Tensioning system, monitoring device and monitoring method

By using coils and connecting rods made of shape memory alloy and using switch components to control the current direction, the compensated tension and monitoring of prestressed FRP are realized, which solves the problem of irreversible deformation of high-strength screws in the existing technology, reduces construction costs and Improved operational ease of monitoring.

CN118746486AActive Publication Date: 2024-10-08GUANGZHOU UNIVERSITY
View PDF 8 Cites 0 Cited by

Patent Information

Application Number
CN202410716960.1
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-06-04
Publication Date
2024-10-08
Estimated Expiration
2044-06-04

AI Technical Summary

Technical Problem

In the existing prestressed FRP tensioning system, the deformation of the high-strength screw is difficult to identify and the cost is high, and the operation is difficult. The deformation of the high-strength screw is irreversible, resulting in the inability to compensate for the tension when the prestressed FRP shrinks, which increases the construction cost.

Method used

It uses coils and connecting rods made of shape memory alloys, controls the current direction through switch components, uses the shape memory characteristics of the coils and connecting rods to achieve compensated tension, and monitors prestress through resistance changes. It is easy to operate and low-cost.

Benefits of technology

It realizes prestress monitoring and compensated tensioning of the tested materials, reduces construction costs, is simple to operate, has little disturbance to the structure, and will not cause additional damage.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118746486A_ABST
    Figure CN118746486A_ABST
Patent Text Reader

Abstract

The invention discloses a tensioning system, a monitoring device and a monitoring method.The tensioning system comprises a coil, a connecting rod and an electric wire, the coil and the connecting rod are both made of shape memory alloy, the tensioning end of the connecting rod is connected with a tested material, the coil is wound around the connecting rod, and the electric wire is connected with the coil. The two ends of the coil are connected with the connecting rod, an insulating layer is arranged on the outer surface of the coil, one end of the electric wire is connected with the coil, the other end of the electric wire is connected to the connecting rod to form a circuit, a switch assembly is arranged on the circuit, and long-term monitoring of the prestress of a tested material is achieved through coil resistance changes. The tension system is simple in structure and convenient to operate, a coil or a connecting rod can be excited directionally, the excitation mode is controllable, the operation is convenient, the monitoring device of the tension system is used for monitoring the prestress of a tested material, the operation is convenient, and the monitoring method of the tension system can be used for monitoring the tested material in real time.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application is used in the field of material monitoring technology, and in particular relates to a tensioning system, a monitoring device and a monitoring method. Background Art

[0002] At present, the main function of ordinary prestressed FRP (fiber reinforced composite material) tensioning system is to provide prestress to FRP at one time and fix the prestressed FRP after tensioning. After removing the jack and cutting off the excessively long screw, the high-strength screw that transmits the force is clamped between the wedge-shaped anchor at the tensioning end and the anchor base. Under long-term human disturbance and environmental influences, the high-strength screw resists the tension of the prestressed FRP through its own strength, thereby preventing the loss of prestress of FRP.

[0003] However, when only ordinary prestressed FRP tensioning systems are used, the deformation of high-strength screws is difficult to identify by visual inspection. Combined with the current mainstream monitoring methods such as monitoring instruments, laser radar, photogrammetry technology and GPS measurement technology, there are problems of high cost, difficulty in operation and high training and operation labor costs. In addition, since the deformation of high-strength screws is irreversible, when the prestressed FRP that has been in service for a long time shrinks, the high-strength screws will be extended, the cross-section will become smaller, and compensatory tensioning cannot be achieved. If the prestressed FRP is re-tensioned, it will cost a lot of construction costs. Summary of the invention

[0004] The purpose of the present application is to solve at least one of the technical problems existing in the prior art, and to provide a tensioning system, a monitoring device and a monitoring method, wherein the tensioning system can realize compensatory tensioning, and the monitoring device of the tensioning system is used to monitor the prestress of the material to be tested, which is easy to operate, and the monitoring method of the tensioning system can monitor the material to be tested in real time.

[0005] The technical solution adopted by this application to solve its technical problem is:

[0006] A tensioning system comprises a coil, a connecting rod and an electric wire, wherein the coil and the connecting rod are both made of shape memory alloy, the tensioning end of the connecting rod is connected to a material to be tested, the coil is wound around the connecting rod, both ends of the coil are connected to the connecting rod, an insulating layer is provided on the outer surface of the coil, one end of the electric wire is connected to the coil, and the other end of the electric wire is connected to the connecting rod to form a circuit, and a switch component is provided on the circuit.

[0007] In certain embodiments of the present application, a first connection portion is provided at a welding point between one end of the coil and the connecting rod, and a second connection portion is provided at a welding point between the other end of the coil and the connecting rod.

[0008] In certain embodiments of the present application, the switch assembly is arranged between the first wiring part and the electric wire, and the switch assembly includes a rotating rod and an insulating sleeve. The electric wire extends into the insulating sleeve, the rotating rod is connected to the first wiring part, and a first connector is provided on the outer periphery of the rotating rod. Rotating the rotating rod can connect or disconnect the first connector with the electric wire.

[0009] In certain embodiments of the present application, a third wiring portion is provided in the insulating sleeve, one end of the third wiring portion is connected to the electric wire, and the other end forms a second connector on the inner circumference of the insulating sleeve, and rotating the rotating rod can connect or disconnect the first connector and the second connector, and a connecting portion is provided between the third wiring portion and the coil.

[0010] In certain embodiments of the present application, an insulating contact is provided on the rotating rod, and rotating the rotating rod can connect the first connector to the insulating contact.

[0011] In certain embodiments of the present application, the second connector includes a metal contact and a reaction spring, and the reaction spring is disposed inside the metal contact.

[0012] In certain embodiments of the present application, an anchor is provided at the tensioning end of the connecting rod, and the anchor is used to fix the material to be tested.

[0013] In certain embodiments of the present application, a base is provided at the fixed end of the connecting rod, and the base is used to fix the connecting rod.

[0014] The present application also provides a monitoring device, comprising a device body and the tensioning system in the above embodiment, wherein the fixed end of the material to be measured is connected to the device body.

[0015] The present application also provides a monitoring method using the tensioning system in the above embodiment, which is characterized by comprising the following steps:

[0016] Step 1: disconnect the switch assembly, excite the coil, and measure the resistance of the coil;

[0017] Step 2: closing the switch assembly, generating heat to cause the connecting rod to contract and increase its cross section, thereby achieving compensatory tensioning;

[0018] Repeat the step 1 and the step 2, monitor the change of the difference between the resistances of the coil measured twice adjacently, and realize the prestress monitoring of the measured material.

[0019] One of the above technical solutions has at least one of the following advantages or beneficial effects: when using the tensioning system, a switch assembly is used to control the direction of the current. Since the coil and the connecting rod are both made of shape memory alloy, the switch assembly is in the disconnected state. At this time, power is turned on to generate heat to excite the coil. Since both ends of the coil are connected to the connecting rod, the coil and the connecting rod form a series system. Since an insulating layer is provided on the outer surface of the coil, the coil is regarded as an insulator, and the current only acts on the coil, that is, the coil is excited. After power is turned on and the heat is excited, the coil is tightly wound around the connecting rod and deforms synchronously with the connecting rod, and the resistance of the coil during uncompensated tensioning is measured; then, the switch assembly is in the closed state, and the wires are connected at this time, connecting the coil and the connecting rod in parallel, that is, the coil and the connecting rod form a parallel system. At this time, The coil is excited. Since the resistance of the coil is much greater than the resistance of the connecting rod, the current flows to the connecting rod, which is energized for heat excitation. The shape memory property of the connecting rod is used to shrink the connecting rod and increase its cross-section to achieve compensatory tensioning. Then the switch assembly is disconnected to measure the resistance of the coil after the deformation of the connecting rod. The prestress loss of the material under test (FRP material) is monitored through the correlation between the resistance value and the prestress value. The tensioning system realizes long-term monitoring of the prestress of the material under test through the change of coil resistance, and can excite the coil or connecting rod in a direction to achieve controllable excitation mode and easy operation. The tensioning system is used in the monitoring device, which has little disturbance to other structures and basically does not cause additional damage. The monitoring method of the tensioning system can continuously monitor the prestress of the material under test.

[0020] Additional aspects and advantages of the present application will be given in part in the description below, and in part will become apparent from the description below, or will be learned through the practice of the present application. BRIEF DESCRIPTION OF THE DRAWINGS

[0021] The above and / or additional aspects and advantages of the present application will become apparent and easily understood from the description of the embodiments in conjunction with the following drawings, in which:

[0022] Figure 1 is a structural schematic diagram of an embodiment of the tensioning system in the present application;

[0023] Figure 2 yes Figure 1 The enlarged view of point A in the middle;

[0024] Figure 3 yes Figure 2 Cross-section at the middle BB;

[0025] Figure 4 yes Figure 3 Cross-section at CC;

[0026] Figure 5 It is a partial structural schematic diagram of an embodiment of the tensioning system in the present application. DETAILED DESCRIPTION

[0027] This section will describe in detail the specific embodiments of the present application. The preferred embodiments of the present application are shown in the accompanying drawings. The purpose of the accompanying drawings is to supplement the description of the text part of the specification with graphics, so that people can intuitively and vividly understand each technical feature and the overall technical solution of the present application, but it cannot be understood as a limitation on the scope of protection of the present application.

[0028] In the present application, if there is a description of directions (up, down, left, right, front and back), it is only for the convenience of describing the technical solution of the present application, and does not indicate or imply that the technical features referred to must have a specific orientation, be constructed and operate in a specific orientation. Therefore, it cannot be understood as a limitation on the present application.

[0029] In this application, "several" means one or more, "multiple" means more than two, "greater than", "less than", "exceed" and the like are understood to exclude the number itself; "above", "below", "within" and the like are understood to include the number itself. In the description of this application, if there is a description of "first" or "second", it is only used for the purpose of distinguishing technical features, and cannot be understood as indicating or implying relative importance or implicitly indicating the number of the indicated technical features or implicitly indicating the order of the indicated technical features.

[0030] In this application, unless otherwise clearly defined, the words "set", "install", "connect" and the like should be understood in a broad sense, for example, they can be directly connected or indirectly connected through an intermediate medium; they can be fixedly connected, detachably connected, or integrally formed; they can be mechanically connected, electrically connected, or able to communicate with each other; they can be the internal connection of two elements or the interaction relationship between two elements. Those skilled in the art can reasonably determine the specific meanings of the above words in this application in combination with the specific content of the technical solution.

[0031] in, Figure 1 The reference direction coordinate system of the embodiment of the present application is given. Figure 1 The embodiment of the present application is described with reference to the direction shown.

[0032] FRP (fiber reinforced composite material) tensioning system usually consists of tensioning components that provide support and reaction force, a force transmission connecting rod system and a jacking machine that applies tensioning force. It is used to provide prestress to the FRP at the interface of the reinforced structure. After the initial tensioning is completed, the jacking machine should be removed and the excessively long connecting rod should be cut off. Therefore, after the tensioning is completed, the system consists of tensioning components and a connecting rod system that provides reaction force. Since this system has certain advantages in tensioning effect, working method, ease of operation and cost convenience, it is widely used in the field of structural reinforcement.

[0033] The embodiment of the present application provides a tensioning system, see Figures 1 to 5 The tensioning system includes a coil 100, a connecting rod 200 and a wire 300. The coil 100 and the connecting rod 200 are both made of shape memory alloy. The tensioning end of the connecting rod 200 is connected to the material 400 to be tested. The coil 100 is wound on the connecting rod 200. Both ends of the coil 100 are connected to the connecting rod 200. An insulating layer is provided on the outer surface of the coil 100. One end of the wire 300 is connected to the coil 100, and the other end of the wire 300 is connected to the connecting rod 200 to form a circuit. A switch component 500 is provided on the circuit. When the tensioning system is used, The switch assembly 500 is used to control the direction of the current. Since the coil 100 and the connecting rod 200 are both made of shape memory alloy, the switch assembly 500 is in the disconnected state. At this time, the coil 100 is energized to generate heat and excite the coil. Since both ends of the coil 100 are connected to the connecting rod 200, the coil 100 and the connecting rod 200 form a series system. Since the outer surface of the coil 100 is provided with an insulating layer, the coil 100 is regarded as an insulator, and the current only acts on the coil 100, that is, the coil 100 is excited. After the coil 100 is energized and heated, the coil 100 is tightly wound around the connecting rod 200. The coil 100 is connected to the connecting rod 200 and deforms synchronously with the connecting rod 200, and the resistance of the coil 100 is measured when the tension is not compensated. Then, the switch assembly 500 is closed, and the wire 300 is connected at this time, and the coil 100 and the connecting rod 200 are connected in parallel, that is, the coil 100 and the connecting rod 200 form a parallel system. At this time, the coil 100 is excited. Since the resistance of the coil 100 is much greater than the resistance of the connecting rod 200, the current flows to the connecting rod 200, and the power is turned on to generate heat and excite, and the shape memory property of the connecting rod 200 is used to make the connecting rod 200 shrink and the cross section increase. , to achieve compensatory tensioning; then disconnect the switch assembly 500, measure the resistance of the coil 100 after the connecting rod 200 is deformed, and monitor the prestress loss of the material 400 (FRP material) under test through the correlation between the resistance value and the prestress value. The tensioning system realizes long-term monitoring of the prestress of the material under test through the change of the resistance of the coil 100, and can excite the coil 100 or the connecting rod 200 in a direction, so as to achieve controllable excitation mode and convenient operation. The tensioning system is used in the monitoring device, which has little disturbance to other structures and basically does not cause additional damage.

[0034] It is understandable that the winding pitch, diameter and material of the coil 100 have an impact on the excitation and monitoring effects, and an optimal monitoring excitation scheme should be proposed based on the degree of impact of these factors on excitation and monitoring.

[0035] A first wiring portion 110 is provided at the welding place between one end of the coil 100 and the connecting rod 200, and a second wiring portion 120 is provided at the welding place between the other end of the coil 100 and the connecting rod 200. After the welding between the two ends of the coil 100 and the connecting rod 200 is completed, they should be polished and smoothed to facilitate the installation of the terminal. The terminal is connected to the coil 100 and one end is connected to the wire. The first wiring portion 110 and the second wiring portion 120 are both wiring terminals, and the wiring terminals are used for powering on for excitation.

[0036] The switch assembly 500 is arranged between the first wiring part 110 and the electric wire 300. The switch assembly 500 includes a rotating rod 510 and an insulating sleeve 520. The electric wire 300 extends into the insulating sleeve 520. The rotating rod 510 is connected to the first wiring part 110. The outer periphery of the rotating rod 510 is provided with a first connector 511. Rotating the rotating rod 510 can connect or disconnect the first connector 511 with the electric wire 300. The insulating sleeve 520 is made of rubber material.

[0037] A third wiring portion 521 is provided in the insulating sleeve 520, one end of the third wiring portion 521 is connected to the electric wire 300, and the other end forms a second connector 530 on the inner circumference of the insulating sleeve 520. Rotating the rotating rod 510 can connect or disconnect the first connector 511 and the second connector 530. A connecting portion is provided between the third wiring portion 521 and the coil 100, and the connecting portion includes a metal sheet 522, that is, the metal sheet can connect the coil 100 and the rotating rod 510. Rotating the insulating sleeve 520 makes the metal contact on the rotating rod 510 contact with the metal contact on the rubber head, and the insulating switch is closed; rotating the insulating sleeve 520 makes the insulating contact 512 on the rotating rod 510 contact with the metal contact 531, and the insulating switch is disconnected.

[0038] An insulating contact 512 is disposed on the rotating rod 510 . The first connector 511 can be connected to the insulating contact 512 by rotating the rotating rod 510 . When the switch assembly 500 is disconnected, the first connector 511 and the insulating contact 512 are aligned.

[0039] See also Figure 4 The second connector 530 includes a metal contact 531 and a reaction spring 532 . The reaction spring 532 is disposed inside the metal contact 531 . The reaction spring is used to prevent the metal contact 531 from being excessively recessed.

[0040] An anchor 210 is provided at the tensioning end of the connecting rod 200 . The anchor 210 is used to fix the material 400 to be tested. The anchor 210 is a wedge-shaped anchor to connect the prestressed FRP and the connecting rod 200 .

[0041] A base 220 is provided at the fixed end of the connecting rod 200 , and the base 220 is used to fix the connecting rod 200 .

[0042] The present application also provides a monitoring device, including a device body and the tensioning system of any one of the above embodiments, the fixed end of the material 400 to be tested is connected to the device body, and the base 220 is arranged on the device body.

[0043] The initial tensioning process of the material 400 (FRP) under test is similar to the ordinary tensioning process. The monitoring device of the present application is used for monitoring and compensating tensioning after removing the jack and cutting off the excessively long connecting rod 200. After removing the jack and cutting off the excessively long connecting rod 200, the switch assembly 500 should be disconnected and the initial resistance value of the coil 100 should be collected.

[0044] Among them, the steps of using the monitoring device to initially tension the material 400 (FRP) under test are as follows: 1. Accurately locate and lay out the FRP and anchor positions;

[0045] 2. Drill and grind at corresponding positions according to design requirements;

[0046] 3. Make grooves along the anchor block line area at both ends, with a depth of about 3cm;

[0047] 4. After the grooving is completed, use repair glue to repair it, and grind it smooth after it is completely cured;

[0048] 5. Implant high-strength chemical bolts in the holes or use high-strength mechanical anchor bolts, with the anchor bolt grade not less than 8.8;

[0049] 6. According to the limit frames at both ends, place the anchor blocks in the limit frames respectively, keep the center lines of both ends consistent and fixed, and ensure that the anchor blocks at the tensioning end can slide freely in the limit frames;

[0050] 7. Cut the FRP, leaving 5 to 10 cm at both ends, install the FRP into the wedge-shaped hole of the anchor, slide the tension end anchor block to the starting position, and clamp it with a clamp;

[0051] 8. Install the tensioning system, gasket, nut, baffle and jack at the tensioning end in sequence. The end of the connecting rod (screw) passes through the wedge-shaped anchor, base and baffle at the tensioning end. Adjust the jack to a tight state. The force direction of the jack coincides with the central axis of the FRP plate.

[0052] 9. Take protective measures on site and start pre-tensioning. After unloading the pre-tensioning, evenly apply structural adhesive on the FRP surface, and then carry out formal tensioning step by step. After each level of tensioning, the load must be held for 3 to 5 minutes, and the corresponding tension and elongation must be recorded before proceeding to the next level of tensioning;

[0053] 10. After the tensioning is completed, tighten the nut, remove the jack, cut off the excessively long connecting rod 200, set a pressure plate every two meters to fix it, and apply slight pressure;

[0054] 11. Finally, use fire-retardant and anti-corrosion coating to protect the anchor and FRP.

[0055] The present application also provides a monitoring method using the tensioning system in the above embodiment, which comprises the following steps:

[0056] After the initial tensioning is completed, the jack is removed, and the excessively long connecting rod 200 is cut off. The connecting rod 200 only passes through the tensioning end wedge-shaped anchor and the anchor base, so that the connecting rod 200 and the coil 100 are clamped between the tensioning end wedge-shaped anchor and the anchor base;

[0057] Step 1: disconnect the switch assembly 500, excite the coil 100, and measure the resistance of the coil 100, which is recorded as Ω1;

[0058] Step 2: close the switch assembly 500, heat the connecting rod 200 to shrink, increase the cross section, and achieve compensation tension, thus completing a monitoring-excitation-compensation procedure;

[0059] Repeat steps 1 and 2, and record the resistance measured each time as Ωn (n=1, 2, 3...), monitor the change in the difference between the resistances of the coil 100 measured twice adjacently, realize prestress monitoring of the material 400 under test, characterize the loss degree of the prestressed FRP in different monitoring time periods, and continuously perform compensatory tensioning on the prestressed FRP, so as to realize long-term prestress monitoring and compensatory tensioning of the prestressed FRP.

[0060] This monitoring method can achieve real-time monitoring, low cost, easy operation, multiple compensatory tensioning, quantitative compensatory tensioning and low disturbance effects in various types of structural health monitoring and reinforcement. It is particularly suitable for prestressed FRP reinforced concrete beams and steel beams. It is a prestressed FRP tensioning system worthy of promotion and application.

[0061] In the description of this specification, the description with reference to the terms "example", "embodiment" or "some embodiments" etc. means that the specific features, structures, materials or characteristics described in conjunction with the embodiment or example are included in at least one embodiment or example of the present application. In this specification, the schematic representation of the above terms does not necessarily refer to the same embodiment or example. Moreover, the specific features, structures, materials or characteristics described can be combined in any one or more embodiments or examples in a suitable manner.

[0062] Of course, the invention is not limited to the above-mentioned embodiments, and those skilled in the art may make equivalent modifications or substitutions without violating the spirit of the present application, and these equivalent modifications or substitutions are all included in the scope defined by the claims of the present application.

Claims

1. A tensioning system, characterized in that: It includes a coil, a connecting rod and an electric wire, wherein the coil and the connecting rod are both made of shape memory alloy, the tensioning end of the connecting rod is connected to the material to be tested, the coil is wound on the connecting rod, the two ends of the coil are connected to the connecting rod, an insulating layer is provided on the outer surface of the coil, one end of the electric wire is connected to the coil, and the other end of the electric wire is connected to the connecting rod to form a circuit, and a switch component is provided on the circuit.

2. The tensioning system according to claim 1, characterized in that: A first connection portion is provided at a welding point between one end of the coil and the connecting rod, and a second connection portion is provided at a welding point between the other end of the coil and the connecting rod.

3. The tensioning system according to claim 2, characterized in that: The switch assembly is arranged between the first wiring part and the electric wire. The switch assembly includes a rotating rod and an insulating sleeve. The electric wire extends into the insulating sleeve. The rotating rod is connected to the first wiring part. A first connector is arranged on the outer periphery of the rotating rod. Rotating the rotating rod can connect or disconnect the first connector with the electric wire.

4. The tensioning system according to claim 3, characterized in that: A third wiring portion is provided in the insulating sleeve, one end of the third wiring portion is connected to the electric wire, and the other end forms a second connector on the inner circumference of the insulating sleeve. Rotating the rotating rod can connect or disconnect the first connector and the second connector. A connecting portion is provided between the third wiring portion and the coil.

5. The tensioning system according to claim 4, characterized in that: An insulating contact is provided on the rotating rod, and the first connector can be connected to the insulating contact by rotating the rotating rod.

6. The tensioning system according to claim 4, characterized in that: The second connecting head includes a metal contact and a reaction spring, and the reaction spring is arranged inside the metal contact.

7. The tensioning system according to claim 1, characterized in that: The tensioning end of the connecting rod is provided with an anchor, and the anchor is used to fix the material to be tested.

8. The tensioning system according to claim 1, characterized in that: A base is provided at the fixed end of the connecting rod, and the base is used to fix the connecting rod.

9. A monitoring device, characterized in that: The device comprises a device body and the tensioning system according to any one of claims 1 to 8, wherein the fixed end of the material to be measured is connected to the device body.

10. A monitoring method using the tensioning system according to any one of claims 1 to 8, characterized in that The following steps are involved: Step 1: disconnecting the switch assembly, exciting the coil, and measuring the resistance of the coil; Step 2: closing the switch assembly, generating heat to cause the connecting rod to contract and increase its cross section, thereby achieving compensatory tensioning; Repeat the step 1 and the step 2, monitor the change of the difference between the resistances of the coil measured twice adjacently, and realize the prestress monitoring of the measured material.

Citation Information

Patent Citations

  • Beam member prestress reinforcing device, reinforcing method and reinforcing system

    CN113481880A

  • SMA wire evaluation system and method for simulating real application scene

    CN120445832A

  • Shape memory polymer heating power coupling experimental apparatus