Expansive soil core filling embankment design method
By rationally designing the compaction coefficient K and edge thickness H in the expansive soil core-filled embankment to ensure that the restraining load is greater than the expansion force, the problem of insufficient theoretical basis for the design of expansive soil embankments in the Meiyu climate zone is solved, and the efficient utilization of expansive soil is achieved. Reduction of project costs.
Patent Information
- Application Number
- CN202410760218.0
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-06-13
- Publication Date
- 2024-10-01
AI Technical Summary
In the Meiyu climate zone, there is a lack of theoretical basis for the design of expansive soil embankments. As a result, the expansive soil core-filled embankments are prone to surface slippage, slope collapse, slope erosion and uneven settlement of the roadbed during the Meiyu season. Moreover, due to the expansion of soil areas, Lack of alternative fillers and higher engineering costs.
By determining the reasonable design of the compaction coefficient K and the edge thickness H, it is ensured that the restraint load during the rainy season is greater than the expansion force generated by the core-filled expansive soil. Simulation calculations and experimental verifications are used to add waterproofing or drainage facilities and adjust the embankment structure to reduce the expansion force. impact and reduce project costs.
It effectively reduces the risk of swelling and deformation of the expansive soil embankment during the rainy season, reduces the amount of clay, reduces the project cost, significantly reduces the line operation and maintenance costs, and improves the stability of the expansive soil core-filled embankment.
Smart Images

Figure CN118734394A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of railway roadbed engineering, in particular to a design method for an expansive soil core-filled embankment. Background Art
[0002] Expansive soil is a special soil rich in highly hydrophilic clay minerals and is widely distributed in my country. Expansive soil has the engineering characteristics of swelling when exposed to water and shrinking when dehydrated. Expansive soil embankment slopes are prone to surface collapse, slope collapse, slope erosion, and uneven subsidence of the roadbed. Therefore, expansive soil is not suitable for embankment construction. However, since expansive soil areas often lack other fillers, replacing all expansive soil with non-expansive soil will greatly increase the project cost. If the expansive soil is chemically modified by cement, lime, slag mixture, etc., it will increase the project cost.
[0003] Continuous rainfall infiltration during the plum rain season is a key factor affecting the performance of expansive soil embankments in plum rain climate zones. In order to effectively utilize the spoil generated by excavation of expansive soil cuttings, when filling the roadbed, the expansive soil can be filled in the middle and the clay can be wrapped on the outside to reduce the permeability of the embankment surface, so as to avoid the core-filled expansive soil from absorbing water and swelling and deforming, which affects the stability of the roadbed and driving safety. The key to the design of expansive soil core-filled roadbed is to design a reasonable thickness and compaction of the edge-wrapped clay layer, and to minimize the amount of clay and save engineering costs while ensuring that the expansive soil does not absorb water and swell under continuous rainfall during the plum rain season. There is currently no relevant design method. In practice, the design is mainly based on experience or reference monitoring data, and the design theory is insufficient. Summary of the invention
[0004] The invention aims to propose a design method for an expansive soil core-filled embankment in a plum rain climate zone, so as to solve the problems of insufficient theoretical basis and lack of design method for the design of an expansive soil core-filled embankment in a plum rain climate zone.
[0005] The present invention adopts the following technical solution:
[0006] A method for designing an expansive soil core-filled embankment comprises the following steps:
[0007] (1) Determine the effect of compaction coefficient K on the engineering properties of expansive soil and edge-wrapped clay;
[0008] (2) Determine the relationship between the swelling force and water content of the expansive soil through the swelling force test of the expansive soil;
[0009] (3) Determine the embankment restraining load;
[0010] (4) Under the condition that the restraining load during the rainy season is greater than the expansion force generated by the core-fill expansive soil, determine the appropriate edge thickness H and compaction coefficient K;
[0011] (5) Verify whether the proposed design meets the requirements of the specification; if not, increase the edge thickness H or compaction coefficient K and verify again until it meets the requirements of the specification;
[0012] Furthermore, it also includes step (6) of adding waterproof or drainage facilities according to the locations of weak parts shown by the rainfall infiltration simulation calculation results.
[0013] In step (1), the influence of the compaction coefficient K on the engineering properties of the expansive soil and the edge-wrapped clay is determined by experiment, specifically, the permeability coefficient, saturated water content, density, elastic modulus, cohesion, and internal friction angle of the edge-wrapped clay and the expansive soil with different compaction coefficients are determined.
[0014] In step (3), the constraint load of the expansive soil core-filled embankment with different compaction coefficients K and edge thicknesses H is calculated; the constraint load is the sum of the load of the infiltrated clay and the load of the infiltrated core-filled expansive soil.
[0015] Step (4) comprises:
[0016] (a) The embankment compaction coefficient K takes the minimum value specified in the specification, and the value range of the edge thickness H is determined according to the construction requirements;
[0017] (b) According to the construction requirements, determine the minimum value of the edge thickness and the value range of the compaction coefficient K;
[0018] (c) When the compaction coefficient K takes the minimum value, the minimum value of the edge thickness H is determined under the condition that the restraint load in the rainy season is always greater than the expansion force generated by the expansive soil core filling area;
[0019] (d) When the edge thickness H takes the minimum value, the minimum value of the compaction coefficient K is determined under the condition that the restraint load in the rainy season is always greater than the maximum expansion force generated by the expansive soil core fill area.
[0020] In step (4), the swelling force is the discrete integral value of the swelling force generated by the strips of different volume water contents in the core-filled expansive soil infiltrated by rainwater, as shown in the following formula:
[0021]
[0022] In the formula, p e is the expansion force, p i is the expansion force generated by the i-th block.
[0023] In step (5), the safety factor of the last day of the rainy season is calculated based on the edge thickness H and the compaction coefficient K obtained in step (c) and step (d).
[0024] In step (5), the safety factor is calculated by the following formula:
[0025]
[0026] K f is the safety factor; W i is the weight of the ith block; A is the earthquake acceleration; α i is the inclination angle of the sliding surface of the i-th block; β i is the groundwater flow direction of the ith block; c i , are the cohesion and internal friction angle of the ith block respectively; N wi is the pore water pressure; ψ j is the transfer coefficient when the residual landslide thrust of the i-th block is transmitted to the i+1-th block (j=i); R n and T n are the anti-sliding force and sliding force of the nth block respectively; h i1 、h i2 are the heights of the left and right sides of the expansive soil part of the i-th block that is wetted by rainwater; l i is the bottom length of the i-th block; p e For expansion force.
[0027] In step (5), when the calculated safety factor is less than 1.25, the edge thickness H or the compaction coefficient K is increased and the safety factor is calculated again until the safety factor is greater than or equal to 1.25.
[0028] The beneficial effect of the present invention is that the present invention reduces the influence of external moisture on the core-filled expansive soil and limits the effect of the expansive force by controlling the thickness of the edge and the compaction coefficient of the embankment. This method takes into account the development of the expansive force caused by the change in the volumetric water content of the expansive soil core-filled area caused by continuous rainfall in the plum rain season, and adjusts the edge thickness H and the compaction coefficient K of the embankment so that the constraint load is always greater than the expansive force generated by the core-filled expansive soil, so that the expansive force generated by the core-filled expansive soil can be offset by the constraint load, and based on the principle of saving materials and reducing waste, the design of the expansive soil core-filled embankment is carried out to minimize the project cost and speed up the project progress. It effectively solves the problem of insufficient theoretical basis and lack of design methods for the design of expansive soil core-filled embankments in plum rain climate zones, is conducive to solving the problem of insufficient utilization of expansive soil in roadbed engineering expansive soil areas, greatly reduces the probability of catastrophic changes in expansive soil embankments in plum rain climate zones, and can significantly reduce the cost of line operation and maintenance. BRIEF DESCRIPTION OF THE DRAWINGS
[0029] Figure 1 This is a schematic diagram of the expansive soil core-fill embankment structure;
[0030] Figure 1 Among them, 1. Expansive soil core filling area; 2. Clay edge anti-seepage area; 3. Foundation.
[0031] Figure 2 It is a schematic diagram of the method flow of the present invention.
[0032] Figure 3 Schematic diagram of the continuous water absorption expansion force test device.
[0033] Figure 4 is the swelling force of expansive soil with different volumetric water content.
[0034] Figure 5 Volumetric water content at the slope foot of the expansive soil core fill area with different edge thicknesses.
[0035] Figure 6 Volumetric water content at the slope toe of the expansive soil core fill area under different compaction coefficients.
[0036] Figure 7 This is the moisture content distribution of the expansive soil core-fill embankment in Scheme 1.
[0037] Figure 8 This is the moisture content distribution of the expansive soil core-fill embankment in Scheme 2. DETAILED DESCRIPTION
[0038] The present invention will be further described below in conjunction with the accompanying drawings.
[0039] like Figure 1 As shown, a method for designing an expansive soil core-filled embankment structure of the present invention includes an expansive soil core-filled embankment structure including an expansive soil core-filled area 1 and a clay-enclosed anti-seepage area 2 with a thickness H covering the expansive soil core-filled area 1.
[0040] The present invention is applicable to embankment projects in expansive soil areas. Figure 2 The method flow chart shown mainly includes the following steps:
[0041] Firstly, the relationship between swelling force and water content is determined through swelling force test of expansive soil.
[0042] Then, the numerical simulation method was used to study the relationship between the internal volumetric water content of the expansive soil core-fill roadbed in the rainy season and the edge thickness H and the compaction coefficient K. The development of the expansive force of the core-fill expansive soil was determined in combination with the expansive force test results of the expansive soil.
[0043] Finally, adhering to the principle of saving materials and reducing waste, the appropriate edge thickness H and compaction coefficient K are determined by ensuring that the restraint load during the rainy season is greater than the expansion force generated by the core-filling expansive soil. And verify whether the proposed design meets the requirements of the specification.
[0044] Next, the method of the present invention is specifically described by taking the Tongling Jiangbei Port Railway dedicated line expansive soil core filling embankment project as an example.
[0045] The expansive soil was taken from the expansive soil road cutting of the Tongling Jiangbei Port Railway dedicated line, and the edging clay was taken from the borrow yard near the project site.
[0046] (1) Determine the influence of compaction coefficient K on the engineering properties of expansive soil and edge-wrapped clay
[0047] Geotechnical tests were carried out with reference to "TB10102-2023 Geotechnical Test Code for Railway Engineering" to determine the permeability coefficient, saturated water content, density, elastic modulus, cohesion, and internal friction angle of clay and expansive soil with different compaction coefficients.
[0048] (2) Determine the relationship between expansion force and volumetric water content
[0049] Expansive soil swells when it absorbs water. When the volume increase of the expansive soil is blocked, it will generate expansion force. The expansion force of the expansive soil is measured by using a continuous water absorption expansion force test device, by controlling the expansion deformation of the expansive soil during the wetting process and measuring the overburden load value that constrains the expansion deformation of the expansive soil.
[0050] Specifically, the continuous water absorption expansion force test device is as follows Figure 3 As shown in the figure, the upper part of the soil sample is a waterproof steel plate, a load cell and a reaction bolt, and the force measuring element is a load cell. The waterproof steel plate and the reaction bolt have sufficient rigidity to fix the soil sample and the force measuring element. When the expansive soil absorbs water, the reaction bolt provides a corresponding reaction force to ensure that the expansive soil does not deform. By controlling the expansion deformation of the expansive soil during the humidification process, the overburden load value that constrains the expansion deformation of the expansive soil is measured to determine the expansion force of the expansive soil.
[0051] The same method was used to conduct 6 groups of tests on the soil samples. The average of the test results was taken to obtain the values of the expansion force generated by the expansive soil with different volumetric water contents, such as Figure 4 As shown in the figure. The swelling force reaches a peak value of 17 kPa when the volumetric water content of the expansive soil sample increases to 31%, and then remains at 17 kPa. The results show that the expansive soil is a weak expansive soil. The wedge force generated between the soil particles after absorbing water is small and insufficient to redistribute the soil particles. There is no swelling force attenuation phenomenon.
[0052] (3) Determine the embankment restraint load
[0053] The restraint load should be the sum of the wetted clay and wetted core-fill expansive soil loads, from which the restraint load of the expansive soil core-fill embankment with different compaction coefficients K and edge thicknesses H is calculated.
[0054] The load of the soaked clay is the sum of the weight of the clay itself and the weight of water when the entire clay is soaked.
[0055] The load of the soaked core-fill expansive soil is the sum of the weight of the core-fill expansive soil soaked by rainwater and the weight of water.
[0056] Since the increase in compaction factor will increase the weight of the soil, the restraint load will also increase. The increase in the thickness of the edge will increase the amount of clay, which will also increase the restraint load.
[0057] Assuming that the hemming area is the volume of a rectangular cross section, with a length of L, a width of W, and a thickness of H, the volume can be expressed as: V = L × W × H
[0058] V=L·WH
[0059] The restraint load can be expressed as P = V (expansive soil) × γ (expansive soil) + V (wetted expansive soil) × γ (expansive soil) + G
[0060] Among them, γ represents the weight of soil and G represents the weight of infiltration water.
[0061] The γ values of different compaction coefficients can be determined through geotechnical tests in the "Geotechnical Test Code for Railway Engineering".
[0062] (4) Determine the expansion force of the core-fill expansive soil area during the rainy season
[0063] The expansion force is calculated by discrete integration method. The expansion force is the discrete integral value of the expansion force generated by the strips with different volume water contents in the core expansive soil infiltrated by rainwater. The formula is as follows:
[0064]
[0065] In the formula, p e is the expansion force, p i is the expansion force generated by the i-th block.
[0066] (I) The compaction coefficient K of the embankment shall be the minimum value specified in the specification, and the value range of the edge thickness H shall be determined according to the construction requirements.
[0067] According to the Railway Roadbed Design Code (TB10001), the compaction coefficient of embankment filling should be ≥0.90. In the Tongling Jiangbei Port Railway Special Line Expansive Soil Core Embankment Project, the embankment compaction coefficient K is 0.90. Here, the minimum compaction coefficient is selected first, and then the appropriate (minimum) edge thickness is calculated. This can save the use of machinery, reduce the use of clay fillers, shorten the construction period, and thus reduce the project cost.
[0068] The edge thickness H is determined according to the construction requirements. If H is too small, it will be inconvenient for construction, and if H is too large, it will cause waste of clay filler. In this project, the minimum value of edge thickness H is 1m, the maximum value is 2m, and the interval is 0.25m, that is, 1m, 1.25m, 1.5m, 1.75m, 2m. The smaller the interval, the more accurate the design, and too large an interval may cause waste of clay filler.
[0069] Using the rainfall infiltration numerical simulation model of expansive soil core-filled embankment, the volumetric water content distribution and change of each part of the expansive soil core-filled embankment with different edging thicknesses during the rainy season are determined, and the part with the largest expansion force (the part with the largest volumetric water content) is found. Based on the expansion force test results of the expansive soil, the expansion force value of this part is determined in combination with formula (1).
[0070] The numerical simulation model of rainfall infiltration in expansive soil core-filled embankment is mainly based on the Richards equation to describe the movement of water in the soil. The Richards equation is a basic equation that describes the movement of water in unsaturated soil, combining Darcy's law and the law of conservation of mass. The equation is as follows:
[0071]
[0072] Among them, θ is the volumetric water content of the soil; t is the time; z is the depth; K is the permeability coefficient; ψ is the soil water potential.
[0073] The calculation results show that the volumetric water content at the toe of the expansive soil core-filled area of the Tongling Jiangbei Port Railway Dedicated Line is always the largest, and the expansion force at this location is always the largest. In the design, the volumetric water content at the toe of the expansive soil core-filled area can be focused on. Figure 5 shown.
[0074] (II) Based on construction requirements and taking into account economic benefits, the minimum value of the edge thickness is determined and the range of the compaction coefficient is determined.
[0075] In the Tongling Jiangbei Port Railway Line expansive soil core embankment project, the embankment edge thickness H is 1m, the embankment compaction coefficient K is 0.90 at the minimum and 0.96 at the maximum, with an interval of 0.02, i.e. 0.90, 0.92, 0.94, and 0.96. The smaller the interval, the more accurate the design, and too large an interval may slow down the construction progress.
[0076] According to the numerical simulation model of rainfall infiltration of expansive soil core-filled embankment, the volumetric water content distribution and change of each part of the expansive soil core-filled embankment with different compaction coefficients in the rainy season are determined, and the part with the largest expansion force (the part with the largest volumetric water content) is found. And according to the expansion force test results of expansive soil, the value of the expansion force of this part is determined in combination with formula (1).
[0077] The calculation results show that the volumetric water content at the toe of the expansive soil core-filled area of the Tongling Jiangbei Port Railway Dedicated Line is always the largest, and the expansion force at this part is always the largest. In the design, the volumetric water content at the toe of the expansive soil core-filled area can be focused on. Figure 6 shown.
[0078] (6) Select appropriate edge thickness H and compaction coefficient K
[0079] (i) When the compaction coefficient K is determined to take the minimum value, the restraint load in the rainy season is always greater than the minimum value of the edge thickness H of the expansion force generated by the expansive soil core fill area.
[0080] In the Tongling Jiangbei Port Railway Special Line Expansive Soil Core Filling Embankment Project, the constraint load calculation results determined that when the compaction coefficient K takes the minimum value of 0.90, the minimum edge thickness H is 1.25m so that the constraint load in the rainy season is always greater than the maximum expansion force. The maximum volume water content at the foot of the core filling part in the rainy season is 22.6%, and the expansion force at this part is 95.8kN / m 2 , the restraint load is 137.6kN / m 2 , the expansive soil core fill area will not expand and deform.
[0081] Therefore, the design scheme 1 is: the roadbed edge thickness H is 1.25m, and the compaction coefficient K is 0.90. The rainfall infiltration reaches the maximum on the last day of the plum rain season. The water content distribution of the expansive soil core embankment of scheme 1 on the last day of the plum rain season is as follows: Figure 7 shown.
[0082] (ii) When the minimum value of the edge thickness H is determined, the minimum value of the compaction coefficient K is determined so that the restraint load during the rainy season is always greater than the maximum expansion force generated in the expansive soil core fill area.
[0083] In the Tongling Jiangbei Port Railway Special Line Expansive Soil Core Filling Embankment Project, the calculation results of the constraint load determined that when the minimum value of the edge thickness H is 1m, the minimum compaction coefficient K that makes the constraint load always greater than the maximum expansion force during the rainy season is 0.92. The maximum volume water content at the foot of the core filling part during the rainy season is 18.9%, and the expansion force at this part is 58.3kN / m 2 , the restraint load is 117.1kN / m 2 , the core fill expansive soil will not expand and deform.
[0084] Therefore, the second design scheme is: the thickness of the roadbed edge H is 1m, and the compaction coefficient K is 0.92. The rainfall infiltration reaches the maximum on the last day of the plum rain season. The water content distribution of the expansive soil core embankment of scheme 2 on the last day of the plum rain season is as follows: Figure 8 shown.
[0085] (7) Stability verification of expansive soil core-filled embankment
[0086] (a) Safety factor calculation formula considering expansion force
[0087] The specification stipulates that the safety factor of embankment changes should not be less than 1.25. The safety factor calculation formula for introducing the expansion soil force into the broken line sliding surface is as follows:
[0088]
[0089] In formula (2), K f is the safety factor, which should be no less than 1.25; W i is the weight of the ith block; A is the earthquake acceleration; α i is the inclination angle of the sliding surface of the i-th block; β i is the groundwater flow direction of the ith block; c i , are the cohesion and internal friction angle of the ith block respectively; N wi is the pore water pressure; ψ j is the transfer coefficient when the residual landslide thrust of the i-th block is transmitted to the i+1-th block (j=i); R n and T n are the anti-sliding force and sliding force of the nth block respectively; h i1 、h i2 are the heights of the left and right sides of the expansive soil part of the i-th block that is wetted by rainwater; l i is the bottom length of the i-th block; p e For expansion force.
[0090] (b) Safety factor verification of expansive soil core-filled embankment
[0091] According to engineering experience, the safety factor of the slope continues to decrease with the increase of rainfall duration. Therefore, the verification of embankment stability only requires calculating the slope safety factor on the last day of the rainy season.
[0092] (c) If the safety factor meets the requirements of the specifications after calculation, construction can be carried out; if the safety factor does not meet the requirements of the specifications after calculation, the edge thickness or compaction factor can be appropriately increased and the safety factor can be verified again until it meets the requirements of the specifications.
[0093] In the Tongling Jiangbei Port Railway Special Line Expansive Soil Core Filled Embankment Project, the safety factor calculation results of the expansive soil core filled roadbed of Scheme 1 and Scheme 2 were 1.13 and 1.41 respectively. Therefore, Design Scheme 2 was selected for the design of the expansive soil core filled embankment.
[0094] (8) Add other waterproofing or drainage facilities
[0095] In the expansive soil core-fill embankment project of Tongling Jiangbei Port Railway Special Line, calculation results show that the toe of the expansive soil core-fill area is the part most susceptible to rainfall. The expansion force of this part first develops to the maximum value. This part is relatively weak, and seepage wells should be added at this part.
[0096] At the toes of the slopes on both sides of the expansive soil core filling area 1, seepage wells are set vertically downward and inserted into the permeable layer in the foundation 3. The filling is carried out in layers according to a single particle size, and coarse and fine materials must not be mixed. Crushed stone or pebbles and other filling materials with good permeability are suitable. The mud content of the filling material should be less than 5%, and a filter layer should be set between the well wall and the filling material.
[0097] As another treatment method, in the Tongling Jiangbei Port Railway Dedicated Line expansive soil core-filled embankment project, a concrete coating is set on the slope of the expansive soil core-filled embankment. The thickness of the concrete coating should be no less than 5cm. The concrete strength should meet the relevant standards. Under normal circumstances, the concrete strength should not be less than C25. At the same time, under the premise that the concrete strength meets the requirements, in order to increase the durability of the concrete, an appropriate amount of slag powder, silica fume, etc. can be added to the concrete. The concrete coating can isolate the external environment and prevent external moisture from entering the interior of the roadbed. If vegetation grows on the slope of the roadbed, the roots of the vegetation have a strong water storage function, and the roadbed soil is prone to maintain a high water content, which is not conducive to maintaining the long-term service performance of the roadbed. Surface scraping concrete can prevent the growth of slope vegetation and maintain a low water content inside the roadbed.
Claims
1. A method for designing an expansive soil core-filled embankment, characterized in that: It includes the following steps: (1) Experimentally determine the effect of compaction coefficient K on the engineering properties of expansive soil and edge-wrapped clay; (2) Determine the relationship between the swelling force and water content of the expansive soil through the swelling force test of the expansive soil; (3) Determine the embankment edge load; (4) Under the condition that the restraining load during the rainy season is greater than the expansion force generated by the core-fill expansive soil, the appropriate edge thickness H and compaction coefficient K are determined; (5) Verify whether the proposed design meets the requirements of the specification; if not, increase the edge thickness H or compaction coefficient K and verify again until it meets the requirements of the specification.
2. The expansive soil core-filled embankment design method according to claim 1, characterized in that: The method further comprises step (6) of adding waterproof or drainage facilities according to the locations of weak parts indicated by the rainfall infiltration simulation calculation results.
3. The expansive soil core-filled embankment design method according to claim 1, characterized in that: In step (1), the influence of the compaction coefficient K on the engineering properties of the expansive soil and the edge-wrapped clay is determined by determining the permeability coefficient, saturated water content, density, elastic modulus, cohesion, and internal friction angle of the edge-wrapped clay and the expansive soil with different compaction coefficients.
4. The method for designing an expansive soil core-filled embankment according to claim 3, characterized in that: In step (3), the constraint load of the expansive soil core-filled embankment with different compaction coefficients K and edge thicknesses H is calculated; the constraint load is the sum of the load of the infiltrated clay and the load of the infiltrated core-filled expansive soil.
5. The method for designing an expansive soil core-filled embankment according to claim 4, characterized in that: Step (4) comprises: (a) The embankment compaction coefficient K takes the minimum value specified in the specification, and the value range of the edge thickness H is determined according to the construction requirements; (b) According to the construction requirements, determine the minimum value of the edge thickness and the value range of the compaction coefficient K; (c) When the compaction coefficient K takes the minimum value, the minimum value of the edge thickness H is determined under the condition that the restraint load in the rainy season is always greater than the expansion force generated by the expansive soil core filling area; (d) When the edge thickness H takes the minimum value, the minimum value of the compaction coefficient K is determined under the condition that the restraint load in the rainy season is always greater than the maximum expansion force generated by the expansive soil core fill area.
6. The method for designing an expansive soil core-filled embankment according to claim 5, characterized in that: In step (4), the swelling force is the discrete integral value of the swelling force generated by the strips of different volume water contents of the core-filled expansive soil infiltrated by rainwater, as shown in the following formula: In the formula, p e is the expansion force, p i is the expansion force generated by the i-th block.
7. The method for designing an expansive soil core-filled embankment according to claim 5, characterized in that: In step (5), the safety factor of the last day of the rainy season is calculated based on the edge thickness H and the compaction coefficient K obtained in step (c) and step (d).
8. The method for designing an expansive soil core-filled embankment according to claim 7, characterized in that: In the step (5), the safety factor is calculated by the following formula: K f is the safety factor; W i is the weight of the ith block; A is the earthquake acceleration; α i is the inclination angle of the sliding surface of the i-th block; β i is the groundwater flow direction of the ith block; c i 、j i are the cohesion and internal friction angle of the ith block respectively; N wi is the pore water pressure; ψ j is the transfer coefficient when the residual landslide thrust of the i-th block is transmitted to the i+1-th block (j=i); R n and T n are the anti-sliding force and sliding force of the nth block respectively; h i1 、h i2 are the heights of the left and right sides of the expansive soil part of the i-th block that is wetted by rainwater; l i is the bottom length of the i-th block; p e For expansion force.
9. The method for designing an expansive soil core-filled embankment according to claim 8, characterized in that: In the step (5), when the calculated safety factor is less than 1.25, the edge thickness H or the compaction coefficient K is increased and the safety factor is calculated again until the safety factor is greater than or equal to 1.25.
Citation Information
Cited By
Design method of core filling type fill roadbed structure
CN119720326A