Power grid equipment selection method and device, electronic equipment and storage medium

By predicting the load demand and rated capacity of power grid equipment, the problem of unpredictable replacement of power grid equipment is solved, and efficient power supply and safe and stable operation of the distribution network are achieved.

CN118735203APending Publication Date: 2024-10-01GUANGZHOU KETENG INFORMATION TECH
View PDF 0 Cites 1 Cited by

Patent Information

Application Number
CN202410879135.3
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-07-02
Publication Date
2024-10-01

AI Technical Summary

Technical Problem

In the existing technology, the rated capacity of power grid equipment does not match the load of the distribution network, resulting in the inability to replace it in time, affecting the quality and safety of power supply.

Method used

By obtaining historical load data of power grid equipment, future load demand is predicted, and the rated capacity is determined based on the influencing factor data. If the demand is not met, the minimum rated capacity is determined, and appropriate power grid equipment is selected from the equipment library to meet the load demand.

Benefits of technology

Predictive replacement is achieved, which improves the power supply quality, safety and stability of the distribution network, and avoids waste of resources and equipment overload.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118735203A_ABST
    Figure CN118735203A_ABST
Patent Text Reader

Abstract

The invention discloses a power grid equipment selection method and device, electronic equipment and a storage medium, and the method comprises the steps: obtaining the historical load data of a line where monitored power grid equipment is located, predicting the load demand of the line according to the historical load data, obtaining the influence factor data of the power grid equipment, and determining the rated capacity of the power grid equipment based on the influence factor data, and determining whether the rated capacity meets the load demand or not according to the load demand and the rated capacity, if not, determining the lowest rated capacity according to the load demand, and selecting target power grid equipment from the equipment library according to the lowest rated capacity. Whether the rated capacity of the power grid equipment in the future time period meets the load requirement of the line can be predicted, and when the rated capacity of the power grid equipment cannot meet the load requirement of the line, proper power grid equipment can be selected from the equipment library in time for replacement, so that the power supply quality of the power distribution network is improved, and safe and stable operation of the power distribution network is guaranteed.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of power grid equipment selection, and in particular to a power grid equipment selection method, device, electronic equipment and storage medium. Background Art

[0002] In the distribution network, in order to ensure the power supply quality of the distribution network, the rated capacity of the grid equipment in the distribution network should be able to meet the current and future load requirements of the distribution network. If the load of the distribution network exceeds the rated capacity of the grid equipment, it may cause the grid equipment to be overloaded, thereby reducing the reliability and safety of the equipment. Conversely, if the load of the distribution network is far lower than the rated capacity of the grid equipment, it may cause a waste of resources.

[0003] With the continuous development of distribution networks and the increase in operating time, the change in rated capacity caused by the aging of grid equipment has become an important challenge facing the power industry. Grid equipment whose rated capacity does not match the distribution network load needs to be replaced in a timely manner. In the existing technology, grid equipment is usually replaced only after the rated capacity of grid equipment is found to be mismatched with the distribution network load during grid operation. This is difficult to predict, resulting in the inability to purchase and select grid equipment for replacement in a timely manner, affecting the power supply of the distribution network. Summary of the invention

[0004] The present invention provides a method, device, electronic device and storage medium for selecting power grid equipment to solve the problem that the replacement of power grid equipment is unpredictable, resulting in the inability to purchase and select power grid equipment in a timely manner, affecting the power supply of the distribution network.

[0005] In a first aspect, the present invention provides a method for selecting a power grid device, comprising:

[0006] Obtain historical load data of the line where the monitored power grid equipment is located;

[0007] predicting the load demand of the line according to the historical load data;

[0008] Acquiring influencing factor data of the power grid equipment;

[0009] Determine the rated capacity of the power grid equipment based on the influencing factor data;

[0010] Determining whether the rated capacity meets the load demand according to the load demand and the rated capacity;

[0011] If not, determine the minimum rated capacity based on the load demand;

[0012] A target power grid device is selected from a device library according to the minimum rated capacity.

[0013] Optionally, predicting the load demand of the line according to the historical load data includes:

[0014] The historical load data is input into a preset load forecasting model to obtain the load demand of the line.

[0015] Optionally, the load forecasting model is an autoregressive differential moving average model, and the historical load data is input into a preset load forecasting model to obtain the load demand of the line, including:

[0016] Determining the autoregressive order, the difference order, the moving average order and the seasonal parameter of the autoregressive difference moving average model according to the historical load data;

[0017] The historical load data is input into an autoregressive difference moving average model after determining parameters to obtain the load demand of the line.

[0018] Optionally, determining the rated capacity of the power grid device based on the influencing factor data includes:

[0019] The influencing factor data is input into a multiple linear regression model to obtain the rated capacity of the power grid equipment.

[0020] Optionally, the expression of the multivariate linear regression model is as follows:

[0021] C=β0+β1x1+β2x2+…+β n x n +ε;

[0022] Where C is the rated capacity of the power grid equipment, x1, x2, ..., x n are the influencing factor data, β1,β2,…,β n is the regression coefficient, β0 represents the intercept term, and ε represents the random error term.

[0023] Optionally, determining whether the rated capacity meets the load demand according to the load demand and the rated capacity includes:

[0024] Determine whether the rated capacity is less than the load demand;

[0025] When the rated capacity is less than the load demand, determining that the rated capacity does not meet the load demand;

[0026] When the rated capacity is greater than the load demand, determining that the rated capacity meets the load demand;

[0027] Determine the minimum rated capacity based on the stated load requirements, including:

[0028] The product of the load demand and a preset coefficient is determined as the minimum rated capacity, wherein the preset coefficient is a coefficient greater than 1.

[0029] Optionally, selecting a target power grid device from a device library according to the minimum rated capacity includes:

[0030] Determine from the device library the power grid devices whose rated capacity is greater than the minimum rated capacity and whose difference between the rated capacity and the minimum rated capacity is less than a preset value as the first candidate device set;

[0031] Obtaining working requirement parameters of power grid equipment in the line;

[0032] Selecting power grid devices whose operating parameters meet the operating requirement parameters from the first candidate device set as the second candidate device set;

[0033] A low-cost power grid device is selected from the second candidate device set as the target power grid device.

[0034] In a second aspect, the present invention provides a power grid equipment selection device, comprising:

[0035] A historical load data acquisition module is used to acquire historical load data of the line where the monitored power grid equipment is located;

[0036] A load prediction module, used for predicting the load demand of the line according to the historical load data;

[0037] An influencing factor data acquisition module, used to acquire influencing factor data of the power grid equipment;

[0038] A rated capacity prediction module, used to determine the rated capacity of the power grid equipment based on the influencing factor data;

[0039] A judgment module, used for determining whether the rated capacity meets the load demand according to the load demand and the rated capacity, and if not, executing a minimum rated capacity determination module;

[0040] A minimum rated capacity determination module, used to determine the minimum rated capacity according to the load demand;

[0041] The target power grid equipment selection module is used to select the target power grid equipment from the equipment library according to the minimum rated capacity.

[0042] In a third aspect, the present invention provides an electronic device, the electronic device comprising:

[0043] at least one processor; and

[0044] a memory communicatively connected to the at least one processor; wherein,

[0045] The memory stores a computer program executable by the at least one processor, and the computer program is executed by the at least one processor so that the at least one processor can execute the power grid equipment selection method described in any one of the first aspects of the present invention.

[0046] In a fourth aspect, the present invention provides a computer-readable storage medium storing computer instructions, wherein the computer instructions are used to enable a processor to implement the method for selecting a power grid device as described in any one of the first aspects of the present invention when executed.

[0047] The embodiment of the present invention predicts the future load demand of the line through the historical load data of the line where the power grid equipment is located, and predicts the future rated capacity of the power grid equipment through the influencing factor data of the power grid equipment. When it is determined that the rated capacity cannot meet the load demand, the minimum rated capacity is determined according to the load demand, and the target power grid equipment is selected from the equipment library according to the minimum rated capacity. It is possible to predict whether the rated capacity of the power grid equipment in the future time period will meet the load demand of the line, so as to select the power grid equipment that can meet the load demand of the line from the equipment library, and when there is no suitable power grid equipment in the equipment library, the power grid equipment can be purchased in advance, and the suitable power grid equipment can be selected from the equipment library in time for replacement, so as to improve the power supply quality of the distribution network and ensure the safe and stable operation of the distribution network.

[0048] It should be understood that the contents described in this section are not intended to identify the key or important features of the embodiments of the present invention, nor are they intended to limit the scope of the present invention. Other features of the present invention will become easily understood through the following description. BRIEF DESCRIPTION OF THE DRAWINGS

[0049] In order to more clearly illustrate the technical solutions in the embodiments of the present invention, the following briefly introduces the drawings required for use in the description of the embodiments. Obviously, the drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without creative work.

[0050] Figure 1 is a flow chart of a method for selecting power grid equipment provided by Embodiment 1 of the present invention;

[0051] Figure 2 is a flow chart of a method for selecting power grid equipment provided in Embodiment 2 of the present invention;

[0052] Figure 3 It is a structural schematic diagram of a power grid equipment selection device provided in Embodiment 3 of the present invention;

[0053] Figure 4 It is a schematic diagram of the structure of an electronic device provided in Embodiment 4 of the present invention. DETAILED DESCRIPTION

[0054] In order to enable those skilled in the art to better understand the scheme of the present invention, the technical scheme in the embodiments of the present invention will be clearly and completely described below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work should fall within the scope of protection of the present invention.

[0055] Embodiment 1

[0056] Figure 1 This is a flowchart of a method for selecting a power grid device provided in the first embodiment of the present invention. This embodiment is applicable to the case of selecting a power grid device. The method can be executed by a power grid device selection device. The power grid device selection device can be implemented in the form of hardware and / or software and can be configured in an electronic device. Figure 1 As shown, the power grid equipment selection method includes:

[0057] S101. Obtain historical load data of the line where the monitored power grid equipment is located.

[0058] In this embodiment, the power grid equipment may be electrical equipment on the transmission line of the distribution network. By way of example, the power grid equipment may be a transformer, a storage capacitor, a battery, a generator, a switch, a relay or other equipment. The line may be a transmission line. The load data of the line where the power grid equipment is located may be recorded in a preset period and stored in a database to obtain the historical load data of the line where the power grid equipment is located. By way of example, the load of the line may be recorded in periods such as one hour or one day to obtain the historical load data of the transmission line within a certain time period, such as the historical load data per hour in the past year, quarter or month.

[0059] S102. Predict the load demand of the line according to historical load data.

[0060] This embodiment needs to predict the load demand of the line where the power grid equipment is located in the future, such as the load demand at multiple time points in a certain time period in the future, or the load demand at a certain time point in the future.

[0061] In one embodiment, a load prediction model may be pre-trained, and the load demand of the line at multiple time points in a future time period may be predicted by inputting historical load data into the load prediction model.

[0062] In another embodiment, after inputting historical load data, the load forecasting model can also forecast the load demand at a certain point in the future. For example, the load demand 30 days later or 60 days later can be forecasted based on the historical load data.

[0063] S103. Obtain influencing factor data of power grid equipment.

[0064] In this embodiment, the influencing factor data may be data of factors that cause aging of the power grid equipment and a decrease in the rated capacity during the use of the power grid equipment. By way of example, the influencing factor data may include operating environment data, such as temperature, humidity, vibration amplitude, vibration frequency, dust concentration, air pressure and other data, and may also include equipment operating status data, such as load rate, operating voltage, operating current, power factor, insulation resistance and other data. In this embodiment, the influencing factor data that can affect the power grid equipment and cause the rated capacity of the power grid equipment to decrease can be selected according to different power grid equipment. The influencing factor data of the power grid equipment can be collected by sensors and recorded in a database, and the influencing factor data of the power grid equipment can be read from the database.

[0065] S104. Determine the rated capacity of the power grid equipment based on the influencing factor data.

[0066] Rated capacity refers to the parameter of the amount of electric energy carried by grid equipment. The rated capacity of different types of grid equipment has different meanings. For example, the rated capacity of a capacitor may refer to the rated capacitance value of the capacitor, the rated capacity of a battery in an energy storage power station may refer to the capacity of the battery, the rated capacity of a transformer may refer to the rated transmission power of the transformer, the rated capacity of a generator may refer to the rated output power of the generator, and the rated capacity of a relay may refer to the maximum current allowed to pass through the contacts of the relay.

[0067] In actual applications, the rated capacity of power grid equipment is approved after manufacturing. After the power grid equipment is installed in the lines of the distribution network and used, as the operating time increases, it ages under the influence of the environment and operation, making the actual capacity less than the rated capacity, and the rated capacity needs to be corrected. After determining the influencing factor data of the power grid equipment, the influencing factor data can be used to predict the revised rated capacity of the power grid equipment at multiple time points in the future time period or at a certain time point. For example, the influencing factor data of a past period of time can be input into a pre-configured model to obtain the revised rated capacity of the power grid equipment at multiple time points in the future period of time or at a specific time point, or the influencing factor data of a past period of time can be input into a preset capacity revision formula to obtain the revised rated capacity at a specific time point.

[0068] S105. Determine whether the rated capacity meets the load demand according to the load demand and the rated capacity.

[0069] In one embodiment, when the rated capacity is less than the load demand, it can be determined that the demand is not met, and when the rated capacity is greater than the load demand, it can be determined that the load demand is met.

[0070] In another embodiment, the rated capacity may be greater than the load demand, and when the difference between the rated capacity and the load demand is less than a preset value, it is determined that the demand is not met; when the difference is greater than the preset value, it is determined that the load demand is met; if it is determined that the load demand is not met, S106 is executed; if it is determined that the load demand is met, the process ends.

[0071] S106. Determine the minimum rated capacity according to the load demand.

[0072] In one embodiment, the load demand can be determined as the minimum rated capacity. Taking the exemplary transformer as an example, when the load demand of the line where the transformer is located at the end of the next month is 30KW, when the revised rated capacity of the transformer is 25KW, it is determined that the load demand is not met, and the minimum rated capacity can be determined as 30KW.

[0073] In another embodiment, the product of the load demand and the preset coefficient can also be calculated as the minimum rated capacity, wherein the preset coefficient is a coefficient greater than 1. Taking the load demand as 30KW, the minimum rated capacity can be 30×1.2=36KW, so as to ensure that the rated capacity of the power grid equipment has a certain margin relative to the load demand, thereby improving the reliability of the power grid equipment.

[0074] S107. Select target power grid equipment from the equipment library according to the minimum rated capacity.

[0075] In one embodiment, the power grid equipment in the equipment library whose rated capacity is greater than the minimum rated capacity and closest to the minimum rated capacity can be determined as the target power grid equipment, which can not only meet the load demand of the line, but also maximize the capacity utilization of the target power grid and avoid waste caused by using too high a rated capacity.

[0076] In yet another embodiment, the power grid equipment with a rated capacity greater than the minimum rated capacity and the lowest cost in the equipment library may be determined as the target power grid equipment, which can both meet the load demand of the line and minimize the cost.

[0077] Of course, when selecting the target power grid equipment, in addition to the rated capacity being greater than the minimum rated capacity, the target power grid equipment can also be selected from the equipment library based on the working environment, working voltage, working current and other parameters of the line, so that the target power grid equipment can be used to replace the power grid equipment in the line when a future time point is reached. When there is no suitable power grid equipment in the equipment library, the target power grid equipment can be purchased in advance with reference to the future time point (the time point when the load demand is not met) so that the power grid equipment in the line can be replaced in time.

[0078] The embodiment of the present invention predicts the future load demand of the line through the historical load data of the line where the power grid equipment is located, and predicts the future rated capacity of the power grid equipment through the influencing factor data of the power grid equipment. When it is determined that the rated capacity cannot meet the load demand, the minimum rated capacity is determined according to the load demand, and the target power grid equipment is selected from the equipment library according to the minimum rated capacity. It is possible to predict whether the rated capacity of the power grid equipment in the future time period will meet the load demand of the line, so as to select the power grid equipment that can meet the load demand of the line from the equipment library, and when there is no suitable power grid equipment in the equipment library, it can be purchased in advance, and suitable power grid equipment can be selected from the equipment library in time for replacement, so as to improve the power supply quality of the distribution network and ensure the safe and stable operation of the distribution network.

[0079] Embodiment 2

[0080] Figure 2 This is a flow chart of a method for selecting a power grid device provided in the second embodiment of the present invention. The embodiment of the present invention is optimized on the basis of the above-mentioned first embodiment. Figure 2 As shown, the power grid equipment selection method includes:

[0081] S201. Obtain historical load data of the line where the monitored power grid equipment is located.

[0082] The load data of the line where the power grid equipment is located can be recorded according to a preset period and stored in a database to obtain the historical load data of the line where the power grid equipment is located. For example, the load of the line can be recorded according to a period of one hour, one day, etc. to obtain the historical load data of the transmission line in a certain time period, such as the historical load data per hour in the past year, one quarter, or one month.

[0083] S202: Input historical load data into a preset load forecasting model to obtain the load demand of the line.

[0084] In an optional embodiment, the load forecasting model can be an autoregressive integrated moving average model (ARIMA), which is a classic time series forecasting model suitable for data with trends and seasonality. The ARIMA model includes an autoregressive part (AR), a difference part (I) and a moving average part (MA), wherein the autoregressive part is used to analyze the correlation between the current value and the value at the previous time point. In this embodiment, the autoregressive part captures the autocorrelation of historical load data, that is, the relationship between the load at the current time point and the load at the past several historical time points; the difference part is used to differentiate the time series to make it stable, that is, the difference part is used to process the non-stationarity of the data, by differentiating the original data, it is converted into a stable time series, in this embodiment, the difference part is used to differentiate the time series historical load data to obtain stable historical load data; the moving average part represents a linear combination of the current value and the error term of the previous few time points. In this embodiment, the moving average part captures the random fluctuations and irregularities in the historical load data, and models it by moving the error term.

[0085] After obtaining historical load data, such as the load of the line every hour or every day in a certain period of time in the past, this embodiment can generate a load time series diagram in chronological order, and then perform a stationarity test in the differential part, such as testing the stationarity of the load time series through statistical detection algorithms such as ADF (Augmented Dickey-Fuller). When it is detected that the load time series is not stable, differential processing can be performed to make the load time series tend to be stable. Furthermore, in the autoregressive part, the autocorrelation function (ACF) and partial autocorrelation function (PACF) can be used for analysis.

[0086] Autocorrelation function ACF (Autocorrelation Function), ACF is a function that calculates the correlation of the time series itself. It is used to calculate the correlation of time series data under different lags. By calculating the ACF value and drawing the ACF graph, the autocorrelation of load data under different lags can be observed. If some lag values ​​in the ACF graph have significant autocorrelation, it indicates that there is a correlation between the current value and the lag value. The partial autocorrelation function (PACF) can also be used to calculate the autocorrelation under different lags after eliminating the influence of the intermediate lag. By calculating the PACF value and drawing the PACF graph, if some lag values ​​in the PACF graph have significant partial autocorrelation, it indicates that there is a direct correlation between the current value and the lag value.

[0087] When constructing the ARIMA model and selecting the model parameters of the ARIMA model, the appropriate autoregressive order p and moving average order q can be selected according to the ACF graph and the PACF graph. For example, the ACF graph gradually decays and the PACF graph is cut off at a certain lag point. You can consider selecting the corresponding autoregressive order p. The PACF graph gradually decays and the ACF graph is cut off at a certain lag point. You can consider selecting the corresponding moving average order q. By performing one or more difference processing on the load time series, the data is stabilized and the difference order d is determined. If the load time series is seasonal, it is necessary to determine the seasonal parameters (P, D, Q, m), where m is the seasonal cycle.

[0088] The above is an ARIMA model. Specifically in this embodiment, the historical load data can be first processed by removing outliers, filling missing values, smoothing, etc. to ensure the quality and stability of the historical load data. Then, according to the seasonal characteristics of the historical load data, the autoregressive part (AR), the difference part (I) and the moving average part (MA) of the ARIMA model are determined, and the parameters of each part are determined, that is, the autoregressive order p, the moving average order q, the difference order d and the seasonal cycle m are determined, so as to complete the ARIMA model construction. Then, the constructed ARIMA model is trained using the historical load data. During the training, the maximum likelihood estimation function can be used to estimate the model parameters, as follows:

[0089]

[0090] Among them, L(θ) is the function value of the maximum likelihood estimation function, θ is the combination of ARIMA model parameters, and y t is the actual load value at time t, is the load value predicted by the model parameter θ at time t, σ is the variance of the set residual, T is the number of moments included in a cycle, and the cycle includes multiple moments t. Take t as every day as an example, T is a month. After obtaining a month of historical load data, the load on the 16th day can be predicted by the load of the first 15 days of a month. Substitute the actual load value and the predicted load value on the 16th day into the above formula.

[0091] For the convenience of calculation, the log-likelihood function is as follows:

[0092]

[0093] Then, the Newton-Raphson method and BFGS (Broyden-Fletcher-Goldfarb-Shanno) are used to maximize the log-likelihood function to obtain the estimated value of the parameter combination θ, that is, the trained ARIMA model is obtained. The historical load data is input into the preset load forecasting model ARIMA to obtain the load demand of the line in the future.

[0094] Of course, in practical applications, the load forecasting model can also be various convolutional neural networks, recurrent neural networks, and deep neural networks instead of just the ARIMA model. When the load forecasting model is various convolutional neural networks, recurrent neural networks, and deep neural networks, the training method of the load forecasting model can refer to the supervised training method of convolutional neural networks, recurrent neural networks, and deep neural networks, which will not be described in detail here.

[0095] This embodiment predicts the load demand of the line by inputting the historical load data of the line into the load prediction model, so as to determine whether the rated capacity of the power grid equipment meets the load demand through the load demand, thereby achieving early prediction.

[0096] S203. Obtain influencing factor data of power grid equipment.

[0097] In this embodiment, the influencing factor data may include operating environment data and operating status data of power grid equipment. The operating environment data may include at least one of temperature, humidity, vibration amplitude, vibration frequency, dust concentration, air pressure and other data. The equipment operating status data may include at least one of load rate, operating voltage, operating current, power factor, insulation resistance and other data. The influencing factor data can be collected by sensors and stored in a database, and the influencing factor data of power grid equipment can be read from the database.

[0098] S204. Input the influencing factor data into a multiple linear regression model to obtain the rated capacity of the power grid equipment.

[0099] Specifically, the expression of the multiple linear regression model is as follows:

[0100] C=β0+β1x1+β2x2+…+β n x n +ε;

[0101] Among them, C is the rated capacity of the power grid equipment in the future time period, x1, x2, ..., x n are the influencing factor data, β1,β2,…,β n is the regression coefficient, β0 represents the intercept term, and ε represents the random error term.

[0102] In this embodiment, the intercept term and each regression coefficient of the multivariate linear regression model can be solved by the least squares method, and the specific process is as follows:

[0103] Construct a linear regression model in matrix form. There are n sample observations, each sample has p influencing factor data. For example, the rated capacity of the power grid equipment is revised n times during use. Each revised rated capacity is used as a sample observation. At the same time, each time the rated capacity is revised, there are P influencing factor data. The recorded sample is (Yi, Xi), where Yi is the observation value of the i-th sample, and Xi is the set of P influencing factor data in the i-th sample. The linear regression model in matrix form is constructed as follows:

[0104] Y = Xβ + ε;

[0105] Y is the n×1 dependent variable vector, X is the n×(p+1) independent variable matrix, the first column is all 1s indicating the intercept term, β is the (p+1)×1 regression coefficient vector, and ε is the n×1 random error vector;

[0106] Estimate the regression coefficients using the least squares method:

[0107] β'=(X'X) -1 *X'Y;

[0108] X' represents the transposed matrix of X, (X'X) -1 Represents the inverse matrix of X'X. After calculating the intercept term β0 and each regression coefficient to obtain β', each element is taken as the estimated value of the regression coefficient, and β'0 is used as the estimated value of the intercept term β0; β'1, β'2, …, β' n As β1, β2, …, β n The specific process can refer to the least squares method and will not be described in detail here.

[0109] Furthermore, the coefficient of determination was used to evaluate the goodness of fit of the multiple linear regression model:

[0110]

[0111] SSE represents the residual sum of squares, that is, the difference between the actual value y and the predicted value The sum of squares of the difference between the actual value y and the predicted value The sum of squares of the differences in the means of y i represents the actual value of the i-th sample; Represents the predicted value of the i-th sample; It represents the sample mean and is evaluated using the coefficient of determination R2. It can be understood as the proportion of the variation in the dependent variable that can be explained by the estimated multiple linear regression equation. The coefficient of determination R2 measures the degree to which each independent variable explains the variation in the dependent variable. The coefficient of determination R2 ranges from 0 to 1. The closer the coefficient of determination R2 is to 1, the higher the degree of explanation of the variable. The closer the coefficient of determination R2 is to 0, the weaker the degree of explanation of the coefficient of determination R2.

[0112] In addition, the F test can also be used to test the significance of the multiple linear regression model:

[0113]

[0114] In the formula: SSR = SST-SSE, which means regression sum of squares, p means the number of independent variables, i.e. the number of influencing factor data, and n means sample capacity, i.e. the number of samples;

[0115] Furthermore, the t-test can be used to test the significance of each regression coefficient:

[0116]

[0117] β j represents the estimated value of the jth regression coefficient, se(β j ) represents β j The standard error of .

[0118] When the goodness of fit, the significance of the multivariate linear regression model, and the significance of the regression coefficient meet the requirements, the result of this round of iterative solution is determined as the final intercept term and each regression coefficient.

[0119] This embodiment predicts the rated capacity of power grid equipment in the future through a multivariate linear regression model, so as to determine whether the load demand is met through the rated capacity in the future, thereby achieving early prediction.

[0120] S205: Determine whether the rated capacity is less than the load demand.

[0121] In one embodiment, when the rated capacity is less than the load demand, it is determined that the rated capacity does not meet the load demand, and S206 can be executed. When the rated capacity is greater than the load demand, it is determined that the rated capacity meets the load demand, that is, there is no need to replace the power grid equipment on the line, and the process can be ended.

[0122] S206. Determine the product of the load demand and the preset coefficient as the minimum rated capacity.

[0123] In this embodiment, the preset coefficient may be a coefficient greater than 1 to ensure that the minimum rated capacity is greater than the load demand, and a certain margin is reserved relative to the load demand to improve the reliability of the power grid equipment.

[0124] S207 . Determine from the device library the power grid devices whose rated capacity is greater than the minimum rated capacity and whose difference between the rated capacity and the minimum rated capacity is less than a preset value as the first candidate device set.

[0125] Specifically, power grid devices with rated capacity greater than the minimum rated capacity can be screened out from the equipment library first, and then the difference between the rated capacity of the screened power grid devices and the minimum rated capacity can be calculated, and the power grid devices with the difference less than the preset value can be determined as the first candidate device set to avoid selecting power grid devices with excessively large rated capacity as target power grid devices and causing waste of resources.

[0126] S208. Obtain working requirement parameters of power grid equipment in the line.

[0127] In this embodiment, the working requirement parameters of the power grid equipment of the line can be determined by the line, and the specific process is as follows:

[0128] Grid topology analysis:

[0129] Collect grid topology data, including the connection relationship and line parameters between each node, draw a grid topology diagram, mark each node and power line, analyze the power line, and determine the main line, substation location and load center.

[0130] Grid voltage analysis:

[0131] Estimate the voltage level of each node, consider factors such as voltage drop and voltage stability, and determine the minimum and maximum voltage levels to ensure that power grid equipment can operate normally within the determined voltage range.

[0132] Grid current analysis:

[0133] Calculate the current load of each node, consider the load type and size, and determine the maximum current load that the grid equipment needs to withstand.

[0134] Power factor analysis:

[0135] Analyze the power factor of each node in the power grid, consider the actual power and apparent power of the power grid equipment, and determine the power factor requirements that the power grid equipment needs to meet. The power factor calculation formula is: Power factor = active power / apparent power, where active power is the actual power consumed and apparent power is the rated voltage of the power grid equipment multiplied by the rated current.

[0136] Environmental conditions analysis:

[0137] Considering the environmental conditions of the grid nodes, including temperature, humidity and other factors, the operating temperature range of the grid equipment is determined to ensure the reliability and stability of the grid equipment under various environmental conditions.

[0138] S209: Select power grid devices whose working parameters meet working requirement parameters from the first candidate device set as the second candidate device set.

[0139] That is, power grid equipment whose operating voltage, operating current, power, operating temperature and humidity meet the voltage, current, power, temperature and humidity of the line is selected from the first candidate equipment set to obtain the second candidate equipment set to ensure that the selected target power grid equipment can operate normally in the line environment.

[0140] S210 . Select a low-cost power grid device from the second candidate device set as a target power grid device.

[0141] Each power grid equipment in the equipment library has a purchase price. The power grid equipment with the lowest purchase price in the second candidate equipment set can be used as the target power grid equipment, so that the target power grid equipment can be obtained from the equipment library before reaching a future time point to replace the power grid equipment on the line. If a suitable target power grid equipment is selected from the equipment library, the purchase target power grid equipment can be extracted according to the future time point.

[0142] The embodiment of the present invention uses the historical load data of the line where the power grid equipment is located to predict the future load demand of the line through the ARIMA model, and predicts the future rated capacity of the power grid equipment through the influencing factor data of the power grid equipment and the multivariate linear regression model. When it is determined that the rated capacity cannot meet the load demand, the minimum rated capacity is determined according to the load demand, and the target power grid equipment is selected from the equipment library according to the minimum rated capacity. It is possible to predict whether the rated capacity of the power grid equipment in the future time period meets the load demand of the line, so as to select the power grid equipment that can meet the load demand of the line from the equipment library, and when there is no suitable power grid equipment in the equipment library, it can be purchased in advance and the suitable power grid equipment can be selected from the equipment library in time for replacement, so as to improve the power supply quality of the distribution network and ensure the safe and stable operation of the distribution network.

[0143] Embodiment 3

[0144] Figure 3 This is a schematic diagram of the structure of a power grid equipment selection device provided in the third embodiment of the present invention. Figure 3 As shown, the power grid equipment selection device includes:

[0145] The historical load data acquisition module 301 is used to acquire the historical load data of the line where the monitored power grid equipment is located;

[0146] A load prediction module 302, configured to predict the load demand of the line according to the historical load data;

[0147] An influencing factor data acquisition module 303 is used to acquire influencing factor data of the power grid equipment;

[0148] A rated capacity prediction module 304, configured to determine the rated capacity of the power grid equipment based on the influencing factor data;

[0149] A judgment module 305 is used to determine whether the rated capacity meets the load demand according to the load demand and the rated capacity, and if not, execute a minimum rated capacity determination module 306;

[0150] A minimum rated capacity determination module 306, configured to determine a minimum rated capacity according to the load demand;

[0151] The target power grid device selection module 307 is used to select a target power grid device from the device library according to the minimum rated capacity.

[0152] Optionally, the load prediction module 302 includes:

[0153] The load forecasting model forecasting unit is used to input the historical load data into a preset load forecasting model to obtain the load demand of the line.

[0154] Optionally, the load forecasting model is an autoregressive differential moving average model, and the load forecasting model prediction unit is used to:

[0155] Determining the autoregressive order, the difference order, the moving average order and the seasonal parameter of the autoregressive difference moving average model according to the historical load data;

[0156] The historical load data is input into an autoregressive difference moving average model after determining parameters to obtain the load demand of the line.

[0157] Optionally, the rated capacity prediction module 304 includes:

[0158] The multiple linear regression model prediction unit is used to input the influencing factor data into the multiple linear regression model to obtain the rated capacity of the power grid equipment.

[0159] Optionally, the expression of the multivariate linear regression model is as follows:

[0160] C=β0+β1x1+β2x2+…+β n x n +ε;

[0161] Where C is the rated capacity of the grid equipment in the future time period, x1, x2, …, x n are the influencing factor data, β1,β2,…,β n is the regression coefficient, β0 represents the intercept term, and ε represents the random error term.

[0162] Optionally, the judging module 305 includes:

[0163] A judging unit, used to judge whether the rated capacity is less than the load demand, if so, execute the first determining unit, if not, execute the second determining unit;

[0164] a first determining unit, configured to determine that the rated capacity does not meet the load demand when the rated capacity is less than the load demand;

[0165] a second determining unit, configured to determine that the rated capacity satisfies the load demand when the rated capacity is greater than the load demand;

[0166] The minimum rated capacity determination module 306 includes:

[0167] A product calculation unit is used to determine the product of the load demand and a preset coefficient as the minimum rated capacity, wherein the preset coefficient is a coefficient greater than 1.

[0168] Optionally, the target power grid device selection module 307 includes:

[0169] A first candidate device set determining unit, configured to determine, from a device library, power grid devices whose rated capacity is greater than the minimum rated capacity and whose difference between the rated capacity and the minimum rated capacity is less than a preset value, as a first candidate device set;

[0170] A working requirement parameter acquisition unit, used to acquire working requirement parameters of power grid equipment in the line;

[0171] A second candidate device set determining unit, configured to select, from the first candidate device set, power grid devices whose operating parameters meet the operating requirement parameters as the second candidate device set;

[0172] The target power grid device selection unit is used to select a power grid device with low cost from the second candidate device set as a target power grid device.

[0173] The power grid equipment selection device provided in the embodiment of the present invention can execute the power grid equipment selection method provided in any embodiment of the present invention, and has the corresponding functional modules and beneficial effects of the execution method.

[0174] Embodiment 4

[0175] Figure 4A schematic diagram of the structure of an electronic device 40 that can be used to implement an embodiment of the present invention is shown. The electronic device is intended to represent various forms of digital computers, such as laptop computers, desktop computers, workstations, personal digital assistants, servers, blade servers, mainframe computers, and other suitable computers. The electronic device can also represent various forms of mobile devices, such as personal digital processing, cellular phones, smart phones, wearable devices (such as helmets, glasses, watches, etc.) and other similar computing devices. The components shown herein, their connections and relationships, and their functions are merely examples and are not intended to limit the implementation of the present invention described and / or required herein.

[0176] like Figure 4 As shown, the electronic device 40 includes at least one processor 41, and a memory connected to the at least one processor 41, such as a read-only memory (ROM) 42, a random access memory (RAM) 43, etc., wherein the memory stores a computer program that can be executed by at least one processor, and the processor 41 can perform various appropriate actions and processes according to the computer program stored in the read-only memory (ROM) 42 or the computer program loaded from the storage unit 48 to the random access memory (RAM) 43. In the RAM 43, various programs and data required for the operation of the electronic device 40 can also be stored. The processor 41, the ROM 42, and the RAM 43 are connected to each other through a bus 44. An input / output (I / O) interface 45 is also connected to the bus 44.

[0177] A number of components in the electronic device 40 are connected to the I / O interface 45, including: an input unit 46, such as a keyboard, a mouse, etc.; an output unit 47, such as various types of displays, speakers, etc.; a storage unit 48, such as a disk, an optical disk, etc.; and a communication unit 49, such as a network card, a modem, a wireless communication transceiver, etc. The communication unit 49 allows the electronic device 40 to exchange information / data with other devices through a computer network such as the Internet and / or various telecommunication networks.

[0178] The processor 41 may be a variety of general and / or special processing components with processing and computing capabilities. Some examples of the processor 41 include, but are not limited to, a central processing unit (CPU), a graphics processing unit (GPU), various special artificial intelligence (AI) computing chips, various processors running machine learning model algorithms, a digital signal processor (DSP), and any appropriate processor, controller, microcontroller, etc. The processor 41 executes the various methods and processes described above, such as a method for selecting a power grid device.

[0179] In some embodiments, the grid device selection method may be implemented as a computer program, which is tangibly contained in a computer-readable storage medium, such as a storage unit 48. In some embodiments, part or all of the computer program may be loaded and / or installed on the electronic device 40 via the ROM 42 and / or the communication unit 49. When the computer program is loaded into the RAM 43 and executed by the processor 41, one or more steps of the grid device selection method described above may be performed. Alternatively, in other embodiments, the processor 41 may be configured to execute the grid device selection method in any other appropriate manner (e.g., by means of firmware).

[0180] Various implementations of the systems and techniques described above herein can be implemented in digital electronic circuit systems, integrated circuit systems, field programmable gate arrays (FPGAs), application specific integrated circuits (ASICs), application specific standard products (ASSPs), systems on chips (SOCs), complex programmable logic devices (CPLDs), computer hardware, firmware, software, and / or combinations thereof. These various implementations can include: being implemented in one or more computer programs that can be executed and / or interpreted on a programmable system including at least one programmable processor, which can be a special purpose or general purpose programmable processor that can receive data and instructions from a storage system, at least one input device, and at least one output device, and transmit data and instructions to the storage system, the at least one input device, and the at least one output device.

[0181] Computer programs for implementing the methods of the present invention may be written in any combination of one or more programming languages. These computer programs may be provided to a processor of a general-purpose computer, a special-purpose computer, or other programmable data processing device, so that when the computer program is executed by the processor, the functions / operations specified in the flow chart and / or block diagram are implemented. The computer program may be executed entirely on the machine, partially on the machine, partially on the machine and partially on a remote machine as a stand-alone software package, or entirely on a remote machine or server.

[0182] In the context of the present invention, a computer-readable storage medium may be a tangible medium that may contain or store a computer program for use by or in combination with an instruction execution system, device or equipment. A computer-readable storage medium may include, but is not limited to, electronic, magnetic, optical, electromagnetic, infrared, or semiconductor systems, devices or equipment, or any suitable combination of the foregoing. Alternatively, a computer-readable storage medium may be a machine-readable signal medium. A more specific example of a machine-readable storage medium may include an electrical connection based on one or more lines, a portable computer disk, a hard disk, a random access memory (RAM), a read-only memory (ROM), an erasable programmable read-only memory (EPROM or flash memory), an optical fiber, a portable compact disk read-only memory (CD-ROM), an optical storage device, a magnetic storage device, or any suitable combination of the foregoing.

[0183] To provide interaction with a user, the systems and techniques described herein may be implemented on an electronic device having: a display device (e.g., a CRT (cathode ray tube) or LCD (liquid crystal display) monitor) for displaying information to the user; and a keyboard and a pointing device (e.g., a mouse or trackball) through which the user can provide input to the electronic device. Other types of devices may also be used to provide interaction with the user; for example, the feedback provided to the user may be any form of sensory feedback (e.g., visual feedback, auditory feedback, or tactile feedback); and input from the user may be received in any form (including acoustic input, voice input, or tactile input).

[0184] The systems and techniques described herein may be implemented in a computing system that includes backend components (e.g., as a data server), or a computing system that includes middleware components (e.g., an application server), or a computing system that includes frontend components (e.g., a user computer with a graphical user interface or a web browser through which a user can interact with implementations of the systems and techniques described herein), or a computing system that includes any combination of such backend components, middleware components, or frontend components. The components of the system may be interconnected by any form or medium of digital data communication (e.g., a communication network). Examples of communication networks include: a local area network (LAN), a wide area network (WAN), a blockchain network, and the Internet.

[0185] A computing system may include a client and a server. The client and the server are generally remote from each other and usually interact through a communication network. The client and server relationship is generated by computer programs running on the corresponding computers and having a client-server relationship with each other. The server may be a cloud server, also known as a cloud computing server or cloud host, which is a host product in the cloud computing service system to solve the defects of difficult management and weak business scalability in traditional physical hosts and VPS services.

[0186] It should be understood that the various forms of processes shown above can be used to reorder, add or delete steps. For example, the steps described in the present invention can be executed in parallel, sequentially or in different orders, as long as the desired results of the technical solution of the present invention can be achieved, and this document does not limit this.

[0187] The above specific implementations do not constitute a limitation on the protection scope of the present invention. It should be understood by those skilled in the art that various modifications, combinations, sub-combinations and substitutions can be made according to design requirements and other factors. Any modification, equivalent substitution and improvement made within the spirit and principle of the present invention should be included in the protection scope of the present invention.

Claims

1. A method for selecting power grid equipment, characterized in that: include: Obtain historical load data of the line where the monitored power grid equipment is located; predicting the load demand of the line according to the historical load data; Acquiring influencing factor data of the power grid equipment; Determine the rated capacity of the power grid equipment based on the influencing factor data; Determining whether the rated capacity meets the load demand according to the load demand and the rated capacity; If not, determine the minimum rated capacity based on the load demand; A target power grid device is selected from a device library according to the minimum rated capacity.

2. The method for selecting power grid equipment according to claim 1, characterized in that: The predicting the load demand of the line according to the historical load data comprises: The historical load data is input into a preset load forecasting model to obtain the load demand of the line.

3. The method for selecting power grid equipment according to claim 1, characterized in that: The load forecasting model is an autoregressive differential moving average model. The historical load data is input into a preset load forecasting model to obtain the load demand of the line, including: Determining the autoregressive order, the difference order, the moving average order and the seasonal parameter of the autoregressive difference moving average model according to the historical load data; The historical load data is input into an autoregressive difference moving average model after determining parameters to obtain the load demand of the line.

4. The method for selecting power grid equipment according to claim 1, characterized in that: Determining the rated capacity of the power grid device based on the influencing factor data includes: The influencing factor data is input into a multiple linear regression model to obtain the rated capacity of the power grid equipment.

5. The method for selecting power grid equipment according to claim 4, characterized in that: The expression of the multivariate linear regression model is as follows: C=β0+β1x1+β2x2+…+β n x n +e; Where C is the rated capacity of the power grid equipment, x1, x2, ..., x n are the influencing factor data, β1,β2,…,β n is the regression coefficient, β0 represents the intercept term, and ε represents the random error term.

6. The method for selecting power grid equipment according to claim 1, characterized in that: Determining whether the rated capacity meets the load demand according to the load demand and the rated capacity includes: Determine whether the rated capacity is less than the load demand; When the rated capacity is less than the load demand, determining that the rated capacity does not meet the load demand; When the rated capacity is greater than the load demand, determining that the rated capacity meets the load demand; Determine the minimum rated capacity based on the stated load requirements, including: The product of the load demand and a preset coefficient is determined as the minimum rated capacity, wherein the preset coefficient is a coefficient greater than 1.

7. The method for selecting power grid equipment according to claim 1, characterized in that: Selecting target power grid equipment from the equipment library according to the minimum rated capacity includes: Determine from the device library the power grid devices whose rated capacity is greater than the minimum rated capacity and whose difference between the rated capacity and the minimum rated capacity is less than a preset value as the first candidate device set; Obtaining working requirement parameters of power grid equipment in the line; Selecting power grid devices whose operating parameters meet the operating requirement parameters from the first candidate device set as the second candidate device set; A low-cost power grid device is selected from the second candidate device set as the target power grid device.

8. A power grid equipment selection device, characterized in that: include: A historical load data acquisition module is used to acquire historical load data of the line where the monitored power grid equipment is located; A load prediction module, used for predicting the load demand of the line according to the historical load data; An influencing factor data acquisition module, used to acquire influencing factor data of the power grid equipment; A rated capacity prediction module, used to determine the rated capacity of the power grid equipment based on the influencing factor data; A judgment module, used for determining whether the rated capacity meets the load demand according to the load demand and the rated capacity, and if not, executing a minimum rated capacity determination module; A minimum rated capacity determination module, used to determine the minimum rated capacity according to the load demand; The target power grid equipment selection module is used to select the target power grid equipment from the equipment library according to the minimum rated capacity.

9. An electronic device, characterized in that: The electronic device comprises: at least one processor; and a memory communicatively connected to the at least one processor; wherein, The memory stores a computer program executable by the at least one processor, and the computer program is executed by the at least one processor so that the at least one processor can execute the power grid device selection method according to any one of claims 1 to 7.

10. A computer-readable storage medium, characterized in that: The computer-readable storage medium stores computer instructions, and the computer instructions are used to enable a processor to implement the method for selecting a power grid device according to any one of claims 1 to 7 when executed.

Citation Information

Cited By

  • Efficient ultrahigh-pressure water jet cleaning system and method

    CN119747276A