air blowing is completed, the clean room should be cleaned and wiped again, and then the sub-high efficiency filter or high efficiency filter should be installed immediately, and sealant should not be directly applied between the frame and the frame of the high efficiency filter;
[0063] Step 4: Decoration and final construction:
[0064] Carry out decoration construction on the clean operating room, install air supply and exhaust louvers, and use aluminum alloy louvers with medium-efficiency filters;
[0065] Step 5: Installation effect test, including wind speed and volume test, HEPA filter leak detection, interval pressure difference test, cleanliness test, temperature and humidity test and noise test:
[0066] 1. The wind speed and air volume test includes the following steps:
[0067] Step 501: First, use a hot-bulb anemometer to confirm that the wind speed and air volume of the high-efficiency filter outlets in each area meet the requirements, and the air outlets in the area are uniform; ensure that the air supply volume in the clean room is sufficient to dilute, replace or eliminate the pollution generated in the room.
[0068] Step 502: The measuring point of the operating area of the Class I clean operating room and the Class I clean auxiliary room is the cross-sectional wind speed and speed unevenness of the working surface 1.2m above the ground. The average wind speed in the working area is 0.2-0.25m / s, and the speed unevenness should be less than or equal to 0.24.
[0069] Step 503, the measuring point range should be the area within 0.12m of the boundary of the central air supply cover projection area, evenly distributed, the measuring point plane layout measuring point height 1.2m from the ground, there should be no operating table or work surface obstruction, the measuring point spacing should not be greater than 0.3m, and the arithmetic mean of the wind speed readings at all measuring points is taken as the average wind speed; the minimum resolution of the detection instrument should be able to reach 0.01m / s, the instrument measuring rod should be fixed in position and should not be handheld. The detection time for each point should not be less than 5s, record once per second, and take the average value. For the average wind speed of the air supply cover in Class II to Class IV clean operating rooms, the measuring point height should be within 0.1m below the air supply surface, and the distance between measuring points should not exceed 0.3m; the outermost measuring point of the air supply surface speed measurement point section layout should be 0.05m within the boundary of the air supply port, and the points should be evenly distributed. The wind speed range of each point on the air supply cover should be between 0.1 and 0.4m / s, and there should be no blind area with no speed. After reaching the wind speed conditions at the above points, the ventilation frequency should be calculated according to the following formula. The ventilation frequency test result should not be less than the specification, and should not exceed 15% of the design value. For the dispersed air supply outlets of Class IV clean operating rooms and clean auxiliary rooms, the ventilation frequency should be calculated by testing the air volume of the air supply outlets. The air volume hood should be used to cover the air supply outlets and directly read the displayed value, which should not exceed 15% of the design value.
[0070] 2. High efficiency filter leak detection includes the following steps:
[0071] Use the DOP leak detection method to inspect the high-efficiency filter and its outer frame to ensure that suspended pollutants will not penetrate the filter, the gap between the filter and its outer frame, or other parts of the filter device and invade the room;
[0072] Leak detection steps: remove the diffuser plate, scan the seals of the entire high-efficiency filter, the filter and the frame, the frames and the frame and the high-efficiency static pressure box; when scanning, the sampling head is about 2 to 3 cm away from the filter surface of the high-efficiency filter, and the scanning speed does not exceed 5 cm / s; the scanning is carried out back and forth in a straight line, and the lines should overlap; if there is an alarm during the detection process, indicating a leak, the leak should be plugged with silicone or tightened before scanning and inspection. It takes about 5 minutes to check a filter. During the test, you should often confirm that the concentration of upstream aerosol remains between 10 and 50ug / l, and it is generally better to control it at 20ug / l;
[0073] The leakage rate of the high-efficiency filter should be less than or equal to 0.01%. If the leakage rate of all points of the high-efficiency filter does not exceed 0.01% during the inspection, it is qualified. If one point is judged as unqualified, the point should be marked and need to be repaired or replaced. Special glue is allowed to be used to repair the leakage of high-efficiency filter material, but the area of a single leakage point cannot be greater than 1% of the total area, and the area of all leakage points cannot be greater than 5% of the total area.
[0074] 3. The interval pressure difference test includes the following steps:
[0075] According to the design value of pressure difference in each room, adjust the opening degree and response speed of each indoor return air valve, so that the pressure difference of each indoor area is maintained within the design range; during the test, the air conditioning system operates normally, and the air volume of the air supply outlet is balanced; the exhaust system operates normally, and the air volume of the exhaust outlet is balanced; use a micro differential pressure gauge or a digital micro differential pressure gauge to measure the pressure difference relative to atmospheric pressure at one point in each independent area;
[0076] The static pressure difference should be measured when the doors of all rooms are closed. When there is exhaust, it should be measured under the condition of maximum exhaust volume, and the pressure difference of adjacent rooms should be measured from the innermost room on the plane to the outside in turn, until the pressure difference between the clean area and the non-clean area and the outdoor environment is measured. For the one-way flow clean room with cleanliness level 5 or better, the height of the indoor working surface 0.6m away from the door should also be measured when the door is open. For the clean room with an opening that cannot be closed and connected to the adjacent room, the flow rate and flow direction at the opening should also be measured. The pressure difference of each area is kept within the design requirements, the airflow direction and pressure gradient are correct, the air in the clean room flows from the clean area to the area with poor cleanliness, the flow of polluted air reaches the minimum, and the air flow direction at the door and in the indoor building is correct. This ensures that the air between the clean areas does not pollute each other.
[0077] 4. Cleanliness test:
[0078] The cleanliness test is to confirm whether the design and construction effect of the purification air conditioner can meet the cleanliness standard requirements of each area. During the test, the purification air conditioner unit operates normally; the air volume of the air supply and exhaust outlets has been adjusted to the design requirements and is in normal operation; the high-efficiency filter leak detection has been completed and there is no leakage; the pressure difference of each area has been adjusted; the indoor cleaning work has been completed; there shall be no more than 2 testers, and the number of testers may be increased appropriately when the area exceeds 100 square meters and the measurement task needs to be completed quickly; the testers must wear clean clothes, should be on the downwind side of the measurement point and away from the measurement point, move gently and remain still;
[0079] When using a dust particle counter for sampling testing, there should be no less than 3 sampling points in each controlled environment; for clean rooms with a cleanliness level of 5 or better, the number of sampling points should be appropriately increased, and the user (builder) should agree and record it. The sampling points should be evenly distributed throughout the clean room and located at the height of the working area (0.8m from the ground). When the working area is distributed at different heights, there can be more than one measuring surface. The sampling points in a turbulent clean room must not be arranged directly below the air supply outlet. The number of samplings at each point should be sufficient to continuously record three stable similar values, and the average of the three times represents the value at that point. When it is suspected that the on-site test results may exceed the standard, the number of measuring points can be increased. When measuring unidirectional flow, the sampling head should be aligned with the airflow; when measuring non-unidirectional flow, the sampling head should always be facing upward;
[0080] When the air outlets are arranged in a centralized manner, the operating area and the surrounding area should be tested separately. The number and location of the measuring points should comply with the provisions of the left table, and the number of measuring points should be no less than 3 points. When there are significant obstacles nearby, they can be avoided appropriately; they should avoid being directly below the air outlets. When the air outlets are arranged in a dispersed manner, they should be tested uniformly in the whole room according to the above-mentioned content. The measuring points can be evenly distributed, but they should not be arranged directly below the air outlets. The minimum sampling volume of each particle counter sampling should be 8.6L in the level 5 area and 2.83L in the following levels. The measuring points should be arranged on a plane 0.8m above the ground, and there should be no operating table when testing the operating area. When the operating table is fixed, the measuring point on the table should be 0.25m above the table surface, and it should be recorded. When testing in the level 5 area, the sampling port should face the direction of the airflow; when testing in other level areas, the sampling ports should all be upward. When testing the dust concentration, all operating room lights should be turned on except the shadowless lamp.
[0081] 5. Temperature and humidity test:
[0082] Use the handheld thermometer and hygrometer GM1360 to confirm whether the temperature and humidity values in each area of the room meet the requirements. During the test, the air conditioning unit operates normally for at least 12 hours; the air volume at the air supply and exhaust outlets is adjusted to the design requirements; the air conditioning water system is debugged, and the cold and heat sources can meet the supply; the automatic control system (design temperature and humidity part) is adjusted, and the system is set according to the temperature and humidity design parameters of each room; after the system starts automatic control, observe the actual control effect, and if there is any abnormality, the system should be adjusted in time to ensure that the system reaches the best control state.
[0083] The instantaneous measurement value of temperature and humidity, the instrument display value is the measurement value of the measuring point, the measuring point is arranged at the same height of more than 0.5m from the outer wall surface and 0.8m from the ground, the room area is 50m 2 Measure 5 points within the room; each increase of 20 to 50m 2 Add 3 to 5 measuring points; the maximum value of each temperature deviation from the control point reached by more than 90% of the measuring points is the room temperature fluctuation range of the room, which should not exceed the design requirements; the deviation value between the average temperature of each measuring point and the lowest or highest temperature of each measuring point reached by more than 90% of the measuring points is the regional temperature difference of the room, which should not exceed the design requirements.
[0084] 6. The noise test includes the following steps:
[0085] Use the sound level meter TES1350A to confirm whether the noise level in each area of the room meets the requirements. During the test, the air supply and exhaust volumes are balanced and the pressure difference adjustment is completed. This is a static test under the normal operation of the air supply and exhaust systems. The equipment is not turned on during the test, and external human interference is avoided.
[0086] Use a sound level meter to measure directly. The minimum scale of the sound level meter should not be lower than 0.2dB. The instrument display value is the measured value of the measuring point. There should be no reflective objects within 1m of the measuring point. The test height is 1.1m from the ground and the area is 15m 2 For clean rooms below 15m, only the center point can be measured. 2 In addition to the central point, the above clean rooms should also measure 4 diagonal points, each 1m away from the side wall, and the measuring points should be directed toward each corner. When it is a mixed flow clean room, the noise in the unidirectional flow area and non-unidirectional flow area should be measured separately.
[0087] When conditions permit, it is advisable to measure the background noise after the air conditioning purification system stops running. When the difference between the indoor noise and the background noise is less than 10dB, the measuring point value should be corrected; when the difference is (6-9)dB, subtract 1dB, when the difference is (4-5)dB, subtract 2dB, when the difference is 3dB, subtract 3dB; when the difference is less than 3dB, the measured value is invalid.
[0088] Eligibility Criteria:
[0089] Recovery room ≤48dB;
[0090] Class II, III, and IV clean operating rooms: ≤49dB;
[0091] Class I clean operating room and special rooms requiring aseptic operation ≤51dB;
[0092] Clean area corridor ≤52dB;
[0093] Nursing station, pre-anesthesia room, scrub room ≤ 55dB;
[0094] Extracorporeal circulation, sterile dressing room, storage room for unopened instruments, sterile medicines, disposable items and precision instruments, and operating room anteroom ≤ 60dB.
[0095] Application example 1: Phase I project of the new campus of the First Affiliated Hospital of Henan University of Traditional Chinese Medicine:
[0096] Project Overview:
[0097] The first phase of the new campus project of the First Affiliated Hospital of Henan University of Traditional Chinese Medicine has a total construction area of
[0098] 156032.35m 2 The project cost is 519,336,197,820 yuan. The outpatient and medical technology building is for emergency first aid, paid registration, pediatrics, consulting room, pharmacy, ICU, ultrasound, radiology, surgery and other functional areas. The inpatient part is the rehabilitation ward, nursing inpatient ward, etc. The project format is a national tertiary-level A-class Chinese medicine hospital. The construction will start on September 10, 2020 and will be completed on July 19, 2022.
[0099] In terms of material costs, 0.7 tons of chemical disinfection materials were saved, at 3,000 yuan per ton, for a total saving of 2,100 yuan.
[0100] In terms of labor costs, it saved 2 disinfection and dust removal workers (400 yuan / day), a total of 60 shifts, and a total of 48,000 yuan.
[0101] In terms of machinery costs, the rental fee of electrostatic dust removal equipment was saved by 20,000 yuan, and the total cost was saved by 70,100 yuan.
[0102] Application example 2: Laboratory of the Emergency Comprehensive Building of Qilu Hospital of Shandong University (Section 1)
[0103] Project Overview:
[0104] Shandong University Qilu Hospital Emergency Comprehensive Building Laboratory (Section 1), total construction area 6300m 2 The project cost is RMB 17.92 million. There are 2 floors above ground. The construction will start on July 30, 2022 and will be completed on January 30, 2023.
[0105] In terms of material costs, 1.2 tons of chemical disinfection materials were saved at 3,000 yuan per ton, saving a total of 3,600 yuan.
[0106] In terms of labor costs, it saved 2 disinfection and dust removal workers (400 yuan / day), a total of 75 shifts, and a total of 60,000 yuan.
[0107] In terms of machinery costs, the rental fee of electrostatic dust removal equipment was saved by 20,000 yuan, and the total cost was saved by 83,600 yuan.
[0108] The above description is only the preferred embodiment of the present application and is not intended to limit the present application. For those skilled in the art, the present application may have various modifications and variations. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present application shall be included in the protection scope of the present application.
Claims
1. A construction process for providing a clean operating room purification air conditioning system, characterized in that: The following steps are involved: Step 1: Production, inspection and installation of air ducts: Step 101, clean the plate, use a joint angle bite to form the bite seam of the air duct, and connect the air duct with the flange; Step 102, check whether the air duct has light leakage, and the air duct that has no light leakage can be installed; Step 103: installing the air duct; Step 2: Static pressure box installation: The four corners of the static pressure box are hoisted in the center of the operating room. The length of the static pressure box should be consistent with the length of the operating table. The static pressure box and the air supply duct should be connected with a flexible joint. After the static pressure box is hoisted and connected to the air duct, it should be sealed. Step 3: Installation of functional units. Functional units include circulation units and fresh air units. Circulation units include filtration and disinfection units. The specific installation steps are as follows: Step 301: Before installing the fresh air unit, check whether the configuration of each section of the unit is consistent with the design. The floor of the equipment room of the fresh air unit should be waterproofed and equipped with a condensate discharge port; Step 302, the filtration and disinfection unit is set in the ceiling, and the foundation platform is welded with No. 12 channel steel. The foundation should be flat, without distortion, and the flatness should not be greater than 2mm / 2m. Spring shock absorbers must be installed on the hanging rods. The four corners of the filtration and disinfection unit should be limited by angle steel blocks. All foundations must be treated with anti-corrosion after welding; Step 303, the fresh air unit includes a deep pretreatment unit, a filter unit and a fresh air preliminary pretreatment unit, and the filter unit includes a primary filter, a medium filter and a high efficiency filter; before installing the high efficiency filter, the system fresh air preliminary pretreatment unit and the system deep pretreatment unit should be installed and operational; the air duct should be installed after air blowing for 10-14 hours, and the filter unit should be cleaned and installed after the air blowing is completed; Step 4: Decoration and final construction: Carry out decoration construction on the clean operating room, install air supply and exhaust louvers, and use aluminum alloy louvers with medium-efficiency filters; Step 5: Installation effect test, including wind speed and volume test, high-efficiency filter leak detection, interval pressure difference test, cleanliness test, temperature and humidity test and noise test.
2. The construction process according to claim 1, characterized in that: In step 103, when the air duct is installed, the tightening torque of each bolt on the flange should be consistent and tightened symmetrically and gradually, and the flange bolts should face the direction of air flow.
3. The construction process according to claim 1, characterized in that: In step 2, when the static pressure box is hoisted, the height difference of the four corners shall not exceed 2mm.
4. The construction process according to claim 1, characterized in that: In step 5, the wind speed and air volume test includes the following steps: Step 501: First, use a hot-bulb anemometer to confirm that the wind speed and air volume of the air outlet of the high-efficiency filter in each area meet the requirements, and the air outlet of each air outlet in the interval is uniform; Step 502: The measuring point of the operating area of the Class I clean operating room and the Class I clean auxiliary room is the cross-sectional wind speed and speed unevenness of the working surface 1.2m above the ground. The average wind speed in the working area is 0.2-0.25m / s, and the speed unevenness should be less than or equal to 0.
24. Step 503, the measuring point range should be the area within 0.12m of the boundary of the concentrated cover projection area, evenly distributed, and the measuring point plane layout measuring point height is 1.2m from the ground, there should be no operating table or work surface blocking, the measuring point spacing should not be greater than 0.3m, and the arithmetic mean of the wind speed readings at all measuring points is taken as the average wind speed.
5. The construction process according to claim 1, characterized in that: In step 5, the high efficiency filter leak detection includes the following steps: Remove the diffuser plate and scan the seals of the entire high-efficiency filter, the filter and the frame, the frames and the frame and the high-efficiency static pressure box; when scanning, the sampling head is about 2 to 3 cm away from the filter surface of the high-efficiency filter, and the scanning speed does not exceed 5 cm / s; the scan is carried out back and forth in a straight line, and the lines should overlap; if there is an alarm during the detection process, indicating a leak, the leak should be plugged with silicone or tightened before scanning and inspection.
6. The construction process according to claim 5, characterized in that: When checking for leaks on a high-efficiency filter, its leakage rate should be less than or equal to 0.01%. If the leakage rate at all points on the high-efficiency filter does not exceed 0.01% during the test, it is qualified. If one point is judged as unqualified, the point should be marked and needs to be repaired or replaced. Special glue is allowed to be used to repair the leakage of filter material of the high-efficiency filter, but the area of a single leakage point cannot be greater than 1% of the total area, and the area of all leakage points cannot be greater than 5% of the total area.
7. The construction process according to claim 1, characterized in that: In step 5, the interval pressure difference test includes the following steps: According to the design value of pressure difference in each room, adjust the opening degree and response speed of each indoor return air valve, so that the pressure difference of each indoor area is maintained within the design range; during the test, the air conditioning system operates normally, and the air volume of the air supply outlet is balanced; the exhaust system operates normally, and the air volume of the exhaust outlet is balanced; use a micro differential pressure gauge or a digital micro differential pressure gauge to measure the pressure difference relative to atmospheric pressure at one point in each independent area; The static pressure difference should be measured when the doors of all rooms are closed. When there is exhaust, it should be carried out under the condition of maximum exhaust volume, and the pressure difference of adjacent connected rooms should be measured from the innermost room on the plane to the outside in sequence until the pressure difference between the clean area and the non-clean area and the outdoor environment is measured. For unidirectional flow clean rooms with cleanliness level 5 or better, the height of the indoor working surface 0.6m away from the door should also be measured when the door is open. For clean rooms with non-closable openings that connect to adjacent rooms, the flow rate and direction at the openings should also be measured.
8. The construction process according to claim 1, characterized in that: In step 5, the cleanliness test includes the following steps: When using a dust particle counter for sampling testing, there should be no less than 3 sampling points in each controlled environment; the sampling points should be evenly distributed throughout the clean room and located at the height of the work area. When the work area is distributed at different heights, more than one measurement surface should be set; when measuring unidirectional flow, the sampling head should be aligned with the airflow; when measuring non-unidirectional flow, the sampling head should always be upward; When the air supply outlets are arranged in a centralized manner, the operating area and the surrounding areas shall be inspected separately; the minimum sampling volume of the particle counter each time shall be 8.6L in the Level 5 area and 2.83L in the areas below; the measuring points shall be arranged on a plane 0.8m above the ground; there shall be no operating table when inspecting the operating area; when the operating table is fixed, the measuring point on the table shall be 0.25m above the table; when inspecting in the Level 5 area, the sampling port shall face the direction of the airflow; when inspecting in areas of other levels, the sampling ports shall all face upward; when inspecting the dust concentration, all operating room lights except the shadowless lamp shall be turned on.
9. The construction process according to claim 1, characterized in that: In step 5, the temperature and humidity test includes the following steps: During the test, the air conditioning unit operates normally for at least 12 hours; the air volume at the supply and exhaust outlets is adjusted to within the design requirements; the air conditioning water system is debugged and the cold and heat sources can meet the supply; the automatic control system (design temperature and humidity part) is adjusted and the system is set according to the temperature and humidity design parameters of each room; after the system starts automatic control, observe the actual control effect, and if there is any abnormal situation, adjust the system in time to ensure that the system reaches the best control state. The instantaneous measurement value of temperature and humidity, the instrument display value is the measurement value of the measuring point, the measuring point is arranged at the same height of more than 0.5m from the outer wall surface and 0.8m from the ground, the room area is 50m 2 Measure 5 points within the room; each increase of 20 to 50m 2 Add 3 to 5 measuring points; the maximum value of each temperature deviation from the control point reached by more than 90% of the measuring points is the room temperature fluctuation range of the room, which should not exceed the design requirements; the deviation value between the average temperature of each measuring point and the lowest or highest temperature of each measuring point reached by more than 90% of the measuring points is the regional temperature difference of the room, which should not exceed the design requirements.
10. The construction process according to claim 1, characterized in that: In step 5, the noise test includes the following steps: Use a sound level meter to measure directly. The minimum scale of the sound level meter should not be lower than 0.2dB. The instrument display value is the measured value of the measuring point. There should be no reflective objects within 1m of the measuring point. The test height is 1.1m from the ground and the area is 15m 2 For clean rooms below 15m, only the center point can be measured. 2 In addition to the central point, the above clean rooms should also measure 4 diagonal points, each 1m away from the side wall, and the measuring points should be directed toward each corner. When it is a mixed flow clean room, the noise in the unidirectional flow area and non-unidirectional flow area should be measured separately.